See Full Document Text
Report of the Joint Working Group (JWG) on Issues related to
EoDB in Indian Upstream Sector
Report of the Joint Working Group
(JWG) on Issues related to EoDB in
Indian Upstream Sector
Interim Report
M inistry of Petroleum and Natural Gas,
Government of India
April 2025
1 | PageReport of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Page intentionally left blank.
2Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Preface
The Ministry of Petroleum and Natural Gas (MoPNG) constituted this Joint Working Group
(JWG) to assess and address issues affecting the EoDB in the upstream oil and gas
sector. The working group, comprising representatives from key E&P operators and
government, has reviewed and examined eighty three (83) unique issues submitted by
the operators over the course of several deliberative meetings. Based on our assessment,
sixteen (16) issues have been identified as addressable through policy guidelines
within the jurisdiction of the MoPNG.
The JWG has formulated a set of recommendations, aiming to enhance Ease of Doing
Business for E&P industry and ultimately reducing import dependency through necessary
policy and regulatory interventions.
These recommendations, finalized by the JWG after deliberations on 06thFebruary, 2025,
are expected to streamline and simplify existing E&P processes and introduce new
policies or guidelines that can boost investors’ confidence in the Indian hydrocarbon
sector.
We, the undersigned, Members of the JWG submit the report on this 12day ofApril, 2025.
_______________ _______________ _______________ _______________
Shri Praveen M.Khanooja Shri Vinod Seshan Shri Akash Goyal Shri Pankaj Kumar
Additional Secretary, JS (Expl.), MoPNG ADG (Coordination), DGH Director (P),
MoPNG Member Secretary Member ONGC
Chairperson & Convenor Member
_______________ _______________ ___________________ _ ______________
Shri Saloma Yomdo Shri Pankaj Kalra Shri Manish Maheshwari Shri Kapil Garg
Director (E&D), OIL CEO, EOGEPL Chairman and CEO CMD, Oilmax
Member Member Invenire Energy Energy Pvt Ltd
Member Member
____________________ _________________ _______________
Shri Avinash K. Pathak Shri Padam Singh Shri Rakesh Agiwal
Senior Vice President, RIL President, SunPetro Ltd CPRO, Vedanta Ltd
Member Member Member
3Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Table of Contents
1. Executive Summary 11
2. Introduction 16
2.1. Indian E&P Sector Regulatory Framework — Contractual
Regimes 17
2.1.1. Nomination Based Regime 17
2.1.2. Production Sharing Contracts (PSCs) 18
2.1.3. Revenue Sharing Contracts (RSCs) 24
2.1.4. Unconventional Hydrocarbons in India 29
2.2. Role of Key Stakeholders 30
2.3. Ease of Doing Business in the E&P Sector 31
2.4. E&P Sector Performance 32
2.5. E&P sector Outlook 37
2.6. Joint Working Group (JWG) 39
3. Issues submitted by E&P operators 40
4. Initiatives adopted by DGH to elevate EODB in the
Hydrocarbon sector 43
5. Analysis and Recommendations 45
Part A: Issues resolvable within the jurisdiction of MoPNG 45
5.1. Approval for delivery point(s) within and outside the contract
area 46
5.2. Grant of Excusable Delays/ Extra Days for delays in
government related approvals 48
5.3. Reduction in contract area and work programme, due to denial
or delay in statutory clearances for exploratory activities 52
5.4. Bank Guarantee (BG) renewal towards Committed/Minimum/
Bid Work Programme 56
5.5. Field Development Plan (FDP) approvals of PSC blocks 59
4Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.6. Grant of Extension in Exploration/Development Period across
contractual regimes 63
5.7. Process for PSC extension applications and approvals 65
5.8. Provisions for incentives on sale of natural gas to private
operators in Northeast region 66
5.9. Transfer of Participating Interest (PI) among existing PI holders
under a contract 67
5.10. Annual Work Programme (AWP) and Budget approval under
CBM regime 69
5.11. Flexibility to deploy new exploration technology/ methods for
meeting Minimum, Committed or Bid Work Programme 70
5.12. Flexibility to swap exploration activities across contracts
within the same or higher category basin 73
5.13. Field Handover process in DSF contracts 74
5.14. Exchange rate conversion methodology across contract
regimes 76
5.15. Open-Source National Data Repository (NDR) 78
5.16. Collaborative resource-sharing among operators in E&P sector
79
Part B: Issues to be resolved with cross-ministerial support 81
6. Annexures 84
5Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
List of Figures
Figure 1: Import Dependency of Crude oil and Natural Gas in India for the last 10 years
(%) ............................................................................................................................... 16
Figure 2: Evolution of the India's E&P Contractual regime ........................................... 17
Figure 3: Current status of blocks awarded under nomination regime .......................... 18
Figure 4: Pre-NELP Exploration Blocks awarded ......................................................... 19
Figure 5: Current status of blocks awarded under Pre-NELP exploration rounds ......... 19
Figure 6: Pre-NELP Discovered Field or Development Rounds ................................... 20
Figure 7: Current status of blocks awarded under Pre-NELP discovered field rounds .. 21
Figure 8: NELP Bid Rounds ......................................................................................... 22
Figure 9: Major Policy Reforms for PSCs ..................................................................... 23
Figure 10: Current status of blocks awarded under NELP rounds ................................ 23
Figure 11: OALP Bid Round details ............................................................................. 25
Figure 12: Current Status of blocks awarded under OALP rounds ............................... 25
Figure 13: DSF Round-wise contract areas awarded and active .................................. 26
Figure 14: Current Status of blocks awarded under DSF contract regime .................... 27
Figure 15: Comparative analysis of contractual regimes in India ................................. 28
Figure 16: Salient Features of NDR .................................................................................
Figure 17: Regime-wise Crude Oil Production in India for the last 20 years (MMT) ..... 32
Figure 18: Share of PSU and Private Companies for Crude Oil Production ................. 33
Figure 19: Regime- wise Natural Gas Production in India for the last 20 years (BCM) . 34
Figure 20: Share of PSU and Private Companies in Gas Production ........................... 35
Figure 21: Regime-wise total number of wells drilled, and discoveries made ............... 36
Figure 22: Regime-wise number of sick, non-flowing and flowing wells ....................... 37
Figure 23: Natural gas production forecast for the next decade (BCM) ........................ 38
Figure 24: Crude oil production forecast for the next decade (MMT) ............................ 38
6Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
List of Tables
Table 1 List of issues addressed by JWG .................................................................... 12
Table 2 Summary of policy actions undertaken by MoPNG and DGH .......................... 13
Table 3: Approving authorities for major E&P processes across regimes .................... 30
7Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
List of Abbreviations
Abbreviation Explanation Abbreviation Explanation
2D Two Dimensional Coastal Regulation
CRZ
Zone
3D Three Dimensional
Cyclic Steam
CSS
Airborne Gravity Stimulation
AGG
Gradiometry
Committed Work
CWP
AI Artificial Intelligence Programme
Acquisition Processing Directorate General of
API DGH
and Interpretation Hydrocarbons
Administered Pricing Directorate General of
APM DGMS
Mechanism Mines Safety
Adani Welspun District Level
AWEL DLC
Exploration Limited Committee
Annual Work Department for
AWP
Programme DPIIT Promotion of Industry
and Internal Trade
Annual Work
AWP&B Programme and Darwin Platform
DPRL
Budget Refineries Limited
BCM Billion Cubic Meters DSF Discovered Small Field
BG Bank Guarantee Decision Support
DSS
System
bp British Petroleum
Exploration and
BP Exploration E&P
BPEAL Production
(Alpha) Limited
EC Environment Clearance
Bharat Petroleum
BPRL
Resources Limited Excusable Days/ Extra
ED
Days
BWP Bid Work Programme
Essar oil and Gas
Compensatory
CA EOGEPL Exploration and
Afforestation
Production Limited
CAPEX Capital Expenditure
EOI Expression of Interest
CBM Coal Bed Methane
Central Empowered EOR Enhanced Oil Recovery
CEC
Committee
EPU Early Production Unit
CG Corporate Guarantee
ERD Extended Reach Drilling
CGD City Gas Distribution ESZ Eco-Sensitive Zone
Financial Benchmarks
FBIL
Central Mine Planning India Private Limited
CMPDI
and Design Institute
FC Forest Clearance
Contract Management
CMS
System
FCA Forest Conservation Act
Compressed Natural
CNG
Gas Foreign Direct
FDI
Investment
Cost of Unfinished
COUWP
Work Programme FDP Field Development Plan
8Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Abbreviation Explanation Abbreviation Explanation
Foreign Investment Megha Engineering &
FIPB MEIL
Promotion Board Infrastructures Limited
FRA Forest Rights Act ML Mining Lease
FSI Forest Survey of India ML Machine Learning
Great Eastern Energy Metric Million British
GEECL MMBTU
Corporation Limited Thermal Unit
General Financial Mines and Minerals
GFR
Rules MMDR (Development and
Regulation)
Good International
GIPIP Petroleum Industry Minimum Miscibility
MMP
Practices Pressure
GN Guidance Note MMT Million Metric Tonnes
GoI Government of India Ministry of
MoEFCC Environment, Forest
Gujarat State
GSPC and Climate Change
Petroleum Corporation
MoF Ministry of Finance
Goods and Services
GST
Tax Ministry of Home
MoHA
Affairs
GTE Global Tender Enquiry
MoM Ministry of Mines
Hydrocarbon
HELP Exploration Licensing Ministry of Petroleum
MoPNG
Policy and Natural Gas
Hindustan Oil Ministry of Tribal
HOEC MoTA
Exploration Limited Affairs
High Pressure, High Minimum Work
HPHT MWP
temperature Programme
HRP High Revenue Point National Agriculture
NAIFF
Infra Financing Facility
HSD High Speed Diesel
Non-Associated
Initial Exploration NANG
IEP Natural Gas
Period
National Data
International Financial NDR
IFRS Repository
Reporting Standards
New Exploration
Indian oil Corporation NELP
IOCL Licensing Policy
Limited
National Investment
Invenire Petrodyne
IPL NIIF and Infrastructure
Limited
Fund
ITC Input Tax Credit
NIO Notice Inviting Offers
JV Joint Venture
NOC National Oil Company
JWG Joint Working Group
NPV Net Present Value
LD Liquidated Damages
Non-Resident Taxable
LIBOR London Interbank NRTP Persons
Offered Rate
Open Acreages
LKM Line Kilometer OALP Licensing Policy
LRP Lower Revenue Point OC Operating Committee
Management Operating Committee
MC Committee OCR Resolution
9Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Abbreviation Explanation Abbreviation Explanation
Original Equipment SC Steering Committee
OEM
Manufacturer
SCBM Special CBM
Oilmax Energy Private
OEPL Standing Committee
Limited
SC-NBWL for National Board of
OIL Oil India Limited Wildlife
Oil Industry Safety Shanti GD Ispat and
OISD SHANTIGD
Directorate Power Private Limited
Oil and Natural Gas SKM Square Kilometer
ONGC
Corporation
Secured Overnight
SOFR
OPEX Operating Expenditure Financing Rate
Petroleum and Natural Standardized
P&NG
Gas SoP Operating
PA Protected Area Procedure
Pollution Control Single Point of
PCB SPOC
Board Contact
Petroleum Exploration Technical Assessment
PEL TAR
Licenses Report
Petroleum and TCF Trillion Cubic Feet
PESO Explosives Safety
Tax Deducted at
Organisation TDS
Source
PI Participating Interest
TOR Terms of Reference
Production-linked
PLP United Nations
Payment
UNDP Development
Petroleum Mining Programme
PML
Lease
UOP Unit of Production
Petroleum and Natural
PNGRB USD US Dollars
Gas Regulatory Board
United States
Petroleum Planning & USGS
PPAC Geological Survey
Analysis Cell
VAT Value Added Tax
Production Sharing
PSC WLS Wildlife Sanctuary
Contract
PSC Management
PSCMS
System
QPU Quick Production Unit
Research and
R&D
Development
RBI Reserve Bank of India
Revised Field
RFDP
Development Plan
Reliance Industries
RIL
Limited
Ramayana Ispat
RIPL
Private Limited
Revenue Sharing
RSC
Contract
Special Additional
AED
Excise Duty
10Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
1. Executive Summary
India’s Exploration and Production (E&P) sector has undergone a significant
transformation over the years, driven by the nation’s rising energy demand, its strategic
objective of reducing import dependence, and its broader economic growth ambitions. As
one of the world’s fastest-growing economies and the third-largest energy consumer,
India’s reliance on oil and gas is expected to increase in the foreseeable future. To meet
this demand, the government has introduced various policies to enhance domestic
production, attract private and foreign investment, foster technological innovation, and
ensure long-term energy security.
In this regard, the Government of India has undertaken a series of policy and fiscal
interventions aimed at improving the investment climate in the upstream oil and gas
sector. Notwithstanding these efforts, regulatory and operational challenges continue to
hinder the sector’s full potential. Recognizing these concerns, the government remains
committed to foster a more conducive environment for hydrocarbon sector by addressing
critical bottlenecks that affect the ease of doing business (EoDB) in the sector.
In pursuance of this objective, and with a view to address industries concerns, the Ministry
of Petroleum and Natural Gas (MoPNG) constituted a Joint Working Group (JWG) to
examine critical issues affecting EoDB in India’s E&P sector. The JWG was mandated to
identify key challenges faced by operators, analyze the causes of delays in obtaining
statutory clearances, and explore opportunities for process simplification.
Additionally, the JWG was tasked to assess the feasibility of introducing self-certification
mechanisms within existing contractual frameworks and develop targeted
recommendations to streamline regulatory procedures.
Overview of issues addressed by JWG
A total of eighty-three (83) unique issues were submitted for consideration by various
stakeholders. These were subsequently categorized based on the nature of the issue—
procedural, self-certification-related, fiscal, financial, or other—and mapped to the
relevant ministry or authority, including MoPNG, the Directorate General of Hydrocarbons
(DGH), the Ministry of Environment, Forest and Climate Change (MoEFCC), the Ministry
of Defence (MoD), the Ministry of Finance (MoF) among others.
Additionally, the issues were classified based on their anticipated resolution timeframe,
encompassing immediate (within six months), short-term (less than one year), medium-
term (one to two years), and long-term (beyond two years) interventions.
Following deliberations and assessment, sixteen (16) issues were identified as
resolvable through policy guidelines under the jurisdiction of MoPNG. These
include matters related to delivery point approvals, statutory clearances, bank
guarantees, and the extension of development periods, among others.
A list of issues addressed by the JWG is presented in the table below.
11Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Table 1 List of issues addressed by JWG
S.No. Areas of concern
1 Approval for delivery point(s) within and outside the contract area
2 Grant of Excusable Delays/ Extra Days for delays in government related approvals
3 Reduction in contract area and work programme, due to denial or delay in statutory
clearances for exploratory activities
4 Bank Guarantee (BG) renewal towards unfinished Work Programme
5 Field Development Plan (FDP) approvals of PSC blocks
6 Grant of Extension in Exploration/Development Period across contractual regimes
7 Process for PSC extension applications and approvals
8 Provisions for incentives on sale of natural gas to private operators in Northeast region
9 Transfer of Participating Interest (PI) among existing PI holders under a contract
10 Annual Work Programme (AWP) and Budget approval under CBM regime
11 Flexibility to deploy new exploration technology/ methods for meeting Minimum,
Committed or Bid Work Programme
12 Flexibility to swap exploration activities across contracts within the same or higher
category basin
13 Field handover process in DSF contracts
14 Exchange rate conversion methodology across contracts regimes
15 Open-Source National Data Repository (NDR)
16 Collaborative resource-sharing among operators in E&P sector
The JWG has formulated a set of recommendations for submission to the competent
authority, aiming to facilitate further examination within the framework of existing
contractual provisions and enable necessary policy and regulatory actions. A detailed
account of these recommendations is provided in Chapter 5 of this report.
Ongoing policy actions undertaken by MoPNG and DGH
Following discussions with the stakeholders, the MoPNG and the DGH have actioned on
several fronts, with various policy initiatives and guidelines that have already been
implemented. Additionally, several measures are under implementation stage and are
being actively pursued to further improve the EODB in the upstream hydrocarbon sector.
A summary of the policy actions undertaken or being pursued are providing in the table
below.
12Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Table 2 Summary of policy actions undertaken by MoPNG and DGH
S.no. Area of concern Policy action
• For OALP Blocks:
1 Grant of Excusable Delays/
Extra Days for delays in • From OALP-VIII onwards, the scope of
government-related excusable delays has been expanded to
approvals include all necessary permits, approvals, and
clearances.
• Additionally, a 120-day approval period has
been introduced, along with an exit option
without liquidated damages (LD) if statutory
clearances are delayed beyond two years.
• A proposal is under consideration to extend
these provisions to OALP-I to VII contracts.
• For DSF Blocks:
• From An exit clause for statutory and other
clearances beyond two years has been
applicable since DSF-III. A proposal is under
consideration to extend this provision to DSF-
I and II contracts.
• Currently, extra days in lieu of environmental
and forest clearances (EC & FC) are not
available for DSF-III onwards. A proposal is
under consideration to introduce this
provision for DSF-III, Special DSF, and future
DSF rounds.
2 Grant of extension in • For OALP Blocks:
exploration/development
period across regimes • A two-year paid extension in the Initial
Exploration Period (IEP) is proposed for
OALP-I to III blocks.
• Paid extensions of up to 8-10 years are
proposed for Category-II & III basins in
OALP-IV to VII blocks.
• A two-year paid extension for Category-I
basins in OALP-IV onwards is under
consideration.
• Extensions for blocks in the Northeast region
and Andaman Basin are proposed to have
discounted terms compared to other regions.
• For DSF Blocks:
• A one-year paid extension in the
development period has been applicable
from DSF-III onwards. A proposal is under
13Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.no. Area of concern Policy action
consideration to extend this provision to DSF-
I and II rounds
3 Standardization of exchange • A proposal is under consideration to standardize
rate conversion methodology the exchange rate conversion methodology
across contracts across all OALP blocks awarded from OALP-I to
VII, aligning them with the provisions applicable
from OALP-VIII onwards.
• Under the proposed framework, contractors shall
remit royalty, the government’s share of revenue,
and any other contractual dues in Indian Rupees
(INR).
• Currency conversion between USD and INR (or
any other currency) will be based on the
RBI/FBIL/RBI-authorized agency’s reference
exchange rate on the date of remittance
Beyond these measures, DGH has undertaken several strategic initiatives to enhance
the efficiency and attractiveness of India's upstream sector. Key measures include
upgrading digital platforms such as the National Data Repository (NDR) for improved data
accessibility, launching Mission Anveshan to conduct extensive seismic surveys across
unexplored basins, and approving the drilling of stratigraphic wells to enhance subsurface
geological understanding. Additionally, DGH is implementing an Integrated Management
System (IMS) to streamline stakeholder engagement, while the newly established
Hydrocarbon Efficiency & New Energy (HENE) department focuses on emissions
monitoring, CCUS, and renewable energy integration. Through initiatives such as DGH
UrjaVarta, targeted technical workshops on regulatory clearances and academic
collaborations, DGH continues to drive EODB in India’s upstream hydrocarbon sector.
Institution of a Mechanism for addressing Cross-ministerial
concerns
Beyond the sixteen priority issues identified under the purview of MoPNG, several
additional challenges require coordinated efforts across multiple ministries and state
governments for effective resolution.
Key among these challenges are the streamlining of statutory approvals, such as forest
clearance (FC) and environmental clearance (EC), as well as tax incentives to stimulate
upstream investment. As these issues fall under the jurisdiction of multiple regulatory
authorities, their resolution requires a structured and collaborative approach across
government agencies.
To address this, JWG has proposed broadening its scope to involve representatives from
state governments and other relevant ministries in a formal mechanism to address these
issues and further advance efforts for Ease of Doing Business.
14Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
The recommendations put forth by the JWG emphasizes the need for targeted policy
interventions to improve the operational efficiency and competitiveness of India’s
upstream oil and gas sector.
While the immediate and short-term measures identified within the purview of MoPNG
are expected to ease regulatory constraints, broader structural challenges necessitate
sustained inter-ministerial collaboration for policy alignment and regulatory streamlining.
The establishment of the proposed Joint Standing Committee will be instrumental in
fostering ongoing dialogue, accelerating decision-making, and creating an investment-
friendly environment for upstream activities. Collectively, these reforms will enhance
India’s attractiveness as a destination for upstream investment, support the sustainable
development of domestic hydrocarbon resources, and contribute meaningfully to the
nation’s overarching objective of energy security and self-reliance.
15Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
2. Introduction
India’s Exploration and Production (E&P) regime has undergone a remarkable
transformation over the past decades, reflecting the country’s growing energy needs, its
ambition for self-reliance in energy, and its drive for economic development. As one of
the world’s fastest-growing economies and the third-largest consumer of energy, India’s
demand for oil and gas is expected to continue rising.
However, as the world’s third-largest importer and consumer of oil, India remains
significantly dependent on crude oil imports to meet its growing energy needs, driven by
a growing population and rapid industrialization. This reliance on imported oil and gas
has a significant impact on the country’s economy, increasing foreign exchange outflows
and contributing to a trade deficit. This dependency also exposes the country to
fluctuations in global oil prices, which can lead to inflation. Furthermore, it creates
strategic risks amid geopolitical tensions and potential supply disruptions.
The figure below illustrates the trend of crude oil and natural gas import dependency in
India over the past decade.
Figure 1: Import Dependency of Crude oil and Natural Gas in India for the last 10
years (%)
78.3% 80.6% 81.7% 82.9% 83.8% 85.0% 84.4% 85.5% 87.3% 87.7% 88.1%
52.8% 54.3% 51.5%
44.5% 45.3% 47.3% 48.4% 43.9% 46.4%
40.7%
36.2%
2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 2024-25
Crude Oil Import Dependency Natural Gas Import Dependency
Source – DGH, status as on 31 December 2024
The figure above illustrates India's import dependency for crude oil and natural gas over
the past decade. In FY 2014-15, crude oil import dependency was 78.3%, while natural
gas import dependency stood at 36.2%. Currently, approximately 88% of India’s crude oil
consumption is met through imports. Meanwhile, over the last ten years, natural gas
import dependency has steadily risen from 36% to 51%, indicating an increasing reliance
on imports to meet domestic demand.
To address the growing dependency on oil and gas imports, the nation has recognized
the need to bolster its domestic production capabilities. This realization has driven
significant changes in the country’s exploration and production (E&P) contractual regimes
over the years.
16Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
2.1. Indian E&P Sector Regulatory Framework — Contractual
Regimes
India’s E&P sector has evolved through various contractual regimes, each reflecting the
country’s strategic priorities and regulatory framework. Initially, Petroleum Exploration
Licenses (PELs) were granted on a nomination basis to the NOCs, marking a period of
foundational development from 1960 to 1980. The introduction of Production Sharing
Contracts (PSCs) marked a significant shift, attracting foreign investment while
maintaining sovereign control over natural resources. Recently, the sector has
transitioned to Revenue Sharing Contracts (RSCs), reflecting policy reforms aimed at
enhancing transparency, efficiency, and competitiveness. The evolution of the India’s
E&P contractual regime is illustrated in the figure below:
Figure 2: Evolution of the India's E&P Contractual regime
2.1.1. Nomination Based Regime
India's hydrocarbons upstream sector between 1960 and 1980 marked a period
characterized by the strong presence and control of national entities. During this era, the
landscape of India’s hydrocarbon exploration was dominated by two NOCs —ONGC and
OIL. The GoI granted PEL to these companies on a nomination basis, placing them at
the forefront of the country's exploration and production efforts.
This nomination-based regime ensured that ONGC and OIL held the core responsibility
for exploration and production activities, reinforcing the government's emphasis on self-
17Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
reliance and energy security. Private sector participation remained limited, as the focus
was on building the capacity of the NOCs and maximizing domestic production.
By the late 1970s, India's E&P sector had made significant progress, although largely
driven state entities. However, the sector faced significant constraints in terms of
technology, expertise, and investment capital. Deeper offshore exploration required
advanced drilling technologies and significant financial resources, both of which were in
limited supply. The current status of the blocks under nomination regime is illustrated in
the figure below.
Figure 3:Current status of blocks awarded under nomination regime
Source –DGH, status as on 01 April 2024
Recognizing these limitations, the Indian government made a strategic decision in 1979
to open the country’s hydrocarbons E&P sector to attract foreign investment and
collaboration. This led to the launch of the Pre-New Exploration Licensing Policy (Pre-
NELP) rounds, governed by Production Sharing Contracts (PSCs).
2.1.2. Production Sharing Contracts (PSCs)
Production Sharing Contracts (PSCs) represented a pivotal shift in the exploration and
production framework, designed to attract foreign investment while maintaining sovereign
control over natural resources. Under a PSC, the government grants an exploration
license to a contractor who assumes the full risk and cost of exploration. If commercial
quantities of hydrocarbons are discovered, the contractor is permitted to recover its costs
from a share of the production. Once cost recovery is complete, the remaining output is
divided between the government and the contractor according to a predetermined
formula.
This model aligns with the interests of both the government and the contractor, ensuring
that the state secures a share of the production while incentivizing companies to explore
and develop hydrocarbon resources. PSCs became a widely adopted mechanism in
many developing countries, including India and were first introduced under Pre-NELP
exploration and discovered field rounds, which brought upon changes in the fiscal system.
1.1.2.1 Pre-NELP Exploration Rounds
The period leading up to the introduction of the NELP marked India's initial steps towards
liberalizing its oil and gas exploration sector and encouraging private sector participation.
18Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Between 1980 and the launch of NELP, 28 exploration blocks were awarded to private
companies. While private companies were granted exploration rights during this phase,
state-owned entities ONGC and OIL retained strategic rights to participate in the blocks
if hydrocarbons were discovered. This arrangement reflected the government's strategy
of balancing private sector expertise and capital with the need to maintain control over
critical hydrocarbon discoveries.
The exploration blocks awarded under Pre-NELP are illustrated in the figure below.
Figure 4: Pre-NELP Exploration Blocks awarded
11Blocks
9Blocks
5
5Blocks 6
3 2Blocks
6
1Block
3 1
2
1 1
1980 1991 1993 1994 1995
Source – DGH
The current status of blocks awarded under Pre-NELP exploration rounds are provided
in the figure below.
Figure 5: Current status of blocks awarded under Pre-NELP exploration rounds
Source – DGH, status as on 31 December 2024
1.1.2.2 Pre-NELP Discovered Field or Development Rounds
In the early 1990s, India made a notable move to increase private sector involvement in
its upstream oil and gas sector by introducing the Pre-NELP Discovered Field Rounds.
19
skcolB
fo
rebmuN
Offshore OnshoreReport of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
This marked a strategic shift in the country’s E&P policy, with the government aiming to
attract private capital and expertise to accelerate the development of small to medium-
sized fields, where proven reserves had already been identified by the NOCs. In 1992,
the PML for these discovered fields were offered to the private sector, opening new
avenues for private operators to contribute to India's hydrocarbon production.
The PSCs awarded during this period, from 1991 to 1993, were distinctive. Private
companies were appointed as operators, but ONGC and OIL retained significant
participating interests. This structure allowed the NOCs to remain integral to the
development process while leveraging the technological capabilities and operational
efficiencies brought in by private players.
The response to the bidding rounds launched under Pre-NELP regime was highly
positive, attracting considerable interest from both domestic and international E&P
operators. These rounds led to the signing of 28 contracts covering 29 discovered fields,
including the high-profile PSC for the Panna-Mukta field.
The contracts signed under Pre-NELP discovered field or development round are
illustrated in the figure below.
Figure 6: Pre-NELP Discovered Field or Development Rounds
18
10
1992 1993
Source – DGH
The current status of blocks awarded under Pre-NELP discovered field rounds is
illustrated in the figure below
20
dengiS
stcartnoC
fo
rebmuNReport of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Figure 7: Current status of blocks awarded under Pre-NELP discovered field
rounds
Source – DGH, status as on 31 December 2024
1.1.2.3 New Exploration Licensing Policy (NELP)
The introduction of the New Exploration Licensing Policy (NELP) in 1997, operationalized
in 1999, marked a defining moment in the evolution of India's E&P sector. Until then, the
sector had been predominantly controlled by state-owned NOCs. NELP aimed to attract
both domestic and foreign investment through a more transparent and competitive
bidding process for exploration blocks. For the first time, the policy allowed 100% Foreign
Direct Investment (FDI) in the oil and gas exploration sector, encouraging international
oil companies to participate, and promoting greater transparency and efficiency in E&P
activities.
The launch of NELP in 1997, represented a fundamental shift in India's approach to
managing its hydrocarbon resources. It promoted competition, reduced direct
government control over the E&P sector, and fostered technological advancement
through foreign company participation.
The NELP regime was implemented in a series of nine bidding rounds, starting with
NELP-I in 1999 and concluding with NELP-IX in 2012. Over the course of these nine
rounds, a total of 254 exploration blocks contracts were signed, covering both onshore
and offshore regions, including deep-water areas. The bidding rounds attracted
considerable interest from both domestic and international companies, leading to a
significant increase in exploration activities in India’s underexplored basins.
The number of contracts signed under NELP rounds are illustrated in the figure below.
21Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Figure 8: NELP Bid Rounds
52
41
32
24 23 23
20 20 19
3 4 3 4 6 5 5
1 1
NELP-I NELP-II NELP-III NELP-IV NELP-V NELP-VI NELP-VII NELP-VIII NELP-IX
(1999) (2000) (2002) (2003) (2005) (2006) (2007) (2009) (2010)
Source – DGH
Key outcomes of NELP rounds include:
1. Increased Exploration Activity: NELP significantly increased the level of
exploration activity in India. By the end of the ninth round, exploration under NELP
covered nearly 48% of India’s sedimentary basin area, a considerable
improvement compared to the Pre-NELP era. NELP also facilitated the discovery
of several key hydrocarbon fields, particularly in the deep-water areas of the KG
Basin, the Cauvery Basin, and the Rajasthan onshore.
2. Increased Private Sector Participation: NELP successfully attracted private and
foreign investment into India’s E&P sector. Major international companies such as
British Gas, Cairn Energy, Eni, BHP Billiton, and bp participated in the NELP
bidding rounds, bringing advanced exploration technologies and capital into
India’s upstream industry.
3. Challenges and Limitations: Despite its successes, NELP rounds had its
challenges. One of the major issues was the delays in obtaining clearances,
including environmental and regulatory approvals, which often resulted in
significant project delays. Additionally, disputes over cost recovery under the PSC
regime led to disagreements between contractors and the government, with both
parties interpreting the contracts differently.
Recognizing the need to improve the Ease of Doing Business in the sector, the GoI
introduced a series of policy reforms and incentives aimed at addressing these
inefficiencies. The figure below illustrates major policy reforms and initiatives undertaken
by GoI to improve PSC framework.
22
dengiS
CSP
fo
rebmuN
PSC Signed Active BlocksReport of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Figure 9:Major Policy Reforms for PSCs
Source –DGH
These policies made considerable progress in addressing operational bottlenecks and
providing clarity to contractors and have also contributing towards significant investments
in the country. The current status of blocks awarded under NELP rounds is illustrated in
the figure below.
Figure 10:Current status of blocks awarded under NELP rounds
Source –DGH, status as on 31 December 2024
23Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Despite the relative success of NELP rounds and policy reforms, the government felt the
need to introduce further reforms to enhance transparency, streamline processes, and
reduce conflicts between the government and contractors.
In 2016, the Hydrocarbon Exploration and Licensing Policy (HELP) was introduced to
address the challenges faced under NELP and create a more investor-oriented regime.
HELP replaced the PSC model with a Revenue Sharing Contract (RSC) model, simplified
the licensing framework, and introduced greater flexibility in exploration and production
activities. This marked a transformational shift in India’s E&P regime, with a stronger
focus on reducing operational complexities, increasing transparency, and providing
greater autonomy to operators.
2.1.3. Revenue Sharing Contracts (RSCs)
The introduction of Revenue Sharing Contracts (RSCs) reflects the GoI's vision to create
a more transparent, efficient, and competitive environment in India's oil and gas sector,
aligning with global best practices. RSCs represent a critical evolution in the contractual
framework and are designed to address some of the limitations of the previous PSC
model such as intricate cost recovery process, leading to delays, bureaucratic
bottlenecks, and disputes over recoverable expenses
To operationalize the RSC framework, the Government of India introduced two key
policies: the Hydrocarbon Exploration and Licensing Policy (HELP) and the Discovered
Small Field (DSF) Policy. HELP, introduced in 2016, represents a broader reform
designed to open India's vast sedimentary basins for exploration under a uniform
licensing regime. This regime covers all forms of hydrocarbons—oil, gas, and
unconventional sources—under a single contract. The DSF policy focuses on monetizing
smaller fields that had been discovered but remained undeveloped due to their marginal
size. Under the DSF regime, these fields offer smaller operators an attractive opportunity
to enter the Indian market with reduced financial and operational risks.
Both the DSF and HELP have been instrumental in advancing nation's goal of becoming
a self-reliant energy producer. The details of HELP and DSF are provided below.
1.1.3.1 Hydrocarbon Exploration and Licensing Policy (HELP)
The Hydrocarbon Exploration and Licensing Policy (HELP), introduced in 2016,
represents a cornerstone in nation’s efforts to strengthen its upstream oil and gas sector.
This comprehensive policy marked a shift in the E&P landscape by replacing the previous
PSC model with RSC framework that enhances India's energy security by simplifying the
regulatory environment and fostering ease of doing business.
Under RSCs, the contractor and government share revenue from the sale of
hydrocarbons at pre-agreed percentages, regardless of the costs incurred during
exploration and production.
The RSC regime was implemented in a series of eight bidding rounds, starting with OALP-
I round in 2018 and concluding with OALP VIII in 2022 with changes such as reduced bid
bonds, from USD 200,000 to USD 20,000 and rationalized tender fee set at INR 500,000.
24Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Over the course of these eight rounds, a total of 144 exploration blocks contracts were
signed, covering both onshore and offshore regions, including deep-water areas.
