Publication of Notification in the Extraordinary Gazette of India under Section 3 1 of Petroleum and Minerals Pipelines Acquisition of Right of User in Land Act 1962 for acquisition of ROU in land for laying underground pipeline form 3 Q GAS LIFT LINE FROM WELL 157 TO WELL 760 GGS IV in State of Gujarat
## Report on Land Acquisition for Petroleum Pipeline in Gujarat, India
**1. Executive Summary:**
This report analyzes a government notification concerning the acquisition of Right of User (RoU) in land for laying a 3" gas lift pipeline by Oil and Natural Gas Corporation Ltd. (ONGC) in Gujarat, India. The notification initiates the process of acquiring land rights for the pipeline project, allowing affected parties to raise objections. The core purpose is to facilitate the construction of essential infrastructure for petroleum and natural gas transport.
**2. Introduction:**
This report aims to provide an informative overview of a government notification regarding the acquisition of land use rights for a petroleum pipeline project in Gujarat, India. The analysis is based solely on the provided notification text.
**3. Policy Overview:**
This appears to be a *new* policy action related to the execution of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962.
* **Core Objective(s):** As inferred from the text, the primary objective is to enable the laying of a 3" gas lift pipeline from WELL157 to WELL760GGS IV in Gujarat by ONGC. This involves acquiring the necessary rights to use land for the pipeline's construction and operation.
**4. Background and Rationale:**
As this is a new policy action related to a specific infrastructure project, the underlying problem being addressed is the need for improved or expanded infrastructure for the transportation of petroleum and natural gas. The text explicitly states that the central government deems the pipeline's construction necessary in the public interest. The pipeline will connect WELL157 to WELL760GGS IV.
**5. Key Provisions / Changes:**
* The notification declares the government's intention to acquire RoU in the land described in the attached schedule.
* It provides a 21-day window for individuals with vested interests in the land to object to the pipeline's laying.
* Objections must be submitted in writing to the Competent Authority, Oil and Natural Gas Corporation Ltd. (ONGC) at a specific address in Ankleshwar, Gujarat.
* Objectors must indicate whether they wish to be heard in person or through a legal practitioner.
* The schedule lists the specific land plots (survey numbers, block numbers, village names) in the TA: VAGRA DIST.:BHARUCH STATE : GUJARAT where RoU is to be acquired, along with their respective areas in hectares, ares, and centiares.
**6. Target Audience and Stakeholders:**
The primary target audience and stakeholders are:
* Landowners and individuals holding interests in the land parcels listed in the schedule.
* Oil and Natural Gas Corporation Ltd. (ONGC), the company responsible for laying the pipeline.
* Residents and communities in the vicinity of the pipeline route who may be directly or indirectly affected.
* Government agencies responsible for overseeing infrastructure development and land acquisition.
**7. Implementation Aspects (Inferred):**
* **Responsible Agency/Bodies:** The Oil and Natural Gas Corporation Ltd. (ONGC) is the primary body responsible for implementing the pipeline project and addressing objections. The Central Government, specifically the Ministry of Petroleum and Natural Gas, is responsible for issuing the notification and overseeing the land acquisition process under the Petroleum and Minerals Pipelines Act.
* **Timelines and Procedures:** The notification establishes a 21-day objection period, starting from the date the notification copies are made available to the public. Land acquisition will proceed following the review and resolution of any objections, as per the provisions of the Act.
**8. Expected Outcomes / Impact of Changes:**
The intended outcomes include:
* Facilitating the construction of the 3" gas lift pipeline.
* Improving the infrastructure for petroleum and natural gas transport in Gujarat.
* Potentially enhancing the efficiency of ONGC's operations in the region.
* The policy has the potential for disputes over land acquisition if objections are not adequately addressed.
**9. Conclusion:**
The government notification initiates the legal process of acquiring RoU in land for the construction of a 3" gas lift pipeline by ONGC in Gujarat. The notification outlines the affected land parcels, provides a mechanism for raising objections, and sets the stage for the pipeline's construction, which is deemed to be in the public interest. Stakeholders, particularly landowners, should be aware of the notification's provisions and the procedures for raising objections within the stipulated timeframe.
Key Entities Referenced
Gujarat State: State in India where the 3" GAS LIFT LINE FROM WELL157 TO WELL760GGS IV pipeline is planned.
Oil and Natural Gas Corporation Ltd.: The company (ONGC) responsible for laying the 3" GAS LIFT LINE FROM WELL157 TO WELL760GGS IV pipeline.
Petroleum and Minerals Pipelines Acquisition of Right of User in the Land Act, 1962: The legal act under which the Central Government declares its intention to acquire the right of user for laying the pipeline.
3" GAS LIFT LINE FROM WELL157 TO WELL760GGS IV: The name of the pipeline project.
Ankleshwar Asset: Asset of Oil and Natural Gas Corporation Ltd. where objections regarding the pipeline laying can be submitted.
Ankleshwar 390010, Gujarat: Location of ONGC CAMPUS where objections regarding the pipeline laying can be submitted.
Vagra: Taluka (TA) where the land acquisition for the pipeline is taking place in Gujarat.
Bharuch: District (Dist.) where the land acquisition for the pipeline is taking place in Gujarat.
Narnavi: Village where land is being acquired for the pipeline project.
Padariya: Village where land is being acquired for the pipeline project.
Kadodara: Village where land is being acquired for the pipeline project.
New Delhi: Place of Issuance of Notification by the MINISTRY OF PETROLEUM AND NATURAL GAS