GOVERNMENT OF INDIA MINISTRY OF RAILWAYS LOK SABHA UNSTARRED QUESTION NO. 2890 TO BE ANSWERED ON 05.08.2026 TALCHER BIMLAGARH RAIL PROJECT †2890. SHRI RUDRA NARAYAN PANY: Will the Minister of RAILWAYS be pleased to state: (a) whether the Government is likely to expedite the completion of the Talcher Bimlagath' rail project and if so, the details thereof; (b) the time by which this project is expected to be completed; (c) whether the construction work up to Palalahada is likely to be completed by the end of December 2026 and if so, the details thereof; (d) whether the Government proposes to run passenger trains up to Khamara from the point of view of the completed construction work and if so, the details thereof; and (e) whether the Government is likely to take a sympathetic view on the demand to build the Palalahada railway station near Palalahada Sadar (within 1.5 2 km) and if so, the details thereof? ANSWER MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND ELECTRONICS & INFORMATION TECHNOLOGY (SHRI ASHWINI VAISHNAW) (a) to (e): Talcher-Bimalgarh (150 Km) new line project passes through north Odisha covering Angul, Deogarh and Sundargarh Districts. The latest cost of the project is ₹ 3,390 Cr. Expenditure of ₹ 1,901 Cr. have been incurred on this project upto March, 2026. An outlay of ₹ 950 Cr. has been provided for the financial year 2026-27. Section wise status of the project is as under:- § Page 1 of 5S. Section Status No. 1 Talcher – Khamar Commissioned. (48 Km) 2 Khamar – 110 Ha out of 137 Ha requisite land have been Golabandha acquired. Works have been taken up in (35 Km) available land. 41 out of 61 minor Bridges have been completed and works have been taken up on balance minor Bridges. 3 out of 11 ROBs have been completed and works have been taken up on balance ROBs. 12 out of 16 RUBs have been completed and works have been taken up on balance RUBs. Works on Palalahada Station Building near Palahada Sadar has been taken up. 3 Golabandha – 69 Ha out of 113 Ha requisite land have been Mahuldiha (35 Km) acquired. 4 Mahuldiha – 108 Ha out of 134 Ha requisite land have been Bimalgarh (32 Km) acquired. Forestry and Wildlife clearances received. Works have been taken up in available land. 39 out of 72 minor Bridges have been completed and works have been taken up on balance minor Bridges. 12 out of 25 RUBs have been completed and works have been taken up on balance RUBs ODISHA Railway Budget: Budget allocation in recent years has increased significantly. Budget allocation for infrastructure projects and safety works, falling fully/partly in the State of Odisha is as under: Page 2 of 5Period Outlay 2009-14 ₹ 838 Cr./year 2026-27 ₹ 10,928 Cr. (More than 13 times) Track Construction: The details of commissioning/laying of new track falling fully/partly in the State of Odisha is as under: Period New Track Average Commissioning of new tracks per Commissioned year 2009-14 267 Km 53 Km 2014-26 2,236 Km 186 Km (More than 3.5 times) Project Sanctioned: As on 01.04.2026, 55 projects (19 New Lines and 36 Doubling/Multi- tracking), of a total length of 4,256 Km, costing ₹ 81,739 crore, falling fully/partly in Odisha, are sanctioned. The summary is as under:- Category No of Total Length Total Exp sanctioned Length Commissioned upto Mar'26 Projects NL/GC/DL till Mar'26 (₹ in Cr) (in Km) (in Km) New Lines 19 1,544 277 7,288 Doubling/Multi- 36 2,712 1,309 21,675 tracking Total 55 4,256 1,586 28,963 Recently Completed Projects: Details of some of the recently completed projects falling fully/partly in Odisha are as under: S. Name of Project Cost No. (In Crores of ₹) 1 Daitari-Banspani New Line and Jakhapura- 1,317 Haridaspur 3rd Line (179 Km) 2 Jharsuguda - Sardega New Line (53 Km) 1,598 3 Haridaspur-Paradeep New Line (82 Km) 2,397 4 Angul-Sukinda New Line (104 Km) 2,834 Page 3 of 5S. Name of Project Cost No. (In Crores of ₹) 5 Champa-Jharsuguda 3rd Line (152 Km) 1,227 6 Sambalpur-Titlagarh Doubling (182 Km) 2,262 7 Rourkela-Jharsuguda 3rd Line (101 Km) 1,313 8 Banspani- Jakhapura Doubling (164 Km) 1,827 9 Sambalpur-Talcher Doubling (174 Km) 1,539 10 Raipur - Titlagarh Doubling (203 Km) 1,171 11 Jharsuguda-Sardega Doubling (50 Km) 3,200 Ongoing Projects: Further, some of the main projects falling fully/partly in Odisha which have been taken up are as under: S. Name of Project Total Cost No. (In Crores of ₹) 1 Junagarh-Nabarangpur New Line (116 Km) 2,865 2 Nabarangpur-Jeypore New Line (41 Km) 748 3 Jeypore-Malkangiri New Line (130 Km) 2,344 4 Malkangiri – Pandurangapuram New Line 3,592 (174 Km) 5 Buramara-Chakulia New Line (60 Km) 1,459 6 Gunupur-Therubali New Line (74 Km) 1,166 7 Puri - Konark New Line (32 Km) 492 8 Badampahar-Kendujhargarh New Line (82 Km) 1,876 9 Bangriposi-Gorumahisani New Line (86 Km) 2,269 10 Bargarh Road-Nawapara Road New Line 2,622 (138 Km) 11 Nergundi - Vizianagaram 3rd Line (385 Km) 4,963 12 Vizianagram-Titlagarh 3rd Line (265 Km) 6,996 13 Sambalpur - Jarapada 3rd and 4th line (127 Km) 3,574 14 Budhapank- Salegaon via Rajatgarh 3rd & 4th Line 3,035 (170 Km) 15 Kottavalasa-Koraput Doubling (189 Km) 3,580 16 Koraput-Singapur Road Doubling (165 Km) 2,462 17 Jagdalpur-Koraput Doubling (107 Km) 1,547 18 Jharsuguda-Bilaspur 4th line (206 Km) 2,596 19 Jharsuguda-Sason 3rd and 4th line (35 Km) 1,113 20 Bondamunda-Ranchi Doubling (159 Km) 3,029 21 Narayangarh-Bhadrak 3rd line (153 Km) 3,425 Page 4 of 5S. Name of Project Total Cost No. (In Crores of ₹) 22 Bhadrak-Nergundi 3rd Line (92 Km) 1,632 23 Cuttack-Nergundi 4th line along with Rail flyover 759 at Nergundi (16 Km) 24 Dangoaposi-Jaroli (Banspani) 3rd & 4th Line 1,638 (43 Km) 25 Jarapada- Budhapank 3rd & 4th Line with flyover 929 at Talcher (101 Km) 26 Flyover from Bondamunda A Cabin to 135 Bondamunda Link B Cabin (5 Km) Completion of Railway project/s depends on various factors which include the following:  Land acquisition  Forest clearance  Shifting of infringing utilities  Statutory clearances from various authorities  Geological and topographical conditions of area  Law and order situation in the area of project site  Number of working months in a year for particular project site etc. All these factors affect the completion time and cost of the project/s. The introduction of train services on any route/section is an on-going process, which depends on various factors including:  Capacity of that section  Availability of path  Availability of required rolling stock  Availability of matching of railway tracks and other assets  Occupancy and the traffic requirement of the section. ***** Page 5 of 5

Continue your research