Date: 2026-01-30Category: Not ApplicableState: Union GovernmentCountry: India
Revised guidelines for Coal and Lignite based Thermal Power Plants (TPPs) to utilize ash as stipulated in the MoEF&CC Notification dated 31.12.2021 and its subsequent amendments dated 30.12.2022 and 01.01.2024
**Executive Summary**
The Ministry of Power (MoP) issued revised guidelines on March 15, 2024, concerning the disposal of ash by coal and lignite-based Thermal Power Plants (TPPs). These guidelines, effective from January 30, 2026, aim to enforce 100% utilization of ash and reduce the tariff burden on electricity consumers, in line with MoEF&CC Notification dated December 31, 2021, and its subsequent amendments. The Central Electricity Authority (CEA) shall monitor the implementation of these guidelines.
**Key Points / Main Content**
* **General Ash Disposal Procedure:**
* TPPs must declare the issuable ash quantity (fly ash, bottom ash, and pond ash) per annum, excluding ash committed for existing tie-ups and other commitments, subject to technical restrictions.
* TPPs shall provide ash to agencies for eco-friendly purposes as per the MoEF&CC Notification through a transparent mechanism.
* TPPs can explore tie-ups with bulk consumers and facilitate ash export, encouraging capacity planning and utilization.
* TPPs should prioritize low-carbon transportation options for ash.
* **Fly Ash Supply to Micro and Small Enterprises (MSEs) and Local Users:**
* TPPs must reserve a percentage of fly ash for MSEs and local users at concessional rates, in accordance with Clause D (4) of the MoEF&CC Notification dated 01.01.2024.
* The quantity and concessional rate will be determined by a plant-level committee.
* Allocation of reserved fly ash will be through an Expression of Interest (EoI) process.
* TPPs will issue reserved fly ash quantities in a fair, transparent, and non-discriminatory manner.
* **Disposal at Non-Pit Head and Pit Head TPPs:**
* Sale of ash should be through a transparent mechanism, preferably "Open Auction" with a predefined floor price.
* If ash remains unutilized, it should be offered free of cost via EoI, with the user bearing transportation costs.
* If ash is still unutilized, TPPs must notify potential users within 300 km, with a copy to the State Pollution Control Board.
* **Disposal of Untied Ash:**
* After following above provisions, for ash utilization beyond 300 km, TPPs' financial liability for transportation is limited to the notional cost of road transport up to 300 km.
* **Ash Transportation Procedure (Cost Borne by TPPs):**
* TPPs must prepare a panel of transportation agencies through competitive bidding.
* **Applicability of Guidelines:**
* These guidelines supersede MoP's guidelines issued on 15.03.2024 and apply prospectively to all coal/lignite-based TPPs.
* TPPs should honour existing ash contractual obligations until expiry.
* Remaining ash quantity and new commitments should be disposed of through the transparent process outlined.
**Impact Analysis**
**Stakeholder: Coal and Lignite based Thermal Power Plants (TPPs)**
*Impact:*
* Must adhere to the revised guidelines for ash disposal.
* Need to establish transparent mechanisms for ash allocation and disposal.
* Limited financial liability for ash transportation beyond 300 km.
*Action Required:*
* Implement the procedures outlined in the guidelines for ash disposal.
* Declare issuable ash quantity.
* Establish committees and conduct EoI processes.
* Prepare a panel of transportation agencies.
**Stakeholder: Micro and Small Enterprises (MSEs) and Local Users**
*Impact:*
* Opportunity to access fly ash at concessional rates.
* Potential for increased utilization of ash in eco-friendly products.
*Action Required:*
* Participate in EoI processes for fly ash allocation.
* Comply with self-declaration requirements for local users.
**Stakeholder: Central Electricity Authority (CEA)**
*Impact:*
* Responsible for monitoring the implementation of the guidelines.
*Action Required:*
* Monitor TPPs' compliance with the revised ash disposal procedures.
**Stakeholder: Ministry of Environment, Forest & Climate Change (MoEF&CC)**
*Impact:*
* The guidelines align with the MoEF&CC Notification and its subsequent amendments.