The number of blocks awarded under OALP bid rounds are illustrated in the figure below.
Figure 11: OALP Bid Round details
55
49
21 21
18
14 13 15
11 10 10 10
7 7 8 8
OALP-I OALP-II OALP-III OALP-IV OALP-V OALP-VI OALP-VII OALP-VIII
(2018) (2019) (2019) (2019) (2020) (2021) (2021) (2022)
Source – DGH
The current status of blocks awarded under OALP rounds is illustrated in the figure below.
Figure 12: Current Status of blocks awarded under OALP rounds
Source – DGH, status as on 31 December 2024
With the success of previous OALP rounds, On 3 January 2024, the Government
launched OALP Bid Round-IX, offering 28 blocks for International Competitive Bidding.
Bidders can access data through NDR and select blocks for submission via the dedicated
online e-bidding portal. The round includes 9 Onland Blocks, 8 Shallow-Water Blocks,
25
skcolB
fo
oN
Blocks Awarded Blocks ActiveReport of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
and 11 Ultra Deep-Water Blocks. The bidding was concluded on September 21, 2024,
and the bid evaluation is under process.
1.1.3.2 Discovered Small Field (DSF)
The Discovered Small Field (DSF) Policy, introduced by the GoI in 2015, represents a
pivotal reform in the country’s oil and gas sector. The policy is aimed at monetizing small
and marginal fields that had been discovered by the NOCs but were not developed due
to their perceived lack of economic viability under previous regimes. These fields, though
modest in size, possess significant potential for boosting domestic hydrocarbon
production.
The DSF policy was designed to lower entry barriers and encourage new participants in
the E&P sector, particularly smaller operators who may not have had the capacity to
compete for larger fields.
Three DSF bidding rounds have been successfully conducted, offering a total of 103
contract areas across 10 sedimentary basins, including 7 Category-I and 3 Category-II
basins. These areas cover approximately 17,593 square km and encompass 201
discoveries. Out of these, 85 contract areas, covering around 16,508 square km have
been awarded to about 35 Indian and foreign companies. These awarded areas include
175 discoveries with estimated potential inplace reserves of approximately 464 MMToe,
significantly contributing to India’s hydrocarbon resource development. With the success
of the first three rounds, a fourth bidding round for DSF is currently underway.
The number of contract areas awarded under DSF bid rounds are illustrated in the figure
below
Figure 13: DSF Round-wise contract areas awarded and active
31
30
24
23
16
12
DSF-I (2016) DSF-II (2018) DSF-III (2021)
Source – DGH, status as on 31 December 2024
The response from the industry to the DSF rounds has been overwhelmingly positive.
The policy has drawn participation from a wide range of E&P companies, including those
with specialized expertise in the development of marginal fields and has also introduced
~15 more new players in the sector. The current status of blocks awarded under DSF
contract regime is illustrated in the figure below.
26
skcolb
fo
oN
Blocks Awarded Blocks ActiveReport of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Figure 14: Current Status of blocks awarded under DSF contract regime
Source – DGH, status as on 31 December 2024
Subsequently, a Special DSF Bid Round was launched on May 28, 2024, offering two
Discovered Small Fields located in Mumbai Offshore and one Discovered Coal Bed
Methane field in West Bengal. These fields are available through International
Competitive Bidding. The bidding for this special round closed on September 13, 2024,
and the evaluation is under process.
27Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
2.1.4. Unconventional Hydrocarbons in India
The GoI is also focusing on developing unconventional hydrocarbons to ensure long-term
energy security. These unconventional resources, which require advanced recovery
technologies due to their complex extraction processes, are poised to become pivotal in
India’s current and future energy landscape. Notably, significant reserves of Coal Bed
Methane (CBM) and Shale gas and oil have been discovered in India.
1.1.4.1 Coal Bed Methane (CBM)
India’s journey in Coal Bed Methane (CBM) exploration began in the 1990s to diversify
its energy mix and reduce reliance on conventional hydrocarbons. With an estimated 91.8
TCF of CBM resources, the Government of India (GoI) identified CBM as crucial for
enhancing energy security. In 2001, India offered CBM blocks through international
competitive bidding, awarding 30 blocks to various companies and an additional 3
through nomination and the Foreign Investment Promotion Board (FIPB). These blocks
span states like Andhra Pradesh, Jharkhand, West Bengal, and Rajasthan. Policies
introduced in 2007, 2015, and 2016 further incentivized CBM production. In 2017, a policy
for the Early Monetization of CBM was established to promote a gas-based economy,
providing marketing and pricing freedom for CBM and addressing operational issues in
existing blocks.
1.1.4.2 Shale Gas and Oil
The nation’s shale gas and oil potential has also attracted investor interest due to its
ability to supplement conventional hydrocarbons. Prospective sedimentary basins include
Cambay, Krishna-Godavari, Cauvery, and Assam. A 2013 assessment estimated 187.5
TCF of shale gas resources across five basins, while the Central Mine Planning and
Design Institute (CMPDI) estimated 45.8 TCF in the Gondwana basin. The United States
Geological Survey (USGS) identified 6.1 TCF of technically recoverable shale gas across
three basins in 2011. Recognizing this potential, the GoI has encouraged exploration and
exploitation of shale resources under the PSC regime.
To unlock India’s shale gas and oil potential, the GoI introduced a Shale Gas and Oil
Exploration Policy on October 14, 2013, specifically for NOCs like ONGC and OIL, tasking
them with exploration in their PML and ML areas. Building on the policy frameworks
introduced in 2016 (HELP) and 2018 (Unconventional Hydrocarbon Policy), the MoPNG
announced a policy in October 2018 to promote and incentivize Enhanced Recovery
Methods for Oil and Gas. This framework provides fiscal incentives from the first day of
production from future discoveries of unconventional hydrocarbons, including shale gas,
oil, and gas hydrates. Consequently, many CBM operators have shown keen interest in
exploring and exploiting shale gas resources within their regions, marking significant
progress for the sector.
29rotceS
maertspU
naidnI
ni
BDoE
ot
detaler
seussI
no
)GWJ(
puorG
gnikroW
tnioJ
eht
fo
tropeR
ytirohtuA
gnivorppA
ssecorP
oN.S
MBC
FSD
CSR
CSP
tnemnrevoG
etatS/lartneC
tnemnrevoG
etatS/lartneC
tnemnrevoG
etatS/lartneC
tnemnrevoG
etatS/lartneC
LEP
fo
tnarG
1
tnemnrevoG
etatS/lartneC
tnemnrevoG
etatS/lartneC
tnemnrevoG
etatS/lartneC
tnemnrevoG
etatS/lartneC
LMP
fo
tnarG
2
CCFEoM
CCFEoM
CCFEoM
CCFEoM
CE
fo
tnarG
3
CCFEoM
CCFEoM
CCFEoM
CCFEoM
CF
fo
tnarG
4
eht
ni
denifed
toN
eht
ni
denifed
toN
HGD
HGD
syaD
artxE
/syaleD
elbasucxE
5
tcartnoC
tcartnoC
HGD
:revorppA
1L
HGD
tnemnrevoG
HGD
noitcudeR
aerA
kroW
muminiM
6
tnemnrevoG
:revorppA
2L
CS
CM
CM
CM
AC/kcolB
fo
tnemhsiuqnileR
7
tnemnrevoG
tnemnrevoG
tnemnrevoG
tnemnrevoG
eetnarauG
knaB
8
eht
ni
noisivorp
oN
eht
ni
noisivorp
oN
,dnuor
IIIV
PLAO
roF
eht
ni
noisivorp
oN
noitarolpxE
weN
fo
gnippawS
9
tcartnoc
tcartnoc
HGD
tcartnoc
seuqinhceTReport of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
2.3. Ease of Doing Business in the E&P Sector
Over the past decades, the GoI has introduced a series of policy initiatives aimed at
strengthening the development of E&P sector in India.
One of the most significant initiatives was setting up of the National Data Repository
(NDR), a centralized platform where companies can access to the geoscientific data such
as seismic, well, and other geological information. By making this data available, the NDR
helps companies assess the potential of exploration blocks more accurately, reducing
uncertainties and risks involved in exploration.
The salient features and success of NDR is illustrated in the figure below
Figure 16: Salient Features of NDR
Source –DGH
The GoI has also implemented series of policy initiatives on gas pricing to encourage
domestic production and create a more market-driven, transparent, and investor-friendly
environment for gas exploration and production. In 2023, the government revised its
domestic gas pricing guideline to ensure better returns for the producers while keeping
the consumer prices in check. As per the revised guidelines, the APM prices are now
10% of the Indian Crude Basket Price as defined by Petroleum Planning and Analysis
Cell (PPAC) from time to time with an initial floor and ceiling prices of $4/MMBTU and
$6.5/MMBTU respectively for gas produced by National Oil Companies (NOCs) from their
nomination fields. Further, a premium of 40% is allowed on the gas produced from new
well or well intervention in the nomination fields operated by NOCs.
Government has prioritized the ease of doing business in the E&P sector especially the
simplification of procedures and processes leading to a transparent and efficient system.
This includes initiatives like setting up of PSC Management System (PSCMS), a
workflow-based system for management of contractual approval processes, self-
certification of contractual processes under PSC through standardized formats, online
system for managing PML/PEL application process and various other online systems for
31Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
management of production, revenue, audited accounts, EOI submission, site restoration
fund, etc.
2.4. E&P Sector Performance
Over the recent years, India’s oil and gas production trends have underscored both the
challenges and opportunities in the nation’s pursuit of energy security. These trends are
closely tied to government policies, with successive initiatives aimed at enhancing
domestic E&P of hydrocarbon resources. The government’s ongoing efforts to streamline
regulatory processes, improve EODB, and attract foreign and private investment are
designed to revitalize the sector and achieve the country’s long-term energy objectives.
This combined impact of the policy reforms introduced by the GoI has enabled the country
in enhancing domestic oil and gas production and reduce import dependency.
The production trends of hydrocarbons in India over the past 20 years is illustrated below.
Figure 17: Regime-wise Crude Oil Production in India for the last 20 years (MMT)
37.6938.0937.8637.8037.4636.96
36.0135.69
33.98 33.9934.1333.5133.69 34.21
32.19 32.17
4 5 5 5 5 5 10 11 12 12 12 11 11 10 10 30.4929 0.6929 0.1829 00.36
8
7
7 7 7
21.57
00
5
30 28 29 29 29 28 28 28 26 26 26 26 25 26 24 24 23 22 23 23
17
Nomination PSC RSC DSF
Oil Production (MMT)
Year Total (MMT)
Nomination PSC RSC DSF
FY 04-05 29.68 4.3 0 0 33.98
FY 05-06 27.64 4.6 0 0 32.19
FY 06-07 29.16 4.8 0 0 33.98
FY 07-08 29.04 5.1 0 0 34.13
FY 08-09 28.83 4.7 0 0 33.50
FY 09-10 28.43 5.3 0 0 33.69
FY 10-11 28.01 9.7 0 0 37.69
FY 11-12 27.56 10.5 0 0 38.09
FY 12-13 26.22 11.6 0 0 37.86
FY 13-14 25.72 12.1 0 0 37.79
FY 14-15 25.67 11.8 0 0 37.45
32Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Oil Production (MMT)
Year Total (MMT)
Nomination PSC RSC DSF
FY 15-16 25.6 11.4 0 0 36.95
FY 16-17 25.48 10.5 0 0 36.01
FY 17-18 25.63 10.1 0 0 35.68
FY 18-19 24.34 9.9 0 0 34.20
FY 19-20 23.74 8.44 0 0 32.17
FY 20-21 23.47 7.37 0 0 30.49
FY 21-22 22.44 7.25 0 0 29.69
FY 22-23 22.65 6.5 0.005 0.025 29.18
FY 23-24 22.56 6.741 0.016 0.046 29.36
FY 24-25* 16.55 4.95 0.026 0.030 21.56
Source – DGH, *status as on 31 December 2024
Over the past two decades, India’s crude oil production has slightly declined, from 33.98
MMT in FY 2004-05 to 29.36 MMT in FY 2023-24. While production levels have remained
relatively stable, the country’s oil consumption has continued to rise, leading to a
significant increase in oil imports. This growing dependency on imported oil underscores
the urgent need to enhance domestic production capabilities. Boosting local production
is essential not only to meet rising demand but also to ensure national security and reduce
vulnerability to global market fluctuations. The introduction of the DSF and RSC
represents relatively new contractual regimes, with most fields under these contracts yet
to reach commercial production. However, some production has been observed over the
last two years, indicating a positive trend.
The government’s proactive efforts have been instrumental in fostering an ecosystem
that encourages both NOCs and private companies to explore and produce more
hydrocarbons. This collaborative environment has been crucial in maintaining steady
production levels and driving growth in the sector. The share of contributions of NOCs
and private companies towards crude oil production is illustrated in the figure below.
Figure 18: Share of PSU and Private Companies for Crude Oil Production
27% 24% 24% 22% 21% 20%
73% 76% 76% 78% 79% 80%
FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24 FY 24-25
PSU Private
Source – DGH, status as on 31 December 2024
The above graph showcases the contributions of private companies and PSUs towards
crude oil production has remained about consistent over the last five years, with private
companies accounting for about one-fourth of the country’s total crude oil output. This
33Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
trend is expected to shift positively with the introduction of new players under the DSF
rounds, potentially increasing the overall contribution from private entities.
Additionally, over the past 20 years, India’s gas production has grown significantly to
36.44 BCM, achieving 95.4% of the target of 38.181 BCM for FY 2023-24. While
significant contributions from the DSF and RSC regimes are yet to materialize, notable
progress has been made in these areas. The regime-wise natural gas production in the
country is illustrated in the figure below.
Figure 19: Regime- wise Natural Gas Production in India for the last 20 years (BCM)
52
47 0 48
0 0
41
3 72 3 72 3 72 3 82 3 803 22 27 22 10
4
3 905 3 904 3 802 3 612 3 613 3 513 3 411
2 419
13
1
04 13
011
15 13 001 37
2 0017
10
25 25 25 25 25 26 25 26 26 26 25 24 25 26 27 26 24 24 23 22
17
FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY FY
04-0505-0606-0707-0808-0909-1010-1111-1212-1313-1414-1515-1616-1717-1818-1919-2020-2121-2222-2323-2424-25
Nomination PSC RSC DSF CBM Total
Natural Gas Production (BCM)
Year
Nomination PSC RSC DSF CBM Total
FY 04-05 24.98 6.78 0 0 0 31.76
FY 05-06 24.74 7.36 0 0 0 32.10
FY 06-07 24.71 7.04 0 0 0 31.75
FY 07-08 24.67 7.73 0 0 0 32.40
FY 08-09 24.75 8.07 0 0 0.02 32.84
FY 09-10 25.51 21.95 0 0 0.04 47.50
FY 10-11 25.44 26.73 0 0 0.04 52.21
FY 11-12 25.95 21.53 0 0 0.08 47.56
FY 12-13 26.19 14.38 0 0 0.11 40.68
FY 13-14 25.91 9.33 0 0 0.17 35.41
FY 14-15 24.74 8.68 0 0 0.23 33.65
FY 15-16 24.02 7.84 0 0 0.39 32.26
FY 16-17 25.03 6.31 0 0 0.57 31.90
FY 17-18 26.31 5.60 0 0 0.74 32.65
FY 18-19 27.4 4.77 0 0 0.71 32.88
FY 19-20 26.42 4.12 0 0 0.66 31.20
FY 20-21 24.35 3.68 0 0 0.64 28.67
FY 21-22 23.52 9.82 0 0 0.68 34.02
FY 22-23 23.01 10.7 0.01 0.6 0.67 34.99
FY 23-24 22.41 13.38 0.06 0.08 0.65 36.58
FY 24-25* 16.55 9.99 0.128 0.067 0.557 27.306
Source – DGH, *status as on 31 December 2024
34Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
It is further observed that, natural gas sector in India is experiencing a rising trend, driven
by the government’s concerted efforts to enhance production and create a favorable
investment ecosystem. Policies and initiatives from the government has been pivotal in
attracting both domestic and international players to the sector. These policies, coupled
with advancements in technology and infrastructure, have significantly boosted
production levels.
The increase in natural gas production in the nation is a testament to the effectiveness of
these government initiatives. By fostering a more transparent and competitive
environment, the government has enabled both NOCs and private companies to explore
and develop new fields more efficiently. It has been further observed that, the NOCs
continue to be frontrunners in natural gas production, leveraging their extensive
infrastructure and experience to maintain steady production levels. However, private
companies have also made notable strides, where new fields and advanced technologies
have driven increased output. The share of contributions of both NOCs and private
companies for gas production is illustrated in the figure below.
Figure 20: Share of PSU and Private Companies in Gas Production
15% 15%
31% 33% 39% 37%
85% 85%
69% 67% 61% 63%
FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24 FY 24-25
PSU Private
Source – DGH, status as on 31 December 2024
The above graph illustrates a significant growth in natural gas production from private
companies over the past five years, with these entities now contributing nearly 40% of
the total natural gas output. This trend underscores the favorable investment ecosystem
within India’s E&P sector and reflects the confidence that private investors have in the
country’s regulatory framework.
The upstream oil and gas sector is a high-risk endeavor with geological factors and high
capital expenditure requirements, impacting the geological chances of success in the
sector. At present, a total of ~21,291 wells have been drilled across various contractual
regimes and 924 discoveries have been made in the sector.
The figure below illustrates regime-wise number of wells drilled and number of
discoveries made.
35Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Figure 21: Regime-wise total number of wells drilled, and discoveries made
18559
656
177
1442
423 70 912 423 0
11
10 0
Nomination Pre-NELP Pre-NELP NELP OALP DSF
Discovered Exploration
Source – DGH, status as on 31 December 2024
As evident from the data depicted above, the difference between the total wells drilled
and the actual discoveries showcases a fundamental characteristic of the E&P
business—success rates are typically low, and the process of exploration often yields
limited results. This reality has shaped the development of the sector, requiring
companies to balance high-risk exploration activities with significant financial investments
and long timelines.
Further complicating the landscape, as illustrated by the subsequent figure, is a
significant number of wells in India remain classified as sick or non-flowing. These wells,
despite being drilled, fail to produce hydrocarbons in commercially viable quantities, often
due factors such as geological complexities, depletion of reservoir pressure, or technical
challenges in extraction. The presence of these non-flowing wells not only adds to the
operational costs but also highlights the need for enhanced recovery techniques and
innovative solutions to unlock their potential.
The following figure illustrates regime-wise number of sick, non-flowing and flowing wells.
36
dellird
sllew
fo
rebmuN
seirevocsid
fo
rebmuN
Exploratory Wells Appraisal Wells Development Wells Discovery madeReport of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Figure 22: Regime-wise number of sick, non-flowing and flowing wells
6834
1,729
1,216 248
286 838 830
513 368
82 0 0 0 2 3 1 4 13 76172
Nomination PSC RSC DSF CBM
Sick Wells Shut In Non-Flowing Flowing
Source – DGH, status as on 31 December 2024
As observed from the graph above, 2,349 wells out of 10,866 wells are classified as non-
flowing, representing a substantial portion of underutilized resources. It was further
observed that, PSC regime has the highest percentage of non-flowing wells at
approximately 30%.
2.5. E&P sector Outlook
India stands at a pivotal juncture in its energy evolution, with growing demands spurred
by rapid economic expansion, urbanization, and industrial growth. The future of India's
energy landscape will depend on how effectively it navigates the complexities of
production, imports, and alternative energy sources.
India’s current natural gas production stands at 36.58 BCM. Driven by strategic policy
initiatives, technological advancements, and new discoveries, the natural gas sector is
positioned for considerable growth in the coming years. According to projections, India’s
natural gas production is expected to rise to 54.7 BCM by FY 2029-30, and further
increase to 63.7 BCM by FY 2034-35. This growth trajectory aligns with the government’s
objective of increasing the share of natural gas in the primary energy mix from 6% to 15%
by 2030, reinforcing India’s commitment to cleaner energy sources and reduced carbon
emissions.
Natural gas production forecast is illustrated in the figure below.
37Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Figure 23: Natural gas production forecast for the next decade (BCM)
57.4 58.9 60.5 62.1 63.7
54.7
51.7
48.8
46.2
43.6
36.6
FY 24-25 FY 25-26 FY 26-27 FY 27-28 FY 28-29 FY 29-30 FY 30-31 FY 31-32 FY 32-33 FY 33-34 FY 34-35
Natural Gas Production (BCM)
Source – BP Energy Outlook 2024
Similarly, the nation’s current crude oil production stands at 29.36 MMT. While production
is expected to increase over the short term, reaching 45.5 MMT by FY 2029-30,
projections indicate a subsequent decline, with output anticipated to fall to 27.2 MMT by
FY 2034-35. This trend reflects the growing challenges of maturing oil fields and the
limited scope of recent discoveries in onshore and shallow water basins. The crude oil
production forecast is illustrated in the figure below:
Figure 24: Crude oil production forecast for the next decade (MMT)
49.5 48.5 47.5 46.5 45.5
43.6
38.7
34.4
29.4 30.6
27.2
FY 24-25 FY 25-26 FY 26-27 FY 27-28 FY 28-29 FY 29-30 FY 30-31 FY 31-32 FY 32-33 FY 33-34 FY 34-35
Crude Oil Production (MMT)
Source – BP Energy Outlook 2024
India’s energy outlook reflects both challenges and opportunities, with a promising growth
trajectory in natural gas production balanced by constraints in crude oil production. By
aligning natural gas expansion with sustainability goals and managing the decline in
crude oil production, India can continue to secure its energy future and strengthen its
position in the global energy landscape.
38Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
2.6. Joint Working Group (JWG)
The E&P sector in India has made significant strides in strengthening the energy security
of the nation, yet there are still operational and regulatory challenges faced by the
operators that hinder growth of the sector, as observed in the previous sections. However,
the GoI remains committed to support the development of upstream oil and gas sector
and achieve nation's long-term energy goals
With a view to address industry concerns that persist in E&P sector, a Joint Working
Group (JWG) was constituted Ministry vide its order number Expl-11032(11)/10/2024-
Expl-I-PNG (E-49999), dated 25 July 2024 (Annexure 6.2.2). The JWG is tasked with the
mandate to examine issues related to EoDB in the Indian E&P sector, assess existing
policies and procedures, and evaluate the need for its revisions.
The composition of the JWG is as follows –
i. Shri Praveen M. Khanooja, Additional Secretary, MoPNG (Chairperson)
ii. Shri Vinod Seshan, Joint Secretary(E), MoPNG, (Member Secretary & Convenor)
iii. Shri Akash Goyal, Additional Director General (Coordination), DGH
iv. Shri Pankaj Kumar, Director (Production), ONGC
v. Shri Saloma Yomdo, Director (E&D), OIL
vi. Shri Pankaj Kalra, CEO, Essar Oil and Gas Exploration and Production Limited
vii. Shri Padam Singh, President, Sun Petrochemicals Limited
viii. Shri Avinash K Pathak, Senior Vice President, Reliance Industries Limited
ix. Shri Manish Maheshwari, Chairman & CEO, Invenire Energy
x. Shri Kapil Garg, CMD, Oilmax Energy Private Limited
xi. Shri Rakesh Agiwal, CPRO, Vedanta Limited
The Terms of Reference (TOR) for the JWG is as follows:
a) Identify areas of concern and cause of delay in grant of clearances/licenses/approvals
to Operators and possible simplifications/ process re-engineering
b) Identify processes under contract regimes which can be brought under the self-
certification route and verifiable post-audit of accounts, based on the experience of
extant self-certification processes and global leading practices.
c) Provide recommendations along with appropriate safeguards for revisions and
improvements to address the identified issues and promote EoDB in the sector.
KPMG was engaged as a knowledge partner to support the JWG for providing market
insights and formulating the final set of recommendations
39Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
3. Issues submitted by E&P operators
The JWG held extensive discussions with industry stakeholders, gathering a list of issues
faced by operators in the nation’s upstream sector. These issues cover a broad range of
challenges, including policy and procedural hurdles, fiscal and financial constraints, and
matters related to self-certification. Each issue was examined by the JWG to better
understand the regulatory and operational obstacles affecting the EoDB in the sector.
The issues included procedural challenges such as delays in obtaining Environmental
and Forest Clearances, financial matters such as stringent requirement for bank
guarantees, indirect taxation on the procurement of goods, and simplification of
processes including, self-certification. Further, stakeholders have also highlighted the
need for providing additional fiscal incentives such as reasonable rates for royalty, cess,
and other statutory levies. A detailed list of all the submissions received from the JWG
members is enclosed in Annexure IV.
A summary of major concerns that emerged from the submissions and subsequent
deliberation during the JWG consultations, is presented below –
i. Challenges faced in securing Environmental Clearances (EC): Streamlining
process of obtaining EC through initiatives such as single window clearance,
making EC co-terminus with PML, implementing a unified consent process for
social licenses under a single application etc.
ii. Challenges faced in acquisition of Forest Clearances (FC): Streamlining issues
related to forest clearance and approval from Standing Committee for National
Board of Wildlife (SC-NBWL) through measures such as creation of land bank for
Compensatory Afforestation, de-linking FC from online EC applications on
Parivesh portal etc.
iii. Taxation issues involved in procurement of goods and products: Contractual
disputes related to procurement of goods, such as applicability of the
concessional GST rate of 12%, applicability of GST-TDS in addition to advance
payment of estimated GST on the contract for Non-Resident Taxable Persons
etc., leading to litigation proceedings and delays in project execution.
iv. Challenges in withdrawal of Site Restoration Fund: Utilization of Site Restoration
Fund for carrying out the planned abandonment activities, and not just for removal
of all equipment and installations on the expiry or termination of the agreement or
relinquishment of part of the contract area.
v. Absence of standardized procedure for field handover from an operator: Lack of
Standardized Operating Procedure (SOP) for field handover from an operator,
particularly prevalent in DSF blocks where delays occur due to transfer of PML or
EC certification between the operators.
vi. Extension in current Initial Exploration Period (IEP) for onshore & offshore OALP
blocks with seismic and drilling program: Submission by JWG member for
extension in IEP especially for logistically inaccessible and difficult terrains such
as North-East region.
40Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
vii. Lack of provision for fiscal incentives including royalty, cess and other statutory
levies: Submission by JWG members for recommendations for fiscal incentives
such as payment of Royalty and Profit Petroleum on actual realized prices instead
of Indian Basket price, allowance for post wellhead cost for Royalty purposes all
to improve project viability.
viii. Gas evacuation challenges from isolated fields: Challenges related to
monetization and evacuation of natural gas, produced in small quantity, that may
be kept outside the Gas allocation scheme or out of e-auction and be allowed to
sale on arm’s length basis.
ix. Issues related to approval for delivery point for within and outside the contract
area: Delays in approval for delivery points proposed outside the contract area
due to logistical constraints, such as absence of accessible refineries within the
block, impacting project timelines.
x. Issues related to estimating for Extra Days/Excusable delays: Inconsistency in
grant of excusable delays or extra days across contractual regime, wherein some
regimes provide for delay in any statutory clearance, some provide only EC and
FC which some contracts due not provide for extra days under existing clauses of
the contract.
xi. Challenges faced by operators for work programme completion: Issues
encountered by operators due to delay or denials in obtaining necessary statutory
clearances, while these clearances were earlier accorded “in-principle” approval,
for conducting seismic surveys or drilling activities as outlined in their work
programme, thereby impacting the timeline and execution of planned exploration
activities.
xii. Issues related to submission of bank guarantee (BG) in RSC during renewal:
Financial implications borne by the operator due submission of BG equivalent to
the Liquidated Damages for the entire work programme, instead of the
uncomplete portion of the work programme, under the current contractual
provisions.
xiii. Absence of provisions for allowing PSC application to be submitted within two
years of preceding contract expiry: In many cases, operators had to seek
condonation for submitting extension applications beyond the stipulated period,
which introduces uncertainty in situations where unforeseen delays or challenges
arise closer to the contract's end.
xiv. Issues related to Participating Interest (PI) transfer: Submission by JWG members
for delays encountered in approval of PI transfer from government, leading to
operational inefficiencies.
xv. Inconsistent exchange rate conversion methodology across contracts regimes:
Variations in exchange rate methodologies across contractual regimes has led to
complications in accounting, auditing, and financial reporting for operators
managing assets across multiple fields.
xvi. Delays in FDP approvals: Operators have encountered delays during the process
of technical alignment between JV partners for the Operating Committee
Resolution (OCR) on FDP. Additionally, delays in securing FDP approval from MC
have been highlighted. Further, operators have raised concerns regarding the
41Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Contract Management System (CMS) portal, where operators have experienced
issues while submitting FDP/RFDP documents.
xvii. Challenges in Annual Work Programme (AWP) approval and financing for CBM:
Submission from operators to highlight the need to streamline the approval
process for AWP submissions, proposing the introduction of self-certification
mechanisms to expedite approvals and facilitate in securing of funds for CBM
operations across various CBM rounds.
xviii. Limited subsidy for natural gas pricing in North- East region: Operators have
pointed out disparities in gas pricing in North-East region, where ONGC and OIL
benefit from discounted gas prices, creating an uneven playing field for other
operators.
Addressing these unresolved issues can enhance the EODB in India’s upstream sector
and unlock its full hydrocarbon potential. Streamlining regulatory approvals, fostering
domestic technological capabilities, ensuring fair taxation policies, and enabling
transparent gas marketing mechanisms will create a more competitive and investor-
friendly environment. Cross-ministerial coordination, policy refinements, and industry
consultations will be essential in resolving these challenges effectively. By implementing
these reforms, India can strengthen its energy security while aligning with global leading
practices in hydrocarbon management.
42Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
4. Initiatives adopted by DGH to elevate EODB in
the Hydrocarbon sector
In line with the liberalized economic policy adopted by the GoI in July 1991, which aimed
to deregulate and de-license key sectors, including petroleum, significant structural
reforms were introduced to enhance private sector participation. It became imperative to
establish an independent body to administer and regulate their operations in alignment
with national interests.
The Directorate General of Hydrocarbons (DGH) was formally established on April 8,
1993, through Government of India Resolution No. 0-20013/2/92/ONG-III, under the
administrative control of the MoPNG. DGH has been entrusted with a broad spectrum of
responsibilities, including the implementation of the NELP, administration of PSCs for
discovered fields and exploration blocks, facilitation of investment in the E&P sector, and
rigorous monitoring of upstream activities, including reservoir performance reviews of
producing fields. Additionally, DGH plays a pivotal role in expanding exploration into
unexplored areas and fostering the development of non-conventional hydrocarbon
resources such as CBM, gas hydrates, and oil shales, which are essential for India's long-
term energy security.
As a key regulatory authority, DGH has remained at the forefront of addressing
stakeholder concerns and implementing strategic initiatives to enhance EoDB in the
hydrocarbon sector. A summary of the initiatives are provided below:
i. Multiple internal orders have been issued with an aim to simply and standardize
existing processes under various contractual regimes, including:
• Simplification of processes related to work programme and budget proposals
for E&P contracts (order dated 15 July 2024)
• Re-engineering of Internal SOP for processing of Appraisal Plan or FDP or its
revision in CMS for PSC's (order dated 16 July 2024)
• Simplification and standardization of procedures and processes under PSC of
Pre-NELP/NELP Blocks. (order dated 12 July 2024)
• Approval process in management of PSCs/RSCs for facilitating Management
Committee meeting. (order dated 3 July 2024)
• Issuance of Bank Guarantee (BG) towards unfinished work programme
ii. Significant upgrades have been implemented across online platforms such
as the Contract Management System (CMS), focusing on process digitization,
system enhancements, e-simplification, and the introduction of standardized
forms to facilitate smoother submission.
iii. A major step towards expanding India’s exploration footprint is Mission
Anveshan, launched in February 2024. The program aims to conduct 20,275
LKM of 2D seismic surveys across seven onshore sedimentary basins to identify
new hydrocarbon reserves. By leveraging a collaborative approach between
43Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
public and private stakeholders and ensuring targeted funding, this initiative is
expected to significantly enhance geological understanding.
iv. To complement these efforts, the government has approved the drilling of
stratigraphic wells in key offshore basins such as Mahanadi, Bengal,
Saurashtra, and the Andamans. This initiative is expected to improve subsurface
geological understanding, enhance hydrocarbon prospectivity, and strengthen
bidding rounds under the Open Acreage Licensing Policy (OALP).
v. Recognizing the importance of data accessibility, the National Data Repository
(NDR) is undergoing a major transformation into a cloud-based platform,
ensuring instant access to seismic, well, and production data.
vi. As part of its academic collaboration, a dedicated data center is being established
at the University of Houston, facilitating seamless access to India’s hydrocarbon
data for international investors.
vii. DGH is also in the process of implementing an Integrated Management System
(IMS) to streamline stakeholder engagement and improve business efficiency
across all contractual regimes. IMS will enable centralized data management and
provide a unified view of all regulatory interactions. Equipped with digital
dashboarding, artificial intelligence (AI), and machine learning (ML) capabilities,
IMS will deliver intelligent insights to enhance decision-making and operational
oversight.
viii. The Hydrocarbon Efficiency & New Energy (HENE) department of DGH is
planning to carry out studies and/or pilot projects in the areas of emissions
monitoring, renewable energy integration, and Carbon Capture, Utilization, and
Storage (CCUS) and Hydrogen etc.
ix. DGH has also launched DGH UrjaVarta, an annual strategic and technical forum
for bringing together industry operators, policymakers, service providers, think
tanks, and academia. This platform facilitates knowledge exchange, networking,
and collaboration with an aim to maximize India’s upstream hydrocarbon potential.
x. Further, recognizing the need for streamlined environmental clearances, DGH is
organizing specialized workshops with relevant stakeholders to address key
challenges in obtaining environmental and forest-related approvals.
Through these initiatives, DGH aims to reinforce its commitment to enhance the EODB
in India’s upstream oil and gas sector, drive technological and policy innovation, and
ensure a sustainable and investor-friendly hydrocarbon ecosystem.
44Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5. Analysis and Recommendations
The JWG, in its review process has considered the viewpoints and submissions from a
wide range of stakeholders, including industry experts and government officials. This
collaborative approach has resulted in comprehensive recommendations aimed at
addressing the challenges faced by the sector.
The identified issues are categorized by their anticipated resolution timeframe: immediate
(within next 6 months), short-term (within 1 year) and long-term (beyond 1 year).
This section is divided into in two parts:
• Part A: Issues resolvable within the jurisdiction of MoPNG: Among the issues
reviewed, eighteen critical issues have been prioritized as resolvable in the
immediate and short-term period. This part also includes specific actionable
recommendations to address these issues expeditiously.
• Part B: Issues to be resolved with cross-ministerial support: This part outlines
the next steps identified by the JWG for issues that require further deliberation and/or
require coordination and support across multiple ministries.
Part A: Issues resolvable within the jurisdiction of MoPNG
This section addresses the critical issues identified by the JWG that fall within the
jurisdiction of the MoPNG and can be resolved within immediate and short-term
timeframes.
The recommendations are further categorized as follows:
A. Recommendations for Immediate Resolution (within 6 months)
B. Recommendations for Short-Term Resolution (within 1 year)
These targeted interventions proposed are designed to promote sustainable growth and
streamline operations in the E&P sector.
45Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
A. Recommendations for Immediate Resolution (within 6
months)
5.1. Approval for delivery point(s) within and outside the
contract area
5.1.1. Description of the issue
The current provisions under the PSC, RSC, DSF, and CBM frameworks define the
delivery point as the point where petroleum reaches the outlet flange of the delivery
facility, whether onshore or offshore. Further, as per the current interpretation of the E&P
contracts, the cost incurred beyond the delivery point towards marketing or transportation
of petroleum was not allowed for cost recovery, until a process for ascertaining market
price was followed by the contractor.
In many cases, operators have proposed delivery points outside the contract area due to
limited access to common treatment facility of ONGC, refineries or gas consumers for the
production from the block or due to other technical or operational constraints. An Office
Memorandum (OM) dated October 10, 2019, issued by MoPNG, restricted the power to
approve delivery points outside the contract area to the Government of India (GoI).
However, in March 2024, MoPNG/ECS empowered the Management Committee (MC)
for approval of multiple delivery points for Oil and Gas within the contract areas for Pre-
NELP field round blocks.
Since the MC is comprised of two government nominees, it may be recommended to
delegate the power to approve delivery points from the GoI to the MC and/or allow self-
certification for delivery points to the operators in certain cases, for streamlining project
execution timelines.
5.1.2. Relevant provisions under various contractual regimes
i. Under Production Sharing Contract (PSC)
• According to Clause 1.31 of Article 1- Definitions, Delivery Point(s) shall be
approved by the Management Committee (MC).
• According to Appendix C – Accounting Procedure to the Contract, Section
3- Recoverable Costs, Expenditures And Income, Clause 3.2 (iii), costs of
marketing or transportation of Petroleum beyond the Delivery Point(s) are not
recoverable and not allowable for cost recovery under the contract.
ii. Under Revenue Sharing Contract (RSC)
• According to Clause 1.1.34, of Article 1 – Definitions, Delivery Point(s) are
allowed to be established for purposes of sales. The approving authority has not
been defined in the contract.
iii. Under Discovered Small Fields (DSF) Contract
• According to Clause 1.29, of Article 1 - Definitions, Delivery Point(s) are
allowed to be established for purposes of sales. The approving authority has not
been defined in the contract.
iv. Under Coal Bed Methane (CBM) Contract
46Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
• According to Clause 1.29 of Article 1 – Definitions, Delivery Point(s) for the
purpose of sale(s) of CBM from the contract area shall be approved by the
Steering Committee.
The detailed relevant provisions under various contractual regimes may be referred in
Annexure 4.3.1.
5.1.3. Recommendations
A policy guideline applicable for contract areas under various contractual regimes
i.e., PSC, RSC, DSF and CBM may be issued to effect following:
a) For delivery points within the contract area:
i. Contractor may be allowed to establish new delivery point(s), shift existing
delivery point(s), or establish multiple delivery point(s) (subject to a
maximum of total three) within the contract area on a self-certification basis
for all contractual regimes inter-alias PSC, RSC, DSF, and CBM. An
intimation shall be provided to the Management Committee (MC) prior to
setting up of the delivery points.
b) For delivery points outside the contract area:
i. Approval for new, shifted, or multiple delivery points outside the contract
area under PSC, RSC, DSF and CBM regimes shall be granted as follows
a. If the Investment Multiple (IM) slab remains unaffected (wherever
applicable), MC may be empowered to grant the approval.
b. If the IM slab is impacted (wherever applicable), approval shall be
required from the Government of India
ii. The revenue to be considered for the purpose of calculating royalty and
PP/PLP shall be determined on the prices obtained by the contractor at
such delivery point(s).
c) The above provisions in a) and b) shall be applicable to all contracts where the
approval mechanism for delivery points is not specified in the respective
contracts. The recommended provisions shall supersede any previously issued
office orders.
Logic adopted for formulating recommendation
The recommendation establishes a streamlined framework that allows contractors to
autonomously manage delivery points within the contract area, while reducing
procedural delays. It promotes consistency and transparency in the approval
process.
47Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.2. Grant of Excusable Delays/ Extra Days for delays in
government related approvals
5.2.1. Description of the issue
In many areas, contractors experience delays in obtaining the necessary government
approvals, clearances, and permits from central and/or state governments. To address
these delays, contractors are allowed to request Excusable delays/Extra days for the lost
period to meet their work program commitments. However, the current provisions under
the PSC, RSC, DSF, and CBM contracts offer an inconsistent approach to manage such
delays.
For instance, the GoI allowed extensions in exploration period for delays caused due to
delays in obtaining various statutory approvals under PSC regime. While under RSC
regime, Extra Days are only granted for delays in obtaining Environmental and Forest
Clearances (EC and FC). In certain cases, no Excusable delays/Extra days is granted,
regardless of the nature of the delay. This inconsistency hinders project execution and
can delay investments in these projects.
For example, in a few blocks located in Cambay, Rajasthan, approvals for EC and FC
have been delayed, leading operators to claim 300-350 extra days. Similarly, in blocks
located in the Krishna Godavari and Kutch basins awarded under RSC, operators have
requested extensions due to delays in statutory approvals such as renewing Petroleum
Exploration Licenses (PEL). However, as clause 14.5 of the RSC only allows for
extensions related to EC and FC delays, no additional time has been granted for other
statutory clearance delays. In either case, the delays caused are beyond reasonable
control of the operator and should be treated at par to allow extended timelines for the
operator to meet the contractual work commitment.
5.2.2. Relevant provisions under various contractual regimes
i. Under Production Sharing Contract (PSC)
• The policy for extension in the exploration phase dated April 18, 2006, defines
excusable delays as demonstrable delays in obtaining Government approvals,
permits, or clearances which are not attributable on part of contractor. These
excusable delays were approved by the Government.
• Subsequently, according to Clause 3 of MoPNG policy dated 25 June 2018
“Policy framework for streamlining the operations, relaxation of timelines and
delegation of powers to Director General, Directorate General of Hydrocarbons
(DGH) under Production Sharing Contracts (PSCs)”, the Government has
delegated its power to DG, DGH to approve cases of demonstrable delays
as excusable delays after confirming demonstrable delays within the extant
policy framework of 2006 and requires quarterly reports to the MoPNG detailing
the cases and their justifications. Further on 30 October 2019 MoPNG issued
guidelines & checklist to process such cases of excusable delays based on SoPs
issued by MoPNG on 28 August 2018
ii. Under Revenue Sharing Contract (RSC)
Till OALP Round VII
48Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
• As per Clause 14.5 of Article 14 - Protection of the Environment, in the event
the Government or the State Government takes more than the time period
stipulated under the applicable laws for providing Environment Clearance (EC)
or Forest Clearance (FC), or where no specific time period is provided for grant
of such clearance, more than 120 days (“Approval Period”), then the days taken
by the Government or State Government in addition to the approval period to grant
such approval (“Extra Days”) shall be taken into account in determining all time
periods provided for discharge of obligations of the operator under the Contract
and such time periods, if already determined, shall stand extended by the number
of Extra Days.
• According to Clause 5.5 (d) / 5.7 (d) of Article 5 – Work Programme, if delay
due to lack of statutory and other clearances is beyond 2 years in any of the
blocks, then the Contractor can either exit from the contract without payment of
Liquidated Damages as specified in Article 5.4 or if the Contractor continues
exploration in the reduced area, then proportional reduction in Committed Work
Programme shall be allowed, rounded off to the nearest integer with a minimum
number of one. PEL for area not made available will be cancelled and future PEL
fee would be reduced proportionately. In such cases the application for such
reduction /exiting should be made within 3 months of the expiry of the 2-year
period from the date of application for clearance. Any delay attributable to the
Contractor shall not be considered in the above-mentioned two-year period.
Under OALP Round VIII
• According to Clause 33.10 of Article 33 - Entire Agreement, Amendments,
Waiver and Miscellaneous, in the event that the necessary statutory clearances,
permits, approvals or consents are not granted by the Government or the relevant
State Government or any of their respective agencies, ministries, institutions or
authorities within the time period stipulated under applicable laws of India or where
no time period is provided for grant of such permits, clearances, approvals or
consents, within 120 days (“Approval Period”), then the period taken by the
government or relevant State Government or their respective agencies, ministries,
institutions or authorities in addition to the approval period (“Extra Days”) shall be
added to the relevant time period(s) for discharge of obligations of the Contractor
under the Contract; subject to a maximum cumulative of 720 Extra Days for the
entire Exploration Period; and such time period(s), if already determined, shall
stand extended by the number of Extra Days, and any obligation to pay liquidated
damages for any delay under this Contract shall calculated only after taking into
the account the Extra Days.
• If delay due to lack of statutory and other clearances is beyond 2 years and
verified by DGH, then the Contractor would be permitted to relinquish the
Contract area without payment of Liquidated Damages as specified in Article 5.4.
In such cases, the application for such exiting should be made within 60 days prior
to the expiry of the 2-year period.
The powers for approval of Extra Days are not clearly defined under RSC due to
which currently all applications for Extra Days are routed to the government for
approval.
iii. Under Discovered Small Fields (DSF) contract
• Under DSF Round I & II , according to Clause 14.5 of Article 14 – Protection
of the Environment, in the event the Government or the State Government takes
49Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
more than the time period stipulated under the Applicable Laws for providing
Environment Clearance (EC) or Forest Clearance (FC), or where no specific
time period is provided for grant of such clearance, more than 120 days (“approval
period”), then the days taken by the Government or State Government in addition
to the approval period to grant such approval (“Extra Days”) shall be taken into
account in determining all time periods provided for discharge of obligations of the
operator under the Contract and such time periods, if already determined, shall
stand extended by the number of Extra Days.
• Under DSF III & Special Round contract, there is no clause which defines the
provision of Extra Days due to delay in getting clearances from the Government
or the State Government.
iv. Under Coal Bed Methane (CBM) Contract
• As per the MoPNG notification Policy framework for early monetization of Coal
Bed Methane dated April 11, 2017:
o Basis Clause 2, Director General, Directorate General of Hydrocarbons
(DG, DGH) is empowered for condoning the delays in notice periods,
annual work programme and budgets and to approve the excusable delays
regarding clearances from State and Central Government
o Basis Clause 2.4, DGH is empowered to approve excusable delays,
without set off from subsequent phases, in development phase due to Land
Acquisition/ Force Majeure condition or any other matter beyond control of
operator after confirming demonstrable delays.
The detailed relevant provisions under various contractual regimes may be referred in
Annexure 4.3.2.
50Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.2.3. Recommendation
A policy guideline applicable for contract areas under various contractual regimes
i.e., PSC, RSC, DSF and CBM may be issued to effect following:
a) Delay in any of the approvals, clearances, or permits by Central or State
Government or respective ministries, or agencies, beyond the designated
approval timeline and not attributable to the contractor, may be eligible for grant
of Extra Days (wherever applicable). In case of non-availability of designated
approval timeline of specific approval under consideration, a standard timeline
of 120 days may be considered for computation of the Extra Days.
b) The approvals, clearances or permits mentioned in a) shall include – grant of
PEL/ PML, Environment related Clearance (EC), Eco-Sensitive Zone (ESZ)
Clearance, Forest Clearance (FC), Wildlife Clearance, Coastal Regulation
Zone (CRZ) Clearance and Ministry of Defence Clearances.
c) To qualify the claim for Extra Days, as mentioned in above (a), the contractor
shall demonstrate substantiated efforts to obtain the necessary approvals and
provide timely intimation to the MC within a period of 6 months from the date
of such application submitted and at such further instance as the MC may direct
thereafter.
d) DG, DGH basis MC recommendation may be empowered to approve the
provisions proposed in above a).
e) If such a delay period is more than 2 years, the contractor may be provided an
option to:
i. Continue the contract under revised timelines with the approved extra
days.
ii. Relinquish the block without liability for Liquidated Damages (LD). The
mechanism of relinquishment shall be as per the provisions of the existing
contract and the extent policy or guidelines.
f) Additionally, the existing mechanism under the PSC for case reviews by the
Multi-Disciplinary Committee (MDC) at the DGH may be continued for above
proposed provisions.
51Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Logic adopted for formulating recommendation
The current provisions under the PSC, RSC, DSF, and CBM contracts related to
excusable delays/ extra days are inconsistent which hinders the project execution
and can delay investments in these projects.
For instance, the GoI allowed extensions in exploration period for delays caused due
to delays in obtaining various statutory approvals under PSC regime. While under
RSC regime, till OALP round VII, Extra Days are only granted for delays in obtaining
Environmental and Forest Clearances (EC and FC) while from OALP round VIII,
extra days are provided for delay in grant of necessary statutory approvals. In certain
cases (such as blocks under DSF round III & special round), no Excusable
delays/Extra days is granted, regardless of the nature of the delay.
Therefore, the recommendation standardizes the granting of extra days, ensuring
consistent treatment across all contractual regimes.
5.3. Reduction in contract area and work programme, due to
denial or delay in statutory clearances for exploratory
activities
5.3.1. Description of the issue
In many blocks, operators face challenges in obtaining the necessary statutory
clearances, such as Environmental or Forest Clearances, from the Government for
conducting seismic surveys or drilling activities as outlined in their work programme.
Although these clearances were previously granted “in-principle” approval, operators
have been denied permission to carry out work in the entire block or parts of it.
These challenges are particularly prevalent in blocks that overlap with Special Economic
Zones (SEZ), reserve forests, naval exercise areas, Defense Research and Development
Organization (DRDO) danger zones, national parks, urban areas, and firing ranges of
police or armed forces.
While the current contractual provisions allow the operator to seek approval for
proportionate area reduction and work programme reduction, these provisions are
inconsistent across contract regimes. For e.g., under PSC, an operator can avail this
provision for denial of clearances by Government agencies, while under RSC, an operator
can avail this provision for delays in obtaining clearances from Government agencies.
5.3.2. Relevant provisions under various contractual regimes
i. Under Production Sharing Contract (PSC)
• According to Clause 3.1 of MoPNG notification ‘Policy Framework for
relaxations, extensions and Clarifications at the development and production
stage under the PSC’ dated November 10, 2014, contractor may propose an
annual work programme for review by the MC to complete the Minimum Work
Programme (MWP). In some cases, exploration activities are denied by
52Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Government bodies or other ministries (e.g., MoEFCC, MoD, etc.), which earlier
were accorded “in-principle” approval. It has been decided that when the
contract area is reduced due to the denial of clearances by Government
agencies, DGH is empowered to exercise a proportionate reduction of the
MWP based on MC recommendations. Further, in case, the contractor does
not exercise his option to reduce his contract area within three months of the
communication received by the contractor for reduction but proposes to exit from
the contract later, a penalty will be imposed of liquidated damages to the extent
of cost of unfinished MWP proportional to the reduced area. This will be
applicable to all existing PSCs.
ii. Under Revenue Sharing Contract (RSC)
• According to Clause 5.5(d) of Article 5 – Work Programme of RSC, if there is
a denial or delay of necessary clearances or licenses by the Government or
State Governments for part of the contract area, and the delay exceeds 2 years
for reasons not attributable to the contractor, the contractor can either
relinquish the contract without paying Liquidated Damages (as specified in
Article 5.4) or seek approval from the Government for a proportionate
reduction in the Committed Work Programme (CWP), proportional reduction
of the future license fee, and PEL area.
• Further in clause 5.5(b) of Article 5 – Work Programme, if the contractor does
not exercise this option within three months of receipt of the communication of
reduction of area but proposes to exit from the Contract later, an LD will be levied
to the extent of unfinished Committed Work Programme, proportional to the
reduced area.
iii. Under Discovered Small Fields (DSF) Contract
• In DSF Rounds, clause 5.4 of Article 5 – Work Programme, states that,
notwithstanding any other provision of this Contract, in the event the contract
area is reduced due to denial of clearances by government agencies, then the
Government (acting through DGH) is empowered to exercise such powers
of proportionate reduction of the Bid Work Programme, on the
recommendations of the Management Committee.
In case, the contractor does not exercise his option within three months but
proposes to relinquish the contract area later, liquidated damages shall be
payable as per the rates in article 5.2.
• In DSF bid round III and Special rounds, according to clause 5.4 (d), of
Article 5 – Work Programme, if delay due to lack of statutory and other
clearances is beyond 2 years and verified by DGH, the contractor would be
permitted to relinquish the contract area without payment of liquidated damages
as specified in article 5.2. in such cases the application for such reduction/ exiting
should be made within 30 days of the expiry of the 2-year period from the date
of application for clearance. Any delay attributable to the contractor shall not be
considered in the above mentioned 2-year period.
• Further in clause 5.4(b) of Article 5 – Work Programme, if contractor does not
exercise this option within three months of receipt of the communication of
reduction of area but proposes to exit from the contract later, an LD will be levied
53Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
to the extent of unfinished committed work programme, proportional to the
reduced area.
iv. Under Coal Bed Methane (CBM) Contract
• As per the MoPNG notification, “Policy framework for early monetization of Coal
Bed Methane” dated April 11, 2017, basis Clause 2.5, DGH is empowered to
reduce Minimum Work Programme (MWP) in proportion to the contract area
if the contract area is reduced by the government for any reason. If the contractor
does not accept the reduction in contract area, operator would be permitted to
exercise exit option from the contract without payment of Cost of Unfinished
Work Programme (COUWP)
• As per the MoPNG notification, “Policy framework for early monetization of Coal
Bed Methane” dated April 11, 2017, basis Clause 2.7, in cases of inordinate
delays in granting clearances i.e., beyond 2 years in any block, the contractor if
exercises its exit option, will be permitted to exit from the block without payment
of Cost of Unfinished Work Programme. DGH is empowered to review and
examine such cases and approve exit option exercised by the Contractor
from the CBM contract. Further, policy dated April 11, 2017, for “Early
monetization of CBM” is applicable for all present and past cases of CBM Blocks.
• Accordingly to Clause 5.5 (d) of Article 5 – Work Programme, if there is a
denial or delay of necessary clearances or licenses by the Government or State
Governments for part of the contract area, and the delay exceeds 2 years for
reasons not attributable to the operator, the operator can either relinquish the
contract without paying Liquidated Damages (as specified in Article 5.4) or
seek approval from the Government for a proportionate reduction in the
Committed Work Programme (CWP), proportional reduction of the license fee,
and amendment of the license.
The detailed relevant provisions under various contractual regimes may be referred in
Annexure 4.3.3.
54Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.3.3. Recommendation
A policy guideline applicable for contract areas under various contractual regimes
i.e., PSC, RSC, DSF and CBM may be issued to effect following:
a) If any clearances required for conducting Minimum Work Programme (MWP) or
Committed Work Programme (CWP) under the exploration phase or Bid Work
Programme (BWP) under the development phase, in the entire block or part of it,
has been denied or delayed by the state or central government, or respective
ministries or agencies, for over a period of two years, a contractor may claim
proportionate reduction in contract area and work programme.
b) The approvals, clearances or permits mentioned in a) shall include – grant of
PEL/ PML, Environment related Clearances (EC), Eco-Sensitive Zone (ESZ)
Clearance, Forest Clearance (FC), Wildlife Clearance, Coastal Regulation Zone
(CRZ) Clearance and Ministry of Defence Clearances.
c) To qualify the claim for reduction, as mentioned in above (a), the contractor shall
demonstrate substantiated efforts to obtain the necessary approvals and provide
timely intimation to the MC within a period of 6 months from the date of such
application submitted and at such further instance as the MC may direct
thereafter.
d) The above provision, as specified in (a), would be available provided the
contractor submits such application for proportionate area reduction within 90
days of receiving denial or expiry of two-year period of delay or expiry of current
phase, whichever is earlier.
e) The Government approval shall be required for such cases specified in above in
(a), based on recommendations of the Management Committee (MC).
f) If the contractor decides not to accept any reduction in contract area and work
programme or does not concur with the proposed reduction by the MC or the
government, then the contractor should be permitted to exit from the contract
without payment of Liquidated Damages, subject to prior approval from the
government. However, this provision shall be available to be exercised by the
contractor within 30 days of receiving approval of CWP/contract area reduction.
55Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Logic adopted for formulating recommendation
Currently, the CWP and area reduction in the PSC blocks is existent and power is
delegated to DG, DGH.
The recommendation standardizes the approval process by setting clear timelines,
thereby enhancing ease of doing business in the sector.
5.4. Bank Guarantee (BG) renewal towards
Committed/Minimum/ Bid Work Programme
5.4.1. Description of the issue
Under existing contractual regimes, operators are required to furnish a Bank Guarantee
(BG) equivalent to the Liquidated Damages (LD) calculated based on the pre-defined
rates specified in the respective contracts. This requirement serves as a financial
safeguard or deterrent to ensure the fulfilment of contractual obligations, especially the
work programme commitments. However, during the renewal of the BG, operators are
mandated to secure an amount that covers the entire work programme, including portions
that have already been completed.
This imposes an additional financial burden on operators as they are required to continue
to furnish BG for the portions of the work programme that they have already completed.
Recognizing these challenges, the General Financial Rules (GFR) 2017 have been
amended to allow the use of Surety Bonds as an alternative to BGs. Issued by insurance
companies and approved by the Ministry of Finance, these Surety Bonds provide a viable
and efficient substitute, addressing the limitations of the existing framework.
5.4.2. Relevant provisions under various contractual regimes
i. Amendment to General Financial Rules (GFR), 2017 by Ministry of Finance to
include Insurance Surety Bonds as Security Instrument
• According to rule 170(i) of Amendment to GFR 2017, The bid security may be
accepted in the form of Insurance Surety Bonds, Account Payee Demand Draft,
Fixed Deposit Receipt, Banker's Cheque or Bank Guarantee from any of the
Commercial Banks or payment online in an acceptable form, safeguarding the
purchaser's interest in all respects.
• According to rule 170 (ii) of Amendment to GFR 2017, Performance Security
may be furnished in the form of Insurance Surety Bonds, Account Payee
Demand Draft, Fixed Deposit Receipt from a Commercial bank, Bank Guarantee
from a Commercial bank or online payment in an acceptable form safeguarding
the purchaser interest in all respects
ii. Under Production Sharing Contracts (PSC)
• Clause 29.2 of Article 29 – Guarantees, contractor must furnish a Bank
Guarantee (BG) in favor of Government an amount equal to 35% of the
company's participating interest share of the total estimated annual expenditure
in respect of the Minimum Work Programme to be undertaken by the contractor
in the contract area during the relevant year of a Phase subject to Article 29.3.
56Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
• Clause 29.3 (a) of Article 29 – Guarantees, states at the end of each year, BG
shall be automatically renewed for an amount equal to a company’s participating
interest share of 35% of the total estimated expenditure in respect of the
Minimum Work Programme to be undertaken for the following year of an
exploration phase, unless the contractor has terminated the contract in
accordance with the terms thereof. The guarantee shall be renewed at the end
of each year positively 30 days before the expiry of the guarantee period.
• Clause 29.3 (b) of Article 29 – Guarantees, states that after the completion
and due performance of the Minimum Work Programme of a particular
Exploration Phase, the guarantee will be released in favor of the Company on
presentation to the bank of a certificate from the Government that the obligation
of the Contractor has been fulfilled and the guarantee may be released, subject
to Article 29.4.
iii. Under Revenue Sharing Contracts (RSC)
• Clause 27.1 (a) of Article 27 – Guarantees requires the contractor to furnish a
Bank Guarantee (BG) in favor of the Government. The amount, as specified in
Clause 27.2, corresponds to Liquidated Damages calculated using the rates in
Article 5.4. This BG must be valid for the 3-year period of bid commitments
outlined in Article 5.1, with a claim period of 60 days. The guaranteed amount
for each contractor group member is proportional to their individual Participating
Interest.
• Based on this clause, while renewing the BG, contractors are required to furnish
an amount equivalent to the Liquidated Damages for all activities outlined in the
initial committed work plan, rather than just for the uncompleted work. This
requirement places a significant financial burden on operators.
iv. Under Discovered Small Fields (DSF) Contract
• Clause 27.1 (a) of Article 27 – Guarantees mandates each of the companies
constituting the contractor shall procure and deliver to the Government within 30
days from the effective date of this contract an irrevocable, unconditional bank
guarantee from a reputed bank of good standing in India, acceptable to the
government, in favor of the government, for the amount specified in Article 27.2
and valid for the period (3, 4, 6 years as the case may be) specified in Article 3.2
with claim period of 90 days, in a form provided at Appendix E.
• According to Clause 27.2 (a) of Article 27 – Guarantees, the Bank Guarantee
referred to in Article 27.1 (a) above shall be for an amount calculated at rates
specified in Article 5.2. in respect of the bid work program specified in article 5.1,
provided that in the absence of any Bid Work Program stipulated in Article 5.1,
the bank guarantee shall be submitted for a minimum guarantee of equivalent
amount of USD 0.15 million, USD 0.23 million, and USD 0.30 million respectively
for contract area in on-land, shallow water, and deep-water.
• Basis Clause 27.2 (b) of Article 27 – Guarantees, the guarantee will be
returned to the company, provided that a bank guarantee submitted in respect
of the minimum amount shall be returned on commencement of commercial
production or on completion of period stipulated in Article 3.2 of RSC, whichever
is earlier after the completion and due performance of the Bid Work Programme.
57Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
v. Under Coal Bed Methane (CBM) Contract
Till CBM Round IV
• Clause 26.1 (a) of Article 26 – Financial and Performance Guarantees
mandates the contractor to furnish an irrevocable, unconditional Bank
Guarantee (BG) in favor of Government with an amount as per Clause 26.2
which is equal to a company's participating interest share and shall be 35%
of the total estimated annual expenditure in respect of the work
programme to be undertaken by the contractor in the contract area during
each year of a Phase up to Phase-II, and subject to Article 26.3.
• According to Clause 26.3 (a) of Article 26 – Financial and Performance
Guarantees, the amount referred to in Article 26.2 shall be automatically
adjusted at the end of each Year for an amount equal to a Company's
Participating Share of 35% of the total estimated expenditure in respect of
the work programme to be undertaken for the following year of the relevant
phase till Phase-II. The guarantee shall be renewed at the end of each year
positively 30 days before the expiry of guarantee period.
• Basis Clause 26.3 (b) of Article 26 – Financial and Performance Guarantees,
at the end of the relevant phase, the guarantee will be released in favor of the
contractor on presentation to the bank of a certificate by the Government that
the obligation of the contractor has/have been fulfilled and the guarantee may
be released.
In Special CBM Round
• Clause 27.1 (a) of Article 27 – Guarantees mandates the contractor to furnish
an irrevocable, unconditional Bank Guarantee (BG) in favor of Government with
an amount as per Clause 27.2 which shall be equal to the Liquidated Damages
computed by applying the rates specified in the table in Appendix I. The
amount of guarantee of the Members comprising the Contractor under this
Contract shall be to the extent of their individual Participating Interest.
The detailed relevant provisions under various contractual regimes may be referred in
Annexure 4.3.4.
58Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.4.3. Recommendation
A policy guideline applicable for contract areas under various contractual regimes
i.e., RSC, DSF and CBM may be issued to effect following:
a) During Bank Guarantee (BG) renewal process (post completion of the time
duration of BG provided in the contract), contractor should be allowed to submit
BG amount equivalent only to the value of the uncompleted/ pending work
programme as intimated/vetted by the DGH.
b) The contractor may be allowed to submit an unconditional and irrevocable Surety
Bond against a new or existing Bank Guarantee (BG) of an equivalent amount
defined in the contract or Notice Inviting Offers (NIO).
Logic adopted for formulating recommendation
The recommendation streamlines BG renewal process, and reduces capital lock-up,
introduces contractual safeguards, ensuring consistency and uniformity by aligning
financial commitments with actual project progress.
5.5. Field Development Plan (FDP) approvals of PSC blocks
5.5.1. Description of the issue
According to the guidance document titled “Guidance Document for Online Submission
of PSC Processes as per DGH Notifications dated April 25, 2020, and July 12, 2021”, the
contractor must obtain an Operating Committee Resolution (OCR) before submitting the
FDP. In the OCR, each party is required to agree on the technical activities proposed in
the FDP.
Further, as per the contract, the contractors are required to submit the FDP to the
Management Committee (MC) within 200 days of declaring an oil discovery (Clause 10.7)
and within one year of discovery for gas projects (Clause 21.5.6).
However, it has been observed that delays often arise between the parties while obtaining
OCR, particularly when a government nominee i.e., NOCs holds a Participating Interest
along with private operators. These conflicts often consume considerable time, resulting
in FDP submissions being delayed until close to the deadline, creating additional
procedural burdens.
Additionally, if the FDP is approved after the annual budget has been approved, the
operator has to seek further approval for any additional CAPEX incurred, which affects
project timelines and cost structures.
5.5.2. Relevant provisions under various contractual regimes
i. Under Production Sharing Contract (PSC)
• According to Clause 10.7 of Article 10 - Discovery, Development and
Production, If the Contractor declares the Discovery a Commercial Discovery
after taking into account the advice of the Management Committee as referred
59Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
in the Article 10.6, within two hundred (200) days of the declaration of the
Discovery as a Commercial Discovery, the Contractor shall submit to the
Management Committee a comprehensive development plan of the
Commercial Discovery.
• According to Clause 10.8 of Article 10 - Discovery, Development and
Production, A proposed development plan submitted by the Contractor
pursuant to Article 10.7 may be approved by the Management Committee within
110 days of submission thereof or 80 days of receipt of any additional information
requested by the Management Committee. In case the Management Committee
requires any reasonable additional information, the same shall be requested by
it within 80 days from the submission of the development plan. The Contractor
shall provide such additional information within 30 days from the request by the
Management Committee. If, within a period of 110 days after submission of a
proposed development plan or 80 days from the receipt of any additional
information, where asked by the Management Committee, the Management
Committee fails to convey a decision to the Contractor, the Contractor shall have
option to submit the proposal to the Government. Also, where, the Management
Committee rejects the development plan of the Contractor, the Contractor can
submit the development plan for the approval of the Government. The
Government shall respond on the proposed development plan submitted by the
Contractor within 110 days. In case Government refuses to approve the
proposed development plan, it shall convey the reasons for such refusal and the
Contractor shall be given opportunity to make appropriate modifications to meet
concerns of Government and the provisions of the foregoing Article and re-
submit the plan within 90 days from the date of receipt of refusal from the
Government.
• According to Clause 10.10 of Article 10 - Discovery, Development and
Production, Work Programmes and Budgets for Development and
Production Operations shall be submitted to the Management Committee
as soon as possible after the approval of a Development Plan under Article 10.8
and thereafter not later than 31st December each Year in respect of the Year
immediately following.
• According to Clause 10.13 of Article 10 - Discovery, Development and
Production, Proposed revisions to the details of a Development Plan or an
annual Work Programme or Budget in respect of Development and
Production Operations shall, for good cause and if the circumstances so
justify, be submitted for approval to the Management Committee
In case of discovery of Non-Associated Natural Gas (NANG)
• According to Clause 21.5.6 of Article 21 – Natural Gas, If the Contractor
declares the Discovery a Commercial Discovery after taking into account the
advice of the Management Committee as referred to in the Article 21.5.5, the
Contractor shall, within 1 year of the declaration of the Discovery as a
Commercial Discovery, submit a development plan for the development of
the Discovery to the Management Committee for approval. Such plan shall
be supported by all relevant information including, inter alia, the information
required in Article 10.7.
60Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
• According to Clause 21.5.7 of Article 21 – Natural Gas, Unless otherwise
agreed by the Management Committee, it shall consider the proposed
development plan and give their approval within 165 days of submission thereof
or 85 days from the receipt of the clarifications/additional information from the
Contractor. Any clarification/ additional information required by the Management
Committee shall be asked for within 85 days of receipt of the proposal from the
Contractor. The Contractor shall provide such additional information within 30
days from the receipt of request by the Management Committee. If the
Management Committee fails to convey its decision within 165 days from the
submission of the development plan or 85 days from the receipt of the
clarifications/additional information, whichever is later, the Contractor may
submit the development plan for the approval of the Government. Also, where,
the Management Committee rejects the development plan of the Contractor, the
Contractor can submit the development plan for the approval of the Government.
• According to Clause 21.5.8 of Article 21 – Natural Gas, Where the
development plan is submitted to the Government for approval pursuant to
Article 21.5.7, the Government shall convey its decision within 115 days from
the date of receipt of the proposal from the Contractor. Government, where it
considers necessary, may ask clarifications/additional information from the
Contractor within 85 days and shall convey its decision within 55 days from the
date of receipt of such clarifications/additional information.
