GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1754
TO BE ANSWERED ON 29.07.2026
UDAIPUR AND DUNGARPUR RAILWAY STATION REDEVELOPMENT
PROJECTS
†1754. SHRI RAJKUMAR ROAT:
Will the Minister of RAILWAYS be pleased to state:
(a) the current status of the redevelopment and modernisation works of
Udaipur and Dungarpur Railway Stations including the sanctioned cost,
date of commencement of work and targeted completion period of both
the projects;
(b) the details of the specific works currently in progress at the said
railway stations including the percentage of work completed so far and
the reasons for the relatively slow progress of these works; and
(c) whether the Government proposes to take necessary steps to expedite
these works at the said railway stations to ensure their completion
within the scheduled timeframe and if so, the time by which it is likely
to be completed?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): Ministry of Railways has identified Udaipur City and Dungarpur
Railway Stations for redevelopment under Amrit Bharat Station Scheme.
The status of these stations is given below:
Udaipur City Station: The redevelopment of Udaipur City station has been
sanctioned at a cost of Rs. 354 Crores.The master plan of Udaipur City
station redevelopment envisages following works:
Provision of main entry station building (West side)
Provision of second entry station building (East side)
§ Page 1 of 6 Provision of 72 m wide air concourse
Provision of 6 m wide foot over bridge
Provision of platform shelter and improvement of platform surface
Provision of lifts and escalators
Improvement of circulating area and parking
4 m wide Skywalk for connecting foot over bridge (Ajmer end) to
second entry station building
The structural work of main station building and second entry station
building has been completed. The works of finishes of main entry and
second entry station buildings and air concourse have been taken up.
Dungarpur Station:The redevelopment of Dungarpur station has been
sanctioned at a cost of Rs. 18.43 Crores (approx.). The master plan of
Dungarpur station redevelopment envisages following works:
Improvement of station building and porch
Improvement of platform shelter on PF 1&2
Improvement of PF surface
Improvement of amenities for Divyangjan
Provision of foot over bridge & lifts
Improvement of circulating area and parking
The works for improvement of station building, porch, circulating area,
parking, platform shelters, platform surfacing, toilet block, installation of
coach indication board and signages have been completed. The work of
foot over bridge and amenities for Divyangjanhas been taken up.
Amrit Bharat Station Scheme envisages development of stations on a
continuous basis with a long-term approach. It involves preparation of
master plans and their implementation in phases to improve the stations of
Indian Railways. The master planning, keeping in view the necessity of
each station, includes:
Improvement of access to station and circulating areas
Page 2 of 6 Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/subway to commensurate with
passenger traffic
Provision of lifts/escalators/ramps
Improvement of platform surface/ provision of platform shelter
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking development
Amenities for Divyangjans
Better passenger information systems
Provision of air concourse, executive lounges, Multimodal integration,
landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions,
provision of ballastless tracks etc. as per necessity, phasing and feasibility
and creation of city centre at the station in the long term.
