GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 864
ANSWERED ON 23rd JULY, 2026
UPGRADATION OF NH-373
864. SHRI SHREYAS M PATEL:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) whether the Government is aware of the deteriorated condition
of National Highway (NH) -373 between Arsikere and Huliyar in
Hassan district, Karnataka, if so, the details thereof;
(b) whether any proposal has been received for the strengthening,
widening, reconstruction or comprehensive upgradation of this
stretch of NH-373;
(c) if so, the present status of the proposal including the estimated
project cost, length of the road, funding pattern and the expected
timeline for approval and its completion;
(d) whether any Detailed Project Report (DPR), technical survey or
condition assessment has been carried out for the Arsikere-Huliyar
section of NH-373, if so, the details thereof; and
(e) the interim measures taken by the Government to repair
potholes, improve road safety, strengthen drainage and prevent
accidents on this stretch until permanent reconstruction is
completed?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)(a) to (e) The Government in Ministry of Road Transport and
Highways is primarily responsible for the development and
maintenance of National Highways of the country. The stretch from
Arsikere to Huliyar does not lie on NH-373. Arasikere and Huliyar in
Hassan district is connected by State Highway SH-102 from
Arasikere to Panchhanahalli hand post (33 km) and further by NH-69
from Panchannahalli hand post to Huliyar (20 km). The stretch of
NH-69 from Panchanahalli hand post to Huliyar is 2 lane with paved
shoulders (20 km) and is in good condition. Status of NH-373 is at
Annexure-A.Annexure - A
ANNEXURE-A REFERRED TO IN REPLY TO PART (a) to (e) OF LOK
SABHA UNSTARRED QUESTION NO. 864 ANSWERED ON 23RD JULY,
2026 ASKED BY SHRI SHREYAS M PATEL REGARDING
UPGRADATION OF NH-373
From (Km) To (Km) Present Status
0.000 (AIT Circle) 3.800 4-Lane + PS constructed
(Hiremagaluru) by the State Tourism
Department. Presently
the stretch is covered
under Short-term
Maintenance Contract
(STMC) up to 09.04.2027
3.800 4.200 Presently the stretch is
(Hiremagaluru) (Heremagaluru covered under STMC up
ROB) to 09.04.2027.
4.200 5.050 STMC work ended in May
(Hiremagaluru) (Karthikere) 2026. To maintain the
stretch renewal of
wearing course is
proposed to be carried
out through special
repair.
5.050 24.560 Special repair is
(Karthikere) (Belur) proposed.
24.560 58.125 Widening to 4L+PS from
(Belur) (Hassan) Km 25.00 To Km 58.60
has been awarded on
16.02.2025. Presently
the stretch is to be
maintained through
STMC.
58.125 93.680 The stretch is 4L+PS for
(Hassan) (Holenarsipura) which Performance
Based Maintenance
Contract (PBMC)
sanctioned on
31.03.2026.
93.680 105.780 The stretch is 2L+PS for(Holenarsipura) (Yedegowdanahalli) which STMC is under
sanction.
105.780 128.080 Special Repair work
(Yedegowdanahalli) (Arjunahalli) approved on 24.06.2026.
128.080 151.330 Special Repair work
(Arjunahalli) (Bilikere) approved on 24.06.2026.
*****