Official TranscriptGOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS LOK SABHA UNSTARRED QUESTION NO. 2211 ANSWERED ON 12TH FEBRUARY, 2026 UPGRADATION OF ROAD INFRASTRUCTURE †2211. SHRI ZIA UR REHMAN: Will the Minister of ROAD TRANSPORT AND HIGHWAYS सड़क परिवहन औि िाजमार्ग मंत्री be pleased to state: (a) whether the Government is aware of poor road conditions, traffic congestion and high accident rates on...
GOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS LOK SABHA UNSTARRED QUESTION NO. 2211 ANSWERED ON 12TH FEBRUARY, 2026 UPGRADATION OF ROAD INFRASTRUCTURE †2211. SHRI ZIA UR REHMAN:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) whether the Government is aware of poor road conditions, traffic congestion and high accident rates on highways in Western Uttar Pradesh;
(b) if so, the details of the steps taken to upgrade road infrastructure and improve road safety in the region;
(c) whether similar road safety and infrastructure challenges exist in other parts of the country; and
(d) if so, the details of the national initiatives undertaken to modernise highways and reduce road accidents? ANSWER THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS (SHRI NITIN JAIRAM GADKARI)
(a) to (d) The Government in Ministry of Road Transport and Highways is primarily responsible for development and maintenance of National Highways (NHs).
The Government receives proposals from various State Governments / Union Territories (UTs), including from the districts of Western Uttar Pradesh (UP) from time to time, for declaration / upgradation of State Roads, including State Highways (SHs), as newNHs. Decisions are taken to notify State Roads as NHs from time to time based on the broad principles of declaration of NHs, requirement of connectivity, traffic density and synergy with PM Gati Shakti National Master Plan (NMP).
Development and maintenance of National Highways (NHs) is a continuous process. Works on NHs, are accordingly taken up based on the traffic density, condition of road and synergy with PM Gati Shakti National Master Plan to keep the NHs in traffic worthy conditions.
Government has focused on development of NHs in accordance with the traffic volume and also ensuring that no
section of NHs should be left without any contractual maintenance agency.
The details of completed NHs projects for development and maintenance of NHs passing through Western UP during last three years and current year are at Annexure I.
Project-wise details of sanctioned/ongoing NHs projects for development and maintenance of NHs passing through Western UP with the time-frame of completion are at Annexure II.
Funds are allocated for development and maintenance of NHs State/ Union Territory-wise/agency wise and not district / region- wise.
The details of funds allocated and expenditure incurred towards development and maintenance of NHs in the State of Uttar Pradesh during each of the last three years and the current year are
as follows:
Amount in Rs Crore Year Allocation Expenditure 2022-23 21,453.40 21,453.40 2023-24 28,113.83 28,113.83 2024-25 20,682.48 20,664.95 2025-26 (Till 31.12.2025) 19,676.39 17,513.89A number of schemes have been implemented by the Government for development of NHs in the country. These are Bharatmala Pariyojana including subsumed National Highways Development Project (NHDP), Special Accelerated Road Development Programme for North-East Region (SARDP-NE), Special Programme for development of Roads in Left Wing Extremism affected Area (LWE) and Externally Aided Projects (EAP). NHs stretches not covered under any of the above schemes are taken up for development under National Highway Original [NH(O)] works depending upon traffic density, condition of road and synergy with PM Gati Shakti National Master Plan.
Regarding Accidents, the details of the number of accidents and fatalities reported on NHs including Western UP during each of
the last three years are as under: - 2023 2024 2025 Accidents Fatalities Accidents Fatalities Accidents Fatalities 150,177 63,112 150,958 64,772 1,34,307 57,482 Figures for calendar year 2024 onwards based on latest eDAR (Electronic Detailed Accident Report) data.
All NHs works are carried out as per standards, guidelines, manual, code of practice of Indian Roads Congress as well as specifications for Road and Bridge Works. Necessary road safety measures inter-alia include provision of crash barriers, signage boards, foot over bridges, etc. are taken up during design, construction, operation and maintenance stages.
Further, Guidelines have been issued for regular safety audit of all NHs at design, construction, pre-opening stage of NH projects as well as on existing NHs for ensuring road safety.
Road Safety Audit is carried out for the independent assessment of newly constructed roads before opening them to commercial traffic. All identified road safety issues, including those related to road signages and markings, are addressed before the road is opened to the public. Subsequently, during the operation of the project highway, assessment is carried out at regular intervalsto identify safety issues that may have emerged during operation stage and any necessary remedial measures are taken in a time- bound manner. Besides this, accident data on all existing and new National Highways is monitored on a pan-India basis through the eDAR (electronic Detailed Accident Report) portal, and accident spots are identified. Further, field officers have been delegated powers to take advance remedial action on these identified accident spots, preventing them from being converted to blackspots.
