**Policy Analysis Report: Land Acquisition for National Highway 152D (Haryana)**
**1. Executive Summary:**
This report analyzes a government notification concerning land acquisition for the building, widening, maintenance, management and operation of the Greenfield alignment of Ismailabad Gangheri Narnaul National Highway No. 152D in the district of Mahendergarh in the state of Haryana. The notification declares the government's intention to acquire specific land parcels between Km 185.800 to Km 227.020 and outlines the process for landowners to object to the acquisition. Key findings include detailed lists of affected land plots (survey/plot numbers), their nature (primarily private agricultural land), and precise area measurements in hectares. The report highlights the affected parties, including landowners within the specified stretch.
**2. Introduction:**
This report provides an overview of a government notification published in the Gazette of India, Extraordinary, Part II, Section 3, Subsection (ii) on April 12, 2021. The purpose of this report is to inform affected parties and stakeholders about the government's intention to acquire land for the development of National Highway 152D in Haryana, based solely on the information presented in the provided document.
**3. Policy Overview:**
* This is a new policy action related to land acquisition.
* **Core Objective(s):** As stated in the provided text, the core objective is to acquire land for the public purpose of "building wideningfourSix laning etc.,, maintenance, management and operation" of National Highway No. 152D.
**4. Background and Rationale:**
The policy addresses the need for land to facilitate the construction, widening, maintenance, management and operation of the Greenfield alignment of the National Highway 152D. The text explicitly mentions that this is for a "public purpose," implying a benefit to the broader community through improved infrastructure and connectivity.
**5. Key Provisions / Changes:**
This is a new policy action, so the key provisions of the *entire* provided text are analyzed:
* **Declaration of Intent to Acquire Land:** The core provision is the formal declaration of the Central Government's intention to acquire land in the district of Mahendergarh, Haryana, specifically between Km 185.800 and Km 227.020 for the National Highway 152D project.
* **Land Details:** The policy includes a detailed schedule listing the specific land parcels intended for acquisition. This schedule specifies the Survey/Plot Number, Type of Land (Private), Nature of Land (Agriculture), and Area in Hectares for each plot.
* **Objection Mechanism:** The policy establishes a mechanism for landowners to object to the land acquisition. It grants a 21-day window from the notification's publication date for interested parties to file objections with the Competent Authority (District Revenue Officer, Mahendragarh).
* **Objection Procedure:** The policy outlines the process for handling objections. Objectors are entitled to a hearing (in person or through legal counsel), and the Competent Authority is empowered to conduct further inquiries before allowing or disallowing the objections. The Competent Authority's decision is final.
* **Availability of Land Plans:** The notification states that land plans and other details related to the land acquisition are available for inspection at the Competent Authority's office.
**6. Target Audience and Stakeholders:**
Based on the provided text, the primary target audience and stakeholders are:
* **Landowners:** Individuals and entities owning the land parcels listed in the schedule within the district of Mahendergarh in the state of Haryana.
* **District Revenue Officer, Mahendragarh:** The designated Competent Authority responsible for handling objections and inquiries related to the land acquisition.
**7. Implementation Aspects (Inferred):**
* **Responsible Agency/Bodies:** The Central Government (Ministry of Road Transport and Highways) is the primary responsible agency. The District Revenue Officer, Mahendragarh, serves as the Competent Authority for local implementation.
* **Timelines:** A 21-day timeline is provided for landowners to submit objections from the date of publication of the notification.
* **Procedures:** The text outlines a clear procedure for filing and addressing objections, involving written submissions, hearings, and potential further inquiries by the Competent Authority.
**8. Expected Outcomes / Impact of Changes:**
The likely intended outcomes of this policy action, based on the provisions in the text, are:
* **Land Acquisition:** Successful acquisition of the land parcels specified in the schedule for the NH-152D project.
* **Infrastructure Development:** Facilitation of the construction, widening, maintenance, management and operation of the National Highway 152D, leading to improved transportation infrastructure and connectivity in the region.
* **Economic Development:** Supporting economic growth and development in the region due to improved connectivity.
**9. Conclusion:**
The government notification declares the intention to acquire land for the development of National Highway 152D in Haryana. It outlines the land acquisition process, including the process for landowners to raise objections. The notification is a crucial step towards the realization of the highway project and its potential benefits for regional connectivity and economic development. Timely adherence to the stipulated timelines and procedures is essential for landowners to protect their interests, and for the Competent Authority to ensure a fair and transparent land acquisition process.
Key Entities Referenced
National Highways Act, 1956: A law under which powers are conferred to acquire land for national highway projects. (48 of 1956)
Central Government: The governing authority responsible for declaring the intention to acquire land for public purposes under the National Highways Act, 1956.
Greenfield alignment of Ismailabad Gangheri Narnaul national highway No. 152D: The specific highway project for which land acquisition is being carried out. The stretch of land from Km. 185.800 to Km. 227.020 is being acquired.
Mahendergarh, Haryana: The district and state where the land acquisition for the highway project is taking place.
Competent Authority, District Revenue Officer, Mahendragarh: The authority designated to handle objections related to the land acquisition process.
