Date: 2022-03-23Category: Extra OrdinaryState: Union GovernmentCountry: India
Publication of Notification in the Extra Ordinary Gazette of India under the Petroleum and Minerals Pipelines (ARUL) Act, 1962 for Srikakulam Angul Natural Gas Pipeline (SAPL) of GAIL (India) Limited.
## Policy Analysis Report: Acquisition of Right of User for SRIKAKULAM ANGUL PIPELINE SAPL PROJECT
**1. Executive Summary:**
This report analyzes a government notification regarding the acquisition of the Right of User (RoU) in land for the SRIKAKULAM ANGUL PIPELINE (SAPL) PROJECT in Andhra Pradesh, specifically in the Srikakulam District. The notification declares the Central Government's intention to acquire RoU for laying a natural gas pipeline by GAIL India Ltd. The key finding is a detailed schedule of land parcels affected by this acquisition, specifying locations by village and survey number. This report aims to inform stakeholders about this acquisition process and their rights regarding objections.
**2. Introduction:**
The purpose of this report is to provide a comprehensive overview and analysis of a recent government notification concerning the acquisition of the Right of User (RoU) for land required for the SRIKAKULAM ANGUL PIPELINE (SAPL) PROJECT, based solely on the provided policy text. This report will outline the policy's objectives, affected areas, and potential implications for stakeholders.
**3. Policy Overview:**
* **Type:** New Policy (Declaration of Intent to Acquire Right of User)
* **Core Objective(s):** The core objective, as inferred from the text, is to facilitate the transportation of natural gas by acquiring the Right of User in land for the SRIKAKULAM ANGUL PIPELINE (SAPL) PROJECT.
**4. Background and Rationale:**
The policy addresses the need for a natural gas pipeline connecting Srikakulam and Angul. The notification states it is "necessary in the public interest" to transport natural gas via the SRIKAKULAM ANGUL PIPELINE (SAPL) PROJECT. This indicates that improved natural gas infrastructure is deemed beneficial for the public, likely for energy supply and industrial development in the region.
**5. Key Provisions / Changes:**
Since this is a new declaration of intent, the key provisions are the establishment of the acquisition process for the Right of User. This involves:
* **Declaration of Intent:** The Central Government declares its intention to acquire the Right of User in the land described in the schedule annexed to the notification.
* **Affected Lands:** The land schedule specifies the district (Srikakulam), state (Andhra Pradesh), mandals, villages, survey numbers, and area (in Hector Are. Sq.mtr.) of the land parcels where the RoU is to be acquired. Detailed area information is provided for multiple villages within Sompeta, Bushabadra, Siripuram, Hunnali, Budarasingi, Cheepi, Singupuram, Nuvagam, Tubburu, Mandavuru, Banjaruyuvarajapuram, Killoyi, Bogabanda and Konkadaputti Mandals.
* **Objection Mechanism:** Individuals interested in the listed land parcels are given the right to object in writing to the acquisition of the RoU or the laying of the pipeline within 21 days from the date the notification is made available to the general public. Objections must be submitted to the Competent Authority, GAIL India Ltd., at the specified address.
**6. Target Audience and Stakeholders:**
Based on the text, the primary target audience and stakeholders are:
* **Landowners/Individuals:** Those who own or have an interest in the land parcels specifically listed in the schedule within the Srikakulam District.
* **GAIL India Ltd.:** The company responsible for laying the pipeline and, as the "Competent Authority," for receiving and addressing objections.
* **Residents of Andhra Pradesh, specifically Srikakulam District** who may benefit from the completed project.
**7. Implementation Aspects (Inferred):**
* **Responsible agency/bodies:** Central Government (issuing the notification), GAIL India Ltd. (laying the pipeline and handling objections), Competent Authority (within GAIL India Ltd.).
* **Timelines:** A 21-day objection period is specified, starting from the date the notification is made available to the public.
* **Procedures:** Landowners can submit written objections to the Competent Authority within the given timeframe. The notification implies that GAIL India Ltd. will be responsible for reviewing and addressing these objections.
**8. Expected Outcomes / Impact of Changes:**
The likely intended outcomes of this policy, based on the text, are:
* **Secure Right of User:** Acquisition of the necessary RoU to facilitate the construction of the natural gas pipeline.
* **Pipeline Construction:** Enable the laying of the SRIKAKULAM ANGUL PIPELINE (SAPL) PROJECT for transporting natural gas.
* **Improved Energy Infrastructure:** Contribute to improved natural gas infrastructure and supply in the region, potentially supporting economic development and energy access.
* **Facilitate Public Benefit:** Public interest in the development of natural gas infrastructure
**9. Conclusion:**
The government notification signals the commencement of land acquisition for the SRIKAKULAM ANGUL PIPELINE (SAPL) PROJECT, a project deemed to be in the public interest. This report has identified the key provisions, affected stakeholders, and inferred implementation aspects based solely on the provided text. The notification gives landowners a window to object to the acquisition process. This is a key step towards potentially improving the natural gas infrastructure and supply within the Srikakulam District and potentially the Andhra Pradesh state.
Key Entities Referenced
NEW DELHI: Place of Publication
MARCH 23, 2022: Date of Publication
CHAITRA 2, 1944: Date of Publication as per the Saka calendar
Petroleum and Minerals Pipeline Acquisition of Right of User in the land Act, 1962: Law mentioned in the notification
SRIKAKULAM ANGUL PIPELINE SAPL PROJECT: Project Name
Srikakulam District: District where project is located.
Andhra Pradesh: State where project is located
GAIL India Ltd.: Organization responsible for laying the pipeline
Sompeta: Mandal in Srikakulam District, Andhra Pradesh
Bushabadra: Mandal in Srikakulam District, Andhra Pradesh
Mandasa: Mandal in Srikakulam District, Andhra Pradesh
Sunkidi: Village in Sompeta Mandal, Srikakulam District, Andhra Pradesh
Siripuram: Village in Mandasa Mandal, Srikakulam District, Andhra Pradesh
Hunnali: Village in Mandasa Mandal, Srikakulam District, Andhra Pradesh
Budarasingi: Village in Mandasa Mandal, Srikakulam District, Andhra Pradesh
Cheepi: Village in Mandasa Mandal, Srikakulam District, Andhra Pradesh
Singupuram: Village in Mandasa Mandal, Srikakulam District, Andhra Pradesh
Nuvagam: Village in Mandasa Mandal, Srikakulam District, Andhra Pradesh
Tubburu: Village in Mandasa Mandal, Srikakulam District, Andhra Pradesh
Mandavuru: Village in Mandasa Mandal, Srikakulam District, Andhra Pradesh
Banjaruyuvarajapuram: Village in Mandasa Mandal, Srikakulam District, Andhra Pradesh
Killoyi: Village in Mandasa Mandal, Srikakulam District, Andhra Pradesh
Bogabanda: Village in Mandasa Mandal, Srikakulam District, Andhra Pradesh
Konkadaputti: Village in Mandasa Mandal, Srikakulam District, Andhra Pradesh
Sandhigam: Village in Mandasa Mandal, Srikakulam District, Andhra Pradesh
RAKESH MISHRA: Under Secretary