Date: 2022-12-08Category: Extra OrdinaryState: Union GovernmentCountry: India
Publication of Notification in the Extra Ordinary Gazette of India under the Petroleum and Minerals Pipelines (ARUL) Act, 1962 for Jagdishpur Haldia and Bokaro Dhamra Gas Pipeline (JHBDPL) and Spur Pipeline of GAIL (India) Limited.
## Policy Analysis Report: Acquisition of Right of User for Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) Spur Pipeline Project
**1. Executive Summary:**
This report analyzes a notification from the Ministry of Petroleum and Natural Gas, Government of India, dated December 5, 2022. The notification declares the government's intention to acquire the Right of User (RoU) in land for the purpose of laying a natural gas pipeline by GAIL India Limited, specifically the Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) spur pipeline project in West Bengal. The key finding is that landowners have 21 days from the date the notification is made public to object to the acquisition of RoU. This action is taken under the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962.
**2. Introduction:**
This report aims to provide an informative overview of the policy notification issued by the Ministry of Petroleum and Natural Gas regarding the acquisition of the Right of User (RoU) for land required for the Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) spur pipeline project in West Bengal. This analysis is based solely on the provided text.
**3. Policy Overview:**
This appears to be a *new policy action* specifically targeting the acquisition of land rights for the JHBDPL spur pipeline project, and is not an amendment. The core objective, as inferred from the text, is to facilitate the transportation of natural gas through the JHBDPL spur pipeline project by acquiring the necessary RoU in land.
**4. Background and Rationale:**
As this is a new policy action for the JHBDPL spur pipeline project in West Bengal, the text suggests that the government has determined that establishing this pipeline is in the public interest. The underlying problem this policy addresses is likely the need to secure access to land for laying the pipeline, a prerequisite for developing the natural gas infrastructure.
**5. Key Provisions / Changes:**
This is a new policy action, so we'll detail the main components, rules, and actions mandated by the provided text. The policy establishes the following:
* **Declaration of Intent:** The Government of India declares its intention to acquire the Right of User (RoU) in land for laying the JHBDPL spur pipeline by GAIL India Limited.
* **Legal Basis:** The action is based on the powers conferred by subsection 1 of Section 3 of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962.
* **Objection Period:** Persons interested in the land described in the schedule have 21 days from the date of public notification to object to the acquisition in writing.
* **Competent Authority:** Objections must be submitted to the Competent Authority, GAIL India Limited.
* **Project Scope:** The specific project this notification pertains to is the JAGDISHPURHALDIA BOKARODHAMRA PIPELINE JHBDPL AND SPUR PIPELINE PROJECT DURGAPURHALDIA,SECTION3B LAND SCHEDULE
* **Location:** The affected land is located in the State of West Bengal, specifically in PURBA BARDHAMAN, BURDWANI, BAGHAR, Map LR 1517.
**6. Target Audience and Stakeholders:**
Based on the text, the primary target audience and stakeholders directly affected by this policy action are:
* Landowners in the specified areas of West Bengal (PURBA BARDHAMAN) where the JHBDPL spur pipeline is proposed to be laid.
* GAIL India Limited, as the entity responsible for laying the pipeline.
* Residents of the state of West Bengal who would benefit from the transport of natural gas
* The Competent Authority at GAIL India Limited, who are responsible for handling objections.
**7. Implementation Aspects (Inferred):**
The text provides limited information on implementation but allows for the following inferences:
* **Responsible Agency:** GAIL India Limited is responsible for laying the pipeline.
* **Timeline:** Landowners have 21 days to object from the date the notification is made public.
* **Procedure:** Objections must be submitted in writing to the Competent Authority at GAIL India Limited.
**8. Expected Outcomes / Impact of Changes:**
The likely intended outcomes of this policy action are:
* Facilitation of the construction of the JHBDPL spur pipeline.
* Securement of Right of User in land for the pipeline project.
* Enhanced transportation of natural gas in the region.
* Economic and industrial development in the region due to improved energy infrastructure.
**9. Conclusion:**
The notification from the Ministry of Petroleum and Natural Gas signals a crucial step in the development of natural gas infrastructure in West Bengal. By declaring the intent to acquire the Right of User in land for the JHBDPL spur pipeline project, the government aims to facilitate the transportation of natural gas and stimulate economic growth in the region. Landowners and GAIL India Limited are the primary stakeholders affected by this policy action. The 21-day objection period provides an opportunity for affected parties to voice their concerns.
Key Entities Referenced
Petroleum and Minerals Pipelines Acquisition of Right of User in Land Act, 1962: A law enacted in 1962 that provides the Government of India with the authority to acquire the right of user in land for the purpose of laying petroleum and mineral pipelines.
Government of India: The governing authority of India, which is exercising its powers under the Petroleum and Minerals Pipelines Acquisition of Right of User in Land Act, 1962 to acquire land for the Jagdishpur-Haldia-Bokaro-Dhamra pipeline.
Jagdishpur-Haldia-Bokaro-Dhamra pipeline: A natural gas pipeline project (JHBDPL) for the transportation of natural gas.
West Bengal: An eastern state in India where the pipeline is proposed to be laid.
GAIL India Limited: The company responsible for laying the Jagdishpur-Haldia-Bokaro-Dhamra pipeline.
