**Executive Summary**
This report describes the PRAGATI (Pro-Active Governance and Timely Implementation) platform, a Government of India initiative for fast-tracking projects, schemes, and grievance redressal. Launched in 2015, it facilitates real-time review by the Prime Minister. PRAGATI has significantly accelerated India's development, with 382 major national projects reviewed and monitored. The report further emphasizes that PRAGATI has completed its 50th meeting milestone.
**Key Points / Main Content**
* **Overview of PRAGATI:**
* PRAGATI is a flagship platform for fast-tracking projects, schemes, and grievance redressal.
* It ensures real-time coordination between the Centre and States under the Prime Minister's supervision.
* PRAGATI integrates digital data management, video conferencing, and geo-spatial technology.
* **Impact and Scale:**
* PRAGATI has expedited projects worth over ₹85 lakh crore.
* 2,958 out of 3,187 identified issues have been resolved.
* 382 projects have been reviewed under PRAGATI since 2014.
* **Review and Follow-up Process:**
* Prime Minister chairs PRAGATI review meetings with Chief Secretaries of States and Secretaries of Central Ministries/Departments.
* A multi-tier follow-up mechanism ensures the timely implementation of decisions.
* **Cooperative Federalism:**
* PRAGATI enables faster resolution of inter-state and Centre-State issues.
* It ensures direct coordination between multiple ministries and State governments.
* **Sectoral Impact:**
* PRAGATI has played a pivotal role in accelerating the implementation and resolving bottlenecks across major infrastructure sectors such as Railways, Road, Transport & Highways, and Power.
* **Projects Unlocked:**
* Several long-pending projects, including the Bogibeel rail-cum-road bridge and the Navi Mumbai International Airport, were unlocked through PRAGATI.
* **Critical Infrastructure Interventions:**
* PRAGATI facilitated critical interventions in power transmission projects and highway projects.
* **Social Sector & Citizen-Centric Governance:**
* PRAGATI has expanded to include social sector schemes and public grievances.
**Impact Analysis**
**Stakeholder: Government of India and State Governments**
* **Impact:** Improved coordination, faster project implementation, resolution of inter-state and Centre-State issues, and better governance.
* **Action Required:** Participation in PRAGATI review meetings, implementation of decisions, and resolving pending issues at the district level.
**Stakeholder: Citizens**
* **Impact:** Faster completion of projects and schemes, quicker grievance redressal, improved access to infrastructure and services.
* **Action Required:** Utilize PRAGATI platform to highlight and resolve grievances.
**Stakeholder: Implementing Agencies (Central Ministries/Departments)**
* **Impact:** Faster clearances, issue resolution, and increased accountability.
* **Action Required:** Update project milestones, participate in review meetings, and implement decisions in a time-bound manner.
Key Entities Referenced
PRAGATI: Pro-Active Governance and Timely Implementation; Government of India's platform for fast-tracking projects, schemes, and grievance redressal through real-time review by the Prime Minister.
Prime Minister's Office (PMO): Oversees the monitoring of schemes and grievances reviewed under PRAGATI.
Cabinet Secretariat: Monitors projects following PRAGATI meetings to ensure timely implementation.
States: The policy emphasizes real-time coordination between the Center and States, involving Chief Secretaries of States in review meetings.
DPIIT: Department for Promotion of Industry and Internal Trade. Involved in reviewing public and private projects and issues, especially for escalation to PRAGATI.
PIB Headquarters
PRAGATI: A Decade of Cooperative, Outcome-
Driven Governance
प्रव तथ: 13 JAN 2026 7:08PM by PIB Delhi
Key Takeaways
PRAGATI has significantly accelerated India’s development by fast-tracking projects worth
more than ₹85 lakh crore.
Under PRAGATI, 382 major national projects have been systematically reviewed and closely
monitored.
Out of 3,187 identified issues, 2,958 have already been resolved, significantly reducing delays
and cost overruns.
The platform ensures real-time coordination between the Centre and States under direct Prime
Ministerial supervision, strengthening accountability.
