Date: 2022-12-21Category: Extra OrdinaryState: Union GovernmentCountry: India
Publication of notification in the Extraordinary Gazette of India under Section 3(1) of the PMP Act 1962 in respect of New Mundra Panipat Crude Pipeline(MPPL) project to be laid by Indian Oil Corporation Ltd. (IOCL) for acquisition of ROU in the State of Haryana Tehsil Israna Distt Panipat
## Report on Acquisition of Right of User for Crude Oil Pipeline in Haryana
**1. Executive Summary:**
This report analyzes a notification from the Ministry of Petroleum and Natural Gas, Government of India, published in the Gazette of India on December 21, 2022. The notification declares the Central Government's intention to acquire the right of user in land for laying a crude oil pipeline from Chudva to Panipat under the New Mundra-Panipat Pipeline Project by Indian Oil Corporation Limited (IOCL) in Haryana. Key findings highlight the affected areas, the process for raising objections, and the implementing agency.
**2. Introduction:**
This report aims to provide a clear and concise overview of a notification concerning the acquisition of right of user for land to facilitate the laying of a crude oil pipeline in Haryana. This analysis is solely based on the information provided within the notification text.
**3. Policy Overview:**
This notification enacts a provision under the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962.
* **Core Objective:** The primary objective, as stated in the text, is to acquire the right of user in land for laying a crude oil pipeline from Chudva to Panipat, deemed necessary in the public interest.
**4. Background and Rationale:**
The notification indicates that the Central Government believes it is "necessary in the public interest" to lay the specified crude oil pipeline. This suggests the policy addresses a need for enhanced transportation infrastructure for crude oil in the region. The specific reasons for this necessity are not detailed in the provided text, but could be related to increasing refining capacity or improving supply chain efficiency.
**5. Key Provisions / Changes:**
This is a *new* policy action, not an amendment, establishing the Central Government's intention to acquire right of user. The main components are:
* **Acquisition of Right of User:** The core action is the declaration of intent to acquire the right of user in specified lands. This doesn't transfer ownership but grants the right to lay and maintain the pipeline.
* **Project Details:** The pipeline is part of the New Mundra-Panipat Pipeline Project by Indian Oil Corporation Limited (IOCL). The pipeline route is from Chudva to Panipat, passing through Tehsil Israna of Panipat District, Haryana.
* **Affected Land:** The specific parcels of land affected are listed in the schedule, including village (Kurana and Chhichhdana), Mustil Number, Survey Number, and area (in Hectare, Are, and Sq.mtr.).
* **Objection Mechanism:** A process is established for persons interested in the land to object to the acquisition. Objections must be submitted in writing within 21 days of the notification's publication to the Competent Authority, Shri Balraj Singh, at the specified address.
**6. Target Audience and Stakeholders:**
The directly affected stakeholders are:
* Landowners in the villages of Kurana and Chhichhdana, Tehsil Israna, Panipat District, Haryana, whose land falls within the specified survey numbers in the schedule.
* Indian Oil Corporation Limited (IOCL), as the implementing agency for the pipeline project.
**7. Implementation Aspects (Inferred):**
* **Responsible Agency:** The Central Government, through the Ministry of Petroleum and Natural Gas, is responsible for the overall decision to acquire the right of user. Indian Oil Corporation Limited (IOCL) is responsible for laying the pipeline.
* **Competent Authority:** Shri Balraj Singh, Competent Authority, New Mundra Panipat Pipeline Project, Indian Oil Corporation Limited, Northern Region Pipelines, Near Panipat Refinery, Baholi Panipat 132140, Haryana, is responsible for receiving and processing objections.
* **Timeline:** Landowners have 21 days from the date the notification is made publicly available to submit objections.
**8. Expected Outcomes / Impact of Changes:**
The likely intended outcomes of this policy are:
* Facilitation of the New Mundra-Panipat Pipeline Project.
* Improved infrastructure for the transportation of crude oil.
* Potential economic benefits associated with enhanced oil supply and refining capacity.
* Potential impact on landowners in the affected areas, who may experience temporary disruption during pipeline construction and will receive compensation for the right of user acquired on their land. The notification does not detail specifics about compensation.
**9. Conclusion:**
The notification outlines the Central Government's intention to acquire the right of user in land for laying a crude oil pipeline in Haryana, a project deemed necessary in the public interest. The policy establishes a process for landowners to raise objections and designates IOCL as the implementing agency. The successful implementation of this policy will likely contribute to enhanced crude oil transportation infrastructure and potential economic benefits for the region, while landowners are given the opportunity to raise concerns within a specified timeframe.
Key Entities Referenced
Petroleum and Minerals Pipelines Acquisition of Right of User in land Act, 1962: An act related to the acquisition of the right of user in land for petroleum and minerals pipelines.
Indian Oil Corporation Limited: A company laying a Crude Oil Pipeline from Chudva to Panipat under New MundraPanipat Pipeline Project.
New MundraPanipat Pipeline Project: A pipeline project by Indian Oil Corporation Limited.
Panipat District: A district in the State of Haryana where the pipeline is being laid.
Haryana: A state in India where the pipeline project is located.
Chudva: Starting point of Crude Oil Pipeline.
Panipat: Destination point of Crude Oil Pipeline.
Tehsil Israna: A tehsil of Panipat District in the State of Haryana.
Balraj Singh: Competent Authority, New Mundra Panipat Pipeline Project, Indian Oil Corporation Limited, Northern Region Pipelines.
Northern Region Pipelines: A region of Indian Oil Corporation Limited.
Baholi Panipat 132140: Location of Competent Authority, New Mundra Panipat Pipeline Project office.
Kurana: A village in Tehsil Israna of Panipat District in the State of Haryana.
Chhichhdana: A village in Tehsil Israna of Panipat District in the State of Haryana.
Ministry of Petroleum and Natural Gas: The ministry responsible for the notification regarding the Crude Oil Pipeline project.
New Delhi: Place of publication of notification.