See Full Document Text & PDF Transcript
F. No. 1/30/2023-PIU
Government of India
Ministry of Finance
Department of Economic Affairs
Infrastructure Support & Development Division
Private Investment Unit (PIU)
KKKKK
5'" Floor, Jawahar Vyapar Bhawan,
Tolstoy Marg, New Delhi
Dated: 11° November 2024
Office Memorandum
Subject: Record of Discussion (RoD) of 116° PPPAC and 46" Empowered Committee for
considering the three project proposals of the Department of Higher Education, Ministry
of Education on PPP mode with VGF support.
The undersigned is directed to forward the Record of Discussion of the 116" PPPAC
and 46° Empowered Committee (EC) held on 19'" October 2024 for considering the three
project proposals of the Department of Higher Education, Ministry of Education on PPP mode
with VGF support, for information and necessary action.
2. This issues with the approval of the Competent Authority.
To,
1. Secretary, Department of Higher Education, Ministry of Education, Shastri Bhawan,
New Delhi.
2. CEO, NIT] Aayog, Yojana Bhawan, New Delhi.
w Secretary, Department of Expenditure, North Block, New Delhi.
4. Secretary, Department of Legal Affairs, Ministry of Law & Justice.
Copy to:
1. Sr. PPS to Secretary (EA)
2. Sr. PPS to JS (ISD)Subject: Record of Discussion of meetings of 116 PPPAC and 46'° Empowered
Committee for considering the following project proposals (i) Selection of a Private
partner to develop Infrastructure at IIM Udaipur on PPP mode, (ii) Selection of a Private
Partner to develop Student Hostels (Vaigai Hostel, Sarayu Extension Hostel) at IIT
Madras on PPP mode and (iii) Construction, Development, Financing, Operation and
Maintenance of Students’ Hostel in the campus of Indian Institute of Information
Technology, Nagpur on Design, Build, Finance, Operate and Transfer Basis under PPP
Mode
The 116% PPPAC and 46 Empowered Committee (EC) was held on 19" October 2024 at
15:30 hrs to consider the following three proposals of the Department of Higher Education
(DHE), Ministry of Education:
i. Selection of a Private partner to develop Infrastructure at the Indian Institute of
Management (IIM) - Udaipur on PPP mode;
ii. Selection of a Private Partner to develop Student Hostels (Vaigai Hostel, Sarayu
Extension Hostel) at Indian Institute of Technology (IIT) Madras on PPP mode; and
iii. | Construction, Development, Financing Operation and Maintenance of Students’
Hostel in the campus of Indian Institute of Information Technology (IIIT), Nagpur on
Design, Build, Finance, Operate and Transfer (DBFOT) Basis under PPP Mode.
The List of attendees is placed in Annexure I.
Joint Secretary (ISD) welcomed the attendees to the meeting and informed that as per the
PPPAC guidelines, proposals for projects costing INR 250 Crores or more are to be
appraised by PPPAC. While the proposals for IIM Udaipur and IIIT Nagpur fall below this
threshold, the DHE has requested that they be appraised by the PPPAC as, on the one hand,
these are first of its kind projects with no precedence in the education sector; and on the
other hand, it requires EC consideration for the VGF support. This will not only save time
and expedite the projects but will also set a template for undertaking more such projects.
Additionally, it was informed that as in these project proposals, there is no RfQ stage, and
the bidding is single stage two envelope bidding. Therefore, PPPAC may consider for ‘In-Principle and Final Approval’ simultaneously. With the approval of the Chair, these projects
were considered for PPPAC and EC appraisal simultaneously.
With the approval of the Chair, the three institutions were requested to make presentations
on the project proposals. Director IIM Udaipur, Director IIT Madras and Registrar IIIT Nagpur
made detailed presentations:
IIM Udaipur: IIM Udaipur, established in 2011, offers postgraduate, doctoral, and
executive management programs. The institute plans to increase MBA intake, PhD
student intake, and expand executive program training days by 2027-28. Currently,
hostel accommodation is not adequate, including no hostel for PhD or executive
program students. The proposed development will be undertaken in DBFOT mode
with a 30 year concession period, including 2.5 years for construction. The project
consists of three key components: a Student Hostel (7,100 sqm) to accommodate
150 students on a single occupancy basis across three blocks each with a G+5
structure and an additional block for dining; a Married Student Hostel (2,200 sqm)
for 30 married students (with preference for PhD students) on a single occupancy
basis, developed as a single G+5 structure; and an Executive Hostel (12,000 sqm)
with 100 rooms, 10 suite rooms, 4 classrooms, 4 breakout rooms, a conference
room, dining hall, administrative offices, kitchen, and indoor sports area. The
concessionaire will be responsible for financing, infrastructure design, construction,
building maintenance, housekeeping, and asset replacement for all hostels. IIM
Udaipur will be responsible for food and beverages (F&B), utilities, and fixing user
charges. The concessionaire will collect user charges directly from students for the
student hostel, while for the married and executive hostels, the concessionaire
collects charges from IIM Udaipur. The details of the project are in Annexure Il.
