Executive Summary & Key Takeaways
Executive Summary:
These notifications declare the Government of India's acquisition of the Right of User for land in Odisha for laying a natural gas pipeline by GAIL India Limited, specifically the Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) Spur Pipeline. The notifications, S.O. 5188(E) and S.O. 5189(E), follow prior notifications and consideration of public objections. The right of user is vested in GAIL India Limited.
Key Points / Main Content:
Acquisition of Right of User:
* The Government of India declares the acquisition of the Right of User in specified lands.
* The acquisition is for laying a pipeline for transporting natural gas.
* The pipeline is part of the Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) Spur Pipeline project.
* The project is in the state of Odisha.
Vesting of Rights:
* The Right of User in the land vests in GAIL India Limited, not the Government of India.
* This vesting is effective from the date of publication of the declaration.
* The land is free from all encumbrances.
Land Details:
* The specific land plots affected are detailed in the Schedule appended to each notification, including survey numbers and area measurements.
* S.O. 5188(E) concerns land in the Bhadrak district, specifically in Chandbali Tehsil, Nuagan, and Talabandha villages.
* S.O. 5189(E) concerns land in the Jajpur district, specifically in Danagadi Tehsil, Daniabar village.
Procedural Context:
* The declarations follow earlier notifications S.O. No. 1172(E) dated 12.03.2018 and S.O. No. 2123(E) dated 14.06.2017.
* Public objections to the pipeline laying were considered and disposed of by the Competent Authority.
* The Competent Authority submitted a report to the Government of India, which was considered before the declaration.
Impact Analysis:
GAIL India Limited:
* Impact: GAIL India Limited receives the Right of User for the specified lands to lay the pipeline and is responsible for the pipeline project.
* Action Required: Proceed with laying the pipeline according to the project plan, ensuring compliance with all applicable regulations.
Landowners/Public:
* Impact: Landowners lose certain rights to the specified land areas, but are presumably entitled to compensation as per the Act. The public has already had the opportunity to raise objections.
* Action Required: Await further communication regarding compensation and any necessary cooperation with GAIL India Limited for the pipeline laying process.
Government of India:
* Impact: The Government facilitates the infrastructure project by acquiring the necessary rights and transferring them to GAIL.
* Action Required: Ensure the project progresses according to regulations and address any disputes or issues that may arise.
Key Entities Referenced
Petroleum and Minerals Pipeline Acquisition of Right of User in Land Act, 1962 : A law enacted in 1962, providing the legal framework for the acquisition of land rights for petroleum and mineral pipelines.
GAIL India Limited : The company responsible for laying the pipeline, as specified in the notification.
Jagdishpur-Haldia-Bokaro-Dhamra Pipeline : A pipeline project for the transportation of natural gas.
JHBDPL Spur Pipeline : Spur pipeline of Jagdishpur-Haldia-Bokaro-Dhamra Pipeline
Dhamra Angul Pipeline : A section of the Jagdishpur-Haldia-Bokaro-Dhamra Pipeline project.
Odisha : The Indian state where the pipeline is being laid.
Bhadrak : A district in Odisha, India where land acquisition is taking place for the pipeline project.
Jajpur : A district in Odisha, India where land acquisition is taking place for the pipeline project.