So far, 1340 stations have been identified for development under Amrit
Bharat Station Scheme, out of which 85 stations including Udaipur City and
Dungarpurrailway stations are located in Rajasthan. The names of stations
identified for development under Amrit Bharat Station Scheme in Rajasthan
are as following:
No. of
State Names of Stations
Stations
Rajasthan 85 Abu Road, Ajmer, Alwar, Anupgarh, AsalpurJobner,
Balotra, Bandikui, Baran, Barmer, Bayana,
Beawar, Bharatpur, Bhawani Mandi, Bhilwara,
Bijainagar, Bikaner, Bundi, Chanderiya, Chhabra
Page 3 of 6Gugor, Chittorgarh Jn., Churu, Dakaniya Talav,
Dausa, Deeg, Degana, Deshnoke, Dholpur,
Didwana, Dungarpur, Falna, Fatehnagar, Fatehpur
Shekhawati, Gandhinagar Jaipur, Gangapur City,
Gogameri, Gotan, Govind Garh, Hanumangarh,
Hindaun City, Jaipur Jn, Jaisalmer, Jalor, Jawai
Bandh, Jhalawar City, Jhunjhunu, Jodhpur,
Kapasan, Khairthal, Kherli, Kota Jn, Lalgarh Jn,
Mandal Garh, MandawarMahwa Road, Marwar
Bhinmal, Marwar Jn, Mavli Jn, Merta Road Jn,
Nagaur, Naraina, Nim ka Thana, Nokha, Pali
Marwar, Phalodi Jn, Phulera Jn, Pindwara, Rai
singhnagar, Rajgarh, Ramdevra, Ramganj Mandi
Jn, Ranapratapnagar, Rani, Ratangarh Jn, Ren,
Ringas, Sadulpur, Sanganer, Sawai Madhopur, Shri
Mahaveerji, Sikar, Sojat Road, Somesar, Sri
ganganagar, Sujangarh, Suratgarh, Udaipur City
Completed Stations:
Development works at railway stations under Amrit Bharat Station Scheme
in Rajasthan have been taken up at a good pace. Details of stations
completed in Rajasthan are as under:
State No. of Name of stations
stations
Barmer, Bundi, Dausa, Deeg, Deshnoke, Fatehnagar,
Fatehpur Shekhawati, Gangapur City, Gogameri,
Rajasthan 18 Gotan, Govind Garh, Jaisalmer, Khairthal, Mandal
Garh, MandawarMahwa Road, Rajgarh, Sojat Road,
Somesar
Page 4 of 6The activities for redevelopment at other stations in Rajasthan have also
been taken up at good pace and progress of some of the stations is as
given below:
New Kota: The structural work of front &rear station building, parcel
building, new panel room, RPF building, improvement of rear & front side
circulating area, platform shelter at platform no. 1 and air concourse have
been completed. The work of lifts, escalators, through roof, finishing of
front & rear side station building, improvement of platform shelters at
platform no 2&3, overhead tank and underground tank etc. have also been
taken up.
Gandhi Nagar Jaipur Station: The works of main entry station building,
second entry station building, two level basement, air concourse, through
roof launching, provision of platform shelters, platform resurfacing and
improvement of circulating area and utilities have been completed. The
work of finishes has been taken up.
Jaipur Station: The works of 6 m wide foot over bridge at dausa end,
second entry side basement, approach road, structural work of main entry
side basement, structural work of air concourse and 8m wide central foot
over bridge connecting concourse have been completed. The work of 6m
wide foot over bridge at Sikar end, structural work of main entry station
building, foot over bridge along the track and roofing & flooring work of
central foot over bridge have been taken up.
Churu station: The works of new station building, improvement of platform
shelter at platform no. 1 & 2, booking office, waiting room, retiring room,
toilet, installation of coach indication board and signages have been
completed. The work of lifts and 12 m wide foot over bridge has been taken
up.
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and works
Page 5 of 6in this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on category
of station/condition/traffic handled etc.
Development / Upgradation of stations is complex in nature involving safety
of passengers & trains and requires various statutory clearances such as
fire clearance, heritage, tree cutting, airport clearance etc. The progress
also gets affected due to brownfield related challenges such as shifting of
utilities (involving water/sewage lines, optical fibre cables, gas pipelines,
power/signal cables, etc.), infringements, operation of trains without
hindering passenger movement, speed restrictions due to works carried out
in close proximity of tracks and high voltage power lines, etc. and these
factors affect the completion time.
Indian Railways has a well established mechanism to monitor
implementation of projects including their reviews, inspection, check for
time and cost overruns, quality of works and audits. Monitoring of projects
is done at various levels including through dedicated portal of Indian
Railways named Indian Railway Project Sanction and Management (IRPSM).
Works are carried out adhering to the standards and specifications laid
down in various codes and manuals. Inspections/audits/checks are carried
out from time to time by various agencies/officials/multi-disciplinary teams
as per laid down instructions and actions for correction are taken
immediately. The issues faced by the executing units are accordingly
addressed. This is a continuous and ongoing process.
*****