lIT Madras: IIT Madras, established in 1959, is a leading institute offering
undergraduate, postgraduate, and doctoral programs in engineering and sciences.
It currently accommodates 11,000 students in 8,000 hostel rooms. In addition, there
are 750 project staff who require accommodation, but the current infrastructure
cannot meet this demand. The institute plans to develop a hostel to address this gap,
catering specifically to PhD scholars and project staff. The proposed project will be
2undertaken in DBFOT mode with a 30 year concession period, including 1.5 years
for construction. The project consists of two key components: Vaigai Hostel, with
1,208 rooms (6,610 sqm) including 820 single occupancy rooms, 360 double
occupancy rooms, 14 guest rooms, 10 PWD rooms, and 4 office rooms, all within a
G+11 structure; and Sarayu Hostel, with 270 rooms (2,250 sqm) with 222 single
occupancy rooms, 40 double occupancy rooms, 2 guest rooms, 2 PWD rooms, and
4 office rooms, also in a G+11 structure. The project employs fast-track construction
using prefabricated elements to ensure better quality, faster execution, and reduced
waste, with a 100 year life guarantee for the main structure. The concessionaire will
be responsible for financing, infrastructure design, construction, building
maintenance, housekeeping, and asset replacement for all hostels. IIT Madras will
be responsible for F&B, utilities, and fixing user charges. The concessionaire will
collect user charges directly from the students. The details of the project are in
Annexure Ill.
IIIT Nagpur: IIIT Nagpur, established under the Indian Institute of Information
Technology (Public-Private Partnership) Act, 2017. The institute currently offers
undergraduate courses, PhD programs, a Post-Graduate Diploma, and an M. Tech
in Information & Communication Technology in collaboration with the Military
College of Telecommunication Engineering, Mhow. It currently accommodates 1,420
students in a single hostel with a capacity of 870. The institute plans to increase its
undergraduate intake to 2,400 students by 2027-28. Additionally, there are 200-250
PhD students to be accommodated. The proposed project will be undertaken in
DBFOT mode, with a 22 year concession period, including 2 years for construction.
The project consists of one hostel with 550 rooms (1,691 sqm) on double occupancy
in a G+10 structure with facilities like common toilets, dining areas, warden office,
lobby, laundry rooms, medical and storerooms, gym, indoor and outdoor sports
facilities, fire control, and associated external infrastructure (such as STP, WTP, and
power stations). The concessionaire will be responsible for financing, infrastructure
design, construction, building maintenance, housekeeping, utilities, F&B and asset
replacement for the hostel. IIIT Nagpur will be responsible for fixing user charges.The concessionaire will collect user charges directly from the students. The details
of the project are in Annexure IV.
The Chair then asked the members to raise any pending substantive issues. The members
submitted the following:
Department of Economic Affairs (DEA): DEA stated that all their comments have
been addressed and has no further comments.
Niti Aayog: NITI Aayog stated that all their comments have been addressed and has
no further comments.
Department of Expenditure (DoE): DoE stated that all their comments have been
addressed and has no further comments except one observation that a clear
distinction may be made by the DHE between projects eligible for HEFA funding and
those that can be supported through a VGF grant. Proper segregation between these
two mechanisms may be ensured to avoid overlap and ensure that each project is
aligned with the appropriate funding source.
Department of Legal Affairs (DoLA): DoLA had NIL comments.
The Chair then raised the following observations:
Are proposed project revenue streams, O&M costs, occupancy rate, etc.
reasonable?
Why are there variations in the proposed hostel fees across these three projects?
Has the impact of the Goods and Services Tax (GST) been factored into?
Rather than having different fee escalation rates, can we have 4% YoY fee escalation
rates?7. DHE, along with IIM Udaipur, IIT Madras and IIIT Nagpur, submitted the following with respect
to the observations raised:
The assumptions used for project revenue streams, O&M costs and occupancy rate
have been benchmarked with the existing similar facilities and current capacity
levels.
