Date: 2025-04-11Category: Extra OrdinaryState: Union GovernmentCountry: India
Publishing Corrigendum for Construction of new Road Over Bridge in lieu of Level Crossing No409 at Km 597/17 19 at Dwarapudi yard with 2.50m Road Under Bridge
## Policy Analysis Report: Corrigendum to Railway Infrastructure Project in Andhra Pradesh
**1. Executive Summary:**
This report analyzes a corrigendum issued by the Ministry of Railways, South Central Railways, regarding a project for the Construction of Road Over Bridge in lieu of Level Crossings in the District of Dr.B.R.Ambedkar Konaseema, in the State of Andhra Pradesh. The corrigendum, published on April 4th, 2025, clarifies a clause related to the power under which the project is notified and amends the geographical scope of the project by replacing the District of East Godavari with the District of Dr.B.R.Ambedkar Konaseema. This change seems crucial for the accurate implementation of the railway infrastructure project and land acquisition.
**2. Introduction:**
This report provides an analysis of a corrigendum (S.O. 1697E) to a previously published notification by the Ministry of Railways concerning a railway infrastructure project in Andhra Pradesh. The analysis is based solely on the text provided in the official notification.
**3. Policy Overview:**
* **Amendment to:** S.O. 4156E, published September 23rd, 2024, concerning the Construction of Road Over Bridge in lieu of Level Crossings in the District of Dr.B.R.Ambedkar Konaseema, in the State of Andhra Pradesh.
* **Core Objective(s) (as inferred from the text):** To facilitate the construction of a new Road Over Bridge in lieu of Level Crossing No. 409 at Km. 5971719 at Dwarapudi yard with 2.50m Road Under Bridge, designating it as a Special Railway Project for land acquisition in the designated district of Andhra Pradesh and to provide National Infrastructure for a public purpose.
**4. Background and Rationale:**
The document is a *corrigendum*. This suggests an error or omission in the original notification (S.O. 4156E) that needs to be rectified. The primary reason for this specific amendment is to correct a discrepancy in the district where the land acquisition for the project will take place. The change indicates a shift in the project's focus from land acquisition in the District of East Godavari to the District of Dr.B.R.Ambedkar Konaseema, potentially due to updated project plans or an initial error in specifying the correct district.
**5. Key Provisions / Changes:**
This document is a *corrigendum* meaning that the changes included are amendments to the original policy. The provided text shows the following:
* **Specific Part of Original Policy Changed:** The location where land acquisition is to occur.
* **New Rule/Provision:** The land acquisition for the project, previously identified as taking place in the District of East Godavari, will *instead* occur in the District of Dr.B.R.Ambedkar Konaseema.
* **Difference/Effect of Change:** The change directly impacts landowners and stakeholders in the District of Dr.B.R.Ambedkar Konaseema, as they are now the affected parties for land acquisition under this project. It also suggests a possible realignment of the project's physical scope within the region.
**6. Target Audience and Stakeholders:**
The primary target audience and stakeholders directly affected by this corrigendum are:
* Landowners and residents in the **District of Dr.B.R.Ambedkar Konaseema** (Andhra Pradesh) where land acquisition is planned for the road over bridge project.
* The Ministry of Railways and its associated departments responsible for project implementation.
* Construction companies and contractors involved in the infrastructure project.
* Local authorities and government bodies in the District of Dr.B.R.Ambedkar Konaseema responsible for facilitating land acquisition and project approvals.
**7. Implementation Aspects (Inferred):**
* **Responsible agency/bodies mentioned:** Ministry of Railways, South Central Railways, Chief EngineerCRSP.
* **Any timelines or procedures specified in the text:** The corrigendum is effective from the date of publication in the Official Gazette (April 11, 2025).
* **Implementation Aspects related specifically to the changes:** The primary implementation aspect is the shift in the geographical focus of the land acquisition process. All subsequent land acquisition activities must now be conducted within the District of Dr.B.R.Ambedkar Konaseema, adhering to the Railways Act, 1989.
