## Policy Analysis Report: Acquisition of Right of User for Crude Oil Pipeline - New Mundra Panipat Pipeline Project
**1. Executive Summary:**
This report analyzes a new policy notification from the Ministry of Petroleum and Natural Gas, Government of India, published on December 15, 2022. The policy declares the Central Government's intention to acquire the right of user in land for laying a crude oil pipeline from Chudva to Panipat under the New Mundra Panipat Pipeline Project by Indian Oil Corporation Limited (IOCL). The key finding is that this notification initiates the land acquisition process, inviting objections from landowners within a specified timeframe.
**2. Introduction:**
This report aims to provide a comprehensive overview of the policy notification S.O. 5998(E), published in the Gazette of India on December 21, 2022, regarding the acquisition of the right of user in land for a crude oil pipeline project. This analysis is based solely on the information provided within the policy text.
**3. Policy Overview:**
* **Type:** New Policy Notification
* **Core Objective(s):** To acquire the right of user in land required for laying a crude oil pipeline from Chudva to Panipat under the New Mundra Panipat Pipeline Project by Indian Oil Corporation Limited. This is explicitly stated in the text: "it is necessary in the public interest to lay Crude Oil Pipeline from Chudva to Panipat under New Mundra Panipat Pipeline Project..." and "...it is necessary to acquire the right of user in the land described in the schedule annexed to this notification."
**4. Background and Rationale:**
As a new policy notification, this likely addresses the need for expanding and improving the crude oil pipeline infrastructure in India. The project aims to connect Chudva to Panipat, suggesting a strategic move to enhance the transportation network for crude oil. The text explicitly states that the laying of this pipeline is deemed "necessary in the public interest," implying that the project aims to improve the supply and distribution of crude oil.
**5. Key Provisions / Changes:**
As this is a new policy declaration, the key provision outlined in the text is the declaration of intent by the Central Government to acquire the right of user in the land specified in the attached schedule. The policy outlines the following main components:
* **Declaration of Intent:** The core of the policy is the government's stated intention to acquire the right of user in the specified land.
* **Project Details:** The policy identifies the project as the "New Mundra Panipat Pipeline Project" and names the implementing entity as "Indian Oil Corporation Limited."
* **Geographic Scope:** The affected land is located in Taluka Bhachau of Kutch District in the State of Gujarat. Specific Khasara numbers and areas to be acquired are listed in a schedule.
* **Objection Mechanism:** The policy establishes a mechanism for affected individuals to object to the acquisition. It provides a timeframe of twenty-one days from the publication date for submitting objections in writing.
* **Contact Information:** The policy provides the contact information of the "Competent Authority," Shri Bharat J. Akruwala, for submitting objections.
**6. Target Audience and Stakeholders:**
The primary target audience and stakeholders are:
* **Landowners:** Individuals or entities who own land within the specified areas (listed in the schedule with Khasara numbers) in Taluka Bhachau, Kutch District, Gujarat. These landowners are directly affected by the proposed acquisition.
* **Indian Oil Corporation Limited (IOCL):** The implementing agency responsible for the New Mundra Panipat Pipeline Project.
* **General Public:** While not explicitly stated, the phrase "public interest" suggests that the broader community stands to benefit from improved crude oil infrastructure.
**7. Implementation Aspects (Inferred):**
* **Responsible Agency:** The Ministry of Petroleum and Natural Gas is the responsible government body. Indian Oil Corporation Limited (IOCL) is the implementing agency for the pipeline project. Shri Bharat J. Akruwala, Additional Collector Retd., is identified as the "Competent Authority" for handling objections.
* **Timeline:** A 21-day period is provided for landowners to file objections, starting from the date the notification is made available to the public.
* **Procedure:** The policy outlines a procedure for landowners to object in writing to the acquisition of the right of user or the laying of the pipeline. The objections must be submitted to the designated Competent Authority.
**8. Expected Outcomes / Impact of Changes:**
The intended outcome of this policy is to facilitate the laying of the crude oil pipeline by acquiring the necessary rights of user in the land. The successful implementation of the New Mundra Panipat Pipeline Project is expected to improve the transportation and supply of crude oil, contributing to energy security and economic development. The impact on landowners includes potential compensation for the right of user acquired. The policy aims to balance the public interest with the rights of individual landowners by providing a mechanism for objections and presumably fair compensation.
