Date: 2025-04-29Category: Public Private Partnership in IndiaState: Union GovernmentCountry: India
Six lane Acess Control Greenfield Capital Region Ring Road Bhubaneshwar Bypass from Rameshwar to Tangi in the state of Odisha on HAMFour-lane, Parmakudi to Ramanathapuram Section of NH-87 in the state of Tamil Nadu on HAM4 Laning of Rajapalayam to Shenkottai Section of NH-744 from Km 71+600 to Km 139+900 (Design Chainage) in Tamil Nadu on Hybrid Annuity Mode (Project Length-68.3Km)
**Executive Summary**
This document forwards the Record of Discussion of the 122nd meeting of the PPPAC held on April 29th, 2025, to consider two project proposals from the Ministry of Road, Transport & Highways (MoRTH) regarding highway projects in Odisha and Tamil Nadu. The document details the projects, responses to previous observations, and resulting recommendations. It is issued for information and necessary action by the listed recipients.
**Key Points / Main Content**
* **Meeting Overview:**
* The 122nd PPPAC meeting occurred on April 29th, 2025, chaired by the Finance Secretary & Secretary (EA).
* NHAI made a detailed presentation on two road projects.
* **Project 1: Six-lane Access Control Greenfield Capital Region Ring Road (Bhubaneswar Bypass), Odisha**
* Project Scope: Development of a new 6-lane highway of total length Km. 110.875 on Hybrid Annuity Mode in the state of Odisha.
* Total Capital Cost: Rs. 8307.74 crore.
* Revised Tolling Strategy: Allows users to travel an equivalent distance free on the proposed bypass, shifting the toll plaza to Ch. 78km.
* Recommendation: Unanimously recommended for administrative approval, subject to specific recommendations, including that MoRTH develop a policy for regulated development along ring roads/bypasses.
* **Project 2: Four-lane, Parmakudi to Ramanathapuram Section of NH-87, Tamil Nadu**
* Project Scope: 4-laning of a 46.665 km section of NH-87 on Hybrid Annuity Mode in Tamil Nadu.
* Total Capital Cost: Rs. 1853.16 crore.
* Recommendation: Unanimously recommended for administrative approval, subject to specific recommendations, including exploring the possibility of developing a combined Madurai-Ramanathapuram stretch on the BOT (Toll) model.
* MORTH to adopt a forward-thinking approach for designing road projects.
* **Common Recommendations:**
* All approvals (forest clearance, tree cutting, etc.) to be obtained by NHAI before bid submission.
* Revalidation by PPPAC is not required for changes in date/time, risk allocation, or modifications improving the project.
* **Third Project: Development of 4 Laning of Rajapalayam to Shenkottai Section of NH-744**
* The project was deferred for consideration after receiving response of the MoRTH on comments at Annexure-III.
**Impact Analysis**
**Secretary, Department of Expenditure, CEO, NITI Aayog, Secretary, Ministry of Road, Transport & Highways, Secretary, Department of Legal Affairs.**
* **Impact:** Responsible for being aware of the Record of Discussion of the PPPAC meeting and understanding the recommendations.
* **Action Required:** Review the information and take any necessary actions within their respective departments.
**Ministry of Road Transport and Highways (MoRTH) / National Highways Authority of India (NHAI)**
* **Impact:** Responsible for actioning the PPPAC's recommendations for the Odisha and Tamil Nadu projects.
* **Action Required:** Address observations, develop policies, obtain necessary approvals, and proceed with the approval process. For Rajapalayam to Shenkottai, act on the comments at Annexure-III and resubmit.
**Finance Secretary & Secretary (EA)**
* **Impact:** Accountable for the overall outcome of the projects and ensuring they are implemented effectively.
* **Action Required:** Monitor the progress of the projects and provide guidance as needed.
Key Entities Referenced
Public Private Partnership Appraisal Committee (PPPAC): Committee responsible for appraising Public Private Partnership projects.
Ministry of Road, Transport & Highways (MoRTH): The Indian government ministry responsible for the formulation and administration of the rules, regulations and laws relating to road transport, transport research and inland water transport.
National Highways Authority of India (NHAI): The government agency responsible for the development, maintenance and management of national highways in India.
Hybrid Annuity Mode (HAM): A model for infrastructure development where the government pays 40% of the project cost during the construction period and the remaining 60% over a period of time, with interest.
Odisha: The state where the Capital Region Ring Road (Bhubaneswar Bypass) project is located.
F.No.2/2/2025-PIU
Government of India
Ministry of Finance
Department of Economic Affairs
Infrastructure Finance Secretariat
ISD Division
(PIU)
*****
STCs Building, Janpath New Delhi
Dated: 12th May 2025
Record of Discussion
Subject: Record of Discussion of the 122nd meeting of the PPPAC for
considering the Two project proposals of the Ministry of Road, Transport &
Highways (MoRTH) on PPP mode.
Reference: 120th Meeting of the PPPAC meeting held on 11th February 2025
& 122nd meeting held on 29th April 2025.
Sir/Madam,
The undersigned is directed to forward the Record of Discussion of the 122nd
meeting of the PPPAC held on 29th April 2025, under the Chairmanship of
Finance Secretary & Secretary (EA) for information and necessary action.