• According to Clause 21.5.9 of Article 21 – Natural Gas, If the Government has
failed to approve or disapproves the Contractor’s proposed development plan,
within 115 days from receipt or within 55 days from the receipt of clarifications/
information from the Contractor as mentioned in the Article 21.5.8, the
Government shall advise the Contractor, in writing, of the reasons for such failure
or disapproval and the Government and the Contractor shall meet to discuss the
said development plan and the reasons for the said failure to approve or
disapproval, and use their best efforts to agree on appropriate modifications
thereto to meet the Government’s concerns or objections. Thereafter, the
Contractor shall have the right to resubmit, within 85 days of communication from
the Government, the proposed development plan duly amended to meet the
Government’s concerns. Such right of resubmission of the proposed
development plan shall be exercisable by the Contractor only once. The
Government will respond to the re-submitted plan within 115 days. If no such
plan is submitted to the Government within the above specified period, the
Contractor shall relinquish its right to develop such Gas Discovery and such
Discovery shall be excluded from the contract area.
The detailed relevant provisions under various contractual regimes may be referred in
Annexure 4.3.5.
61Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.5.3. Recommendation
A policy guideline applicable for contract areas under PSC regime may be issued to effect
following:
a) For blocks where the Annual Work Programme and Budget (AWP&B) is approved by
the Operating Committee (OC) , the Management Committee (MC) shall provide its
approval on or before the start of next financial year.
b) For blocks where the AWP&B is submitted without the approval by the OC, the MC
may consider approving the said AWP&B subject to concurrence of at least 75% of the
Participating Interest (PI) holding.
c) For Blocks with Government Nominee has a Participating Interest (PI) along with
Private Operators:
i. Brownfield Projects: Agreement on technical and cost alignment of the Field
Development Plan (FDP) or Revised Field Development Plan (RFDP), should
be reached within 60 days from the submission of the same by the operator to
the OC.
ii. Greenfield Projects: Agreement on technical and cost alignment of the FDP or
RFDP, should be reached within 120 days from the submission of the same by
the operator to the OC.
iii. The MC shall take a decision on the FDP/RFDP within 90 days from the date
of submission of the complete FDP/RFDP, provided OC approval has been
obtained.
iv. If technical agreement is not reached within the proposed timelines, the
contractor may call for an MC meeting within 15 days after the end of proposed
timelines to obtain the directions of the MC.
v. For all blocks where the static and dynamic model of the FDP/RFDP and the
reserves (OIIP & GIIP) are vetted by a DGH-empaneled third party, the review
may be expedited by the DGH.
d) The MC may concurrently approve the work programme and budget for the remaining
part of the current fiscal year during the MC meeting at which the FDP is approved.
62Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Logic adopted for formulating recommendation
The recommendation aims to expedite FDP approvals by introducing stringent timelines
to accelerate development, without undue delays. It also enhances operational efficiency
and aligns concurrent approvals for work programme and budget, driving transparency
and accountability in PSC block development.
5.6. Grant of Extension in Exploration/Development Period
across contractual regimes
5.6.1. Description of the issue
Currently, the Central Government or State Government based on recommendation from
the Central Government, grants the PEL for the Initial Exploration Phase (IEP) and any
applicable phase extensions as specified in the contracts.
However, in cases where Excusable Delays (or Extra days) or Force Majeure are granted,
the relevant exploration phase is extended, requiring PEL extension for the extended
duration to continue exploration activities. It has been observed that obtaining PEL
extension from the government can take 2-3 months of time-period post submission of
application for extension. Further, cases where other statutory approvals are already
delayed, an additional requirement of PEL extension may be deterrent.
5.6.2. Relevant provisions under various contractual regimes
i. Under Production Sharing Contract (PSC)
• Clause A of the policy for extension of exploration phases under NELP and Pre-
NELP production sharing contracts dated 04 April 2006, allows MC or the
Government to extend the overall exploration period by 6 months for completing
the unfinished work program, while maintaining the original terms and conditions
of the contract. Further extensions of up to 18 months are permitted based on
the terms outlined in the PSC.
ii. Under Revenue Sharing Contract (RSC)
• For all OALP rounds, as per clause 11.2.1 of Article 11 - Petroleum
Exploration License and Lease, the application for the petroleum lease along
with application fee, in respect of the proposed development area in respect of
offshore blocks shall be submitted by operator to the Government within 30
days from the approval of TAR pursuant to Article 10.
• For the OALP Rounds I to III, Clause 3.2 of Article 3 - License and Exploration
Period, specifies that the exploration period begins on the effective date and
consists of two phases: the Initial Exploration Phase includes 3 consecutive
contract years, with a provision for a single extension of up to 1 year for onland
and shallow water areas, and up to two extensions of 1 year each for deep water,
ultra-deep water, and specified basins.
• For OALP Rounds IV to VIII, Clause 3.4 of Article 3 - License and Exploration
Period, allows the contractor to extend the exploration period by up to 9
months for onland/shallow water/CBM blocks and up to 18 months for deep
63Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
water/ultra deep-water blocks by making a payment to the Government at least
30 days prior to the expiration of the Exploration Period.
iii. Under Discovered Small Fields (DSF) Contract
• According to Clause 11.1 of Article 11 – Petroleum Exploration License and
Petroleum Mining Lease, in the event existing discovery (lies), being a
discovered small field/ contract area operated by ONGC/OIL and the
license/lease has already been issued in favor of ONGC/OIL, the Government
hereby agrees that it shall approve and enable the transfer of the
license/lease, as applicable, by ONGC / OIL in favor of the contractor under
the provisions of rule 17 of the P&NG Rules. Provided that in the event that such
transfer could not be completed within 60 days of the execution of this Contract,
the issued License/Lease shall be terminated. The Contractor thereafter shall
submit forthwith an application for grant of Lease in respect of the contract area.
• According to Clause 11.2 of Article 11 – Petroleum Exploration License and
Petroleum Mining Lease, in the event the field/contract area did not have an
earlier lease already issued or such lease could not be transferred, the
Government shall on the application of the contractor grant to the
contractor a lease, to enable the contractor to carry out petroleum operations
in the contract area.
• Basis Clause 11.3 (b) of Article 11 – Petroleum Exploration License and
Petroleum Mining Lease, the lease shall be granted for an initial period of 20
years from the date of grant thereof subject to the lease period may be
extended by mutual agreement between the government and the
contractors for such period as may be agreed after taking into account the
balance recoverable reserve and balance economic life of the Field/ contract
area in the contract area from the expiry of the initial period. Provided that such
extension would be for a period up to 5 years or beyond as may be mutually
agreed or as per extant Government policies/ guidelines.
iv. Under Coal Bed Methane (CBM) Contract
• As per the clause 5 (vi) of policy for Extension of Exploration Phases for
Exploration and Production under Coal Bed Methane contracts dated November
17, 2007, first six months extensions may be granted by Steering committee in
terms of respective contract. Further, additional extensions of 6 months or
beyond 12 months and upto18 months, are permitted based on the terms
outlined in the policy.
• According to Clause 2.6 of MoPNG notification Policy framework for early
monetization of Coal Bed Methane dated April 11, 2017, if delay in grant of
Petroleum Exploration License (PEL) exceeds 2 years from the State
Government in any block, the Contractor if exercises exit option from the CBM
block, will be permitted to exit without paying cost of unfinished work
programme.
The detailed relevant provisions under various contractual regimes may be referred in
Annexure 4.3.6.
64Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.6.3. Recommendation
A policy guideline applicable for contract areas under various contractual regimes
i.e., RSC, DSF and CBM may be issued to effect following:
a) The Contractor may request a two-year extension of exploration/development
period, in addition to any extensions already provided in the contract, subject to
the payment of fees as provided:
i. For Onland/Shallow Water: USD 25,000 or its INR equivalent per month
or any part of the month for the duration of extension sought.
ii. For Deep Water/Ultra-Deep-Water Blocks: USD 50,000 or its INR
equivalent per month or any part of the month for the duration of extension
sought.
b) In addition to (a), two one-year free extension of exploration period may be
granted for blocks in Andaman basin and North-East region.
c) The above extensions shall be capped upto exploration period of 8 years for
Onland and Shallow water areas and upto 10 years for Deep Water and Ultra-
Deep Water areas, inline with HELP policy dated 30 March 2016.
Logic adopted for formulating recommendation
The recommendation provides contractors the flexibility to extend their exploration or
development period, addressing unforeseen delays and encouraging project
completion
5.7. Process for PSC extension applications and approvals
5.7.1. Description of the issue
Under the current PSC framework, Clause 1 of policy for granting extension to PSC dated
March 28, 2016, permits contractors to apply for contract extensions provided
applications are submitted at least two years before the contract expiry. However, there
is no provision to address situations where operators request an extension within this
two-year period.
This lack of flexibility creates uncertainty for contractors facing unforeseen delays or
challenges that arise closer to the end of the contract term, potentially impacting project
continuity, investment planning, and overall operational efficiency.
65Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.7.2. Relevant provisions under various contractual regimes
i. Under Production Sharing Contract (PSC)
• According to Clause 1 of the policy for granting extension to PSC dated March
28, 2016, operators are required to submit an approval request for contract
extension to MoPNG at least 2 years in advance of the expiry date of contract
with a copy to DGH. DGH is required to provide recommendations to MoPNG
within 6 months of submission of application by the operator. The Government
will take a decision on the request for extension within 3 months of receipt of the
proposal from DGH.
The detailed relevant provisions under various contractual regimes may be referred in
Annexure 4.3.7.
5.7.3. Recommendation
A policy guideline applicable for contract areas under PSC regime may be issued to
effect following:
a) The approval for condonation of delay in submission of PSC extension applications
upto a period of 6 months prior to the date of contract expiry may be delegated to
DG, DGH.
Logic adopted for formulating recommendation
The recommendation aims to streamline the approval process and reduce procedural
delays. The delegation of approval authority will provide operational flexibility,
minimize project disruptions and ensure timely contract management under PSC
regime.
5.8. Provisions for incentives on sale of natural gas to private
operators in Northeast region
5.8.1. Description of the issue
The existing gas price mechanism in the north-east region is characterized by the
coexistence of multiple gas prices, which poses significant challenges for private
operators. According to the New Domestic Natural Gas Pricing Guidelines, a subsidy of
40% on APM allocated natural gas is provided to the NOCs in the region. However, the
guidelines lack clarity in applicability of the subsidy for natural gas supplied by private
operators in the north-east region. This arrangement allows ONGC and OIL to benefit
from discounted gas prices and undermines the competitiveness of private companies.
5.8.2. Relevant provisions under various contractual regimes
• According to Clause 2 of notification titled “Price of APM natural gas produced
by National Oil Companies (NOCs)” dated 31 May 2010, the net consumer price
66Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
of natural gas produced by NOCs for customers in Northeast would be 60% of
APM price i.e., US $ 2.52/MMBTU, on NCV basis.
• According to Clause 12 of “New Domestic Natural Gas Pricing Guidelines,
2014”, 40% subsidy will be provided for gas supplied by NOCs (ONGC/OIL) in
Northeast region. Additionally, the subsidy would also be available to private
players to incentivize exploration and production.
The detailed relevant provisions under various contractual regimes may be referred in
Annexure 4.3.8.
5.8.3. Recommendation
A policy guideline applicable for natural gas supplied by operators may be issued to
effect following:
a) The subsidy of 40% on supply of natural gas may be extended to every
operator in the North-East region.
b) The subsidy mechanism proposed in (a), may be gradually tapered down over
the next 5 years.
5.9. Transfer of Participating Interest (PI) among existing PI
holders under a contract
5.9.1. Description of the issue
Under the existing contractual provisions of PSC, RSC, DSF and CBM regimes, PI
transfer within the existing parties of the contractor requires prior written consent from the
Government. However, this process involves a comprehensive technical, financial, and
legal due diligence for each case.
In such cases, as the PI holders have already undergone verification during the initial
contract award stage, evaluation for any change in PI among existing parties of the
contract may be foregone. Further, in many cases it has been observed that internal
transfer approval can take up to six months of time-period, leading to significant project
delays.
5.9.2. Relevant provisions under various contractual regimes
i. Under Production Sharing Contract (PSC)
• According to Clause 28.1 of Article 28 – Assignment of Participating
Interest, any Party comprising the Contractor may assign, or transfer, a part or
all of its Participating Interest, with the prior written consent of the Government.
ii. Under Revenue Sharing Contract (RSC)
67Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Till OALP Round VII
• According to Clause 26.1 of Article 26 – Assignment of Participating
Interest; any Member comprising the Contractor may assign, or transfer, a
part or all of its Participating Interest, with the prior written consent of the
Government.
In OALP Round VIII
• According to Clause 26.3 of Article 26 – Assignment of Participating
Interest, In case of any change in the status of a member or its shareholding
resulting in a change in its relationship with any company providing the
guarantee specified under Article 27.1(a) and 27.1 (b). Such change or changes,
as the case may be, shall be deemed as an assignment of Participating Interest
of the Member and the concerned Member shall seek prior written consent of
the Government for any such change or changes
• According to Clause 26.7 of Article 26 – Assignment of Participating
Interest, nothing in this Article 26 shall prevent a Party comprising the
Contractor from assigning or transferring a part or all of its Participating
Interest to an Affiliate, with the approval of the Government, provided that:
iii. Under Discovered Small Fields (DSF) Contract
• According to Clause 26.1 of Article 26 – Assignment of Participating
Interest, any Party comprising the Contractor may assign, or transfer, a part or
all of its Participating Interest, with the prior written consent of the
Government.
iv. Under Coal Bed Methane (CBM) Contract
• According to Clause 25.1 of Article 25 - Assignment of Participating Interest,
a Company may assign, or transfer, a part or in whole of its Participating Interest,
with the prior written consent of the Government.
Under SCBM Rounds
• According to Clause 26.1 of Article 26 - Assignment of Participating Interest;
any Member comprising the Contractor may assign, or transfer, a part or all of
its Participating Interest, with the prior written consent of the Government.
The detailed relevant provisions under various contractual regimes may be referred in
Annexure 4.3.12.
68Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.9.3. Recommendation
A policy guideline applicable for contract areas under various contractual regimes
i.e., PSC, RSC, DSF and CBM may be issued to effect following:
a) The Management Committee (MC) may be empowered to approve Participating
Interest (PI) transfer cases where contractor intends to transfer the PI within the
existing parties of the contract, subject to no change in operatorship.
b) The proposed provision for amendment in a) may continue to be signed by the
representative from the Government of India.
c) PI holders should be required to comply with all the existing conditions of the
contract.
Logic adopted for formulating recommendation
The recommendation aims to expedite the approval process and reduce project
delays, thereby promoting transparency and ease of doing business
5.10. Annual Work Programme (AWP) and Budget approval
under CBM regime
5.10.1. Description of the issue
Under CBM contracts, contractors are mandated to submit their Annual Work Program to
the Steering Committee by the 31st of December each year. However, since CBM
contracts do not include a cost recovery mechanism, the requirement for steering
committee approval of the annual work program adds a layer of procedural burden.
Streamlining this process could enhance operational efficiency by reducing regulatory
oversight.
5.10.2. Relevant provisions under various contractual regimes
i. Under Coal Bed Methane Contract (Round I-IV)
• According to clause 10.3 of Article 10 – Development and Production,
annual work programmes and budgets for development operations shall be
submitted to the steering committee as soon as possible after the approval of
the development plan and thereafter not later than 31st December of each year
immediately following.
The detailed relevant provisions under various contractual regimes may be referred in
Annexure 4.3.10.
69Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.10.3. Recommendation
A policy guideline applicable for contracts areas under CBM regime may be issued
to effect following:
a) Contractors may be allowed to submit the Annual Work Programme (AWP) and
Budget for development and production phase on a self-certification basis, with
an intimation to the Steering Committee, subject to no decline in production in
the last three years in the field.
Logic adopted for formulating recommendation
The recommendation aims to streamlines the approval process by granting
autonomy to the contractors, thereby improving the EoDB in the sector.
B. Recommendations for Short-term Resolution (within 1 year)
5.11. Flexibility to deploy new exploration technology/ methods
for meeting Minimum, Committed or Bid Work Programme
5.11.1. Description of the issue
The existing work programme requirements under PSC, RSC, DSF, and SCBM contracts,
allows swapping of traditional 2D seismic and 3D seismic survey against each other, to
meet the work program commitments. With advent of new emerging exploration
techniques such as Airborne Gravity Gradiometry and Electromagnetic Surveys, it is
observed that globally many E&P players are deploying such techniques to either
overcome any technical, operational or logistical challenges or to improve the exploration
outcomes. At present, operators are not adequately incentivized to consider such
techniques and adopt them to meet their work program commitments. This limits the
integration of new technologies which could accelerate exploration in logistically
challenging areas and potentially lead to new hydrocarbon discoveries.
However, from OALP round VIII onwards, new exploration technologies such as Gravity
Magnetic Potential API has been allowed for swapping with traditional 2D seismic and 3D
seismic survey.
5.11.2. Relevant provisions under various contractual regimes
i. Under Production Sharing Contracts (PSC)
• According to clause 4.1 of the MoPNG notification, Policy Framework for
Relaxations, Extensions and Clarifications at the development and Production
Stage under the PSC dated November 10, 2014, there is no provision in PSC
to swap 2D seismic survey program of MWP with 3D survey program which
may be required due to technical or logistical reasons.
70Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
• However, clause 4.2 states that DGH is empowered to approve the swapping
of 2D Acquisition Processing and Interpretation (API) data and 3D API data
with each other, where it is justified on the basis of technical and logistical
merits, after proper scrutiny on recommendations of MC. However, when the
contractor has bid for entire area for 2D seismic and full entire area for 3D
seismic, then substitution would not be allowed.
ii. Under Revenue Sharing Contract (RSC)
Till OALP Round VII,
• As per Clause 5.4 of Article 5 – Work Programme, DGH shall approve the
swapping of 2D Acquisition, processing and interpretation data and 3D
acquisition, processing and interpretation data with each other, in a manner
such that the weighted seismic programme quoted, and the marks obtained at
the time of bidding remains the same or are higher. In case of swapping of 2D
and 3D acquisition, processing and interpretation data, the LD will be levied as
per committed work programme.
Under OALP Round VIII,
• According to clause 5.7 of Article 5 – Work Programme, for blocks falling in
Category I basin, DGH shall approve the swapping of 2D acquisition,
processing and interpretation data and 3D acquisition, processing and
interpretation data with each other, in a manner such that the weighted
seismic programme quoted, and the marks obtained at the time of bidding
remains the same or are higher. In case of swapping of 2D and 3D acquisition,
processing and interpretation data, the LD will be levied as per committed work
programme.
For blocks falling in Category II/III basin, DGH shall permit the swapping of
committed work programme under phase-I of exploration period, with
other work programme(s) as per ratios defined in Appendix–M. In case the
swapping is permitted for any block, the LD will be levied as per committed work
programme. Note that the mandatory exploratory wells, including wells opted for
drilling for retaining relinquished area, under Phase-II (Part A& B) of exploration
period for blocks falling in Category-II/III basins, shall not be interchangeable
with any other work programme.
iii. Under Discovered Small Fields (DSF) Contract, there is no clause for swapping in
Bid Work Programme
iv. Under Coal Bed Methane (CBM) Contract
Till CBM Round IV, there are no provisions for swapping in Committed Work
Programme
In Special CBM round,
• According to Clause 5.4 of Article 5 – Work Programme, DGH shall approve
the swapping of 2D Acquisition, Processing and Interpretation data and 3D
71Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Acquisition, Processing and Interpretation data with each other, in a manner
such that the weighted seismic programme quoted, and the marks obtained at
the time of bidding remains the same or are higher. In case of swapping of 2D
and 3D Acquisition, Processing and Interpretation data, the LD will be levied as
per Committed Work Programme.
The detailed relevant provisions under various contractual regimes may be referred in
Annexure 4.3.11.
5.11.3. Recommendation
A policy guideline applicable for contract areas under various contractual regimes
i.e., PSC, RSC, DSF and CBM may be issued to effect following:
a) The existing provisions for swapping MWP/CWP/BWP as provided in OALP
Round VIII (Appendix-M) should be extended to the OALP Rounds I-VII and
other contractual regimes.
b) For emerging exploration techniques such Airborne Gravity Gradiometry
(AGG) or Artificial Intelligence (AI) / Machine Learning (ML) driven seismic
survey methods,
i) Contractors may be allowed the flexibility to swap MWP/CWP/BWP
with such techniques , subject to the Management Committee (MC)
approval. The said data of survey should be generated/acquired by
the contractor but not purchased from NDR.
ii) Standardized conversion equivalence ratios would be pre-specified
by Directorate General of Hydrocarbons (DGH) for ready reference of
the industry based on the GIPIP guielines. DGH may form a standing
committee consisting of national and international exploration experts
to review and update these ratios every two years.
Logic adopted for formulating recommendation
The recommendation aims to spur the adoption of advanced technologies, thereby
improving results from exploration activities and increase possibilities for new
discoveries.
72Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.12. Flexibility to swap exploration activities across contracts
within the same or higher category basin
5.12.1. Description of the issue
Under the current provisions of PSC, RSC, CBM and DSF contracts, contractors are
required to complete activities as outlined in their work programmes. However, in case
the initial exploration efforts do not yield the envisioned results, the contractor is still
required to complete the entire work programme and incur the associated capital
expenditure. This mechanism limits the flexibility for contractors to reallocate resources
for exploration efforts to other contract areas that may offer better prospects based on
evolving geological insights.
At present, there is no provision in these contracts that allows contractors to transfer or
swap CWP/MWP/BWP activities between different contract areas within the same or
higher basin category and geological regions (Onland/Shallow-water/Deep-water), which
could have enabled efficient utilization of resources.
Note: Higher Category basin denotes either Category II basins (basin which have
contingent resources pending commercial production) or Category III basins (basin which
have prospective resources awaiting discovery). Since, Category II and Category III
basins are relatively less explored than Category I, therefore swapping in lower Category
basin may not be considered.
73Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.12.2. Recommendations
A policy guideline applicable for contract areas under various contractual regimes i.e.,
PSC, RSC, DSF and CBM may be issued to effect following:
a) Contractors may be allowed to swap MWP/CWP/BWP activities across
contracts but within the same contractual regime (Pre-NELP PSC, NELP PSC,
OALP, DSF and CBM) and within the same or higher basin category and
geological region (Onland/ Shallow-water/Deepwater), provided the number of
units of each activity remains same.
b) The above provision stated in (a) shall be available to the contractor subject
to:
i. All remaining work programme activities or equivalent value of work
programme in the transferor block shall be completely swapped.
ii. The swapped work programme shall be completed by the contractor
within the remaining exploration/development period of transferor block
as on date of swapping.
iii. No extensions except for Extra Days or Force Majure to the
exploration/development period as provided in the relevant contracts
shall be provided for the swapped work programme.
iv. The time taken for swapping the work programme shall not be
considered as Extra Days.
v. Swapping may only be undertaken if no Extra Days have been availed
in the transferor block.
c) The swapping proposed in above (a), shall be subject to the Management
Committee (MC) approval.
Logic adopted for formulating recommendation
The recommendation allows operators to redirect efforts towards either the same or
higher category basins (basins which are relatively less explored) based on updated
geological data, thereby optimizing exploration and development outcomes. Such
measures may encourage more adaptive and economically viable exploration
activities.
5.13. Field Handover process in DSF contracts
5.13.1. Description of the issue
At present, there is no Standard Operating Procedure (SOP) for the handover of DSF
between the transferor and the transferee , resulting in significant delays due to issues
related to land maintenance and transfers, PML approvals, or EC certificate transfers.
This delay can disrupt production timelines and lead to financial consequences, including
increased costs or lost revenue opportunities. There is also ambiguity in the provision for
transfer of the assets in the DSF contracts particularly related to transfer of assets at zero
value, leading to issues related to land transfer. This may not only affect parties but can
74Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
also impact the broader industry landscape, delaying the development of resources that
are critical for ensuring energy supply.
5.13.2. Recommendation
A policy guideline applicable for contract areas under DSF regime may be issued
to effect following:
a) For land owned by the transferor,
i. The transferee may choose to purchase the land from the transferor,
subject to the consent of the transferor and at the rates determined by
the relevant government authority.
ii. Alternatively, the transferee may choose to lease the land from the
transferor at the rates agreed upon by the parties.
b) For land leased from a third party,
i. The transferor shall provide for the land maintenance, including rental
payments, for upto a period of two years from the date of signing of the
contract or till the field is handed over to the transferee, whichever is
earlier.
ii. The transferee shall assume responsibility for land maintenance,
including rental payments, after the initial two-year period or the field
handover, whichever is earlier.
iii. The above provisions as stated in (b). i) and (b). ii) shall be available,
provided the transferee signs an amendment to the principal contract,
confirming the above provisions.
c) The NOCs shall submit the inputs for SOP for field handover process to DGH
within a period of one month. The DGH shall review and adopt the SOP
accordingly.
Logic adopted for formulating recommendation
The recommendation aims to mitigate delays and ambiguities currently experienced
during asset transfers under DSF handover process. The standardized approach will
enhance the EoDB and streamline the transfer process, fostering smoother
operations and development within the sector.
75Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.14. Exchange rate conversion methodology across contract
regimes
5.14.1. Description of the issue
Under the current contractual framework, different exchange rate conversion
methodologies are applied across contract regimes. For instance, PSCs uses exchange
rates published by the State Bank of India (SBI), while RSCs from OALP Rounds I to VII
use rates determined by Financial Benchmarks India (FBIL) or RBI. OALP Round VIII
utilizes exchange rates published by the Reserve Bank of India (RBI), FBIL, or RBIL.
Meanwhile, DSF Rounds I and II employ London Interbank Offered Rate (LIBOR) rates,
DSF Round III and Special Rounds use the Secured Overnight Financing Rate (SOFR),
and CBM contracts also rely on RBI exchange rates.
These inconsistencies in exchange rate conversion methodologies create significant
accounting and auditing challenges for contractors managing assets across multiple
contractual regimes. The lack of a standardized approach complicates financial reporting,
cost calculations, and compliance processes, as contractors must adapt to different
requirements depending on the contract regime.
5.14.2. Relevant provisions under various contractual regimes
i. Under Production Sharing Contract (PSC)
• According to Clause 1.6.1 of Appendix C – Accounting Procedure, Section
1 – General Provisions, For conversion purposes between United States
Dollars and Indian Rupees or any other currency, the monthly average of the
daily mean of the buying and selling rates of exchange as quoted by the State
Bank of India (or any other financial body as may be mutually agreed by the
Parties) for the Month in which the revenues, costs, expenditures, receipts or
income are recorded, shall be used. However, in the case of any single non-US
Dollar transaction in excess of the equivalent of fifty thousand (50,000) US
Dollars, the conversion into US Dollars shall be performed on the basis of the
average of the applicable exchange rates for the day on which the transaction
occurred.
ii. Under Revenue Sharing Contract (RSC)
Under OALP Round VII
• According to Clause 15.6 of Article 15 – Revenue Share, The Contractor shall
remit Royalty and Government share of Revenue in Indian Rupees (INR). For
conversion purposes between United States Dollars and Indian Rupees or any
other currency, the Reserve Bank of India Reference Rate of Exchange for
the transaction day on which the revenues receipts or income are recorded shall
be used.
• According to Appendix G – Performa of Bank Guarantee to be provided
pursuant to Article 29, Bank Guarantee can be submitted in INR. For exchange
rate from USD to INR, exchange rate published by FBIL for the same day or
immediate previous working day can be used.
Under OALP Round VIII
76Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
• According to Clause 15.6 of Article 15 – Revenue Share, The Contractor shall
remit Royalty and Government share of Revenue or any other Government dues
under the Contract in Indian Rupees (INR). For conversion purposes between
United States Dollars and Indian Rupees or any other currency, the
RBI/FBIL/RBI authorized agency reference rate of Exchange on the
transaction day on which such remittance is made shall be used.
iii. Under Discovered Small Fields Contract (DSF)
Under DSF Round I & II
• According to Clause 15.5 of Article 15 – Revenue Share, The Government's
share of Revenue for a month shall be paid by the Contractor to the Government
latest by the end of succeeding Month. In the event of any failure to pay
Government's share of Revenue within the due date, the Contractor shall pay
interest compounded on daily basis for the entire period of delay at LIBOR as
defined in Article 1.60 plus two (2) percentage points used.
Under DSF III & SDSF
• According to Clause 15.6 of Article 15 – Revenue Share, The Government's
share of Revenue for a month shall be paid by the Contractor to the Government
latest by the end of succeeding Month. In the event of any failure to pay
Government's share of Revenue within the due date, the Contractor shall pay
interest compounded on daily basis for the entire period of delay at “SOFR plus
0.42826 percentage points” plus 2 (two) percentage points/200 basis points.
iv. Under Coal Bed Methane Contract (CBM)
Under CBM Round I to IV
• According to Clause 17.3 of Article 17 – Currency and Exchange Control
Provisions, The rates of exchange for the purchase and sale of currency by the
Contractor and its constituents shall be the prevailing rates of general application
determined by the Reserve Bank of India or such other financial body as may
be mutually agreed by the Parties and, for accounting purpose under this
Contract, these rates shall apply as provided in Section 1.6 of Appendix C.
points.
Under SCBM Round
• According to Clause 15.6 of Article 15 – Revenue Share, The Contractor shall
remit Royalty and Government share of Revenue in Indian Rupees (INR). For
conversion purposes between United States Dollars and Indian Rupees or any
other currency, the Reserve Bank of India Reference Rate of Exchange for
the transaction day on which the revenues receipts or income are recorded shall
be used
The detailed relevant provisions under various contractual regimes may be referred in
Annexure 4.3.13.
The detailed analysis of RBI and SBI exchange rate may be referred in Annexure V
77Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.14.3. Recommendation
A policy guideline applicable for contract areas under various contractual regimes
i.e., PSC, RSC, DSF and CBM may be issued to effect following:
a) Operators with more than one block may be allowed the flexibility to choose a
single, standardized exchange rate methodology, as prescribed by the RBI or
SBI, for all their existing contracts across regimes on prospective basis.
Contractors
b) with more than one block may be allowed the flexibility to choose a single,
standardized exchange rate methodology, as prescribed by the RBI or SBI, for
all their existing contracts across regimes on prospective basis. Proposals for
such cases for a standardized exchange rate conversion methodology may be
done on a self-certification basis with an intimation to the MC.
c) The exchange rate methodology as stated in above (a) shall supersede the
previously specified methodology in the respective contracts.
Logic adopted for formulating recommendation
Since operators use either RBI or SBI prescribed exchange rates, extending the
flexibility to choose the methodology is advisable. Over time, it has been observed
that both exchange rates show nominal differences. The recommendation aims to
standardize the exchange rate conversion methodology across all contractual
regimes This uniform approach eliminates the complexities and inconsistencies
currently experienced in financial reporting by the contractors
5.15. Open-Source National Data Repository (NDR)
5.15.1. Description of the issue
In India, seismic and other geological data are currently not available as open-source
information, which restricts access for potential investors and limits transparency in the
country's energy sector. Such data, if provided accessible to the public could attract
Indian and global players by providing them with the critical information needed to identify
exploration and production opportunities.
Open sourcing the data could also foster a collaborative environment among E&P
companies, encouraging Joint Ventures (JVs), resource sharing, and technological
partnerships. This initiative would allow the use of the data for various purposes, including
training Large Language Models (LLMs) to improve the industry’s understanding of
geological surveys and subsurface conditions.
78Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.15.2. Recommendation
A policy guideline may be issued to effect following:
a) Open sharing of NDR data at zero charge may be enabled to MSME, startups and
academic institutions.
b) NDR data may be integrated with the repositories of the National Oil Companies
(NOCs), such as ONGC and OIL, and other ministries such as Ministry of Mines,
Ministry of Coal, Ministry of Earth Sciences, Central Ground Water Board etc.
ensuring seamless access to comprehensive datasets, including seismic, well,
and other geological information.
c) The cost of data transfer and associated media shall be borne by the beneficiary.
d) Transfer of data should comply with the government guidelines, including
restriction on sharing with entities or countries subject to government-imposed
limitations
Logic adopted for formulating recommendation
The recommendation promotes knowledge sharing, collaborative ventures, and
technological advancements through enhanced data accessibility. thereby
encouraging innovations in the oil and gas industry
5.16. Collaborative resource-sharing among operators in E&P
sector
5.16.1. Description of the issue
E&P operators in the oil and gas industry face significant challenges due to the substantial
capital expenditure required to acquire and maintain specialized equipment, tools, and
materials. These challenges are particularly acute during the development and production
phases, where timely access to critical resources is essential.
Resource-sharing among operators offers a solution by pooling assets, which reduces
both capital and operational costs. This can include shared use of drilling resources,
infrastructure, and other tangible assets, leading to more cost-efficient operations.
Further, in emergency situations, access to shared resources allows for quicker response
times and minimizes operational downtime.
This collaborative approach not only streamlines exploration activities but also
accelerates project timelines and improves overall operational efficiency.
79Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.16.2. Recommendation
A policy guideline may be issued to effect following:
a) The existing Upstream Portal should be upgraded as a dedicated and centralized
marketplace for the upstream oil and gas sector for resource transfer and sharing.
This marketplace, operating on a lease or sale model, would allow operators to
access a wide range of equipment, such as drilling rigs, and various services
such as inventory pooling and inventory loan from different providers.
Logic adopted for formulating recommendation
The recommendation aims to promote resource sharing among the operators which
will enhance operating efficiency and reduce capital expenditure through facilitating
access to shared equipment and services.
80Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Part B: Issues to be resolved with cross-ministerial support
Besides the issues highlighted in Part A of the section, there are several identified issues
that remain under review and require either further analysis or cross-ministerial
collaboration before final recommendations can be submitted. A brief summary of some
of these issues along with potential solution suggested by the operator is provided below:
• Environmental Clearances (EC): Procedural delays remain a significant challenge.
Proposed solutions include a single-window clearance system, aligning EC validity
with the Production Mining Lease (PML) period, and introducing a unified consent
process for social licenses under a single application.
• Forest Clearances (FC): The requirement for approvals from the Standing Committee
of the National Board for Wildlife (SC-NBWL) creates delays, particularly for projects
within protected areas (PAs) and eco-sensitive zones (ESZs). Potential measures
suggested including creation of a land bank for Compensatory Afforestation and
delinking FC approvals from the Parivesh portal’s EC application process.
