Date: 2021-12-17Category: Extra OrdinaryState: Union GovernmentCountry: India
Publication of Notification in the Extra Ordinary Gazette of India under the Petroleum and Minerals Pipelines (ARUL) Act, 1962 for Jagdishpur Haldia and Bokaro Dhamra Gas Pipeline (JHBDPL) and Spur Pipeline of GAIL (India) Limited.
## Report on Notification Regarding Right of User for Jagdishpur-Haldia-Bokaro-Dhamra Pipeline Spur Pipeline Project
**1. Executive Summary:**
This report analyzes a notification from the Ministry of Petroleum and Natural Gas, Government of India, concerning the acquisition of Right of User (RoU) in land for the Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) Spur Pipeline project in Odisha. The notification declares the government's intention to acquire RoU for the pipeline's construction, inviting objections from interested parties. The core purpose is to facilitate the transportation of natural gas via the pipeline, deemed necessary in the public interest. A key finding is the detailed schedule outlining specific land parcels within Jajpur district subject to RoU acquisition.
**2. Introduction:**
This report provides an overview and analysis of a notification published by the Government of India, Ministry of Petroleum and Natural Gas, regarding the acquisition of Right of User (RoU) in land for the JHBDPL Spur Pipeline project in the state of Odisha. This analysis is based solely on the information contained within the provided notification text.
**3. Policy Overview:**
* **Core Objective(s):** The core objective, as stated in the notification, is to facilitate the *transportation of natural gas* through the Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) Spur Pipeline. This transportation is explicitly stated as being "necessary in public interest."
**4. Background and Rationale:**
* **New Policy:** This appears to be a *new policy action* to enable the laying of the pipeline. The policy likely addresses the need for efficient and reliable transportation of natural gas to the region, addressing potential energy demands or infrastructure gaps. The public interest rationale suggests a wider benefit to the community, potentially including economic development or improved access to energy resources.
**5. Key Provisions / Changes:**
* **New Policy:** This notification initiates the process of acquiring Right of User (RoU) in specified lands for laying the pipeline.
* The policy establishes the intention of the Government of India to acquire RoU under the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962.
* It provides a detailed "SCHEDULE" listing specific areas, survey numbers, districts, tahsils, and villages in Odisha (specifically Jajpur district) where land is targeted for RoU acquisition. The schedule includes "Notified Area" and "Revised Area" details in hectares, ares, and square meters.
* It allows individuals with an interest in the listed lands a period of twenty-one days to submit written objections to the acquisition to the Competent Authority, Odisha, GAIL India Limited, at the provided address.
**6. Target Audience and Stakeholders:**
The primary target audience and stakeholders are:
* Landowners and individuals with vested interests in the land parcels listed in the Schedule, particularly those within the Jajpur district of Odisha.
* GAIL India Limited, identified as the entity responsible for laying the pipeline.
* The general public in the region, who are expected to benefit from the pipeline's operation through increased natural gas availability.
**7. Implementation Aspects (Inferred):**
* **Responsible Agency/Bodies:**
* Ministry of Petroleum and Natural Gas (issuing the notification).
* GAIL India Limited (responsible for pipeline construction).
* Competent Authority, Odisha, GAIL India Limited (receives objections).
* **Timelines/Procedures:**
* A 21-day period is provided for interested parties to submit written objections from the date the notification is made available to the general public.
* The process follows the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962.
**8. Expected Outcomes / Impact of Changes:**
* **New Policy:** The intended outcomes of this policy are:
* Facilitation of the construction of the JHBDPL Spur Pipeline.
* Enhanced transportation of natural gas to the region.
* Potential economic and developmental benefits for the public due to improved energy infrastructure.
* Legal acquisition of land rights necessary for the project, potentially leading to disputes or compensation claims if not handled appropriately.
**9. Conclusion:**
The notification signifies a crucial step towards the development of the JHBDPL Spur Pipeline project in Odisha. It initiates the legal process for acquiring RoU, outlining the affected land parcels and providing a mechanism for addressing objections. The successful implementation of this policy is vital for enhancing the region's natural gas infrastructure and achieving broader public interest objectives related to energy security and economic development. Industry participants should pay close attention to the timelines and procedures outlined in the notification, especially regarding the submission of objections.
Key Entities Referenced
Ministry of Petroleum and Natural Gas: A ministry of the Government of India responsible for petroleum and natural gas.
New Delhi: The capital city of India, where the notification was issued.
Government of India: The governing body of India.
Jagdishpur-Haldia-Bokaro-Dhamra Pipeline: A natural gas pipeline project.
JHBDPL Spur Pipeline: A spur pipeline related to the Jagdishpur-Haldia-Bokaro-Dhamra Pipeline project.
State of Odisha: A state in India where the pipeline is to be laid.
GAIL India Limited: The company responsible for laying the pipeline.
Petroleum and Minerals Pipelines Acquisition of Right of User in Land Act, 1962: The act under which the right of user in the land is being acquired.
Competent Authority, Odisha: The authority in Odisha to whom objections regarding the land acquisition can be submitted.
Utkal Signature, Pahala, NH 16, Bhubaneswar: Address of GAIL India Limited office in Odisha.
Jajpur: A district in Odisha.
Bari: A Tahasil in Jajpur district, Odisha.
Baring: A village in Bari Tahasil, Jajpur district, Odisha
RAKESH MISHRA: Under Secretary.