2. This issues with the approval of the Competent Authority.
(Arya Balan Kumari)
Joint Director (PIU)
011-2370 1219
To,
1. Secretary, Department of Expenditure, North block, New Delhi-01
2. CEO, NITI Aayog, Yojana Bhawan, New Delhi-01
3. Secretary, Ministry of Road, Transport & Highways, Transport
Bhawan, New Dehi-01
4. Secretary, Department of Legal Affairs, Shastri Bhawan, New Delhi.
Copy to:
1. Sr. PPS to Finance Secretary & Secretary (EA)
2. Sr.PPS to OSD, DEA
3. Sr. PPS to JS (ISD)
Page 1 of 24Subject: Record of Discussion of the 122nd meeting of the PPPAC for
considering the following project proposals: -
(i) Six-lane Access Control Greenfield Capital Region Ring Road
(Bhubaneswar Bypass) from Rameshwar to Tangi in the State of
Odisha on HAM.
(ii) Four-lane, Parmakudi to Ramanathapuram Section of NH-87 in the
State of Tamil Nadu on HAM.
(iii) 4 Laning of Rajapalayam to Shenkottai Section of NH-744 from Km
71+600 to Km 139+900 (Design Chainage) in Tamil Nadu on Hybrid
Annuity Mode (Project Length-68.3Km)
1. The 122nd meeting of the PPPAC was held on 29th April 2025 at 06:15 Hours
under the Chairmanship of Finance Secretary cum Secretary (EA) to consider the
above-mentioned road projects of MoRTH. Project (i) and (ii) were discussed in
the 120th PPPAC also but deferred in the light of observation of the PPPAC.
MoRTH has provided a detailed response to the observations of the 120th
PPPAC. The responses of MoRTH are annexed at Annexure-I & II.
2. The project at serial number (iii) was deferred for consideration after receiving
response of the MoRTH on comments at Annexure-III
3. List of attendees is placed at Annexure-IV.
4. With the permission of Finance Secretary cum Secretary (EA), Joint Secretary
(ISD) welcomed all the attendees to the meeting. NHAI made a detailed
presentation on these two road projects.
Page 2 of 24I. Six-lane Access Control Greenfield Capital Region Ring Road
(Bhubaneswar Bypass) from Rameshwar to Tangi in the State of Odisha on
HAM.
1. The basic details of the project are given in the table below:
Table 1: Details of the project
Development of new 6-lane Access Control Greenfield Capital Region
Project Ring Road (Bhubaneswar Bypass) from Rameshwar Near Kuspangi (NH-
Description 16) to Tangi Near Bandalo Toll Plaza (NH-16) total length Km. 110.875
on Hybrid Annuity Mode in the State of Odisha
PPP Model HAM
Sponsoring
Ministry of Road Transport and Highways (MoRTH)
Authority
Implementing
National Highways Authority of India (NHAI)
Agency
State: Odisha
Location
District: Khurda, Dhenkanal & Cuttack
Length 110.875 Km
Type of
Flexible
pavement
Lane
Six Lane (6-Lane)
configuration
Proposed
60 m
RoW
Sl. Total
Description Package-1 Package-2 Package-3
No.
1 Length(km) 40.250 30.295 40.330 110.875
2 Interchange 2 3 1 6
4 Viaduct 1 Nil 2 4
5 VUP 08 Nos. 03 Nos. 06 Nos. 17 Nos.
6 LVUP 08 Nos. 06 Nos. 16 Nos. 30 Nos.
7 SVUP 07 Nos. 03 Nos. 03 Nos. 13 Nos.
Structures EUP/Animal 12 Nos.
8 07 Nos. 03 Nos. 02 Nos.
Underpass
10 ROB 01 No. Nil 2 Nos
3 Nos.
11 Major Bridges Nil 03 Nos 02 Nos 5 Nos.
12 Minor Bridges 10 Nos. 11 Nos. 23 Nos. 44 Nos.
13 Culverts 142 Nos 90 Nos 69 Nos. 301 Nos.
Waysides 3 Nos.
14 01 No. 01 No. 1 Nos.
Amenity
Page 3 of 24One Main
One Main
Plaza and Only Ramp
Plaza and
ramp Plaza Plazas at
15 Toll Plaza ramp Plaza
at Exit - exit- entry
at Exit -entry
entry locations.
locations
locations
Sl. Total
Project Description Package-1 Package-2 Package-3
No.
Packages
1 Length(km) 40.250 30.295 40.330 110.875
Concession
17.5 years (2.5 years of construction + 15 years of O&M)
Period
Sl. DESCRIPTION Package- Package- Package-
Total
No. OF WORKS 1 2 3
Cost of Civil
A 1584.36 1314.22 1742.25 4640.83
Works
Utility Shifting
B 25.64 11.78 8.49 45.91
Cost
Total Civil
Construction
Estimated Cost
1 1610 1326.00 1750.74 4686.74
Capital Cost (including cost
with Break- of Utility
up under Shifting)
major heads
I/C & Pre-
of
Operative
expenditure 2 16.10 13.26 17.51 46.87
Expenses (1 %
of Civil Cost)
Financing Cost
3 7.18 5.89 6.39 19.46
(1% of debt )
Interest during
4 82.03 57.50 52.69 191.04
construction
Estimated
5 Project Cost 1715.31 1402.64 1827.33 4945.28
(1+2+3+4)
Page 4 of 24GST @ 18 %
on Total Civil
6 293.99 252.48 315.13 861.6
Cost (Excluding
Utility Shifting)
Contingency @
1% on Civil
7 15.84 13.14 17.51 46.49
Cost (Excluding
Utility Shifting)
O&M Cost for
15 years as per
8 Ministry OM 216.57 177.16 240.76 634.49
dated
23.05.2022
Escalation @
5% per year for
9 3 Years (on 253.74 208.98 275.92 738.64
Civil Cost ic.
