Date: 2022-04-13Category: Extra OrdinaryState: Union GovernmentCountry: India
Publication of Notification in the Extra Ordinary Gazette of India under the Petroleum and Minerals Pipelines (ARUL) Act, 1962 for Jagdishpur Haldia and Bokaro Dhamra Gas Pipeline (JHBDPL) and Spur Pipeline of GAIL (India) Limited.
## Report on Notification Regarding Right of User Acquisition for Jagdishpur-Haldia-Bokaro-Dhamra Pipeline Spur Pipeline Project
**1. Executive Summary:**
This report analyzes a notification issued by the Ministry of Petroleum and Natural Gas, Government of India, regarding the acquisition of Right of User (RoU) in land for the Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) Spur Pipeline project. The notification declares the government's decision to acquire RoU for laying the pipeline in a specified area in Odisha and directs that this right shall vest in GAIL India Limited, free from all encumbrances. This report outlines the policy's objectives, key provisions, affected stakeholders, and expected outcomes, based solely on the provided notification text.
**2. Introduction:**
This report aims to provide an informative overview of a notification (S.O. 1814(E)) issued by the Ministry of Petroleum and Natural Gas concerning the acquisition of Right of User (RoU) for a section of the Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) Spur Pipeline project in Odisha. This analysis is based solely on the content of the provided policy text.
**3. Policy Overview:**
* The policy, as evidenced by the provided notification, concerns the acquisition of RoU for laying a natural gas pipeline.
* **Core Objective(s):** To acquire the Right of User in land for laying a pipeline for the transportation of natural gas, specifically for the Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) Spur Pipeline project.
**4. Background and Rationale:**
* This is likely a *new* application of policy and not an amendment.
* The policy addresses the need to secure land rights for infrastructure development, specifically for the JHBDPL Spur Pipeline project. The rationale, inferred from the text, is to ensure the smooth transportation of natural gas through the region, likely to support industrial and economic development. Without securing RoU, the pipeline project could face delays and legal challenges.
**5. Key Provisions / Changes:**
* **Acquisition of Right of User (RoU):** The notification declares the acquisition of RoU in the land specified in the schedule for laying the pipeline.
* **Vesting of RoU:** The RoU is vested in GAIL India Limited, not the Government of India, from the date of publication of the notification. This vesting is "free from all encumbrances," meaning GAIL receives the right without any pre-existing claims or liabilities attached to the land related to the RoU.
* **Specific Location:** The schedule specifies the area to be acquired, which includes:
* State: Odisha
* District: Kendrapara
* Tehsil: Kendrapara
* Village: Baro
* Survey No.: 3995
* Area: 00 Hectares 00 Are 81 Sq. Mtr.
**6. Target Audience and Stakeholders:**
The stakeholders directly affected by this notification include:
* **GAIL India Limited:** As the entity in which the RoU is vested, GAIL is responsible for the pipeline construction and operation.
* **Landowners in the specified area (Baro Village, Kendrapara, Odisha):** The landowners are directly affected as their land is subject to the RoU acquisition.
* **Residents of Baro Village, Kendrapara, Odisha:** These residents are impacted by the JHBDPL and the changes this pipeline makes to their environment, landscape and the location of their residences.
* **Ministry of Petroleum and Natural Gas:** The ministry is responsible for overseeing the RoU acquisition process.
* **Competent Authority:** Refers to an authority appointed by the government to perform functions under the Act.
**7. Implementation Aspects (Inferred):**
* **Responsible Agency/Bodies:** The Ministry of Petroleum and Natural Gas is responsible for issuing the notification. GAIL India Limited is responsible for laying the pipeline. A "Competent Authority" submitted a report to the Government of India, indicating a role in assessing the land requirement.
* **Timelines/Procedures:** The notification takes effect from the date of its publication. The text references the Petroleum and Minerals Pipeline (Acquisition of Right of User in Land) Act, 1962, implying that the acquisition process follows the procedures outlined in that Act.
**8. Expected Outcomes / Impact of Changes:**
The intended outcomes of this notification include:
* **Facilitating Pipeline Construction:** Securing RoU in the specified land will enable GAIL to proceed with the laying of the JHBDPL Spur Pipeline.
* **Timely Project Completion:** The vesting of RoU in GAIL, free from encumbrances, should expedite the project's completion.
