Date: 2022-09-23Category: Extra OrdinaryState: Union GovernmentCountry: India
Publication of Notification in the Extra Ordinary Gazette of India under the Petroleum and Minerals Pipelines (ARUL) Act, 1962 for North East Natural Gas Pipeline Grid Project of M/s. Indradhanush Gas Grid Limited (IGGL).
**Policy Analysis Report: Acquisition of Right of User for Natural Gas Pipeline**
**1. Executive Summary:**
This report analyzes a government notification regarding the acquisition of the Right of User (RoU) in land for the laying of a natural gas pipeline. Based on the provided text, this is a declaration under *The Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962*, specifically concerning the Guwahati-Shillong-Silchar-Panisagar Section of the North East Natural Gas Pipeline project by Indradhanush Gas Grid Limited (IGGL) in Assam. The core purpose is to legally secure the land rights necessary for the pipeline construction. This notification declares the acquisition of RoU and directs that the right of user vests in IGGL.
**2. Introduction:**
This report provides an informative overview of a government notification concerning the acquisition of Right of User (RoU) for a natural gas pipeline, based on the details contained within the provided policy text. The report aims to outline the policy’s objectives, background, key provisions, stakeholders, inferred implementation aspects, and expected outcomes.
**3. Policy Overview:**
* This notification is issued under *The Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962*.
* **Core Objective:** The core objective, as inferred from the text, is to legally acquire the Right of User (RoU) in specific land parcels to facilitate the laying of a natural gas pipeline. This ensures the project can proceed legally.
**4. Background and Rationale:**
The policy addresses the need for secure land access for the construction and operation of the Guwahati-Shillong-Silchar-Panisagar Section of the North East Natural Gas Pipeline. The policy suggests that without legally acquiring the RoU, the pipeline project would face legal challenges and potential delays. The notification explicitly mentions that public objections were received, considered, and disposed of, indicating a process of addressing land-related concerns before formal acquisition.
**5. Key Provisions / Changes:**
This policy establishes the following:
* Declaration of Right of User Acquisition: The Government of India formally declares that the Right of User in the lands specified in the attached schedule is acquired.
* Vesting of Rights: The Right of User in the specified land is vested in Indradhanush Gas Grid Limited (IGGL), free from all encumbrances. This means IGGL has the right to use the land for the pipeline, and that any previous claims or liens on the land are superseded.
* Land Details: A detailed schedule lists the specific land parcels where the RoU is acquired. This includes the district, sub-division, state, village, mouza, survey number, and the area in hectare/are/sq.mtr. for each parcel.
**6. Target Audience and Stakeholders:**
The target audience and stakeholders directly affected by this notification are:
* Indradhanush Gas Grid Limited (IGGL): As the entity receiving the RoU, IGGL is the primary beneficiary, gaining the legal right to construct and operate the pipeline.
* Landowners: Landowners whose properties are listed in the schedule are directly affected, as the government has acquired the right to use their land for the pipeline.
* Residents in Affected Areas: Communities residing near the pipeline route are stakeholders due to potential environmental and social impacts during and after construction.
**7. Implementation Aspects (Inferred):**
* **Responsible Agency/Bodies:**
* Ministry of Petroleum and Natural Gas: Responsible for issuing the notification and overseeing the RoU acquisition process.
* Competent Authority: Responsible for considering and disposing of public objections and submitting a report to the Government of India.
* Indradhanush Gas Grid Limited (IGGL): Responsible for executing the pipeline project, utilizing the acquired RoU.
* **Timelines/Procedures:**
* The notification follows a process involving declaration of intent, consideration of public objections, submission of a report by the Competent Authority, and a final declaration of RoU acquisition.
* The date of publication of the notification is the date on which the RoU vests in IGGL.
**8. Expected Outcomes / Impact of Changes:**
The likely intended outcomes of this notification are:
* Facilitation of Pipeline Construction: Securing the RoU enables IGGL to proceed with the construction of the Guwahati-Shillong-Silchar-Panisagar Section of the North East Natural Gas Pipeline without legal impediments.
* Infrastructure Development: Successful completion of the pipeline will contribute to the development of natural gas infrastructure in the region, potentially leading to economic growth and improved energy access.
* Reduced Legal Challenges: By addressing and resolving public objections prior to the acquisition, the notification aims to minimize potential legal challenges and delays.
**9. Conclusion:**
The notification regarding the acquisition of Right of User for the Guwahati-Shillong-Silchar-Panisagar Section of the North East Natural Gas Pipeline represents a crucial step in facilitating the development of natural gas infrastructure in Assam. By legally securing the necessary land rights and vesting them in IGGL, the notification is intended to pave the way for the timely and efficient completion of the pipeline project, contributing to regional economic growth and energy security.
Key Entities Referenced
Ministry of Petroleum and Natural Gas: The Indian government ministry responsible for petroleum and natural gas.
New Delhi: The location where the notification was issued.
19th September, 2022: Date of the notification.
Petroleum and Minerals Pipelines Acquisition of Right of User in Land Act, 1962: The law under which the notification is issued.
Extra Ordinary Gazette of India: The official gazette in which the notification was published.
Guwahati Shillong Silchar Panisagar Section of North East Natural Gas Pipeline: The specific pipeline project mentioned in the notification.
Assam: The state where the pipeline laying is occurring.
Indradhanush Gas Grid Limited IGGL: The company responsible for laying the pipeline.
Cachar: District in Assam where land acquisition is taking place.
Katigorah: Area/Circle/Tahsil in Cachar district, Assam.
Mohanpur: Village in Katigorah, Cachar District, Assam
Chandpur: Village in Katigorah, Cachar District, Assam
Udarbond: Area/Circle/Tahsil in Cachar district, Assam.
Arcuttepur Grant: Village in Udarbond, Cachar District, Assam
Lakhipur: Area/Circle/Tahsil in Cachar district, Assam.
Chandrapur: Village in Lakhipur, Cachar District, Assam
Sonai: Area/Circle/Tahsil in Cachar district, Assam.
Badripar: Village in Sonai, Cachar District, Assam
Bagpur: Village in Sonai, Cachar District, Assam
RAKESH MISHRA: Under Secretary.
Mayapuri, New Delhi: Location of the Government of India Press.
Delhi: Location of the Controller of Publications.