GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 3934
TO BE ANSWERED ON 12.08.2026
PIRPAINTI–JASIDIH NEW RAIL LINE PROJECT
†3934. SHRI AJAY KUMAR MANDAL:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the total number of ongoing and pending railway projects
in the State of Bihar till May 2026 along with their sanctioned cost,
expenditure incurred till date including completed railway sections;
(b) the details of the current progress of new railway line construction,
track doubling/third line works and the redevelopment of 92 stations
selected under the Amrit Bharat Station Scheme in Bihar under recent
budget allocations; and
(c) the details of the sanctioned cost, expenditure incurred so far including
the length of track constructed and the target completion date for
100% completion of the Pirpainti-Jasidih new railway line project?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): Budget allocation in the recent years has increased significantly.
Budget allocation for infrastructure projects falling fully/partly in the Bihar
is as under:-
Period Outlay
2009-14 ₹1,132 Cr./year
2026-27 ₹10,379 Cr. (More than 9 times)
Track construction:
The details of commissioning/laying of new track falling fully/partly in the
State of Bihar is as under:-
§ Page 1 of 10Period New Track Average Commissioning of new
Commissioned tracks
2009-14 318 Km 63.6 Km/year
2014-26 2,034 Km 169.5 Km/year (More than 2.5 times)
Projects sanctioned:
As on 01.04.2026, 59 projects (32 New Lines, 01 Gauge Conversions and 26
Doubling), covering a total length of 5,067 km, costing ₹96,651 crore,
falling fully/partly in Bihar are sanctioned. The summary is as under:-
Category No of Total Length Total Exp upto
sanction Length Commissione Mar'26
ed (in Km) d till Mar'26 (₹ in Cr)
Projects (in Km)
New Lines 32 2,616 533 14,806
Gauge 1 69 52 544
Conversion
Doubling/Mult 26 2,382 465 14,509
i-tracking
Total 59 5,067 1,050 29,860
Recently completed projects:
Details of some of the recently completed projects falling fully/partly in
Bihar are as under:-
SN. Project Cost
(In Crores of
Rs)
1 Patna bridge (28 Km) 3,310
Page 2 of 102 Munger rail cum road Bridge (15 Km) 3,040
3 Kosi Bridge (22 Km) 863
4 Daniawan-Biharsharif new line (38 Km) 354
5 Chandan-Banka new line (40 Km) 496
6 Rampurhat-Mandarhill new line (130 Km) 908
7 Maharajganj-Masrakh new line (35 Km) 412
8 Rajgir-Tilaiya & Natesar-lslampur new line (67 726
Km)
9 Jaynagar-Narkatiaganj gauge conversion (260 967
Km)
10 Kaptanganj-Chhapra gauge conversion (234 819
Km)
11 Sakri-Nirmali, Saharasa-Forbesganj gauge 2,113
conversion (206 Km)
12 Mansi-Saharsa, Saharsa-Purnia, Banmakhi- 752
Bihariganj gauge conversion (169 Km)
13 Sahibganj-Pirpainti doubling (23 Km) 129
14 Maheshkunt-Thanabihpur doubling (32 Km) 115
15 Hajipur-Ramdayalu Nagar doubling (48 Km) 367
16 Pirpainti-Bhagalpur doubling (51 Km) 493
17 Kiul-Gaya doubling (124 Km) 2,462
18 Hajipur-Bachwara doubling (72 Km) 930
19 Araria-Galgalia (Thakurganj) new line (110 Km) 2,132
20 Samastipur-Darbhanga Doubling (38 Km) 874
Ongoing projects:
Some of the projects falling fully/partly in the State of Bihar which have
been taken up are as under:
Page 3 of 10SN. Project Cost (Rs.
in Cr.)