* **Increased Natural Gas Transportation Capacity:** The JHBDPL Spur Pipeline will likely contribute to an increase in the transportation capacity of natural gas in the region.
* **Economic Development:** Access to natural gas can support industrial and economic development in the region.
**9. Conclusion:**
The notification analyzed in this report signifies the government's commitment to facilitating infrastructure development for the transportation of natural gas. By acquiring RoU for the JHBDPL Spur Pipeline project and vesting it in GAIL India Limited, the government aims to ensure the timely completion of this critical infrastructure project, which is expected to enhance the region's energy infrastructure and support economic growth. The key stakeholders are GAIL, who take on the responsibility of completing the project and the residents of Baro Village, Kendrapara, Odisha, who will be directly affected.
Key Entities Referenced
Ministry of Petroleum and Natural Gas: A ministry of the Government of India responsible for the exploration, production, refining, distribution, marketing, import, and export of petroleum, natural gas, and petrochemicals.
Petroleum and Minerals Pipeline Acquisition of Right of Users in Land Act, 1962: An act of the Government of India providing the legal framework for acquiring the right of user in land for laying pipelines for petroleum and minerals.
GAIL India Limited: A Government of India owned natural gas processing and distribution company headquartered in New Delhi, India.
Odisha: A state in eastern India.
Jagdishpur-Haldia-Bokaro-Dhamra Pipeline: A natural gas pipeline project.
JHBDPL Spur Pipeline: A spur pipeline connected to the Jagdishpur-Haldia-Bokaro-Dhamra Pipeline.
Paradeep Spur Pipeline: A section of the Jagdishpur-Haldia-Bokaro-Dhamra pipeline project.
Kendrapara: A district in Odisha, India.
Kendrapara: A tehsil in Kendrapara district of Odisha, India.
Baro: A village in Kendrapara tehsil of Kendrapara district, Odisha, India.
New Delhi: The capital of India.
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
सी.जी.-डी.एल.-अ.-16042022-235164
xxxGIDHxxx
CG-DL-E-16042022-235164
xxxGIDExxx
असाधारण
EXTRAORDINARY
भाग II—खण् ड 3—उप-खण्ड (ii)
PART II—Section 3—Sub-section (ii)
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 1727] नई दिल्ली, बुधिार, अप्रलै 13, 2022/चत्रै 23, 1944
No. 1727] NEW DELHI, WEDNESDAY, APRIL 13, 2022/CHAITRA 23, 1944
परै ोजलयम और प्राकृजतक गसै मत्रं ालय
अजधसचू ना
नई दिल्ली, 12 अप्रैल, 2022
का.आ. 1814(अ).—भारत सरकार ने पेरोजलयम और खजनि पाइपलाइन (भूजम में उपयोग के अजधकार का अिजन)
अजधजनयम, 1962 (1962 का 50) (जिसे इसमें इसके पश्चात उक्त अजधजनयम कहा गया ह)ै की धारा 3 की उपधारा (1) के अधीन
िारी भारत सरकार के पेरोजलयम और प्राकृजतक गैस मंत्रालय की अजधसूचना संख्या का.आ. 121(अ) तारीख 03.01.2022 द्वारा उस
अजधसूचना से संलग्न अनुसूची में जिजनर्िष्टज भूजम में गेल (इजण्डया) जलजमटेड द्वारा ओजडसा राज्य में िगिीिपुर-हजल्िया – बोकारो-
धामरा पाइप लाइन (िे एच बी िी पी एल) & स्ट्पर पाइप लाइन के माध्यम से प्राकृजतक गैस के पररिहन के जलए पाइपलाइन जबछाने
के प्रयोिन के जलए उपयोग के अजधकार का अिजन करने के अपने आिय की घोषणा की थी;
और उक्त रािपजत्रत अजधसूचना की प्रजतयां िनता को उपलब्ध करा िी गई थी;
और, सक्षम प्राजधकारी न,े उक्त अजधजनयम की धारा 6 की उप-धारा (1) के अधीन भारत सरकार को अपनी ररपोटज ि ेिी है;
और भारत सरकार ने, उक्त ररपोटज पर जिचार करने के पश्चात और यह संतुष्ट हो िाने पर दक उक्त भूजम पाइपलाइनें जबछाने