PRAGATI: A Model of Real-Time Governance
PRAGATI (Pro-Active Governance and Timely Implementation) is the Government of India’s
flagship platform for fast-tracking projects, schemes, and grievance redressal through direct, real-time
review by the Prime Minister, in partnership with States and Union Ministries. PRAGATI is a strong
example of how digital governance can translate intent into real, visible progress. Launched in 2015
under Prime Minister Narendra Modi, PRAGATI has reshaped how India tracks and drives major
infrastructure projects and key social programmes. More than a review forum, it reflects a push to break
bureaucratic inertia, strengthen a Team India approach across the Centre and States, and build a culture
where decisions are time-bound, follow-through is expected, and outcomes are measured. Several long-
pending projects initiated by previous governments were also taken up under the PRAGATI platform and
subsequently unlocked or completed. These include the Bogibeel rail-cum-road bridge (conceived in
1997), Navi Mumbai International Airport (conceptualised in 1997), Bhilai Steel Plant modernisation
(approved in 2007) among various others.
PRAGATI: What It Is and Why It Was Needed
Large time and cost overruns had long been a persistent challenge in India’s public projects and schemes.
To address this issue across all levels of government, the Prime Minister conceptualized PRAGATI as a
comprehensive solution. PRAGATI is a distinctive, integrated, and interactive platform designed to
both resolve grievances of and to monitor and review key programmes and projects of the Government of
India, along with projects highlighted by State Governments. The PRAGATI platform uniquely brings
together three modern technologies—digital data management, video conferencing, and geo-spatial
technology. Through this system, the Prime Minister can directly engage with concerned Central and Stateofficials, supported by complete information and up-to-date visual evidence from project sites. This
initiative also represents an innovative step in e-governance and exemplifies the principles of good
governance.
PRAGATI’s Origin and Evolution
PRAGATI draws its inspiration from SWAGAT (State Wide Attention on Grievances by Application
of Technology). SWAGAT was then Chief Minister of Gujarat Shri Narendra Modi’s brainchild, launched
in April 2003, and one of India’s early, technology-enabled platforms of its kind for grievance redressal.
Aptly named—SWAGAT means “welcome” in many Indian languages—it was designed to make
government more accessible and accountable. Citizens could submit complaints online, track their
applications, view decisions, and even interact with officials through video conferencing. A structured
screening process ensured that serious, high-priority petitions reached the Chief Minister’s desk, while
monthly public hearings created a direct channel for citizens to place their concerns before the state
leadership. Over time, SWAGAT came to be widely recognised for strengthening transparency,
responsiveness, and accountability in public service delivery.
After taking office as Prime Minister in 2014, PM Modi sought to scale the underlying discipline of
SWAGAT to the national level. With PRAGATI, the focus expanded from individual grievances to the
larger, more complex challenge of driving delivery across major projects and key programmes - especially
where issues were stuck due to multi-agency dependencies or Centre–State coordination. In that sense,
PRAGATI was not merely a digital upgrade; it represented a shift in how governance is executed—more
time-bound, more outcome-driven, and more collaborative, aligned with the broader principle of
“Minimum Government, Maximum Governance.”
Structured Review and Follow-up Process
PRAGATI is a technology-driven platform for monitoring projects, redressing citizen grievances,
and reviewing scheme implementation through coordinated efforts of Central Ministries and State
Governments. It also integrates platforms such as PM GatiShakti, PARIVESH, and the PM Ref
Portal.At the apex level, the Prime Minister chairs PRAGATI review meetings with Chief Secretaries of
States and Secretaries of Central Ministries/Departments to resolve issues related to identified
projects and schemes.
Following the meetings, a multi-tier follow-up mechanism ensures timely implementation of
decisions. Projects are monitored by the Cabinet Secretariat, while schemes and grievances are
reviewed at the Ministry level under continuous oversight of the Prime Minister’s Office (PMO).
Project & Issue Escalation Mechanism
Regular issues are resolved at the Ministry level, while complex and critical issues are escalated for
review up to PRAGATI.
Strengthening Cooperative Federalism and Governance
PRAGATI institutionalises cooperative federalism in action. Chief Secretaries of States and Secretaries to the Government of
India participate together, answerable in real time, enabling faster resolution of inter-state and Centre-State issues. The platform
breaks silos by ensuring:
Direct coordination between multiple ministries and State governments.
Time-bound follow-up monitored by the Cabinet Secretariat.
Shared ownership of outcomes rather than fragmented responsibility.