Also, identified blackspots are rectified by carrying out short- term measures like road markings, signages, crash barriers, road studs, delineators, closure of unauthorized median openings, traffic calming measures, etc. in a time bound manner. Further, long-term measures like improvement of road geometrics, junction improvements, spot widening of carriageway, construction of underpasses/overpasses, etc. are also taken as permanent rectification measures based on road safety audit report and site conditions.
Furthermore, Government has formulated a multi-pronged strategy to address the issue of road safety based on 4E's i.e.
Education, Engineering (both of roads and vehicles), Enforcement and Emergency Care, details of which are placed at Annexure-III.ANNEXURE-I ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (d) OF LOK SABHA UNSTARRED QUESTION NO. 2211 FOR ANSWER ON
12.02.2026 ASKED BY SHRI ZIA UR REHMAN REGARDING "UPGRADATION OF ROAD INFRASTRUCTURE".
Details of completed NHs projects for development and maintenance of NHs passing through Western UP during last three years and current year Total Project S. Date of Expenditure NH No. District Project Name Cost No. completion (Rs Crores) (Rs Crores) Six lane Flyover with slip road along NH 44 at junction of NH 530B at start point (design chainage km 1 530B 0.0) of Mathura Bypass at 44.757 07.09.2024 44.757 existing km 154.200 of NH 02 (New NH 44) in the State of Uttar Pradesh on EPC mode.
Mathura Four Laning of NH - 530B from Mathura Byepass
(Start) (Existing km 266.000 of SH 33/Design km 0.000) to Gaju village (End) PCOD 2 530B 885 885 (Design Km 32.982) 30.08.2025 (Design Length=32.982 km) in the State of Uttar Pradesh on HAM mode (PACKAGE 1B) Four Lanning of NH 530B from Gaju Village (Design Km 32.982 Mathura -Aligarh District Boundary) to Devinagar Bypass (Existing 3 530B Hathras & Aligarh Km 208.00 of Sh-33(NH- 738 28.04.2025 738 530B) (Design Km
66.000)).(Design Length
33.018Km) in Uttar Uttar Pradesh on HAM mode (PKG – 1C)Aligarh-Kanpur section NH- 34 (Old NH- 4 34 (Aligarh-Bhadwas, Pkg- 2069.6 16.05.2023 1235.26
91)
1) Aligarh-Kanpur section NH- 34 (Old NH- 5 Etah 34 (Bhadwas-Kalyanpur, 3135.28 12.06.2021 1493.66
91) Pkg-2) Aligarh-Kanpur section NH- 34 (Old NH- 6 Mainpuri 34 (Kalyanpur-Naviganj, 3563.44 25.10.2021 1813.2
91) Pkg-3) Six Laning of Hapur Bypass to Moradabad Section including Hapur Bypass from Km. 50.000 (Design Hapur, Amroha & Chainage 50.000) to Km.
7 NH-09 2140.93 13.09.2025 - Moradabad 148.277 (Design Chainage
149.867) of NH-24 (New NH-09) in the State of Uttar Pradesh on DBFOT (Toll) under NHDP-V.
Four Laning of Moradabad- Bareilly Section of NH-24 NH-09, 530, Moradabad, Rampur from Km 148.00 to Km 8 1267 30.07.2019 - 30 & Bareilly 262.00 in the state of Uttar Pradesh Under NHDP Phase-III on DBFOT Basis Periodic Renewal from km.
28.580 to km. 29.639, 9 334DD Bulandshahr km.30.029 to km.30.060 & 11.05 14.06.2023 6.78 km. 30.659 to km. 44.843 of NH-334DD Improvement / Augmentation of Aligarh- Moradabad Section of NH- 93 to 2 Laning with Paved Shoulders from Km 85.650 Moradabad,Sambhal, (Existing Chainage Km
1046.65 02.06.2022 1093.13 10 NH-509 Bulandshahr & 85.650) to Km 232.020 Aligarh (Existing Chainage Km
232.000) in the State of Uttar Pradesh under NHDP Phase-IV on Engineering, Procurement and Construction (EPC) Mode.
2-Lane Existing Rampur Bypass of Rampur to be developed to 4-Lane in the 11 NH-09 Rampur State of Uttar Pradesh (Km 364.47 31.10.2025 272.09 0+000 to Km 10+190) (Length= 10.19 km) on EPC Mode.Bareilly - Sitapur Section from km. 262.00 to km.