Ateli Taluk, Haryana: Specifies a sub-division of Mahendergarh District, Haryana where land acquisition is planned.
Kanina Taluk, Haryana: Specifies a sub-division of Mahendergarh District, Haryana where land acquisition is planned.
Narnaul Taluk, Haryana: Specifies a sub-division of Mahendergarh District, Haryana where land acquisition is planned.
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
सी.जी.-डी.एल.-अ.-13042021-226560
xxxGIDHxxx
CG-DL-E-13042021-226560
xxxGIDExxx
असाधारण
EXTRAORDINARY
भाग II—खण् ड 3—उप-खण्ड (ii)
PART II—Section 3—Sub-section (ii)
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 1446] नई ददल्ली, सोमवार, अप्रैल 12, 2021/चत्रै 22, 1943
No. 1446] NEW DELHI, MONDAY, APRIL 12, 2021/CHAITRA 22, 1943
सड़क पररवहन और रािमाग गमत्रं ालय
अजधसचू ना
नई ददल् ली, 12 अप्रैल, 2021
का.आ. 1557(अ).—केन्द्रीय सरकार, राष्ट्रीय रािमागग अजधजनयम 1956 (1956 का 48) (जिसे इसम ें इसके
पश्चात ् उक्त अजधजनयम कहा गया ह)ै की धारा 3क की उप-धारा (1) द्वारा प्रदत्त िजक्तयों का प्रयोग करते हुए, यह समाधान
हो िाने के पश्चात ् दक हररयाणा राज्य के महन्द्े रगढ़ जिले म ें इस्ट्माईलाबाद (गगं हड़े ी) - नारनौल राष्ट्रीय रािमागग संख्या
152डी के दक.मी. 185.800 से दक.मी. 227.020 तक के भ-ू खण्ड के जनमाणग (चौड़ीकरण/4-लेन/6-लेन का बनाना आदद),
अनुरक्षण, प्रबन्द्धन और प्रचालन के लोक प्रयोिन के जलए वह भूजम अपेजक्षत ह ै जिसका संजक्षप्त वणगन नीच े अनुसूची म ें ददया
गया ह,ै ऐसी भूजम का अिगन करने के अपने आिय की घोषणा करती ह ै।
कोई भी व्यजक्त, िो उक्त भूजम म ें जहतबद्ध ह,ै उक्त अजधजनयम की धारा 3ग की उप-धारा (1) के अधीन पूवोक्त
प्रयोिन के जलए ऐसी भूजम के उपयोग पर रािपत्र म ें इस अजधसूचना के प्रकािन की तारीख स े इक्कीस ददन के भीतर अपनी
आपजत्त प्रकट कर सकेगा ।
ऐसी प्रत्येक आपजत्त सक्षम प्राजधकारी, अथागत् जिला रािस्ट्व अजधकारी, महन्द्े रगढ़ को जलजखत रूप म े प्रस्ट्तुत की
िाएगी और उसम ें उसके आधार अजधकजथत दकए िाएगं े और सक्षम प्राजधकारी, आपजत्तकता ग को व्यजक्तगत रूप म े या दकसी
जवजधक पेिेवर द्वारा सुने िान े का अवसर देगा और ऐसी आपजत्तयों की सुनवाई के पश्चात ् तथा ऐसी और िााँच करने के
2202 GI/2021 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
पश्चात,् यदद कोई हो, जिसे सक्षम प्राजधकारी आवश्यक समझे, आदेि द्वारा या तो आपजत्तयों को अनुज्ञात कर सकेगा या
अननुज्ञात कर सकेगा ।
उक्त अजधजनयम की धारा 3ग की उप-धारा (2) के अधीन सक्षम प्राजधकारी द्वारा दकया गया कोई भी आदेि
अंजतम होगा ।
इस अजधसूचना के अतं गतग आने वाली भूजम के रेखांक और अन्द्य ब्यौरे सक्षम प्राजधकारी के उक्त कायागलय म ें
उपलब्ध ह ैंऔर उनका जहतबद्ध व्यजक्तयों द्वारा जनरीक्षण दकया िा सकता ह ै।
अनसु चू ी
हररयाणा राज्य के महन्द्े रगढ़ जिल े म ेंइस्ट्माईलाबाद (गगं हड़े ी) - नारनौल राष्ट्रीय रािमाग ग सख्ं या 152डी के
दक.मी. 185.800 स ेदक.मी. 227.020 के जलए अिनग की िान े वाली सरं चना रजहत अथवा सरं चना सजहत भजू म
का सजं क्षप्त जववरण ।
राज्य का नाम: हररयाणा जिल ेका नाम: महन्द्े दरगढ़
क्रजमक सख्ं या सवक्षे ण सख्ं या भजू म का प्रकार भजू म की प्रकृजत भजू म का क्षत्रे फल भजू म का क्षत्रे फल
(स्ट्थानीय इकाई) (हेक्टेयर)
तालुक का नाम: अटेली
गावं का नाम: सागरपुर
1 37//1/2 Min जनिी कृजष 0.0202000(हक्े टेयर) 0.0202000
2 37//10/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
3 37//11/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
तालुक का नाम: कनीना
गावं का नाम: बाघोत
1 115//3/1/1 min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
2 115//8/2/2 Min जनिी कृजष 0.0278000(हक्े टेयर) 0.0278000
3 65//6/2/2 जनिी कृजष 0.0481000(हक्े टेयर) 0.0481000
4 92//13/2/1 min जनिी कृजष 0.0051000(हक्े टेयर) 0.0051000
5 92//18/2/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
6 92//23/1/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
गावं का नाम: दोंगडा अहीर
1 16//13/1/1 Min जनिी कृजष 0.0202000(हक्े टेयर) 0.0202000
2 16//13/2/1 Min जनिी कृजष 0.0152000(हक्े टेयर) 0.0152000