This model has substantially improved inter-ministerial coordination and reduced procedural bottlenecks
that traditionally delayed large public projects.PRAGATI’s Impact Across Key Infrastructure Sectors
PRAGATI has played a pivotal role in accelerating implementation and resolving bottlenecks across major
infrastructure sectors. Some key sectoral impacts are highlighted below.Beyond Infrastructure: Social Sector & Citizen-Centric Governance
While PRAGATI initially focused on large infrastructure projects, its scope has expanded to social sector schemes and public
grievances, making it a people-centric governance instrument.
Examples of Long-Pending Projects Unlocked Through PRAGATI
Several projects that had remained stalled for decades were completed or decisively unlocked after being
taken up under the PRAGATI platform, demonstrating the impact of sustained high-level monitoring and
inter-governmental coordination.
The Bogibeel rail-cum-road bridge in Assam, first conceived in 1997, had remained pending for
over two decades due to funding and coordination challenges. Following regular reviews under
PRAGATI, inter-agency issues were resolved, and execution was closely monitored, leading to theproject’s completion and inauguration in 2018, significantly improving connectivity and strategic
mobility in the North-East.
The Navi Mumbai International Airport, conceptualised in 1997, remained delayed for around 25
years due to land acquisition, rehabilitation of project-affected families and the involvement of
multiple agencies. Following PRAGATI intervention, these long-pending issues were addressed in a
time-bound manner through Centre–State coordination, unlocking the project and significantly
accelerating construction. Hon’ble Prime Minister inaugurated phase I of the project in October
2025.
The modernisation and expansion of the Bhilai Steel Plant, approved in 2007, faced prolonged
delays of nearly 15 years due to contractual disputes, execution challenges and cost overruns. High-
level monitoring under PRAGATI helped resolve inter-ministerial and PSU-level bottlenecks,
enabling completion of the modernisation programme and enhancement of the plant’s capacity and
efficiency.
The LARA Super Thermal Power Project (Stage-I) in Chhattisgarh, sanctioned in December
2012, experienced delays for more than 13 years due to land acquisition and contractor-related
constraints. Continuous monitoring and issue resolution through PRAGATI helped unblock the
project, resulting in the commissioning of the units and the addition to national power generation
capacity.
The Gadarwara Super Thermal Power Project in Madhya Pradesh, approved in 2008, had
remained delayed for over a decade because of land, fuel linkage and execution-related issues. After
being taken up under PRAGATI, outstanding clearances and coordination issues were fast-tracked,
leading to the commissioning of the project and strengthening of regional power availability.Recognised as a critical anchor in India’s eastern power generation landscape, the North
Karanpura Super Thermal Power Project (NKSTPP) is a flagship pit-head thermal power
initiative aimed at strengthening base-load electricity availability and grid reliability in eastern
India. The physical progress of the project stood at approximately 60% during FY 2019–20.
Following focused reviews and coordinated interventions, including a PRAGATI review conducted
in September 2021, project execution witnessed a marked acceleration, with physical progress
increasing to around 87% by FY 2023–24.
The Nabinagar Super Thermal Power Project (NSTPP) occupies a strategic position in India’s
energy security architecture. Upon escalation under the PRAGATI mechanism, unresolved land and
rehabilitation issues were addressed. This intervention enabled focused monitoring and
accountability, leading to progressive resolution of land-related constraints and resumption of
project execution.
All India Institute of Medical Sciences (AIIMS), Bibinagar is being established at Bibinagar in
Yadadri Bhuvanagiri District, Telangana, under the Pradhan Mantri Swasthya Suraksha Yojana
(PMSSY). The project was reviewd under the PRAGATI mechanism on 28.06.2023, following
which a clear progress in project execution was observed. As of 14.09.2023, the physical progress
stood at 29%, which increased sharply to 57% by the end of FY 2023–24, reflecting the impact of
focused monitoring and expedited decision-making under PRAGATI.
Jammu & Kashmir has entered a new era of healthcare accessibility and excellence with the
establishment of the All-India Institute of Medical Sciences (AIIMS), Jammu, at Samba. Given
the national importance of AIIMS Jammu in strengthening healthcare access in the region, the
project and its critical bottlenecks were taken up through the Project Monitoring Group (PMG) and
subsequently escalated to the PRAGATI mechanism. The project was reviewed under
PRAGATI on 28-06-2023. The PRAGATI intervention proved decisive in altering the project’s
execution environment. With the issue elevated to the highest level of governance, accountability
across departments was sharply reinforced.
