## Report on Amendment to Metro Railways Construction of Works Act, 1978 concerning Bangalore Metro Rail Project
**1. Executive Summary:**
This report analyzes a notification (S.O. 852(E)) issued by the Ministry of Housing and Urban Affairs on February 25, 2022, which amends the Schedule of the Metro Railways Construction of Works Act, 1978. The amendment expands the Act's applicability to include specific metro alignments for the Bangalore Metro Rail Project, encompassing Phase 1, Phase 2, Phase 2A, and Phase 2B corridors within the metropolitan area of Bangalore. This inclusion aims to facilitate the construction and operation of these metro lines under the purview of the Act.
**2. Introduction:**
The purpose of this report is to provide an informative overview of the notification S.O. 852(E), dated February 25, 2022, which pertains to an amendment of the Metro Railways Construction of Works Act, 1978, with a specific focus on the Bangalore Metro Rail Project. The analysis is based solely on the information contained within the provided policy text.
**3. Policy Overview:**
This notification amends the Schedule of the Metro Railways Construction of Works Act, 1978. The core objective, as inferred from the text, is to extend the legal framework of the Act to cover the newly added metro alignments of the Bangalore Metro Rail Project. This will grant the Central Government the powers conferred by the act for construction of works.
**4. Background and Rationale:**
This is an amendment to an existing law. The rationale for this specific amendment appears to be the need to formally incorporate the Bangalore Metro Rail Project Phase 1, Phase 2, Phase 2A and 2B Corridors under the umbrella of the Metro Railways Construction of Works Act, 1978. This inclusion likely aims to streamline the construction process by leveraging the powers and provisions granted under the Act. Without specific mention in the text, it is possible this amendment is needed to address new construction areas or expansions that were not part of the original Act's schedule.
**5. Key Provisions / Changes:**
The key change introduced by this amendment is the addition of specific Bangalore Metro Rail Project alignments to the Schedule of the Metro Railways Construction of Works Act, 1978. Specifically, the following corridors are added:
* **Bangalore Metro Rail Project, Phase 1:** Corridor I (East-West), Corridor II (North-South) with detailed lists of stations.
* **Bangalore Metro Rail Project, Phase 2:** Corridor I (East side, West side), Corridor II (North side, South side), Corridor III (New Line), Corridor IV (New Line) with detailed lists of stations.
* **Bangalore Metro Rail Project, Phase 2A and 2B:** Corridor I (Phase 2A ORR Line), Corridor II (Phase 2B Airport Line), including a detailed list of stations.
The effect of this change is to bring these specified sections of the Bangalore Metro Rail Project under the legal and regulatory framework of the Metro Railways Construction of Works Act, 1978. This provides the Central Government with authority relating to the construction of these lines.
**6. Target Audience and Stakeholders:**
Based on the text, the primary stakeholders directly affected by this amendment include:
* **Bangalore Metro Rail Corporation Limited (BMRCL):** The entity responsible for the development and operation of the Bangalore Metro.
* **Construction companies** involved in the Bangalore Metro project.
* **Residents and businesses** located along the specified metro alignments, as construction and operation may impact them.
* **Commuters** who will utilize the extended metro network.
* **Government agencies** involved in urban planning and transportation in Bangalore.
**7. Implementation Aspects (Inferred):**
* **Responsible Agency/Bodies:** The Ministry of Housing and Urban Affairs is the issuing authority. BMRCL would likely be the primary implementing agency.
* **Timelines/Procedures:** The text does not specify any timelines or procedures for implementation, other than the date of the notification (February 25, 2022). However, the amendment likely triggers further processes related to land acquisition, construction permits, and project oversight under the Metro Railways Construction of Works Act, 1978.
**8. Expected Outcomes / Impact of Changes:**
The intended outcome of this amendment is likely to:
* **Facilitate smoother construction and operation of the Bangalore Metro expansion:** Bringing the project under the Metro Railways Construction of Works Act may expedite approvals and provide a clearer legal framework.
* **Accelerate the completion of the Bangalore Metro expansion:** By streamlining the regulatory process, the amendment may contribute to faster project completion and earlier availability of metro services to the public.
* **Improve urban mobility in Bangalore:** The extended metro network is expected to alleviate traffic congestion and provide a more efficient public transportation option.