3 16//18/1/2 Min जनिी कृजष 0.0051000(हक्े टेयर) 0.0051000
4 16//18/2/2 Min जनिी कृजष 0.0278000(हक्े टेयर) 0.0278000
5 16//23/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
6 19//3/1 Min जनिी कृजष 0.0278000(हक्े टेयर) 0.0278000[भाग II—खण् ड 3(ii)] भारत का रािपत्र : असाधारण 3
7 19//8/1/2 Min जनिी कृजष 0.0278000(हक्े टेयर) 0.0278000
8 19//8/2/2 Min जनिी कृजष 0.0076000(हक्े टेयर) 0.0076000
गावं का नाम: खरकड़ा बास
1 166//11/2 min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
2 166//20 Min जनिी कृजष 0.0051000(हक्े टेयर) 0.0051000
3 167//17/2 min जनिी कृजष 0.0379000(हक्े टेयर) 0.0379000
4 167//24/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
5 170//4/1 min जनिी कृजष 0.0076000(हक्े टेयर) 0.0076000
6 69//12/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
7 69//19 Min जनिी कृजष 0.0051000(हक्े टेयर) 0.0051000
8 69//9/1 min जनिी कृजष 0.0278000(हक्े टेयर) 0.0278000
9 95//14/1 min जनिी कृजष 0.0278000(हक्े टेयर) 0.0278000
10 95//17/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
11 95//19/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
12 95//24/1/2 Min जनिी कृजष 0.0152000(हक्े टेयर) 0.0152000
13 95//24/2/1 Min जनिी कृजष 0.0228000(हक्े टेयर) 0.0228000
गावं का नाम: खड़े ी
1 101//13/1/2 Min जनिी कृजष 0.0278000(हक्े टेयर) 0.0278000
2 101//13/2 Min जनिी कृजष 0.0051000(हक्े टेयर) 0.0051000
3 101//3/2 Min जनिी कृजष 0.0278000(हक्े टेयर) 0.0278000
4 101//8/1/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
गावं का नाम: पाथडे ा
1 79//14/3 Min जनिी कृजष 0.0126000(हक्े टेयर) 0.0126000
2 79//15/1/2 Min जनिी कृजष 0.0076000(हक्े टेयर) 0.0076000
3 79//15/2/2 Min जनिी कृजष 0.0126000(हक्े टेयर) 0.0126000
4 79//5/2 min जनिी एग्रीकल्चर 0.0278000(हक्े टेयर) 0.0278000
5 79//6/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
गावं का नाम: पौता
1 21//3/2 min जनिी कृजष 0.0278000(हक्े टेयर) 0.0278000
2 21//4/2 Min जनिी कृजष 0.0025000(हक्े टेयर) 0.00250004 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
3 29//10/1/1 min जनिी कृजष 0.0076000(हक्े टेयर) 0.0076000
4 29//10/2/1 Min जनिी कृजष 0.0228000(हक्े टेयर) 0.0228000
5 29//11 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
6 29//20/1/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
7 29//20/4/1 Min जनिी कृजष 0.0025000(हक्े टेयर) 0.0025000
8 30//1/3/2 min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
9 30//10/1 min जनिी कृजष 0.0152000(हक्े टेयर) 0.0152000
10 30//10/4/1 Min जनिी कृजष 0.0126000(हक्े टेयर) 0.0126000
11 30//11/2 Min जनिी कृजष 0.0152000(हक्े टेयर) 0.0152000
12 30//20/1 Min जनिी कृजष 0.0076000(हक्े टेयर) 0.0076000
तालुक का नाम: महन्द्े रगढ़
गावं का नाम: अकबरपुर नगं ल
1 25//8/1 Min जनिी कृजष 0.0126000(हक्े टेयर) 0.0126000
2 31//15/2/2 Min जनिी कृजष 0.0228000(हक्े टेयर) 0.0228000
3 31//16/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
4 31//25/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
5 32//11/1 Min जनिी कृजष 0.0076000(हक्े टेयर) 0.0076000
6 48//5 Min जनिी कृजष 0.0051000(हक्े टेयर) 0.0051000
7 53//21/2 Min जनिी कृजष 0.0126000(हक्े टेयर) 0.0126000
8 69//1/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
गावं का नाम: भालखी
1 100//4/1 Min जनिी कृजष 0.0379000(हक्े टेयर) 0.0379000
2 16//25/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
3 35//13/1/2 Min जनिी कृजष 0.0278000(हक्े टेयर) 0.0278000
4 35//14/2 Min जनिी कृजष 0.0152000(हक्े टेयर) 0.0152000
5 35//15/2 Min जनिी कृजष 0.0051000(हक्े टेयर) 0.0051000
6 35//16 Min जनिी कृजष 0.0076000(हक्े टेयर) 0.0076000
7 35//17/1 Min जनिी कृजष 0.0556000(हक्े टेयर) 0.0556000
8 35//18/1/2 Min जनिी कृजष 0.0607000(हक्े टेयर) 0.0607000
9 35//23/1 Min जनिी कृजष 0.1442000(हक्े टेयर) 0.1442000[भाग II—खण् ड 3(ii)] भारत का रािपत्र : असाधारण 5