Utilities)
Supervision
9 Charges on 0.64 0.29 0.21 1.14
Utility Cost
Land
10 acquisition and 426.26 383.17 220.0 1029.43
R&R
Environmental
11 & Forest 22 15.32 13.34
Mitigation Cost 50.66
Total Capital
Cost
12 2944.36 2453.18 2910.20 8307.74
(5+6+7+8+9+10
+11)
Per km of Total
13 Capital Cost 73.15 80.97 72.15 74.93
(Cr. / km)
Page 5 of 24Total Required: 840.39 Ha
Land
3A: 95%,
Acquisition
3D: 95%
Status
3G: 85%
Particulars Package1 Package2 Package3
Project IRR (in %) 12.66% 13.08% 12.83%
Equity IRR (in %) 15% 15% 15%
Financial Project NPV @12% 27.39 Crs. 36.27Crs. 36.73 Crs.
Viability discounting (Rs. in Cr.)
Project NPV @WACC of 105.82 Crs. 120.71 Crs 123.19 Crs
10.31% (Rs. in Cr.)
Min. DSCR 1.34 1.37 1.31
Concession
Based on MCA for Hybrid Annuity Model
Agreement
Bidding
Bids will be evaluated on the basis of the lowest Bid Project Cost.
parameter
Bidding
Single Stage Two Envelop Process
process
2. The primary purpose of the proposed 6 Lane access-controlled project Highway is to
ease up congestion in the existing NH-16 (Part of GQ) passing through Khorda,
Bhubaneswar & Cuttack (86 Km). The Existing NH-16 (Kolkata- Chennai) passes
through highly urbanized areas of 3 major cities of Khorda, Bhubaneswar and
Cuttack. Considering the rapid urbanization and growth in the state capital, it is not
practical to widen or augment the existing National Highway. The traffic in the city has
already crossed 1 Lakh PCU leading to multiple congestion points. Therefore, the
proposed project is essential to address the huge traffic congestion problem and for
the overall development of the Region.
3. The travel time on the existing road section is around 120 minutes. During the peak
hours, the travel time on existing road section increases from 120 minutes to 150
minutes. The proposed greenfield alignment, designed for 100 km/h, is expected to
reduce travel time from 120 minutes to 80 minutes. The proposed 6-lane road
project, spanning 110.875 km with a 60m right-of-way, is expected to yield significant
savings in Vehicle Operating Costs (VOC).
4. The project will be executed under the HAM model with a Total Capital Cost of
Rs.8,307.74 crore. Subsequently, it will be monetized through InvIT or TOT models.
The project will be implemented in three packages and is part of NH(O) Scheme. The
financial assessment indicates a Project IRR of both the packages are higher than
12% and equity IRR of 15%. With respect to land acquisition, the 3G of 85% has
Page 6 of 24been achieved in the project. Further, state govt. is sharing 50% of land acquisition
cost in the project. Accordingly, 200 Cr. has already been deposited by state Govt for
this purpose.
5. The project has been considered in the 120th PPPAC meeting held on 4th Feb 2025.
The queries raised by the PPPAC and the response of MoRTH are provided at
Annexure I. The main observation was on the tolling plan of the proposed road
including proposal of revenue sharing with the existing BOT concessionaire. In its
reply, MoRTH said that the tolling plan proposed during the 120th PPPAC meeting
has been revised, eliminating the need for compensating the existing BOT
concessionaire through toll revenue sharing. Tangi serves as the toll plaza for the
BOT (Toll) project, located 16KM from the proposed roadway. Between Bhubaneswar
and the Tangi toll plaza, the distance is 44.3KM. As per the revised tolling strategy, no
toll is to be paid by the passengers for 33KM on the proposed bypass (which is the
equivalent distance of 44.3 KM of existing BoT Road). In other words, it is now
proposed to allow the user to travel equivalent road length free on proposed bypass
to ensure no financial impact on the commuter as well as the existing BOT
concessionaire. The toll Plaza of CRRR on Tangi side shall be shifted in Ch. 78km
(approx.) at suitable location. With the integrated tolling system, commuters from
Chennai and Kolkata will be tolled at the Tangi Plaza, ensuring that the operation
remains free of financial losses to the existing concessionaire.
6. After the detailed presentation, the Chair asked the PPPAC members for their
observations. DEA, NITI Aayog, DoE and DoLA supported the proposal and stated
that no further comments to offer.
7. The Chair made the following observations:
a) How MoRTH is addressing the problem of unregulated ribbon development
along the ring roads/bypasses?
b) Has any legal advice been sought regarding revised tolling strategy
envisaged for the project?
c) The per KM for Package-2 is higher than the normative costs and those of the
other two packages?
8. MoRTH submitted the following to the queries raised by the PPPAC Members: -
a) MoRTH is finalizing a policy on development of access-controlled Ring
roads/ bypasses for major cities for urban decongestion. Under the
proposed policy, emphasis is on regulated development along proposed
bypasses. The policy would require a development control zone of 15m on
either side of the NH bypass or ring road shall be notified by the State
Page 7 of 24Government as a green zone under the planning laws enacted by the
State Government where development shall be prohibited unless it is for
public transport or mobility infrastructure, public utility infrastructure like
electricity, water or sewerage pipeline or green zone infrastructure.
