**Executive Summary**
This document is a notification from the Tamil Nadu Government Gazette regarding the sanction of a new 110KV Single Circuit (SC) transmission line by TANTRANSCO to meet increasing power demands. The line will run from Thalavaipettai 110KV SS to Kugalur 110KV SS. Interested parties have one month from the date of publication to submit representations.
**Key Points / Main Content**
* **Project Sanction:**
* TANTRANSCO has sanctioned the erection of a transmission line.
* **Line Details:**
* Erection of a 110KV SC line on a Double Circuit (DC) tower with Panther conductor.
* The line will run from Thalavaipettai 110KV SS to Kugalur 110KV SS.
* The route length is 14.145 Km.
* **Route:**
* The line passes through the following villages:
* Oricheri
* Appakudal
* Perunthaliyur
* P.Mettupalayam
* Odathurai
* Kugalur (Erode District)
* The list of villages is tentative and not exhaustive.
* **Authority:**
* TANTRANSCO Proceeding No. 55, dated 15-04-2015
* **Representation Period:**
* Interested parties have one month from the date of publication to make representations as per the Electricity Act 2003.
**Impact Analysis**
**Villagers in Affected Areas**
* **Impact:** Villagers along the transmission line route may be affected by the construction and presence of the line.
* **Action Required:** Any interested person can make representation on the above schemes within 1 month from the date of issue of this publication to the undersigned as per the Electricity Act 2003.
**TANTRANSCO**
* **Impact:** The project requires TANTRANSCO to construct and maintain the new transmission line.
* **Action Required:** Proceed with the erection of the new 110KV SC line.
Key Entities Referenced
Tamil Nadu Government Gazette: Official publication containing notifications issued by the Tamil Nadu Government.
TANTRANSCO: Tamil Nadu Transmission Corporation Limited, the entity responsible for the sanctioned power transmission line erection.
Electricity Act 2003: The act under which any person can make representation on the schemes within 1 month of the date of issue of this publication.
Coimbatore: Location of the General Construction Circle of TANTRANSCO, responsible for the erection of transmission lines.