10 35//24/2 Min जनिी कृजष 0.0860000(हक्े टेयर) 0.0860000
11 35//3/1 Min जनिी कृजष 0.0152000(हक्े टेयर) 0.0152000
12 35//5/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
13 35//6/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
14 40//13/1/2 Min जनिी कृजष 0.0708000(हक्े टेयर) 0.0708000
15 40//14/1/2 Min जनिी कृजष 0.0759000(हक्े टेयर) 0.0759000
16 40//14/2 Min जनिी कृजष 0.1113000(हक्े टेयर) 0.1113000
17 40//17/1 Min जनिी कृजष 0.1720000(हक्े टेयर) 0.1720000
18 40//24/1/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
19 40//24/1/2/1 Min जनिी कृजष 0.0607000(हक्े टेयर) 0.0607000
20 40//3/1 Min जनिी कृजष 0.1568000(हक्े टेयर) 0.1568000
21 40//3/2/1 Min जनिी कृजष 0.0101000(हक्े टेयर) 0.0101000
22 40//4/2 Min जनिी कृजष 0.0910000(हक्े टेयर) 0.0910000
23 40//7/1 Min जनिी कृजष 0.1543000(हक्े टेयर) 0.1543000
24 40//8/1/2 Min जनिी कृजष 0.0253000(हक्े टेयर) 0.0253000
25 40//8/2 Min जनिी कृजष 0.0607000(हक्े टेयर) 0.0607000
26 59//4 Min जनिी कृजष 0.0076000(हक्े टेयर) 0.0076000
27 97//24/2/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
गावं का नाम: बचुं ावास
1 105//3/1 min जनिी कृजष 0.0152000(हक्े टेयर) 0.0152000
2 99//14 min जनिी कृजष 0.0025000(हक्े टेयर) 0.0025000
3 99//17/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
गावं का नाम: खड़े ा
1 2//19/3/2 min जनिी कृजष 0.0051000(हक्े टेयर) 0.0051000
2 2//20/1/1 Min जनिी कृजष 0.0126000(हक्े टेयर) 0.0126000
3 2//20/2/1 Min जनिी कृजष 0.0202000(हक्े टेयर) 0.0202000
4 2//21/1/1 Min जनिी कृजष 0.0076000(हक्े टेयर) 0.0076000
5 2//21/2/1 Min जनिी कृजष 0.0152000(हक्े टेयर) 0.0152000
6 2//21/3/2 Min जनिी कृजष 0.0076000(हक्े टेयर) 0.00760006 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
7 5//1/1 min जनिी कृजष 0.0228000(हक्े टेयर) 0.0228000
8 6//5/1 min जनिी कृजष 0.0076000(हक्े टेयर) 0.0076000
गावं का नाम: सरु िनवास
1 8//14/2/2 min जनिी कृजष 0.0228000(हक्े टेयर) 0.0228000
2 8//15/1/1/2 Min जनिी कृजष 0.0126000(हक्े टेयर) 0.0126000
3 8//17/1/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
4 8//24/2 Min जनिी कृजष 0.0051000(हक्े टेयर) 0.0051000
तालुक का नाम: नारनौल
गावं का नाम: बड़गावाँ (१६५ )
1 33//5 जनिी कृजष 0.0025000(हक्े टेयर) 0.0025000
2 39//2/1 जनिी कृजष 0.0202000(हक्े टेयर) 0.0202000
गावं का नाम: दबु लाना(१७४)
1 12//11/2 Min जनिी कृजष 0.0304000(हक्े टेयर) 0.0304000
2 12//2/2/1 Min जनिी कृजष 0.0304000(हक्े टेयर) 0.0304000
3 12//20/1 Min जनिी कृजष 0.0304000(हक्े टेयर) 0.0304000
4 12//9/1 Min जनिी कृजष 0.0304000(हक्े टेयर) 0.0304000
गावं का नाम: गुवानी
1 52//21/1 min जनिी कृजष 0.0304000(हक्े टेयर) 0.0304000
गावं का नाम: ननू ी कला(ं १७३)
1 35//25 Min जनिी कृजष 0.0025000(हक्े टेयर) 0.0025000
2 36//21 Min जनिी कृजष 0.0051000(हक्े टेयर) 0.0051000
3 38//19/2 Min जनिी कृजष 0.0202000(हक्े टेयर) 0.0202000
4 38//20/2 Min जनिी कृजष 0.0202000(हक्े टेयर) 0.0202000
5 38//4/1 Min जनिी कृजष 0.0076000(हक्े टेयर) 0.0076000
6 38//5/1 Min जनिी कृजष 0.0379000(हक्े टेयर) 0.0379000
7 39//25 Min जनिी कृजष 0.0202000(हक्े टेयर) 0.0202000
8 50//13/3 Min जनिी कृजष 0.0126000(हक्े टेयर) 0.0126000
9 50//14/2 Min जनिी कृजष 0.0354000(हक्े टेयर) 0.0354000
10 50//18/1 Min जनिी कृजष 0.0278000(हक्े टेयर) 0.0278000
11 50//19/1 Min जनिी कृजष 0.0152000(हक्े टेयर) 0.0152000[भाग II—खण् ड 3(ii)] भारत का रािपत्र : असाधारण 7
12 50//22/2/2 Min जनिी कृजष 0.0076000(हक्े टेयर) 0.0076000
13 50//7/3 Min जनिी कृजष 0.0076000(हक्े टेयर) 0.0076000
14 62//4/2 Min जनिी कृजष 0.0202000(हक्े टेयर) 0.0202000
15 62//5 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
16 62//7/1 Min जनिी कृजष 0.0228000(हक्े टेयर) 0.0228000
17 62//8/1/1 Min जनिी कृजष 0.0228000(हक्े टेयर) 0.0228000
गावं का नाम: जसहमा
1 104//15/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
