Parliament Question: Pirpainti–Jasidih New Rail Line Project

Issued by Ministry of Railways · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF RAILWAYS LOK SABHA UNSTARRED QUESTION NO. 3934 TO BE ANSWERED ON 12.08.2026 PIRPAINTI–JASIDIH NEW RAIL LINE PROJECT †3934. SHRI AJAY KUMAR MANDAL: Will the Minister of RAILWAYS be pleased to state: (a) the details of the total number of ongoing and pending railway projects in the State of Bihar till May 2026 along with their sanctioned cost, expenditure incurred till date including completed railway sections; (b) the details of the current progress of new railway line construction, track doubling/third line works and the redevelopment of 92 stations selected under the Amrit Bharat Station Scheme in Bihar under recent budget allocations; and (c) the details of the sanctioned cost, expenditure incurred so far including the length of track constructed and the target completion date for 100% completion of the Pirpainti-Jasidih new railway line project? ANSWER MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND ELECTRONICS & INFORMATION TECHNOLOGY (SHRI ASHWINI VAISHNAW) (a) to (c): Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure projects falling fully/partly in the Bihar is as under:- Period Outlay 2009-14 ₹1,132 Cr./year 2026-27 ₹10,379 Cr. (More than 9 times) Track construction: The details of commissioning/laying of new track falling fully/partly in the State of Bihar is as under:- § Page 1 of 10Period New Track Average Commissioning of new Commissioned tracks 2009-14 318 Km 63.6 Km/year 2014-26 2,034 Km 169.5 Km/year (More than 2.5 times) Projects sanctioned: As on 01.04.2026, 59 projects (32 New Lines, 01 Gauge Conversions and 26 Doubling), covering a total length of 5,067 km, costing ₹96,651 crore, falling fully/partly in Bihar are sanctioned. The summary is as under:- Category No of Total Length Total Exp upto sanction Length Commissione Mar'26 ed (in Km) d till Mar'26 (₹ in Cr) Projects (in Km) New Lines 32 2,616 533 14,806 Gauge 1 69 52 544 Conversion Doubling/Mult 26 2,382 465 14,509 i-tracking Total 59 5,067 1,050 29,860 Recently completed projects: Details of some of the recently completed projects falling fully/partly in Bihar are as under:- SN. Project Cost (In Crores of Rs) 1 Patna bridge (28 Km) 3,310 Page 2 of 102 Munger rail cum road Bridge (15 Km) 3,040 3 Kosi Bridge (22 Km) 863 4 Daniawan-Biharsharif new line (38 Km) 354 5 Chandan-Banka new line (40 Km) 496 6 Rampurhat-Mandarhill new line (130 Km) 908 7 Maharajganj-Masrakh new line (35 Km) 412 8 Rajgir-Tilaiya & Natesar-lslampur new line (67 726 Km) 9 Jaynagar-Narkatiaganj gauge conversion (260 967 Km) 10 Kaptanganj-Chhapra gauge conversion (234 819 Km) 11 Sakri-Nirmali, Saharasa-Forbesganj gauge 2,113 conversion (206 Km) 12 Mansi-Saharsa, Saharsa-Purnia, Banmakhi- 752 Bihariganj gauge conversion (169 Km) 13 Sahibganj-Pirpainti doubling (23 Km) 129 14 Maheshkunt-Thanabihpur doubling (32 Km) 115 15 Hajipur-Ramdayalu Nagar doubling (48 Km) 367 16 Pirpainti-Bhagalpur doubling (51 Km) 493 17 Kiul-Gaya doubling (124 Km) 2,462 18 Hajipur-Bachwara doubling (72 Km) 930 19 Araria-Galgalia (Thakurganj) new line (110 Km) 2,132 20 Samastipur-Darbhanga Doubling (38 Km) 874 Ongoing projects: Some of the projects falling fully/partly in the State of Bihar which have been taken up are as under: Page 3 of 10SN. Project Cost (Rs. in Cr.) 1 Sakri-Hasanpur new line (76 Km) 802 2 Fatuha-lslampur new line (167 Km) 3,158 3 Koderma-Tilaiya new line (65 Km) 2,287 4 Hajipur-Sagauli new line (151 Km) 2,820 5 Araria-Supaul new line (96 Km) 2,170 6 Kursela-Bihariganj new line (58 Km) 194 7 Pirpainti-Jassidih new line (97 Km) 2,700 8 Chhitauni-Tumkuhi Road new line (59 Km) 1,881 9 Jalalgarh-Kishanganj new line (51 Km) 407 10 Sitamarhi-Nirmali new line (189 Km) 2,833 11 Bihta-Aurangabad new line (120 Km) 3,606 12 Gaya-Chatra and Gaya-Natesar new line (135 4,543 Km) 13 Sultanganj-Katuria new line (77 Km) 291 14 Jaynagar-Bijalpura Gauge conversion (69 Km) 900 15 Dhanbad-Sonnagar 3rd line (291 Km) 7,906 16 Sagauli-Valmikinagar Doubling (110 Km) 1,456 17 Muzaffarpur-Sugauli Doubling (101 Km) 1,745 