The All India Institute of Medical Sciences (AIIMS), Guwahati, was sanctioned on 24th May
2017 under the Pradhan Mantri Swasthya Suraksha Yojana (PMSSY). PRAGATI served as a
critical intervention platform, with reviews in April 2018 and February 2023. PRAGATI’s
oversight directly enabled resolution of key dependencies, including commissioning of
electricity infrastructure, acceleration of stormwater management systems, alignment of water
supply readiness, and overall synchronisation necessary for operationalisation.Mumbai Urja Marg Limited (MUML) is a Ministry of Power, Government of India–envisaged
transmission strengthening project in Maharashtra, designed to reinforce the power transmission backbone
for the Mumbai Metropolitan Region. The project faced multiple interlinked land, forest, Right of Way
(RoW), and administrative bottlenecks. It was sanctioned in October 2024. PRAGATI-driven
interventions converted fragmented approvals into synchronized action, enabling progressive
achievement of milestones—80 per cent RoW clearance by 2023, 100 per cent foundation, erection,
and stringing completion by August 2024, and successful charging of transmission lines in
September 2024—thereby restoring execution momentum and ensuring timely commissioning of the
MUML project.
The 400 kV D/C Teesta III–Kishanganj Transmission Line (214 km) is an Inter-State Transmission
System (ISTS) project designed to evacuate power from Sikkim’s commissioned hydro assets. It stands as
evidence of how PRAGATI converts high-level directives into field-level delivery by resolving
jurisdictional constraints and aligning multi-agency execution, rather than altering engineering design. It
remains a reference case of coordinated Centre–State intervention enabling commissioning in challenging
terrain with sustained operational performance.
The UER-II project along NH-344M was conceived as a transformative intervention to augment
Delhi’s road infrastructure and restore traffic efficiency. Given its strategic importance for Delhi-NCR
mobility, the project was taken up for close monitoring under the Project Monitoring Group (PMG) and
subsequently reviewed at the national level through the PRAGATI mechanism. The PRAGATI
intervention proved pivotal in breaking long-standing inter-departmental bottlenecks as each pending issue
was digitally tracked with assigned responsibilities and timelines.
The four-laning of the Sangareddy–Akola–Nanded section of NH-161 spans 426 km from Akola (NH-
53) in Maharashtra to Sangareddy in Telangana, passing through Washim, Hingoli, Nanded and
Degloor. Forming part of the Indore–Hyderabad Economic Corridor under the Bharatmala Pariyojana,
this strategic highway provides seamless connectivity between major urban and economic centres across
Central and Southern India. The project was escalated to the PRAGATI portal. The coordinatedintervention brought all stakeholders—State authorities, district administration and the project proponent
—onto a single implementation framework with clear timelines and accountability. The resolution of
these long-standing issues within a short span of six months highlights the transformative role of the
PRAGATI mechanism in unlocking complex infrastructure bottlenecks and driving time-bound delivery.
Work on the Jammu–Udhampur–Srinagar–Baramulla rail link started in October 1994 while the date
of sanction was 31st March 1994 but progress remained slow for nearly 25 years owing to difficult terrain,
land acquisition constraints, forest clearances, and security-related challenges. After the project was
reviewed under PRAGATI, critical clearances were expedited, and bottlenecks were addressed through
coordinated action, resulting in the completion of the project and operational rail connectivity in the
Kashmir Valley.
The four-laning of the Khajuri–Wyndhamganj section of NH-75 (Sec-V) represents a strategically
important highway upgradation initiative in Jharkhand, aimed at strengthening regional and inter-state
road connectivity. The value of PRAGATI-led oversight is reflected in the project’s ability to maintain
momentum through its more complex later stages. Physical progress had reached 44.4% prior to the
PRAGATI review in August 2024, and subsequently advanced to 92.02%, demonstrating sustained
execution and effective issue management. At a stage where large infrastructure projects often experience
slippages due to land, clearance and coordination challenges, the continued progression underscores
how high-level monitoring and coordinated action at the State and district levels helped prevent
stagnation and ensured timely consolidation of works.