NH-30 (Old Bareilly and 12 419.590 in the State of Uttar 994.68 08.11.2025 1134.5 NH-24) Shahjahanpur Pradesh Rehabilitation and Up- gradation to 2L+PS of Allahganj–Miranpur Katra
section (Km 52.770 to 13 730C Shahjahanpur 316.05 27.02.2024 299.06 Km.114.000) of NH-730C under GNHCP with loan assistance of World Bank on EPC Mode R/U to 2-lane with PS of Radhaita to Pilibhit Section of 46.130 km., which includes (i) 6.850 km of NH- 730C, 730B & Shahjahanpur/ 730C from Km.137.250 to 14 219.19 09.01.2025 208.74 731K Pilibhit 144.100), (ii) 3.550 of NH- 730B (from Km.144.100 to
147.650) & (iii) 35.730 km of NH-731K (from Km.147.650 to 183.380) Balance work of construction of a minor 15 731K Shahjahanpur bridge over Kaimua Nala in 0.72 22.02.2025 0.71 Km.24.00 of NH-731K on item rate basis PR in km 1 (1420m) to km 12, km 19 to 21, km 40 and 16 731K Shahjahanpur 7.77 09.04.2023 5.53 km 43 of NH-731K on EPC mode Balance Work of 2L PS of Sitarganj-Bareilly from Km.
NH-30 (Old 17 Pilibhit & Bareilly 254.820 to Km. 329.280 213.39 30.04.2023 199.68 NH-74)
section of Old NH-74 in the State of UP & UK NH-709B, Pkg.-II: Six lane access controlled in Uttar Pradesh portion of Delhi Saharanpur Highway from Delhi/UP Border to EPE Ghaziabad & 18 NH-709B Junction (Ch. 14.750 to Ch. 2002.79 01.12.2025 1731.21 Baghpat
31.600) in the State of Uttar Pradesh on EPC mode under Economic Corridor in phase-I of Bharatmala PariyojanaWidening of two lane with paved shoulder with 19 21 Agra Strengthening from Km. 43.73 30.06.2018 24.87
0.165 to 17.756 of NH-11 (New NH No.21) Six Laning of Delhi - Agra Project PCC issued
section from Km.20.500 to implemented 20 NH-44 Mathura & Agra 1928.22 w.e.f Km.200 in the State of under BOT
20.05.2022 Haryana and U.P. (Toll) Mode Widening of existing four lane to six lane road from 21 235 Meerut km 3.000 to km 7.469 of 44.92 31.07.2025 44.43 NH-235 (New NH-334) under EPC mode NH-334B from Meerut to Haryana Border via 22 334B Meerut & Baghpat Baghpat in the State of 371.37 18.10.2022 316.29 Uttar Pradesh on EPC mode.
Meerut, Bidoli (HR/UP Border) – 23 709A Muzaffarnagar, 761.26 03.11.2023 1021.93 Shamli-Meerut Baghpat & Shamli Panipat to Shamli Pkg-I of 24 709AD Shamli NH-709AD (Lenght - 1252.61 25.01.2023 1326.12
35.580km) Shamli to Shamli & Muazaffarnagar Pkg-II of 25 709AD 1621.08 02.01.2024 1709.39 Muzaffarnagar NH-709AD (Lenght -
42.870km) Shamli to Saharanpur 26 709B Shamli & Saharanpur section of NH-709B, Pkg-II 739.09 22.03.2025 800.25 (length - 62.772Km) Spur(SHAMLI) of NH- 27 SPUR Shamli 326.79 03.05.2025 244.28 709AD connecting NH-709A 4-Laning of Meerut Najibabad Section from km.
11.500 to km 39.250 and 03.02.2025 28 NH-119 Meerut & Bijnor 2836.9 1995.75 km 86.590 to Km. (COD)
112.545.in the state of Uttar Pradesh on HAM Mode.
Muzaffarnagar - Miranpur
section of NH-709AD package - iii from Km. 30.10.2024 29 NH-709AD Muzaffarnagar 947.89 853.97
97.450 to Km. 123.450 in (COD) the state of Uttar Pradesh on EPC Mode.Spur of Muzaffarnagar Spur connecting NH-58 to NH- 30.10.2024 30 Muzaffarnagar 408.94 227.74 Muzaffarnagar 709AD in the state of Uttar (COD) Pradesh on EPC Mode.