• Taxation on Procurement of Goods and Services: Contractual disputes have arisen
regarding the applicability of the concessional 12% GST rate, the imposition of GST-
TDS on advance payments for Non-Resident Taxable Persons, and other taxation
ambiguities, leading to litigation and project delays. Resolution requires policy clarity
and engagement with the Ministry of Finance (MoF).
• Deductions under Section 42 for Revenue-Sharing Contracts (RSC): Issues related
to tax deductions for RSC blocks remain unresolved and require policy intervention to
ensure clarity and consistency across contracts.
• One-Time PESO Approval for HSD Tanks: Unlike approvals granted for pressure
vessels, there is no one-time PESO license for High-Speed Diesel (HSD) tanks used
in mobile rigs. A streamlined licensing framework as a potential solution would reduce
administrative burdens.
• Approvals from the Standing Committee of the National Board for Wildlife (SC-
NBWL): Projects located in eco-sensitive zones (ESZs) outside protected area
boundaries face delays in securing approvals despite due recommendations from the
State Board for Wildlife.
• Multiple Statutory Approvals and Inter-Departmental Conflicts: E&P projects require
clearances from multiple central and state government agencies, leading to delays
and cost overruns. A streamlined single-window clearance mechanism has been
proposed to address these inefficiencies.
• Global Tender Enquiries (GTEs): The existing regulation does not permit GTE for
procurements up to Rs. 200 Crores in various categories including goods, services,
and turnkey projects. However, the DoE has allowed exceptions valid until the end of
December 2025 for certain critical operational items and services, provided these
exceptions are approved by the Secretary of the MoPNG. While the GTE exemption
81Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
applies to goods procured on a Nomination or Proprietary basis, there is ambiguity
regarding whether the exemption also pertains to services procured in the same way.
• Extension of Tax Holiday under Income Tax Act, 1961: A restoration of the 100% tax
holiday under Section 80IB (9) should be granted for undertakings engaged in natural
gas exploration and production where commercial operations commenced post-31st
March 2017. This is suggested to be extended to a minimum of 15 years, aligning with
tax incentives provided to infrastructure sectors such as power generation.
• VAT Refund on Natural Gas: Until natural gas is brought under the GST regime, a
VAT refund mechanism is suggested to be introduced to ease the tax burden on
operators. China offers a 7% VAT refund along with a 7% state subsidy for CBM
production, a model that could be considered for India.
• Depletion Accounting Based on 2P Reserves: The current ICAI guidance mandates
using Proved Developed Reserves (1P) for calculating the Unit of Production (UOP)
rate. However, it is suggested that industry players be given the flexibility to use either
1P or Proved and Probable Reserves (2P), in alignment with IFRS standards, to allow
for a more accurate reflection of future economic benefits and asset depreciation.
• Reconsideration of GST Levy on Corporate Guarantees: Corporate guarantees, being
fiduciary in nature, is suggested not to be classified as taxable services. The
imposition of GST on such guarantees could discourage financial support
mechanisms that are critical to capital-intensive sectors, warranting a review of this
policy.
The JWG proposes that such issues be addressed in the next phase of deliberations,
involving wider collaboration with other ministries, such as the Ministry of Environment,
Forest and Climate Change (MoEFCC), the Ministry of Mines (MoM), and the Ministry of
Finance (MoF), etc. This collaborative approach will aim to resolve cross-jurisdictional
concerns effectively and ensure enhanced EODB for the upstream sector.
82Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Annexure
83Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
6. Annexures
6.1. Annexure I: Definitions
1 “Article” means an article of the respective Contract and the term “Articles” means
more than one Article.
2 “Bid Work Programme” means the Work Programme specified by the Contractor in
its Bid that is provided under Article 5 of the DSF contract.
3 “Contract” means agreement between contractor and Government for the purpose of
carrying out Petroleum Operations
4 “contract area” means that part of the Original contract area or any portion of the said
area remaining after relinquishment or surrender from time to time pursuant to the
terms of the Contract and shall include any additional area granted as per the
provisions of the Contract, for which Contractor has valid License(s)/Lease(s) at any
point during the currency of the Contract.
5 “Contractor” means pursuant to the NIO the company(ies) submitting the Bid
accepted by the Government, and have been awarded, through this Contract with the
Government, to carry out Petroleum Operations. If there is more than one Party
Constituting Contractor, they shall be individually referred as “Member” and
collectively referred as “Contractor”, including their respective successors and
permitted assigns under the Contract.
6 “Contractual Regime” means frameworks governing Petroleum Operations
agreements stating the roles, responsibilities, accounting mechanisms etc. between
Government and Contractors such as PSC, RSC, DSF and CBM
7 “Discovery” means the finding, during Petroleum Operations, of a deposit or several
deposits of Petroleum in the same well not previously known to have existed, which
can be demonstrated as recoverable at the surface, by testing methods which are in
adherence to Good International Petroleum Industry Practices (GIPIP). Discoveries
within the same pool shall not be treated as separate discoveries
8 “Field Development Plan” or “FDP” means the comprehensive plan formulated by the
Contractor in relation to the development of a Discovery(ies), in accordance with
corresponding article in Contract.
9 “Lease” means a Petroleum Mining Lease (“PML”) granted pursuant to the Rules
10 “LIBOR” means the London Inter-Bank Offer Rate for six-month maturates of United
States Dollars as quoted by the International Swaps and Derivative Association or
such other bank being an ICE LIBOR contributor panel bank as the Parties may
agree.
11 “License” means a Petroleum Exploration License (“PEL”) granted pursuant to the
Rules
12 “Liquidated Damages” or “LD” with respect to Committed Work Programme shall
have the meaning ascribed to the term in Contract.
13 “NIO” or “Notice Inviting Offers” means the notice inviting offers issued by the
Government of India dated dd-mm-yyyy pursuant to which Contractor had submitted
their Bid for the Block
14 “Participating Interest” means, in respect of each Party constituting the Contractor,
the undivided share expressed as a percentage of such Party’s participation in the
rights and obligations stated in the respective Contract
15 “Petroleum Operations” means, as the context may require, Exploration Operations,
Development Operations or Production Operations or any combination of two or more
of such operations, including construction, operation and maintenance of all
necessary facilities, plugging and abandonment of wells, safety, environmental
protection, transportation, storage, sale or disposition of Petroleum to the Delivery
84Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Point, Site Restoration and any or all other incidental operations or activities as may
be necessary.
16 “Royalty” means the royalty payable by the Contractor to the Government, payable
at the rates specified under the respective contract
17 “Work Programme” means MWP/CWP or additional work programme in accordance
with the respective Contract, for the purpose of carrying out Petroleum Operations
85Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
6.2. Annexure II: MoPNG and DGH Office Orders
6.2.1. Constitution of DGH. (OM dated 8 April 1993)
86Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
87Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
88Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
6.2.2. MoPNG Order for the constitution of Joint Working Group (JWG)
89Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
90Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
6.2.3. MoPNG Policy “Upgradation of Powers and Functions of DGH" dated 20
March 2007
91Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
92Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
93Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
6.2.4. MoPNG Policy “Delegation of Powers to DGH for appointment of advocate
and counsels, Law Firms
94Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
6.2.5. Policy framework for streamlining the operations, relaxation of timelines
and delegation of powers to Director General, Directorate General of
Hydrocarbons (DGH) under Production Sharing Contracts (PSCs). (OM
dated 25 June 2018)
95Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
96Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
97Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
6.2.6. Revised instructions related to Work Programme & Budget Proposals for
E&P contracts (Office Order 25 July 2024)
98Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
99Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
6.2.7. Re-engineering of Internal Standard Operating Procedure (SOP) for
processing of Appraisal Plan/ FDP or its revision in Contract Management
System for PSC's (Office Order dated 16 July 2024)
100Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
101Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
6.2.8. Further simplification and standardization of procedures and processes
under Production Sharing Contract of Pre-NELP/NELP Blocks. (Office
Order dated 12 July 2024)
102Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
103Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
104Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
105Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
106Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
107Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
108Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
109Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
6.2.9. Approval process in Management of PSCs/RSCs. (Office order dated 3 July
2024)
110Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
6.3. Annexure III: Relevant Policies/Clauses
6.3.1. Approval for delivery point(s) within and outside the contract area
i. Under Production Sharing Contract
a) Clause 1.31 of Article 1 of MPSC
“Delivery Point” means, except as otherwise herein provided or as may be otherwise
agreed between the Parties having regard to international practice, the point at which
Petroleum reaches the outlet flange of the delivery facility, either offshore or onshore and
different Delivery Point(s) may be established for purposes of sales. Delivery Point(s)
shall be approved by the Management Committee.
b) Appendix C, Section 3, Clause 3.2 (iii) of PSC
3.2 Costs not recoverable and not allowable under the Contract
The following costs and expenses shall not be recoverable or allowable (whether directly
as such or indirectly as part of any other charges or expense) for cost recovery and profit-
sharing purposes under the Contract:
(i) costs and charges incurred before the Effective Date including costs in respect of
preparation, signature or ratification of this Contract;
Explanatory Note: It is clarified that Costs and expenditures, incurred prior to the Effective
Date but after the execution of the Contract, for making statutory payments in connection
with the
Petroleum Operations such as Petroleum Exploration License (PEL) fee and application
fee shall be allowed as Contract Cost and shall be cost recoverable.
(ii) expenditures in respect of any financial transaction to negotiate, float or otherwise
obtain or secure funds for Petroleum Operations including, but not limited to, interest,
commission, brokerage and fees related to such transactions, as well as exchange losses
on loans or other financing, whether between Affiliates or otherwise;
(iii) costs of marketing or transportation of Petroleum beyond the Delivery Point;
(iv) expenditures incurred in obtaining, furnishing and maintaining the guarantees
required under the Contract and any other amounts spent on indemnities with regard to
non-fulfillment of contractual obligations;
(v) attorney’s fees and other costs and charges in connection with arbitration proceedings
and sole expert determination pursuant to the Contract;
(vi) fines, interest and penalties imposed by Courts of law of the Republic of India;
(vii) donations and contributions;
(viii) expenditures on creation of any partnership or joint venture arrangement;
(ix) amounts paid with respect to non-fulfillment of contractual obligations;
111Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
(x) costs incurred as a result of failure to insure where insurance is required pursuant to
the Contract, or of failure to follow procedures laid down by an insurance policy or where
the Contractor has elected to self-insure, or has under-insured;
(xi) costs and expenditures incurred as a result of misconduct or negligence of the
Contractor;
(xii) expenses of the members of the Management Committee as per Article 6.12:
(xiii) financing cost of inventory, loss on disposal of inventory; and
(xiv) Costs which are not adequately supported and documented.
ii. Under Revenue Sharing Contract
a) Clause 1.1.34 of Article 1 of MRSC
“Delivery Point” means, except as otherwise herein provided or as may be otherwise
agreed between the Parties having regard to international practice, the point at which
Petroleum reaches the outlet flange of the delivery facility, either offshore or onshore and
different Delivery Point(s) may be established for purposes of sales.
iii. Under DSF Contracts
a) Clause 1.29 of Article 1 of DSF Contract
“Delivery Point” means, except as otherwise herein provided or as may be otherwise
agreed between the Parties having regard to international practice, the point at which
Petroleum reaches the outlet flange of the delivery facility, either offshore or onshore and
different Delivery Point(s) may be established for purposes of sales.
iv. Under CBM Contracts
a) Clause 1.29 of Article 1 of CBM Contract
"Delivery Point" means, except as otherwise herein provided or as may be otherwise
agreed between the Parties having regard to international practice, the point at which
CBM reaches the outlet flange of the delivery facility and different Delivery Points may be
established for purposes of sales. Delivery Point(s) for the purpose of sale(s) of CBM
from the contract area shall be approved by the Steering Committee.
6.3.2. Grant of Excusable Delays/ Extra Days for delays in government related
approvals
i. Under Production Sharing Contracts
a) Clause 3 of Office Memorandum “Policy framework for streamlining the
operations, relaxation of timelines and delegation of powers to Director General,
Directorate General of Hydrocarbons (DGH) under Production Sharing Contracts
(PSCs)” (OM dated 25 June 2018)
3. Delegating powers to Director General, Directorate General of Hydrocarbons
(DGH) under Production Sharing Contracts
112Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
i) Empowering DG, DGH for approval of Excusable Delays under the Policy for
Extension in Exploration Phase, dated 18.04.2006
a) Government issued the policy dated 18.04.2006 which inter-alia states that
demonstrable delays on account of getting government approvals/permits/clearances will
be counted as excusable delays. The excusable delays are approved by Government.
To expedite the approval process, it has now been decided to delegate the power to DG,
DGH to. approve cases of demonstrable delays as excusable delays after confirming
demonstrable delays within the extant policy framework of 2006.
b) The DGH will constitute a Multi- Disciplinary Committee to review and recommend
the proposal for final approval of DG, DGH. The DGH would properly define· excusable
delays and prescribe detailed procedure for allowing excusable delays.
c) The DGH would furnish a statement listing out the cases decided with brief facts of
each case on quarterly basis to this Ministry.
b) Standard Operating Procedure (SoP) for implementation of Para 3 of Policy
framework dated November 10, 2014, for PSC regime, Relinquishment cases
under and Excusable delay cases under Policy dated April 18, 2006, and Exit
cases under Policy dated April 11, 2017, for early monetization of CBM
A. Background
Government of India on 10.11.2014 approved a policy wherein DGH was empowered to
relax, extend and clarify on provisions of Production Sharing Contracts (PSC) for early
monetization of PSC blocks. Further vide policy dated 11.04.2017, Govt. of India
empowered DGH to debottleneck Coal Bed Methane (CBM) contractual issues, examine
and approve exit cases and take decisions on behalf of Govt. of India on select issues
and provide clarity on CBM contract. Now, vide policy dated 25.06.2018, Govt. has
delegated its power to DGH to examine and approve excusable delays on account of
Govt. approval/clearances/permits that are demonstrable. For this a multi-disciplinary
committee has to be constituted that would prescribe detailed procedure for allowing
excusable delays. Taking cognizance of empowerment of DGH vide Govt. policies dated
10.11.2014, 11.04.2017 and 25.06.2018 to examine and approve select cases pertaining
to exit due to delay in clearances and excusable delays/force majeure, DGH has
constituted a Multi-Disciplinary Committee that has framed the Standard Operating
Procedures (SOP) to examine cases that may be referred to under the three policies. The
primary objective of these SOPs is to bring transparency and objectivity for assessment
of cases referred to under the said policies. Following are the SOPs under respective
policies.
ii. Under Revenue Sharing Contract
Till OALP Round VII
a) Clause 14.5 of Article 14 in MRSC of OALP Round VII
113Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
14.5 Subject to the provisions of all Applicable Laws and Notifications on protection of
environment, any new project or expansion or modernization projects for Petroleum
Operations for which a proposal is submitted by the Contractor, the Government and
relevant State Government shall accord environmental clearance in accordance with the
relevant notifications, rules, regulations and orders concerning Environmental Impact
Assessment issued by the Ministry of Environment, Forests and Climate Change from
time to time. However, wherever forest land is involved, the Contractor shall have to
obtain approval of the Central Government through the relevant State Government
concerned under the Forest (Conservation) Act, 1980 and Rules made thereunder. In the
event the Government or the State Government takes more than the time period
stipulated under the Applicable Laws for providing such clearances, or where no specific
time period is provided for grant of such clearance, more than 120 (one hundred and
twenty) days (Approval Period), then the days taken by the Government or State
Government in addition to the Approval Period to grant such approval (Extra Days) shall
be taken into account in determining all time periods provided for discharge of obligations
of the Contractor under the Contract and such time periods, if already determined, shall
stand extended by the number of Extra Days.
b) Clause 5.5 (d) of Article 5 in MRSC of OALP Round VII
d) If delay due to lack of statutory and other clearances is beyond two (2) years in any
of the Blocks, then the Contractor will be given a choice to choose between (a) and (c)
above. In such cases the application for such reduction /exiting should be made within
three (3) months of the expiry of the two (2) year period from the date of application for
clearance. Any delay attributable to the Contractor shall not be considered in the above-
mentioned two-year period
Under OALP VIII
o Clause 33.10 of Article 33 in MRSC of OALP Round VIII
33.10 In the event that the Contractor has taken all the requisite, and necessary
steps for obtaining any requisite permits, clearances, approvals or consents as may be
required for performance of its obligations under this Contract, and the requisite permits,
clearances, approvals or consents is not granted by the Government or the relevant State
Government or any of their respective agencies, ministries, institutions or authorities
within the time period stipulated under Applicable Laws of India for providing such
permits, clearances, approvals or consents (or where no time period is provided for grant
of such permits, clearances, approvals or consents, within 120 (one hundred and twenty)
days) (“Approval Period”), then the period taken by the Government or relevant State
Government or their respective agencies, ministries, institutions or authorities in addition
to the Approval Period to provide such permits, clearances, approvals or consents (“Extra
Days”) shall be added to the relevant time period(s) for discharge of obligations of the
Contractor under the Contract; subject to a maximum cumulative of 720 Extra Days for
the entire Exploration Period; and such time period(s), if already determined, shall stand
extended by the number of Extra Days, and any obligation to pay liquidated damages for
any delay under this Contract shall calculated only after taking into the account the Extra
Days.
The obligation of the Contractor to take all the requisite, and necessary steps for obtaining
any requisite permits, clearances, approvals or consents as may be required for
performance of its obligations under this Contract shall include but not be limited to make
the requisite applications, pay the necessary fees and comply with all pre-conditions as
114Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
may be applicable for grant of the such permits, clearances, approvals or consents,
respond to any queries that may be received from the relevant authority and liaise with,
and follow up with the relevant authorities after making of the relevant applications. In the
event the Contractor fails to undertake the necessary steps for obtaining any requisite
permits, clearances, approvals or consents, the Extra Days shall not be added to the time
period for completion of the Contractor’s obligations under the Contract.
If delay due to lack of statutory and other clearances is beyond two (2) years and verified
by DGH, then the Contractor would be permitted to relinquish the Contract area without
payment of Liquidated Damages as specified in Article 5.4. In such cases, the application
for such exiting should be made within 60 days prior to the expiry of the two (2) year
period. Any delay attributable to the Contractor shall not be considered in the above
mentioned two (2) year period.
iii. Under DSF Contract
Under DSF Round I & II
a) Clause 14.5 of Article 14 of MRSC of DSF Round I & II
14.5 Subject to the provisions of all applicable laws and notifications on protection of
environment, any new project or expansion or modernization projects for Petroleum
Operations for which a proposal is submitted by the Contractor, the Government shall
accord environmental clearance in accordance with the relevant notifications, rules,
regulations and orders concerning Environmental Impact Assessment issued by the
Ministry of Environment, Forests and Climate Change from time to time. However,
wherever forest land is involved, the Contractor shall have to obtain approval of the
Central Government through the State Government concerned under the Forest
(Conservation) Act, 1980 and Rules made thereunder. In the event the Government or
the State Government takes more than the time period stipulated under the applicable
laws for providing such clearances, or where no specific time period is provided for grant
of such clearance, more than 120 (one hundred and twenty) days ("Approval Period"),
then the days taken by the Government or State Government in addition to the Approval
Period to grant such approval ("Extra Days") shall be taken into account in determining
all time periods provided for discharge of obligations of the Contractor under the Contract
and such time periods, if already determined, shall stand extended by the number of extra
days.
Under DSF III & Special Round contract, there is no clause which defines the provision
of Extra Days due to delay in getting clearances from the Government or the State
Government
iv. Under Coal Bed Methane (CBM) Contract
a) Clause 2 and 2.4 of MoPNG notification Policy framework for early monetization
of Coal Bed Methane dated 11 April 2017
2. Contractual Issues
115Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Director General, Directorate General of Hydrocarbons (DG, DGH) is empowered for
condoning the delays in notice periods, annual work program and budgets and to approve
the excusable delays regarding clearances from State and Central Government. The DG,
DGH will dispose such cases within the time-limits below:
2.4 Excusable delay in development phase due to land acquisition / force majeure
issues or any other such matter beyond the control of Operator
DGH is empowered to approve the excusable delays, without set off from subsequent
Phases, in development phase due to Land Acquisition / Force Majeure condition or any
other such matter beyond the control of Operator after confirming demonstrable delays.
116Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
6.3.3. Reduction in contract area and work programme, due to denial or delay in
statutory clearances for exploratory activities
i. Under Production Sharing Contract
a) Clause 3.1 of MoPNG notification ‘Policy Framework for relaxations, extensions
and Clarifications at the development and production stage under the PSC’ dated
November 10, 2014
3.1 The blocks are offered for bidding after securing clearance from six agencies.
Subsequently, after the grant of PEL for the entire block area, the contractor is required
to complete the MWP as per PSC. For completion of MWP, · contractor proposes annual
work programme for review of MC every year. In some cases, while executing the seismic
work and drilling of exploration ells in the block as per MWP, some of the agencies like
Ministry of Defence (MOD), Ministry of Environment and Forest (MoEF) and State
Government/Departments, who had earlier accorded 'in principle' approval, have denied
permission to carry out work in the entire block or a part of it. It has been decided that
where the contract area has been reduced due to denial of clearances by Government
agencies, DGH is empowered to exercise such powers of proportionate reduction of
MWP on the recommendation of MC as follows:
a) the Contractor decides not to accept any reduction in area at any stage before
Petroleum Mining Lease (PML) is granted, the contractor would be permitted to exit from
the Contract without payment of cost of Unfinished Work Programme. In such cases, the
proposal for relinquishment shall be submitted within three months of the communication
received by the contractor for such reduction.
b) If the contractor agrees to continue exploration in the reduced area, then he· may
be allowed a proportional reduction in MWP in 2D, 3D work programme and also for
drilling of wells rounded off to the nearest integer with a minimum number of one. The
choice of the wells to be drilled would be left to the contractor.
c) PEL for the area not made available for exploration ·will be cancelled arid future
PEL fee for the future years would be reduced proportionately in all cases in 3 (b) above.
d) In case, the Contractor does not exercise his option -within three months but
proposes to exit from the contract later, it has been decided to impose penalty of
liquidated damages to the extent of cost of unfinished MWP proportional to the reduced
area. This will be applicable to all existing PSCs.
e) If delay due to lack of statutory and other clearances is beyond two years in any of
the blocks, then the contractor will be given a choice to choose between (a) and (b) above.
In such cases the application for such reduction/exiting should be submitted within 3
months of the expiry of the two-year period from date of application for clearance.
117Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
ii. Under Revenue Sharing Contract
a) Clause 5.5 (b) and Clause 5.5 (d) of Article 5 in MRSC
5.5 In case of reduction in the contract area due to reasons including but not limited to
denial of License(s) by Government/State Government(s), lack of necessary clearances
such as Blocks overlapping with Special Economic Zone (SEZ), Reserve Forest, Naval
Exercise Areas, Defence Research and Development Organization (DRDO), Danger
Zones, National parks, urban areas, firing ranges of police/armed forces etc.,
Government, shall approve proportionate reduction in Committed Work Programme, as
the case may be as follows:
a) If the Contractor decides not to accept any reduction in contract area at any stage
before the Petroleum Mining Lease (PML) is granted, the Contractor would be permitted
to exit from the contract without payment of Liquidated Damages as specified in Article
5.4. In such cases, the proposal for relinquishment shall be submitted within three months
of the communication received by the Contractor for such reduction.
b) In case the Contractor does not exercise this option within three months of receipt
of the communication of reduction of area but proposes to exit from the Contract later, an
LD will be levied to the extent of unfinished Committed Work Programme, proportional to
the reduced area.
c) If the Contractor continues exploration in the reduced area, then proportional
reduction in Committed Work Programme shall be allowed, rounded off to the nearest
integer with a minimum number of one. PEL for area not made available will be cancelled
and future PEL fee would be reduced proportionately.
d) If delay due to lack of statutory and other clearances is beyond two (2) years in any
of the Blocks, then the Contractor will be given a choice to choose between (a) and (c)
above. In such cases the application for such reduction /exiting should be made within
three (3) months of the expiry of the two (2) year period from the date of application for
clearance. Any delay attributable to the Contractor shall not be considered in the above-
mentioned two-year period.
iii. Under DSF Contract
In all DSF Rounds
a) Clause 5.4 of Article 5 in DSF Contract
5.4 Notwithstanding any other provision of this Contract, in the event the contract area
is reduced due to denial of clearances by Government agencies, then the Government
(acting through DGH) is empowered to exercise such powers of proportionate reduction
of the Bid Work Programme, on the recommendations of the Management Committee,
as under:
a) If the Contractor does not accept any reduction in the contract area at any stage
before the Lease is granted, the Contractor would be permitted to relinquish the Contract
area without payment of Liquidated Damages as specified in Article 5.2. In such cases,
the proposal for relinquishment shall be submitted by the Contractor within three months
of the communication received by the Contractor for such reduction of the contract area.
118Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
b) If the Contractor agrees for the reduced contract area, then the Contractor may be
allowed a proportional reduction in Bid Work Programme. In case of wells, the number of
wells shall be rounded off to the nearest integer with a minimum number of one. The
choice of the wells to be drilled may be decided by the Contractor.
c) In case, the Contractor does not exercise his option within three months but
proposes to relinquish the contract area later, Liquidated Damages shall be payable as
per the rates in Article 5.2.
In DSF III and SDSF Round
b) Clause 5.4 (b) and Clause 5.4 (b) of Article 5 in DSF Contract
5.4 Notwithstanding any other provision of this Contract, in the event the contract area is
reduced due to denial of clearances by Government agencies, etc., then the Government
(acting through DGH) is empowered to exercise such powers of proportionate reduction
of the Bid Work Programme, on the recommendations of the Management Committee,
as under:
a) If the Contractor does not accept any reduction in the contract area at any stage before
the Lease is granted, the Contractor would be permitted to relinquish the contract area
without payment of Liquidated Damages as specified in Article 5.2. In such cases, the
proposal for relinquishment shall be submitted by the Contractor within three months of
the communication received by the Contractor for such reduction of the contract area.
b) If the Contractor agrees for the reduced contract area, then the Contractor may be
allowed a proportional reduction in Bid Work Programme. In case of wells, the number of
wells shall be rounded off to the nearest integer with a minimum number of one. The
choice of the wells to be drilled may be decided by the Contractor.
c) In case, the Contractor does not exercise his option within three months but proposes
to relinquish the contract area later, Liquidated Damages shall be payable as per the
rates in Article 5.2.
d) If delay due to lack of statutory and other clearances is beyond two (2) years and
verified by DGH, then the Contractor would be permitted to relinquish the Contract area
without payment of Liquidated Damages as specified in Article 5.2. In such cases the
application for such reduction/ exiting should be made within 30 days of the expiry of the
two (2) year period from the date of application for clearance. Any delay attributable to
the Contractor shall not be considered in the above mentioned two (2) year period.
iv. Under CBM Contract
a) Clause 2.5 and Clause 2.7 of MoPNG notification Policy framework for early
monetization of Coal Bed Methane dated April 11, 2017
2.5 Reduction in minimum work programme
DGH is empowered to reduce Minimum Work Programme (MWP) in proportion to the
contract area if contract area is reduced by Government for any reason. If the Contractor
decides not to accept any reduction in contract area, the Contractor would be permitted
119Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
to exercise exit option from the contract without payment of Cost of Unfinished Work
Programme (COUWP).
2.7 Non-grant or delayed permission of clearances by State Government and
Central Government.
In cases of inordinate delays in granting clearances i.e., beyond two (2) years in any
block, the Contractor if exercises is exit option, will be permitted to exit from the contract
without paying Cost of Unfinished Work Programme. DGH is empowered to review and
examine such cases and approve exit option exercised by the Contractor from the CBM
Contract.
b) Clause 5.5 (d) of Article 5 of SCBM contract
5.5 In case of reduction in the contract area due to reasons including but not limited to
denial of License(s) by Government/State Government(s), lack of necessary clearances
such as Blocks overlapping with Special Economic Zone (SEZ), Reserve Forest, Naval
Exercise Areas, Defence Research and Development Organization (DRDO), Danger
Zones, National parks, urban areas, firing ranges of police/armed forces etc.,
Government, shall approve proportionate reduction in Committed Work Programme, as
the case may be as follows:
a) If the Contractor decides not to accept any reduction in contract area at any stage
before the Petroleum Mining Lease (PML) is granted, the Contractor would be permitted
to exit from the contract without payment of Liquidated Damages as specified in Article
5.4. In such cases, the proposal for relinquishment shall be submitted within three months
of the communication received by the Contractor for such reduction.
b) In case the Contractor does not exercise this option within three months of receipt
of the communication of reduction of area but proposes to exit from the Contract later, an
LD will be levied to the extent of unfinished Committed Work Programme, proportional to
the reduced area.
c) If the Contractor continues exploration in the reduced area, then proportional
reduction in Committed Work Programme shall be allowed, rounded off to the nearest
integer with a minimum number of one. PEL for area not made available will be cancelled
and future PEL fee would be reduced proportionately.
d) If delay due to lack of statutory and other clearances is beyond two (2) years in any
of the Blocks, then the Contractor will be given a choice to choose between (a) and (c)
above. In such cases the application for such reduction /exiting should be made within
three (3) months of the expiry of the two (2) year period from the date of application for
clearance. Any delay attributable to the Contractor shall not be considered in the above-
mentioned two-year period.
6.3.4. Bank Guarantee (BG) renewal towards unfinished Work Programme
i. Under Production Sharing Contract
a) Clause 29.2, Clause 29.3 (a) and Clause 29.3 (b) of Article 29 of PSC Contract
120Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
29.2 If the Contractor elects to retain the contract area during the Subsequent Exploration
Period by committing to drill Exploration Wells after completing the Minimum Work
Programme, under Article 3.4 (a), each of the Companies constituting the Contractor shall
procure and deliver to the Government before the expiry of the Initial Exploration Period
an irrevocable, unconditional bank guarantee from a reputed bank of good standing in
India, acceptable to the Government, in favour of the Government, for the amount
specified in Article 29.3 and valid for the Subsequent Exploration Period opted by the
Contractor, in a form provided at Appendix-G.
29.3
(a) The amount of the guarantee referred to in Articles 29.1 (a) and 29.2 above shall be
an amount equal to seven and one half percent (7 ½ %) of the Company’s Participating
Interest share of the total estimated expenditure in respect of Minimum Work Programme
including Mandatory Work Programme or Work Program as the case may be, to be
undertaken by the Contractor in the contract area during the Initial or Subsequent
Exploration Period. The total estimated expenditure for the Exploration Period for the
purpose of furnishing bank guarantee by the Contractor shall be higher of the cost
estimates by the Contractor or the Budget estimates presented to the Management
Committee, or the amount of Liquidated damages specified in Article 5.
(b) after the completion and due performance of the Minimum Work Programme including
Mandatory Work Programme or committed Work Programme during Initial Exploration
Period or the Subsequent Exploration Period, as the case may be, the guarantee will be
released in favour of the Company on presentation to the bank of a certificate from the
Government that the obligation of the Contractor has been fulfilled and the guarantee
may be released. Such certificate shall be provided within thirty (30) days from the
completion of the said Work Programme and fulfilment of obligations under the Contract
to the satisfaction of the Government.
ii. Under Revenue Sharing Contract
a) Clause 27.1 (a) of Article 27 of RSC Contract
27.1 Each of the Members constituting the Contractor or their Parent Companies or the
Operator on behalf of the other Members, shall procure and deliver to the Government
within thirty (30) days from the Effective Date, or within thirty (30) days from the date of
opting for the mandatory Exploratory well(s) for Phase-II (Part-A and Part-B), as
applicable:
(a) an irrevocable, unconditional Bank Guarantee from a Scheduled Commercial Bank of
good standing in India, acceptable to the Government, in favor of the Government, for the
amount specified in Article 27.2 and valid for the Exploration Period for which bid
commitments are made as specified in Article 5.1 with claim period of sixty (60) days, in
a form provided at Appendix G;
iii. Under DSF Contract
a) Clause 27.1 (a), Clause 27.2 (a) and Clause 27.2 (b) of Article 27 of DSF
Contract
121Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
27.1 Each of the Companies constituting the Contractor shall procure and deliver to the
Government within thirty (30) days from the Effective Date of this Contract:
(a) an irrevocable, unconditional bank guarantee from a reputed bank of good standing
in India, acceptable to the Government, in favour of the Government, for the amount
specified in Article27.2 and valid for the period (3, 4, 6 years as the case may be) specified
in Article 3.2 with claim period of 90 days, in a form provided at Appendix E;
27.2 (a) The bank guarantee referred to in Article 27.1 (a) above shall be for an amount
calculated at rates specified in Article 5.2. in respect of the Bid Work Program Specified
in Article 5.1, provided that in the absence of any Bid Work Program stipulated in Article
5.1, the bank guarantee shall be submitted for a minimum guarantee of equivalent
amount of USD 0.15 million, USD 0.23 million and USD 0.30 million respectively for
contract area in on-land, shallow water and deep water.
(b) After the completion and due performance of the Bid Work Program, the guarantee
will be returned to the Company, provided that a bank guarantee submitted in respect of
the minimum amount shall be returned on commencement of commercial production or
on completion of period stipulated in Article 3.2 of RSC, whichever is earlier.
iv. Under CBM Contract
Till CBM Round IV
a) Clause 26.1 (a), Clause 26.3 (a) and Clause 26.3 (b) of Article 26 of CBM
Contract
26.1 Subject to Article 26.1 (d), each of the Companies constituting the Contractor shall
produce and deliver to the Government on the Effective Date of this Contract:
(a) an irrevocable, unconditional bank guarantee from a reputed bank of good standing
in India, acceptable to the Government, in ·favour of the Government, for the amount
specified in Article 26.2 in a form and substance acceptable to the Government as set out
in Appendix-F;
26.3 The guarantee shall provide that:
(a) the amount referred to in Article 26.2 shall be automatically adjusted at the end of
each Year for an amount equal to a Company's participating share of thirty five percent
(35%) of the total estimated expenditure in respect of the Work Programme to be
undertaken for the following Year of the relevant Phase till Phase-II. The guarantee shall
be renewed at the end of each Year positively thirty (30) days before the expiry of the
guarantee period; and
(b) after the completion and due performance of the Minimum Work Programme of
Phase-I or Phase-II, as the case may be, the guarantee will be released in favour of the
Company on presentation of a certificate from the Government to the bank that the
obligation of the Contractor has been fulfilled and the guarantee may be released, subject
to Article 26.4. Such certificate shall be provided within thirty (30) days from the
completion of the Minimum Work Programme and fulfillment of obligation under the
contract to the satisfaction of the government.
122Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Under SCBM Round
a) Clause 27.1 (a) of Article 27 of SCBM Contract
27.1 Each of the Members constituting the Contractor or their Parent Companies or the
Operator on behalf of the other Members, shall procure and deliver to the Government
within thirty (30) days from the date on which this Contract is executed by the Parties:
(a) an irrevocable, unconditional Bank Guarantee from a Scheduled Commercial Bank
of good standing in India, acceptable to the Government, in favor of the Government, for
the amount specified in Article 27 .2 and valid for the Exploration Period for which bid
commitments are made as specified in Article 5.1 with claim period of sixty (60) days, in
a form provided at Appendix G;
123Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
6.3.5. Field Development Plan (FDP) approvals of PSC blocks with GoI nominee
a) Clause 10.7 of Article 10 of PSC Contract
10.7 If the Contractor declares the Discovery a Commercial Discovery after taking into
account the advice of the Management Committee as referred in the Article 10.6, within
two hundred (200) days of the declaration of the Discovery as a Commercial Discovery,
the Contractor shall submit to the Management Committee a comprehensive
development plan of the Commercial Discovery which shall:
(a) relate to the Discovery Area and contain a Reservoir or part thereof and the
boundaries of the proposed Development Area;
(b) be designed to ensure the most efficient, beneficial and timely use of the Petroleum
resources discovered; and
(c) be prepared in accordance with sound engineering, economic, safety and
environmental principles recognised in the generally accepted modern oilfield and
petroleum industry practices.
Such plan shall contain detailed proposals by the Contractor for the construction,
establishment and operation of all facilities and services for and incidental to the recovery,
storage and transportation of the Petroleum from the proposed Development Area to the
Delivery Point together with all data and supporting information including but not limited
to:
(i) description of the nature and characteristic of the Reservoir, data, statistics,
interpretations and conclusions on all aspects of the geology, Reservoir evaluation,
Petroleum engineering factors, Reservoir models, estimates of reserve in place, possible
production magnitude, nature and ratio of Petroleum fluids and analysis of producible
Petroleum;
(ii) outlines of the development project and/or alternative development projects, if any,
describing the production facilities to be installed and the number of Wells to be drilled
under such development project and/or alternative development projects, if any;
(iii) estimate of the rate of production to be established and projection of the possible
sustained rate of production in accordance with modern oilfield and petroleum industry
practices under such development project and/or alternative development projects, if any,
which will ensure that the area does not suffer an excessive rate of decline of production
or an excessive loss of Reservoir pressure;
(iv) estimates of Development Costs and Production Costs under such development
project and/or alternative development projects, if any;
(v) Contractor’s recommendations as to the particular project that it would prefer;
(vi) Work Programme and Budget for development proposals relating to the proposed
Development Area;
(vii) anticipated adverse impact on the environment and measures to be taken for
prevention or minimisation thereof and for general protection of the environment in
conduct of operations;
124Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
(viii) measures to be taken for the health and safety of persons employed in Petroleum
Operations;
(ix) the information required in Article 21.
(x) schedule of implementation and targets
b) Clause 10.8 of Article 10 of PSC Contract
10.8 A proposed development plan submitted by the Contractor pursuant to Article 10.7
may be approved by the Management Committee within one hundred and ten (110) days
of submission thereof or eighty (80) days of receipt of any additional information
requested by the Management Committee. In case the Management Committee requires
any reasonable additional information, the same shall be requested by it within eighty
(80) days from the submission of the development plan. The Contractor shall provide
such additional information within thirty (30) days from the request by the Management
Committee. If, within a period of one hundred and ten (110) days after submission of a
proposed development plan or eighty (80) days from the receipt of any additional
information, where asked by the Management Committee, the Management Committee
fails to convey a decision to the Contractor, the Contractor shall have option to submit the
proposal to the Government. Also, where, the Management Committee rejects the
development plan of the Contractor, the Contractor can submit the development plan for
the approval of the Government. The Government shall respond on the proposed
development plan submitted by the Contractor within one hundred and ten (110) days. In
case Government refuses to approve the proposed development plan, it shall convey the
reasons for such refusal and the Contractor shall be given opportunity to make
appropriate modifications to meet concerns of Government and the provisions of the
foregoing Article and re-submit the plan within ninety (90) days from the date of receipt
of refusal from the Government.
c) Clause 10.10 of Article 10 of PSC Contract
10.10 Work Programmes and Budgets for Development and Production Operations shall
be submitted to the Management Committee as soon as possible after the approval of a
Development Plan under Article 10.8 and thereafter not later than 31st December each
Year in respect of the Year immediately following.
d) Clause 10.13 of Article 10 of PSC Contract
Proposed revisions to the details of a Development Plan or an annual Work Programme
or Budget in respect of Development and Production Operations shall, for good cause
and if the circumstances so justify, be submitted for approval to the Management
Committee.
e) Clause 21.5.6 of Article 21 of PSC Contract
21.5.6 If the Contractor declares the Discovery a Commercial Discovery after taking into
account the advice of the Management Committee as referred to in the Article 21.5.5, the
Contractor shall, within one (1) year of the declaration of the Discovery as a Commercial
Discovery, submit a development plan for the development of the Discovery to the
125Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Management Committee for approval. Such plan shall be supported by all relevant
information including, inter alia, the information required in Article 10.7.
f) Clause 21.5.7 of Article 21 of PSC Contract
21.5.7 Unless otherwise agreed by the Management Committee, it shall consider the
proposed development plan and give their approval within one hundred and sixty five
(165) days of submission thereof or eighty five (85) days from the receipt of the
clarifications/additional information from the Contractor. Any clarification/ additional
information required by the Management Committee shall be asked for within eighty five
(85) days of receipt of the proposal from the Contractor. The Contractor shall provide
such additional information within thirty (30) days from the receipt of request by the
Management Committee. If the Management Committee fails to convey its decision within
one hundred and sixty five (165) days from the submission of the development plan or
eighty five (85) days from the receipt of the clarifications/additional information, whichever
is later, the Contractor may submit the development plan for the approval of the
Government. Also, where, the Management Committee rejects the development plan of
the Contractor, the Contractor can submit the development plan for the approval of the
Government.
g) Clause 21.5.8 of Article 21 of PSC Contract
21.5.8 Where the development plan is submitted to the Government for approval pursuant
to Article 21.5.7, the Government shall convey its decision within one hundred and fifteen
(115) days from the date of receipt of the proposal from the Contractor. Government,
where it considers necessary, may ask clarifications/additional information from the
Contractor within eighty five (85) days and shall convey its decision within fifty five (55)
days from the date of receipt of such clarifications/additional information.
h) Clause 21.5.9 of Article 21 of PSC Contract
21.5.9 If the Government has failed to approve or disapproves the Contractor’s proposed
development plan, within one hundred and fifteen (115) days from receipt or within fifty
five (55) days from the receipt of clarifications/ information from the Contractor as
mentioned in the Article 21.5.8, the Government shall advise the Contractor, in writing, of
the reasons for such failure or disapproval and the Government and the Contractor shall
meet to discuss the said development plan and the reasons for the said failure to approve
or disapproval, and use their best efforts to agree on appropriate modifications thereto to
meet the Government’s concerns or objections. Thereafter, the Contractor shall have the
right to resubmit, within eighty five (85) days of communication from the Government, the
proposed development plan duly amended to meet the Government’s concerns. Such
right of resubmission of the proposed development plan shall be exercisable by the
Contractor only once. The Government will respond to the re-submitted plan within one
hundred and fifteen (115) days. If no such plan is submitted to the Government within the
above specified period, the Contractor shall relinquish its right to develop such Gas
Discovery and such Discovery shall be excluded from the contract area.
6.3.6. Grant of Extension in Exploration Period across contractual regimes
i. Under Production Sharing Contract
a) Clause A of the policy for extension of exploration phases under NELP and Pre-
NELP production sharing contracts dated 04 April 2016
126Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
A. Extension within the overall exploration period of 7 years or 8 years in phase I
& II (but excluding any proposed excusable delays on account of the Government
approvals / permits / clearance etc.)
Sl.
Type of proposal Suggestion along with proposed conditions
No.
(applicable for
extension in phase I &
II)
Where MWP has not been completed and no
1. Where Minimum Work
hydrocarbon discovery have been made by the
Programme (MWP) of
contractor, the following procedure shall apply:
the relevant phase has
not been completed
within the stipulated a) First 6 months extension may be granted by
period of that phase MC or the Government in terms of the
and no hydrocarbon provisions of respective PSCs maintaining
discovery (as defined the same terms and conditions of the PSCs.
in the PSC) made b) An additional upto 6 months extension (that
is between 6 – upto 12 months) may be
granted on the following terms and
conditions:
The contractor will provide 100% bank
guarantee and 10% cash payment as
agreed pre- estimated liquidated
damages for the unfinished minimum
work programme as reasonably
determined by DGH, keeping in view
the relevant factors in computing cost
of such unfinished minimum work
programme.
The contractor would be required to
relinquish the area in terms of the
provisions of the PSC at the beginning
of this extension period.
This period of extension will be set off
from the next exploration phase
c) Any extension beyond 12 months and upto 18
months may be considered subject to the
following:
The contractor would be required to
relinquish the area as applicable at
the end of relevant phase.
The contractor would be required to
give 100% bank guarantee for
unfinished minimum work
programme and deposit a cash
payment as agreed pre-estimated
127Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
liquidated damages of 30% of the
unfinished minimum work
programme as reasonably
determined by DGH, keeping in view
the relevant factors in computing cost
of such unfinished minimum work
programme.
This period of extension will be set off
from the next exploration phase.
In case the contractor and DGH, based on available
2. Where MWP has not
information at that time, come to a conclusion that
been completed
the prospectivity of the block / area is poor and does
within the stipulated
not warrant completion of MWP (say drilling of
period of an exploration wells due to lack of techno- commercial
exploration phase and viable prospects), DGH will reasonably decide based
the operator feels that on the available information whether the
the prospectivity is prospectivity of the block is indeed poor and also
too poor to undertake determine an alternative work programme in
consultation with the contractor, which will be atleast
further exploration /
equal in terms of investment and effort (in physical
drilling:
terms) the unfinished minimum work programme.
Such substitution of work programme would require
the Governments approval.
In this scenario with a substitute work programme,
extension may be granted as under:
a) For the first 6 months by the Management
Committee or the Government in terms of
the provisions of respective PSCs
maintaining same terms and conditions of
the PSCs (except for unfinished substituted
work programme to be approved by the
Government).
b) Next 6 months extension (i.e. 6-upto 12
months) may be granted on the following
terms and conditions:
The contractor will provide a 100%
bank guarantee of the unfinished
minimum work programme
(equivalent unfinished substituted
work programme to be approved by
the Government).
The block will come in the domain of
open acreage and may be offered in
a bidding round or under open
acreage system (as and when it
comes in force). However, in case of
any discovery or any drilling under
implementation during this period,
the contractor will have the right to
retain such areas as reasonably
determined by DGH. In case the
128Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
contractor as a result of exploration
during this extended period desires
to go to the next phase of exploration,
the contractor would be allowed to
proceed to the next phase for only
such areas for which no licenses /
leases have been issued or which
has not been placed under a bidding
process by such time.
No further extension will be given
beyond 12 months and the contractor
shall be required to relinquish the
entire area along with payment, if
any, equivalent to the unfinished
minimum work programme, to the
Government in terms of the
provisions of the PSCs.
3. Where MWP has not
In this scenario, DGH will reasonably decide the work
been completed but a
programme, in addition to the unfinished minimum
hydrocarbon
work programme, required to be carried out in the
discovery is made area which is not proposed for relinquishment by the
within the exploration contractor. The following extension may be granted:
phase and does not
want to relinquish the First 6 months extension may be given in terms
area at the end of of the provisions of the respective PSCs.
phase: Another extension of upto 12 months (i.e., 6-upto
18 months) may be given subject to the
contractor providing 50% bank guarantee of the
unfinished minimum work programme and the
additional work programme (for retaining
additional area) reasonably decided by DGH.
The contractor would undertake to appraise,
decide on commerciality and development of the
discovery within the time frame provided in the
PSCs for these activities.
In this scenario, the contractor may be given
4 Where MWP has been
extension as under:
completed with no
(a) 6 months extension may be given in terms of the
hydrocarbon
provisions of the PSC.
discovery and
additional work
(b) Additional upto 6 months (6-upto 12
programme is
months) extension may be given subject to the
proposed:
following:
The contractor will provide bank guarantee of
35% amount of the unfinished additional work
programme.
129Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Will not be able to set off this work programme
from subsequent phase (s).
DGH will reasonably determine the expected
time required for completing additional work
programme.
In this scenario, the extension may be granted in the
5 Where MWP has been
following manner:
completed and
hydrocarbon a) 6 months extension may be given in terms of the
discovery has been provisions of the PSCs.
made and the
b) Additional extension of upto 12 months (6 – upto
contractor wants to
18 months) may be given subject to the following:
retain the area for
DGH will reasonably determine the estimated
additional exploration
time required for completing additional
exploration work programme.
the contractor would be required to give a bank
guarantee of 35% amount of the unfinished
additional work programme.
Will not be able to set off this work programme
from subsequent phase.
In case the contractor is unable to complete the
additional work programme within this period,
the contractor will pay for 50% of the unfinished
additional work programme
6 Where MWP has been In this scenario, the extension may be granted in the
completed and following manner:
hydrocarbon
discovery has been a) 6 months extension may be given in terms of
made and the the PSCs.
b) Additional 6 months (6 – upto 12 months)
contractor is willing to
extension may be given on the following
relinquish the area as
conditions:
per the PSC, however,
wants extension to DGH will reasonably determine the estimated
carry out additional time required for completing additional work
exploration: programme.
Will not be able to set off this work programme
from subsequent phase.
130Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
the contractor would be required to give a bank
guarantee of 35% amount of the unfinished
additional work programme.
In case unable to complete the additional work
programme within this period, will pay for 35%
of the unfinished additional work programme.
c) Another 6 months (12-upto 18 months)
extension (beyond 12 months) may be granted
subject to the following:
DGH will reasonably determine the estimated
time required for completing additional work
programme.
the contractor would be required to give a bank
guarantee of 50% of the unfinished additional
work programme.
Will not be able to set off this work programme
from subsequent phase.
In case unable to complete the additional work
programme within this period, will pay for 50%
of the unfinished minimum work programme.
In this scenario, the extension may be granted in
7 Blocks falling in
following
unprospective area, manner:
MWP has not been
completed (these may
a) 6 months extension may be given in terms of
be blocks, which were
the provisions of the PSCs.
awarded on a single
bid basis) b) Another upto 12 months (6-upto 18 months)
extension may be given subject to the
following:
DGH to determine the block falls in
unprospective area along with the
supporting documents / data.
DGH to reasonably determine the time for
completing the unfinished minimum
work programme.
The contractor will provide bank
guarantee of 50% amount of the
unfinished minimum work programme.
The contractor will relinquish the area in
terms of the provisions of the PSC at the
131Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
beginning of this extension period.
The block will come in the domain of open
acreage and may be offered in a bidding
round or under open acreage system (as
and when it comes in force). However, in
case of any discovery as a result of work
programme under implementation during
this period, the contractor will have the
right to retain the relevant discovery
areas as reasonably determined by DGH
/ MC. In case, the contractor as a result of
exploration during this extended period
desires to go to the next phase of
exploration, the contractor would be
allowed to proceed to the next phase
provided no licenses / leases have been
issued or the area has not been offered
under bidding process at the time.
Will be required to pay equivalent amount
of the unfinished minimum work
programme, if MWP is not completed in
the extended period.
In this scenario, extension may be given in the
8 Block falling in
following manner:
unprospective area
and MWP have been
completed but the a) 6 months extension may be given in terms of
contractor wants to the provisions of the PSCs.
retain the area to carry b) Another 12 months (6-upto 18 months)
out additional work extension may be given subject to the following:
(these may be blocks, DGH to determine whether the block falls in
which were awarded unprospective area on the basis of
on a single bid basis): supporting documents / data.
DGH to reasonably determine the time for
completing the unfinished additional work
programme
The contractor to provide bank guarantee of
35% amount of the unfinished minimum
work programme.
The contractor to relinquish any area in
terms of the provisions of the PSC at the
beginning of this extension period.
The contractor will not be able to set off the
additional work programme from the next
phase.
The block will come in the domain of open
acreage and may be offered in a bidding
132Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
round or under open acreage system (as
and when it comes in force). However, in
case of any discovery as a result of work
programme under implementation during
this period, the contractor will have the right
to retain the relevant discovery areas as
reasonably determined by DGH / MC. In
case, the contractor as a result of
exploration during this extended period
desires to go to the next phase of
exploration, the contractor would be allowed
to proceed to the next phase for such
remaining area as is still open i.e., no
licenses / leases have been issued or has
not been offered under any bidding process
at the time
Will be required to pay 50% of the equivalent
amount of the unfinished additional work
programme, if MWP is not completed in the
extended period.
ii. Under Revenue Sharing Contract
Under all OALP Rounds
a) Clause 11.2.1 of Article 11 of MRSC
11.2.1 (a) The application for the Lease along with application fee, in respect of the
approved Development Area in respect of Offshore Blocks shall be submitted to the
Government within thirty (30) days from the approval of Development Area pursuant to
Article 10.
(b) The application for the Lease along with application fee, in respect of the approved
Development Area located in onshore area shall be submitted to the relevant State
Government within thirty (30) days from the approval of Development Area pursuant to
Article 10.
Under OALP Rounds I to III
a) Clause 3.2 of Article 3 of MRSC
3.2 Except as otherwise provided in Articles 3.3 and 3.4, the Exploration Period shall
begin on the Effective Date, shall consist of two phases – Initial Exploration Phase and
Subsequent Exploration Phase. The Exploration period will be of six (6) years for all types
of Blocks. The Initial Exploration Phase shall consist of
a) Initial three (3) consecutive Contract Years with a provision for single extension of
maximum one (1) year for contract areas falling in Onland and Shallow Water; and
133Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
b) Initial three (3) consecutive Contract Years with a provision for up to two extensions of
maximum one (1) year each in case of contract areas falling in Deep Water, Ultra Deep
Water and Specified Basin
The Contractor shall have an option to proceed to the Subsequent Exploration Phase as
per Article 3.3. Subsequent Exploration Phase shall consist of
a) Maximum of three (3) consecutive Contract Years as per Article 3.3 with a provision
for single extension of maximum one year for contract areas falling in Onland and Shallow
Water; and
b) Maximum of three (3) consecutive Contract Years as per Article 3.3 with a provision
for up to two extensions of maximum one year each in case of contract areas falling in
Deepwater, Ultra-Deepwater and Specified Basin
Provided that the Lease period granted for an initial period of twenty (20) years in the
manner as prescribed under Article 11 shall not comprise of the Exploration Period under
Clause 3.
Exploration Period shall be for a duration not exceeding the time period as given in the
table in Appendix K.
Under OALP Rounds IV to VIII
a) Clause 3.4 of Article 3 of MRSC
3.4 For the purpose of completion of Committed Work Programme, the Contractor may
extend the Exploration Period specified in Article 3.2 for a maximum period of nine (9)
months in case of Onland/Shallow Water/CBM Blocks and eighteen (18) months in case
of Deep Water/ Ultra-Deep Water Blocks by making a payment to the Government at
least thirty (30) days prior to the expiry of Exploration Period as follows:
i) For Onland/Shallow Water/CBM Blocks: USD 25,000 or its INR equivalent per month
or any part of the month for the duration of extension sought.
ii) For Deep Water/Ultra-Deep Water Blocks: USD 50,000 or its INR equivalent per month
or any part of the month for the duration of extension sought.
The payment for seeking extension shall be made to the Bank Account prescribed by
Government. The extension shall be automatic on making the payment in the account.
The extensions can be sought multiple times by making requisite payment subject to
cumulative maximum period prescribed above.
iii. Under DSF Contract
a) Clause 11.1, Clause 11.2 and Clause 11.3 (b) of Article 11 of MRSC
134Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
11.1 Petroleum Exploration License and Lease
11.1.1 In the event Existing Discovery (ies), being a discovered small field/ contract area
operated by ONGC/OIL and the License/Lease has already been issued in favour of
ONGC/OIL, the Government hereby agrees that it shall approve and enable the transfer
of the License/Lease, as applicable, by ONGC / OIL in favour of the Contractor under the
provisions of Rule 17 of the P&NG Rules. Provided that in the event that such transfer
could not be completed within [60] sixty days of the execution of this Contract, the issued
License/Lease shall be terminated. The Contractor thereafter shall submit forthwith an
application for grant of Lease in respect of the contract area.
11.1.2 In the event the Field/contract area did not have an earlier Lease already issued
or such Lease could not be transferred, then the Government shall on the application of
the Contractor grant to the Contractor a Lease, to enable the Contractor to carry out
Petroleum Operations in the contract area.
11.1.3 The Lease shall be granted for an initial period of twenty (20) years from the date
of grant thereof subject to: a. cancellation in accordance with its terms, or on termination
of this Contract in accordance with its terms;
b. the Lease period may be extended by mutual agreement between the Government
and the Contractors for such period as may be agreed after taking into account the
balance recoverable reserve and balance economic life of the Field/ contract area in the
contract area from the expiry of the initial period. Provided that such extension would be
for a period up to five (5) years or beyond as may be mutually agreed or as per extant
Government policies/ guidelines.
c. the terms of this Contract and other terms and conditions as set forth in such Lease be
consistent with this Contract and the relevant legislation.
11.2 Right to undertake Exploration for the duration of the Lease The Contractor shall
have the right to explore for Petroleum (of any type) within the area covered by the mining
Lease for the entire duration of the said Lease.
11.3 Where a Discovery extends beyond the Development Area designated in the Field
Development Plan, subject to Article 10, such area may be included in the proposed
Development Area, in relation to which application for a Lease is made, on such terms
and conditions as decided by the Government; provided that such area is:
a. not subject to a License or Lease granted to any other person;
b. not the subject of negotiations/bidding for a License or Lease; and
c. Available for licensing (i.e., is not an area over which Petroleum Operations are
excluded; and in relation to all areas which are not subject to any litigation or arbitration).
iv. Under CBM Contract
135Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
a) Clause 5 of Policy for Extension of Exploration Phases for Exploration and
Production under Coal Bed Methane contracts dated November 17, 2007
In order to adopt a transparent and consistent framework for granting extension in
exploration phases, 'the Government in line with the existing policy of extension under
NELP contract has framed. an extension policy for considering proposals seeking.
extension in exploration phases under CBM contracts, which are either pending with the
Government or may be received in future. The extension in phases under CBM Contracts
in terms of, this policy. guidelines ·would be considered within the validity of the
exploration period of 8 years. The broad objective of the extension policy is as under:
To maintain the integrity of the bidding process and the spirit of the Contract to explore
·and produce CBM gas early.
To grant reasonable extension of time so as. to enable contractors to complete MWP or
additional exploration work programme;
Not to delay the execution of development plan or production or the life cycle of the entire
project and payment of Royalty, taxes and contractual payments
iv) To act as deterrent for seeking unnecessary extension or holding on acreages
without doing any or little expl6ration activities or activity at slow pace.
v) The. policy envisages a system of penalty by way of submission of bank guarantee
and pre-estimated agreed Liquidated damages (in some cases/situations in lieu of
unfinished or additional work programme. While proposing the amount of Bank
guarantee, situations/factors. such as whether extension. is for completing MWP or
additional Work Programme, whether commerciality has been established in the contract
area, whether contract wants to retain the area for further exploration have been kept in
mind.
vi) Up to 6 months extension may be given by the Steering Committee or the Government.
on merit in terms of the provisions of the respective Contracts.
vii) Demonstrable delays on account of getting Government approvals /permits /
clearances which are not attributable to the contractors will be counted as excusable
delays and such delays shall be condoned. In this regard, if some extensions have
already been granted by Steering Committee/Government on account of excusable
delays, which took place from effective date of the Contract i.e., including delays prior to
the extension policy coming in force the same will be regulated as CBM extension policy
viii) In case, the contractor does not fulfill the work programme within the stipulated period
or extended period, as may be the case, he shall be required to pay money for the
unfinished work programme, if any, to the Government in terms of the respective
provisions of the contracts.
b) Clause 2.6 of MoPNG notification Policy framework for early monetization of Coal
Bed Methane dated 11 April 2017
2.6 Effective date of the contract
136Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
If delay in grant of Petroleum Exploration License (PEL) exceeds two (2) years from the
State Governments in any Block, the Contractor if exercises exit option from the CBM
Block, will be permitted to exit without paying cost of unfinished work program.
6.3.7. Process for PSC extension applications and approvals
a) Clause 1 of the policy for granting extension to PSC dated March 28, 2016
1.Submission, Consideration and Approval of request for extension of Contract:
The Contractor should submit the application duly approved by the Operating Committee
for extension of Contract to MoPNG at least 2 years in advance of the expiry date, of
Contract. but not more than 6 years in advance, with a copy to DGH. DGH will make a
recommendation to MoPNG within 6 months of submission of application by the
contractor The Government will take a decision on the request for, extension within 3
months of receipt of the proposal from DGH
6.3.8. Provisions of incentives on sale for natural gas to private operators in
Northeast region
a) Clause 2 of notification titled “Price of APM natural gas produced by National Oil
Companies (NOCs)” dated 31 May 2010
2. For customers in North-East, the net consumer price would be 60% of the above,
i.e., US $ 2.52/mmbtu, on NCV basis. The difference would be paid to ONGC & OIL
through Government budget.
b) Clause 12 of “New Domestic Natural Gas Pricing Guidelines, 2014”
12. In the Northeastern Region (NER), the 40% subsidy would continue to be available
for gas supplied by ONGC/OIL. However, as private operators are also likely to start
production of gas in NER, and would be operating in the same market, this subsidy would
also be available to them to incentivize exploration and production.
6.3.9. Transfer of Participating Interest (PI) among existing PI holders under a
contract
i. Under Production Sharing Contract
a) Clause 28.1, Clause 28.1.1 and Clause 28.2 of Article 28 of MPSC
28.1 Subject to the terms of this Article and other terms of this Contract, any Party
comprising the Contractor may assign, or transfer, a part or all of its Participating Interest,
with the prior written consent of the Government, which consent shall not be
unreasonably withheld, provided that the Government is satisfied that:
137Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
(a) the prospective assignee or transferee is of good standing, has the capacity and ability
to meet its obligations hereunder, and is willing to provide an unconditional undertaking
to the Government to assume its Participating Interest share of obligations and to provide
guarantees in respect thereof as provided in the Contract;
(b) the prospective assignee or transferee is not a company incorporated in a country
with which the Government, for policy reasons, has restricted trade or business;
(c) the prospective assignor or transferor and assignee or transferee respectively are
willing to comply with any reasonable conditions of the Government as may be necessary
in the circumstances with a view to ensuring performance under the Contract;
(d) the assignment or transfer will not adversely affect the performance or obligations
under this Contract or be contrary to the interests of India.
(e) the prospective assignor or transferor of small size onland block having contract area
less than 200 Sq. Km has completed the Minimum Work Programme committed under
Initial Exploration Period as specified in Article 5.2 and 5.2.1
28.1.1 Subject to Article 28.7, nothing in this Article 28 shall prevent a Party comprising
the Contractor from assigning or transferring a part or all of its Participating Interest to an
Affiliate, with the approval of the Management Committee, provided that;
(a) the assignee provides an irrevocable, unconditional bank guarantee from a reputed
bank of good standing in India, acceptable to the Government, in favour of the
Government, for the amount specified in Article 29.3, in a form provided at Appendix-G;
(b) the assignee provides a parent financial and performance guarantee issued by the
guarantor which furnished the guarantee pursuant to Article 29 in respect of the assignor
Party’s obligations under this Contract in favour of the Government, of the performance
of such Affiliate assignee of its obligations under this Contract;
(c) the prospective Affiliate is not a company incorporated in a country with which the
Government, for policy reason, has restricted trade or business;
(d) the assignment will not adversely affect the performance or obligations under this
Contract or be contrary to the interest of India.
(e) the prospective assignor or transferor of small size onland block having contract area
less than 200 Sq. Km has completed the Minimum Work Programme committed under
Initial Exploration Period as specified in Article 5.2 and 5.2.1
28.2 In case of any change in the status of a Company or its shareholding resulting in a
change in:
(a) the control of the Company; or
138Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
(b) its relationship with the company(ies) providing the guarantee under Article 29.1 (a),
29.1 (b) and 29.2;
the Company shall seek prior written consent of the Government for assigning the
Participating Interest under the changed circumstances and the provisions of this Article
28 shall apply, mutatis mutandis, to be obtaining of such consent. For the purpose of this
Article 28.2, control has the same meaning as in Article1.3.
ii. Under Revenue Sharing Contract
Till OALP Round VII
a) Clause 26.1 of Article 26 of MRSC
26.1 Subject to the terms of this Article and other terms of this Contract, any Member
comprising the Contractor may assign, or transfer, a part or all of its Participating Interest,
with the prior written consent of the Government, which consent shall not be
unreasonably withheld, provided that the Government is satisfied that:
(a) the prospective assignee or transferee, has the capacity and ability to meet its
obligations hereunder, and is willing to provide an unconditional undertaking to the
Government to assume its Participating Interest share of obligations and to provide
guarantees in respect thereof as provided in the Contract;
(b) the prospective assignee or transferee is not a company incorporated in a country
with which the Government, for policy reasons, has restricted trade or business;
(c) the prospective assignor or transferor and the assignee or transferee are willing to
comply with any reasonable conditions of the Government as may be necessary in the
circumstances with a view to ensuring performance under the Contract; and
(d) the assignment or transfer will not adversely affect the performance or obligations
under this Contract or be contrary to the interests of India.
Under OALP Round VIII
a) Clause 26.3 and Clause 26.7 of Article 26 of MRSC
26.3 In case of any change in the:
(a) status of a Member or its shareholding resulting in a change in the “control” of any
Member comprising the Contractor; or
(b) the “control” of the Parent Company of any Member; or
(c) status of a Member or its shareholding resulting in a change in its relationship with
any company providing the guarantee specified under Article 27.1(a) and 27.1 (b);
139Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Such change or changes, as the case may be, shall be deemed as an assignment of
Participating Interest of the Member and the concerned Member shall seek prior written
consent of the Government for any such change or changes and the provisions of this
Article 26 shall apply, mutatis mutandis, to the obtaining of such consent and approval
thereof by the Government. For the purpose of this Article, “control” shall have the same
meaning as in Article 1.1.2.
iii. Under DSF Contract
a) Clause 26.1 and Clause 26.2 of Article 26 of DSF Contract
26.1 Subject to the terms of this Article and other terms of this Contract, any Party
comprising the Contractor may assign, or transfer, a part or all of its Participating Interest,
with the prior written consent of the Government, which consent shall not be
unreasonably withheld, provided that the Government is satisfied that:
(a) the prospective assignee or transferee is of good standing, has the capacity and ability
to meet its obligations hereunder, and is willing to provide an unconditional undertaking
to the Government to assume its Participating Interest share of obligations and to provide
guarantees in respect thereof as provided in the Contract;
(b) the prospective assignee or transferee is not a company incorporated in a country
with which the Government, for policy reasons, has restricted trade or business;
(c) the prospective assignor or transferor and assignee or transferee respectively are
willing to comply with any reasonable conditions of the Government as may be necessary
in the circumstances with a view to ensuring performance under the Contract; and
(d) the assignment or transfer will not adversely affect the performance or obligations
under this Contract or be contrary to the interests of India.
26.2 In case of any change in the status of a Company or its shareholding resulting in a
change in:
(a) the control of the Company; or
(b) its relationship with the company(ies) providing the guarantee under Article 27; the
Company shall seek prior written consent of the Government and the provisions of this
Article 26 shall apply, mutatis mutandis, to be obtaining of such consent. For the purpose
of this Article 26.2, control has the same meaning as in Article1.3.
iv. Under CBM Contract
Till CBM Round IV
a) Clause 25.1 and Clause 25.2 of Article 25 of CBM Contract
140Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
25.1 Subject to the terms of this Article and other terms of this Contract, a Company may
assign, or transfer, a part or in whole of its Participating Interest, with the prior written
consent of the Government, which consent shall not be unreasonably withheld, provided
that the Government is satisfied that;
(a) the prospective assignee or transferee has financial capability and technical
competence where relevant to the satisfaction of Government to meet its obligations
hereunder, and is willing to provide an unconditional undertaking to assume its
Participating Interest share of obligations and to provide guarantees in respect thereof as
provided in the Contract;
(b) the prospective assignee or transferee is not a company incorporated in a country
with which the Government, for policy reasons, has restricted trade or business;
(c) the assignor or transferor and the prospective assignee or transferee respectively
are willing to comply with any reasonable conditions of the Government as may be
necessary in the circumstances with a view to ensuring performance under the Contract;
and
(d) the assignment or transfer will not adversely affect the performance or obligations
under this Contract or be contrary to the interests of India.
25.2 In case of any change in the status of a Company or its shareholding resulting in a
change in:
a) the control of the Company; or
b) its relationship with the company(ies) providing the guarantee under Articles 26.1
(a) and 26.1 (b);
the Company shall seek the consent of the Government for assigning the Participating
Interest under the changed circumstances and the provisions of this Article 25 shall apply,
mutatis mutandis, to be obtaining of such consent. For the purpose of this Article 25.2,
control has the same meaning as in Article 1.3.