**9. Conclusion:**
The policy notification S.O. 5998(E) represents a crucial step in the development of the New Mundra Panipat Pipeline Project. By declaring the intention to acquire the right of user in land, the government initiates the process of building vital infrastructure for crude oil transportation. The notification provides a clear framework for affected landowners to raise concerns and seek redress, highlighting the government's commitment to due process and public interest. The success of this project hinges on the efficient and equitable implementation of this policy.
Key Entities Referenced
Crude Oil Pipeline: Type of infrastructure being laid
Chudva: Starting point of the Crude Oil Pipeline
Panipat: End point of the Crude Oil Pipeline
New Mundra Panipat Pipeline Project: Name of the pipeline project
Indian Oil Corporation Limited: Company responsible for laying the pipeline
Bhachau Taluka: Taluka where the land acquisition is taking place
Kutch District: District where the land acquisition is taking place
Gujarat: State where the land acquisition is taking place
Petroleum and Minerals Pipelines Acquisition of Right of User in land Act, 1962: The law under which the land is being acquired
Bharat J. Akruwala: Additional Collector Retd. Competent Authority for the New Mundra Panipat Pipeline Project
Gandhidham: City in Kutch District, Gujarat where the Competent Authority is located
Chhadavada: Name of a village where land is being acquired
Shivlakha: Name of a village where land is being acquired
New Delhi: Place of Notification
Ministry of Petroleum and Natural Gas: Central Government Ministry publishing the notification
रजजस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
सी.जी.-डी.एल.-अ.-22122022-241305
xxxGIDHxxx
CG-DL-E-22122022-241305
xxxGIDExxx
ऄसाधारण
EXTRAORDINARY
भाग II—खण् ड 3—ईप-खण्ड (ii)
PART II—Section 3—Sub-section (ii)
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 5757] नइ दिल्ली, ब धवार, दिसम्ब र 21, 2022/ऄग्रहायण 30, 1944
No. 5757] NEW DELHI, WEDNESDAY, DECEMBER 21, 2022/AGRAHAYANA 30, 1944
परे ोजलयम एव ंप्राकृजतक गसै मत्रं ालय
ऄजधसचू ना
नइ दिल्ली, 15 दिसम् बर, 2022
का.अ. 5998(ऄ).—केन्द्रीय सरकार को लोकजहत म ें यह अवश्यक प्रतीत होता ह ै दक आंजडयन ऑयल कॉपोरेिन
जलजमटेड को कच्चे तेल के पररवहन के जलए, न्द्यू म ंरा-पानीपत कच्चा तेल पाआपलाआन पररयोजना के तहत, च डवा गांव स े
पानीपत तक पाआपलाआन को ताल का: भचाई, जजला कच्छ, राज्य ग जरात मे जबछाइ जानी चाजहए।
और केन्द्रीय सरकार को ऐसी पाआपलाआन जबछाने के प्रयोजन के जलये यह अवश्यक प्रतीत होता ह ै दक ऐसी भूजम
में जो आस से ईपाबद्ध ऄन सूची मे वर्णणत ह,ै और जजस में ईक्त पाआपलाआन जबछाइ जाने का प्रस्ट्ताव है, ईपयोग के ऄजधकार
का ऄजजन दकया जाए ।
ऄतः ऄब, केन्द्रीय सरकार, परे ोजलयम और खजनज पाआपलाआन (भूजम म े ईपयोग के ऄजधकार का ऄजनज )
ऄजधजनयम, 1962 (1962 का 50) की धारा 3 की ईपधारा (1) द्वारा प्रित् त िजक्तय का प्रयोग करत े ुएए ईस भूजम के
ईपयोग के ऄजधकार ऄजजन करने के ऄपन ेअिय की घोषणा करती ह ै ।
कोइ व्यजक्त, जो ईक्त ऄन स ची में वर्णणत भूजम म ें जहतबद्ध ह,ै ईस तारीख स,े जजसको आस ऄजधसूचना म ें यक्त