Widening and strengthening from km 0.00 to km 15.089 of NH-334A (Purkaji-Laksar- 31 334A Muzaffarnagar Haridwar Road) to two lane 227.06 31.12.2024 144.99 with paved shoulder configuration under EPC mode in the State of UP.ANNEXURE-II ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (d) OF LOK SABHA UNSTARRED QUESTION NO. 2211 FOR ANSWER ON
12.02.2026 ASKED BY SHRI ZIA UR REHMAN REGARDING "UPGRADATION OF ROAD INFRASTRUCTURE".
Project wise details of sanctioned/ ongoing NHs projects for development and maintenance of NHs passing through Western UP Origina Revise Total P Date of l contr Physic d/ S. roject Appo NH N Length Sanctio actual al prog Target N District Project Name Cost ( inted o. (km) n/ Awar date of ress in date of o. Rs Cro date d comple % comple res) tion tion STMC work of NH-321 fr om Km.0.000 to 15.010 19.11.20 1 321 Agra 5.81 40.01 At Bid Evaluation stage & NH-91A from Km.41.0 25 00 to 66.000 Maintenance of Km 0.00 0 to Km 51.600 of NH-32
29.11.20 1G (Agra-Jalesar-Etah) r 24/ 21.02 20.02.2 20.02.2 2 321G Agra oad under Short Term M 4.96 51.60 85
27.01.20 .2025 026 026 aintenance Contract on 25 percentage rate basis for financial year 2024-25
11.03.20 Aligarh-Palwal section, P
1663.3 24/ 27.03 26.03.2 3 334D Aligarh kg-1 from Km. 0.000 to 46.39 7 - 8 13.03.20 .2025 027 Km. 46.390 24
15.03.20 Aligarh-Palwal section, P 24/ 27.08 26.08.2 4 334D Aligarh kg-2 from Km. 46.390 to 986.88 22.72 2.5 -
01.08.20 .2025 027 Km. 61.110 24 Improvement & Up-grad ation of NH-734 section of Moradabad - Thakurd wara - Kashipur: “Packa ge-II: Moradabad – Thak 30.09.20 NH-7 Moradaba 2006.8 15.03 14.03.2 07.12.2 5 urdwara” (Length= 38.77 38.77 22/08.12. 39.1 34 d 2 .2024 026 026 0 km) Start from Ch. 0+0 2022 0 (Existing Km. 389+00 at Bijna) and ends at Ch.
38+770 (near UP/UK Bo rder)on EPC ModeOperation and Maintena nce of Aligarh to Morada Moradaba bad of NH-93 (New NH d,Sambhal NH-5 – 509) Km. 79.000 to K 30.12.20 31.03 30.03.2 , Bulandsh 102.23 153.02 O&M work 6 09 m. 232.020 for a Length 24 .2025 030 ahr & Aliga
153.02 kms. with 2-Lane rh Paved Shoulders on PB MC mode 4L of Bareilly-Pilibhit-Sit 03.02.20 Bareilly & arganj from Km. 0.000 to 1391.6 25/ 14.03 13.03.2 17.08.2 7 30 32.5 43.56 Pilibhit Km. 32.500 of NH-30 (P 4 28.03.20 .2024 026 026 kg-1) 23 4-laning of Pilibhit - Sitar 07.02.20 ganj from Km. 32.500 to 1464.1 23/ 14.03 13.03.2 25.01.2 8 30 Pilibhit 38.3 23.42 Km. 70.800 (Pkg-2) of N 9 27.03.20 .2024 026 027 H-30 23 Improvement and Up-Gr adation of Existing Road
30.03.20 to 2/4L PS from Km 40.0 Shahjahnp 22/ 03.02 02.02.2 15.02.2 9 731 00 to 88.750, start of Kh 762.62 48.75 99.2 ur 20.06.20 .2023 025 026 utar bypass to start of S 22 hahjahanpur bypass of NH 731(Pkg-I) Improvement and Up-Gr adation of Existing Road
20.09.20 Shahjahnp to 4L PS from Km 88.75 1 22/ 19.01 18.01.2 20.06.2 731 ur & Hardo 0 to 123.650, from Start 947.74 34.9 53.9 0 30.11.20 .2024 026 026 i of Shahjahanpur Bypass 22 to start of Shahabad byp ass of NH 731(Pkg.-2A) Construction of 4/6 lane Highway of Southern Ba reilly Bypass, starting at Ch. 237+000 of NH 530 18.12.20 1 near Jhumka chauraha, 2117.0 24/ 24.12 23.06.2 23.06.2 530B Bareilly 29.92 0.6 1 Dhantiya village and end 7 28.03.20 .2025 028 028 ing at Ch. 267+000 of N 25 H 30 near Invertis Univer sity including Trumpet In terchange Bareilly, S Strengthening & overlay NH-3 hahjahanp on intermittent locations 0 (Ol ur, Hardoi, of Bareilly‐Sitapur balan 19.01.20 12.03 11.03.2 31.03.2 1 202.56 98.8 96.45% 2 d NH-Lakhimpur ce works section from K 24 .2024 025 026
24) Khiri & Sit m. 262.000 to Km. 419.5 apur 90 of NH‐304-laning of NH-530B (Pa ckage-II) from Devinagar Bypass (End) [Existing K m.208.000 of NH-530B/
20.03.20 Hathras, E Design Km.66.000] to K 1 2289.5 23/ 06.06 05.06.2 31.12.2 tah & Kasgasganj Bypass (End) [Ex 57.967 50.97% 3 2 29.03.20 .2024 026 026 anj isting Km.150.100 of NH 23 -530B/Design Km.123.1 00] in the state of UP un der Bharatmala Pariyojn a on HAM.