**9. Conclusion:**
The amendment to the Metro Railways Construction of Works Act, 1978, detailed in notification S.O. 852(E), is a significant step towards the expansion of the Bangalore Metro Rail Project. By including specific metro alignments within the Act's Schedule, the amendment aims to streamline the construction and operation of the expanded metro network. This will help ensure proper implementation and execution of the project with central government oversight. This amendment plays a crucial role in supporting urban development and improving transportation infrastructure in Bangalore.
Key Entities Referenced
Metro Railways Construction of Works Act, 1978: A central legislation governing metro railway construction, referenced by its act number (33 of 1978) and year of enactment.
Yelachenahalli Station: A station on Corridor II of the Bangalore Metro Rail Project.
Bangalore: Metropolitan area in the State of Karnataka where the Metro Railways Construction of Works Act, 1978 has been extended and where the metro alignments are added to the Schedule of the said Act.
Karnataka: The State in which the metropolitan area of Bangalore is located.
Bangalore Metro Rail Project: The specific metro rail project in Bangalore that is the subject of the notification, including Phase 1, Phase 2, Phase 2A and 2B Corridors.
Baiyappanahalli: A location within Bangalore, serving as a station and depot for Corridor I of the Bangalore Metro Rail Project.
Swami Vivekananda Road: A station on Corridor I of the Bangalore Metro Rail Project.
Indiranagar: A station on Corridor I of the Bangalore Metro Rail Project.
Halasuru: A station on Corridor I of the Bangalore Metro Rail Project.
Trinity: A station on Corridor I of the Bangalore Metro Rail Project.
Mahatma Gandhi Road: A station on Corridor I of the Bangalore Metro Rail Project.
Cubbon Park: A station on Corridor I of the Bangalore Metro Rail Project.
Dr. B.R. Ambedkar Station, Vidhan Soudha: A station on Corridor I of the Bangalore Metro Rail Project.
Sir M. Visvesaraya Station, Central College: A station on Corridor I of the Bangalore Metro Rail Project.
Nadaprabhu Kempegowda Station, Majestic: A station on Corridor I & II of the Bangalore Metro Rail Project.
Krantivira Sangolli Rayanna Railway Station: A station on Corridor I of the Bangalore Metro Rail Project.
Magadi Road: A station on Corridor I of the Bangalore Metro Rail Project.
Sri Balagangadharanatha Swamiji Station, Hosahalli: A station on Corridor I of the Bangalore Metro Rail Project.
Vijaya Nagar: A station on Corridor I of the Bangalore Metro Rail Project.
Attiguppe: A station on Corridor I of the Bangalore Metro Rail Project.
Deepanjali Nagar: A station on Corridor I of the Bangalore Metro Rail Project.
Mysore Road: A station on Corridor I of the Bangalore Metro Rail Project.
Nagasandra: A station on Corridor II of the Bangalore Metro Rail Project.
Dasarahalli: A station on Corridor II of the Bangalore Metro Rail Project.
Jalahalli: A station on Corridor II of the Bangalore Metro Rail Project.
Peenya Industry: A station on Corridor II of the Bangalore Metro Rail Project.
Peenya: A location within Bangalore, serving as a station and depot for Corridor II of the Bangalore Metro Rail Project.
Goraguntepalya Metro Station: A station on Corridor II of the Bangalore Metro Rail Project.
Yeshwanthpur: A station on Corridor II of the Bangalore Metro Rail Project.
Sandal Soap Factory: A station on Corridor II of the Bangalore Metro Rail Project.
Mahalakshmi: A station on Corridor II of the Bangalore Metro Rail Project.
Rajajinagar: A station on Corridor II of the Bangalore Metro Rail Project.
Mahakavi Kuvempu Road: A station on Corridor II of the Bangalore Metro Rail Project.
Srirampura: A station on Corridor II of the Bangalore Metro Rail Project.
Mantri Square Sampige Road Station: A station on Corridor II of the Bangalore Metro Rail Project.
Chickpete: A station on Corridor II of the Bangalore Metro Rail Project.
Krishna Rajendra Market: A station on Corridor II of the Bangalore Metro Rail Project.
National College: A station on Corridor II of the Bangalore Metro Rail Project.