**8. Expected Outcomes / Impact of Changes:**
The likely intended outcome of this specific change is to ensure accurate and legally sound land acquisition for the railway project. The impact of the amendment is:
* **Corrected Scope:** Ensures the project proceeds with land acquisition in the correct district, preventing legal challenges and delays.
* **Focused Impact:** Concentrates the project's direct impact (land acquisition, construction disruption) on the District of Dr.B.R.Ambedkar Konaseema.
* **Potential Delays:** Depending on the timing of the change, there is potential for some delays in the land acquisition process as the focus shifts to a different geographical area.
**9. Conclusion:**
The corrigendum S.O. 1697E is a critical amendment to the original notification regarding the railway infrastructure project in Andhra Pradesh. It rectifies an error concerning the district where land acquisition will occur, shifting the focus from the District of East Godavari to the District of Dr.B.R.Ambedkar Konaseema. This correction is essential for the project's legal validity and successful implementation. Stakeholders in the District of Dr.B.R.Ambedkar Konaseema should be aware of this change and its potential impact.
Key Entities Referenced
S.O. 1697E: Notification of the Government of India, Ministry of Railways regarding Construction of Road Over Bridge.
Ministry of Railways: Government organization responsible for railways.
Gazette of India: Official government publication.
Part II, Section 3, Subsection ii: Section of the Gazette of India.
23rd September 2024: Date of the notification in the Gazette of India.
S.O. 4156E: Notification number related to Construction of Road Over Bridge.
Dr.B.R.Ambedkar Konaseema: District in Andhra Pradesh.
State of Andhra Pradesh: State in India.
Section 2: Section of the Railways Act, 1989.
Railways Act, 1989: Legislation related to railways in India.
Level Crossing No. 409: Identifies a specific railway level crossing.
2.50m: Measurement related to Road Under Bridge.
Special Railway Project: Designation for the Construction of Road Over Bridge.
Official Gazette: Official government publication.
National Infrastructure: Infrastructure related to the Road Over Bridge project.
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
सी.जी.-टी.एल.-अ.-11042025-262408
CG-TLxx-xEG-I1D1H0x4x2x0 25-262408
xxxGIDExxx
असाधारण
EXTRAORDINARY
भाग II—खण् ड 3—उप-खण्ड (ii)
PART II—Section 3—Sub-section (ii)
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 1666] नई ददल्ली, िुक्रवार, अप्रलै 11, 2025/चत्रै 21, 1947
No. 1666] NEW DELHI, FRIDAY, APRIL 11, 2025/CHAITRA 21, 1947
रेल मत्रं ालय
(दजिण मध्य रेलव)े
िजु िपत्र
जसकंदराबाद, 4 अप्रैल, 2025
का.आ. 1697(अ).—भारत सरकार, रेल मंत्रालय की अजधसूचना, िो एस.ओ. 4156(अ) के अतं गतग भारत के
रािपत्र, असाधारण, भाग II, धारा 3, उपधारा (ii) ददनांदकत 23 जसतंबर 2024 को “आंध्र प्रदिे राज्य के
डॉ.बी.आर.अम्बेडकर कोनसीमा जिला म ें जस्ट्ित समपार फाटक के स्ट्िान पर ऊपरी पैदल पलु का जनमागण” के संबंध म ें
प्रकाजित हुई िी, म ेंरेल मंत्रालय एतद्द्वारा जनम्नजलजखत िुजिपची तैयार करता ह,ै जिसका जववरण नीच े ददया गया ह:ै
क्र.स.ं इस रूप म ेंप्रकाजित इस प्रकार पढा िाए
1 केंद्र सरकार, रेलव े अजधजनयम, 1989 के एस.ओ. केंद्र सरकार, रेलवे अजधजनयम, 1989 के एस.ओ.