2 104//16/1/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
3 104//25/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
4 104//6/2/2 Min जनिी कृजष 0.0126000(हक्े टेयर) 0.0126000
5 105//10/2/1 Min जनिी कृजष 0.0228000(हक्े टेयर) 0.0228000
6 105//11/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
7 105//20/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
8 105//21/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
9 106//1/2 Min जनिी कृजष 0.0152000(हक्े टेयर) 0.0152000
10 107//15/1/1 Min जनिी कृजष 0.0202000(हक्े टेयर) 0.0202000
11 107//5/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
12 107//6/1/2 Min जनिी कृजष 0.0202000(हक्े टेयर) 0.0202000
13 107//6/2/2 Min जनिी कृजष 0.0126000(हक्े टेयर) 0.0126000
14 43//1/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
15 43//10/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
16 43//11/1 min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
17 43//12/2/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
18 43//7/2/2 min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
19 43//9/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
20 65//12/2 min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
21 65//19/1/1 min जनिी कृजष 0.0152000(हक्े टेयर) 0.0152000
22 65//19/2/1 min जनिी कृजष 0.0152000(हक्े टेयर) 0.0152000
23 65//2/2 min जनिी कृजष 0.0303000(हक्े टेयर) 0.03030008 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
24 65//22/1/2 Min जनिी कृजष 0.0126000(हक्े टेयर) 0.0126000
25 65//22/2/2 Min जनिी कृजष 0.0202000(हक्े टेयर) 0.0202000
26 65//9/1 min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
27 82//16/2/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
28 82//25/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
29 82//5 Min जनिी कृजष 0.0051000(हक्े टेयर) 0.0051000
30 83//1/1 Min जनिी कृजष 0.0278000(हक्े टेयर) 0.0278000
31 83//12/1/2 Min जनिी कृजष 0.0126000(हक्े टेयर) 0.0126000
32 83//12/2/2 Min जनिी कृजष 0.0202000(हक्े टेयर) 0.0202000
33 83//19/2 Min जनिी कृजष 0.0304000(हक्े टेयर) 0.0304000
34 83//2/2 Min जनिी कृजष 0.0278000(हक्े टेयर) 0.0278000
35 83//21/2 Min जनिी कृजष 0.0051000(हक्े टेयर) 0.0051000
36 83//22/2 Min जनिी कृजष 0.0278000(हक्े टेयर) 0.0278000
37 83//9/1 Min जनिी कृजष 0.0304000(हक्े टेयर) 0.0304000
38 86//1/2 Min जनिी कृजष 0.0278000(हक्े टेयर) 0.0278000
39 86//10/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
40 86//11/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
41 86//2 Min जनिी कृजष 0.0051000(हक्े टेयर) 0.0051000
42 87//15/2/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
43 87//5/1/1 Min जनिी कृजष 0.0025000(हक्े टेयर) 0.0025000
44 87//5/2/1 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
45 87//6/2 Min जनिी कृजष 0.0303000(हक्े टेयर) 0.0303000
कुल 4.6513 4.6513
[फा. स.ं EC08/07/GF/3a6/3A1]
रािेि गुप् ता, जनदेिक
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
NOTIFICATION
New Delhi, the 12th April, 2021
S.O. 1557(E).—In exercise of powers conferred by sub-section (1) of section 3A of the National Highways
Act, 1956 (48 of 1956) (hereinafter referred to as the said Act), the Central Government, after being satisfied that for
the public purpose, the land, the brief description of which is given in the Schedule below, is required for building
(widening/four/Six laning etc.,), maintenance, management and operation of Greenfield alignment of Ismailabad[भाग II—खण् ड 3(ii)] भारत का रािपत्र : असाधारण 9
(Gangheri) - Narnaul national highway No. 152D in the stretch of land from Km. 185.800 to Km. 227.020 in the
district of Mahendergarh in the state of HARYANA, hereby declares its intention to acquire such land.