New Delhi: Location of Ministry of Petroleum and Natural Gas
PURBA BARDHAMAN: District in West Bengal
RAKESH MISHRA: Under Secretary
रजजस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
xxxGIDHxxx
सी.जी.-डी.एलxx.-xअGI.D-E0x8x1x2 2022-240887
CG-DL-E-08122022-240887
असाधारण
EXTRAORDINARY
भाग II—खण् ड 3—उप-खण्ड (ii)
PART II—Section 3—Sub-section (ii)
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 5483] नई ददल्ली, बहृ स्ट्प जतवार, ददसम्ब र 8, 2022/अग्रहायण 17, 1944
No. 5483] NEW DELHI, THURSDAY, DECEMBER 8, 2022/AGRAHAYANA 17, 1944
परे ोजलयम और प्राकृजतक गसै मत्रं ालय
अजधसचू ना
नई ददल्ली, 5 ददसम् बर, 2022
का.आ. 5719(अ).—भारत सरकार को लो कजहत में यह आवश् यक प्रतीत होता ह ै दक राज्य में
जगदीिपुर-हजल्दया & बोकारो-धामरा पाइपलाइन (ज े एच बी डी पी एल) और स्ट्पर पाईपलाईन के माध्यम स े प्राकृजतक
, ;
गैस के पररवहन के जलए गले (इजण्डया) जलजमटेड द्वारा एक पाइपलाईन जबछाई जानी चाजहए
और भारत सरकार को उक्त पाइपलाईन जबछान े के प्रयोजन के जलए यह आवश् यक प्रतीत होता ह ै दक उस भूजम
, ,
में जजसमें उक्त पाइपलाईन जबछाए जाने का प्रस्ट् ताव ह ै और जो इस अजधसूचना म े संलग्न अनुसूची में व्णत है उपयोग के
;
अजधकार का अजजन दकया जाए
, ,
अत: अब भारत सरकार पेरोजलयम और खजनज पाइपलाईन(भूजम में उपयोग के अजधकर का अजनज )
, ,
अजधजनयम 1962 (1962 का 50) की धारा 3 की उपधारा (1) द्वारा प्रद त िजतियय का प्रयोग करत े हुए उस भूजम में उपयोग
;
के अजधकार का अजजन करने के अपन ेआिय की घोषणा करती है
, ,
कोई व् यजतिय जो उक्त अनुसूची में व्णत भूजम म ें जहतब्ध है उस तारीख से जजसको उक्त अजधजनयम की धारा 3 की
उपधारा (1) के अधीन भारत के राजपत्र म ें यथा प्रकाजित इस अजधसूचना की प्रजतयॉं साधारण जनता को उपलब् ध कर दी
, , , ,
जाती है 21 ददन के भी तर भूजम के नीचे पाइपलाईन जबछाए जाने के संबंध में सक्षम प्राजधकारी गेल (इजण्डया) जलजमटेड को
जलजखत रूप म ें आक्षपे भेज सकेगा।
8149 GI/2022 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
अनुसूची
जगदीिपरु - हजल्दया- बोकारो- धामरा पाइपलाइन (ज०े एच०बी०डी०पी०एल०) एवम स्ट्पर पाइपलाइन
दगु ापज रु - हजल्दया, सक्े सन-3 बी
अनसु चू ी
राज्य - पजिम बगं ाल
1 2 3 4 5 6 7
1517 0 04 25
[फा. सं. एल-14014/225/2022-जी-पी-II(ई-45066)]
राकेि जमश्रा, अवर सजचव
MINISTRY OF PETROLEUM AND NATURAL GAS
NOTIFICATION
New Delhi, the 5th December, 2022
S.O. 5719(E).—Whereas it appears to Government of India that it is necessary in public interest that for
transportation of natural gas through Jagdishpur-Haldia & Bokaro-Dhamra pipeline (JHBDPL) & spur pipeline, in the
State of West Bengal, a pipeline should be laid by GAIL (India) Limited;
And, whereas it appears to Government of India that for the purpose of laying the said pipeline, it is necessary
to acquire the Right of User in the land under which the said pipeline is proposed to be laid and which is described in
the Schedule annexed to this notification;
Now, therefore, in exercise of powers conferred by sub-section (1) of Section 3 of the Petroleum and Minerals
Pipelines (Acquisition of Right of User in Land) Act, 1962, (50 of 1962) Government of India hereby declares its
intention to acquire the Right of User therein;
Any person interested in the land described in the said Schedule may, within twenty one days from the date of
which the copies of the notification issued under sub-section (1) of Section 3 of the said Act, as published in the
Gazette of India are made available to the general public, object in writing to the acquisition of the right of User therein
for laying of the pipeline under the land to Competent Authority, GAIL (India) Limited.
SCHEDULE
JAGDISHPUR-HALDIA -BOKARO-DHAMRA PIPELINE (JHBDPL) AND SPUR PIPELINE PROJECT
DURGAPUR-HALDIA,SECTION-3B
LAND SCHEDULE
State : West Bengal
Area
J.L. Survey
District Block Mauza Map Sq.
No. No. Hect. Are
mtr.
1 2 3 4 5 6 7
PURBA BARDHAMAN BURDWAN-I BAGHAR 11 LR 1517 0 04 25
[F. No. L-14014/225/2022-GP-II(E- 45066)]
RAKESH MISHRA , Under Secy.
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.