## Policy Analysis Report: Land Acquisition for ROB RBK30 on NH75E
**1. Executive Summary:**
This report analyzes a notification from the Ministry of Road Transport and Highways, Government of India, regarding land acquisition for the construction of Road Over Bridge (ROB) RBK30 on National Highway 75E (NH75E) in the West Singhbhum district of Jharkhand. The notification authorizes specific officers to act as competent authorities for land acquisition related to this project, covering a stretch from Km. 169.075 to 170.865. This report outlines the policy's objective, key provisions, affected stakeholders, and expected outcomes, all based solely on the provided official gazette notification.
**2. Introduction:**
This report provides an analysis of a notification published in the Gazette of India concerning land acquisition for the construction of ROB RBK30 on NH75E. The analysis is based exclusively on the text provided in the notification. The purpose is to inform stakeholders about the key aspects of this specific land acquisition policy.
**3. Policy Overview:**
* This is a *new* policy directly related to a specific infrastructure project.
* **Core Objective(s):** The core objective, as inferred from the text, is to facilitate the construction of ROB RBK30 on NH75E by authorizing designated officers to acquire the necessary land within the specified stretch.
**4. Background and Rationale:**
* **New Policy:** This policy addresses the need to acquire land for the construction of infrastructure, specifically a Road Over Bridge (ROB), on a designated National Highway. The construction of ROBs generally aims to improve transportation efficiency, safety, and connectivity by eliminating level crossings and streamlining traffic flow. The rationale for this specific ROB (RBK30) is not explicitly stated, but it can be inferred that it is intended to address existing transportation challenges or support planned development along NH75E.
**5. Key Provisions / Changes:**
* **New Policy:** The notification's key provision is the authorization of officers listed in the schedule to act as competent authorities under the National Highways Act, 1956, for the purpose of land acquisition. This authorization applies specifically to land required for the construction of ROB RBK30 on NH75E from Km. 169.075 to Km. 170.865 in the West Singhbhum district of Jharkhand. The Schedule outlines the specific stretch of land and villages (Iligara and Nurda) affected. This action empowers the listed officers to perform functions related to land acquisition as defined by the National Highways Act, 1956.
**6. Target Audience and Stakeholders:**
Based on the provided text, the directly affected target audience and stakeholders include:
* **Landowners and Residents:** Individuals and communities owning land or residing within the specified stretch of NH75E (Km. 169.075 to 170.865) in the West Singhbhum district, specifically in the villages of Iligara and Nurda.
* **Construction Companies:** Companies involved in the construction of the ROB RBK30, as the land acquisition directly impacts their ability to commence and complete the project.
* **West Singhbhum District Administration:** The district administration of West Singhbhum, Jharkhand, which will be involved in the land acquisition process and its associated activities.
**7. Implementation Aspects (Inferred):**
* **Responsible agency/bodies mentioned:** The Central Government (Ministry of Road Transport and Highways) and the District Land Acquisition Officer are directly mentioned. The schedule outlines which officer will function as the competent authority.
* **Any timelines or procedures specified in the text:** The notification takes effect from the date of its publication in the Official Gazette (March 24, 2022). The procedures for land acquisition are governed by the National Highways Act, 1956, although the specifics of these procedures are not detailed in the provided text.
* The notification specifies the State (Jharkhand), District (West Singhbhum), Taluk/Mandal (Hatgamhriya), and Villages (Iligara and Nurda) where the land acquisition will take place.
**8. Expected Outcomes / Impact of Changes:**
* **New Policy:** The intended outcome of this policy is to enable the smooth and timely acquisition of land required for the construction of ROB RBK30 on NH75E. This, in turn, is expected to facilitate the construction of the ROB, leading to improved transportation infrastructure, reduced traffic congestion, enhanced safety, and better connectivity in the West Singhbhum district of Jharkhand. Ultimately, this could foster economic development and improve the quality of life for residents.
**9. Conclusion:**
The notification analyzed authorizes land acquisition for the construction of ROB RBK30 on NH75E in the West Singhbhum district of Jharkhand. This policy is a necessary step for infrastructure development, potentially leading to improved transportation and economic benefits. The key element is the authorization of designated officers to act as competent authorities for this specific land acquisition, streamlining the process under the National Highways Act, 1956. This notification represents a crucial step in the advancement of transportation infrastructure in the region.
Key Entities Referenced
National Highways Act, 1956: A law enacted in 1956, referenced as the basis for conferring powers to authorities for land acquisition and construction of national highways.
Central Government: The governing body that authorizes officers to perform functions related to the National Highways Act.
West Singhbhum district: A district located in Jharkhand State, where land acquisition is taking place for the construction of a road overbridge (ROB).
Jharkhand State: A state in India where the land acquisition and construction project is located.
ROB RBK30: Road Over Bridge with code RBK30, which is being constructed on NH75E.
NH75E: National Highway 75E, the location of the construction project (ROB RBK30).
Iligara: A village in West Singhbhum district of Jharkhand State, where land acquisition is taking place.