See Full Document Text
jftLVªh laö Mhö ,yö&33004@99 REGD. NO. D. L.-33004/99
vlk/kj.k
EXTRAORDINARY
Hkkx II—[k.M 3—mi&[k.M (ii)
PART II—Section 3—Sub-section (ii)
izkf/dkj ls izdkf'kr
PUBLISHED BY AUTHORITY
la- 4003] ubZ fnYyh] eaxyokj] vDrwcj 9] 2018@vkf'ou 17] 1940
No. 4003] NEW DELHI, TUESDAY, OCTOBER 9, 2018/ASVINA 17, 1940
पपपप(cid:3)(cid:3)ेे(cid:3)(cid:3)ेे ोोोोििििललललययययमममम औऔऔऔरररर (cid:9)(cid:9)(cid:9)(cid:9)ााााककककृृृृििििततततकककक गगगगससैैससैै ममममं(cid:15)ं(cid:15)ं(cid:15)ं(cid:15)ााााललललयययय
अअअअििििधधधधससससचचूूचचूू ननननाााा
नई (cid:1)द(cid:3)ली, 1 अ(cid:7) टूबर, 2018
ककककाााा....आआआआ.... 5555111188888888((((अअअअ))))....————भारत सरकार ने पे(cid:13)ोिलयम और खिनज पाइपलाइन (भूिम म(cid:18) उपयोग के अिधकार का अज(cid:20)न) अिधिनयम,
1962 (1962 का 50) (िजसे इसम(cid:18) इसके प(cid:24)ात उ(cid:28) अिधिनयम कहा गया ह)ै क(cid:30) धारा 3 क(cid:30) उपधारा (1) के अधीन जारी भारत सरकार
के पे(cid:13)ोिलयम और (cid:31)ाकृितक गैस मं"ालय क(cid:30) अिधसूचना का.आ. 1172 (अ) तारीख 12.03.2018 जो भारत के असाधारण राजप"
तारीख 16.03.2018 मे (cid:31)किशत क(cid:30) गई थी, +ारा उस अिधसूचना से संल, अनुसूची म(cid:18) िविन.द/ भूिम म(cid:18) गेल (इि0डया) िलिमटेड +ारा
ओिडशा रा3य म(cid:18) जगदीशपुर-हि(cid:3)दया-बोकारो-धामरा पाइपykbZu (जे एच बी डी पी एल) एवं 5पर ikbiykbZu के मा6यम से (cid:31)ाकृितक गैस
के प7रवहन के िलए ikbiykbZu िबछाने के (cid:31)योजन के िलए उपयोग के अिधकार का अज(cid:20)न करने के अपने आशय क(cid:30) घोषणा क(cid:30) थी;
और उ(cid:28) राजपि"त अिधसूचना क(cid:30) (cid:31)ितयां जनता को उपल8ध करा दी गई थी;
और स:म (cid:31)ािधकारी ने जनता से (cid:31)ा; आ:ेप= को परी:ण के उपरांत िनपटान कर (cid:1)दया ह;ै
और, स:म (cid:31)ािधकारी ने, उ(cid:28) अिधिनयम क(cid:30) धारा 6 क(cid:30) उप-धारा (1) के अधीन भारत सरकार को अपनी 7रपोट (cid:20)द ेदी ह;ै
और भारत सरकार ने, उ(cid:28) 7रपोट(cid:20) पर िवचार करने के प(cid:24)ात और यह संतु/ हो जाने पर (cid:1)क उ(cid:28) भूिम ikbiykbZu िबछाने के
िलए अपेि:त ह,ै उसम(cid:18) उपयोग के अिधकार का अज(cid:20)न करने का िविन(cid:24)य (cid:1)कया ह;ै
अतः अब, भारत सरकार, उ(cid:28) अिधिनयम क(cid:30) धारा 6 क(cid:30) उपधारा (1) +ारा (cid:31)द@A शि(cid:28)य= का (cid:31)योग करते Bय,े यह घोषणा
करती ह ै (cid:1)क इस अिधसूचना से संल, अनुसूची म(cid:18) िविन.द/ भूिम म(cid:18) ikbiykbZu िबछाने के िलए उपयोग के अिधकार का अज(cid:20)न (cid:1)कया
जाता ह;ै
और भारत सरकार, उ(cid:28) अिधिनयम (cid:1)क धारा 6 (cid:1)क उपधारा (4) +ारा (cid:31)दA शि(cid:28)य= का (cid:31)योग करते Bय,े िनदCश दते ी ह ै (cid:1)क
पाइपलाइन(cid:18) िबछाने के िलए भूिम म(cid:18) उपयोग का अिधकार, इस घोषणा के (cid:31)काशन क(cid:30) तारीख को, भारत सरकार म(cid:18) िनिहत होने के
बजाए, सभी िव(cid:3)लंगम= से मु(cid:28), गेल (इि0डया) िलिमटेड म(cid:18) िनिहत होगा।