1 Sakri-Hasanpur new line (76 Km) 802
2 Fatuha-lslampur new line (167 Km) 3,158
3 Koderma-Tilaiya new line (65 Km) 2,287
4 Hajipur-Sagauli new line (151 Km) 2,820
5 Araria-Supaul new line (96 Km) 2,170
6 Kursela-Bihariganj new line (58 Km) 194
7 Pirpainti-Jassidih new line (97 Km) 2,700
8 Chhitauni-Tumkuhi Road new line (59 Km) 1,881
9 Jalalgarh-Kishanganj new line (51 Km) 407
10 Sitamarhi-Nirmali new line (189 Km) 2,833
11 Bihta-Aurangabad new line (120 Km) 3,606
12 Gaya-Chatra and Gaya-Natesar new line (135 4,543
Km)
13 Sultanganj-Katuria new line (77 Km) 291
14 Jaynagar-Bijalpura Gauge conversion (69 Km) 900
15 Dhanbad-Sonnagar 3rd line (291 Km) 7,906
16 Sagauli-Valmikinagar Doubling (110 Km) 1,456
17 Muzaffarpur-Sugauli Doubling (101 Km) 1,745
18 Barauni-Bachwara 3rd & 4th line (32 Km) 486
19 Narkatiaganj-Darbhanga, Sitamarhi-Muzaffarpur 4,080
doubling (256 Km)
20 Chhapra-Ballia Patch Doubling (65 Km) 1,046
21 Katihar-Kumedpur and Katihar-Mukuria Doubling 943
(65 Km)
22 Son Nagar-Andal Multitracking (749 Km) 12,334
Page 4 of 1023 Punarakh- Bhaktiyarpur New 4th line & balance 422
3rd line (28 Km)
24 Aluabari Road-Thakurganj Doubling (20 Km) 327
25 Bhagalpur-Jamalpur 3rd line (53 Km) 1,156
26 Bhagalpur-Dumka-Rampurhat doubling (177 Km) 3,169
27 Bakhtiyarpur-Rajgir-Tilaiya doubling (104 Km) 2,192
28 Bakthiyarpur-Fatuha 3rd and 4th line (24 Km) 931
29 Punarakh-Kiul 3rd and 4th line (50 Km) 2,668
30 Kiul-Jhajha 3rd Line (54 Km) 962
31 Mansi-Saharsa doubling (44 Km) 499
Zonal Railway wise details of Railway projects are made available in public
domain on Indian Railway’s website.
Pirpainti-Jasidih new line (97 km)
Pirpainti-Jasidih new line (97 km) has been sanctioned at a cost of ₹2700
Cr. Expenditure of ₹1697 Cr has been incurred in this project and ₹270 Cr
has been allocated in FY 2026-27. 38 Km out of 97 km has been
commissioned. Works have been taken up in balance sections.
338 Ha out of 613 Ha land acquisition has been completed and
balance land acquisition taken up.
03 major bridges out of 31 have been completed. Work on balance
bridges have been taken up.
45 minor bridges out of 119 have been completed. Work on balance
bridges have been taken up.
25 ROBs out of 37 have been completed. Work on balance ROBs have
been taken up.
02 RUBs out of 39 have been completed. Work on balance RUBs have
been taken up.
Page 5 of 10 38 Km track linking out of 97 Km has been completed. Work on
balance track has been taken up.
Completion of Railway projects/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
Station Redevelopment:
Ministry of Railways has launched Amrit Bharat Station Scheme for
redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their implementation
in phases to improve the stations of Indian Railways. The master planning,
keeping in view the necessity of each station, includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water booths
Provision of wider foot over bridge/subway to commensurate with
passenger traffic
Provision of lifts/escalators/ramps
Improvement of platform surface/ provision of platform shelter
Page 6 of 10 Provision of kiosks for local products through schemes like 'One Station
One Product'
Parking development
Amenities for Divyangjans
Better passenger information systems
Provision of air concourse, executive lounges, Multimodal integration,
landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions
etc. as per necessity, phasing and feasibility and creation of city centre at
the station in the long term.
