Executive Summary:
The Ministry of Railways addresses questions regarding the Udhampur-Srinagar-Baramulla Rail Link (USBRL) project, a 272 km railway line in Jammu and Kashmir. The response details environmental impact assessments, safeguards for ecological balance, socio-economic contributions including employment and tourism, land acquisition, compensation, and mechanisms for resolving pending claims up to June 2025. The project, commissioned recently, faced challenging Himalayan terrain.
Key Points / Main Content:
* **Project Overview:**
* The USBRL project spans 272 km, covering Udhampur, Reasi, Ramban, Srinagar, Anantnag, Pulwama, Budgam, and Baramulla districts.
* The project includes the world's highest railway bridge over the Chenab River (1315m long, 467m arch span, 359m above river bed) and India's first cable-stayed bridge over the Anji Khad (331m deck above river bed, 193m main pylon height).
* **Socio-Economic Impact:**
* Generated over 50 million mandays of employment.
* Construction of over 215 km of approach roads, including a tunnel and 320 small bridges, improving local connectivity and socio-economic status.
* **Environmental Safeguards:**
* Environmental Impact Assessments conducted by NEERI for the Katra-Qazigund line, including Chenab and Anji Khad bridges.
* Implementation of safeguards and mitigation measures based on NEERI's Environmental Management Plan (EMP).
* Construction of sedimentation tanks, alternative water sources, lined drains, and stepped chutes.
* Use of controlled blasting techniques and installation of air quality monitoring sensors in tunnels.
* Electrification of the rail project to reduce the carbon footprint.
* Slope stability designed and proof checked by Indian and global firms, following NEERI guidelines.
* **Safety Measures:**
* Tunnels longer than 2 km equipped with mechanical ventilation systems.
* Firefighting systems installed in all tunnels.
* Escape tunnels totaling 66 km made where tunnel length exceeds 3 km.
* **Land Acquisition and Compensation:**
* Land acquired as per the Jammu and Kashmir State Land Acquisition Act 1990.
* Total land acquired: 1559.48 Ha private land and 276.71 Ha Govt. Land.
* Rs. 816.21 Cr deposited with the Collector Land Acquisition for compensation.
* Section 18 of the Jammu and Kashmir State Land Acquisition Act 1990 provides the mechanism for resolving pending claims.
Impact Analysis:
* **Local Population:**
* Impact: Improved connectivity, socio-economic status, and potential for increased tourism. Possible displacement due to land acquisition.
* Action Required: Utilize new infrastructure. Pursue pending claims through the Jammu and Kashmir State Land Acquisition Act 1990 if applicable.
* **Environment:**
* Impact: Potential disturbance to Himalayan ecology. Mitigated through slope stabilization, EMP implementation, and biodiversity conservation efforts.
* Action Required: Monitor the effectiveness of environmental safeguards.
* **Government (Ministry of Railways/District Administration):**
* Impact: Successful commissioning of a major infrastructure project with socio-economic benefits and environmental considerations.
* Action Required: Ensure continued monitoring of safety measures, address pending claims related to land acquisition, and continue implementing environmental safeguards.
Key Entities Referenced
UdhampurSrinagarBaramulla Rail Link USBRL project: A railway project in Jammu and Kashmir, connecting Udhampur, Srinagar, and Baramulla.
Chenab Bridge: The world's highest Railway Bridge over Chenab river in Reasi district of Jammu Kashmir, part of the USBRL project.
Anji Khad bridge: Indian Railway's first cable stayed bridge constructed over Anji Khad as part of the USBRL project.
Jammu and Kashmir: The Union Territory where the USBRL project is located, encompassing districts such as Udhampur, Reasi, Ramban, Srinagar, Anantnag, Pulwama, Budgam, and Baramulla.
SHRI ASHWINI VAISHNAW: Minister of Railways, Information Broadcasting and Electronics Information Technology
National Environmental Engineering Research Institute NEERI, Nagpur: An institute that conducted Environmental Impact Assessments for the KatraQazigund new rail line, including Chenab and Anji Khad bridges.
Indian Institute of Science, Bangalore IITDelhi: Institutes involved in the slope stability design for the Chenab Bridge.
Jammu Kashmir State Land Acquisition Act 1990: The legal framework used for land acquisition related to the USBRL project in Jammu and Kashmir.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2781
TO BE ANSWERED ON 06.08.2025
UDHAMPUR-SRINAGAR-BARAMULLA RAIL LINK
2781. SHRI AGA SYED RUHULLAH MEHDI:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government has conducted any environmental
impact assessments of the Chenab and Anji Khad bridges in
fragile Himalayan zones;
(b) if so, the key details of the findings including risks to local ecology
and slope stability;
(c) the details of the safeguards implemented to prevent ecological
imbalance caused by the Udhampur-Srinagar-Baramulla Rail Link
(USBRL) project;
(d) the details of the quantifiable impact of the project on local
employment and tourism in Kashmir;
(e) the details of the number of households fully or partially
displaced due to land acquisition along with the number of them
received compensation, rehabilitation till June 2025; and
(f) the details of the mechanism available for resolving pending
claims related to displacement and resettlement?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f): Udhampur-Srinagar-Baramulla Rail Link (USBRL) project of
total length 272 Km has been recently commissioned. USBRL projectcovers the districts of Udhampur, Reasi, Ramban, Srinagar, Anantnag,
Pulwama, Budgam and Baramulla of Jammu and Kashmir.