Any person interested in the said land may, within twenty-one days from the date of publication of this
notification in the Official Gazette, object to the use of such land for the aforesaid purpose under sub-section(1) of
section 3C of the said Act.
Every such objection shall be made to the Competent Authority, namely, District Revenue Officer,
Mahendragarh in writing and shall set out the grounds thereof and the Competent Authority shall give the objector an
opportunity of being heard, either in person or by a legal practitioner, and may, after hearing all such objections and
after making such further enquiry, if any, as the Competent Authority thinks necessary, by order, either allow or
disallow the objections.
Any order made by the Competent Authority under sub-section (2) of section 3C of the said Act shall be
final.
The land plans and other details of the land to be acquired under this notification are available and can be
inspected by the interested persons at the aforesaid office of the Competent Authority.
SCHEDULE
Brief Description of the land to be acquired with or without structures falling on Greenfield alignment of
Ismailabad (Gangheri) - Narnaul national highway no. 152D in the stretch of land from Km. 185.800 to
Km. 227.020 in the district of Mahendergarh in the state of HARYANA.
State: HARYANA District: Mahendergrah
Sl. No. Survey/Plot Number Type of Land Nature of Land Area Area
(in Local Unit) (in Hectare)
Taluk: Ateli
Village: Sagarpur
1 37//1/2 Min Private Agriculture 0.0202000(Hectare ) 0.0202000
2 37//10/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
3 37//11/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
Taluk: Kanina
Village: Bhagot
1 115//3/1/1 min Private Agriculture 0.0303000(Hectare ) 0.0303000
2 115//8/2/2 Min Private Agriculture 0.0278000(Hectare ) 0.0278000
3 65//6/2/2 Private Agriculture 0.0481000(Hectare ) 0.0481000
4 92//13/2/1 min Private Agriculture 0.0051000(Hectare ) 0.0051000
5 92//18/2/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
6 92//23/1/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
Village: Dongra Ahir
1 16//13/1/1 Min Private Agriculture 0.0202000(Hectare ) 0.0202000
2 16//13/2/1 Min Private Agriculture 0.0152000(Hectare ) 0.0152000
3 16//18/1/2 Min Private Agriculture 0.0051000(Hectare ) 0.0051000
4 16//18/2/2 Min Private Agriculture 0.0278000(Hectare ) 0.0278000
5 16//23/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
6 19//3/1 Min Private Agriculture 0.0278000(Hectare ) 0.027800010 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
7 19//8/1/2 Min Private Agriculture 0.0278000(Hectare ) 0.0278000
8 19//8/2/2 Min Private Agriculture 0.0076000(Hectare ) 0.0076000
Village: Kharkara Bass
1 166//11/2 min Private Agriculture 0.0303000(Hectare ) 0.0303000
2 166//20 Min Private Agriculture 0.0051000(Hectare ) 0.0051000
3 167//17/2 min Private Agriculture 0.0379000(Hectare ) 0.0379000
4 167//24/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
5 170//4/1 min Private Agriculture 0.0076000(Hectare ) 0.0076000
6 69//12/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
7 69//19 Min Private Agriculture 0.0051000(Hectare ) 0.0051000
8 69//9/1 min Private Agriculture 0.0278000(Hectare ) 0.0278000
9 95//14/1 min Private Agriculture 0.0278000(Hectare ) 0.0278000
10 95//17/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
11 95//19/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
12 95//24/1/2 Min Private Agriculture 0.0152000(Hectare ) 0.0152000
13 95//24/2/1 Min Private Agriculture 0.0228000(Hectare ) 0.0228000
Village: Kheri
1 101//13/1/2 Min Private Agriculture 0.0278000(Hectare ) 0.0278000
2 101//13/2 Min Private Agriculture 0.0051000(Hectare ) 0.0051000
3 101//3/2 Min Private Agriculture 0.0278000(Hectare ) 0.0278000
4 101//8/1/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
Village: Pathera
1 79//14/3 Min Private Agriculture 0.0126000(Hectare ) 0.0126000
2 79//15/1/2 Min Private Agriculture 0.0076000(Hectare ) 0.0076000
3 79//15/2/2 Min Private Agriculture 0.0126000(Hectare ) 0.0126000
4 79//5/2 min Private Agriculture 0.0278000(Hectare ) 0.0278000
5 79//6/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
Village: Pota
1 21//3/2 min Private Agriculture 0.0278000(Hectare ) 0.0278000
2 21//4/2 Min Private Agriculture 0.0025000(Hectare ) 0.0025000
3 29//10/1/1 min Private Agriculture 0.0076000(Hectare ) 0.0076000
4 29//10/2/1 Min Private Agriculture 0.0228000(Hectare ) 0.0228000