5921 GI/2018 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
अअअअननननुसुसुसुसचचूूचचूू ीीीी
जगदीशपुर-हि(cid:3)दया-बोकारो-धामरा गैस पाइपलाइन और 5पर पाइपलाइन (cid:31)ोज(cid:7)े ट धामरा - अनगुल पाइपलाइन (सेकशन - 2A )
रा(cid:3)य - ओिड़शा
खे(cid:14)फल
िजला तहसील गावँ सव(cid:8) नबं र
ह(cid:18)े टर आर वग(cid:21)मीटर
1 2 3 4 5
भ(cid:2)ख चांदबाली नुआगा ँ 568 00 03 43
560 00 07 93
550 00 08 13
549 00 04 41
548 00 00 38
556 00 11 62
555 00 00 23
557 00 02 35
545 00 20 30
544 00 03 69
540 00 05 06
541 00 02 84
542 00 06 71
489 00 02 48
488 00 02 43
487 00 02 93
384 00 12 49
385 00 14 43
386 00 10 52
387 00 10 55
394 00 00 76
389 00 19 80
390 00 00 20
375 00 00 00
366 00 03 15
365 00 10 57
364 00 05 12
357 00 15 77¹Hkkx IIµ[k.M 3(ii)º Hkkjr dk jkti=k % vlk/kj.k 3
363 00 01 40
358 00 04 47
355 00 04 56
226 00 16 72
224 00 04 06
131 00 12 81
193 00 13 91
192 00 14 38
194 00 02 64
191 00 02 25
190 00 10 40
185 00 07 94
171 00 08 09
184 00 03 63
172 00 12 20
173 00 01 82
168 00 06 99
167 00 20 74
166 00 01 75
174 00 00 43
164 00 03 24
165 00 18 18
80 00 18 36
78 00 08 04
79 00 03 44
21 00 15 86
20 00 16 56
19 00 00 12
22 00 03 07
18 00 16 82
24 00 03 71
25 00 01 61
27 00 00 364 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
भ(cid:2)ख चांदबाली तलबंध 1056 00 04 16
1057 00 04 82
1054 00 01 05
1058 00 08 31
1053 00 07 97
1061 00 00 27
1059 00 09 26
1052 00 10 35
1053 00 00 20
1051 00 03 45
1050 00 05 73
1048 00 09 42
1053 00 00 07
1047 00 12 91
1046 00 18 98
1039 00 00 06
1041 00 28 76
1042 00 00 56
1123 00 18 34
1146 00 01 30
1124 00 06 03
1146 00 10 85
1129 00 00 03
1145 00 03 36
1129 00 00 09
1144 00 01 67
1147 00 00 22
1143 00 17 29
1142 00 01 08
1141 00 08 01
1140 00 08 64
1158 00 00 17
1159 00 01 14¹Hkkx IIµ[k.M 3(ii)º Hkkjr dk jkti=k % vlk/kj.k 5
1160 00 00 94
1169 00 17 81
1170 00 09 91
1234 00 08 23
1230 00 00 01
1236 00 00 16
1234 00 00 12
1235 00 12 04
1229 00 02 49
1263 00 00 75
1262 00 00 11
1264 00 07 89
1265 00 02 69
1266 00 04 35
1260 00 00 82
1259 00 09 52
1271 00 27 47
1341 00 23 76
1334 00 05 03
1331 00 04 33
1333 00 05 74
1320 00 06 17
1344 00 03 46
1316 00 23 38
1317 00 00 02
1352 00 02 78
1315 00 04 75
1314 00 09 03
1677 00 00 14
1675 00 04 45
1676 00 01 49
1691 00 05 38
1692 00 08 026 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
1693 00 04 82
1694 00 02 29
1689 00 00 75
1709 00 07 41
1695 00 00 24
1696 00 00 63
1707 00 02 67
1708 00 04 75
1710 00 13 97
1744 00 16 09
1712 00 03 87
1721 00 00 41
1720 00 02 08
1719 00 06 78
1714 00 00 07
1718 00 03 34
1717 00 02 10
1716 00 08 24
1715 00 08 97
1714 00 03 15
1728 00 00 01
1729 00 05 92
1634 00 01 73
1635 00 00 51
1633 00 02 82