*Action Required:*
* Continue to provide guidance and support for the implementation of the notification.
Key Entities Referenced
MoEF&CC Notification dated 31.12.2021: Notification by the Ministry of Environment, Forest & Climate Change regarding utilization of ash from Thermal Power Plants, which forms the basis for the revised guidelines.
Ministry of Power (MoP): The primary issuer of the revised guidelines concerning the disposal and utilization of ash from coal and lignite-based Thermal Power Plants.
Thermal Power Plants (TPPs): Coal and Lignite based power plants that are the subject of this policy regarding ash utilization.
Central Electricity Authority (CEA): The entity responsible for monitoring the implementation of the ash utilization guidelines by Thermal Power Plants.
New Delhi: Location of the Ministry of Power headquarters and the origin of the notification
No. 9/8/2024-St. Th.
Government of India
Ministry of Power
KK KKK
Shram Shakti Bhawan, Rafi Marg
New Delhi, 30 January, 2026
To:
i. CMDs/MDs of coal/lignite based Thermal Power Plants (Central /
State / Private);
ii. Principal Secretary/Additional Chief Secretary (Power/ Energy) of all
States/UTs;
iii. Chairperson, Central Electricity Authority
Subject: Revised guidelines for Coal and Lignite based Thermal
Power Plants (TPPs) to utilize ash as stipulated in the
MoEF&CC Notification dated 31.12.2021 and_ its
subsequent amendments dated 30.12.2022 and
01.01.2024 — reg.
Madam /Sir,
The Ministry of Power (MoP) has issued guidelines dated
15.03.2024, in line with the Ministry of Environment Forest and Climate
Change (MoEF&CC) Notification dated 31.12.2021 and its amendments
dated 30.12.2022 and 01.01.2024, for disposal of ash by coal and Lignite
Thermal Power Plants with primary objective of the Government to
enforce 100% utilization of ash with least burden on the electricity
consumers.
2. Several representations have been received from various
stakeholders including Micro and Small Enterprises (MSEs), Cement
Industries and TPPs to revise the MoP Guidelines dated 15.03.2024.
Based on the representations received and in accordance with the
aforesaid MoEF&CC Notification, the draft revised Guidelines were
circulated by Ministry of Power for Stakeholders consultation. The
comments/suggestions received from several stakeholders were duly
examined, and necessary modifications have been incorporated to ensure
that the guidelines remain comprehensive, implementable and aligned
with the objectives of the MoEF&CC Notification.
3. Accordingly, the revised Guidelines are enclosed at Annexure for
all the coal and lignite based Thermal Power Plants (Central / State /°
Private sector) for the disposal of ‘Current and Legacy Ash’ with the
primary objective of meeting the ash utilization targets as per the said
cMoonEsFu&mCerCs .N otification and also, reduce the tariff burde-n o_n the electricity
30° ol por-64. All concerned are directed to take necessary action accordingly.
Central Electricity Authority (CEA) shall monitor the implementation of
these guidelines.
5. This issues with the approval of Hon’ble Minister of Power and
Housing & Urban Affairs.
Encl: As above (06 pages)
026
(Satish amar)
Director (Thermal)
Tel: 011-23738817
Copy to:
ij. Secretary, Ministry of Environment, Forest & Climate Change;
ii. Secretary, Ministry of Coal;
iii. Secretary, Ministry of Road Transport and Highways;
iv. Secretary, Ministry of Housing and Urban Affairs;
v. Secretary, Ministry of Micro, Small and Medium Enterprises;
vi. Secretary, Ministry of Mines;
vii. Chairman, Central Pollution Control Board;
viii. Chairman, State Pollution Control Boards/PCCs;
ix. Chairman, National Highways Authority of India;
xX. All Chief Secretaries of States/ Union Territories;
xi. Secretary, CERC;
xii. Secretaries of all SERCs/JERCs.
