GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2890
TO BE ANSWERED ON 05.08.2026
TALCHER BIMLAGARH RAIL PROJECT
†2890. SHRI RUDRA NARAYAN PANY:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government is likely to expedite the completion of the
Talcher Bimlagath' rail project and if so, the details thereof;
(b) the time by which this project is expected to be completed;
(c) whether the construction work up to Palalahada is likely to be
completed by the end of December 2026 and if so, the details thereof;
(d) whether the Government proposes to run passenger trains up to
Khamara from the point of view of the completed construction work
and if so, the details thereof; and
(e) whether the Government is likely to take a sympathetic view on the
demand to build the Palalahada railway station near Palalahada Sadar
(within 1.5 2 km) and if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Talcher-Bimalgarh (150 Km) new line project passes through
north Odisha covering Angul, Deogarh and Sundargarh Districts.
The latest cost of the project is ₹ 3,390 Cr. Expenditure of ₹ 1,901 Cr. have
been incurred on this project upto March, 2026. An outlay of ₹ 950 Cr. has
been provided for the financial year 2026-27.
Section wise status of the project is as under:-
§ Page 1 of 5S. Section Status
No.
1 Talcher – Khamar Commissioned.
(48 Km)
2 Khamar – 110 Ha out of 137 Ha requisite land have been
Golabandha acquired. Works have been taken up in
(35 Km) available land.
41 out of 61 minor Bridges have been
completed and works have been taken up on
balance minor Bridges.
3 out of 11 ROBs have been completed and
works have been taken up on balance ROBs.
12 out of 16 RUBs have been completed and
works have been taken up on balance RUBs.
Works on Palalahada Station Building near
Palahada Sadar has been taken up.
3 Golabandha – 69 Ha out of 113 Ha requisite land have been
Mahuldiha (35 Km) acquired.
4 Mahuldiha – 108 Ha out of 134 Ha requisite land have been
Bimalgarh (32 Km) acquired. Forestry and Wildlife clearances
received. Works have been taken up in
available land.
39 out of 72 minor Bridges have been
completed and works have been taken up on
balance minor Bridges.
12 out of 25 RUBs have been completed and
works have been taken up on balance RUBs
ODISHA
Railway Budget:
Budget allocation in recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Odisha is as under:
Page 2 of 5Period Outlay
2009-14 ₹ 838 Cr./year
2026-27 ₹ 10,928 Cr. (More than 13 times)
Track Construction:
The details of commissioning/laying of new track falling fully/partly in the
State of Odisha is as under:
Period New Track Average Commissioning of new tracks per
Commissioned year
2009-14 267 Km 53 Km
2014-26 2,236 Km 186 Km (More than 3.5 times)
Project Sanctioned:
As on 01.04.2026, 55 projects (19 New Lines and 36 Doubling/Multi-
tracking), of a total length of 4,256 Km, costing ₹ 81,739 crore, falling
fully/partly in Odisha, are sanctioned. The summary is as under:-
Category No of Total Length Total Exp
sanctioned Length Commissioned upto Mar'26
Projects NL/GC/DL till Mar'26 (₹ in Cr)
(in Km) (in Km)
New Lines 19 1,544 277 7,288
Doubling/Multi- 36 2,712 1,309 21,675
tracking
Total 55 4,256 1,586 28,963
Recently Completed Projects:
Details of some of the recently completed projects falling fully/partly in
Odisha are as under:
S. Name of Project Cost
No. (In Crores of ₹)
1 Daitari-Banspani New Line and Jakhapura- 1,317
Haridaspur 3rd Line (179 Km)
2 Jharsuguda - Sardega New Line (53 Km) 1,598
3 Haridaspur-Paradeep New Line (82 Km) 2,397
4 Angul-Sukinda New Line (104 Km) 2,834
Page 3 of 5S. Name of Project Cost
No. (In Crores of ₹)
5 Champa-Jharsuguda 3rd Line (152 Km) 1,227
6 Sambalpur-Titlagarh Doubling (182 Km) 2,262
7 Rourkela-Jharsuguda 3rd Line (101 Km) 1,313
8 Banspani- Jakhapura Doubling (164 Km) 1,827
9 Sambalpur-Talcher Doubling (174 Km) 1,539
10 Raipur - Titlagarh Doubling (203 Km) 1,171
11 Jharsuguda-Sardega Doubling (50 Km) 3,200
Ongoing Projects:
Further, some of the main projects falling fully/partly in Odisha which have
been taken up are as under:
S. Name of Project Total Cost
No. (In Crores of ₹)
1 Junagarh-Nabarangpur New Line (116 Km) 2,865
2 Nabarangpur-Jeypore New Line (41 Km) 748
3 Jeypore-Malkangiri New Line (130 Km) 2,344
4 Malkangiri – Pandurangapuram New Line 3,592
(174 Km)
5 Buramara-Chakulia New Line (60 Km) 1,459
6 Gunupur-Therubali New Line (74 Km) 1,166
7 Puri - Konark New Line (32 Km) 492
8 Badampahar-Kendujhargarh New Line (82 Km) 1,876
9 Bangriposi-Gorumahisani New Line (86 Km) 2,269
10 Bargarh Road-Nawapara Road New Line 2,622
(138 Km)
11 Nergundi - Vizianagaram 3rd Line (385 Km) 4,963
12 Vizianagram-Titlagarh 3rd Line (265 Km) 6,996
13 Sambalpur - Jarapada 3rd and 4th line (127 Km) 3,574
14 Budhapank- Salegaon via Rajatgarh 3rd & 4th Line 3,035
(170 Km)
15 Kottavalasa-Koraput Doubling (189 Km) 3,580
16 Koraput-Singapur Road Doubling (165 Km) 2,462
17 Jagdalpur-Koraput Doubling (107 Km) 1,547
18 Jharsuguda-Bilaspur 4th line (206 Km) 2,596
19 Jharsuguda-Sason 3rd and 4th line (35 Km) 1,113
20 Bondamunda-Ranchi Doubling (159 Km) 3,029
21 Narayangarh-Bhadrak 3rd line (153 Km) 3,425
Page 4 of 5S. Name of Project Total Cost
No. (In Crores of ₹)
22 Bhadrak-Nergundi 3rd Line (92 Km) 1,632
23 Cuttack-Nergundi 4th line along with Rail flyover 759
at Nergundi (16 Km)
24 Dangoaposi-Jaroli (Banspani) 3rd & 4th Line 1,638
(43 Km)
25 Jarapada- Budhapank 3rd & 4th Line with flyover 929
at Talcher (101 Km)
26 Flyover from Bondamunda A Cabin to 135
Bondamunda Link B Cabin (5 Km)
Completion of Railway project/s depends on various factors which include the
following:
Land acquisition
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
The introduction of train services on any route/section is an on-going
process, which depends on various factors including:
Capacity of that section
Availability of path
Availability of required rolling stock
Availability of matching of railway tracks and other assets
Occupancy and the traffic requirement of the section.
*****
Page 5 of 5