Lalbagh: A station on Corridor II of the Bangalore Metro Rail Project.
South End Circle: A station on Corridor II of the Bangalore Metro Rail Project.
Jayanagar: A station on Corridor II of the Bangalore Metro Rail Project.
Rashtreeya Vidyalaya Road: A station on Corridor II of the Bangalore Metro Rail Project.
Banashankari: A station on Corridor II of the Bangalore Metro Rail Project.
Jaya Prakash Nagar: A station on Corridor II of the Bangalore Metro Rail Project.
Benniganahalli: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
K.R. Puram: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Mahadevapura: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Garudacharpalya: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Hoodi Junction: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Seetharam Palya: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Kundalahalli: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Nallur Halli: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Sri Sathya Sai Hospital Metro Station: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Pattandur Agrahara: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Kadugodi: A location within Bangalore, serving as a station and depot for Corridor I of the Bangalore Metro Rail Project, Phase 2.
Channasandra: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Whitefield: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Nayandahalli: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Rajarajeshwari Nagar: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Jnanabharathi: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Pattanagere: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Kengeri Bus Terminal: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Kengeri: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2.
Challaghatta: A location within Bangalore, serving as a station and depot for Corridor I of the Bangalore Metro Rail Project, Phase 2.
Manjunatha Nagar: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2.
Chikkabidarakallu: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2.
Madavara: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2.
Konanakunte Cross: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2.
Doddakallasandra: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2.
Vajarahalli: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2.
Talaghattapura: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2.
Silk Institute: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2.
Anjanapura: A location within Bangalore, serving as a depot for Corridor II of the Bangalore Metro Rail Project, Phase 2.
R.V. Road: A station on Corridor III of the Bangalore Metro Rail Project.
Ragigudda: A station on Corridor III of the Bangalore Metro Rail Project.
Jayadeva Hospital: A station on Corridor III of the Bangalore Metro Rail Project.
BTM Layout: A station on Corridor III of the Bangalore Metro Rail Project.
Central Silk Board: A station on Corridor III of the Bangalore Metro Rail Project.
Bommanahalli: A station on Corridor III of the Bangalore Metro Rail Project.
Hongasandra: A station on Corridor III of the Bangalore Metro Rail Project.
Kudlu Gate: A station on Corridor III of the Bangalore Metro Rail Project.
Singasandra: A station on Corridor III of the Bangalore Metro Rail Project.
Hosa Road: A station on Corridor III of the Bangalore Metro Rail Project.
Beratena Agrahara: A station on Corridor III of the Bangalore Metro Rail Project.
Electronic City: A station on Corridor III of the Bangalore Metro Rail Project.
Infosys Foundation: A station on Corridor III of the Bangalore Metro Rail Project.
Konappana Agrahara: A station on Corridor III of the Bangalore Metro Rail Project.
Huskur Road: A station on Corridor III of the Bangalore Metro Rail Project.
Hebbagodi: A location within Bangalore, serving as a station and depot for Corridor III of the Bangalore Metro Rail Project.
Bommasandra: A station on Corridor III of the Bangalore Metro Rail Project.
Kalena Agrahara: A station on Corridor IV of the Bangalore Metro Rail Project.
Hulimavu: A station on Corridor IV of the Bangalore Metro Rail Project.
I.I.M.B: A station on Corridor IV of the Bangalore Metro Rail Project.
J.P. Nagar 4th Phase: A station on Corridor IV of the Bangalore Metro Rail Project.
Tavarekere: A station on Corridor IV of the Bangalore Metro Rail Project.
Dairy Circle: A station on Corridor IV of the Bangalore Metro Rail Project.
Lakkasandra: A station on Corridor IV of the Bangalore Metro Rail Project.
Langford Town: A station on Corridor IV of the Bangalore Metro Rail Project.
Rashtriya Military School: A station on Corridor IV of the Bangalore Metro Rail Project.
M.G. Road: A station on Corridor IV of the Bangalore Metro Rail Project.
Shivaji Nagar: A station on Corridor IV of the Bangalore Metro Rail Project.
Cantonment Railway Station: A station on Corridor IV of the Bangalore Metro Rail Project.