xiii. NIC Cell, Ministry of Power, for updating on website.Government of India
Ministry of Power
KKKKK
“Revised Guidelines
for
Coal and Lignite based Thermal Power Plants
(TPPs) to utilise ash as stipulated in the MoEF&CC
Notification dated 31.12.2021 and its subsequent
Amendments dated 30.12.2022 and 01.01.2024”
January, 2026
30-0
Page 1 of 6TABLE OF CONTENTS
“MoP’s Revised Guidelines for coal and lignite based Thermal
Power Plants (TPPs) to utilize ash as stipulated in the MoEF&CC
Notification dated 31.12.2021 and its subsequent amendments
dated 30.12.2022 and 01.01.2024”
Para Topics Page No.
1 |Procedure for disposal of ash by TPPs 3-5
1.A |General Procedure for disposal of ash 3
1.B [Procedure for Fly ash supply to Micro and Small 4
Enterprises and Local MSEs/Local users engaged in
ash-based products manufacturing
1.C |Procedure for Disposal of ash at Non-Pit Head and Pit 5
Head TPPs
1.D |Disposal of untied ash (Fly ash, Bottom ash & Pond 5
ash) by Thermal Power Plants
2 |Applicability of Guidelines 6
aes
Page re 6“MoP’s Revised Guidelines for coal and lignite based Thermal
Power Plants (TPPs) to utilize ash as stipulated in the MoEF&CC
Notification dated 31.12.2021 and its subsequent amendments
dated 30.12.2022 and 01.01.2024”
All the coal and lignite based Thermal Power Plants (Central / State/
Private sector) shall follow the procedure given below for disposal of
‘Current and Legacy Ash’.
1.
Procedure for disposal of Ash by TPPs:
General Procedure for disposal of ash:
Issuable ash (Fly ash, Bottom ash & Pond ash separately) per
(i)
annum means quantity of ash available for issue by the Thermal
Power Plants (TPPs) in a year after excluding ash for existing tie-ups
and other commitments subject to technical restrictions, dyke
safety and current / future ash generation. This quantity shall be
declared by TPPs prior to start of the ash disposal process.
TPPs shall provide ash to agencies for eco-friendly purposes as
(ii)
stipulated in the MoEF&CC Notification dated 31.12.2021 as
amended on 30.12.2022 and 01.01.2024 through a transparent
mechanism to achieve the compliance cycle target of ash utilization.
TPPs may explore tie-ups for any duration particularly with the bulk
(iii)
consumers like cement manufacturers, fly ash-based product
manufacturers etc. and for the export of ash through a suitable
transparent mechanism to ensure sustainable ash utilization. This
will also encourage better planning of capacity additions by the bulk
consumers and export of ash and enhance opportunities for ash
utilization.
Modes for ash transportation: Besides conventional road transport,
(iv)
TPPs may also adopt other low-carbon options such as waterways,
rail, Rail-cum-Road (RCR), or Roll-on / Roll-off (RORO), pipeline
system etc. for ash transportation.
All ash transporters shall be responsible as per para-C (4) of the
(v)
MoEF&CC Notification dated 31.12.2021.
apo r0r&
Page 3 of 6Procedure for Fly Ash supply to Micro and Small Enterprises
(MSEs) and Local MSEs/Local Users engaged in ash-based
products manufacturing:
A Thermal Power Plant (TPP) shall reserve a certain percentage of
issuable quantity of fly ash separately for supply to Micro and Small
Enterprises (MSEs) and ‘Local users’ at a concessional rate, in
accordance with Clause D (4) of the MoEF&CC Notification dated
01.01.2024. The supply of fly ash shall be made on an “as is where
is” basis.
The quantum of fly ash to be reserved for MSEs / ‘Local Users’ and
the applicable concessional rate shall be determined by the
Committee constituted at the plant level, to be chaired by the Head
of the Plant (HoP). The Committee shall include members from the
Local Administration, MSEs/ Ash users’ associations, etc.