1630 00 04 52
1538 00 00 83
1552 00 05 02
1539 00 00 05
1551 00 03 75
1553 00 01 30
1556 00 09 81
1549 00 00 86¹Hkkx IIµ[k.M 3(ii)º Hkkjr dk jkti=k % vlk/kj.k 7
1555 00 00 79
1562 00 02 46
1563 00 02 74
1564 00 02 43
1561 00 05 85
1557 00 00 48
1565 00 00 07
1576 00 00 99
1575 00 02 94
1560 00 00 18
1586 00 03 48
[फा. सं. एल-14014/13/2018- जीपी – II]
राज (cid:1)कशोर, अवर सिचव
MINISTRY OF PETROLEUM AND NATURAL GAS
NOTIFICATION
New Delhi, the 1st October, 2018
S.O. 5188(E).—Whereas by notification of Government of India in the Ministry of Petroleum and Natural Gas
S.O. No. 1172 (E) dated 12.03.2018 ; issued under sub- section (1) of section 3 of the Petroleum and Minerals Pipeline
(Acquisition of Right of User in Land) Act, 1962 (50 of 1962) (hereinafter referred to as the said Act), published in the
Extraordinary Gazette of India dated 16.03.2018, the Government of India declared its intention to acquire the Right of
User in the land specified in the Schedule appended to that notification for the purpose of laying pipeline for
transportation of natural gas through Jagdishpur-Haldia & Bokaro-Dhamra Pipeline (JHBDPL) & Spur Pipeline in the
State of Odisha by GAIL (India) Limited;
And whereas copies of the said Gazette notification were made available to the public;
And whereas the objections received from the public to the laying of the pipeline have been considered and
disposed of by the Competent Authority;
And, whereas the Competent Authority has, under sub-section (1) of Section 6 of the said Act, submitted its
report to Government of India;
And whereas Government of India after considering the said report and on being satisfied that the said land is
required for laying the pipelines, has decided to acquire the Right of User therein;
Now, therefore, in exercise of the powers conferred by sub-section (1) of section 6 of the said Act, Government
of India hereby declares that the Right of User in the land specified in the Schedule appended to this notification is
hereby acquired for laying the pipeline;
And, further, in exercise of the powers conferred by sub-section (4) of Section 6 of the said Act, Government of
India hereby directs that the Right of User in the land for laying the pipeline shall, instead of vesting in Government of
India, vest, on this date of the publication of the declaration, in the GAIL (India) Limited, free from all encumbrances.8 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
SCHEDULE
JAGDISHPUR-HALDIA-BOKARO-DHAMRA GAS PIPELINE & SPUR GAS PIPELINE PROJECT
DHAMRA - ANGUL PIPELINE (SECTION - 2A)
State : ODISHA
Survey Area
District Tehsil Village
No./Plot No. Hect. Acre Sq. mtr.