Pottery Town: A station on Corridor IV of the Bangalore Metro Rail Project.
Tannery Road: A station on Corridor IV of the Bangalore Metro Rail Project.
Venkateshpura: A station on Corridor IV of the Bangalore Metro Rail Project.
Kadugondanahalli: A station on Corridor IV of the Bangalore Metro Rail Project.
Nagawara: A station on Corridor IV of the Bangalore Metro Rail Project.
Kothanur: A location within Bangalore, serving as a depot for Corridor IV of the Bangalore Metro Rail Project.
HSR Layout: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2A.
Agara: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2A.
Ibbalur: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2A.
Bellandur Line: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2A.
Kadubeesanahalli: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2A.
Kodibeesanahalli: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2A.
Marathahalli: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2A.
ISRO: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2A.
Doddanekundi: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2A.
DRDO Sports Complex: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2A.
Saraswathi Nagar: A station on Corridor I of the Bangalore Metro Rail Project, Phase 2A.
Kasturi Nagar: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
Horamavu: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
HRBR Layout: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
Kalyan Nagar: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
HBR Layout Line: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
Veeranna Palya: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
Kempapura: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
Hebbal: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
Kodigehalli: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
Jakkur Cross: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
Yelahanka: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
Bagalur Cross: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
Bettahalasuru: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
Doddajala: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
Airport City: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
KIA Terminal: A station on Corridor II of the Bangalore Metro Rail Project, Phase 2B.
Shettigere: A location within Bangalore, serving as a depot for Corridor I & II of the Bangalore Metro Rail Project Phase 2A and 2B.
Ministry of Housing and Urban Affairs: The government ministry responsible for the notification concerning the Bangalore Metro Rail Project.
New Delhi: The location where the notification was issued.
Central Government: The governing authority issuing the notification and exercising powers under the Metro Railways Construction of Works Act, 1978.
Jaideep: The OSDUT ExOfficio Jt. Secy.
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
xxxGIDHxxx
सी.जी.-डी.एलxx.x-GअID.-E2x8xx0 22022-233740
CG-DL-E-28022022-233740
ऄसाधारण
EXTRAORDINARY
भाग II—खण्ड 3—ईप-खण्ड (ii)
PART II—Section 3—Sub-section (ii)
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 822] नइ ददल्ली, , फरवरी 25, 2022/फाल्ग नु 6, 1943
No. 822] NEW DELHI, FRIDAY, FEBRUARY 25, 2022/PHALGUNA 6, 1943
अवासन और िहरी काय यमत्रं ालय
(एमअरटीएस-II)
ऄजधसचू ना
नइ ददल्ली, 25 फरवरी, 2022
का.अ. 852(ऄ).—केन्द्रीय सरकार ने भूजमगत रेल (संकमय सजिमायण) ऄजधजनयम, 1978 (1978 का 33) की
धारा 1 की ईप-धारा (3) द्वारा प्रदत्त िजियों का प्रयोग करते हुए, ददनांक 16 ऄिूबर, 2009 की ऄपनी ऄजधसूचना
संख्या का.अ. 2625 (ऄ) के द्वारा कनायटक राज्य म ें बैंगलुरु के महानगरीय क्षेत्र तक ईि ऄजधजनयम के ईपबंधों का जवस्ट्तार
दकया ह।ै
ऄतः ऄब केन्द्रीय सरकार, भूजमगत रेल (संकमय सजिमायण) ऄजधजनयम, 1978 (1978 का 33) की धारा 32 की
ईप-धारा (1) के खंड (क) द्वारा प्रदत्त िजियों का प्रयोग करते हुए, ईि ऄजधजनयम की ऄनुसूची िोड़ती ह,ै बैंगलरुु के
महानगरीय क्षेत्र के संबंध में बैंगलरुु मेरो रेल पररयोिना चरण-1, चरण-2 और चरण-2क और 2ख कॉररडोर के मेरो
संरेखण आस प्रकार ह ैंऄथायत् : -
1329 GI/2022 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
“बैंगलरुु के महानगरीय क्षेत्र
बगैं लरुु मरे ो रेल पररयोिना, चरण-1
कॉररडोर- I (पूव-य पजिम) बैयप्पनहल्ली - स्ट्वामी जववेकानंद रोड - आंददरानगर - हलासुरु - ररजनटी- महात्मा
गांधी रोड- कब्बन पाकय- डॉ बीअर ऄंबेडकर स्ट्टेिन, जवधान सौधा - सर एम.