Under SCBM Round
a) Clause 26.1 of Article 26 of SCBM Contract
26.1 Subject to the terms of this Article and other terms of this Contract, any Member
comprising the Contractor may assign, or transfer, a part or all of its Participating Interest,
with the prior written consent of the Government, which consent shall not be
unreasonably withheld, provided that the Government is satisfied that:
(a) the prospective assignee or transferee, has the capacity and ability to meet its
obligations hereunder, and is willing to provide an unconditional undertaking to the
141Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
Government to assume its Participating Interest share of obligations and to provide
guarantees in respect thereof as provided in the Contract;
(b) the prospective assignee or transferee is not a company incorporated in a country
with which the Government, for policy reasons, has restricted trade or business;
(c) the prospective assignor or transferor and the assignee or transferee are willing to
comply with any reasonable conditions of the Government as may be necessary in the
circumstances with a view to ensuring performance under the Contract; and
(d) the assignment or transfer will not adversely affect the performance or obligations
under this Contract or be contrary to the interests of India.
6.3.10. Annual Work Programme (AWP) approval under CBM regime
a) Clause 10.3 of Article 10 of CBM Contract
10.3 Annual Work Programmes and Budgets for Development Operations shall be
submitted to the Steering Committee as soon as possible after the approval of the
Development Plan and thereafter not later than 31 December of each Year immediately
following.
6.3.11. Flexibility to deploy new exploration technology/ methods for meeting
Minimum, Committed or Bid Work Programme
i. Under Production Sharing Contract
a) Clause 4 of the MoPNG notification, Policy Framework for Relaxations,
Extensions and Clarifications at the development and Production Stage under the
PSC dated November 10, 2014
4 Swapping of 2D (Dimensional) and 3D Seismic in Minimum Work Programme
(MWP)
4.1 There is no provision in PSC to swap 2D seismic survey program of MWP with 3D
survey program which may be required due to technical or logistical reasons and vice
versa.
4.2 DGH is empowered to approve the swapping of 2D Acquisition Processing and
Interpretation (API) data and 3D API data ·with each other, where it.is justified on the
basis of technical and logistical merits, after proper scrutiny on recommendations of MC.
The basis of conversion would be 1sq.km of 3D would be equivalent 10 Line Kilometer
(km). of 2D. This would cover mandatory 2D Seismic API also and will be applicable to
the existing and future cases in all PSCs. However, when the contractor has bid for full
area 2D and full area 3D, then substitution would not be allowed.
ii. Under Revenue Sharing Contract
Till OALP Round VII
142Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
a) Clause 5.4 of Article 5 of MRSC
5.4 Subject to Article 29, in the event that the Contractor fails to fulfill the said Committed
Work Programme, then each Member constituting the Contractor shall pay to the
Government its Participating Interest share for an amount which shall be equivalent to
Liquidated Damages as specified in Appendix I.
LD shall be payable for the quantum that falls short against Committed Work Programme.
However, in case of Well(s) which have not been drilled upto the depth specified in the
Committed Work Programme stated under article 5.1, the Contractor shall pay LD for the
entire Well, irrespective of the meterage left to be drilled.
DGH shall approve the swapping of 2D Acquisition, Processing and Interpretation data
and 3D Acquisition, Processing and Interpretation data with each other, in a manner such
that the weighted seismic programme quoted, and the marks obtained at the time of
bidding remains the same or are higher.
In case of swapping of 2D and 3D Acquisition, Processing and Interpretation data, the LD
will be levied as per Committed Work Programme.
Under OALP Round VIII
a) Clause 5.7 of Article 5 of MRSC
5.4 Subject to Article 29, in the event that the Contractor fails to fulfill the said Committed
Work Programme, then each Member constituting the Contractor shall pay to the
Government its Participating Interest share for an amount which shall be equivalent to
Liquidated Damages as specified in Appendix I.
LD shall be payable for the quantum that falls short against Committed Work Programme.
However, in case of Well(s) which have not been drilled upto the depth specified in the
Committed Work Programme stated under article 5.1, the Contractor shall pay LD for the
entire Well, irrespective of the meterage left to be drilled.
DGH shall approve the swapping of 2D Acquisition, Processing and Interpretation data
and 3D Acquisition, Processing and Interpretation data with each other, in a manner such
that the weighted seismic programme quoted, and the marks obtained at the time of
bidding remains the same or are higher.
In case of swapping of 2D and 3D Acquisition, Processing and Interpretation data, the LD
will be levied as per Committed Work Programme.
iii. Under CBM Contract
Till CBM Round IV, there are no provisions for swapping in Committed Work
Programme
Under SCBM Round
a) Clause 5.4 of Article 5 of SCBM Contract
143Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
5.4 Subject to Article 29, in the event that the Contractor fails to fulfill the said Committed
Work Programme, then each Member constituting the Contractor shall pay to the
Government its Participating Interest share for an amount which shall be equivalent to
Liquidated Damages as specified in Appendix I.
LO shall be payable for the quantum that falls short against Committed Work Programme.
However, in case of Well{s) which have not been drilled upto the depth specified in the
Committed Work Programme stated under article 5.1, the Contractor shall pay LO for the
entire Well(s), irrespective of the meterage left to be drilled.
DGH shall approve the swapping of 2D Acquisition, Processing and Interpretation data
and 3D Acquisition, Processing and Interpretation data with each other, in a manner such
that the weighted seismic programme quoted, and the marks obtained at the time of
bidding remains the same or are higher. In case of swapping of 2D and 3D Acquisition,
Processing and Interpretation data, the LD will be levied as per Committed Work
Programme.
6.3.12. Exchange rate conversion methodology across contract regimes
i. Under Production Sharing Contract
a) Clause 1.6.1 of Appendix C Section 1 of MPSC
1.6 Currency Exchange Rates
1.6.1 For conversion purposes between United States Dollars and Indian Rupees or any
other currency the Reserve Bank of India Reference Rate of Exchange for the transaction
day on which the revenues, costs, expenditure, receipts or income are recorded shall be
used.
If Royalty or Government share of Profit Petroleum is remitted in Indian Rupees, the
Reserve Bank of India Reference Rate of exchange of the day preceding the payment
day shall be used.
1.6.2 Any realized or unrealized gains or losses from the exchange of currency in respect
of Petroleum Operations shall be credited or charged to the accounts. A record of the
exchange rates used in converting Indian Rupees or any other currencies into United
States Dollars as specified in Section 1.6.1 shall be maintained by the Contractor and
shall be identified in the relevant Statements required to be submitted by the Contractor
in accordance with Section 1.4.2.
ii. Under Revenue Sharing Contract
Till OALP Round VII
a) Clause 15.6 of Article 15 of MRSC
15.6 The Contractor shall remit Royalty and Government share of Revenue in Indian
Rupees (INR). For conversion purposes between United States Dollars and Indian
Rupees or any other currency, the Reserve Bank of India Reference Rate of Exchange
144Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
for the transaction day on which the revenues receipts or income are recorded shall be
used.
b) Under Appendix G of MRSC
* Bank Guarantee can be submitted in INR. For exchange rate from USD to INR,
exchange rate published by FBIL for the same day or immediate previous working day
can be used.
**Jurisdiction of the BG shall be New Delhi or Place of issuance of BG.
Under OALP Round VIII
a) Clause 15.6 of Article 15 of MRSC
15.6 The Contractor shall remit Royalty and Government share of Revenue or any other
Government dues under the Contract in Indian Rupees (INR). For conversion purposes
between United States Dollars and Indian Rupees or any other currency, the
RBI/FBIL/RBI authorized agency reference rate of Exchange on the transaction day on
which such remittance is made shall be used. The abbreviation of RBI and FBIL shall
mean Reserve Bank of India and Financial Benchmarks India (P) Limited, respectively.
iii. Under DSF Contract
Till DSF Round II
a) Clause 15.5 of Article 15 of DSF Contract
15.5 The Government's share of Revenue for a month shall be paid by the Contractor to
the Government latest by the end of succeeding Month. In the event of any failure to pay
Government's share of Revenue within the due date, the Contractor shall pay interest
compounded on daily basis for the entire period of delay at LIBOR as defined in Article
1.60 plus two (2) percentage points.
Under DSF Round III and SDSF Round
a) Clause 15.6 of Article 15 of DSF Contract
15.6 The Government's share of Revenue for a month shall be paid by the Contractor to
the Government latest by the end of succeeding Month. In the event of any failure to pay
Government's share of Revenue within the due date, the Contractor shall pay interest
compounded on daily basis for the entire period of delay at “SOFR plus 0.42826
percentage points” plus 2 (two) percentage points/200 basis points.
iv. Under CBM Contract
Till CBM Round IV
145Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
a) Clause 17.3 of Article 17 of CBM Contract
17.3 The rates of exchange for the purchase and sale of currency by the Contractor and
its constituents shall be the prevailing rates of general application determined by the
Reserve Bank of India or such other financial body as may be mutually agreed by the
Parties and, for accounting purpose under this Contract, these rates shall apply as
provided in Section 1.6 of Appendix C.
Under SCBM Round
a) Clause 15.6 of Article 15 of SCBM Contract
15.6 The Contractor shall remit Royalty and Government share of Revenue in Indian
Rupees (INR). For conversion purposes between United States Dollars and Indian
Rupees or any other currency, the Reserve Bank of India Reference Rate of Exchange
for the transaction day on which the revenues receipts or income are recorded shall be
used.
6.3.13. Acceptance of Unconditional and Irrevocable Surety Bonds In lieu of Bank
Guarantee (BG)
i. Amendment to General Financial Rules (GFR), 2017 to include Insurance
Surety Bonds as Security Instrument
146Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
ii. Under Production Sharing Contract
b) Clause 29.2, Clause 29.3 (a) and Clause 29.3 (b) of Article 29 of PSC Contract
29.2 If the Contractor elects to retain the contract area during the Subsequent Exploration
Period by committing to drill Exploration Wells after completing the Minimum Work
Programme, under Article 3.4 (a), each of the Companies constituting the Contractor shall
procure and deliver to the Government before the expiry of the Initial Exploration Period
an irrevocable, unconditional bank guarantee from a reputed bank of good standing in
India, acceptable to the Government, in favour of the Government, for the amount
specified in Article 29.3 and valid for the Subsequent Exploration Period opted by the
Contractor, in a form provided at Appendix-G.
29.3
(a) The amount of the guarantee referred to in Articles 29.1 (a) and 29.2 above shall be
an amount equal to seven and one half percent (7 ½ %) of the Company’s Participating
Interest share of the total estimated expenditure in respect of Minimum Work Programme
including Mandatory Work Programme or Work Program as the case may be, to be
147Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
undertaken by the Contractor in the contract area during the Initial or Subsequent
Exploration Period. The total estimated expenditure for the Exploration Period for the
purpose of furnishing bank guarantee by the Contractor shall be higher of the cost
estimates by the Contractor or the Budget estimates presented to the Management
Committee, or the amount of Liquidated damages specified in Article 5.
(b) after the completion and due performance of the Minimum Work Programme including
Mandatory Work Programme or committed Work Programme during Initial Exploration
Period or the Subsequent Exploration Period, as the case may be, the guarantee will be
released in favour of the Company on presentation to the bank of a certificate from the
Government that the obligation of the Contractor has been fulfilled and the guarantee
may be released. Such certificate shall be provided within thirty (30) days from the
completion of the said Work Programme and fulfilment of obligations under the Contract
to the satisfaction of the Government.
iii. Under Revenue Sharing Contract
b) Clause 27.1 (a) of Article 27 of RSC Contract
27.1 Each of the Members constituting the Contractor or their Parent Companies or the
Operator on behalf of the other Members, shall procure and deliver to the Government
within thirty (30) days from the Effective Date, or within thirty (30) days from the date of
opting for the mandatory Exploratory well(s) for Phase-II (Part-A and Part-B), as
applicable:
(a) an irrevocable, unconditional Bank Guarantee from a Scheduled Commercial Bank of
good standing in India, acceptable to the Government, in favor of the Government, for the
amount specified in Article 27.2 and valid for the Exploration Period for which bid
commitments are made as specified in Article 5.1 with claim period of sixty (60) days, in
a form provided at Appendix G;
iv. Under DSF Contract
b) Clause 27.1 (a), Clause 27.2 (a) and Clause 27.2 (b) of Article 27 of DSF
Contract
27.1 Each of the Companies constituting the Contractor shall procure and deliver to the
Government within thirty (30) days from the Effective Date of this Contract:
(a) an irrevocable, unconditional bank guarantee from a reputed bank of good standing
in India, acceptable to the Government, in favour of the Government, for the amount
specified in Article27.2 and valid for the period (3, 4, 6 years as the case may be) specified
in Article 3.2 with claim period of 90 days, in a form provided at Appendix E;
27.2 (a) The bank guarantee referred to in Article 27.1 (a) above shall be for an amount
calculated at rates specified in Article 5.2. in respect of the Bid Work Program Specified
in Article 5.1, provided that in the absence of any Bid Work Program stipulated in Article
5.1, the bank guarantee shall be submitted for a minimum guarantee of equivalent
amount of USD 0.15 million, USD 0.23 million and USD 0.30 million respectively for
contract area in on-land, shallow water and deep water.
148Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
(b) After the completion and due performance of the Bid Work Program, the guarantee
will be returned to the Company, provided that a bank guarantee submitted in respect of
the minimum amount shall be returned on commencement of commercial production or
on completion of period stipulated in Article 3.2 of RSC, whichever is earlier.
v. Under CBM Contract
Till CBM Round IV
b) Clause 26.1 (a), Clause 26.3 (a) and Clause 26.3 (b) of Article 26 of CBM
Contract
26.1 Subject to Article 26.1 (d), each of the Companies constituting the Contractor shall
produce and deliver to the Government on the Effective Date of this Contract:
(a) an irrevocable, unconditional bank guarantee from a reputed bank of good standing
in India, acceptable to the Government, in ·favour of the Government, for the amount
specified in Article 26.2 in a form and substance acceptable to the Government as set out
in Appendix-F;
26.3 The guarantee shall provide that:
(a) the amount referred to in Article 26.2 shall be automatically adjusted at the end of
each Year for an amount equal to a Company's participating share of thirty five percent
(35%) of the total estimated expenditure in respect of the Work Programme to be
undertaken for the following Year of the relevant Phase till Phase-II. The guarantee shall
be renewed at the end of each Year positively thirty (30) days before the expiry of the
guarantee period; and
(b) after the completion and due performance of the Minimum Work Programme of
Phase-I or Phase-II, as the case may be, the guarantee will be released in favour of the
Company on presentation of a certificate from the Government to the bank that the
obligation of the Contractor has been fulfilled and the guarantee may be released, subject
to Article 26.4. Such certificate shall be provided within thirty (30) days from the
completion of the Minimum Work Programme and fulfillment of obligation under the
contract to the satisfaction of the government.
Under SCBM Round
b) Clause 27.1 (a) of Article 27 of SCBM Contract
27.1 Each of the Members constituting the Contractor or their Parent Companies or the
Operator on behalf of the other Members, shall procure and deliver to the Government
within thirty (30) days from the date on which this Contract is executed by the Parties:
(a) an irrevocable, unconditional Bank Guarantee from a Scheduled Commercial Bank
of good standing in India, acceptable to the Government, in favor of the Government, for
the amount specified in Article 27 .2 and valid for the Exploration Period for which bid
commitments are made as specified in Article 5.1 with claim period of sixty (60) days, in
a form provided at Appendix G.
149Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
150Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
6.4. Annexure IV: Regime-wise issues pending for deliberation
for next phase of JWG
Resolution Time Short Term Medium Term Long Term
S.
Issues Submission by JWG Members Regime Category
No.
Para 8 of the Site Restoration
Fund Scheme, 1999, provides that
“A depositor shall be entitled to
withdraw from the amount
standing to the credit of the
account only such amount as is
necessary to meet any
expenditure to be incurred by him
on the expiry or termination of
the agreement or
relinquishment of part of the
contract area, towards removal
of all equipment and
installations, in a manner agreed
with the Central Government
pursuant to an abandonment plan
or towards all necessary site
restoration in accordance with
modern oilfield and petroleum
industry practices and towards
meeting all other expenses
Withdrawal and
necessary to prevent hazards to
Utilization of amount
life or property or environment
deposited as per Site
consequent on such expiry,
Restoration Fund
1 termination or relinquishment.” PSC Financial
Scheme (Section
33ABA read with Site
DGH is denying the bona fide
Restoration Fund
request for withdrawal of Site
Scheme, 1999)
Restoration Fund for carrying out
the planned abandonment
activities on the plea that the
abandonment activities proposed
to be carried out are not
followed/coupled by the expiry or
termination of the agreement or
relinquishment of part of the
contract area.
It is suggested, para 8 of the Site
Restoration Fund Scheme, 1999
may be modified as follows-
“A depositor shall be entitled to
withdraw from the amount
standing to the credit of the
account only such amount as is
necessary to meet any
expenditure to be incurred by him
either on the expiry or
termination of the agreement or
relinquishment of part of the
151Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
contract area or otherwise,
towards removal of all
equipment and installations, in a
manner agreed with the Central
Government pursuant to an
abandonment plan or towards all
necessary site restoration in
accordance with modern oilfield
and petroleum industry practices
and towards meeting all other
expenses necessary to prevent
hazards to life or property or
environment consequent on such
expiry, termination or
relinquishment.”
. Medium Term
Methodology for determining
eligible deduction u/s 42 in
respect of RSC blocks
Relevant Article of RSC signed
with the GoI in respect of OALP &
DSF blocks has provided that all
expenditure incurred on
exploration, development and
production shall be allowed as
deduction u/s 42 of the Act.
However, it does not provide for
the methodology for claiming such
expenditure, unlike in earlier PSCs
(under NELP regime)
Issues related to
DGH proposed for amendment in
2 deductions u/s 42 in RSC Financial
RSCs of OALP (Rounds I to VII) to
respect of RSC Blocks
incorporate the methodology in
line with amendment in model
RSC of OALP VIII, with
retrospective effect.
As per proposed amendment, tax
treatment of survey expenditure
would be in line with the tax
treatment of exploration/drilling
expenditure i.e., survey
expenditure incurred before
commercial production needs to
be accumulated till the year of
relinquishment of the area or
commencement of the commercial
production.
152Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
Proposed amendment in RSC for
OALP (Rounds I to VII), would
debar the ONGC from claiming
survey expenditure in such blocks
on incurrence basis and tax
deduction already claimed would
also get impacted.
MoP&NG/DGH may like to review
the proposed methodology for
claiming tax deduction u/s 42 of
the Act being incorporated in the
RSC and to make any amendment
in the already signed RSCs with
prospective effect.
. Medium Term
Amendment in RSC blocks to
allow exemptions under section 42
of the Income Tax Act (pending for
3 RSC Financial
4 years)
. Long Term
Precisely defining the scope of On-
shore and Off-shore Oil & Gas
Exploration activities in the gazette
notification S.O.236 (E) dtd 16th
January 2020, through which such
activities has been categorized as
B2 schedule project under EIA
Notification, 2006
Complex procedure to Gazette notification S.O.236 (E)
obtain Environmental dtd 16th January 2020 need to be All
4 Procedural
Clearances (EC) and amended by incorporating a 3rd regimes
other clearances point in the note column of the
gazette as detailed below:
“Off-shore and Onshore oil and
gas Exploration will include
Appraisal Testing and Extended
Testing with associated Flaring
and required facilities like Early
Production Unit (EPU) / Quick
Production Unit (QPU) etc.”
Long Term
153Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
Environmental clearance for oil
and gas exploration projects
located beyond 12 NM of the
Indian territorial water need not to
be insisted under purview of EIA
Notification, 2006 or the Draft EIA
Notification, 2020, which presently
under public consultation since
after gazette notification published
on 23.03.2020
DGH to modify the clause 14.5.1 &
14.5.2 in PSC /RSC contract
replacing the clause of obtaining
Govt. approval of EIA reports for
Off-shore Drilling activities beyond
12 NM with - “EIA report to be
made as per international All
Procedural
Standard with self-certification by regimes
the operator and duly vetted by
OISD” -No approval from Govt
Agency etc. should be included
there OISD may be considered as
the competent authority for
approving the EIA Report and
authorized to monitor
environmental parameters beyond
12 NM, as OISD-RP-201 already
prescribes Environment
Management in E&P sector and
there are similar other
Standards/RP/GDN available with
OISD for Offshore operations
. Long Term
The validity of Environment
Clearance (EC) for Oil & Gas E&P
All
activities need to be made co- Procedural
regimes
terminus with PML under provision
of EIA Notification,2006
Long Term
154Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
To facilitate part transfer of EC for
Discovered Small Field (DSF)
blocks from previous Lessee to
other Operators by carving areas
from the PML blocks, for which
valid ECs are available with the
original PML block owners-OIL/
ONGC/ Others
DGH may facilitate/ mediate for
such EC bifurcation/ transfer
process for which valid EC is
available and such are permissible
under provision of clause (11) of
EIA notification, 2006. which reads
as: A prior environmental
clearance granted for a specific
project or activity to an applicant
Bifurcation of original EC into two
parts proposed with amendment of
original EC under provision of
regulation 11 (Transferability of
Environmental Clearance) of EIA
Notification, 2006, will facilitate the
operator to save this time and start
Oil & Gas extraction Process
, Medium Term
To permit construction of linear
pipeline projects in non-forestland
land at risk and cost of the
Operator, for the EC proposals All
Procedural
which involves both forest as well regimes
as non-forest lands
Long Term
Consideration of Industry
suggestions on amendment of
draft EIA Notification, 2020
published by MoEF&CC through
gazette notification S.O 1199 (E)
dtd 23rd March 2020 MoPNG may All
consider the suggestions put regimes
forwarded by the industry group
and forward the same to
MoEF&CC
. Long Term
155Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
Common consent for Social
Licenses (EC, FC, CRZ, PCB)
under a single application
Unified approval for Marine O&G
All
Infrastructure (DGS, MOHA, Procedural
regimes
Naval, Maritime Board, Customs).
Zero Date to be linked to
Regulatory Approvals.
Long Term
Streamlining and simplification of
time consuming and complex
procedures by involving the DGH,
which may reduce delays in project
execution: E.g., DGH may issue a
clarifying note on reinjection of PW
to SPCB & MoEF&CC requesting
to allow reinjection in reservoir
All
without requirement of treatment. Procedural
regimes
MoPNG can recommend
MoEF&CC to make DGH a part
proponent for EC approvals: DGH
could facilitate faster approval of
EC
. Long Term
Single window clearance of EC
(CRZ, GPCB, Forest etc.) must be
established being an important
part of the new projects. It is taking
All
more than two years’ time to get Procedural
regimes
these clearances. It will facilitate
early field development
Long Term
Single Window Statutory
clearances (EC, FC, CRZ etc.)
may be provided for the blocks on
offer for bidding or pre-approved
All
bidding areas may be offered for Procedural
regimes
carrying out exploration activities
Finalization of ESZ areas in the
North-East (viz. Dishing Patkai NP,
Borjan-Bherjan Padumoni,
Kaziranga NP) from MoEF&CC
156Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
should be expedited and
completed as soon as possible.
It attracts WLS clearance within
default 10 km radius for any project
sites/ drilling locations and delays
the projects
. Long Term
Extension of
EC for oil and gas projects should All
5 Environment Clearance Others
be linked to the life of the mine regimes
(EC) upto 30 yrs.
Long Term
To bring O&G upstream E&P
activities under administrative
control of OISD under MoPNG
under purview of Oil & Gas
Regulation and Development Act,
1948/ P&NG Rules, 1959 or any
Requirement of
other new regulation framed for the
singular Regulation &
purpose, instead of involvement of
Regulatory Authority
6 multiple Ministries. OISD presently Others Procedural
for governing/
is the standing Technical
monitoring upstream
Directorate for petroleum sector
Oil & Gas E&P Activities
reporting directly to the MoPNG on
Safety related issues and also
functions as regulatory agency for
offshore operations beyond 12 NM
. Long Term
Either one time License to be
Grant of one time PESO granted or if required necessary
approval/License for amendment may be made in the
the HSD Tank for a Act/Regulation for exempting HSD
specific Mobile Rig in tank of mobile rigs for one time
7 Others Procedural
line with those storage license for storing Class B
License/Approvals Petroleum more than 1,000 liters in
granted for pressure a single tank.
vessels etc.
. Medium Term
157Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
Early Site specific Eco Sensitive
Zones (ESZ) notifications
around Protected Areas (PA’s)
DGH to facilitate for early
notification of site specific ESZ
area for all pending cases around
the Oil blocks by prioritization of 8
cases referred above in the States
of Assam and Arunachal Pradesh
Pending site specific ESZ
Notifications, as a stop gap Others Procedural
measure, to adopt
recommendation of CEC (Central
Empowered Committee) in its
report dtd 20th September, 2012
against IA-1000- Which advises to
reduce 10 Km ESZ area to (100
mtr to 2 Km) as per size of the PAs
mentioned in the report.
Streamlining issues
related to approval from . Long Term
Standing Committee for
National Board of
Revive the Wildlife Division’s
Wildlife (SC-NBWL)
guideline dated 26.09.2014
after due
regarding obtaining approval from
recommendation from
SC-NBWL for projects executed in
8 State Board of Wildlife Others Procedural
ESZ areas and requiring EC as
for projects executed
well under EIA Notification, 2006
inside Protected Areas
(PAs) for projects
. Long Term
executed in ESZ areas,
outside the boundaries
of
Oil & Gas E&P activities are not
PAs
to be ‘Prohibited’ in site specific
ESZ areas outside the forest
boundary (notified or to be
notified)- Such should be
permitted as a ‘Regulated
Activities’ under provision of
prevailing regulations with
stringent monitoring
mechanisms, else the nation will
lose lot of reserves in the closed Others Procedural
proximity to forest areas
Instead of prohibiting, Oil & Gas
E&P activities are to be permitted
as a ‘Regulated Activities’ under
provision of prevailing regulations
with stringent monitoring
mechanisms in site specific ESZ
areas outside the forest boundary
158Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
(notified or to be notified)
. Long Term
Oil & Gas Seismic Survey should
be permitted inside National
Park/Wildlife Sanctuary & other
PAs, at least for the awarded
Others Procedural
blocks, else the reserve of
hydrocarbon can’t be assessed
. Long Term
Standing Committee for the State
Board for Wildlife (SC-SBWL) may
be constituted in all State/UTs
under Chairmanship of State Env
Minister in line with the Standing
Committee of National Board for
Wildlife (SC-NBWL) under
Chairmanship of Minister Env &
Others Procedural
Forests and conducting Quarterly
meetings of SC-SBWL for faster
approval of Wildlife Clearance
proposals for projects inside PAs
as well as ESZ areas, else it is
taking minimum 3/ 4 years’ time
. Long Term
Introduce Separate Form for
proposals executed in ESZ areas
and requiring approval from SC-
NBWL instead of using the present
prescribed Five-part format
Others Procedural
designed for execution of projects
with diversion of forest lands inside
the Protected Areas
. Long Term
Oil & Gas extraction and
production activities are to be
treated as Non mining Activity
Streamlining issues under purview of FC Act, 1980
related to Forest In line with EIA Notification, 2006,
9 Others Procedural
Clearance (FC) under Oil & Gas E&P activities need to be
Purview of FC Act, 1980 considered as non-mining
operation
MoPNG also to amend Oil Field
(Regulation and Development)
Act, 1948 and P&NG Rules, 1959
159Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
through appropriate Gazette
notification
. Long Term
Creation of land bank in
State/UTs in order to facilitate
arranging CA land for
Compensatory Afforestation
(CA) in connection with Forest
Clearance Proposal in the
States having poor forest cover
over the States with forest
density more than 75% of its
geographical area
Others Procedural
MoEF&CC may consider for
realization of NPV in lieu of CA
land for faster grant of Stage-I FC
State/UTs having poor forest cover
may create their land bank for CA
for availing the provision made
available vide MoEF&CC’s OM dtd
22.05.2019
. Long Term
Compliance to “Scheduled
Tribes and other Traditional
Forest Dwellers (Recognition of
Forest Rights) Act (FRA), 2006”
not to be stipulated while
granting FC from Central Govt
under section 2(iii) of FCA, 1980
for the purpose of granting on-
shore PML blocks by the
respective State Governments
Clause of compliance of FRA,
2006 not to be stipulated by
Others Procedural
Central Govt while granting FC
under section 2(iii) of FCA, 1980
for the purpose of grant of PML
and either MoEF&CC or MoTA to
issue a guideline to all State/Uts in
line with such exemption notified
through guideline dtd 17.01.2017
in connection with grant of MLs
under provision of MMDR Act,
1957
. Long Term
160Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
Exempt Extended Reach Drilling
(ERD) or other deviational
proposals from outside the
forest boundary for obtaining
FC under purview of section 2(ii)
of FCA, 1980
Applicability of FC for Extended
Reach Drilling (ERD) or other
deviational proposals from outside
the forest boundary need to be
exempted under provision of FCA,
1980 and the committee
constituted for the purpose after
meeting at MoEF&CC on
18.03.2020 may submit its report
at the earliest for necessary Others Procedural
implementation of the same at field
level
Though ERD/Deviational drilling
program are much costlier
compared to conventional drilling
program- Exempting its
applicability under FCA, 1980 as
well as Wildlife Clearance approval
process, would encourage the PPs
to use these technologies to avoid
use of forest land for extraction of
Oil & Gas as well as other
minerals.
. Long Term
Authorize Regional offices (RO),
MoEF&CC ( will be named as
IRO wef 01.10.2020) for
approving Mining proposal up
to 5 ha, till Oil & Gas E&P
activities are treated as Mining
project
In line with empowering REC of
Others Procedural
RO/IRO, MoEF&CC for approving
non-mining and non-hydel projects
up to 40 ha forest land, if not 40 ha,
at least may be considered for
authorizing for approving mining
proposals up to 5 ha
. Long Term
161Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
NPV @ 2 % not to be collected
during grant of PML involving
forestland, as only 2% to 3% of
the allotted land is used for Oil
& Gas E&P activities, but high
amount of NPV is realized for
un-used/ un-broken 98% to 97%
forest land
As recommended in CEC’s report
dtd 25.02.2014 in conjunction with
S’Çourt’s order dtd 08.08.2014
against IA-3627, NPV @ 2% not to
be collected during grant of FC
under section 2(iii) of FCA, 1980
for the purpose of grant of PML, as
Others Procedural
PML only gives the operator
preferential/access right over the
area, without any right over the
surface of the forest land.
For surface right over the forest
land, operator of PML block has to
obtain FC under section 2(ii) first
before start of any E&P activities in
forest lands. Hence instead of
realization of 2 % NPV during
granting PML, NPV @ 100% may
be realized while granting FC
under section 2(ii) of FCA, 1980
. Long Term
De-link Forest Clearance from on-
line EC applications submitted in
Parivesh portal of MoEF&CC Others Procedural
. Long Term
Exclusively for short term
exploratory drilling proposals-
NPV realization in lieu of land for
CA in connection with forest
clearance proposal under FCA,
1980
NPV realization in lieu of land for
Others Procedural
CA in connection with forest
clearance proposal under FCA,
1980 may be considered
exclusively for exploratory drilling
proposals
. Long Term
162Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
Organizing Quarterly/Six
monthly Review meetings of
RO/IRO, MoEF&CC & PCCF &
HoFF of the concerned
State/UTs to asses/resolve the
pending FC and Wildlife
Clearance proposals
Such Quarterly/Six monthly Others Procedural
periodic meeting may be planned
by DGH involving User Agencies,
RO/IRO, MoEF&CC and the PCCF
& HoFF of the concerned
State/UTs for early resolve of the
issues
. Long Term
Digitized geo referenced based
Forest & Wildlife maps need to
be prepared based on latest
satellite imagery for clear
demarcation of forest
boundaries with revenue land
records of the respective States
for all cases including N-Eastern
States , as otherwise
identification of Wildlife, PA and
Forest area takes long time
MoEF&CC to take initiative for
preparation of digitized geo
referenced based Forest & Wildlife
maps based on latest satellite
imagery for clear demarcation of Others Procedural
forest boundaries with revenue
land records of the respective
State/UTs
DGH to make Decision Support
System (DSS) operational in
consultation with NDR for which
they have received the mail ID and
password from the
Forest Survey of India (FSI),
Dehradun. The data on boundaries
of Forest Areas, Protected Areas,
National Parks etc. available in the
DSS system
. Long Term
163Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
Single window clearance
mechanism related to all
clearances/ approvals/
Permission/NOCs etc. under the
prevailing Environmental
regulations is very much
essential. This has to be under
control of MoPNG for revival of
upstream E&P activities in
Indian Basins, which is utmost
hurdle faced by the Operators
since after allotment of the
block by GoI
MoPNG may consider instituting a
single window clearance
mechanism under its control, who
would internally follow-up and give
final consent for the vital
approval/clearances for the blocks
since after allotment by GoI. If
internal stakeholders delay,
deemed approval mechanism to
be formulated
DGH may facilitate for grant of
Streamlining issues PEL/PML for on-shore blocks
10 related to single since after their allotment by GoI, Others Procedural
window clearances and effective date should be after
allotment of PEL/PML only
DGH may facilitate for grant of FC
under section 2(iii) if FCA, 1980
from Central Govt for the purpose
of allotment of on-shore PML
blocks by State Govt for blocks
involving forest lands and effective
date should be after allotment of
PML only for such cases
DGH may also facilitate for faster
grant of Stage-I FC for diversion
proposals under section 2(ii) of
FCA, 1980 and grant of CRZ
Clearance under purview of
Coastal Regulation Zone (CRZ)
Notification, 2011. EC is kept on
hold pending submission of Stage-
I FC as well as CRZ Clearance and
without EC, no activities can be
started in a block - Effective date
should start for such cases only
after grant of EC only
DGH may also facilitate for faster
approval from SC-NBWL for
164Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
projects executed in ESZ area
outside the boundary of Pas
. Medium Term
E&P operators face contractual
disputes related to procurement of
goods, leading to exhaustion of
time and resources in litigation
proceedings and delays in
execution of projects. Some
challenges faced w.r.t. E&P
vendors include the following:
List of items for domestic
procurement and through import
differs significantly
No uniformity in authority
empowered to issue Essentiality
Certificate: DGH for domestic
goods and ONGC for imported
goods
Movement of goods from one state
to another requires another
E&P vendors face EC/NOC from DGH, which is not Others Fiscal
several challenges issued in most cases, leading to
related to indirect non-applicability of concessional
taxation on rates
Procurement of goods ONGC is not able to avail ITC of
and services including taxes paid on inputs since the main
11
specific issue with Non- products are oil and gas that fall
Resident Taxable out of GST ambit.