1 2 3 4 5
BHADRAK CHANDBALI NUAGAN 568 00 03 43
560 00 07 93
550 00 08 13
549 00 04 41
548 00 00 38
556 00 11 62
555 00 00 23
557 00 02 35
545 00 20 30
544 00 03 69
540 00 05 06
541 00 02 84
542 00 06 71
489 00 02 48
488 00 02 43
487 00 02 93
384 00 12 49
385 00 14 43
386 00 10 52
387 00 10 55
394 00 00 76
389 00 19 80
390 00 00 20
375 00 00 00
366 00 03 15
365 00 10 57
364 00 05 12
357 00 15 77
363 00 01 40
358 00 04 47
355 00 04 56
226 00 16 72
224 00 04 06
131 00 12 81
193 00 13 91
192 00 14 38
194 00 02 64
191 00 02 25
190 00 10 40
185 00 07 94¹Hkkx IIµ[k.M 3(ii)º Hkkjr dk jkti=k % vlk/kj.k 9
171 00 08 09
184 00 03 63
172 00 12 20
173 00 01 82
168 00 06 99
167 00 20 74
166 00 01 75
174 00 00 43
164 00 03 24
165 00 18 18
80 00 18 36
78 00 08 04
79 00 03 44
21 00 15 86
20 00 16 56
19 00 00 12
22 00 03 07
18 00 16 82
24 00 03 71
25 00 01 61
27 00 00 36
BHADRAK CHANDBALI TALABANDHA 1056 00 04 16
1057 00 04 82
1054 00 01 05
1058 00 08 31
1053 00 07 97
1061 00 00 27
1059 00 09 26
1052 00 10 35
1053 00 00 20
1051 00 03 45
1050 00 05 73
1048 00 09 42
1053 00 00 07
1047 00 12 91
1046 00 18 98
1039 00 00 06
1041 00 28 76
1042 00 00 56
1123 00 18 34
1146 00 01 30
1124 00 06 03
1146 00 10 85
1129 00 00 03
1145 00 03 36
1129 00 00 09
1144 00 01 67
1147 00 00 22
1143 00 17 29
1142 00 01 0810 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
1141 00 08 01
1140 00 08 64
1158 00 00 17
1159 00 01 14
1160 00 00 94
1169 00 17 81
1170 00 09 91
1234 00 08 23
1230 00 00 01
1236 00 00 16
1234 00 00 12
1235 00 12 04
1229 00 02 49
1263 00 00 75
1262 00 00 11
1264 00 07 89
1265 00 02 69
1266 00 04 35
1260 00 00 82
1259 00 09 52
1271 00 27 47
1341 00 23 76
1334 00 05 03
1331 00 04 33
1333 00 05 74
1320 00 06 17
1344 00 03 46
1316 00 23 38
1317 00 00 02
1352 00 02 78
1315 00 04 75
1314 00 09 03
1677 00 00 14
1675 00 04 45
1676 00 01 49
1691 00 05 38
1692 00 08 02
1693 00 04 82
1694 00 02 29
1689 00 00 75
1709 00 07 41
1695 00 00 24
1696 00 00 63
1707 00 02 67
1708 00 04 75
1710 00 13 97
1744 00 16 09
1712 00 03 87
1721 00 00 41
1720 00 02 08
1719 00 06 78¹Hkkx IIµ[k.M 3(ii)º Hkkjr dk jkti=k % vlk/kj.k 11
1714 00 00 07
1718 00 03 34
1717 00 02 10
1716 00 08 24
1715 00 08 97
1714 00 03 15
1728 00 00 01
1729 00 05 92
1634 00 01 73
1635 00 00 51
1633 00 02 82
1630 00 04 52
1538 00 00 83
1552 00 05 02
1539 00 00 05
1551 00 03 75
1553 00 01 30
1556 00 09 81
1549 00 00 86
1555 00 00 79
1562 00 02 46
1563 00 02 74
1564 00 02 43
1561 00 05 85
1557 00 00 48
1565 00 00 07
1576 00 00 99
1575 00 02 94
1560 00 00 18
1586 00 03 48
[F.No. L-14014/13/2018-GP-II]
RAJ KISHORE, Under Secy.