4-laning of NH-530B (PK G-III) from Kasganj Bypa ss (End) [Existing Km.15
0.100 of NH-530B/Desig
28.03.20 n Km.123.100] to Chand 1 NH-5 Kasganj & 2009.1 23/ 30.05 29.05.2 an Nagar [Existing Km.9 56.40 15.16% _ 4 30B Badaun 1 16.06.20 .2025 027
6.200 of NH-530B/Desig 23 n Km.179.500] in the sta te of Uttar Pradesh unde r Bharatmala Pariyojna o n HAM Four Lane Highway from Chandan Nagar (Existin g Km96.200 of NH 530B /Design Km. 179.500) to
15.10.20 Bareilly Bypass (Start) ( 1 Badaun& 1527.4 24/ 19.11 18.11.2 Existing Km. 59.025 of N 38.50 3.97% _ 5 Bareilly 0 28.03.20 .2025 027 H 530B/ Design Km. 218 25 .000) section of NH 530 B,in the State of Uttar Pr adesh on Hybrid Annuity Mode (HAM).
Road Safety Improveme NH-5 nt of Critical junction on 8 Muzaffarnagar-Haridwar (new section of NH-334 from 1 Muzaffarn 26.05.20 04.10 03.10.2 03.10.2 NH-3 Km 143+000 to Km 196 119.27 6.96 3.75 6 agar 25 .2025 027 027 34 & +000 in the state of Uttar NH-3 Pradesh & Uttarakhand
4) on EPC Mode under NH
(O).
DME, Pkg.-V: 4 lane Co New nnector from Delhi-Meer Gree ut Expressway to Km 8.5 1 n fiel Ghaziabad 1147.2 06.08.20 30.0329.03.2 30.06.2 20 of NH-235 in the stat 14.600 76% 7 d alig& Meerut 6 21 .2022 024 026 e of Uttar Pradesh on E nmen PC Basis (Greenfield ali t gnment)Construction of Greenfiel d Connectivity to Jewar I nternational Airport from 22.06 1 NH-1 Gautambu 2414.6 9.125 07.07.20 21.06.2 01.05.2 DND-Faridabad-Ballabh .2023 63.10% 8 48NA dh Nagar 7 KM 22 025 027 garh Bypass KMP Link - ` Spur to Delhi Mumbai Ex pressway Maintenance of NH-334 DD from Km. 0.000 to K m. 11.200, Km. 13.600 t o Km. 28.580, Km. 29.63 9 to Km. 30.029 and Km.
