Date: 2022-05-18Category: Extra OrdinaryState: Union GovernmentCountry: India
Publication of Notification in the Extra Ordinary Gazette of India under the Petroleum and Minerals Pipelines (ARUL) Act, 1962 for Srikakulam Angul Natural Gas Pipeline (SAPL) of GAIL (India) Limited.
## Policy Analysis Report: Acquisition of Right of User for Srikakulam Angul Pipeline SAPL Spur Pipeline in Odisha
**1. Executive Summary:**
This report analyzes a notification from the Ministry of Petroleum and Natural Gas, Government of India, regarding the acquisition of the Right of User (RoU) in land for the Srikakulam Angul Pipeline (SAPL) Spur pipeline project in the state of Odisha. The core purpose is to formally declare the acquisition of land rights for laying the pipeline and to vest those rights in GAIL (India) Limited. Key findings include the identification of specific land parcels across multiple villages in the Ganjam district affected by this acquisition, as well as the vesting of user rights with GAIL India Limited.
**2. Introduction:**
The purpose of this report is to provide an informative overview of the notification published by the Government of India, Ministry of Petroleum and Natural Gas, concerning the acquisition of Right of User (RoU) for land required for the Srikakulam Angul Pipeline (SAPL) Spur pipeline project in Odisha. This analysis is based solely on the provided policy text.
**3. Policy Overview:**
This notification is related to the Petroleum and Minerals Pipeline (Acquisition of Right of Users in Land) Act, 1962.
* **Core Objective(s):** The core objective is to legally acquire the Right of User in specified land parcels for the purpose of laying a pipeline for transportation of natural gas and vest the right of user to GAIL India Limited.
**4. Background and Rationale:**
This is likely an acquisition of right of user as a part of the existing Act. The text indicates that GAIL (India) Limited is undertaking the project.
**5. Key Provisions / Changes:**
This is a declaration of the formal acquisition of land rights based on earlier intention. The key provisions detailed in this text are:
* **Declaration of Acquisition:** The Government of India declares the acquisition of the Right of User in the land specified in the Schedule appended to the notification for laying the SAPL Spur pipeline.
* **Vesting of Rights:** The Right of User in the land vests in GAIL (India) Limited, free from all encumbrances, from the date of publication of the notification.
* **Land Schedule:** A detailed schedule is included, specifying the District (Ganjam), State (Odisha), Tahasil, Thana, Village, Survey Numbers, and area (in Sq. Mtr. and Hector) of the land acquired. The schedule provides a comprehensive list of specific land parcels affected by the acquisition.
**6. Target Audience and Stakeholders:**
Based on the provided text, the directly affected stakeholders are:
* **Landowners:** Individuals or entities owning land parcels specified in the Schedule within the Ganjam district of Odisha.
* **GAIL (India) Limited:** The company responsible for laying the pipeline and the entity in which the Right of User is vested.
* **Government of India (Ministry of Petroleum and Natural Gas):** The agency responsible for issuing the notification and overseeing the land acquisition process.
* **Competent Authority:** The individual who submitted a report to the Government of India.
**7. Implementation Aspects (Inferred):**
* **Responsible Agency/Bodies:** The Ministry of Petroleum and Natural Gas is responsible for the overall policy, and GAIL (India) Limited is responsible for implementing the pipeline laying. A "Competent Authority" plays a role in reporting to the Government of India.
* **Timelines/Procedures:** The vesting of rights takes effect from the date of publication of the declaration. The text mentions that a report was submitted by the Competent Authority under Section 6 of the Act, suggesting a procedural sequence before the final declaration.
**8. Expected Outcomes / Impact of Changes:**
The intended outcome of this notification is to:
* Facilitate the construction of the Srikakulam Angul Pipeline (SAPL) Spur pipeline project by ensuring GAIL (India) Limited has the necessary Right of User in the specified land.
* Enable the transportation of natural gas through the pipeline, contributing to energy infrastructure development in the region.
* Potentially impact the landowners, requiring them to allow the pipeline to be laid across their land. Compensation for the acquisition of RoU is not explicitly mentioned in the supplied document but is typically part of the overall legal framework under which such acquisitions occur.
**9. Conclusion:**
The notification represents a crucial step in the implementation of the Srikakulam Angul Pipeline (SAPL) Spur pipeline project by legally acquiring the Right of User in the necessary land and vesting these rights in GAIL (India) Limited. The notification signifies progress in expanding natural gas infrastructure in Odisha. The information provided here is based solely on the provided text, and further details regarding compensation, environmental impact assessments, and other aspects of the project may be available in other related documents.
Key Entities Referenced
Ministry of Petroleum and Natural Gas: A ministry of the Government of India responsible for petroleum and natural gas.
NEW DELHI: The capital city of India, mentioned as the place of publication.
Petroleum and Minerals Pipeline Acquisition of Right of Users in Land Act, 1962: An act of the Government of India related to the acquisition of right of users in land for petroleum and mineral pipelines.
Srikakulam Angul Pipeline SAPL Spur pipeline: A pipeline for transportation of natural gas.
State of Odisha: A state in India where the pipeline is being laid.
GAIL India Limited: The company responsible for laying the pipeline.
Ganjam: A district in Odisha, India.
Seragada: A Tahasil in Ganjam district, Odisha, India.
Hinjilikatu: A Tahasil in Ganjam district, Odisha, India.
Sanakhemundi: A Tahasil in Ganjam district, Odisha, India.
RAKESH MISHRA: Under Secretary.