Beyond the No Construction Green Zone, the State Government may
plan, develop, or regulate the development of residential, commercial,
industrial, and institutional infrastructure within a 2 km radial distance on
either side of the bypass or ring road. This will enable value capture for
new development for economic activities using the ring road or bypass as
the centre of development in a regulated manner. Additionally, the access
to ring road/bypass would be only through service roads which would be
constructed at the time of project development and entry to the main
carriageway would be provided only through slip roads or interchanges.
b) A legal opinion has been obtained on the revised tolling strategy, and it
has been confirmed that the proposed mechanism is free from any legal
impediment. The existing BOT concessionaire has also given no objection
to this.
c) The per kilometer cost for Package-2 is Rs. 80.97 crore vis a vis the costs
for the other two packages are in the range of Rs. 73 crore per kilometer.
The main reason for the high per km cost in Package-2 is due to the
construction of bridges over the Mahanadi River.
Recommendations:
9. After detailed deliberations, the PPPAC unanimously recommended the proposal for
“Development of Six-lane Access Controlled Greenfield Capital Region Ring Road
(Bhubaneswar Bypass) from Rameshwar to Tangi in the State of Odisha on HAM” for
consideration of the competent authority for giving administrative approval. The overall
recommendation is subject to following specific recommendation.
a) The appraised Total Capital Cost for all three packages is Rs. 8307.74 crore.
b) The project should be taken up on HAM under the NH (O) scheme.
c) MoRTH should develop a policy for regulated development along Ring roads/
bypasses.
d) All approvals, such as forest clearance, tree cutting, permissions, etc., shall
be obtained by the NHAI well before the bid submission date.
10. Revalidation of its recommendation by the PPPAC is not required for the following post
recommendation changes in the project costs/bid documents: -
Page 8 of 24a) Any change in the date / time period for any time-bound actions like appointed
date, financial close, construction period etc.
b) Non-substantial change in risk-allocation.
c) Any other changes/modification in the project proposal with the overall
objective of making project successful.
d) Further, MoRTH/ NHAI may decide whether the changes proposed post
recommendations of the project proposal by the PPPAC fall within the
threshold criteria as stated above. All such changes falling within the
threshold criteria shall be appraised at the level of Secretary (RTH)/ BoD of
NHAI as the case may be, without any further need of revalidation by the
PPPAC and shall proceed with the approval process accordingly.
***
Page 9 of 24II. Four-lane, Parmakudi to Ramanathapuram Section of NH-87 in the state of
Tamil Nadu on HAM
1. The basic details of the project are given in the table below:
Table 2: Details of the project
4 Laning of Parmakudi to Ramanathapuram Section of NH-87 from Km
Project
80+360 to Km 127+025 (Design Chainage) in the state of Tamil Nadu
Description
on Hybrid Annuity Mode (Project Length-46.665 km)
PPP Model HAM
Sponsoring
Ministry of Road Transport and Highways (MoRTH)
Authority
Implementin
National Highways Authority of India (NHAI)
g Agency
State: Tamil Nadu
Location
Town: Tiruppuvanam to Dhanushkodi
Length 46.665 km
Type of
Flexible
pavement
Lane
configuratio Four lanes (4-lane)
n
Proposed
30m – 45m
RoW
Major Bridges Nil
Major Bridge Cum VUP 1 No.
Minor Bridges 20 Nos
Box Culverts 106 Nos = 49 (New) + 51
(Reconstruction) + 6 (Widening)
Additional Box culverts 10
Cross road Box Culverts 77
Median Drain Out Culverts 26
Flyover Nil
Structures
Interchange Nil
Viaduct Nil
RoB/ RuB Nil
VUP 9 Nos.
Animal Underpass (No) Nil
LVUP 4 Nos
SVUP 4 Nos
VOP 19 Nos.
FOB Nil
Page 10 of 24Junctions below grade separated 18 Nos.
structures
Length of Service Road/ Slip Road 3.430 Km + 20.890 Km = 24.320
(Both Sides) Km
Lined/RCC roadside drain (Both 25.030km
Sides)
Median Drain 42.694 km
Bypass (No. & Length) 2 Nos & 7.870 km
Realignment – length 17.275 km
Bus-bays/ Shelters Bus Bays: 7 Nos.
Bus Shelters: 33 nos.
Truck Lay-byes 2 No (Both Sides)
Rest Area / Way side amenities Nil
Any Other, specify Nil
Project
One package with 46.665KM
Packages
Concession
17 years (2 years construction period + 15 years Operation Period)
Period
Cost (Rs in
Sl. No. Description
crore)
Civil Construction Cost including Utility
(i) 997.63
Shifting (Excl. GST)
(ii) IC & Pre-operative Expenses 9.98
(iii) Financing Cost 4.23
Estimated (iv) Interest During Construction 30.99
Capital Cost
(v) Estimated Project Cost [(i) to (iv)] 1042.83
with Break-
up under
(vi) Civil Construction Cost per km 21.38
major heads
Land Acquisition Cost including R&R &
of (vii) 340.94
Structures
expenditure
Other Cost (like Forest Clearance,
(viii) 6.50
Environmental Mitigation Measures etc.