30.060 to Km. 30.659 (e xcluding Km. 0.100 to K Gautam B 1 334D m. 0.700, Km. 0.850 to K 24.11.20 udhh Naga 1.14 27.17 At Bid Evaluation Stage 9 D m. 1.050, Km. 1.600 to K 25 r m. 1.700, Km. 1.950 to K m. 2.100, Km. 3.200 to K m. 4.000, Km. 4.100 to K m. 4.300, Km. 5.000 to K m. 5.200 and Km. 5.800 to Km. 6.200) under ST MC Emergency repair works on NH-334DD in 2.85 K m in different reaches fro m Km. 0+100 to Km. 6+ 400 & Km 28+000 to Km Gautam B 28+200 in (Abadi portion 2 334D 14.11.20 udhh Nagaof Hamidpur Km. 0+100 20.61 2.85 At Bid Evaluation Stage 0 D 25 r to Km. 6+400 & Km 28+ 000 to Km 28+200 in (A badi portion of Hamidpur and Jewar) under Speci al Repair Head on EPC mode Delhi - Saharanpur - De 2 1602.0 24.12.20 02.09 31.08.2 31.03.2 Baghpat hradun Economic Corrid 27.000 99 1 1 21 .2022 024 026 or PKG-I Baghpat & Delhi - Saharanpur - De 2 1335.4 28.08.20 02.09 31.08.2 31.03.2 Muzaffarn hradun Economic Corrid 29.500 96 2 5 21 .2022 024 026 agar or PKG-II 344G Delhi - Saharanpur - De 2 1159.9 28.08.20 02.09 31.08.2 31.03.2 Shamli hradun Economic Corrid 25.500 99 3 6 21 .2022 024 026 or PKG-III Shamli & Delhi - Saharanpur - De 2 1428.1 28.08.20 02.09 31.08.2 31.03.2 Saharanpuhradun Economic Corrid 37.790 98 4 9 21 .2022 024 026 r or PKG-IV6L access Controlled Gr eenfield Highway from G ogwanJalalpur (Shamli) t Shamli & 2 344G o Ranipur Barsi (Sahara 1843.5 29.07.20 17.05 17.05.2 26.07.2 Saharanpu 46.100 56 5 M npur) of Shamli-Ambala 9 22 .2023 025 026 r
section (Package-I) (Des ign Ch. Form km 00.600t o km 45.500) 4-laning of Behsuma - Bi NH-1 jnor section of NH-119 fr 19 (P Meerut, M 2 om Km. 39.240 to Km. 8 2139.6 29.03.20 20.05 19.05.2 19.05.2 acka uzaffarnag 39.56 54.75% 6 6.590 in the state of Utta 2 23 .2024 026 026 ge - II ar & Bijnor r Pradesh on HAM Mode ) .
Spur of Meerut-Garh-Mu kteshwar section(NH-70 Spur 2 9A) connecting NH-119 23.03.20 17.02 16.02.2 12.07.2 Meer Meerut 953.79 12.028 87.14% 7 and NH-58 bypassing M 22 .2023 025 026 ut eerut Town on EPC Mod e.
NH-7 Bijnor - Kotawali section 09AD of NH-709AD (package-i 2 22.07.20 01.11 03.05.2 15.04.2 (Pack Bijnor v)from Km. 153.660 to K 300.59 21.62 96.00% 8 21 .2021 023 026 age - m. 175.280 in the state o IV) f Uttar Pradesh.
Improvement and Up-gr adation of NH-709A Gar Contractor termi hmukteshwar ( Chainag nated. Matter is 2 NH-7 Meerut & e 83.200 of NH-24) to M 2068.9 12.03.20 10.10 10.10.2
50.254 sub-judice in Ho 9 09A Hapur eerut (Chainage 9.860 o 9 21 .2021 023 n’ble High court f NH-235) including conn of Allahabad. ector to NH-119 Packag e-XII in Uttar Pradesh.
Rehabilitation and upgra dation from km 51.600 to
08.01.20 km 75.700 of NH-321G ( 3 22/ 28.02 27.08.2 30.09.2 321G Etah Nuhkhas to Etah section 343.54 24.10 49 0 02.02.20 .2024 025 026 ) to two lane with paved 23 shoulder configuration u nder EPC mode R/U to 2-lane with PS of
18.04.20 Bewar to near karri villag 3 22/ 12.09 15.03.2 31.03.2 92 Mainpuri e section of NH-92 from 237.47 30.00 90 1 14.03.20 .2022 024 026 km.0.00 to 30.00 under 22 GNHCP Widening/Upgradation to
27.03.20 four lane configuration of 3 Shahjahan 1590.2 23/ Agreement signed on 14.01.20 731K Shahjahanpur - Bisalpur 47.03 2 pur 0 02.12.20 26.
