Executive Summary:
This notification concerns the declaration of land acquisition for the building, widening (four-laning), maintenance, management, and operation of National Highway No. 16 in Andhra Pradesh. The land stretches from Km.681.000 to Km.731.600 (Anandapuram Anakapalli Section) and from Km.0.000 to Km.13.600 (Sabbavaram to Sheela Nagar Junction) in the Visakhapatnam district. The declaration follows the absence of objections and submission of a report to the Central Government. It was published on Wednesday, October 18, 2017.
Key Points / Main Content:
Declaration of Land Acquisition:
The Central Government declares the acquisition of land specified in the schedule for the purpose of National Highway No. 16 construction and related activities.
This declaration follows notifications S.O.No.102E, dated 12th January 2017, and S.O. No.2386E, dated 28th July 2017.
Land Details:
The land is located in the Visakhapatnam district of Andhra Pradesh, specifically along the Anandapuram Anakapalli Section (Km. 681.000 to Km. 731.600) and Sabbavaram to Sheela Nagar Junction (Km. 0.000 to Km. 13.600) of National Highway No. 16.
The schedule provides a detailed description of the land to be acquired, including survey numbers, area, ownership details, and land type.
Transfer of Ownership:
Upon publication of the notification in the Official Gazette, the specified land will vest absolutely in the Central Government, free from all encumbrances.
Impact Analysis:
Landowners:
Impact: Loss of land as specified in the schedule for the highway project.
Action Required: No action specified in the document.
Central Government:
Impact: Acquisition of land for National Highway No. 16 project.
Action Required: Take possession of the land and proceed with the planned construction and related activities.
Project Developers/ Contractors:
Impact: Access to acquired land for building, widening, maintenance, management and operation of National Highway No. 16.
Action Required: Proceed with project activities on the acquired land.
General Public/Commuters:
Impact: Eventual improvement of National Highway No. 16.
Action Required: No action specified in the document.
Key Entities Referenced
National Highways Act, 1956: A law enacted by the Indian Parliament concerning national highways. This act is referenced as the legal basis for acquiring land for highway construction.
Ministry of Road Transport and Highways: The Indian government ministry responsible for the development and maintenance of the national highway network. Notifications from this ministry are cited in the document.
National Highway No. 16: A specific national highway that is undergoing widening and construction, requiring land acquisition.
Andhra Pradesh: The state in India where the land acquisition for the National Highway No. 16 project is taking place.
Visakhapatnam: A district in Andhra Pradesh, India where land is being acquired for the National Highway No. 16 project.
