Date: 2026-07-31Category: Extra OrdinaryState: Union GovernmentCountry: India
Publication of Notification in the Gazette of India 3(1) of the PMP Act, 1962 (50 of 1962) for acquisition of Right of User (RoU) in land for laying underground pipeline from PALIYAD GGS TO WADU GGS (8 INCH DIA) in the State of Gujarat.
**Executive Summary**
This notification, issued by the Ministry of Petroleum and Natural Gas on July 30, 2026, declares the Central Government's intention to acquire the Right of User (RoU) in specific lands in Gujarat for the "Paliyad GGS to Wadu GGS (8" Dia) Pipeline." Executed by ONGC Ltd., the pipeline is intended for transporting crude oil and gas across the Gandhinagar and Mehsana districts. Interested parties have a 21-day deadline from the publication date to file written objections regarding the land acquisition with the Competent Authority in Ahmedabad.
**Key Points / Main Content**
* **Project Objective and Authority**
* The Central Government has mandated the construction of an 8-inch diameter pipeline by Oil and Natural Gas Corporation Limited (ONGC) for the transportation of crude oil and gas.
* The project is declared to be in the public interest.
* **Legal Framework**
* The notification is issued under Section 3(1) of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962.
* The government officially announces its intention to acquire the Right of User (RoU) for laying the pipeline beneath the lands described in the attached schedule.
* **Affected Locations (Gujarat State)**
* **Gandhinagar District (Kalol Taluka):** Affected land parcels are located in the villages of Paliyad and Kantha.
* **Mehsana District (Kadi Taluka):** Affected land parcels are located in the villages of Narola and Vadu-2.
* The document includes a detailed schedule listing specific survey/block numbers and the exact area (measured in hectares, are, and square meters) required for each plot.
* **Objection Submissions**
* Any person with an interest in the listed land can submit written objections to the acquisition of the Right of User.
* Objections must be sent to the Competent Authority, ONGC Ltd. (Ahmedabad Asset), located at Avani Bhavan, Chandkheda, Ahmedabad-380005.
* The deadline for filing objections is 21 days from the date the Gazette notification is made available to the public.
**Impact Analysis**
**Stakeholder: Landowners and Interested Parties in Paliyad, Kantha, Narola, and Vadu-2 villages**
**Impact**
The identified land parcels will be subject to the acquisition of the Right of User, allowing the installation of a sub-surface pipeline, which may restrict certain future land uses directly over the pipeline route.
**Action Required**
Interested persons must review the detailed schedule to identify specific survey numbers and, if necessary, submit a written objection to the Competent Authority within the 21-day statutory period.
**Stakeholder: Oil and Natural Gas Corporation Limited (ONGC)**
**Impact**
ONGC is authorized to proceed with the legal acquisition process and eventual construction of the 8" diameter pipeline project between Paliyad GGS and Wadu GGS.
**Action Required**
Coordinate with the Competent Authority to manage the administrative process for the Right of User acquisition and address any objections received at the Ahmedabad Asset office.
**Stakeholder: Ministry of Petroleum and Natural Gas / Competent Authority**
**Impact**
The Ministry is responsible for the formal legal notification and the subsequent adjudication of objections from the public regarding the project.
**Action Required**
Ensure the notification is accessible to the general public and process all submitted written objections in accordance with the Petroleum and Minerals Pipelines Act, 1962.
Key Entities Referenced
Gandhinagar and Mehsana, Gujarat: The specific geographical locations (districts and state) where the land identified for the pipeline project is situated.
Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962: The legal framework under which the government acquires the right of user in land for laying pipelines.
Paliyad GGS to Wadu GGS (8" Dia) Pipeline: The specific infrastructure project for laying an 8-inch diameter pipeline to transport crude oil and gas.
Oil and Natural Gas Corporation Limited (ONGC): The executing agency responsible for laying the pipeline and for whose project the land rights are being acquired.
Ministry of Petroleum and Natural Gas: The primary central ministry that issued the notification for land acquisition for energy infrastructure.