The fee escalation rate is based on the current fee escalation rates; however, it will
be revised to 4% YoY fee escalation.
The GST has been factored into. However, in most of the proposed facilities, the GST
will not be applicable due to the lower hostel fees, except for the executive hostel in
IIM Udaipur where the same has been appropriately considered.
All three project proposals differ in nature. The IIM Udaipur hostel facilities cater to
postgraduates, PhD candidates, and executives, while the IIT Madras facilities are
intended for PhD candidates and project staff. In contrast, the IIIT Nagpur hostel
primarily serves undergraduates. The IIIT Nagpur facility offers double occupancy,
whereas the others are designed for single occupancy. Additionally, the proposed
fees for IIT Madras are based on the House Rent Allowance (HRA) currently provided
to PhD candidates and project staff.
HEFA provides loans to Higher Education Institutions, while the institutions raise
funds. VGF, on the other hand, offers partial government funding to attract private
sector efficiency and investment including project finance for the project.
8. The Chair then gave the following suggestions for the future projects:
DHE may consider limiting the VGF grant to 50% with appropriate project structuring.
DHE may ensure some uniformity in hostel fees and YoY escalation (which could be
at 4%).
DHE may consider the appropriateness of the facilities such as air conditioning, etc.,
while structuring the student hostels.
A better understanding of GST is needed, and efforts may be made to engage with
the Department of Revenue and State Governments to seek favourable
considerations for social sector infrastructure PPP projects.v. For financial modelling, equity IRR may be considered at 14%.
After detailed deliberations, the PPPAC unanimously recommended the project proposals
for “Final Approval” of the Competent Authority as per the PPPAC Guidelines.
10. The Empowered Committee also unanimously recommended granting ‘In-Principle
Approval’ for VGF support to all three project proposals under the Sub Scheme -— | of the
VGF Scheme to the Competent Authority, as per the VGF Scheme and Guidelines with the
following conditions: -
i. The recommendation for the in-principal approval of the VGF is as follows:
Project Maximum CAPEX Grant (VGF) Gol Share under the VGF
admissible @ 60% of TPC Scheme
(In Rs. Crore) (In Rs. Crore)
IIM Udaipur 60.26 30.13
IIT Madras 238.18 119,09
IIIT Nagpur 52:52 26.26
Total 350.96 175.48
ii. | The fee escalation may be structured at 4% YoY or at 8% every two years for all three
proposals.
iii. | Revalidation of the recommendation of the project proposal by the PPPAC/EC is not
required for the following post-recommendation changes in the project cost/bid
documents:
a. Any change in the date/time period for any time-bound actions like appointed
date, financial close, construction period, etc.
b. Non-substantial change in risk allocation.
c. Any other changes/modifications (except as stated above) in the project
proposals with the overall objective of making the projects successful.
d. Further, the Department of Higher Education will decide whether the changes
proposed post recommendations of the project proposals by the PPPAC fall
within the threshold criteria as stated above. All such changes with the
threshold criteria as stated above shall be appraised at the level of Secretary(DHE) without any further need for revalidation by the PPPAC and DHE shall
proceed with the process accordingly.
iv. | However, the following changes shall warrant revalidation of recommendation of
project proposals by the EC:
a. Any change in the formulation of pre-determined user charges/tariffs.
b. Any change in the concession period by more than 20%.
c. Any changes having an impact on the In-principle approved amount of VGF
for Gol on the higher side.
v. | Necessary amendments to the bid documents to incorporate the decision of the
PPPAC/EC shall be undertaken by DHE/Project Sponsoring Authority (PSA). Further,
DHE/PSA ensure legal vetting of the documents is undertaken to ensure that there
are no discrepancies in the contract documents and to circulate to the members of
the EC for the record.
vi. ‘Final Approval’ for VGF support is contingent upon the compliance of all conditions
of the VGF Scheme.
11. The meeting ended with a vote of Thanks to the Chair.
KRRKRKEKKAnnexure |
List of the attendees of the 116" PPPAC and 46 Empowered Committee (EC) Meeting for
considering the project proposal for (i) Selection of a Private partner to develop Infrastructure at
IIM Udaipur on PPP mode, (ii) Selection of a Private Partner to develop Student Hostel (Vaigai
Hostel, Sarayu Extension Hostel) at IIT Madras on PPP mode and (iii) Construction, Development,
Financing Operation and Maintenance of Students’ Hostel in the campus of Indian Institute of
Information Technology, Nagpur on Design, Build, Finance, Operate and Transfer (DBFOT) Basis
under Public-Private Partnership (PPP) Mode, held on 19.10.2024.
