The Ministry of Railways is undertaking significant infrastructure upgrades totaling ₹1,011 crore at five key stations – Nashik Road, Devlali, Odha, Kherwadi, and Kasbe Sukene – in preparation for the Nashik-Trimbakeshwar Simhastha 2027. Union Railway Minister Ashwini Vaishnaw and MoS Ravneet Singh Bittu reviewed the plans, emphasizing the adoption of best practices from the Maha Kumbh 2025.
The upgrades aim to enhance passenger amenities and streamline pilgrim movement, anticipating a footfall of over 3 crore pilgrims. Infrastructure developments include platform extensions, new foot-over-bridges (FOBs), stabling lines, advanced coach and wagon examination facilities, and yard remodeling. Passenger amenities such as cover-over platforms, water tanks, toilets, and improved Passenger Information Systems are also planned.
Specifically, Nashik Road station will see a bidirectional Platform 4, extended Platform 1, and a new 12m wide FOB. Devlali will gain additional platforms, two 6m wide FOBs, and a sewage treatment plant. Odha will feature an island platform with loop lines and four 6m wide FOBs. Kherwadi will have a new down platform and two 6m wide FOBs, while Kasbe Sukene will have extended platforms and two 6m wide FOBs.
Railways plans to run special trains, including long-distance and MEMU services, connecting Nashik to major stations across India, along with a special circuit train linking the Trimbakeshwar, Grishneshwar, and Omkareshwar Jyotirlingas. Crowd management will be facilitated through large holding areas at stations and a centralized command and control center equipped with CCTV cameras and AI-powered monitoring.
Out of 65 proposed works, estimates for 33 have already been sanctioned. Continuous coordination between Railways and the Maharashtra state government is ongoing, with a joint review planned with Chief Minister Devendra Fadnavis.
Key Entities Referenced
Ashwini Vaishnaw: Union Railway Minister, reviewing the NashikTrimbakeshwar Simhastha 2027 Rail Plans.
Ravneet Singh Bittu: MoS (Minister of State), reviewing the NashikTrimbakeshwar Simhastha 2027 Rail Plans.
NashikTrimbakeshwar Simhastha 2027: A religious event for which railway infrastructure upgrades are planned.
Nashik Road: One of the 5 key railway stations near the Mela area, undergoing upgrades.
Devlali: One of the 5 key railway stations near the Mela area, undergoing upgrades.
Maha Kumbh 2025: A religious gathering event, used as a reference for best practices in managing the NashikTrimbakeshwar Simhastha 2027.
Maharashtra: The State government coordinating with the Ministry of Railways for the Simhastha 2027 preparations.
Devendra Fadnavis: Chief Minister of Maharashtra, expected to jointly review the progress of Simhastha preparations.
Ministry of Railways
Union Railway Minister Ashwini Vaishnaw and MoS
Ravneet Singh Bittu Review Nashik-Trimbakeshwar
Simhastha 2027 Rail Plans
1,011 Cr Infra Push at 5 Key Stations — Nashik,
Devlali, Odha, Kherwadi & Kasbe Sukene for Major
Upgrade in Passenger Amenities during Simhastha
2027
Railways to Implement AI-Powered Monitoring and
Control for Smooth Pilgrim Movement
Emphasis on Adopting Best Practices From Maha
Kumbh 2025
Posted On: 25 JUL 2025 5:09PM by PIB Delhi
As in the case of Prayagraj Maha Kumbh, the Ministry of Railways has started advance preparations for
Nashik-Trimbakeshwar Simhastha to be held in 2027.
The Union Railway Minister Shri Ashwini Vaishnaw and MoS Shri Ravneet Singh Bittu took an extensive
review of the plans. GM Central Railway, DRM Bhusaval division, and other officials briefed the Ministers
and the Railway Board on its planning and execution status.Strengthening connectivity to the Mela area: Railways will undertake comprehensive infrastructure and
operational upgrade for Simhastha. It has prepared an integrated plan to expand the capacity of stations across
the region. The goal is to ensure streamlined passenger movement during the Nashik Simhastha 2027.
The Railway Minister urged the officials to adopt best practices which emerged from the Maha Kumbh 2025
experience. The Minister advised the officials to develop adequate facilities in all nearby stations of Nashik.
He emphasised on the need to have sufficient stabling capacity for seamless transport.
Officials informed that the passenger traffic will be managed at 5 key stations which are within the vicinity of
the Mela area. These are Nashik Road, Devlali, Odha, Kherwadi and Kasbe Sukene stations.
Upgrading infrastructure, enhancing passenger amenities: The railway officials shared the details of
infrastructure works and passenger amenities proposed at each of the 5 identified stations. The works planned
at these stations are projected to cost over ₹1,011 crore.
Nashik Road: Platform-4 will be made bi-directional. Platform-1 will be extended to accommodate 24-coach
trains. A 12m wide FOB will be constructed. Goods shed is proposed to be used as a holding area.Stabling lines are being developed at Nashik Road. The platform surface, boundary wall, and Mela Tower will
also be upgraded.
Devlali: Additional platforms will be constructed. Two 6m wide FOBs will be built. Advanced coach and
wagon examination facilities (with 3 stabling lines & 2 pit lines) are also planned to be built. A Sewage
Treatment Plant is proposed to be set up.
Odha: An island platform with loop lines will be developed. Four 6m wide FOBs will be built. Long-haul
loop line and yard remodeling are also planned. 5 stabling lines are proposed to be built.
Kherwadi: A new down platform will be constructed. Two 6m wide FOBs will be built. Yard remodelling is
also proposed to be undertaken.
Kasbe-Sukene: Platforms will be extended. Two 6m wide FOBs will be built. A common dispatch facility
will be set up.In addition to the above, various passenger amenities are planned to be developed at all 5 stations. These
include Cover Over Platforms, water tanks, new toilets, and water-proof holding areas. The circulating areas,
pathways, entry/exit roads, and Passenger Information Systems are also planned to be upgraded.
Railways is on track to execute the above works well within the timeframe of 2 years. Out of the total 65
proposed works, estimates of 33 have already been sanctioned.
Special trains for Simhastha: The anticipated footfall is over 3 crore pilgrims, nearly 50 times that of the
Simhastha 2015. With this in mind, Railways is planning to run a significantly higher number of special
trains.
Long-distance specials and short-distance MEMU services will be provided to pilgrims travelling from across
India. These will connect Nashik to important stations including Kamakhya, Howrah, Patna, Delhi, Jaipur,
Bikaner, Mumbai, Pune, Nagpur and Nanded.
A round-trip special circuit train will also run. It will connect the 3 Jyotirlingas - Trimbakeshwar,
Grishneshwar, and Omkareshwar.
Ensuring efficient crowd management: Large holding areas are being developed at each major station to
ensure smooth movement of pilgrims. A centralized command and control centre is proposed to be set up. It
will be equipped with CCTV cameras for effective monitoring and AI tools for predictive scheduling.
Joint meeting with CM Maharastra: Railway officials are continuously in touch with the state government
officials. There is close coordination between Railways and Maharashtra state government. In the coming
months, a joint review of progress will be held with Maharashtra CM Shri Devendra Fadnavis.
*****