GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
Municipal Administration and Urban Development Department – Narsaraopet Water
Supply Improvement Scheme under UIDSSMT – Revised Administrative sanction for an
amount of Rs.1825.52 lakhs to Narsaraopet Water Supply Improvement scheme
sanctioned under UIDSSMT scheme– orders – Issued.
MUNICIPAL ADMINISTRATION & URBAN DEVELOPMENT (UBS) DEPARTMENT
G.O.Rt.No. 249 Dated: 27 .02.2012
Read the following:
1. G.O.Ms.No. 84 , MAUD(A1) Department, Dated: 18.08.2008
2. From ENC (PH), Hyderabad Lr.No.777/T3/NRT/WS/UIDSSMT/2009, Dated:
25.10.2010 and 31.10.2011.
3. From Managing Director, APUFIDC Ltd., Hyderabad Lr.No.30703/
APUFIDC/UIDSSMT /Narsaraopet/WS/2010, Dated: 13.6.2011.
<>0<>
ORDER:
In the G.O. 1st read above, orders were issued according administrative
sanction to Narsaraopet Water Supply Improvement Scheme for an amount of
Rs.1657.00 lakhs under UIDSSMT with the following method of financing:
Sl.No. Agency Share ( Rs. in Lakhs)
1. Central share (80%) 931.00
2. State share (10%) 116.00
3. ULB ( 10% of state share + in admissible 610.00
components)
Total: 1657.00
2. The Engineer-in-Chief (Public Health), Hyderabad vide reference 2nd read above,
has submitted that the technical sanction was accorded for Rs.1657.00 lakhs vide
Engineer-in-Chief(PH) R.No.182/2007-08,dt.22.2.2008 and accordingly tenders were
invited through EPC system and the work was entrusted to M/s Megha Engineering and
Infrastructures Limited, Hyderabad.
3 The Engineer-in-Chief (Public Health), Hyderabad has further submitted that the
components of works are in good progress and during the execution of scheme the
necessity of taking of the following additional items was found essential for successful
completion of water supply scheme.
a) Clear Water sump: Clear water sump is to included in the original
sanctioned estimate even though the same is included in the original
DPR. And as per the approved hydraulic designs by the S.E.(PH)
Guntur the clear water sump is essentially required
b) Clear water Feeder main to ELSRs:
280mm dia HDPE main: the length of 280 MM dia feeder mains is
increased form 580 mts to 4380 as per approved design by the S.E. (PH)
to give connections to the ongoing ELSRs in Zone-1 & Zone-3.
225mm dia HDPE main: the length of 225 mm dia HDPE main is
decreased to 1620 mts form 2835 mts as per site conditions and as per
approved designs of SE(PH).
350 mm dia GRP main: The length of 350 mm dia GRP main is
decreased to 280 Mts from 350 Mts as per site conditions and as per
approved designs of SE(PH).
Contd…2…2
600 mm dia GRP main: The length of 600 MM dia feeder mains is
increased form 7135 mts to 7435 mts as per approved design by the
SE(PH). An amount Rs.72.59 lakhs is increased and the same is included
in the revised estimate for laying the above feeder mains.
c) For construction of Pump house duly providing 20 HP Online booster to
800 KL ELSR Vannurukunta Park at Prakash Nagar: As per the
finalized levels MWL,GL, LWL of the ELSR the filling is not possible
with gravity system. The Superintending Engineer(PH) Guntur has
approved online booster to the Reservoir at Vannurukunta Park, but not
included in the deliverables. Hence the same is proposed in the
revised estimate.
4. In view of the above, the Engineer-in-Chief (Public Health), Hyderabad has
requested the Government to accord revised administrative sanction for an amount of
Rs1825.52 lakhs duly meeting the additional amount from the ULB share with the
following method of finance.
G.O.I. Share Rs.931.00 lakh
State share Rs.116.00 lakh
ULB share Rs.778.52 lakh
Total project cost Rs.1825.52 lakh
5. Government after careful examination, hereby accord revised Administrative
Sanction for Narsaraopet Water Supply Improvement Scheme under Sub-Mission on
UIDSSMT under Jawaharlal Nehru National Urban Renewal Mission (JNNURM) for a
total amount of Rs.1825.52 lakhs (Rupees one Thousand Eight Hundred and Twenty
Five Lakhs and Fifty Two Thousand only). The funding pattern among Central
Government, State Government and ULB shall be as detailed below:
(Rs. in lakhs)
Sl. Name of the Project/work Total project GOI State ULB Share (10%)
No. Cost Share Share
(80%) (10%)
1. Narasaraopet Water 1825.52 931.00 116.00 778.52 (10%State share of Rs116.00
Supply Improvement lakhs + other components etc of
Scheme Rs.662.52 lakhs,)
Total: 1825.52 931.00 116.00 778.52
6. The Engineer-in-Chief (Public Health), Hyderabad is informed that the additional
amount of Rs.195.52 lakhs (Rs.1852.57 lakhs – Rs.1657.00 lakhs) against orders
issued vide G.O. 1st read above, shall be met from the departmental funds.
7. The Engineer-in-Chief (Public Health), Hyderabad / The Managing Director,
APUFIDC Ltd., Hyderabad shall take action accordingly.
8. This order issues with the concurrence of Finance Department vide their U.O No.
30252/392/A1/Expr (M&F)/11, dated: 5.1.2012.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
Dr.VIJAY KUMAR
SECRETARY TO GOVERNMENT
To
The Engineer-in-Chief (Public Health), Hyderabad
The Managing Director, APUFIDC Ltd., Hyderabad
Copy to:
The Finance (Expr. M&F) Department
The O.S.D. to Hon,ble (MA)
The P.S. to Secretary (MA) to Government
Sc
//FORWARDED BY ORDER//
RESEARCH OFFICER