अअअअििििधधधधससससचचूूचचूू ननननाााा
नई (cid:1)द(cid:3)ली, 1 अ(cid:7) तबू र, 2018
ककककाााा....आआआआ.... 5555111188889999((((अअअअ))))....————भारत सरकार ने पे(cid:13)ोिलयम और खिनज पाइपलाइन (भूिम म(cid:18) उपयोग के अिधकार का अज(cid:20)न) अिधिनयम,
1962 (1962 का 50) (िजसे इसम(cid:18) इसके प(cid:24)ात उ(cid:28) अिधिनयम कहा गया ह)ै क(cid:30) धारा 3 क(cid:30) उपधारा (1) के अधीन जारी भारत सरकार
के पे(cid:13)ोिलयम और (cid:31)ाकृितक गैस मं"ालय क(cid:30) अिधसूचना का.आ. 2123 (अ) तारीख 14.06.2017 जो भारत के असाधारण राजप"
तारीख 06.07.2017 म(cid:18) (cid:31)किशत क(cid:30) गई थी, +ारा उस अिधसूचना से संल, अनुसूची म(cid:18) िविन.द/ भूिम म(cid:18) गेल (इि0डया) िलिमटेड +ारा
ओिडशा रा3य म(cid:18) जगदीशपुर-हि(cid:3)दया-बोकारो-धामरा ikbiykbZu (जे एच बी डी पी एल) एवं 5पर ikbiykbZu के मा6यम से (cid:31)ाकृितक गैस
के प7रवहन के िलए पाइपलाइन िबछाने के (cid:31)योजन के िलए उपयोग के अिधकार का अज(cid:20)न करने के अपने आशय क(cid:30) घोषणा क(cid:30) थी;
और उ(cid:28) राजपि"त अिधसूचना क(cid:30) (cid:31)ितयां जनता को उपल8ध करा दी गई थी;
और, स:म (cid:31)ािधकारी ने, उ(cid:28) अिधिनयम क(cid:30) धारा 6 क(cid:30) उप-धारा (1) के अधीन भारत सरकार को अपनी 7रपोट (cid:20)द ेदी ह;ै
और भारत सरकार ने, उ(cid:28) 7रपोट(cid:20) पर िवचार करने के प(cid:24)ात और यह संतु/ हो जाने पर (cid:1)क उ(cid:28) भूिम ikbiykbZu िबछाने के
िलए अपेि:त ह,ै उसम(cid:18) उपयोग के अिधकार का अज(cid:20)न करने का िविन(cid:24)य (cid:1)कया ह;ै
अतः अब, भारत सरकार, उ(cid:28) अिधिनयम क(cid:30) धारा 6 क(cid:30) उपधारा (1) +ारा (cid:31)द@A शि(cid:28)य= का (cid:31)योग करते Bय,े यह घोषणा
करती है (cid:1)क इस अिधसूचना से संल, अनुसूची म(cid:18) िविन.द/ भूिम म(cid:18) ikbiykbZu िबछाने के िलए उपयोग के अिधकार का अज(cid:20)न (cid:1)कया जाता
ह;ै12 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
और भारत सरकार, उ(cid:28) अिधिनयम (cid:1)क धारा 6 (cid:1)क उपधारा (4) +ारा (cid:31)दA शि(cid:28)य= का (cid:31)योग करते Bय,े िनदCश दते ी ह ै (cid:1)क
ikbiykbZu िबछाने के िलए भूिम म(cid:18) उपयोग का अिधकार, इस घोषणा के (cid:31)काशन क(cid:30) तारीख से, भारत सरकार म(cid:18) िनिहत होने के बजाए,
सभी िव(cid:3)लंगम= से मु(cid:28), गेल (इि0डया) िलिमटेड म(cid:18) िनिहत होगा।
अअअअननननुसुसुसुसचचूूचचूू ीीीी
जगदीशपुर-हि(cid:3)दया-बोकारो-धामरा गैस पाइपलाइन और 5पर पाइपलाइन (cid:31)ोज(cid:7)े ट धामरा-अनगुल पाइपलाइन (से(cid:7)सन - 2A )
राDय - ओिड़शा
(cid:4)(cid:4)(cid:4)(cid:4)(cid:6)(cid:6)ेे(cid:6)(cid:6)ेे फफफफलललल
ििििजजजजललललाााा ततततहहहहससससीीीीलललल (cid:1)(cid:1)(cid:1)(cid:1)ाााामममम सवC नंबर....