I. Department of Economic Affairs, Ministry of Finance
1. Shri Ajay Seth, Secretary, EA- In Chair
2. Shri Baldeo Purushartha, JS(ISD)
3. Shri. Rahul Singh, Joint Director
Il. Department of Expenditure
1. Ms. Hema Jaiswal, DDG(PFC-II)
Hl. NITI Aayog
1. Ms. Nidhi Arora, Consultant,
IV. Department of Legal Affairs
1. Dr. RJR Kasibhatla, Deputy Legal Adviser
V. Department of Higher Education
1. Shri K Sanjay Murthy, Secretary
2. Shri SK Barnwal, Additional Secretary
Vi. IIM Udaipur
1. Prof. Ashok Banerjee, Director IIM Udaipur
2. Prof. N. Viswanathan, Member of Finance & Audit Committee
VIL. IIT Nagpur
1. Shri Kailas N. Dakhale, Registrar
2. Shri Harshad Pophali, OSD
3. Shri Rajesh Hakke, OSD
Vill. IIT Madras
1. Prof. Ravindra Gettu, DirectorAnnexure Il
Selection of a Private partner to develop Infrastructure at
Project Description
IIM-Udaipur on PPP mode with VGF support
Type of PPP (BOT, BOOT,
DBFOT basis
BOLT, OMT etc.)
Location Udaipur, Rajasthan
Administrative
Department of Higher Education
Ministry/Department
Name of Sponsoring
Authority IIM Udaipur
Name of the
Implementing IIM Udaipur
Agency
Concession Period 30 years
Construction period 30 months
Total Project Cost (TPC) Total Project Cost: INR 100.43 Crore
Project Milestone-1: Completion of construction of 100
rooms of Student Hostel (Regular) and 100% of Married
Student Hostel with all facilities shall occur on the date
falling on the date of expiry of 18 (eighteen) months from
the Appointed Date
Project Milestone-2: Completion of construction of
Project Implementation Executive Hostel shall occur on the date falling on the date
Schedule of expiry of 24 (twenty-four) months from the Appointed
Date.
Project Milestone-3: Completion of construction of an
additional 50 rooms of Student Hostel (Regular) shall occur
on the date falling on the date of expiry of 30 (thirty) months
from the Appointed Date.Scheduled Completion Date: The Scheduled Completion
Date shall be 30 months from the Appointed Date.
Main revenue streams are:
Pre-defined user charge to be collected from students for
Revenue Stream of the
Regular Student Hostel
project
Pre-defined user charge payable by IIM U for Married
Student Hostel and Executive Hostel
pe IM U will fix the user charge to be collected by the
ari
Concessionaire
Debt and Equity in the ratio 70:30 and Grant has been
Source of Financing
considered upto 60% of the Total Project Cost
The VGF support will be provided in accordance with the
VGF Guidelines, i.e. INR 60.26 Crore or actual quote,
whichever is less
VGF
Share of Gol: INR 30.13 Crore (30%)
Share of Project Sponsoring Authority: INR 30.13 Crore
(30%)
Land Acquisitions Land is under the ownership of IIM -Udaipur
Bidding parameter Lowest VGF or Highest Premium
Bidding process Single Stage
Likely Amount of VGF
INR 60.26 Crore or actual quote, whichever is less
required for the project
Project NPV- INR 8.83 Crore
NPV and IRR Project IRR- 12.20%
Equity IRR- 15.48%
10Annexure III
Selection of a Private Partner to develop Student Hostels
Project Description (Vaigai Hostel, Sarayu Extension Hostel) at IIT Madras
on PPP mode.’
Type of PPP (BOT, BOOT,
DBFOT basis
BOLT, OMT etc.)
Location Chennai, Tamil Nadu
Administrative
Department of Higher Education
Ministry/Department
Name of Sponsoring
IIT Madras
Authority
Name of the Implementing
IIT Madras
Agency
Concession Period 30 years
Construction period 18 months
Total Project Cost (TPC) Total Project Cost: INR 396.96 Crore
Project Milestone-1: Project Milestone-| shall occur on
the date falling on the 12 months from the Appointed
Date. The Concessionaire shall have expended not less
than 75% of the Total Project Cost set forth in the
Financial Package.