section from Km. 0.000 t 25 o Km. 47.026 of NH-731K on Hybrid Annuity Mod e in the state of Uttar Pr adesh Rehabilitation and Upgra dation to 2L+PS of Miran pur-Katra to Radhaita of 18.04.20 Shahjahan 3 NH-730C (Km. 114.000 t 20/ 28.07 27.07.2 31.03.2 730C pur/ 172.50 23.25 88 3 o Km. 137.250) (Packag 14.03.20 .2022 024 026 Pilibhit e-III) under GNHCP with 22 loan assistance of World Bank on EPC mode Maintenance of km 0.00 0 to km 82.000 (except c 18.01.20 Shahjahan 3 h. 2.180 to 3.260 & Ch.3 24/ 19.06 18.06.2 18.06.2 730 pur/ 97.44 80.14 75 4 0.840 to 31.620) of NH-7 15.03.20 .2024 029 029 Pilibhit 30 under PBMC for the fi 24 nancial year 2023-24 Maintenance of Km. 0.0
08.01.20 Shahjahan00 to Km 105.500 (exclu 3 24/ 19.06 18.06.2 18.06.2 730A pur/ ding Ch.15.500 to Ch. 1 128.67 104.00 75 5 15.03.20 .2024 029 029 Pilibhit 7.000) of NH-730 under 24 PBMC for FY 2023-24 R/U to 2-lane with PS of
18.04.20 Bewar to Allahganj Secti 3 Farrukhab 20/ 24.11 23.11.2 31.03.2 730C on of NH-730C from km. 340.16 52.77 98 6 ad 14.03.20 .2022 024 026
0.00 to 52.770 under GN 22 HCP Maintenance of NH 730 B - Ch 0.000 to 32.200,
22.11.20 730B/ NH 731K - Ch 40.000 to 3 Bareilly/ 24/ 20.06 19.06.2 19.06.2 731K/ 42.000 & 43.000 to 43.8 3.17 36.50 70 7 Pilibhit 22.05.20 .2025 026 026 730A 00 & NH 730A - Ch 15.5 25 00 to 17.000 under STM C on % rate basic Operation & Maintenanc e of Four-laning stretch of NH-709B, from EPE C rossing (Design Ch. 0+0 3 Baghpat & 00) to the start of Shamli 02-09-20 14.11 12.11.2 12.11.2 709B 67 61.409 20 8 Shamli Bypass (Design Ch. 61+ 25 .2025 030 030
409) on Performance Ba sed Maintenance Contra ct (PBMC) mode in the s tate of Uttar PradeshANNEXURE-III Details of various initiatives taken by the Government in Ministry of
Road Transport and Highways for road safety: -
(1) Education: i. Administers a scheme for setting up of Institutes of Driving Training & Research (IDTRs), Regional Driving Training Centres
(RDTCs) and Driving Training Centres (DTCs) at state/district level across the Country. Recently revised scheme guidelines have been issued, incorporating enhanced financial assistance and streamlined eligibility criteria for establishing Driving Training Institutes. Additionally, incentives have been introduced for setting up Automated Testing Stations (ATS) in conjunction with Driving Training Institutes (DTIs) under the Training-Testing Cluster approach.
ii. Administers Road Safety Advocacy Scheme for raising awareness about road safety and for administering road safety programs. iii. Observance of National Road Safety Month every year for spreading awareness and strengthening road safety.
(2) Engineering:
2.1. Road engineering: i. Road Safety Audit (RSA) of all National Highways (NHs) has been made mandatory through third party auditors/ experts at all stages i.e. design, construction, operation and maintenance etc.
ii. High priority is accorded to identification and rectification of black spots /accident spots on NHs. iii. Road Safety Officer (RSO) has been designated at each Regional Office of road owning agencies under the Ministry to look after RSA and other road safety related works.iv. Administers the electronic Detailed Accident Report (e-DAR) Project to establish a central repository for reporting, management and analysis of road accidents data across the Country.
v. Issued guidelines for the provision of signages on Expressways and National Highways to offer improved visibility and intuitive guidance to the drivers. vi. Provisions have been made in the Motor Vehicles Act, 1988 for failure to comply with standards for the road design, construction and maintenance, as prescribed by the Central Government from time to time.
2.2 Vehicle engineering:
Various initiatives were undertaken to make vehicles safer,
including the following: - i. Mandatory provision of an airbag for the passenger seated on the front seat of a vehicle, next to the driver. ii. Prescribed norms related to safety measures for children below four years of age, riding or being carried on a motor cycle. It also specifies use of a safety harness, crash helmet and restricts speed to 40kmph.
iii. Mandatory provisions for fitment of following listed safety
technologies: - For M1 category vehicles: a. Seat Belt Reminder (SBR) for driver and co-driver. b. Manual Override for central locking system c. Over speed warning system.
