GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 4045
TO BE ANSWERED ON 12.08.2026
TIRUCHIRAPPALLI–KARUR–SALEM RAILWAY LINE AND KARUR–ERODE
RAILWAY LINE
4045. SHRI DURAI VAIKO:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Detailed Project Reports (DPRs) for doubling of the
Tiruchirappalli–Karur– Salem Railway Line and Karur–Erode Railway
Line have been completed;
(b) if so, the details thereof including the present status of these
doubling projects;
(c) whether the Government proposes to accord administrative sanction
and allocate the necessary funds for the implementation of the said
projects; and
(d) if so, the details thereof including the likely timeline for according
administrative sanction, allocation of funds and commencement of
the doubling works?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): To augment the capacity, doubling of Erode – Karur (67 Km) has
been sanctioned recently at a cost of ₹986 crore. Further, to improve the
connectivity, Final Location Survey (FLS) of Salem – Karur – Dindigul
doubling (159 Km) and Tiruchchirappalli-Karur doubling (76 Km) have been
completed and Detailed Project Reports (DPR) have been prepared.
After firming up of Detailed Project Report (DPR), sanctioning of project
requires consultation with various stake-holders including State
§ Page 1 of 6Governments and necessary approvals viz. appraisal of NITI Aayog,
Ministry of Finance etc. As sanctioning of projects is a continuous and
dynamic process, exact timelines depend upon appraisals and approvals by
various stakeholders.
Tamil Nadu:-
Railway Budget:-
Budget allocation in recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Tamil Nadu is as under:
Period Outlay
2009-14 ₹879 crore/year
2026-27 ₹ 7,611 crore (more than 8 times)
Track Construction:-
The details of constructing new track falling fully/partly in the State of
Tamil Nadu are as under:
Period New track Commissioned
2009-14 923 Km
2014-26 1,356 Km
Projects sanctioned:-
As on 01.04.2026, 19 projects (08 new line, 03 gauge conversion and 08
doubling) of total length of 1,874 km, costing ₹27,282 Crore, falling
fully/partly in the State of Tamil Nadu have been sanctioned. The summary
is as under:-
Category No. of Total Length Total Exp. upto
projects Length Commissioned March, 2026
(in km) upto March, 2026 (₹ in Cr)
(in Km)
New Line 8 811 24 1,514
Page 2 of 6Gauge 3 748 631 3,605
Conversion
Doubling
8 314 54 3,693
/Multitracking
Total 19 1,874 709 8,811
Recently Completed Projects:-
Details of some of the recently completed projects falling fully/partly in the
State of Tamil Nadu are as under:-
S.N. Project Cost
(₹ in
Crores)
1 Dindigul- Pollachi gauge conversion (121 km) 610
2 Pollachi-Palghat gauge conversion (56 km) 350
3 Pollachi-Podhanur gauge conversion (40 km) 400
4 Quilon- Tiruchendur gauge conversion (357 km) 1,122
5 Mayiladuturai - Karaikkudi gauge conversion (187 km) 1,338
6 Madurai-Bodinayakkanur gauge conversion (90 km) 593
7 Chengalpattu-Villupuram doubling (102 km) 670
8 Tiruvallur-Arakkonam 4th line (27 km) 83
9 Thanjavur-Ponmalai doubling (48 km) 370
10 Villupuram-Dindigul doubling (273 km) 2,000
11 Chennai Beach-Attipattu 4th line (22 km) 293
12 Omalur-Metturdam Patch doubling (29 km) 327
13 Chengalpattu - Villupuram and Tambaram - 1,122
Chengalpattu-3rd line (133 km)
14 Salem- Omalur doubling (11 km) 115
15 Madurai- Tuticorin doubling (160 km) 1,891
16 Maniyachi-Nagercoil doubling (102 km) 1,752
17 Chennai Beach-Chennai Egmore doubling (4 km) 272
Page 3 of 6Ongoing Projects:-
Some of the projects falling fully/partly in the State of Tamil Nadu which
have been taken up are as under:
Cost
S.N. Project
(₹ in Crores)
1 Tindivanam-Nagari new line (184 km) 3,631
2 Morappur-Dharmapuri new line (36 km) 359
3 Trivandrum-Kanyakumari doubling (87 km) 4,494
4 Irugur-Podanur doubling (11 km) 277
5 Tambaram-Chengalpattu 4th line (30 km) 757
6 Attipattu-Gummidipundi 3rd & 4th line (23 km) 365
7 Tirupati- Katpadi doubling (105 km) 1,216
8 Tindivanam- Tiruvannamalai new line (71 km) 1,400
9 Atipattu – Puttur new line (88 km) 1,700
10 Baiyapannahalli to Hosur doubling (48 km) 1,160
11 Arakkonam-Chengalpattu doubling (68 km) 993
12 Erode- Karur doubling (67 km) 986
Execution of important infrastructure projects falling fully/partly in the
State of Tamil Nadu are held up due to delay in land acquisition. Status of
land acquisition in Tamil Nadu is as under:
Total Land required for Projects in Tamil Nadu 4,612 ha
Land Acquired 1,178 ha (26%)
Balance Land to be acquired 3,434 ha (74%)
Support of the Government of Tamil Nadu is needed to expedite the land
acquisition.
Page 4 of 6Details of some major projects which are delayed due to land acquisition
are as under:-
SN Name of the project Total Land Balance
land acquired Land to be
required (in ha) acquired
(in ha) (in ha)
1. Tindivanam - Tiruvannamalai 276 33 243
new line (71 km)
2. Attiputtu-Puttur new line (88 km) 189 0 189
3. Morappur-Dharmapuri new line 93 47 46
(36 km)
4. Mannargudi-Pattukkottai new 204 0 204
line (41 km)
5. Thanjavur-Pattukottai new line 152 0 152
(52 km)
Further, Rameshwaram – Dhanushkodi new line (18 km) was sanctioned at
a cost of ₹734 Cr. The Foundation Stone of the project was laid on
01.03.2019. However, the project could not be started because the land
acquisition has not been undertaken by the State Govt. of Tamil Nadu.
Government of India is geared up to execute projects, however success
depends upon the support of Government of Tamil Nadu.
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s own operational requirements
Socio-economic considerations
Page 5 of 6 Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****