(ix) Contingency @ 1% of (i) 9.98
(x) GST@18% of (i), (ii) & (iii) 182.13
(xi) Escalation during construction 60.00
(xii) O&M for 15 years including escalation 210.78
Page 11 of 24Total Capital Cost
(xiii) 1853.16
[(v)+(vii)+(viii)+(ix)+(x)+(xi)+(xii)]
Estimated BPC 1313.84
S.No. Description Present Status
1 Total Land Required (Ha)
302.57
2 Existing Land available
(Ha) 107.49
3 Addl. Land Required
(Ha) 195.08
4 Forest land (Ha)
Nil
Land
Acquisition 5 Private land (Ha) 154.11
Status
6 Govt. land (Ha)
40.97
7 3A Status Published for 185.59 Ha
(95.14%)
8 3D Status Published for 185.59 Ha
(95.14%)
9 3G Status Completed for 121.5 Ha
(62.3%)
10 3H Status Completed for 15.1 Ha (7.7%)
Category Value
PIRR 12.70%
EIRR 15%
Financial
Project NPV @ 12% discount rate Rs. 33.75 crore
Viability
Project NPV @WACC of 10.31% (Rs. in Rs. 81.50 crore
crore)
Minimum DSCR 1.59
Concession
Based on MCA for Hybrid Annuity Model
Agreement
Bidding
Bids will be evaluated on the basis of the lowest Bid Project Cost.
parameter
Bidding
Single Stage Two Envelope Process
process
2. The primary purpose of the project is to provide better connectivity between
Paramakudi and Ramanathapuram and also to decongest the existing 2 lane
paved shoulder road. The project road is a section of NH-49 (new NH-87) which
connects two important pilgrimage centers Madurai and Rameshwaram. The
Page 12 of 24Project Road passes through plain terrain and through settlements like
Paramakudi Near Ariyanandel, Sathirakudi, Achundanvayal, Ramanathapuram
and Perungulam. The proposed alignment with designed speed of 80 km/hr, will
connect five economic nodes.
3. The project, with a stretch of 46.665 km, is proposed for 4 lane development in on
Hybrid Annuity Mode. As per the revised proposal for the 46.665 km stretch,
approximately 25 kms is to be developed as greenfield due to the presence of
dense habitation along the existing alignment. Approximately 13 kms of the
existing road are proposed to be widened without demolishing existing road, while
approximately 8 kms are planned for complete reconstruction by demolishing the
existing road, which is inevitable due to approach locations of grade separators
and technical constrains. The financial assessment indicates a Project IRR project
is 12% and equity IRR of 15%. With respect to land acquisition, 3G of 62% land
has been achieved.
4. The project has been considered in the 120th PPPAC meeting held on 4th Feb
2025. The queries raised by the PPPAC and the response of MoRTH are provided
at Annexure II. The main issues raised by the 120th PPPAC was about the
dismantling of the existing road which was constructed in 2019. In its reply,
MoRTH said that in the initial proposal demolition of existing stretches of around
21 km was proposed as per the design requirements of IRC-SP-84-2019,
whereas 2-laning with paved shoulders constructed in 2019 was based on IRC-
SP-73-2007. Now, the proposal is modified by avoiding the demolition of existing
pavement to the possible extent and now only around 8 km stretch is coming
under re-construction in approaches of crossing structures against 21 km
proposed initially. As a result, Rs. 320 crore has been saved as compared to the
initial cost estimates.
5. After the detailed presentation, the Chair asked the PPPAC members for their
observations. DEA, NITI Aayog, DoE and DoLA supported the proposal and
stated that no further comments to offer.
6. The Chair made the following observations:
a) What is the typical lifespan of a 2-lane road?
b) The existing road was constructed in 2019, and the land acquisition process
for the proposed corridor also commenced in 2019. This indicates poor
planning on the part of the authority?
Page 13 of 24c) How will the traffic of the existing stretch will be managed during the
construction phase?
d) The possibility of developing the entire Madurai to Ramanathapuram corridor
on BOT(Toll) mode may be explored?
7. MoRTH submitted the following to the queries raised by the PPPAC Members: -
a) The typical lifespan of a two-lane road is 20 years.
b) In 2014 when the approval process of the existing road was started, the PCU
on the corridor was qualifying for 2-lane only (less than 15000 PCU).
However, the guideline changed in 2016 by which the 4-lane traffic trigger
point was changed to 10,000 PCU. When the project completed in 2019, the
traffic in the stretch was more than 10,000 PCU necessitating the
augmentation to 4-lane. Since the traffic has been triggered for 4-lane in
2019, the land acquisition process has been initiated in 2019 itself.
c) Traffic management during the construction period falls within the scope of
the concessionaire by providing diversions. It will be ensured that there will
be minimal disruption to regular traffic flow.
d) The short stretch of Paramakudi–Ramanathapuram is not financially viable on
its own in BOT (Toll) mode. However, the completed Madurai–Paramakudi
section, built under the EPC model, can be offered to the concessionaire
under the TOT model to enhance overall project viability. Based on financial
analysis and also considering the audit observation, the possibility of
developing combined Madurai–Ramanathapuram stretch on the BOT (Toll)
model shall be explored.
Recommendations:
8. After detailed deliberations, the PPPAC unanimously recommended the proposal
for 4 Laning of Parmakudi to Ramanathapuram Section of NH-87 from Km
80+360 to Km 127+025 (Design Chainage) in the state of Tamil Nadu on Hybrid
Annuity Mode for consideration of the competent authority for giving
administrative approval. The overall recommendation is subject to the following
specific recommendations.
a) The appraised Total Capital Cost is Rs. 1853.16 crore.
Page 14 of 24b) the possibility of developing combined Madurai–Ramanathapuram stretch on
the BOT (Toll) model shall be explored by the MoRTH.
c) MoRTH should adopt a forward-thinking approach for designing road projects,
considering future traffic demands, infrastructure needs, and potential
challenges. This would prevent the need for costly and premature
redevelopment while ensuring that road infrastructure remains sustainable
and efficient over its intended lifespan.
d) All approvals, such as forest clearance, tree cutting, permissions, etc., shall
be obtained by the NHAI well before the bid submission due date.