4156(अ) के अंतगगत धारा 2 के खंड (37 क) , 4156(अ) के अतं गतग धारा 2 के खडं (37 क),
ददनांदकत 23 जसतंबर 2024 द्वारा प्रदत्त िजियों का ददनांदकत 23 जसतंबर 2024 द्वारा प्रदत्त िजियों
प्रयोग करत े हुए, एतद्वारा, “2.50मी. जनचला सड़क का प्रयोग करते हुए, एतद्वारा, “2.50मी. जनचला
पुल सजहत द्वारपुजड याड ग पर 597/17-19 दक.मी. पर सड़क पुल सजहत द्वारपुजड याडग पर 597/17-19
जस्ट्ित समपार फाटक सं. 409 के स्ट्िान पर नया ऊपरी दक.मी. पर जस्ट्ित समपार फाटक स.ं 409 के स्ट्िान
2487 GI/2025 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
पैदल पलु के जनमागण” को िन प्रयोिन हते ु राष्ट्रीय पर नया ऊपरी पैदल पलु के जनमागण” को िन
अवसंरचना प्रदान करने के जलए आंध्र प्रदेि राज्य के प्रयोिन हते ुराष्ट्रीय अवसंरचना प्रदान करने के जलए
पूवग गोदावरी जिला में भूजम अजधग्रहण हते ु आंध्र प्रदिे राज्य के डॉ.बी.आर.अम्बेडकर
आजधकाररक रािपत्र म ेंइस अजधसूचना के प्रकािन की कोनसीमा जिला म ें भूजम अजधग्रहण हते ु
तारीख स े एक जविेष रेल पररयोिना के रूप म ें आजधकाररक रािपत्र म ेंइस अजधसूचना के प्रकािन
अजधसूजचत करती ह.ै की तारीख स े एक जविेष रेल पररयोिना के रूप म ें
अजधसूजचत करती ह.ै
[फा. स.ं RSP/SC/Gazette /37A/LC.409 /BZA -VSKP/BZA/Corrigendum/01]
मनोि कुमार, मुख्य इंिीजनयर/जन /आरएसपी
MINISTRY OF RAILWAYS
(South Central Railways)
CORRIGENDUM
Secunderabad, the 4th April, 2025
S.O. 1697(E).— In the notification of the Government of India, Ministry of Railways published in the Gazette
of India, Extraordinary, Part II, Section 3, Sub-section (ii) Dated 23rd September 2024 vide S.O. 4156(E) regarding
“Construction of Road Over Bridge in lieu of Level Crossings in the District of Dr.B.R.Ambedkar Konaseema, in the
of State of Andhra Pradesh” the Ministry of Railways hereby makes the following corrigendum as detailed below:
Sl.No. Published as To be read as
1 In exercise of the powers conferred by clause (37A) In exercise of the powers conferred by clause
of Section 2 dated 23rd September 2024 vide (37A) of Section 2 dated 23rd September 2024 vide
S.O. 4156(E) of the Railways Act, 1989 the Central S.O. 4156(E) of the Railways Act, 1989 the
Government hereby notifies “Construction of new Central Government hereby notifies “Construction
Road Over Bridge in lieu of Level Crossing No. 409 of new Road Over Bridge in lieu of Level Crossing
at Km. 597/17-19 at Dwarapudi yard with 2.50m No. 409 at Km. 597/17-19 at Dwarapudi yard with
Road Under Bridge" as a Special Railway Project for 2.50m Road Under Bridge" as a Special Railway
acquisition of land in the State of Andhra Pradesh in Project for acquisition of land in the State of
the District of East Godavari for providing National Andhra Pradesh in the District of
Infrastructure for a public purpose with effect from Dr.B.R.Ambedkar Konaseema for providing
the date of publication of this notification in the National Infrastructure for a public purpose with
Official Gazette. effect from the date of publication of this
notification in the Official Gazette.
[F. No. RSP/SC/Gazette /37A/LC.409 /BZA -VSKP/BZA/Corrigendum/01]
MANOJ KUMAR, Chief Engineer/C/RSP
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.