The Mumbai Trans Harbour Link (MTHL), officially named Atal Bihari Vajpayee Sewri–Nhava
Sheva Atal Setu, stands among India’s most transformative urban transport infrastructure initiatives.
Implemented by the Mumbai Metropolitan Region Development Authority (MMRDA) with financial
support from the Government of India, the Government of Maharashtra, and the Japan International
Cooperation Agency (JICA), project represents India’s longest sea bridge, spanning 21.8 kilometres,
and a landmark addition to the national transport network. Guided under the PRAGATI mechanism, the
project progressed through a disciplined, time-bound governance framework that ensured early
institutional alignment and sustained execution momentum.The Jagdishpur–Haldia & Bokaro–Dhamra Natural Gas Pipeline (JHBDPL), implemented by GAIL
(India) Limited is a cross-country pipeline project extending the National Gas Grid into eastern and
north-eastern India. Post PRAGATI, commissioning proceeded wherever technically feasible, while
unresolved segments were escalated to “high-priority status” through structured monitoring cycles at
the Prime Minister’s Office, Cabinet Secretariat, and DPIIT, with State Governments instructed to
resolve pendencies at the district level. This shift from sequential dependence to modular execution
altered the execution trajectory and enabled the project to move from delayed readiness to near
completion.
PRAGATI: A Global Case Study in Project Acceleration
A landmark case study by Oxford’s Said Business School, titled “From Gridlock to Growth: How
Leadership Enables India’s PRAGATI Ecosystem to Power Progress,” highlights PRAGATI as:
Transformative digital governance platform that has strengthened senior-level accountability & fast-
tracked long-pending infrastructure and social sector projects.
Global benchmark and a “Single Source of Truth” for real-time project monitoring and inter-
governmental coordination.
Global best practice and replicable model for developing economies, that can drive infrastructure
delivery, economic growth, and improved public trust.
Institution in cooperative federalism, bringing States/UTs administration and central ministries onto one
platform, ensuring apolitical, uniform attention to projects.Multi-Faceted Impact
PRAGATI’s influence on infrastructure delivery is visible across four dimensions:
Economic: Delays don’t just raise project costs through price escalation and logistical churn—they also postpone the
economic returns these assets generate through higher passenger movement and commercial activity. By accelerating issue-
resolution and completion, PRAGATI helps bring these returns online sooner and improves the value of every rupee invested.
Social: Faster completion means communities benefit earlier. Better roads connect remote areas to schools, hospitals, and
markets; rail links, bridges, and logistics upgrades support local enterprise and job creation. The cumulative effect is a more
connected India—where access, opportunity, and quality of life improve in ways that citizens can feel.
Environmental: Modernisation cannot come at the cost of sustainability. PRAGATI supports responsible development by
helping fast-track environment-related decision-making while keeping safeguards in view, reducing avoidable time overruns
that can increase emissions and resource use. PM GatiShakti puts forests, wildlife and eco‑sensitive zones on the same GIS
planning canvas, so environmental sensitivities are visible before a project is finalised. That early visibility enables alignment
planning, site-suitability and compliance checks—so agencies can adopt alternative alignments and design mitigations upfront
to avoid sensitive habitats and reduce ecological impact. And by relying on digital review and videoconferencing, it reduces the
need for carbon-intensive travel.
Positive Governance: PRAGATI is not only about expediting projects—it strengthens the culture of delivery. It reinforces
transparency, time-bound accountability, and inter-government coordination, and it has helped spread process improvements
across departments. In doing so, it acts as a catalyst for wider modernisation and initiatives that aim to extend the benefits of
growth more evenly across the country.
PRAGATI @ 50
As PRAGATI achieved its 50th meeting milestone, it stands as a defining example of how technology-enabled leadership,
cooperative federalism and continuous monitoring can translate intent into outcomes at a national scale. Five critical
infrastructure projects have been reviewed during the meeting by the Prime Minister across sectors, including Road, Railways,
Power, Water Resources, and Coal. These projects span 5 States, with a cumulative cost of more than ₹40,000 crore. This
acts as symbol of the deep transformation India has witnessed in the culture of governance over the last decade.