9. Revalidation of its recommendation by the PPPAC is not required for the following
post recommendation changes in the project costs/bid documents: -
a) Any change in the date/time period for any time-bound actions like appointed
date, financial close, construction period etc.
b) Non-substantial change in risk-allocation.
c) Any other changes/modification in the project proposal with the overall
objective of making project successful.
d) Further, MoRTH/ NHAI may decide whether the changes proposed post
recommendations of the project proposal by the PPPAC fall within the
threshold criteria as stated above. All such changes falling within the
threshold criteria shall be appraised at the level of Secretary (RTH)/ BoD of
NHAI as the case may be, without any further need of revalidation by the
PPPAC and shall proceed with the approval process accordingly.
***
Page 15 of 24Annexure-I
(Replies to observations to PPPAC committee for Capital Ring Road Project )
S. No. Comments of 120th PPPAC Reply by MoRTH
A. Project Rationale
1. This section passes through The mentioned proposal planned by State The mentioned
2 large cities, Bhubaneswar, proposal planned by State the same is yet to be started.
and Cuttack. The state
government had planned The alignment mentioned is planned from eastern side and
another proposal almost 2 will only bypass Bhubaneswar city. However, MoRTH
years back to decongest the proposal is from western side which is bypassing three Cities
city section at a much lower namely Bhubaneswar, Cuttack ft Khorda.
cost.
Also, The Heavy traffic from NH-55, NH-655, NH-57 ft SH-65
is not captured by State alignment. Further, the State Govt is
sharing the 50% LA cost of proposed Bhubaneswar Bypass.
As the state proposal is at very initial state, costing has not
been finalized for the same, as of now.
The per km per lane estimated civil construction cost of the
MoRTftH project is 6.98 Cr., which is within the normative
cost.
2. The availability of this The existing Khurda-Chandaka-Nanadakanan State Road is
alternate route, besides primarily 2 Lane having poor geometrics, which is already
existing Khurda-Chandaka- congested and may not solve the problem of traffic congesti
Nanadakanan road may on. Further, it ends before Cuttack ft Mahanadi bridge and
have implications on the may not solve the traffic congestion in Khurdha and Cuttack. It
likely traffic on the proposed may not have any implication on likely traffic of proposed
bypass. Bypass as the through traffic of NH-16 on either side of
proposed bypass shall get diverted before
Khordha and Cuttack respectively.
3. The estimated traffic on the Looking into the traffic growth, the widening of existing NH-16
proposed bypass ranges to 8 Lane with Service Road will be costly option with much
from about 20,000 to 24,400 higher cost including LA for additional 20m Land
PCU. Therefore, it would required. The said option has been examined and not found
solve only a part of the urban feasible and hence bypass has proposed.
congestion problem. The
rationale of a very high level The through Traffic on NH-16 shall be diverted on proposed
of congestion (1 lakh PCU Bypass. Thus, the proposed Bypass will ensure smooth travel
per day) in the city limits of through traffic and traffic bound towards western Odisha
appears to be due to the through NH-55, NH-655, NH- 57 & SH-65. Further diversion of
local traffic, and most likely through traffic through the proposed bypass shall result in
will remain partly addressed. substantial reduction in the traffic on existing NH-16 in urban
, area, which will partly de-congest the urban part.
The problem of local traffic not getting catered by the
proposed bypass and creating congestion will be addressed
by the road planned by State Govt. Further, on completion of
CRRR and roads planned by State Government, assessment
would be done and needful action shall be taken accordingly.
4. The urban congestion is The traffic assessment has been made on the basis of 24-
likely to be mostly during the hour OD survey. Further, the existing stretch (NH-16) is also
day period, and that too being tolled. The traffic assessment has been done
during peak hours. During considering both peak and off-peak hours and the estimated
Page 16 of 24off-peak hours and during traffic has been calculated accordingly.
nighttime, the through traffic
may still find it convenient
(shorter distance) to pass
through the 2 cities instead
of using the bypass road.
That may lead to lower than
estimated traffic on the
bypass road and lower toll
earnings for NHAI.
B. Tolling Strategy
1. There seems to have a The existing concession of BOT(Toll) road is up to 2037.
balance period of another 10
to 12 years.
2. The non-compete period in The tolling plan proposed during PPPAC scheduled earlier
the existing concession is has been revised and the revised tolling plan is at Annexure-
perhaps over. However, the 1. It is now proposed not to compensate the existing BoT
concessionaire will may have Concessionaire by sharing toll revenue. Under this plan, it is
to be compensated for a few unlikely that the concession period would be extended.
years (may be 5 to 7 years).
3. NHAI proposes to share a In earlier tolling plan, it was proposed to reduce the user fee
part of the toll collected on charged at BOT Plaza for Vehicle moving from Chennai to
the bypass road with the Kolkata and compensate the same to Concessionaire by the
BOT Concessionaire. Such Authority.
sharing is not envisaged in
the concession agreement Now, tolling strategy has been revised and it is now proposed
(CA). not to compensate the existing BoT Concessionaire by
4. Adopting a compensation sharing toll revenue. The Bypass has been proposed to be
method outside the CA will constructed on HAM mode, to be tolled by NHAI.
involve negotiation of the
CA. In order to avoid unfair charging of user fee (at Bandalo Toll
Plaza on NH-16) for length not travelled by the users in the
BOT project, it is now proposed to allow the user to travel
equivalent length free for both side movement on proposed
bypass. In other words, the toll Plaza of CRRR on Tangi side
shall be shifted in Ch. 78km (approx.) at suitable
location. Revised Tolling Plan attached at Annexure-
A).