Anandapuram Anakapalli Section: A section of National Highway 16 between Km.681.000 to Km.731.600 undergoing expansion.
Sabbavaram to Sheela Nagar Junction: A section of National Highway 16 from Km.0.000 to Km.13.600 undergoing expansion.
Times of India: A newspaper in which the substance of the land acquisition notification was published.
jftLVªh laö Mhö ,yö&33004@99 REGD. NO. D. L.-33004/99
vlk/kj.k
EXTRAORDINARY
Hkkx II—[k.M 3—mi&[k.M (ii)
PART II—Section 3—Sub-section (ii)
izkf/dkj ls izdkf'kr
PUBLISHED BY AUTHORITY
la- 2953] ubZ fnYyh] cq/okj] vDrwcj 18] 2017@vkf'ou 26] 1939
No. 2953] NEW DELHI, WEDNESDAY, OCTOBER 18, 2017/ASVINA 26, 1939
ससससड़ड़ड़ड़कककक पपपप(cid:2)(cid:2)(cid:2)(cid:2)ररररववववहहहहनननन औऔऔऔरररर ररररााााजजजजममममाााागगगग (cid:11)(cid:11)(cid:11)(cid:11)मममम(cid:13)(cid:13)ंं(cid:13)(cid:13)ंं ााााललललयययय
अअअअििििधधधधससससचचूूचचूू ननननाााा
नई (cid:1)द(cid:3)ली, 18 vDrwcj, 2017
dk-vk- 3371¼v½....—dUsnzh; ljdkj u]s jk"Vªh; jktekx Z vf/kfu;e] 1956 ¼1956 dk 48½ ¼ftl s ble sa bld s i’pkr ~
mDr vf/kfu;e dgk x;k gS½ dh /kkjk 3d dh mi/kkjk ¼1½ d s v/khu tkjh dh xbZ Hkkjr ljdkj d s lMd++ ifjogu vkSj
jktekx Z ea=ky; dh vf/klpw uk l[a ;k dk-vk- l[a ;k 102 ¼v½] rkjh[k 12 tuojh] 2017 vkSj ftl s ckn e sa dk-vk- l[a ;k 2386
¼v½] rkjh[k 28 tyq kb]Z 2017 }kjk l’a kkfs/kr dh xb Z Fkh] tk s Hkkjr d s jkti=] vlk/kkj.k] Hkkx II] [k.M 3] mi[kMa ¼ii½ e as
idz kf’kr dh xb Z Fkh] }kjk vk/a kz inz ’s k jkT; d s fo’kk[kkiVu~ e fty s esa jk"Vªh; jktekx Z l[a ;k 16 d s 681-000 fd-eh- l s 731-600
fd-eh- ¼vkuna iqje&vudkiYyh lDs ’ku½ vkSj 0-000 fd-eh- l s 13-600 fd-eh- ¼lCcoje l s 'khyuxj tDa ’ku½ rd d s Hk[w k.M d s
fuek.Z k ¼pkMS +k dju@s pkj yus dk cuku s vkfn]½] vuqj{k.k] icz /a k vkSj ipz kyu d s fy, ml vf/klpw uk l s mikc) vuqlpw h eas
fofufn"ZV Hkfwe dk vtuZ dju s d s viu s vk’k; dh ?kks"k.kk dh Fkh ;
vkSj mDr vf/klpw uk dk lkj mDr vf/kfu;e dh /kkjk 3d dh mi/kkjk ¼3½ d s v/khu rkjh[k 19 vxLr] 2017 dks
^^VkbEl vkWQ bf.M;k** vkSj ^^vk/a k z Hkfwe** e sa idz kf’kr fd;k x;k Fkk vkSj eyw vf/klpw uk dk-vk- l[a ;k 102 ¼v½] rkjh[k
12 tuojh] 2017 dk s ^^itz k’kfDr^^ rkjh[k 03 Qjojh] 2017 vkSj ^^fn fgUn^w^ rkjh[k 02 Qjojh] 2017 esa idz kf’kr dh xb Z Fkh ;
vkSj l{ke izkf/kdkjh dk s fdlh O;fDr l s dkbs Z vk{kis izkIr ugh a g,q gS a ;
vkSj l{ke izkf/kdkjh u s mDr vf/kfu;e dh /kkjk 3?k dh mi/kkjk ¼1½ d s vuqlj.k e]sa dUs nzh; ljdkj dk s viuh
fjikVs Z n s nh gS ;
vr% vc] dUs nzh; ljdkj] l{ke izkf/kdkjh dh mDr fjikVs Z izkIr gks tkus ij vkSj mDr vf/kfu;e dh /kkjk 3?k
dh mi/kkjk ¼1½ }kjk inz Rr 'kfDr;ksa dk i;z kxs djr s g,q ] ;g ?kk"sk.kk djrh gS fd mDr vuqlpw h es a fofufn"ZV Hkfwe dk iwokDZs r
i;z kts u d s fy, vtuZ fd;k tkuk pkfg, ;
vkSj vc] dUsnzh; ljdkj] mDr vf/kfu;e dh /kkjk 3?k dh mi/kkjk ¼2½ d s vuqlj.k esa ;g ?kk"sk.kk djrh gS fd
bl vf/klpw uk d s jkti= e sa izdk’ku ij] mDr vuqlpw h esa fofufn"ZV Hkfwe lHkh foYyxa ek sa ls eqDr gkds j vkR;fUrd :i l s