5 29//11 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
6 29//20/1/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
7 29//20/4/1 Min Private Agriculture 0.0025000(Hectare ) 0.0025000
8 30//1/3/2 min Private Agriculture 0.0303000(Hectare ) 0.0303000
9 30//10/1 min Private Agriculture 0.0152000(Hectare ) 0.0152000
10 30//10/4/1 Min Private Agriculture 0.0126000(Hectare ) 0.0126000
11 30//11/2 Min Private Agriculture 0.0152000(Hectare ) 0.0152000
12 30//20/1 Min Private Agriculture 0.0076000(Hectare ) 0.0076000
Taluk: Mahendergarh[भाग II—खण् ड 3(ii)] भारत का रािपत्र : असाधारण 11
Village: Akbarpur Nangal
1 25//8/1 Min Private Agriculture 0.0126000(Hectare ) 0.0126000
2 31//15/2/2 Min Private Agriculture 0.0228000(Hectare ) 0.0228000
3 31//16/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
4 31//25/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
5 32//11/1 Min Private Agriculture 0.0076000(Hectare ) 0.0076000
6 48//5 Min Private Agriculture 0.0051000(Hectare ) 0.0051000
7 53//21/2 Min Private Agriculture 0.0126000(Hectare ) 0.0126000
8 69//1/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
Village: Bhalkhi
1 100//4/1 Min Private Agriculture 0.0379000(Hectare ) 0.0379000
2 16//25/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
3 35//13/1/2 Min Private Agriculture 0.0278000(Hectare ) 0.0278000
4 35//14/2 Min Private Agriculture 0.0152000(Hectare ) 0.0152000
5 35//15/2 Min Private Agriculture 0.0051000(Hectare ) 0.0051000
6 35//16 Min Private Agriculture 0.0076000(Hectare ) 0.0076000
7 35//17/1 Min Private Agriculture 0.0556000(Hectare ) 0.0556000
8 35//18/1/2 Min Private Agriculture 0.0607000(Hectare ) 0.0607000
9 35//23/1 Min Private Agriculture 0.1442000(Hectare ) 0.1442000
10 35//24/2 Min Private Agriculture 0.0860000(Hectare ) 0.0860000
11 35//3/1 Min Private Agriculture 0.0152000(Hectare ) 0.0152000
12 35//5/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
13 35//6/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
14 40//13/1/2 Min Private Agriculture 0.0708000(Hectare ) 0.0708000
15 40//14/1/2 Min Private Agriculture 0.0759000(Hectare ) 0.0759000
16 40//14/2 Min Private Agriculture 0.1113000(Hectare ) 0.1113000
17 40//17/1 Min Private Agriculture 0.1720000(Hectare ) 0.1720000
18 40//24/1/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
19 40//24/1/2/1 Min Private Agriculture 0.0607000(Hectare ) 0.0607000
20 40//3/1 Min Private Agriculture 0.1568000(Hectare ) 0.1568000
21 40//3/2/1 Min Private Agriculture 0.0101000(Hectare ) 0.0101000
22 40//4/2 Min Private Agriculture 0.0910000(Hectare ) 0.0910000
23 40//7/1 Min Private Agriculture 0.1543000(Hectare ) 0.1543000
24 40//8/1/2 Min Private Agriculture 0.0253000(Hectare ) 0.0253000
25 40//8/2 Min Private Agriculture 0.0607000(Hectare ) 0.0607000
26 59//4 Min Private Agriculture 0.0076000(Hectare ) 0.0076000
27 97//24/2/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
Village: Bhuchawas
1 105//3/1 min Private Agriculture 0.0152000(Hectare ) 0.0152000
2 99//14 min Private Agriculture 0.0025000(Hectare ) 0.0025000
3 99//17/2 Min Private Agriculture 0.0303000(Hectare ) 0.030300012 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
Village: Khera
1 2//19/3/2 min Private Agriculture 0.0051000(Hectare ) 0.0051000
2 2//20/1/1 Min Private Agriculture 0.0126000(Hectare ) 0.0126000
3 2//20/2/1 Min Private Agriculture 0.0202000(Hectare ) 0.0202000
4 2//21/1/1 Min Private Agriculture 0.0076000(Hectare ) 0.0076000
5 2//21/2/1 Min Private Agriculture 0.0152000(Hectare ) 0.0152000
6 2//21/3/2 Min Private Agriculture 0.0076000(Hectare ) 0.0076000
7 5//1/1 min Private Agriculture 0.0228000(Hectare ) 0.0228000
8 6//5/1 min Private Agriculture 0.0076000(Hectare ) 0.0076000
Village: Surjanwas
1 8//14/2/2 min Private Agriculture 0.0228000(Hectare ) 0.0228000
2 8//15/1/1/2 Min Private Agriculture 0.0126000(Hectare ) 0.0126000
3 8//17/1/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
4 8//24/2 Min Private Agriculture 0.0051000(Hectare ) 0.0051000
Taluk: Narnaul
Village: Bargaon (165)
1 33//5 Private Agriculture 0.0025000(Hectare ) 0.0025000
2 39//2/1 Private Agriculture 0.0202000(Hectare ) 0.0202000
Village: Dublana(174)
1 12//11/2 Min Private Agriculture 0.0304000(Hectare ) 0.0304000
2 12//2/2/1 Min Private Agriculture 0.0304000(Hectare ) 0.0304000
3 12//20/1 Min Private Agriculture 0.0304000(Hectare ) 0.0304000
4 12//9/1 Min Private Agriculture 0.0304000(Hectare ) 0.0304000