5. The concession road will As clarified above, it is now proposed not to compensate the
have lower traffic (as a part existing BoT Concessionaire by sharing toll revenue.
of the traffic will use the
bypass road) resulting in Further, despite the use of proposed Bypass Road by through
lower wear & tear requiring traffic, the remaining as well as local traffic shall be using the
lower maintenance cost. existing road.
Yet, the concessionaire is
proposed to be There may not be any significant difference of maintenance
compensated as if the cost. The periodic renewal has to be done as per IRC
diverted traffic was also on Guidelines.
the concession road.
6. A clarity is also needed in As per revised Tolling Plan, there is no requirement of
respect of the appropriate negotiation with Existing BoT Concessionaire
forum and the competent
authority for appraising and
approving the negotiated
concession.
7. In view of the sharing of the The viability of the project has already been considered
toll revenue, the economic taking into account the proposed integrated tolling
Page 17 of 24and financial viability of the mechanism.
project may also be lower.
The viability should be
reworked based on net toll
to NHAI.
Annexure-A
Revised Tolling Strategy
The map showing the tolling strategy is at attached.
Case 1: - For traffic moving from Kolkata to Chennai using Bhubaneswar Bypass: - Car
crossing point P (BOT toll Plaza at Bandola) will be paying full charges at the BOT toll
plaza and the vehicles coming on bypass shall be allow to travel equivalent length (33
Km) free upto point X-X and charges will be applicable for actual distance travelled
beyond point X-X till it exits from Bhubaneswar Bypass.
Case 2: - Vehicle moving from Chennai to Kolkata using Capital Region Ring Road
(Bhubaneswar Bypass).
1 User entering Bhubaneswar Bypass at C (4 Km before next toll Plaza i.e., Gudipada
Toll Plaza) and travelling Length upto & beyond X-X will be paying toll free up to X-X
i.e., 77.630 Km approx.
2 User entering Bhubaneswar Bypass at C (4 Km before next toll Plaza i.e., Gudipada
Toll Plaza) and exiting from intermediate access before X-X will have to pay for
actual length travelled.
Page 18 of 24Page 19 of 24Annexure-II
Replies to observations to PPPAC committee for Paramakudi to Ramanathapuram
Project
Observations of 120th PPPAC Compliance/ Reply by MoRTH
a. Project rationale: The proposal seeks to 2-lane with paved shoulder is the basic and bare
demolish the road section completed barely 6 minimum facilities for National Highway and as such no
years back. traffic parameter exists for providing 2-lane highway and
I. The upgradation of this section to 2-lanes no traffic assumption was made for this project that time.
with paved shoulders was completed in The current traffic in the project highway is 12,700
2019. MoRTH may review whether the PCU/day, therefore the existing road cannot handle the
current traffic far exceed the assumptions traffic for another 7 to 8 years with acceptable service
in that project to require 4-laning now by quality in light of changing socio-economic conditions in
demolishing that work. the country and in order to ensure safe and comfortable
II. MoRTH may examine if the existing road mobility of road users along with reduction in road
can handle the traffic for another 7 to 8 accidents being prime concern for everyone. As per the
years with acceptable service quality. The 2-lane manual (IRC-SP-73-2018) when the design
current traffic on this section appears to service volume of two-lane highway exceeds 10,000
suggest that. PCU/day, the congestion increases necessitating its
upgradation to 4-lane. Therefore 4-lane of the stretch is
required.
In the initial proposal demolition of existing stretches in
around 21 Km was proposed as per the design
requirements of IRC-SP-84-2019, whereas the 2-laning
with paved shoulders (constructed 6 years back) was
based on IRC-SP-73-2007. During appraisal by PPPAC
on 04.02.2025, it was suggested to review and
emphasis was given to utilize the existing highway to the
possible extent. Accordingly, the proposal was modified
by avoiding the demolition of existing pavement to the
possible extent.
III. The land has been acquired (as per the The land acquisition was done in the project as the
proposal) and tenders have been called (as project was earlier included under Bharatmala Scheme
per newspaper reports), even before approval and majority of land have been acquired between 2018-
of the project by the competent authority. 2023(Refer table below). However, no land acquisition
MoRTH may examine if that is the appropriate has been done after MoRTH OM dated 23.11.2023
way of committing and using public funds. (regarding non creation of liability under Bharatmala
Pariyojana Phase-I). Tenders are normally invited after
Page 20 of 24Observations of 120th PPPAC Compliance/ Reply by MoRTH
the appraisal of the project by PATSC in NHAI so that
the bidders get sufficient time to get familiar of the
project; so that they can correctly design and
competitive quotes may be submitted. Accordingly, the
bids were invited in anticipation of approval of the
project. However, it is submitted that tenders will be
received only after getting its approval and sanction of
project from Competent Authority.
3A published (185.59 Ha) 3D published (185.59
Ha)
Date Area (Ha) Date Area (Ha)
17.04.2018 124.74 09.04.2019 124.74
10.05.2018 9.15 09.05.2019 9.15
23.08.2022 6.17 24.11.2022 6.17
05.01.2023 45.53 17.04.2023 45.53
b. Project design:
I. As the land has been acquired, it may be Yes, as the majority of land has already been acquired
too late to consider any alternate design. as brought out above. 2-lane with paved shoulder is the
Nevertheless, MoRTH may verify if the basic and bare minimum facilities for National Highway
option of building a new 2-lane road and as such no traffic parameter exists for providing the
abutting the existing 2-lanes was same and also the same is done within the available
considered, instead of designing for land without much improving the existing geometry and
demolition of the road completed 6 years changing the alignments. Earlier, complete
back. reconstruction of existing highway was proposed as the
2-lane highway constructed 6 years ago was based on
standards of IRC:SP:73-2007, however the IRC
specification got upgraded and the submitted proposal
was based on IRC SP: 84-2019 wherein the geometric
standards got upgraded, due to which it was not
possible to accommodate existing 2-lane carriageway in
4-lane design.