18 Barauni-Bachwara 3rd & 4th line (32 Km) 486 19 Narkatiaganj-Darbhanga, Sitamarhi-Muzaffarpur 4,080 doubling (256 Km) 20 Chhapra-Ballia Patch Doubling (65 Km) 1,046 21 Katihar-Kumedpur and Katihar-Mukuria Doubling 943 (65 Km) 22 Son Nagar-Andal Multitracking (749 Km) 12,334 Page 4 of 1023 Punarakh- Bhaktiyarpur New 4th line & balance 422 3rd line (28 Km) 24 Aluabari Road-Thakurganj Doubling (20 Km) 327 25 Bhagalpur-Jamalpur 3rd line (53 Km) 1,156 26 Bhagalpur-Dumka-Rampurhat doubling (177 Km) 3,169 27 Bakhtiyarpur-Rajgir-Tilaiya doubling (104 Km) 2,192 28 Bakthiyarpur-Fatuha 3rd and 4th line (24 Km) 931 29 Punarakh-Kiul 3rd and 4th line (50 Km) 2,668 30 Kiul-Jhajha 3rd Line (54 Km) 962 31 Mansi-Saharsa doubling (44 Km) 499 Zonal Railway wise details of Railway projects are made available in public domain on Indian Railway’s website. Pirpainti-Jasidih new line (97 km) Pirpainti-Jasidih new line (97 km) has been sanctioned at a cost of ₹2700 Cr. Expenditure of ₹1697 Cr has been incurred in this project and ₹270 Cr has been allocated in FY 2026-27. 38 Km out of 97 km has been commissioned. Works have been taken up in balance sections.  338 Ha out of 613 Ha land acquisition has been completed and balance land acquisition taken up.  03 major bridges out of 31 have been completed. Work on balance bridges have been taken up.  45 minor bridges out of 119 have been completed. Work on balance bridges have been taken up.  25 ROBs out of 37 have been completed. Work on balance ROBs have been taken up.  02 RUBs out of 39 have been completed. Work on balance RUBs have been taken up. Page 5 of 10 38 Km track linking out of 97 Km has been completed. Work on balance track has been taken up. Completion of Railway projects/s depends on various factors which include the following:  Land acquisition by State Government  Forest clearance  Shifting of infringing utilities  Statutory clearances from various authorities  Geological and topographical conditions of area  Law and order situation in the area of project site  Number of working months in a year for particular project site etc. All these factors affect the completion time and cost of the project/s. Station Redevelopment: Ministry of Railways has launched Amrit Bharat Station Scheme for redevelopment of stations with a long-term approach. The scheme involves preparation of master plans and their implementation in phases to improve the stations of Indian Railways. The master planning, keeping in view the necessity of each station, includes:  Improvement of access to station and circulating areas  Integration of station with both sides of city  Improvement of station building  Improvement of waiting halls, toilets, sitting arrangement, water booths  Provision of wider foot over bridge/subway to commensurate with passenger traffic  Provision of lifts/escalators/ramps  Improvement of platform surface/ provision of platform shelter Page 6 of 10 Provision of kiosks for local products through schemes like 'One Station One Product'  Parking development  Amenities for Divyangjans  Better passenger information systems  Provision of air concourse, executive lounges, Multimodal integration, landscaping, etc. The scheme also envisages sustainable and environment friendly solutions etc. as per necessity, phasing and feasibility and creation of city centre at the station in the long term. So far, 1,340 stations have been identified for development under this scheme, out of which 98 stations are located in Bihar. The names of stations identified for development under Amrit Bharat Station Scheme in Bihar are as following: State No. of Name of Stations Stations Bihar 98 Anugraha Narayan Road, Ara, Arariya Court, Bakhtiyarpur, Banka, Banmankhi, Bapudham Motihari, Barahiya, Barauni, Barh, Barsoi Jn, Begusarai, Bettiah, Bhabua Road, Bhagalpur, Bhagwanpur, Bihar Sharif, Bihiya, Bikramganj, Buxar, Chakia, Chausa, Chhapra, Dalsingh Sarai, Darbhanga, Dauram Madhepura, Dehri On Sone, Dholi, Dighwara, Dumraon, Durgauti, Ekma, Fatuha, Gaya, Ghorasahan, Guraru, Hajipur Jn, Jamalpur Jn, Jamui, Janakpur Road, Jaynagar, Jehanabad, Jhanjharpur, Kahalgaon, Karhagola Road, Katihar Jn, Page 