GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 2513
ANSWERED ON 13.03.2026
TOTAL BUDGETARY ALLOCATION FOR RAIL INFRASTRUCTURE IN NORTH
EASTERN REGION
2513 SHRI BIRENDRA PRASAD BAISHYA:
Will the Minister of RAILWAYS be pleased to state:
(a) the total budgetary allocation made in the Union Budget 2026–27 for the development of rail
infrastructure in the North Eastern Region, including the North Eastern Railway;
(b) the State-wise and project-wise break-up of this allocation; and
(c) the physical and financial progress achieved so far on major ongoing and new railway projects in
the region?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c):
North Eastern Region Railway Budget:
States in North Eastern Region are covered under Northeast Frontier Railway (NFR). Budget allocation
during the last five years has increased significantly. Budget allocation for infrastructure projects and
safety works, falling fully/partly in North Eastern Region (NER) is as under:-
Period Outlay
2009-14 ₹2,122 crore/year
2025-26 ₹10,440 crore (about 5 times)
Track Construction:
The details of constructing new track falling fully/partly in North Eastern Region (NER) during 2009-
14 and 2014-2025 is as under:-
Contd...2/-
§-:2:-
Period New track Commissioned Average commissioning of new tracks
2009-14 333 Km 66.6 Km/year
2014-25 1,840 Km 167.27 Km/year (about 2.5 times)
Projects sanctioned:
As on 01.04.2025, 12 Railway projects (08 New Lines, 04 Doubling), of a total length of 777 Km,
costing ₹69,342 crore falling fully/partly in North Eastern Region (NER) have been sanctioned. The
summary is as under:-
Category No. of Total Length Exp. upto
sanctioned Length Commissioned upto Mar’25
projects (in Km) Mar’25 (in Km) (₹ in Cr.)
New Lines 08 448 113 38,078
Doubling/
04 329 165 3,598
Multitracking
Total 12 777 278 41,676
Recently completed projects:
Projects commissioned falling fully/partly in North Eastern Region, are as under:
S.No. Project Cost
(₹ in crore)
1 Agartala - Sabroom new line (112 Km) 3,170
2 865
Agartala - Akhaura new line (5 Km)
3 3,019
Rangiya - Murkongselek gauge conversion (510 Km)
Contd...3/-
§-:3:-
4 1,242
Kumarghat - Agartala gauge conversion (109 Km)
5 Lumding - Badarpur - Silchar & Badarpur - Kumarghat gauge 6,500
conversion (412 Km)
6 410
Lumding - Hojai doubling (45 Km)
7 Digaru - Hojai doubling (102 Km)
1,873
8 New Bongaigaon - Agthori doubling (143 Km)
2,048
9 Bogibeel Bridge (92 Km) 5,820
In addition, to provide capital connectivity to Border State of Mizoram, Bhairabi - Sairang (51.38 Km.)
new line project has been completed and commissioned recently in September, 2025. This project
comprises of 45 tunnels, 55 major bridges and 88 minor bridges built through the difficult terrain and
complex geological conditions in the region.
With the completion of this project, Aizawl becomes the fourth North-Eastern state capital, after
Guwahati, Naharlagun (for Itanagar) and Agartala, to be connected to the Indian Railways network. To
provide connectivity beyond Sairang in Mizoram, Final Location Survey (FLS) for Sairang - Hbichhuah
(223 Km.) new line has been sanctioned for preparation of Detailed Project Report (DPR).
Ongoing Projects:
Some of the main projects falling fully/partly in the North Eastern Region which have been taken up are
as under:-
S.No. Name of the project Cost
(₹ In crore)
1 Jiribam - Imphal new line (111 Km) 21,886
2 Dimapur - Kohima new line (82 Km) 15,230
Contd...4/-
§-:4:-
3 Murkongselek - Pasighat new line (27 Km) 1,249
4 New Bongaigaon - Goalpara - Guwahati (Kamakhaya) doubling (176 4,962
Km)
5 Saraighat Bridge doubling (7 Km) 1,474
6 Kamkhya Guwahati 3rd line (6 Km) 395
7 Lumding – Furkating doubling (140 Km) 2,124
8 Furkating – Tinsukia doubling (194 Km) 3,634
Further, during the last three years i.e. 2022-23, 2023-24, 2024-25 and the current financial year 2025-
26, 45 surveys (24 New Line, and 21 Doubling) of total length 3,590 Km falling in Northeast Frontier
Railway have been sanctioned.
Completion of Railway project/s depends on various factors which include the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
Various steps taken by the Government for effective and speedy implementation of rail projects include:
Substantial increase in allocation of funds.
Delegation of powers at field level.
Close monitoring of progress of project at various levels.
Regular follow up with State Governments and concerned authorities for expeditious
land acquisition, forestry and Wildlife clearances and for resolving other issues
pertaining to projects.
*****
§