## Report on Railway Land Acquisition Notification
**1. Executive Summary:**
This report analyzes a notification from the Ministry of Railways, East Central Railway, regarding land acquisition for the Urda Dhangada New Rail Line Project in Jharkhand. The notification authorizes the District Land Acquisition Officer, Chatra, to act as the competent authority for land acquisition under the Railway Amendment Act 2008. The core purpose is to expedite the land acquisition process for this special railway project. This report outlines the key provisions of the notification, its implications, and the stakeholders involved.
**2. Introduction:**
This report provides an informative analysis of a notification issued by the Ministry of Railways, East Central Railway, concerning land acquisition for a railway project. The analysis is based solely on the provided text of the notification.
**3. Policy Overview:**
* This is a *new* policy related to a specific project, falling under the framework of the Railway Amendment Act 2008.
* Core Objective(s): To authorize a specific individual (District Land Acquisition Officer, Chatra) to be the competent authority for land acquisition related to the Urda Dhangada New Rail Line Project. This is inferred from the explicit wording of the notification.
**4. Background and Rationale:**
* This is a New Policy related to a Specific Project: The notification addresses the need for efficient land acquisition for the Urda Dhangada New Rail Line Project. The project is referred to as a "Special Railway Project," suggesting its importance. Land acquisition can often be a bottleneck in infrastructure projects. This notification aims to streamline the process by designating a competent authority. The Railway Amendment Act 2008 provides the legislative framework for such authorizations.
**5. Key Provisions / Changes:**
* **Key Provision:** The notification designates the District Land Acquisition Officer (DLAO), Chatra, as the "competent authority" to perform the functions outlined in the Railway Amendment Act 2008 concerning land acquisition. This authority extends specifically to the Urda Dhangada New Rail Line Project (15.00 Km) within the state of Jharkhand. This delegation of power is effective from the date of publication in the Gazette of India.
**6. Target Audience and Stakeholders:**
* Landowners within the 15.00 Km area of the Urda Dhangada New Rail Line Project in Jharkhand.
* Residents and communities along the proposed rail line who may be affected by the project.
* The District Land Acquisition Officer, Chatra, who is now responsible for land acquisition.
* The East Central Railway and its contractors involved in the project.
* The State Government of Jharkhand, which nominated the DLAO.
**7. Implementation Aspects (Inferred):**
* **Responsible Agency:** The District Land Acquisition Officer, Chatra, is the primary responsible agency. The East Central Railway is also involved in the project.
* **Timeline:** The authorization is effective from the date of publication of the notification in the Gazette of India (June 6, 2025, as suggested from the document header). The notification itself doesn't specify any other specific timelines for land acquisition.
* **Procedures:** The DLAO is expected to follow the procedures outlined in the Railway Amendment Act 2008 for land acquisition. The details of these procedures are not provided in the notification.
**8. Expected Outcomes / Impact of Changes:**
* The likely intended outcome is to expedite the land acquisition process for the Urda Dhangada New Rail Line Project. By designating a competent authority, the Railway aims to reduce bureaucratic delays and ensure timely completion of the project. This should lead to faster progress on the railway construction and ultimately improve transportation infrastructure in the region. The impact will be felt by those requiring compensation, those affected by the Rail Line going through their land, and those who will benefit from the new Railway Line.
**9. Conclusion:**
The notification analyzed is a crucial step in facilitating land acquisition for the Urda Dhangada New Rail Line Project. By authorizing the District Land Acquisition Officer, Chatra, as the competent authority, the Ministry of Railways aims to streamline the process and accelerate the implementation of this special railway project. The notification has significant implications for landowners, residents, and other stakeholders involved in the project and those that will benefit from it upon completion.
Key Entities Referenced
D. L.3300499: Registration number mentioned at the beginning of the document.
JUNE 6, 2025: Date of publication of the Gazette of India.
JYAISTHA 16, 1947: Corresponding date in the Indian national calendar.
THE GAZETTE OF INDIA: Official government publication.
MINISTRY OF RAILWAYS: Government ministry responsible for railways.
East Central Railway: Name of a railway zone.
NOTIFICATION: Type of document.
Patna: City where the notification was issued.
4th June, 2025: Date of the notification.
S.O. 2497E: Notification number.
Section 2: A section of the Railway Amendment Act 2008.
Railway Amendment Act 2008: Legislation related to railway amendments.
District Land Acquisition Officer, Chatra: Designated authority for land acquisition.
State Government: Government at the state level, implied to be Jharkhand.
Urda Dhangada New Rail Line Project: Name of the railway project.
15.00 Km: Length of the railway line project.
Special Railway Project: Category of the railway project.
Jharkhand: State where the project is located.
F. No. DCEConHZMELANDURDADHANGARA4495: File number.
RAMASHRAY PANDEY: Name of the CAOCon.
CAOCon: Designation of Ramashray Pandey, likely related to construction.
Government of India Press, Ring Road, Mayapuri, New Delhi110064: Location of the printing press.
Controller of Publications, Delhi110054: Publisher of the Gazette of India.
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
सी.जी.-बी.आर.-अ.-06062025-263651
CG-BRxx-xEG-I0D6H0x6x2x0 25-263651
xxxGIDExxx
असाधारण
EXTRAORDINARY
भाग II—खण्ड 3—उप-खण्ड (ii)
PART II—Section 3—Sub-section (ii)
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 2438] नई कदल्ली, िक्रु वार, िनू 6, 2025/ज्य ष्े ठ 16, 1947
No. 2438] NEW DELHI, FRIDAY, JUNE 6, 2025/JYAISTHA 16, 1947
रेल मत्रं ालय
अजधसचू ना
iVuk] 4 twu] 2025
का.आ. 2497(अ).— रेलव े संिोधन अजधजनयम 2008की धारा 2 के खंड 7 ए द्वारा प्रदत्त िजि का प्रयोग करत े
हुए , राज्य सरकार द्वारा नाजमत जिला भू-अिनज पदाजधकारी, को उि अजधजनयम के तहत झारखडं राज्य के अंतगतज
“उरदा-धनगड़ाके बीच नई रेल लाइन पररयोिना 15.00 Km. ” पररयोिना िो जविेष रेलव े पररयोिना का जहस्ट्सा ह ै के
कायज के जलए सक्षम प्राजधकारी के रूप में एतद द्वारा अजधकृत ककया िाता ह ै , िो भारत के रािपत्र में इस अजधसूचना के
प्रकािन कक तारीख से लाग ुहोगा।
[फा. स.ं डीसीई/कॉन/एचिडे एमई/उरदा-धनगड़ा/4495]
jkekJ; ik.Ms;] eq[; iz'kklfud vf/kdkjh@fuekZ.k
3690 GI/2025 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
MINISTRY OF RAILWAYS
(East Central Railway)
NOTIFICATION
Patna, the 4th June, 2025
S.O. 2497(E).— In Exercise of Power conferred under clause 7A of Section 2 of the Railway
(Amendment) Act 2008, the District Land Acquisition Officer, Chatra, as nominated by State Government is
hereby authorized as competent authority to perform the function of such authority under the said act in the
area of “Urda – Dhangada New Rail Line Project (15.00 Km)”,which is part of Special Railway Project,
in the state of Jharkhand with effect from the date of publication of this notification in the Gazette of India.
[F. No. DCE/Con/HZME/LAND/URDA-DHANGARA/4495]
RAMASHRAY PANDEY, CAO/Con.
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064