Date: 2026-04-10Category: Extra OrdinaryState: Union GovernmentCountry: India
Publication of notification in the Extraordinary Gazette of India under Section 3(1) of the PMP Act 1962 (50 of 1962) relating to land schedule in respect of Haldia Panagarh LPG Pipeline Project(HPPL) of Hindustan Petroleum Corporation Limited(HPCL) for acquisition of RoU in the State of West Bengal
**Executive Summary**
This notification, issued by the Ministry of Petroleum and Natural Gas on April 8, 2026, declares the Central Government's intention to acquire the "Right of User" in specific lands in the Bankura District of West Bengal. The acquisition is necessary for laying the Haldia–Panagarh LPG pipeline by Hindustan Petroleum Corporation Limited (HPCL). Interested parties must submit any written objections within 21 days from the date the notification is made available to the public.
**Key Points / Main Content**
**Project Scope and Authority**
* **Purpose:** The project involves the transportation of LPG through a pipeline from Haldia to Panagarh to serve the public interest.
* **Executing Agency:** The pipeline will be laid by Hindustan Petroleum Corporation Limited (HPCL), a Government of India Enterprise.
* **Legal Basis:** The declaration is made under the powers conferred by sub-section (1) of section 3 of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962.
**Land Acquisition Details**
* **Location:** The affected lands are situated within the Bankura District of West Bengal.
* **Affected Areas:** The notification specifically targets land parcels within the jurisdictions of the Kotulpur, Indas, and Patrasayer Police Stations.
* **Schedule of Land:** The document provides an exhaustive list (Schedule) detailing the Mouza, J.L. Number, Plot Number, and specific area (in Hectares, Ares, and Square Meters) for each affected site.
**Objection Procedures**
* **Submission Period:** Objections must be filed within 21 days from the date the notification is made available to the general public.
* **Format:** All objections must be submitted in writing.
* **Recipient:** Objections should be addressed to the Competent Authority, Haldia-Panagarh LPG Pipeline Project, Hindustan Petroleum Corporation Limited, Ullas, Kundu Bhavan, TAAV07, P.O. Jotram, Purba Burdwan, Pin 713104.
**Impact Analysis**
**Landowners and Persons Interested in the Scheduled Land**
**Impact**
The government intends to acquire the Right of User for the land beneath their properties to install and maintain an LPG pipeline.
**Action Required**
Affected individuals must review the land schedule in the notification to identify their plots. If they wish to object to the acquisition, they must submit a written objection to the Competent Authority in Purba Burdwan within 21 days.
**Hindustan Petroleum Corporation Limited (HPCL)**
**Impact**
HPCL is authorized to proceed with the legal process of acquiring user rights for the Haldia–Panagarh pipeline route.
**Action Required**
HPCL must facilitate the acquisition process and coordinate with the Competent Authority to manage any objections received during the statutory period.
**The Competent Authority (Haldia-Panagarh LPG Pipeline Project)**
**Impact**
The office is designated as the official receiver of legal challenges and objections regarding this land acquisition.
**Action Required**
The authority must receive, review, and process written objections submitted by stakeholders within the 21-day deadline.
Key Entities Referenced
Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962: The primary legislation under which the Central Government acquires the right of user in land for laying petroleum and mineral pipelines.
Haldia – Panagarh LPG Pipeline Project: An infrastructure initiative for the transportation of Liquefied Petroleum Gas across West Bengal, for which land usage rights are being acquired.
Hindustan Petroleum Corporation Limited (HPCL): The Government of India enterprise authorized to lay the pipeline and execute the project.
Bankura, West Bengal: The primary location and state where the specific land parcels identified for acquisition are situated.
Ministry of Petroleum and Natural Gas: The central ministry responsible for issuing this notification and overseeing the project's regulatory compliance.