As brought above in response to the project rationale,
after the deliberation and suggestion during appraisal by
PPPAC on 04.02.2025, the proposal was modified
considering the suggested option of building a new 2-
lane road abutting the existing 2-lanes with adopting the
design parameters as per existing vertical profile to the
Page 21 of 24Observations of 120th PPPAC Compliance/ Reply by MoRTH
possible extent. Accordingly, around 13 Km (out of
21Km) existing stretch has been utilized and now the
reconstruction length is proposed only in around 8 Km
which is inevitable at approach locations of grade
separators.
II. A much higher embankment of 2.5 meter The embankment height varies from project to project.
throughout the project length has been 1m embankment height in Normative calculations is
planned instead of the normative 1 meter. taken as an assumption for calculation purpose only as
MoRTH may examine if the project section per MoRTH Circular dated 19.01.2022. However, the
passes through a flood-prone area requiring same being dynamic in nature changes as per design
the higher embankment requirement. The normal construction, the embankment
height is also decided in such a way that the bottom of
the sub-grade is kept 1m above the HFL/NGL.
Therefore, the minimum height of embankment including
sub-grade is around 1.5m. In the instant project, there
are 9 Nos. of VUPs, 3 Nos. of LVUPs & 5 Nos. of
SVUPs provisions in the project. The minimum
clearances for these structures are 4-5m which causes
increase in the height of embankments in its
approaches.
III. The above aspect becomes even more As in the instant project the lead of Earth is around 45km
prominent as the lead distance for the required (being higher due to non-availability of suitable earth in
earth is large at 45 km. vicinity), as brought out above, after deliberation in
PPPAC meeting on 04.02.2025 the proposal has been
modified to optimize the quantities of earth and
accordingly cost have been reduced considerably.
IV. A recently awarded (March 2024) package The per km cost in earlier submission was Rs. 32.09
on Chennai-Tirupati NH has entailed civil Cr/km as it was designed based on currently prevailing
construction cost of Rs. 22.71 Cr./km. The civil IRC specifications. However, in the revised proposal, the
cost of the proposal is almost 50% higher at per km cost is now Rs. 21.4Cr/km arrived based on
Rs. 32.09 Cr/km. MoRTH may examine if the adopting the existing vertical profile to the possible
proposal is over-designed requiring higher extent for utilization of existing highway recently
cost. completed (6 years ago), which is now comparable
(lower) to recently awarded package on Chennai-
Tirupati (March 2024- Rs. 22.71 Cr./km). Both the
projects are widening projects of 2 to 4-lane.
Page 22 of 24Annexure-III
Comments on MoRTH Proposal
1. Development of 4 Laning of Rajapalayam to Shenkottai Section of NH-744
from Km 71+600 to Km 139+900 (Design Chainage) in Tamil Nadu on Hybrid
Annuity Mode (Project Length-68.3Km)
a. Who is the competent authority to approve new NH alignment? What will
be the status of the existing alignment after the construction of the
greenfield alignment?
b. The proposed project is part of the Madurai–Kollam corridor and the
Shenkottai–Kollam stretch currently remains a 2-lane road. As the
corridor from Shenkottai towards Kollam passes through Western Ghats
and involves construction of tunnels for which obtaining clearance is tough
task and uncertain.
c. What is the feasibility of constructing proposed tunnels in the Shenkottai–
Kollam section?
d. As getting the environmental clearances are uncertain, what is the rational
for the proposed project of construction of 4 Laning of Rajapalayam to
Shenkottai?
e. How does the Rajapalayam–Shenkottai project align with NH development
goals such as Bharatmala Pariyojana
f. What is the current status of land acquisition and clearances for the entire
corridor?
Page 23 of 24Annexure-IV
List of the participants of the 123th meeting of the PPPAC
a) Department of Economic Affairs, Ministry of Finance
1. Shri Ajay Seth, Secretary, EA- In Chair
2. Ms. Anuradha Thakur, OSD(EA)
3. Shri Baldeo Purushartha, JS (ISD)
4. Ms. Arya Balan Kumari, Joint Director
5. Ms. Anmol Waraich, AD (PIU)
6. Shri Rajender Singh, SO (PIU)
7. Shri Manjeet Yadav, ASO
b) Department of Expenditure
1. Shri Ranganath Audam, Deputy Director
c) NITI Aayog
1. Shri. Partha Reddy, Programme Director
d) Department of Legal Affairs
1. Shri Kasibhatla, Deputy Legal Adviser
e) Ministry of Road Transport and Highways
1. Shri V Umashankar, Secretary (RTH)
2. Shri Puneet Agarwal AS&FA
3. Shri Alok Deepankar, Member
4. Shri Harish Sharma, CGM
5. Shri Anil Choudhary, Member
6. Shri Wathore, CGM
7. Shri Manoj Kumar, Ministry
8. Shri Vinay Kumar, AS(H)
9. Shri Vinod Choudhary, Dy Manager
10. Shri Surya Manivannan, AT Kearney
f) National Highway Authority of India (NHAI)
1. Shri Santosh Kumar Yadav, Chairman
2. Shri KM Sharma, NHAI
3. Shri K Venkatramana, Member (PPP)
***
Page 24 of 24