जवश्वेश्वरैया स्ट्टेिन, सेंरल कॉलेि - नादप्रभ ु केम्पगे ौड़ा स्ट्टेिन, मैिेजस्ट्टक-क्ांजतजवरा
संगोली रायिा रेलवे स्ट्टेिन-मगदी रोड- श्री बालगगं ाधरनाथ स्ट्वामीिी स्ट्टेिन,
होसहल्ली-जविय नगर - ऄरटगप्ु पे-दीपांिजल नगर-मैसूर रोड
कॉररडोर-I के जलए जडपो बैयप्पनहल्ली में जडपो
कॉररडोर-II (ईत्तर-दजक्षण) नागासांरा - दिरहल्ली - िलाहल्ली - पीन्द्या ईद्योग - पीन्द्या - गोरगुंटेपल्या मेरो
स्ट्टेिन - यिवंतपुर - सैंडल सोप फैक्ट्री - महालक्ष्मी - रािािीनगर - महाकजव कुवेम्पु
रोड - श्रीरामपुरा - मंत्री स्ट्वायर संजपग े रोड स्ट्टेिन - नादप्रभु केम्पगे ौड़ा स्ट्टेिन
मैिेजस्ट्टक - जचकपेटे - कृष्णा रािेंर माकेट – नैिनल कालेि - लालबाग - साईथ एंड
सकयल - ियनगर - राष्ट्रीय जवद्यालय रोड - बनिंकरी - िय प्रकाि नगर -
येलाचेनहल्ली स्ट्टेिन
कॉररडोर-II के जलए जडपो पीन्द्या में जडपो
बगैं लरुु मरे ो रेल पररयोिना, चरण -2
कॉररडोर -I पूवय की ओर बैयप्पनहल्ली - बेजिगनहल्ली - केअर परु म - महादेवपुरा - गरुड़चारपाल्य - हुडी
(चरण-1 पूव-य पजिम कॉररडोर िंक्ट्िन - सीताराम पाल्य - कुंडलाहल्ली - नल्लरू हल्ली - श्री सत्य साइ ऄस्ट्पताल मेरो
का जवस्ट्तार) स्ट्टेिन - पट्टंदरू ऄग्रहारा - कडुगोडी - चिासांरा - व्हाआटफील्ड
कॉररडोर-I के जलए पूवय की ओर कडुगोडी में जडपो ।
जडपो
कॉररडोर -I पजिम की ओर मैसूर रोड - नयनदहल्ली - रािरािेश्वरी नगर - ज्ञानभारती - पट्टानागेरे - केंगरे ी बस
(चरण-1 पूव-य पजिम कॉररडोर टर्ममनल - केंगेरी - चलघट्टा
का जवस्ट्तार)
कॉररडोर-I वेस्ट्ट साआड के जलए चलघट्टा म ेंजडपो ।
जडपो
कॉररडोर-II ईत्तर की ओर नागासांर - मंिुनाथ नगर - जचक्कजबदारकल्लू - मदवार
(चरण-1 ईत्तर-दजक्षण कॉररडोर
का जवस्ट्तार)
कॉररडोर-II दजक्षण की ओर येलाचेनहल्ली - कोनानाकुंटे क्ॉस - डोड्डकल्लासंरा -विारहल्ली - तलाघट्टापुरा -
जसल्क आंजस्ट्टट्यूट
(चरण-1 ईत्तर-दजक्षण कॉररडोर
का जवस्ट्तार)
कॉररडोर-II के जलए दजक्षण की ऄंिनपुर म ेंजडपो
ओर जडपो
कॉररडोर-III नइ लाआन अरवी रोड - रागीगड्डु ा - ियदेव ऄस्ट्पताल - बीटीएम लेअईट - सेंरल जसल्क बोडय -
बोम्मनहल्ली - होंगसांरा - कुडल ू गेट - ससगसांरा - होसा रोड - बेरेटना ऄग्रहारा -
आलेक्ट्रॉजनक जसटी - आंफोजसस फाईंडेिन कोनाप्पना ऄग्रहारा - हुस्ट्कर रोड - हब्े बागोडी
- बोम्मासांरा
कॉररडोर-III नइ लाआन के जलए हब्े बागोडी में जडपो
जडपो
कॉररडोर-IV नइ लाआन कालेना ऄग्रहारा - हुलीमाव ु - अइअइएमबी - िपे ी नगर 4th फेस - ियदेव ऄस्ट्पताल
- तवरेकेरे - डेयरी सकयल - लक्कासांरा - लगैं फोडय टाईन - राष्ट्रीय जमजलरी स्ट्कूल - एमिी
रोड - जिवािी नगर - कैंटोनमेंट रेलव े स्ट्टेिन - पॉटरी टाईन - टेनरी रोड - वेंकटेिपुरा