For all M and N category vehicles: a. Reverse Parking Alert System iv. Mandated Anti-Lock Braking System (ABS) for certain classes of L [Motor vehicle with less than four wheels and includes a Quadricycle], M [Motor vehicles with at least four wheels used for carrying passengers] and N [Motor vehicles with at least fourwheels used for carrying goods which may also carry persons in addition to goods, subject to conditions stipulated in BIS standards] categories.
v. Mandated speed limiting function/speed limiting device in all transport vehicles, except for two wheelers, three wheelers, quadricycles, fire tenders, ambulances and police vehicles. vi. Published the rules for recognition, regulation and control of Automated Testing Stations, which define the procedure for fitness testing of vehicles through automated equipment and the procedure for grant of fitness certificate by ATSs. The rules have been further amended on 31.10.2022 and 14.03.2024.
vii. Formulated the Vehicle Scrapping Policy based on incentives/dis-incentives and for creating an ecosystem to phase out old, unfit and polluting vehicles. viii. Formulated a Scheme to set up one model Inspection & Certification Centre in each State/UT with Central assistance for testing the fitness of vehicles through an automated system.
ix. Published rules regarding the Bharat New Car Assessment Program (BNCAP) to introduce the concept of safety rating of passenger cars and empower consumers to take informed decisions. x. Published rules regarding prescribed level playing field in the area of manufacturing of buses by Original Equipment Manufacturers (OEMs) and Bus Body Builders.
xi. Mandated vehicles, manufactured on or after 1st October, 2025, shall be fitted with an air-conditioning system for the cabin of vehicles of N2 (goods vehicle with gross vehicle weight exceeding
3.5 tonnes but not exceeding 12.0 tonnes) and N3 (goods vehicle with gross vehicle weight exceeding 12.0 tonnes) category. xii. Published rules for revision of standards for Safety Belt, Restraint Systems and Safety Belt Reminder to provide provisions for applicability of revised standards for safety belt assemblies, safety belt anchorages and the installation of Safety Belts and Restraint Systems, in Motor vehicles of category M,N and L7 w.e.f.
01st April, 2025. Further, the vehicles of category M1, manufacturedon and after the 1st April 2025, shall meet the requirement of safety belt reminder for all front facing rear seats as per AIS-145-2018.
xiii. Published rules for Active safety features in Medium and Heavy Duty vehicles, which provide for Braking System including Anti-lock Braking, Endurance Braking System for M2, M3, N1, N2, N3 and Quadricycle (effective for new models from 1st January, 2027 and for existing models from 1st October, 2027), and Advanced Driver Assistance Systems (ADAS) including Vehicle Stability Function (VSF), Lane Departure Warning System (LDWS), Driver Drowsiness and Attention Warning Systems, Blind Spot Information Systems and Moving off Information Systems for M2, M3, N2 and N3 categories of vehicles (effective for new models from 1st October, 2027 and for existing models from 1st January, 2028).
(3) Enforcement: i. The Motor Vehicles (Amendment) Act, 2019 as stands implemented provides for strict penalties for ensuring compliance and enhancing deterrence for violation of traffic rules and strict enforcement through use of technology. Traffic management and enforcement is essentially in the domain of State Governments/UT Administrations. While Central Government formulates rules under the Motor Vehicle Act, 1988, the enforcement of these rules comes under the purview of State Governments/UT Administrations.
ii. Issued rules for Electronic Monitoring and Enforcement of Road Safety. The rules specify the detailed provisions for placement of electronic enforcement devices on high risk & high density corridors on National Highways, State Highways and critical junctions cities having a population of more than one million in the country and cities under National Clean Air Programme (NCAP).
iii. Government has issued guidelines for incentive to States for Implementation of Electronic Enforcement of Road Safety under the Scheme for Special Assistance to States for Capital Investment 2025-26 (SASCI 2025-26) with allocation of Rs. 3,000 Crore (on first come first serve basis).iv. On 10th June, 2024, the Government has issued an advisory to all the States and Union territories on technological interventions for ensuring compliance with Motor Vehicle Act, 1988.
(4) Emergency care: i. Revised the scheme guidelines (named as Rah-Veer) for the protection of Good Samaritan, who in good faith, voluntarily and without expectation of any reward or compensation renders emergency medical or non-medical care or assistance at the scene of an accident to the victim or transports such victim to the hospital. As per the scheme, the reward for Rah-Veer has been increased to Rs. 25,000/- from Rs. 5,000/-.
ii. Enhanced compensation of victims of Hit and Run motor accidents (from Rs. 12,500 to Rs. 50,000 for grievous hurt and from Rs. 25,000 to Rs.2,00,000 for death). iii. The National Highways Authority of India has made provisions for ambulances with paramedical staff/Emergency Medical Technician/Nurse at toll plazas on the completed corridors of National Highways.
iv. Government in Ministry of Road Transport and Highways has notified the Cashless Treatment of Road Accident Victims Scheme, 2025 on 5th May, 2025. The detailed guidelines including process flow, stakeholder wise standard operating procedures and clearly delineated roles and responsibilities have also been notified on 4th June, 2025.
*****