Hatgamhriya: A Taluk/Mandal in West Singhbhum district of Jharkhand State, where land acquisition is taking place.
Nurda: A village in West Singhbhum district of Jharkhand State, where land acquisition is taking place.
Ministry of Road Transport and Highways: The government ministry responsible for the notification regarding land acquisition for the construction project.
New Delhi: The city where the Ministry of Road Transport and Highways is located and from where the notification was issued.
RAJESH GUPTA: Director at Ministry of Road Transport and Highways.
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
xxxGIDHxxx
सी.जी.-डी.एलxx.x-GअID.-E2x5xx0 32022-234452
CG-DL-E-25032022-234452
ऄसाधारण
EXTRAORDINARY
भाग II—खण् ड 3—ईप-खण्ड (ii)
PART II—Section 3—Sub-section (ii)
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 1277] नइ ददल्ली, बहृ स्ट्प जतवार, माच ग24, 2022/चत्रै 3, 1944
No. 1277] NEW DELHI, THURSDAY, MARCH 24, 2022/CHAITRA 3, 1944
सड़क पररवहन और रािमाग गमत्रं ालय
ऄजधसचू ना
नइ ददल् ली, 24 माच,ग 2022
का.अ. 1319(ऄ).—केन्द्रीय सरकार, राष्ट्रीय रािमाग ग ऄजधजनयम, 1956 (1956 का 48) की धारा 3 के
खंड (क) द्वारा प्रदत्त िजियों का प्रयोग करत े हुए, आस ऄजधसूचना के िासकीय रािपत्र म ें प्रकाजित होन े की तारीख स,े
झारखण्ड राज्य के पजिमी ससघभूम जिल े म ें ROB(RBK-30) जनमागण हते ु के दक.मी. 169.075 स े 170.865 तक भूजम
का ऄजधग्रहण हते ु ईि ऄनसु ूची के स्ट्तम्भ (4), (5), (6) और (7) म ें क्रमिः ईजल्लजखत राज्य, जिलों, तालुकों और गावों स े
सम्बजन्द्धत ईि ऄनुसूची के स्ट्तम्भ (3) की तत्सस्ट्थानी प्रजवजि म ें जवजनर्ददि भूजम के सम्बन्द्ध म ें ऄनुसूची के स्ट्तम्भ (2) म ें
ईजल्लजखत ऄजधकाररयों को ईि ऄजधजनयम के ऄन्द्तगगत सक्षम ऄजधकाररयों के कृत्सयों का जनष्पादन करन े के जलए एतद्द्वारा
सक्षम प्राजधकारी के रूप म ेंप्राजधकृत करती ह।ै
2016 GI/2022 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
ऄनसु चू ी
झारखडं राज्य म ेंराष्ट्रीय रािमाग ग सख्ं या-NH75E पर ROB(RBK-30) जनमाणग हते ु के दक.मी. 169.075 स े170.865
तक भजू म का ऄजधग्रहण।
क्रजमक सक्षम भूजम का राज्य जिल ेका तालकु का नाम गावं का नाम
सख्ं या प्राजधकारी जववरण नाम
1 2 3 4 5 6 7
राष्ट्रीय
रािमाग ग
जडजस्ट्रक्ट संख्या
लेन्द्ड NH75E के
एक्वजििन वेस्ट्ट 1 इलीगाड़ा
1 दक.मी. झारखंड हाटगम्हररया
औफसर ससघभूम
2 नूदा ग
169.075
स े
170.865
तक
[फा. स.ं RW/Ranchi/LA/ROB/RBK-30/NH-75E/JHR/2021-22]
रािेि गुप् ता, जनदेिक
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
NOTIFICATION
New Delhi, the 24th March, 2022
S.O. 1319(E).—In exercise of powers conferred by clause (a) of section 3 of the National
Highways Act, 1956(48 of 1956), the Central Government hereby authorizes the officers mentioned in
column (2) of the Schedule annexed here to as the competent authorities to perform the functions of such
authorities under the said Act with effect from the date of publication of this notification in the Official
Gazette, in respect of the stretch of land specified in the corresponding entry in column (3) of the said
Schedule relating to state, districts, taluk and villages mentioned in column (4), (5), (6) and (7) respectively
of the said Schedule for Construction of ROB (RBK-30) on -NH-75E from Km. 169.075 to 170.865 of
West Singhbhumdistrict of Jharkhand State.[भाग II—खण् ड 3(ii)] भारत का रािपत्र : ऄसाधारण 3
SCHEDULE
Land acquisition on National Highway No. NH75E from Km. 169.075 to 170.865 of West
Singhbhumdistrict of Jharkhand State.
Sl. CALA Stretch State District Taluk/Mandal Name of
No. the
Village
1 2 3 4 5 6 7
District Land
Acquisition 169.075 Km.
WEST 1 Iligara
1 Officer To 170.865 JHARKHAND Hatgamhriya
SINGHBHUM 2 Nurda
Km.
[F. No. RW/Ranchi/LA/ROB/RBK-30/NH-75E/JHR/2021-22]
RAJESH GUPTA, Director
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.