dUsnzh; ljdkj e sa fufgr gks tk,xh A
6296 GI/2017 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
vuqlwph
vk/a kiz nz ’s k ®ÉVªÉ BÉEä fo’kk[kkiVu~ e ÉÊVÉãÉä àÉå ®É−]ÉÅÒªÉ ®ÉVÉàÉÉMÉ Ç ºÉÆJªÉÉ 16 BÉEä 681.000 ÉÊBÉE.àÉÉÒ. ºÉä 731.600 ÉÊBÉE.àÉÉÒ rd (vkuna iqje
vudkiYyh&lsD’ku) vkSj 0.000ÉÊBÉE.àÉÉÒ l s13.600 ÉÊBÉE.àÉÉÒ (lCcoje l s 'khykuxj taD’ku) rd +ÉVÉÇxÉ BÉEÉÒ VÉÉxÉä ´ÉÉãÉÉÒ ºÉÆ®SÉxÉÉ
®ÉÊciÉ +ÉlÉ´ÉÉ ºÉÆ®SÉxÉÉ jfgr £ÉÚÉÊàÉ BÉEÉ ºÉÆÉÊFÉ{iÉ ÉÊ´É´É®hÉ
µÉEàÉ ÉÊVÉãÉÉ BÉEÉ iÉÉãÉÖBÉE BÉEÉ MÉÉÄ´É BÉEÉ xÉÉàÉ ºÉ´ÉæFÉhÉ £ÉÚÉÊàÉ BÉEÉ £ÉÚÉÊàÉ BÉEÉÒ £ÉÚÉÊàÉ BÉEÉ £ÉÚº´ÉÉÉÊàɪÉÉå/ ÉÊciɤÉr
ºÉÆJªÉÉ xÉÉàÉ xÉÉàÉ ºÉÆJªÉÉ/ IykV |ÉBÉEÉ® |ÉBÉEßÉÊiÉ FÉäjÉ{ÉEãÉ BªÉÉÎBÉDiɪÉÉå BÉEä xÉÉàÉ
ºÉÆJªÉÉ (´ÉMÉÇ àÉÉÒ
àÉå)
1 2 3 4 5 6 7 8 9
एलमंिचली शंकर राव ,
1.नारायण आया(cid:12)सी िस(cid:17)हाचलम
िपता ((cid:23)वग(cid:26)य)
1 िवशाखाप(cid:2)नम 1.आनंदपुरम गजपितराजुपुरम- 10/1A िनजी शु(cid:7)क 506
समु(cid:28),ंएरा(cid:12) कनकराव
(िबट-1) िपता ((cid:23)वग(cid:26)य) क!"या
(भूि(cid:23)तती सडक)
दो(ाग)ला अ+पाराव
िपता ((cid:23)वग(cid:26)य)
10/8A िनजी शु(cid:7)क 445 पैड"या,आया(cid:12)सी
स-यास(cid:17)मा पित
((cid:23)वग(cid:26)य) अछ!ा
िप)ला ल/मी पित
अ+पाराव,िप)ला ल/मी
10/9A िनजी शु(cid:7)क 364
पित कृ(cid:7)ण,व2क कनकराजु
िपता स-यासी
िप)ला ल/मी पित
10/11A िनजी शु(cid:7)क 324
अ+पाराव
10/12A िनजी शु(cid:7)क 445 मददाला व2कटे(cid:23)वर राव
कुल 2084
ग6ितना सि7बाबु िपता
2.नारायण
((cid:23)वग(cid:26)य)
गजपितराजुपुरम- 3/3C िनजी नम 1679 पोलीनायडू,को9डे ा
सि!बाबु िपता ((cid:23)वग(cid:26)य)
(िबट-II) अ+पडू
3/5 सरकारी पोर(cid:17)बोक 4411 सरकारी
पं:दरीपि)ल अछुताराव
4/2B िनजी शु(cid:7)क 283 िपता ((cid:23)वग(cid:26)य) अ+पाराव
(भूि(cid:23)तती सडक)
7/6 सरकारी पोर(cid:17)बोक 162 सरकारी
7/2C िनजी शु(cid:7)क 445 जन चैत-य लेअउट
7/3A िनजी शु(cid:7)क 1862 जन चैत-य लेअउट
7/7 सरकारी पोर(cid:17)बोक 688 सरकारी
कुल 9530
योग कुल 11614
[Qk- l-a Hkkjkjkizk@11013@Hkwv&3¼,½@ih vkb Z ;&w oStkx&2016&1]
jkt's k xqIrk] mi lfpo
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
NOTIFICATION
New Delhi, the 18th October , 2017
S.O. 3371(E).—Whereas by the notification of the Government of India in the Ministry of Road Transport and
Highways S.O.No.102(E), dated 12th January, 2017 and subsequently amended vide S.O. No.2386(E), dated
28th July, 2017 published in Gazette of India, Extraordinary, Part II, Section 3, Sub-section (ii) issued under sub-section
(1) of section 3A of the National Highways Act, 1956 (48 of 1956) (hereinafter referred to as the said Act), the Central¹Hkkx IIµ[k.M 3(ii)º Hkkjr dk jkti=k % vlk/kj.k 3
Government declared its intention to acquire the land specified in the Schedule annexed to the said notification for
building (widening / four-laning ect ), maintenance, management and operation of National Highway No.16 on the
stretch of land from Km.681.000 to Km.731.600 (Anandapuram - Anakapalli Section) and from Km.0.000 to
Km.13.600 (Sabbavaram to Sheela Nagar Junction) in the district of Visakhapatnam in the State of Andhra Pradesh .