The USBRL project is one of the most difficult new railway line projects
undertaken in the country post-independence. The terrain passes
through young Himalayas, which are full of geological surprises and
numerous problems. In this project, Railway has made the world’s
highest Railway Bridge over Chenab river in Reasi district of Jammu &
Kashmir. The iconic Chenab Bridge is 1315 m long having Arch span of
467 m and height of 359 m above river bed. Indian Railway's first cable
stayed bridge has been constructed over Anji Khad in this project. Its
bridge deck is 331m above the river bed level and height of its Main
pylon is 193m.
The USBRL project has made substantial socio-economic contributions
to the region, with employment generation being a significant aspect of
its impact. The project has generated more than 5 Cr. man-days of
employment.
Another crucial facet of the USBRL Project’s socio-economic
development efforts has been the construction of over 215 km of
approach roads, which include construction of a tunnel and 320 small
bridges. This road network has helped the local population in
improvement of their connectivity with other areas and also
improvement in socio-economic states.
In accordance with international norms, adequate safety provisions
have been kept in the USBRL project. All tunnels having length more
than 2 Km have been provided with mechanical ventilation systems to
ensure air quality. Firefighting systems comprising fire hydrants and
fire extinguishers have been provided to promptly address and contain
potential fire incidents in all the tunnels. Further, to ensure safety of
passenger, escape tunnels have also been made where length of tunnelis more than 3 Km. Total 66 Km escape tunnels have been made in this
project.
To ensure minimum disturbance to Himalayan ecology, due care has
been taken for slope stabilization and the best institutes of the world
were roped in for execution of this project. Comprehensive schemes for
slope stabilization have been adopted as per NEERI guidelines and
Detailed Design Consultants' suggestions to prevent erosion and
damage to natural terrains.
Slope stability at Chenab Bridge was designed by Indian Institute of
Science, Bangalore & IIT/Delhi. Other global firms having experience of
such works were also engaged for independent check for slope stability
for Chenab Bridge. Slope stability at Anji Bridge was also designed and
proof checked by the experienced global firms.
Further, Environmental Impact Assessments due to construction of
Katra-Qazigund new rail line, including Chenab and Anji Khad bridges
have also been conducted through National Environmental Engineering
Research Institute (NEERI), Nagpur. Extensive safeguards and
mitigation measures have been implemented based on the
Environmental Management Plan (EMP) prepared by NEERI.
Sedimentation tanks have been constructed at tunnel outlets before
discharging into natural nallas to manage tunnel excavated material.
Alternative water sources were provided to villages where natural
sources were disrupted by resorting to reverse pumping. Proper lined
drains and stepped chutes were constructed at required locations to
ensure smooth flow of surface water and prevent erosion at muck
yards.Advanced techniques of controlled blasting were adopted during
tunnelling to minimize vibrations and environmental damage. Sensors
have been installed in all tunnels in Katra-Banihal section to monitor
the Air Quality during operational phase also.
The entire rail project is electrified using a overhead conductor system
in tunnels and in open stretches. Rail transportation is most
environment friendly transportation mode, significantly reducing carbon
footprint compared to diesel traction.
While specific measures for biodiversity conservation are delineated in
the EMP, the overall environmental mitigation efforts contribute to
protecting local ecology. Guidelines for site preparation for plantation
activity on dumping sites include planting native species and turfing
with grass for eco-restoration.
With the all-weather, reliable and comfortable rail connectivity of valley
portion with rest of the Indian Railway network, tourism will get a big
boost.
The USBRL project (272 Km) has been constructed completely in the
Union territory of Jammu & Kashmir. Land acquisitions were carried
out as per the prevalent ‘Jammu & Kashmir State Land Acquisition Act
1990’. The Land Acquisition was conducted through Collector Land
Acquisition, appointed by District Administration.
Assessment of land ownership, structures, identification of
beneficiaries, calculation of compensations for land & structures, trees
etc was done. Awards in this regard were published and disbursed the
compensation amount.Total land acquired for USBRL Project includes 1559.48 Ha of Private
land and 276.71 Ha of Govt. Land. Complete payment of these land
acquisitions amounting to Rs. 816.21 Cr. has already been deposited
with concerned Collector Land Acquisition. The mechanism for
resolving pending claims related to land acquisition is already included
vide section 18 of Jammu & Kashmir State Land Acquisition Act 1990.
Railway acquires land through concerned State/District Authorities. All
the activities in connection with land acquisition like assessment of
amount of compensation to land losers etc. are under purview of the
State Government. Compensation for land acquisition is made to the
land losers by the Revenue Department of the State Government after
demanding the same from Railways.
*****