So far, 1,340 stations have been identified for development under this
scheme, out of which 98 stations are located in Bihar. The names of
stations identified for development under Amrit Bharat Station Scheme in
Bihar are as following:
State No. of Name of Stations
Stations
Bihar 98 Anugraha Narayan Road, Ara, Arariya Court,
Bakhtiyarpur, Banka, Banmankhi, Bapudham
Motihari, Barahiya, Barauni, Barh, Barsoi Jn,
Begusarai, Bettiah, Bhabua Road, Bhagalpur,
Bhagwanpur, Bihar Sharif, Bihiya, Bikramganj,
Buxar, Chakia, Chausa, Chhapra, Dalsingh
Sarai, Darbhanga, Dauram Madhepura, Dehri
On Sone, Dholi, Dighwara, Dumraon, Durgauti,
Ekma, Fatuha, Gaya, Ghorasahan, Guraru,
Hajipur Jn, Jamalpur Jn, Jamui, Janakpur
Road, Jaynagar, Jehanabad, Jhanjharpur,
Kahalgaon, Karhagola Road, Katihar Jn,
Page 7 of 10Khagaria Jn, Kishanganj, Kudra, Labha,
Laheria Sarai, Lakhminia, Luckeesarai Jn,
Madhubani, Maheshkhunt, Mairwa, Mansi Jn,
Masrakh, Mokama, Motipur, Munger (Monghyr),
Muzaffarpur Jn, Nabinagar Road, Narkatiaganj
Jn, Naugachia, Nawadah, Paharpur, Patliputra,
Patna Jn, Piro, Pirpainti, Rafiganj,
Raghunathpur., Rajendra Nagar Terminal
(Patna), Rajgir, Ram Dayalu Nagar, Raxaul,
Sabaur, Sagauli, Saharsa, Sahibpur Kamal,
Sakri, Salauna, Salmari, Samastipur, Sasaram,
Shahpur Patoree, Shivanarayanpur, Simri
Bakhtiyarpur, Simultala, Sitamarhi, Siwan,
Sonpur Jn., Sultanganj, Supaul, Taregna,
Thakurganj, Thawe
Completed stations:
Development works at railway stations under Amrit Bharat Station Scheme
in Bihar have been taken up at a good pace. Details of stations completed
in Bihar are as under:
State No. of Name of Stations
Stations
Bihar 08 Banmankhi, Dauram Madhepura, Kahalgaon,
Pirpainti, Sabaur, Shivanarayanpur,
Simultala, Thawe
Page 8 of 10The activities for development at other stations have also been taken up at
good pace and progress of some of the stations is as given below:
Saharsa station: The works of new main entry station building,
parking, improvement to circulating area, platform shelter, entrance
gate and boundary wall have been completed. The work of 12 m wide
foot over bridge has been taken up.
Salauna station: The works of new main entry station building,
platform shelter, improvement of circulating area, entrance gate and
boundary wall have been completed. The work of 12 m wide foot over
bridge has been taken up.
Sonpur station: The works of new atrium building, booking counter,
improvement of station building, improvement of circulating area,
parking and entrance porch have been completed. The work of 12 m
wide foot over bridge has been taken up.
Anugraha Narayan Road station: The works of extension of platform
no. 1/2 & 3/4, improvement of platform surface of platform no. 1/2 & 3/4
and new toilet block have been completed. The works of improvement
of station building, improvement of circulating area, entry/exit gate,
water booths, platform shelter and 6 m wide foot over bridge have been
taken up.
Luckeesarai Junction station: The works of new main entry station
building, extension of foot over bridge and improvement of circulating
area have been completed. The work of lift for existing foot over bridge
has been taken up.
Further, development/ redevelopment/ upgradation/ modernisation of
stations on Indian Railways is a continuous and ongoing process and works
in this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. Development/ redevelopment / upgradation/
Page 9 of 10modernisation of a station is carried out based on category of station/
condition/ traffic handled etc.
Development/upgradation/modernisation of stations including under Amrit
Bharat Station Scheme is generally funded under Plan Head-53 'Customer
Amenities'. The details of allocation and expenditure under Plan Head-53
are maintained Zonal Railway- wise and not station-wise or state-wise.
Bihar is covered under the jurisdiction of four railway zones, namely,
Eastern Railway, East Central Railway, North Eastern Railway and
Northeast Frontier Railway. For these zones, an allocation of ₹1,543 crore
has been made for the current financial year, out of which an expenditure
(up to June, 2026) of ₹677 crore has been incurred so far.
Development/Upgradation of railway stations is a complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as tree cutting, heritage, fire clearance, airport clearance
etc. These stations are in operation since long, so brownfield work
challenges are being faced, such as shifting of utilities (involving
water/sewage lines, optical fibre cables, gas pipelines, power/signal
cables, etc.), infringements, operation of trains without hindering
passenger movement, speed restrictions due to works carried out in close
proximity of the tracks and near to high voltage power lines, etc. and these
factors affect the progress of work and completion time.
*****