On October 9, 2025, Union Minister Ashwini Vaishnaw visited key construction sites of the Mumbai-Ahmedabad High Speed Rail (Bullet Train) project in Sabarmati, Ahmedabad. The Minister reviewed ongoing works at the Sabarmati High Speed Rail (HSR) Station, the HSR Multimodal Transport Hub, and the Rolling Stock Depot.
Sabarmati HSR Station: The terminal station of the Mumbai-Ahmedabad Bullet Train corridor is inspired by Mahatma Gandhi's Charkha at Sabarmati Ashram. The station is being built in a 45,000 sq. m. area.
Sabarmati HSR Multimodal Hub: The hub includes office spaces, hotel facilities, and passenger amenities such as retail outlets and restaurants. It is equipped with parking for about 1,200 vehicles.
Sabarmati HSR Rolling Stock Depot: The hub is spread over 84 hectares.
Mumbai-Ahmedabad Bullet Train project progress: Out of 508 km, 325 km of viaduct and 400 km of pier works have been completed. 17 river bridges, 5 PSC bridges, and 10 steel bridges have also been completed. 216 km of track bed has been laid. Over 4 lakh noise barriers have been installed along the track bed.
Contact Information:
Dharmendra Tewari/ Dr. Nayan Solanki/ Manik Sharma
Release ID: 2177098
Key Entities Referenced
Mumbai-Ahmedabad High Speed Rail (Bullet Train) project: A high-speed rail project between Mumbai and Ahmedabad.
Sabarmati HSR Station: The terminal station of the Mumbai-Ahmedabad Bullet Train corridor.
Sabarmati Ashram: The location of the design inspiration for the Sabarmati HSR station.
Sabarmati HSR Multimodal Hub: A state-of-the-art facility ensuring smooth connectivity between the HSR station, railway station, Metro, and BRTS.
Ministry of Railways
Union Minister Ashwini Vaishnaw Visits Key
Construction Sites of Mumbai–Ahmedabad High
Speed Rail Bullet Train Projects in Ahmedabad
Sabarmati HSR Station Design Inspired by Mahatma
Gandhi’s Iconic Charkha at Sabarmati Ashram
Sabarmati HSR Multimodal Hub Designed to Ensure
Seamless Connectivity Between Bullet Train, Rail,
Metro, and BRTS Networks
Sabarmati HSR Depot — An 84-Hectare World-
Class Facility for Light and Heavy Maintenance of
Train Sets
Posted On: 09 OCT 2025 10:06PM by PIB Delhi
Union Minister for Railways, Information & Broadcasting, and Electronics & Information Technology, Shri
Ashwini Vaishnaw visited key construction sites of the Mumbai–Ahmedabad High Speed Rail (Bullet Train)
project in Sabarmati, Ahmedabad today. The Minister reviewed ongoing works at the Sabarmati High Speed
Rail (HSR) Station, the HSR Multimodal Transport Hub, and the Rolling Stock Depot.
Sabarmati HSR Station: The terminal station of the Mumbai–Ahmedabad Bullet Train corridor is inspired by
Mahatma Gandhi’s Charkha at Sabarmati Ashram. The station is being built in a 45,000 sq. m. area.
Structural work up to the track floor has been completed. Interior, and Mechanical, Electrical, and Plumbing
(MEP) works are in progress. The station will offer world-class passenger facilities—waiting lounges, rest
rooms, nursery, retail and commercial spaces—and will be seamlessly connected to existing railway, metro,
and BRTS networks.
Sabarmati HSR Multimodal Hub: It has been designed as a state-of-the-art facility ensuring smooth
connectivity between the HSR station, Sabarmati railway station, Metro, and BRTS.
The front wall of the building depicts a stainless-steel mural of the Dandi March, honouring Sabarmati’s
historic legacy. The hub includes office spaces, hotel facilities, and passenger amenities such as retail outlets
and restaurants. It is equipped with parking for about 1,200 vehicles. The hub also features extensive green
infrastructure including solar panels, landscaped terraces, and energy-efficient systems.Sabarmati HSR Rolling Stock Depot: It is the largest of three depots being constructed under the project. The
hub is spread over 84 hectares. The hub will support light and heavy maintenance of trainsets with inspection,
stabling, and workshop lines.
Construction of the administration building, inspection sheds, and infrastructure for utilities and tracks is
progressing rapidly. The depot will follow environmental sustainability norms. It will feature rainwater
harvesting, solar provisions and zero liquid discharge treatment systems.
Mumbai-Ahmedabad Bullet Train project progress: Out of 508 km, 325 km of viaduct and 400 km of pier
works have been completed. 17 river bridges, 5 PSC bridges, and 10 steel bridges have also been completed.
216 km of track bed has been laid. Over 4 lakh noise barriers have been installed along the track bed. Work on
all stations in Gujarat is at an advanced stage. Rapid progress is being made at the Mumbai underground
section.
The Railway Minister appreciated the pace of work and emphasized that the project is on track for timely
completion. He remarked that the first bullet train project of the country represents PM Shri Narendra Modi
Ji’s vision for world-class infrastructure and a ‘Viksit Bharat at 2047’.
*****