Publication of notification in the Extra Ordinary Gazette of India under Section 3(1) of the PMP Act 1962 relating to land schedule in respect of Krishnapatnam Hyderabad Petroleum Petroleum Product Pipeline Project to be laid by Bharat Petroleum Corporation Limited (BPCL) for acquisition of ROU in the State of Andhra Pradesh Mandal Chimakurthi, Distt Prakasam
## Report on Land Acquisition for Krishnapatnam-Hyderabad Pipeline Project
**1. Executive Summary:**
This report analyzes a notification from the Ministry of Petroleum and Natural Gas regarding the acquisition of the right of user in land for the transportation of petroleum and petroleum products via a pipeline originating from Krishnapatnam, Andhra Pradesh (A.P), to Madharam near Hyderabad, Andhra Pradesh. The Bharat Petroleum Corporation Limited (BPCL) is responsible for laying the pipeline. The notification declares the government's intention to acquire the right of user for land specified in the schedule and provides a process for landowners to object to the acquisition.
**2. Introduction:**
This report aims to provide affected industry stakeholders with an informative overview of a government notification concerning the acquisition of land usage rights for the Krishnapatnam-Hyderabad pipeline project. The analysis is based solely on the provided text of the notification.
**3. Policy Overview:**
* **Core Objective(s):** The core objective is to facilitate the transportation of petroleum and petroleum products by acquiring the right of user in land for pipeline construction, specifically for the Krishnapatnam-Hyderabad pipeline project.
**4. Background and Rationale:**
* **New Policy:** This is a new policy initiative related to the acquisition of land user rights for the specified pipeline project. The underlying problem addressed is the need for secure land access to construct and operate the pipeline, vital for the transportation of petroleum products. The policy ensures a legal framework for acquiring the necessary rights while providing a mechanism for addressing landowner concerns.
**5. Key Provisions / Changes:**
* **New Policy:** The notification outlines the following key provisions:
* **Declaration of Intent:** The Central Government declares its intention to acquire the right of user in the land described in the attached schedule for the purpose of laying the pipeline.
* **Project Execution:** Bharat Petroleum Corporation Limited (BPCL) is designated as the entity responsible for laying the pipeline.
* **Objection Mechanism:** Individuals interested in the land have 21 days from the date the notification is made available to the public to object to the acquisition in writing.
* **Competent Authority:** The Special Deputy Collector on Deputation from the State of Andhra Pradesh, for Krishnapatnam Hyderabad Pipeline project., Bharat Petroleum Corporation Limited, D.No.35369370510, Housing Board Colony, MIG123, Ongole District, Andhra Pradesh State., is identified as the Competent Authority to receive objections.
* **Land Schedule:** A detailed schedule listing the specific land parcels (by district, revenue division, village, survey number, and area) affected by the acquisition is provided.
**6. Target Audience and Stakeholders:**
The primary target audience and stakeholders are:
* **Landowners:** Individuals or entities owning land within the Prakasam District in Andhra Pradesh, as detailed in the provided schedule.
* **Bharat Petroleum Corporation Limited (BPCL):** The company responsible for laying the pipeline.
* **Central Government of Petroleum Products:** The entity deeming the project necessary.
* **State Government of Andhra Pradesh:** Specifically, the Special Deputy Collector’s office.
**7. Implementation Aspects (Inferred):**
* **Responsible agency/bodies mentioned:**
* Ministry of Petroleum and Natural Gas (issuing the notification).
* Bharat Petroleum Corporation Limited (BPCL) (responsible for pipeline construction).
* Special Deputy Collector (Competent Authority for receiving objections).
* **Any timelines or procedures specified in the text:**
* Landowners have 21 days to submit objections from the date the notification is made publicly available.
**8. Expected Outcomes / Impact of Changes:**
* **New Policy:** The expected outcomes include:
* Secure land access for BPCL to construct the Krishnapatnam-Hyderabad pipeline.
* Enhanced transportation infrastructure for petroleum and petroleum products.
* Potential economic benefits associated with improved supply chain efficiency.
* Resolution of landowner concerns through the objection process.
**9. Conclusion:**
The notification represents a crucial step in facilitating the construction of the Krishnapatnam-Hyderabad pipeline. It outlines the government's intention to acquire land usage rights, identifies key stakeholders, and provides a framework for addressing landowner concerns. This project should lead to improved infrastructure for petroleum product transportation, with associated economic benefits. Landowners should carefully review the notification and, if necessary, submit objections within the specified timeframe to the Competent Authority.
Key Entities Referenced
New Delhi: Place of publication of the gazette notification
Krishnapatnam: Origin point of the Petroleum Products Pipeline in Andhra Pradesh
Madharam: Destination point of the Petroleum Products Pipeline, located near Hyderabad, Andhra Pradesh
Hyderabad: City near the destination point of the pipeline project, in Andhra Pradesh
Andhra Pradesh: State in India where the pipeline is being laid
Bharat Petroleum Corporation Limited: Company laying the petroleum pipeline
Petroleum and Minerals Pipelines Acquisition of Right of User in Land Act, 1962: Act under which the central government is acquiring the right of user
Prakasam: District in Andhra Pradesh where part of the land acquisition is taking place
Ongole: Revenue Division in Prakasam district, Andhra Pradesh
Chimakurthi: Village in Andhra Pradesh
Chandrapadu: Village in Andhra Pradesh
Rangasayipuram: Village in Andhra Pradesh
ILapavu luru: Village in Andhra Pradesh
Ministry of Petroleum and Natural Gas: The ministry issuing the notification