के जलए अपेजक्षत है, उस में उपयोग के अजधकार का अिजन करने का जिजनश्चय दकया ह;ै
2676 GI/2022 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
अतः अब, भारत सरकार, उक्त अजधजनयम की धारा 6 की उप-धारा (1) द्वारा प्रित्त्त िजक्तयों का प्रयोग करते हुये, यह
घोषणा करती ह ैदक इस अजधसूचना से संलग्न अनुसूची में जिजनर्िष्टज भूजम में पाइपलाइनें जबछाने के जलए उपयोग के अजधकार का अिजन
दकया िाता ह;ै
और भारत सरकार, उक्त अजधजनयम दक धारा 6 दक उप-धारा (4) द्वारा प्रित िजक्तयों का प्रयोग करते हुये, जनििे िते ी ह ैदक
पाइपलाइनें जबछाने के जलए भूजम में उपयोग का अजधकार, इस घोषणा के प्रकािन की तारीख को, भारत सरकार में जनजहत होने के
बिाए, पाइपलाइनें जबछाने का प्रस्ट्ताि करने िाली गेल (इजण्डया) जलजमटेड में जनजहत होगा और तिपु रर, भूजम में ऐसे उपयोग का
अजधकार, इस प्रकार अजधरोजपत जनबंधनों और ितों के अधीन रहते हुये, सभी जिल्लंगमों से मुक्त, गेल (इजण्डया) जलजमटेड में जनजहत
होगा।
िगिीिपरु -हजल्िया-बोकारो-धामरा गसै पाइपलाइन और स्ट्पर पाइपलाइन प्रोिक्े ट
पारादिप स्ट्पर पाइपलाइन (सक्े सन - 2A)
अनसु चू ी
राज़्य - ओजििा
क्षत्रे फल
जिला तहसील ग्राम सि ेनबं र.
हक्े टर आर िगजज मटर
केन्द्रापडा केन्द्रापडा बारो 3995 00 00 81
[फा. स.ं एल-14014/70/2022-िीपी-II) (ई- 42196)]
राकेि जमश्रा, अिर सजचि
MINISTRY OF PETROLEUM AND NATURAL GAS
NOTIFICATION
New Delhi, the 12th April, 2022
S.O. 1814(E).—Whereas by the notification of Government of India in Ministry of Petroleum and Natural
Gas vide S. O. No. 121(E) dated 03.01.2022 issued under sub- section (1) of section 3 of the Petroleum and Minerals
Pipeline ( Acquisition of Right of Users in Land ) Act, 1962 (50 of 1962) (hereinafter referred to as the said Act),
Government of India declared its intention to acquire the Right of User in the land specified in the Schedule appended
to that notification for the purpose of laying pipeline for transportation of natural gas through Jagdishpur-Haldia-
Bokaro-Dhamra Pipeline (JHBDPL) & Spur Pipeline in the State of Odisha by GAIL (India) Limited;
And whereas copies of the said Gazette notification were made available to the public;
And, whereas the Competent Authority has, under sub-section (1) of Section 6 of the said Act,
submitted his report to Government of India;
And whereas Government of India after considering the said report and on being satisfied that the
said land is required for laying the pipelines, has decided to acquire the Right of User therein;
Now, therefore, in exercise of the powers conferred by sub-section (1) of section 6 of the said Act,
Government of India hereby declares that the Right of User in the land specified in the Schedule appended to this
notification is hereby acquired for laying the pipeline;[भाग II—खण् ड 3(ii)] भारत का रािपत्र : असाधारण 3
And, further, in exercise of the powers conferred by sub-section (4) of Section 6 of the said Act,
Government of India hereby directs that the Right of User in the land for laying the pipeline shall, instead of vesting in
Government of India, vest, on this date of the publication of the declaration, in the GAIL (India) Limited, free from all
encumbrances.
JAGDISHPUR - HALADIA- BOKARO - DHAMRA PIPELINE & SPUR PIPELINE PROJECT
PARADEEP SPUR PIPELINE (SECTION-2A)
SCHEDULE
STATE : ODISHA
AREA
SURVEY
DISTRICT TEHSIL VILLAGE
NO. HECT. ARE SQ.
MTR.
1 2 3 4 5
KENDRAPARA KENDRAPARA BARO 3995 00 00 81
[F. No. L-14014/70/2022-GP-II (E-42196)]
RAKESH MISHRA, Under Secy.