(ii) The reserved quantity of fly ash referred to in para-B.(i) above, to
be issued at concessional rates, shall be allocated through an
Expression of Interest (EoI) process. The TPP shall invite EoIs from:
(a) MSEs having either a valid ‘Consent to Operate’ (CTO) issued
by CPCB / SPCBs, wherever applicable, or a valid MSE / Udyam
registration certificate.
(b) ‘Local Users' situated within a 100 km radius of the plant, on
the basis of a self-declaration, confirming that the ash will be
utilized solely for eco-friendly purposes.
(iii) TPPs shall issue reserved fly ash quantity in a fair, transparent, and
non-discriminatory manner on a pro-rata basis, based on the EolIs
received from eligible MSEs / ‘Local Users’.
(iv) Untied fly ash quantity from the fly ash reserved for MSEs and
‘Local Users’ shall be included in the issuable fly ash quantity for
‘other user agencies’.
Zo 0'20r6
Page 4 of 6C. Procedure for Disposal of ash at Non-Pit Head and Pit Head
Thermal Power Plants (Fly Ash, Bottom Ash and Pond Ash)
among all users of Ash as per MoEF&CC Notification:
All coal and lignite based Thermal Power Plants shall undertake sale
(i)
through a transparent mechanism. The preferred approach for this
mechanism is via “Open Auction” with a predefined floor price of
“Rupee One per Metric Ton (MT)”.
(ii) If, after para-C.(i) above, some quantity of ash still remains un-
utilized, then it shall be offered free of cost by inviting the Eol for
lifting ash on “as is where is” basis and on “first come, first serve’
basis, provided the user agency is willing to bear ash transportation
cost.
(iii) If, ash remains unutilized even after compliance with the provisions
of Para 1.C.(i) and (ii) above, the TPPs shall serve notices to
agencies of identified avenues within a radius of 300 kms (Road,
Dam, Shoreline Protection, Mine, Low Lying Area etc.), with a copy
to the concerned State Pollution Control Board, for delivering ash
free of cost and bearing cost of transportation as per para D (1) of
the MoEF&CC Notification dated 31.12.2021 and its amendment
Notifications dated 30.12.2022 and 01.01.2024.
Disposal of untied ash (Fly ash, Bottom ash & Pond ash) by
Thermal Power Plants:
After compliance with the provisions of Para 1.C.(i), (ii) and
(iii) above, for any prospective ash _ utilization avenue
involving transportation beyond a distance of 300 kms,
irrespective of the actual mode of transport, the financial
liability of the Thermal Power Plant towards transportation cost shall
be limited to the notional cost equivalent to transportation by road
for a distance of up to 300 km only.
Further, disposal of balance untied ash (Fly ash, Bottom ash & Pond
ash) after exhausting above steps may be carried out as per the
best financial prudence of the Thermal Power Plants.
Procedure to be followed for Ash transportation where cost is
to be borne by TPPs:
TPPs are required to prepare a panel of transportation
agencies for a suitable period in accordance with applicable
government regulations or, organizational policies based on
Page 5 of 6competitive bidding for transportation to Road Projects / Dams /
Shoreline protection / mines etc. which may be used for the period.
Bids may be invited as per the State Schedule of Rates (SOR) (in
which the TPP is located); in case the State SOR is not available,
the Central SOR or any applicable SOR may be referred. The TPPs
shall call for bids well in advance so that the transportation panel is
in place as soon as the previous panel expires. There should be no
gap between the expiry of existing panel and the finalization of the
fresh panel.
Applicability of Guidelines:
These guidelines are in ‘supersession’ of MoP’s guidelines
issued on 15.03.2024, and shall be followed by every coal or lignite
based Thermal Power Plants (i.e. including captive or co-
generating stations or both), mentioned at para-A (1) of the
MoEF&CC Notification dated 31.12.2021. These guidelines shall
apply “prospectively”. Thermal Power Plants (TPPs) are advised to
honour their existing ash contractual obligations until their expiry.
For remaining ash quantity and new commitments, ash shall
invariably be disposed of as per the transparent process as stated
above in these guidelines.
KKK KKK
deh
a)
Pagé 6 of 6