ह(cid:7)े टर आर वग(cid:20) मीटर
1111 2222 3333 4444 5555
जाजपुर दानग(cid:1)द दािनआबर 2185 00 01 22
1815 00 20 47
1879 00 00 97
1890 00 00 91
1899 00 02 07
1900 00 02 13
1904 00 02 38
1751 00 00 51
1778 00 07 12
1723 00 02 35
999913 00 08 76
999914 00 08 37
999915 00 03 29
1421 00 06 36
1456 00 07 51
1820 00 02 61
[फा. सं. एल-14014/13/2018- जीपी – II]
राज (cid:1)कशोर, अवर सिचव
NOTIFICATION
New Delhi, the 1st October, 2018
S. O. 5189(E).—Whereas by notification of Government of India in the Ministry of Petroleum and Natural Gas
S.O. No. 2123 (E) dated 14.06.2017 ; issued under sub- section (1) of section 3 of the Petroleum and Minerals Pipeline
(Acquisition of Right of User in Land) Act, 1962 (50 of 1962) (hereinafter referred to as the said Act), published in the
Extraordinary Gazette of India dated 06.07.2017, the Government of India declared its intention to acquire the Right of
User in the land specified in the Schedule appended to that notification for the purpose of laying pipeline for
transportation of natural gas through Jagdishpur-Haldia & Bokaro-Dhamra Pipeline (JHBDPL) & Spur Pipeline in the
State of Odisha by GAIL (India) Limited;
And whereas copies of the said Gazette notification were made available to the public;
And, whereas the Competent Authority has, under sub-section (1) of Section 6 of the said Act, submitted its
report to Government of India;
And whereas Government of India after considering the said report and on being satisfied that the said land is
required for laying the pipelines, has decided to acquire the Right of User therein;
Now, therefore, in exercise of the powers conferred by sub-section (1) of section 6 of the said Act, Government
of India hereby declares that the Right of User in the land specified in the Schedule appended to this notification is
hereby acquired for laying the pipeline;¹Hkkx IIµ[k.M 3(ii)º Hkkjr dk jkti=k % vlk/kj.k 13
And, further, in exercise of the powers conferred by sub-section (4) of Section 6 of the said Act, Government of
India hereby directs that the Right of User in the land for laying the pipeline shall, instead of vesting in Government of
India, vest, on this date of the publication of the declaration, in the GAIL (India) Limited, free from all encumbrances.
SCHEDULE
JAGDISHPUR-HALDIA-BOKARO-DHAMRA GAS PIPELINE PROJECT
DHAMRA-ANGUL PIPELINE (SECTION-2A)
State : ODISHA
Area
District Tehsil Village Survey No.
Hect. Are Sq. mtr.
1 2 3 4 5
JAJPUR DANAGADI DANIABAR 2185 00 01 22
1815 00 20 47
1879 00 00 97
1890 00 00 91
1899 00 02 07
1900 00 02 13
1904 00 02 38
1751 00 00 51
1778 00 07 12
1723 00 02 35
999913 00 08 76
999914 00 08 37
999915 00 03 29
1421 00 06 36
1456 00 07 51
1820 00 02 61
[F. No. L-14014/13/2018-GP-II]
RAJ KISHORE, Under Secy.
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.