7 of 10Khagaria Jn, Kishanganj, Kudra, Labha, Laheria Sarai, Lakhminia, Luckeesarai Jn, Madhubani, Maheshkhunt, Mairwa, Mansi Jn, Masrakh, Mokama, Motipur, Munger (Monghyr), Muzaffarpur Jn, Nabinagar Road, Narkatiaganj Jn, Naugachia, Nawadah, Paharpur, Patliputra, Patna Jn, Piro, Pirpainti, Rafiganj, Raghunathpur., Rajendra Nagar Terminal (Patna), Rajgir, Ram Dayalu Nagar, Raxaul, Sabaur, Sagauli, Saharsa, Sahibpur Kamal, Sakri, Salauna, Salmari, Samastipur, Sasaram, Shahpur Patoree, Shivanarayanpur, Simri Bakhtiyarpur, Simultala, Sitamarhi, Siwan, Sonpur Jn., Sultanganj, Supaul, Taregna, Thakurganj, Thawe Completed stations: Development works at railway stations under Amrit Bharat Station Scheme in Bihar have been taken up at a good pace. Details of stations completed in Bihar are as under: State No. of Name of Stations Stations Bihar 08 Banmankhi, Dauram Madhepura, Kahalgaon, Pirpainti, Sabaur, Shivanarayanpur, Simultala, Thawe Page 8 of 10The activities for development at other stations have also been taken up at good pace and progress of some of the stations is as given below:  Saharsa station: The works of new main entry station building, parking, improvement to circulating area, platform shelter, entrance gate and boundary wall have been completed. The work of 12 m wide foot over bridge has been taken up.  Salauna station: The works of new main entry station building, platform shelter, improvement of circulating area, entrance gate and boundary wall have been completed. The work of 12 m wide foot over bridge has been taken up.  Sonpur station: The works of new atrium building, booking counter, improvement of station building, improvement of circulating area, parking and entrance porch have been completed. The work of 12 m wide foot over bridge has been taken up.  Anugraha Narayan Road station: The works of extension of platform no. 1/2 & 3/4, improvement of platform surface of platform no. 1/2 & 3/4 and new toilet block have been completed. The works of improvement of station building, improvement of circulating area, entry/exit gate, water booths, platform shelter and 6 m wide foot over bridge have been taken up.  Luckeesarai Junction station: The works of new main entry station building, extension of foot over bridge and improvement of circulating area have been completed. The work of lift for existing foot over bridge has been taken up. Further, development/ redevelopment/ upgradation/ modernisation of stations on Indian Railways is a continuous and ongoing process and works in this regard are undertaken as per requirement, subject to inter-se priority and availability of funds. Development/ redevelopment / upgradation/ Page 9 of 10modernisation of a station is carried out based on category of station/ condition/ traffic handled etc. Development/upgradation/modernisation of stations including under Amrit Bharat Station Scheme is generally funded under Plan Head-53 'Customer Amenities'. The details of allocation and expenditure under Plan Head-53 are maintained Zonal Railway- wise and not station-wise or state-wise. Bihar is covered under the jurisdiction of four railway zones, namely, Eastern Railway, East Central Railway, North Eastern Railway and Northeast Frontier Railway. For these zones, an allocation of ₹1,543 crore has been made for the current financial year, out of which an expenditure (up to June, 2026) of ₹677 crore has been incurred so far. Development/Upgradation of railway stations is a complex in nature involving safety of passengers & trains and requires various statutory clearances such as tree cutting, heritage, fire clearance, airport clearance etc. These stations are in operation since long, so brownfield work challenges are being faced, such as shifting of utilities (involving water/sewage lines, optical fibre cables, gas pipelines, power/signal cables, etc.), infringements, operation of trains without hindering passenger movement, speed restrictions due to works carried out in close proximity of the tracks and near to high voltage power lines, etc. and these factors affect the progress of work and completion time. ***** Page 10 of 10

Continue your research