And whereas the substance of the said notification has been published in “Times of India” & “Andhra Bhoomi”
all dated 19th August 2017 under sub-section (3) of section 3A of the said Act, and the principal notification
S.O.No.102(E), dated 12th January, 2017 has been published in “Prajasakthi” dated 03rd February, 2017 and “The Hindu”
dated 02nd February, 2017.
And whereas no objection has been received from any person by the Competent Authority;
And whereas, in pursuance of sub-section (1) of section 3D of the said Act, the competent authority has
submitted its report to the Central Government;
Now, therefore, upon receipt of the said report of the competent authority and in exercise of the powers conferred by
sub-section (1) of section 3D of the said Act, the Central Government hereby declares that the land specified in the said
Schedule should be acquired for the aforesaid purpose;
And further, in pursuance of sub-section (2) of section 3D of the said Act, the Central Government hereby declares that
on publication of this notification in the Official Gazette, the land specified in the said Schedule shall vest absolutely in
the Central Government, free from all encumbrances.
SCHEDULE
Brief description of the land to be acquired, with or without structure falling within the stretch of land from Km.681.000
to Km.731.600 (Anandapuram-Anakapalli Section) and from Km.0.000 to Km.13.600 (Sabbavaram to Sheelanagar) of
the National Highway No. 16 in the State of Andhra Pradesh
Survey/Sub Area Name of the
Sl. Name of the Name of the Name of the Type of Nature of
divn. (in proposed Registered
No District Taluk Village land land
Number Sq.mt) Holders
1 2 3 4 5 6 7 8 9
Yelamanchili
Shankararao,Aryasi
Simhachalam S/o
1.Narayana Late
1 Visakhapatnam 1.Anandapuram Gajapathiraju 10/1A Private Dry 506 Samudram,Yerra
Puram-(Bit.1) Kanakarao S/o Late
Kannayya,(On
Ground Cement
Road)
Doddagalla Apparao
S/o Late
10/8A Private Dry 445 Pydayya,Aryasi
Sanyasamma W/o
Late Atchanna
Pilla Lakshmi W/o
Apparao,Pilla
Lakshmi W/o
10/9A Private Dry 364
Krishna,Venka
Kanakaraju S/o
Sanyasi
Pilla Lakshmi W/o
10/11A Private Dry 324
Apparao
Maddala
10/12A Private Dry 445
Venkateswararao
Total 2084
Gonthina Sathibabu
2.Narayana
S/o Late Polinaidu,
Gajapathiraju 3/3C Private Wet 1679
Kotteda Sannibabu
Puram (Bit.II)
S/o Late Appadu
3/5 Government Poramboke 4411 Government
Pandiripalli
Atchutarao S/o Late
4/2B Private Dry 283
Apparao On Ground
Road4 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
7/6 Government Poramboke 162 Government
Jana Chaitanya Lay
7/2C Private Dry 445
Out
Jana Chaitanya Lay
7/3A Private Dry 1862
Out
7/7 Government Poramboke 688 Government
Total 9530
Grand
11614
Total
[F. No. NHAI/11013/LA-3(A)/PIU-Vizag/2016-1]
RAJESH GUPTA, Dy. Secy.
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064