Project Implementation Project Milestone-2: Project Milestone-ll shall occur on
Schedule the date falling on the date of expiry of 18 (eighteen)
months from the Appointed Date. The Concessionaire
shall have expended not less than 100% of the Total
Project Cost set forth in the Financial Package
Scheduled Completion Date: The Scheduled
Construction Completion Date shall be 18 months from
the Appointed Date.
11Main revenue streams are:
The Concessionaire shall be granted the right to collect
hostel fees and this shall be the main revenue stream
from the project.
The Concessionaire shall also be allowed to operate the
cafeteria and vending machine within the hostel
Revenue Stream of the
premises and earn revenue from it.
project
The Concessionaire shall also be allowed to earn
revenue from cleaning of rooms (optional based on
request from students and staff) and badminton courts
(for users outside Vaigai and Sarayu Hostel as approved
by Authority) as per the provisions of the Concession
Agreement
IIT Madras will fix the user charge to be collected by the
Tariff
Concessionaire
Debt and Equity in the ratio 70:30 and Grant has been
Source of Financing
considered upto 60% of the Total Project Cost
The VGF support will be provided in accordance with the
VGF Guidelines, i.e. INR 238.18 Crore or actual quote,
whichever is less
VGF
Share of Gol: INR 119.09 Crore (30%)
Share of Project Sponsoring Authority: INR 119.09 Crore
(30%)
Land Acquisitions Land is under the ownership of IIT Madras
Bidding parameter Lowest VGF or Highest Premium
Bidding process Single Stage
Likely Amount of VGF
INR 238.18 Crore or actual quote, whichever is less
required for the project
Project NPV- INR 55.85 Crore
NPV and IRR Project IRR- 13.70%
Equity IRR- 15.80%
12Annexure IV
Construction, Development, Financing Operation and
Maintenance of Students’ Hostel in the campus of Indian
Project Description
Institute of Information Technology, Nagpur on DBFOT
Basis under PPP Mode
Type of PPP (BOT, BOOT,
DBFOT basis
BOLT, OMT etc.)
Location Nagpur, Maharashtra
Administrative
Department of Higher Education
Ministry/Department
Name of Sponsoring
Authority IIIT Nagpur
Name of the
Implementing IIIT Nagpur
Agency
Concession Period 22 years
Construction period 24 months
Total Project Cost (TPC) Total Project Cost: INR 87.54Crore
Project Milestone-1: Project Milestone-| shall occur on the
date falling on the 365" (three hundred and sixty-five) day
from the Appointed Date. The Concessionaire shall have
expended not less than 30% of the total capital cost set forth
in the Financial Package
Project Implementation
Schedule
Project Milestone-2: Project Milestone-II shall occur on the
date falling on the 540" (five hundred and forty) day from
the Appointed Date. The Concessionaire shall have
expended not less than 65% of the total capital cost set forth
in the Financial Package.
13Project Milestone-3: Project Milestone-lll shall occur on
the date falling on the 730" (seven hundred and thirty) day
from the Appointed Date. the Concessionaire shall have
commenced [construction of all Project Facilities and
expended not less than 100% of the total capital cost set
forth in the Financial Package
Scheduled Completion Date: The Scheduled
Construction Completion Date shall be the 730 (seven
hundred and thirty) day from the Appointed Date.
Main revenue streams are:
Pre-defined user charge to be collected from students
Revenue Stream of the Hostel
project Interest on deposits i.e. Electricity, Water, mess etc.
Lease Rental from Utility Shops
Income from Canteen Facilities
aan IIIT Nagpur will fix the user charge to be collected by the
Concessionaire
Debt and Equity in the ratio 60:40 and Grant has been
Source of Financing
considered upto 60% of the Total Project Cost
The VGF support will be provided in accordance with the
VGF Guidelines, i.e. INR 52.52 Crore or actual quote,
whichever is less
VGF
Share of Gol: INR 26.26 Crore (30%)
Share of Project Sponsoring Authority: INR 26.26 Crore
(30%)
Land Acquisitions Land is under the ownership of IIIT Nagpur
Bidding parameter Lowest VGF or Highest Premium
Bidding process Single Stage
Likely Amount of VGF
INR 52.52 Crore or actual quote, whichever is less
required for the project
14Project NPV- INR 9.58 Crore
NPV and IRR
Project IRR- 15.36%
Equity IRR- 18.74%
15