Home India Ministry of Power Revocation of GRID Access Permissions for Renewable Energy (...
Date: 2025-12-08 Category: Press Release State: Union Government Country: India

Revocation of GRID Access Permissions for Renewable Energy (RE) Projects

Issued by Ministry of Power · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

**Executive Summary** This document announces the revocation of grid access permissions for 24 Renewable Energy (RE) projects, totaling 6343 MW, by the Central Transmission Utility of India Limited (CTUIL) due to developer delays, not transmission-related issues. This action aligns with the government's target of achieving 500 GW of non-fossil fuel-based generation capacity by 2030, with 259 GW already connected to the grid. The information was provided by the Minister of State for Power, Shri Shripad Yesso Naik. **Key Points / Main Content** * **Revocation of Grid Access Permissions:** * CTUIL has revoked connectivity for 24 Renewable Energy (RE) projects. * The total revoked RE capacity amounts to 6343 MW. * Cancellations are due to developer delays, not transmission constraints. * State-wise details of revocation are provided at Annexure. * **Reasons for Revocation:** * Failure to comply with milestones. * Annulment of Letter of Award. * Failure in submission of land documents. * Failure in achieving Commercial Operation Date (COD). * Failure in submission of Financial Closure. * **Government Goals and Actions:** * India aims to achieve 500 GW of non-fossil fuel-based generation capacity by 2030. * 259 GW of non-fossil capacity is already connected to the grid. * Inter-State Transmission System (ISTS) is under construction for 172 GW of renewable energy evacuation. * Bids are in process for an additional 19 GW capacity. * The government is collaborating with States for timely development of Intra-State Transmission Systems (152 GW). * **Pending Petitions:** * Sixteen petitions are pending before the Central Electricity Regulatory Commission (CERC). * Petitioners (Power Generators) are seeking protection from revocation of Connectivity. **Impact Analysis** **Renewable Energy Developers** * **Impact:** Developers whose grid access permissions have been revoked will need to address the reasons for delay, such as land document submission, milestone achievement, financial closure and COD, or potentially face project cancellation. * **Action Required:** These developers should review the reasons for revocation and take corrective measures, which could include submitting required documents, securing financial closure, or expediting project completion to meet COD. **Central Transmission Utility of India Limited (CTUIL)** * **Impact:** CTUIL is responsible for managing the revocation process and ensuring that the transmission infrastructure remains aligned with the government's renewable energy targets. * **Action Required:** CTUIL needs to continue monitoring project progress, enforce compliance with grid access regulations, and facilitate the timely development of transmission infrastructure. **Central Electricity Regulatory Commission (CERC)** * **Impact:** CERC is responsible for adjudicating petitions from power generators seeking protection from revocation of connectivity. * **Action Required:** CERC needs to review the pending petitions and issue rulings based on the merits of each case, considering both developer performance and potential impacts on grid stability. **Government of India (Ministry of Power)** * **Impact:** The Ministry of Power is responsible for achieving the 2030 non-fossil fuel capacity target and ensuring the timely development of transmission infrastructure. * **Action Required:** The Ministry needs to continue monitoring project progress, coordinating with States, and taking necessary actions to address any delays or bottlenecks in the implementation of renewable energy projects.

Key Entities Referenced

Renewable Energy (RE) Projects: The subject of grid access permission revocation policy. Central Transmission Utility of India Limited (CTUIL): Entity responsible for revoking connectivity for renewable energy projects. Central Electricity Regulatory Commission (CERC): Regulatory body hearing petitions related to revocation of connectivity. Inter-State Transmission System (ISTS): Infrastructure used for evacuation of renewable energy. Ministry of Power: Primary government body responsible for the policy.
Official Source Record View Original Source →
See Full Document Text
Ministry of Power Revocation of GRID Access Permissions for Renewable Energy (RE) Projects Cancellations Due to Developer Delays, Not Transmission Side Delays ISTS Under Construction for Evacuation of 172 GW of RE, bids in process for 19 GW प्रव तथ: 08 DEC 2025 5:03PM by PIB Delhi Since 2022, Central Transmission Utility of India Limited (CTUIL) has revoked connectivity of 24 grantees with a Renewable Energy (RE) capacity of 6343MW. The cancellations are on account of developer delays and not due to transmission side delays. State-wise details of revocation are provided at Annexure. There are sixteen petitions pending before the Central Electricity Regulatory Commission that pertain to cases where the Petitioners (Power Generators) have approached CERC seeking protection from revocation of Connectivity. The revocation of grid access permissions is not due to shortfall in transmission planning for achieving the 2030 non-fossil capacity target. The Government of India has set a goal of 500 GW of non-fossil fuel- based generation capacity by 2030. Already 259 GW of non-fossil capacity is connected to the grid. Further, Inter-State Transmission System (ISTS) for evacuation of 172 GW of renewable energy is already under construction, and bids are in process for 19 GW capacity. Simultaneously, the Government of India is working with the States to ensure timely development of respective Intra-State Transmission Systems for evacuation of 152 GW of renewable energy. These efforts, together with the planned transmission systems for integrating hydro, nuclear, and other non-fossil capacities, collectively provide a clear implementation plan for achieving the 500 GW non-fossil capacity target.Sl State Location Applicants Connectivity Revoked Reason for revocation No. Quantum Quantum (MW) (MW) 1. Karnataka Koppal PS, 6 1500 1500 Failure to comply Koppal-II PS, milestones/ Annulment of Gadag PS Letter of Award/Failure in submission of land Documents 2. Tamil Nadu Tuticorin-II PS 1 250 32 Failure in achieving COD* 3. Maharashtra Solapur S/s, 8 1090 1090 Failure in achieving Kallam PS, COD/ Failure in Solapur PG submission of Financial Closure 4. Gujarat Jam 6 3243 2871 Failure in submission of Khambhaliya land documents/ Failure PS, KPS1, in submission of KPS3, Bhuj PS, Financial Closure/ Failure Bhuj-II PS in achieving COD 5. Rajasthan Fatehgarh-II, 3 850 850 Failure in achieving COD Fatehgarh-III (Sec-I), Bikaner-II TOTAL 24 6933 6343 This Information was given by the Minister of State for Power, Shri Shripad Yesso Naik, in a written reply in the Rajya Sabha today. ********* NR/MD (रलीज़ आईडी: 2200454) आगंतुक पटल : 1251 इस वज्ञ को इन भाषाओ ंम पढ़: Urdu , ही

Continue your research