भारत के राजपत्र की प्रजतयााँ साधारण जनता को ईपलब्ध करा िी जाती है, आक्कीस दिन के भीतर, भूजम के नीचे पाआपलाआन
जबछाए जाने के जलए, ईसमे ईपयोग के ऄजधकार ऄजनज के सम् बन्द् ध में श्री भरत ज.े ऄक्रूवाला, ऄपर समाहता ज (ऄवकाि
प्राप्त) सक्षम प्राजधकारी, न्द्य ू मन्द् रा पानीपत कच्चा तले पाआपलाआन पररयोजना, आंजडयन ऑयल कॉपोरेिन जलजमटेड, प्लोट
न.ं 346 एव ं347, वाडज न.ं 12 बी, गाधं ीधाम, जजला – कच्छ, गज रात – 370201 को जलजखत रूप म ेंअक्षपे भेज सकेगा।
8566 GI/2022 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
ऄनस ची
ताल का - भचाई जजला – कच्छ राज्य - गज रात
क्रम सपं ादित क्षत्रे फल
ग़ावं का नाम खसरा स.ं
स.ं हेकटेयर एयर वग़ ॅमीटर
1 2 3 4 5 6
1 छाडवाडा 483 00 01 07
481 00 18 83
480 00 56 80
590 00 03 65
593 00 11 74
594 00 03 44
2 िीवलखा 1317 01 54 94
705/2 00 00 20
712 00 13 07
707/2 00 05 64
707/3 00 07 67
707/4 00 13 39
702/1 00 31 58
708 00 00 71
701 00 15 11
700 00 23 49
694/1 00 19 95
693 00 09 45
694/2 00 01 85
689/2 00 00 20
691 00 10 51
692/2 00 22 53
597 00 14 02
389/1 00 08 26
388 00 01 00
[फा. सं. अर- 11017/5/2022-ओअर-I/इ-44402]
पी. सोमाक मार, ऄवर सजचव
MINISTRY OF PETROLEUM AND NATURAL GAS
NOTIFICATION
New Delhi, the 15th December, 2022
S.O. 5998(E).—Whereas, it appears to the Central Government that it is necessary in the public interest to
lay Crude Oil Pipeline from Chudva to Panipat under New Mundra - Panipat Pipeline Project by Indian Oil
Corporation Limited in Taluka Bhachau of Kutch District in State of Gujarat.
And whereas, it appears to the Central Government that for the purpose of laying the said pipeline, it is
necessary to acquire the right of user in the land described in the schedule annexed to this notification.[भाग II—खण् ड 3(ii)] भारत का राजपत्र : ऄसाधारण 3
Now, therefore, in exercise of the powers conferred by Sub Section (1) of Section 3 of the Petroleum and
Minerals Pipelines (Acquisition of Right of User in land) Act, 1962 (50 of 1962), the Central Government hereby
declares its intention to acquire the right of user therein.
Any person interested in the land described in the said schedule may, within twenty–one days from the date
on which the copies of this notification, as published in the Gazette of India, are made available to the General Public,
object in writing to the acquisition of the right of user therein or laying of the pipeline under the land to Shri Bharat
J. Akruwala, Additional Collector (Retd.) Competent Authority, New Mundra Panipat Pipeline Project, Indian
Oil Corporation Limited, Plot No. 346 & 347, Ward No. 12 B, Gandhidham, District Kutch, Gujarat – 370201.
Taluka: - Bhachau District: - Kutch State: - Gujarat
Sl. Area to be acquired
Name of the Village Khasara No.
No. Hectare Are Sq.mtr.
1 2 3 4 5 6
1 Chhadavada 483 00 01 07
481 00 18 83
480 00 56 80
590 00 03 65
593 00 11 74
594 00 03 44
2 Shivlakha 1317 01 54 94
705/2 00 00 20
712 00 13 07
707/2 00 05 64
707/3 00 07 67
707/4 00 13 39
702/1 00 31 58
708 00 00 71
701 00 15 11
700 00 23 49
694/1 00 19 95
693 00 09 45
694/2 00 01 85
689/2 00 00 20
691 00 10 51
692/2 00 22 53
597 00 14 02
389/1 00 08 26
388 00 01 00
[F. No. R-11017/5/2022-OR- 1/E-44402]