Persons (NRTP), Frequent changes such as recent
leading to contractual increase of GST rate from 5% to
disputes with E&P 12% and limiting of eligible items
Operators for concession in case of import
have led vendors to request
additional taxes resulting in
increased costs and contractual
disputes
. Long Term
E&P operators face contractual
disputes related to procurement of
services leading to exhaustion of
time and resources in litigation
proceedings and delays in
Others Fiscal
execution of projects. Some
challenges faced w.r.t. E&P
service providers include the
following:
The applicability of the
concessional GST rate of 12%
165Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
involves subjectivity due to the
absence of clear definitions for
terms like exploration, mining, and
drilling under GST Law.
Services procured by contractors
often attract 18% GST, leading to
an inverted tax structure when they
supply services to ONGC at the
concessional 12% rate. In addition
to the cumbersome process of
claiming refund for the inverted
supply, it also leads to contractual
issues with the vendors.
Contractual disputes during
tendering for work area falling
within onshore as well as offshore,
with different applicable
concessional GST of 18% and
12% respectively.
. Long Term
GST-TDS applied in addition to
advance payment of estimated
GST on the contract for Non-
Resident Taxable Persons (NRTP)
12 Others Fiscal
leads to contractual disputes as
well.
. Long Term
Extraction of oil/ gas should not be
considered at par with coal, iron,
and other mining activities under
purview of MMDR Act 1957 in
respect of forest regulations
Present system require long lead
Requirement of multiple time (2 years minimum) for
statutory approvals obtaining Stage-I and Stage-II
from various agencies clearances
of Central Govt. and
13 State Govt. coupled by One body may be identified and Others Procedural
Inter-departmental authorized for reporting with
conflicts leads to respect to safety related issues
delays and cost (PESO, DGMS, OISD etc.). PESO
overruns. License: Treating drilling
operations as a temporary
operation, the requirement may be
specifically described Covering the
drilling operations as a whole.
Issue PEL/PML through a single
point arrangement at the time of
166Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
signing of RSC. In other words,
One-Point Lease Allotment should
be arranged to save considerable
time
Establishing a central coordinating
body or office to manage and
oversee the regulatory process
. Long Term
Establishing clear, standardized
timelines for each type of statutory
clearance
Setting deadlines for approvals
and responses
Periodically reviewing and
Unnecessary
updating regulatory procedures
prolonged processes
14 and requirements can ensure that Others Procedural
resulting in lower
they remain relevant and effective.
efficiency
This includes eliminating
redundant processes and
incorporating feedback from
stakeholders.
. Medium Term
Onland OALP Blocks (NER) - 5
years: 3 years existing IEP + 2
Years special dispensation for
OALP Blocks in NER may be given
in line with “Policy Framework for
Streamlining the Working of PSC
in respect of Pre-NELP & NELP
Current Initial blocks in NER which allowed
Exploration Period (IEP) additional extension of
for onshore & offshore exploration/appraisal period in all
OALP blocks with Pre-NELP and NELP Blocks in
15 OALP Procedural
seismic and drilling NER, upon request by the
program is too short contractors.
and challenging for
E&P operators Onland Blocks with surface relief
above 150 m. asl (NER) - 7 years:
3 years existing IEP + 2 years in
line with Pre-NELP & NELP NER
policy + 2 years special
dispensation
. Medium Term
167Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
For category II & III
Similar wind-fall gain may also be
basins, the wind-fall
considered in case of Remote,
gain is used to
High altitude, Deepwater, and
16 determine the revenue Others Others
HPHT areas in Category-I basins
share to the
Government based on 4
.
revenue brackets.
Long Term
Liquidated Damages (LD) for
High Liquidated
OALP blocks be in line with the
Damages (LD) for OALP
revised LD provided for DSF-III
17 blocks discourages RSC Others
Round onwards
exploration activities by
E&P operators
.
Long Term
Clause 4 of Policy Framework
related to ER pilot may be
modified
Pilot timeline may be reviewed
depending upon technical
considerations as well as
operational/ environmental issues
Reservoir Pressure must be
Others Procedural
jacked up to MMP level (for mature
reservoirs), which may require
some time in case of CO2 EOR
Risk Mitigation required in case of
CO2 EOR projects since
technology is fairly new.
. Short Term
Modification in EOR
18 Policy 2018 to boost
EOR activities
Clause 6.1 of Policy Framework
related Eligibility for Availing
Fiscal Incentives may be
modified
Benchmark recovery factors of
45% for oil & 70% for gas may be
considered to make the ER Policy
more appealing
Others
Recovery factor is field/reservoir
specific
Benchmark RF of 60% and 80% is
Others
too optimistic in the Indian context
Global Average Recovery Factor is
35%.
. Long Term
168Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
Point B1 of Annexure-IV of
Policy Framework related to
Approval of Unconventional
Hydrocarbon projects/IR
Projects may be modified
UHC Projects from past
discoveries may also be made
eligible for incentives since Others Others
Huge investments required for
development of such projects
proactively.
CSS and Tight Sand Production
may be approved as UHC projects,
, Long Term
Guidelines for Assessment of
CAPEX consideration in Policy
Framework may be modified
CAPEX towards existing
infrastructure to be considered for
upper ceiling
Many investments have already
been made proactively for surface/
subsurface facility buildup.
As additional production from
existing wells is considered,
CAPEX of existing wells may also
be considered for upper ceiling.
OPEX should also be considered.
Others Others
Additionally, Instead of
considering only designated wells,
the field’s total incremental
production over the Base Case
should be considered.
EOR is a complex process, and it
is difficult to identify the beneficiary
wells considering the subsurface
uncertainties
Assessment of EOR performance
is evaluated at reservoir level
rather than well level.
. Long Term
Early implementation of inclusion
of CBM under EOR Policy as
recommended by ER Committee
CBM Others
in 2023.
169Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
It will allow companies upto 75%
waiver of royalty.
. Long Term
Small quantity of associated low
pressure natural gas is produced
along with oil in small, isolated
fields. Such gas is flared/vented at
many small field sites due to low
Small quantity of gas
quantity. As this gas is untreated
from isolated small
19 and at low pressure can be sold to Others Others
fields should be out of
nearby small industries only.
e-auction
Proposes to keep such gas out of
e-auction and be allowed to sale
on arm’s length basis.
. Long Term
Price for calculation of Stamp
Duty, to execute PML deed, shall
not be considered on
likely/anticipated payment. It shall
be calculated from the fixed rent
reserved for the respective PML
Land Acquisition
Surface rent for the land, actually
Acquiring land can
used for mining operation shall be
involve complex
payable on the notified class and
negotiations and
area of the acquired land
processes, particularly
Officials like Tehsildar/patawaris to
if the land is privately
be sensitized/advised to expedite
owned or if it involves
20 all pending, current, and upcoming Others Others
resettlement of affected
proposals of OIL. They may be
communities
directed to sensitize local
The DLC rates paid to
population and facilitate OIL in
landowners is
addressing local problems
inadequate in
Govt dept may explore the
comparison to Solar
possibility to enhance the DLC
companies.
rates which will likely to encourage
the private landowners to provide
their land for operational activities
of OIL.
. Medium Term
170Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
No GTE shall be invited up to Rs.
200 Crores. for procurements
including Goods, Non-consulting
services, Consultancy Services
and Works including turnkey
projects.
General relaxation has been
granted till 31.12.2025 by DoE
w.r.t certain items/services, critical
for operations, to float GTE subject
to prior approval from Secretary,
MoPNG. For procurement of the
items not covered under the
Issues with Global exemption list furnished by DoE,
21 Others Others
Tender Enquiry such requests for exemption are
put up for approval by Cabinet
Secretariat
GTE exemption is applicable for
procurement of goods on
Nomination/Proprietary basis.
However, there is no clarity on
whether the GTE exemption is
applicable to procurement of
services awarded on Nomination
basis as well as on Proprietary
basis.
. Long Term
As per directives, no GTE shall be
invited up to Rs. 200 Crores. for
tenders related to procurement of
some listed iron and steel
products. Any request for
exemption shall be submitted to
the Secretary, Ministry of Steel
along with sufficient proof
Expeditious approval is requested
for the pending applications.
Kind intervention is sought towards
Issues with Steel approval for granting one-time
22 Others Others
procurement exemption from the provisions of
DMI&SP Policy for procurement of
the critical items through GTE, as
a stop gap arrangement.
Capacity building of the indigenous
manufacturers who are constantly
defaulting in delivery schedules.
Possibility to be explored to enter
into a Corporate MoU between OIL
& ONGC for cluster procurement
of common items or services in
order to mitigate such stalemate in
future.
171Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
DPIIT registration process for
vendors who falls under the Border
Sharing clause may be eased, for
smooth & expeditious entry for
them, which will in turn broaden
the vendor base.
. Long Term
All clarifications with respect to
PSC/RSC interpretation and other
contractual issues/ decisions in
PSC/ RSC and extant GoI policies
to be provided within 60 days of its
receipt. In any event, Petroleum
Operations to not be hindered due
Interpretation of PSC/
to pending clarifications.
RSC and other
23 Further, in case of any ambiguity in PSC/RSC Procedural
contractual issues/
contract interpretations, the
decisions
Operator to be allowed to submit
external legal opinions to assist in
its resolution issues. (e.g., Royalty
Calculation, Adjustment of NCCD/
BED) .
. Short Term
Differentiate between Green Field
and Brown Field projects with
respect to approval timelines
(including post facto approvals). It
may be granted within 90 days for
Green Field and within 30 days for
Brown Field or else considered
deemed approved.
CAPEX approval
24 PSC Procedural
timelines in PSC blocks A third-party validation report
should suffice for the Brown Field
project instead of a detailed review
of the RFDP proposals by DGH.
Deemed approval to be formalized
after expiry of 30/90 days through
a written communication by the
operator.
. Short Term
Fast-track development
Self-certification for FDP/RFDP Self-
25 of Contingent PSC
proposals for operator in PSC Certification
Resources
Blocks, from pre to post facto
172Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
approval. To be made applicable
for both OC and MC approvals
. Medium Term
GoI to honor the contractual
provisions with respect to fiscal
stability in contracts. Introduction
of SAED, GST on Royalty (if
applicable) and Customs Duty on
Heavy burden of taxes imports (PSC blocks did not
with implementation of envisage levy of import duties), to
26 Special Additional be allowed to adjust from GoI PSC Fiscal
Excise Duty (SAED) share of Profit Petroleum as
/Wind falls tax envisaged in the fiscal stability
provisions of the contracts, have a
negative impact on oil and gas
companies.
. Long Term
For PSC blocks, 10% BG should
not be applicable for Production
Budget under the PSC Extension
27 BG in PSC Blocks PSC Financial
Policy.
. Long Term
Revenue sharing for crude oil and
gas under RSC should be based
on actual discovered price through
competitive bidding process as per
RSC provisions. It should not be
linked to the Indian Crude Oil
Basket and GOI administered
price mechanism for Gas.
Oil and Gas sale price
mechanism is not
Removal of multiple discounted
28 based on actual RSC Financial
gas price applicable to North-East
discovered price as per
state shall support in better price
RSC provisions
realisation in that region. At
present 40% discount is applicable
to North-East buyers on the GoI
administered prices as well as the
ceiling on gas prices for
ONGC/OIL
. Long Term
173Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
DGH/MOPNG are requested to not
Crude Oil Marketing insist on bringing specific
policy (issued on guidelines as it can lead to
1.10.22) does not negative impact on crude oil
29 Others Financial
envisage any specific pricing due to limited refining
guidelines with respect companies in India.
to e-bidding.
. Long Term
PSC/RSC should be extended to
its economic life to ensure long-
term investment planning.
PSC/RSC extensions should not
be linked to open issues in audit
PSC/RSC
30 objection and such unresolved PSC/RSC Procedural
extension/renewals
contractual issues should be dealt
separately without hindering
Petroleum Operations.
. Short Term
GoI may consider additional time
for fulfillment of committed work
program beyond 341 days granted
for Covid Phase 1. The Covid
Phase 2 had a cascading effect on
the oil and gas industry leading to
OALP Time Extension
scarcity in resources to undertake
31 for Initial Exploration RSC Procedural
the Exploration program. Also,
Period
Global benchmarking suggests 7-
10 years of Exploration timeline as
against 3-4 years provided in
OALP blocks.
. Medium Term
The demarcation of offshore/
onshore portion should have clarity
on the respective block. It may be
Block
resolved with state Government
Offshore/Onshore
32 prior to award of block by DGH to Others Others
Demarcation in line with
avoid hardship by operators &
State Government
delay in getting PEL/PML.
. Long Term
Revenue sharing holiday (2-year
Revenue Sharing holiday in earlier OALP rounds)
33 RSC Others
mechanism should be for each field in a block
instead of the production from the
first field on the block as it
174Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
discourages early production at
field level.
.
Long Term
FTG acquisition and Seismic data
purchased from DGH should be
allowed for set-off against CWP for
earlier OALP rounds as allowed
from OALP round VIII. CWP may
Fulfillment of be allowed to be transferred into
Committed Work more lucrative blocks from the
34 RSC Procedural
Program (CWP) in lesser ones. Further, shortfall in
OALP blocks well depth due to geological
reason should not attract
Liquidated Damages (LD) for non-
fulfillment of CWP
, Medium Term
SPOC shall be appointed by
MoPNG to resolve issues with
State Governments for the
following:
• Receipt of
EC/FC/WLC/CRZC/NOC and
Intensifying DAB issues in NE
35 Exploration activities Grant/Renewal of PEL/PML in Others Procedural
accordance with the contract
period
• Permissions for usage of
explosives from SP/DCP
Land access for Petroleum
Operations
Long Term
.
The MC to meet frequently in
accordance with PSC/RSC
contract provisions (including post
facto approvals). All MC minutes
should to be finalized and signed
at the end of each meeting instead
Conducting MC
36 of time lapse which stretches for PSC/RSC Others
Meetings
many months at present. In the
case of virtual/online meetings, the
MC minutes to be signed within the
next 10 days or considered
deemed approved. In case
meetings are cancelled, the same
should be rescheduled within 48
175Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
hours or approved through
circulation.
.
Short Term
Some cases in MOPNG are
pending for long, there must be
proper monitoring for such cases
for time bound clearances. The
Pending Cases in
37 timelines may be fixed for all Others Procedural
MOPNG
clearances required from the
DGH/Government authorities.
. Short Term
Prior to the start of the financial
year, the DGH should clear the
Work Programme and Budget.
This would allow operators
sufficient time to execute planned
Budget not cleared at
activities. Currently, operators All
38 the start of financial Procedural
submit budget proposals in Regimes
year
December, but DGH approval is
delayed until April. Streamlining
this process would be beneficial.
. Short Term
EC procedure may further be
streamlined such that EC are
available for activities done in the
RSC for which the cost budget is
not submitted for approval to the
Management committee.
Essentiality Certificate
39 Presently, in these blocks EC is RSC Procedural
(EC)
given only if the activity is a part of
FDP or committed work program
thus disincentivizing the operator
to do any extra work.
. Short Term
Lack of cost database for facilities
and absence of self-certification
process for operator proposals
No self-certification
leads to further delays at DGH Self-
40 mechanism for Others
JWG can design a self-certification Certification
operator’s proposals.
program for operators to facilitate
early clearance of operators’
proposals by DGH. It will help in
early development of the field. It
176Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
can also look at creating a
common databank.
. Medium Term
Vide gazette notification dated
11.7.2022, the sale of crude is
deregulated in domestic market
and marketing freedom for crude
oil is provided in domestic market.
Pursuant to this deregulation,
Payment of Royalty and royalty, cess, other statutory
Profit Petroleum on levies, and contractual payments
41 actual realized prices such as profit petroleum, revenue PSC Financial
instead of Indian Basket share etc. on crude oil, shall be
price
fields PSC based on actual sale
price or Indian Basket of Crude Oil
Price, whichever is higher, w.e.f.
1.10.2022 onwards.
. Long Term
Guidelines on allowing post
wellhead cost for Royalty purposes
Post well head cost for may be issued to DGH for
42 PSC Financial
Royalty not applied compliance of the regulation.
. Medium Term
Small quantity of associated low
pressure natural gas is produced
along with oil in small, isolated
fields. Such gas is flared/vented at
many small field sites due to low
Small quantity of gas
quantity. As this gas is untreated
from isolated small
43 and at low pressure can be sold to Others Others
fields should be out of
nearby small industries only.
e-auction
Proposes to keep such gas out of
e-auction and be allowed to sale
on arm’s length basis.
. Long Term
Sharing of resources/
infrastructure/ Inventory for Field
All operators should be
Development (Offshore and
encouraged for sharing
44 Onshore) shall be beneficial for all. Others Others
of resources/
Incentives may be provided to
infrastructure/
operators who share
inventory for Field
infrastructure. This will help in
reduction of capex thereby
177Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
Development (Offshore benefitting both the operator and
and Onshore) the Government.
. Long Term
Encourage collaboration between
research institutions, universities,
and CBM companies to develop
innovative solutions.
Facilitate collaboration between
existing players and new entrants
to leverage their respective Others Others
strengths and expertise.
Promote the transfer of technology
from other countries with
established CBM industries.
. Medium Term
Collaborate: O&G Cos., Service
Partners and DGH (as Facilitator)
for knowledge sharing & risk
reduction.
Innovate: Fast track monetization
of discoveries through plug-and-
produce systems.
Synergize: Sharing of drilling Others Others
resources, infrastructure, and
tangibles for cost effective
operations.
Establish Strategic Energy
Security Fund (NIIF, NAIFF)
. Long Term
Bring Natural Gas and Oil under
GST
This will allow refund of GST paid
on Goods and Services used for
petroleum operations. Refunded
amount will support further
45 GST on Royalty exploration operations Others Fiscal
It will make companies eligible for
Input Tax Credit (ITC) for GST paid
on such Royalty as in case of
Mines.
. Long Term
178Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
The timelines are achievable with
some process re-engineering that
entails a workshop, queries and
Necessity for Timely clarifications and a pre-MC
Approvals of MC meeting within 2 months to resolve
approvals for Annual all issues before the actual MC and
46 PSC Procedural
Work Programme and AWP&B can be decided during the
Budgets (AWP&B) and MC. A similar process can be
FDP/RFDP under PSC followed for FDP/ RFDP approvals
also.
. Short Term
Automatic renewal and extension
of license for a fixed period where
activity has commenced, and
delays are attributable to CBM Procedural
excusable /uncontrollable items
. Medium Term
A uniform model for Stamp Duty
computation for execution of PML
deeds can be issued to states.
While Petroleum and Gas mining
is a Union subject, the PML deed
execution is a State's regulatory
and compliance subject. Given this
is a Union subject, States should
CBM Procedural
not unilaterally impose conditions
CBM Blocks Procedural
47 on registration and content of such
Delays
deeds. A uniform model for Stamp
Duty computation for execution of
PML deeds can be issued to
states.
. Long Term
The approval of AWP&B and FDP
can be fast tracked as these
Contracts are revenue sharing
contracts. The cost and scheduling
risk rests almost entirely with the
CBM Procedural
Contractor and therefore the
Steering Committee (SC) can fast
track entire approval process
. Long Term
179Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
Simplify scope of audit provision,
audited accounts, and
procurement procedures. CBM Procedural
. Long Term
The Contractual provisions survive
and Contractors and MC
obligations to follow those do not
go away by self-certification.
When additional formats (different
from PSC formats and upload
formats) are introduced as part of
approval process the process
becomes complicated as
Self-
48 Duplication of effort Contractor has to now report same PSC
Certification
information in three different
formats
JWG can look at harmonization of
these process and work on
bringing procedural efficiencies to
what is already agreed under the
contract.
. Short Term
Government should grant 3 year
moratorium so that operators can
not only fulfil their obligations but
Moratorium on All
49 also find new oil and gas Financial
Exploration Period Regimes
resources.
. Long Term
Amendment required so that
consumers pay 2% concessional
rate against C Form, until NG is
brought under GST regime
C-Form Eligibility
50 Consumers manufacturing GST Others Fiscal
against purchase of NG
products pay CST@5% since
revision on 28th March 2021.
. Long Term
Enable complete gas pricing
Gas price restriction freedom for gas produced from
acts as a distortion and Deep/ Ultra-deep water and HPHT
51 Others Financial
limits upstream areas by removal of ceiling price
realization on gas
Ceiling price on deepwater gas is
a hindrance for efficient price
180Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
discovery at the Gas exchange
Balanced risk-reward framework is
key to attract investment
This is in line with recommendation
of report by govt. appointed Kirit
Parikh Committee.
. Long Term
Gas/LNG aggregators being
pipeline owners can result in
discriminatory access/ use of the
Separate gas marketing
transportation pipeline
and gas transportation
52 Transparent/ Dynamic information Others Financial
contract till unbundling
on pipeline capacity should be
is done
available
. Long Term
In accordance with GIPIP
guidelines, exploration should be
allowed in the mining lease area
for the duration of the contract.
RSC
Exploration to be Contracts under the OALP provide
allowed in Mining Lease for right to undertake Exploration
53 Area, post expiry of for the duration of the Contract, PSC Others
Exploration Period even after the completion of the
under the PSC Exploration Phase /Period.
Similar rights should be granted to
the Contractor under the PSC in
NELP.
. Medium Term
Contracts explicitly specify
approvals required from the MC for
the conduct of Petroleum
Operations. All parties to the
Compliance with Contract are obligated to comply Self-
54 PSC
Contracts with these provisions and therefore Certification
self-certification cannot substitute
the PSC requirements.
. Short Term
PSCs/RSCs tenure for end of
field(s) life.
55 Policy concerns Define ‘Reserved Matters’ PSC/RSC Others
(FDP/RFDP/PSC Annual Budget)
for specific approvals.
Approval of all ‘Non-Reserved
181Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
Matters’ under the PSCs/RSCs on
a self-certification basis.
. Medium Term
Simplify & streamline the process
for physical data transfer to ensure
faster turn-around times. Allow
Fast Track process of
56 using new age technology Others Others
data transfer
solutions (Cloud technology).
. Long Term
Procedures to have single window
clearance, long term clearance of
employees, contractors from
Simplify MoHA MoHA and faster clearance from
57 Others Procedural
clearances MoF is critical for fast growth of the
sector.
. Long Term
Management Committee (MC)
approval may be treated as Govt
approval since Government
(MoPNG) is part of MC. In many
Simplify Approval All
58 cases, MC recommends to Govt Procedural
Procedure regimes
for approval (e.g., Delivery Point),
which takes additional time.
. Short Term
Management Committee should
be empowered to approve delivery
Evacuation of Oil and
points beyond the block boundary
Gas outside the All
59 and allow cost recovery of both Procedural
boundary limit of the regimes
opex and capex.
block not allowed
. Short Term
Deputation of DGH DGH may depute Co-ordinators
executives from and Nodal Officers from Contract/
60 contractual/ Commercial background Others Others
commercial
background
DGH executives are mostly from
technical background, however job
requirement for PSC/RSC are
182Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
more of contractual/ commercial in
nature.
. Medium Term
A clause for Excusable Delay
should be incorporated in RSC and
provisions of Extra Days should be
Clause for Excusable
included for extension of the
Delay & Provisions of
Development Period in order to
Extra Days to be
61 compensate for the delay on RSC Procedural
included for extension
account of Government
of the Development
clearances such as EC, FC, CTO,
Period
CTE etc. in DSF III.
. Short Term
DGH may expedite proposal
clearances by including expert
Delays in clearing third-party consultants on their
62 Others Procedural
proposals panel for faster clearances.
. Medium Term
SOPs need to be redrawn, and
timelines should be fixed for
Participating Interest Transfer
Participating Interest All
63 procedures will Increase Investor Procedural
Transfer Procedures regimes
confidence.
. Short Term
To develop a SOP for handover of
fields from previous operators for
smooth handover and faster
64 Field Handover SOPs RSC Procedural
operationalization of Fields.
, Short Term
Incentive should be revisited, and
approval delays should be
checked
Early production Owing to delays beyond
65 RSC Financial
Incentive in RSCs contractor’s control, this incentive
will not kick in at all
. Long Term
183Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
Multiple gas prices are Subsidies need to be extended to
in play in North-East private players and given a level
All
66 with ONGC/ OIL having playing field. Financial
Regimes
advantage of
discounted gas prices .
Long Term
Contractor should be allowed to
Fair price is dependent sell both Oil and Gas below price
on quality, supply- declared by PPAC and accordingly
demand dynamics in to be allowed to calculate (1) Govt
67 PSC Financial
the region and share of Revenue & (2) Royalty &
availability of alternate Cess.
cheaper energy source
. Long Term
Royalty may attract GST post
Hon’ble Supreme Court Order
dated July 25, 2024.
Inclusion of crude oil and natural
gas under GST critical to allow
cross utilization of input tax credit. RSC Fiscal
Being a double dip, Windfall Tax
(SAED) not to be applicable on
crude oil production under RSCs.
. Long Term
Some major litigation and
contractual disputes arising out of
the changing policy landscape
Heavy burden of taxes
challenges in E&P sector are:
with implementation of
Disputes with vendors
68 Special Additional
Contractual dispute with vendors
Excise Duty (SAED)
which results into delay in project
/Wind falls tax
execution with
Hybrid system of taxation.
E&P Operators are not able to
avail ITC of GST paid on inputs.
This results in huge stranding of Others Fiscal
taxes
Heavy burden of taxes
With introduction of SAED on
production of crude oil, the
investible surplus of E&P sector
has shrunk.
Disputes under PSC with
Uncertainty regarding the
allocation of GST/ST attributable
to the share of Royalty for specific
partners i.e. whether it should be
borne by them individually or solely
184Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
by the Licensee.
Issue of ST/GST on Royalty
This issue is under litigation before
all the judicial forums resulting into
substantial time and money
involved in litigation.
. Long Term
Maintenance of Fiscal Stability and
consistent interpretation of
PSC/RSC contract terms, prompt
clarification of confusion to attract
long term capital
Increased fiscal burden in form of
SAED, Cess etc.
Persistent interpretations on items
such as Wellhead Royalty, Cost
Recovery disallowances and
restrictions of marketing and PSC/RSC Procedural
pricing freedom that are not
consistent to PSC/RSC intent
RSC of DSF III have clear
definitions of MWP & contract
area. DGH/MoPNG is requested to
implement them in to-to, without
linking it to a general
understanding.
. Long Term
Extensions of PSCs on original
contracted profit split (instead of a
10% top-up).
No BGs for PSCs during
69 Fiscal instability Production Phase. PSC Financial
Restoration of ‘nil’ Custom Duty as
stipulated under the PSCs
. Long Term
‘Government Take’ to be based on
Actual Price Realization of Crude
Oil (& not on Indian Crude Basket
Price).
70 Pricing structure Others Financial
Uniform & Equitable Gas Pricing
Structure to usher in Gas based
economy (Ceiling Price vs. Crude
185Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
Price Indexed3 vs GoG
Competition Price).
. Long Term
Operator to be allowed to adhere
to its contracting process for third
party contract awards. Further,
non-operator should contribute to
their share of costs or else,
Operating freedom in
operator should have the first right
71 Public Private Others Others
to the revenue to recover unpaid
Partnership
contract costs. To safeguard the
interest of the non-operators, audit
rights are in place.
. Medium Term
Clearances should be granted in
less than a year, considering the
shorter timelines to bring blocks
into commercial production - as
early within 4 yrs.
Facilitate easier access to land for
Land Acquisition and
CBM exploration and production
72 Clearances CBM Procedural
activities by streamlining the land
(CBM)
acquisition process and providing
clear guidelines for obtaining
necessary clearances from local
authorities and communities.
. Long Term
Financial incentives shall be
provided to existing players
considering their past investments
Revisit of Fiscal Terms
73 and contributions to the CBM CBM Financial
under HELP Regime
sector under HELP
. Long Term
Currently, the Indian CBM Royalty
(10%) is based on sales volume of
CBM gas (ad valorem)
Hence, instead of a flat Royalty of
10%, a production linked & time
74 Staggered Royalty CBM Financial
staggered Royalty may be best
suited.
Zero royalty up to 1.0 MMSCMD,
rebate in royalty as proposed in
draft ER committee (2023) for
volumes more than 1.0 mmscmd
186Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
would bring more quality
participation CBM exploration and
development.
. Long Term
Fiduciary nature of corporate
guarantees suggests they should
not be treated as taxable services
Levying GST on CG needs
reconsideration as this could deter
GST Levy on Corporate financial support mechanisms
75 Others Financial
Guarantee crucial for the growth and stability
of related entities in such capital-
intensive sector falling outside the
GST ambit
. Long Term
Guidance Note (GN) requires E&P
entities to use Proved developed
reserves (1P) for arriving at Unit of
Production (UOP) rate. Flexibility
should be provided to Industry
players to use either Proved
developed reserves (1P reserves)
or Proved and Probable reserves
(2P reserves) as a basis for
deriving UOP rate based on
management estimates of future
Depletion on 2P
economic benefit from the field.
76 reserves instead of 1P Others Financial
It is a deviation from International
reserves
Financial Reporting Standards
(IFRS) practice which allows
entities to use either proved
developed or proved undeveloped
reserves based on the
management perception of best
scenario to depreciate oil and gas
reserves over the economic life of
assets.
. Long Term
Till the time Oil and Gas is not
brought under GST regime,
77 VAT Refund concept of VAT refund may be Others Fiscal
explored which is currently being
levied on Natural Gas.
In China, there is a VAT refund of
187Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
~ 7% and also state subsidy of 7%
for CBM.
. Long Term
Restoration of 100% Tax Holiday
u/s 80IB (9) is proposed to
undertakings engaged in
exploration and production of
natural gas, where commercial
production has been started after
31st March 2017, with enhanced
limit of at least 15 years as has
been provided for other
Extension of Tax
infrastructure sectors like power
78 Holiday under Income Others Fiscal
generation. Similar to the tax
Tax Act’ 1961
holiday given to contractors for
production of natural gas in blocks
licensed under IV round of bidding
for award of exploration contracts
of CBM blocks for a period of
seven consecutive assessment
years
. Long Term
The recent award of CGD by
PNGRB for quantities below
50,000 SCMD conflicts with areas
where CBM operators are
licensed.
This goes against the CBM policy
in Article 18.1 of the CBM contract,
which allows operators to sell CBM
gas at Arm's Length Price in the
domestic market, subject to
Government policy.
In line with CBM contractual
Without Area and provisions and CBM Policy 1997,
79 CBM Financial
Quantum Restrictions MoPNG and PNGRB should allow
gas marketing rights to CBM
operators both in terms of ‘’PNG’’
and ‘’CNG’’, without any inherent
area or volume restrictions.
This long-term co-existence of
both the CBM and CGD license
holders without any legal
complications could be done by
means of “grandfather” the CBM
policy/contractual clauses into the
current CGD License
Policy/contract.
The Draft PNGRB Rules, 2021
188Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
(Section 3.4) solicit, recognizing
and including a separate ‘’E&P
Entity pipeline’’ and will allow E&P
entity(s), to undertake on crucial
production enhancement activities
under MoPNG E&P Vision
. Long Term
Profit petroleum or PLP (for PSC
and CBM contract respectively)
shall be completely removed from
the policy to incentivize operators
to discover and produce
unconventional hydrocarbons and
financially support for shale gas
exploration activities
Rationale: The profit
Reforms in the vital
petroleum/PLP quoted for
August 2018 Policy for
Conventional Oil blocks is not
80 simultaneous PSC/CBM Others
comparable for Natural Gas
Unconventional
Development as the energy
Hydrocarbon
equivalent realizations is much
less for Gas than crude oil.
In other countries like USA,
Australia and China, several
grants, incentives and financial
support has been extended for
unconventional hydrocarbons.
. Long Term
Relaxations in terms of
procurement policy, sale of
inventory/asset, etc. should be
provided for Old PSCs as given
Relaxation in few terms under New Model Revenue
81 PSC Others
of the old PSCs Sharing Contract (MRSC) for
Special CBM Bid Round 2022
under OALP.
. Long Term
Foreign Service Providers & OEM
mostly dominate the technological
landscape which leads to high
Self-Reliant of
project cost.
82 Domestic Technology Others Others
Technology transfer is required but
to Optimize Cost
Foreign Service Providers & OEM
are reluctant to do so owing to IPR
(Intellectual Property Rights)
issues
189Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
S.
Issues Submission by JWG Members Regime Category
No.
GoI needs to create platform
where Industries should be invited
to develop In-house expertise
(manufacturing & services)
requiring support to the Oil & Gas
industries.
GoI may facilitate some
collaboration with these Foreign
Service Providers & OEM to
develop such In-house expertise
. Long Term
Govt. should launch extensive and
detailed programme in all these
basins, carryout pilot projects and
fund (like UNDP) these projects for
Strengthening Data
entire assessment of these
Generation
unexplored area prior to bidding.
Requirement of proper
NDR should also include huge
83 evaluation to Others Others
data related to coal mines (core
understand the
hole data, gas content etc.)
potential of CBM and
generated since long in order to
Shale Gas development
evaluate CBM\Shale gas potential
& future opportunities.
.
Short Term
190Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
6.5. Annexure V: Exchange Rate Analysis
The comparative analysis between FBIL and SBI exchange rate is mentioned below
FBIL Reference Rate SBI Reference Rate (INR/USD)
Time Period
(INR/USD) Sell Buy Average
2020 74.065 74.296 73.446 73.871
2021 73.924 74.389 73.536 73.962
2022 78.653 79.179 78.326 78.753
2023 82.600 83.034 82.184 82.609
2024* 83.388 83.843 82.993 83.418
*until 17/09/24
Source – FBIL and Internal Analysis
191Report of the Joint Working Group (JWG) on Issues related to EoDB in Indian Upstream Sector
192