Village: Guwani
1 52//21/1 min Private Agriculture 0.0304000(Hectare ) 0.0304000
Village: Nuni Kalan (173 )
1 35//25 Min Private Agriculture 0.0025000(Hectare ) 0.0025000
2 36//21 Min Private Agriculture 0.0051000(Hectare ) 0.0051000
3 38//19/2 Min Private Agriculture 0.0202000(Hectare ) 0.0202000
4 38//20/2 Min Private Agriculture 0.0202000(Hectare ) 0.0202000
5 38//4/1 Min Private Agriculture 0.0076000(Hectare ) 0.0076000
6 38//5/1 Min Private Agriculture 0.0379000(Hectare ) 0.0379000
7 39//25 Min Private Agriculture 0.0202000(Hectare ) 0.0202000
8 50//13/3 Min Private Agriculture 0.0126000(Hectare ) 0.0126000
9 50//14/2 Min Private Agriculture 0.0354000(Hectare ) 0.0354000
10 50//18/1 Min Private Agriculture 0.0278000(Hectare ) 0.0278000
11 50//19/1 Min Private Agriculture 0.0152000(Hectare ) 0.0152000
12 50//22/2/2 Min Private Agriculture 0.0076000(Hectare ) 0.0076000
13 50//7/3 Min Private Agriculture 0.0076000(Hectare ) 0.0076000
14 62//4/2 Min Private Agriculture 0.0202000(Hectare ) 0.0202000
15 62//5 Min Private Agriculture 0.0303000(Hectare ) 0.0303000[भाग II—खण् ड 3(ii)] भारत का रािपत्र : असाधारण 13
16 62//7/1 Min Private Agriculture 0.0228000(Hectare ) 0.0228000
17 62//8/1/1 Min Private Agriculture 0.0228000(Hectare ) 0.0228000
Village: Sihma
1 104//15/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
2 104//16/1/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
3 104//25/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
4 104//6/2/2 Min Private Agriculture 0.0126000(Hectare ) 0.0126000
5 105//10/2/1 Min Private Agriculture 0.0228000(Hectare ) 0.0228000
6 105//11/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
7 105//20/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
8 105//21/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
9 106//1/2 Min Private Agriculture 0.0152000(Hectare ) 0.0152000
10 107//15/1/1 Min Private Agriculture 0.0202000(Hectare ) 0.0202000
11 107//5/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
12 107//6/1/2 Min Private Agriculture 0.0202000(Hectare ) 0.0202000
13 107//6/2/2 Min Private Agriculture 0.0126000(Hectare ) 0.0126000
14 43//1/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
15 43//10/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
16 43//11/1 min Private Agriculture 0.0303000(Hectare ) 0.0303000
17 43//12/2/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
18 43//7/2/2 min Private Agriculture 0.0303000(Hectare ) 0.0303000
19 43//9/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
20 65//12/2 min Private Agriculture 0.0303000(Hectare ) 0.0303000
21 65//19/1/1 min Private Agriculture 0.0152000(Hectare ) 0.0152000
22 65//19/2/1 min Private Agriculture 0.0152000(Hectare ) 0.0152000
23 65//2/2 min Private Agriculture 0.0303000(Hectare ) 0.0303000
24 65//22/1/2 Min Private Agriculture 0.0126000(Hectare ) 0.0126000
25 65//22/2/2 Min Private Agriculture 0.0202000(Hectare ) 0.0202000
26 65//9/1 min Private Agriculture 0.0303000(Hectare ) 0.0303000
27 82//16/2/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
28 82//25/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
29 82//5 Min Private Agriculture 0.0051000(Hectare ) 0.0051000
30 83//1/1 Min Private Agriculture 0.0278000(Hectare ) 0.0278000
31 83//12/1/2 Min Private Agriculture 0.0126000(Hectare ) 0.0126000
32 83//12/2/2 Min Private Agriculture 0.0202000(Hectare ) 0.0202000
33 83//19/2 Min Private Agriculture 0.0304000(Hectare ) 0.0304000
34 83//2/2 Min Private Agriculture 0.0278000(Hectare ) 0.0278000
35 83//21/2 Min Private Agriculture 0.0051000(Hectare ) 0.0051000
36 83//22/2 Min Private Agriculture 0.0278000(Hectare ) 0.0278000
37 83//9/1 Min Private Agriculture 0.0304000(Hectare ) 0.0304000
38 86//1/2 Min Private Agriculture 0.0278000(Hectare ) 0.027800014 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
39 86//10/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
40 86//11/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
41 86//2 Min Private Agriculture 0.0051000(Hectare ) 0.0051000
42 87//15/2/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
43 87//5/1/1 Min Private Agriculture 0.0025000(Hectare ) 0.0025000
44 87//5/2/1 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
45 87//6/2 Min Private Agriculture 0.0303000(Hectare ) 0.0303000
Total 4.6513 4.6513
[F. No. EC08/07/GF/3a6/3A1]
RAJESH GUPTA, Director
uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.