- कडुगोंडानहल्ली - नागवारा[भाग II—खण् ड 3(ii)] भारत का रािपत्र : ऄसाधारण 3
कॉररडोर-IV नइ लाआन के जलए कोतनुर म ेंजडपो
जडपो
बगैं लरुु मरे ो रेल पररयोिना, चरण -2ए और 2बी
कॉररडोर- I (चरण 2 ए - सेंरल जसल्क बोडय - एचएसअर लेअईट - अगारा - आब्बलरू - बेलंदरू - कडुबीसनहल्ली
ओअरअर लाआन) - कोडीबीसनहल्ली - मराठाहल्ली - आसरो - डोड्डानेकुंडी - डीअरडीओ स्ट्पोर्टसय
कॉम्प्लेक्ट्स - सरस्ट्वती नगर - केअर पुरम
कॉररडोर- II (चरण 2 बी - कस्ट्तूरी नगर - होरामावु - एचअरबीअर लअे ईट - कल्याण नगर - एचबीअर लेअईट
एयरपोटय लाआन) - नागवाड़ा - वीरिा पाल्या - केम्पापुरा - हब्े बल - कोजडगहे ल्ली - िक्ट्कुर क्ॉस -
येलहकं ा - बगलूर क्ॉस - बेट्टालासुरु - डोड्डािाला - एयरपोट यजसटी - केअइए टर्ममनल
कॉररडोर- I और II के जलए जडपो
(चरण 2ए - ओअरअर लाआन िेट्टीगेरे में जडपो
और चरण 2बी - एयरपोटय
लाआन)4 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)][भाग II—खण् ड 3(ii)] भारत का रािपत्र : ऄसाधारण 5
[फा.सं. के-14011/26/2021-एमअरटीएस-II]
ियदीप, जविेष कायय ऄजधकारी (य ूटी) और पदेन संयुि सजचव6 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
MINISTRY OF HOUSING AND URBAN AFFAIRS
(MRTS-II)
NOTIFICATION
New Delhi, the 25th February, 2022
S.O. 852(E).—Whereas, in exercise of the powers conferred by sub-section (3) of section 1 of the Metro
Railways (Construction of Works) Act, 1978 (33 of 1978), the Central Government, vide its notification number S.O.
2625 (E) dated 16th October, 2009 has extended the provisions of the said Act to the metropolitan area of Bangalore in
the State of Karnataka.
Now, therefore, in exercise of the powers conferred by clause (a) of sub-section (1) of section 32 of the
Metro Railways (Construction of Works) Act, 1978 (33 of 1978), the Central Government hereby adds to the
Schedule of the said Act, the metro alignments of Bangalore Metro Rail Project Phase-1, Phase-2 and Phase-2A and
2B Corridors in respect of the metropolitan area of Bangalore, namely:-
―The Metropolitan Area of Bangalore
Bangalore Metro Rail Project, Phase-1
Corridor-I (East – West) Baiyappanahalli - Swami Vivekananda Road –Indiranagar – Halasuru – Trinity-
Mahatma Gandhi Road- Cubbon Park- Dr. B.R. Ambedkar Station, Vidhan Soudha
- Sir M. Visvesaraya Station, Central College – Nadaprabhu Kempegowda Station,
Majestic –Krantivira Sangolli Rayanna Railway Station-Magadi Road- Sri
Balagangadharanatha Swamiji Station, Hosahalli – Vijaya Nagar– Attiguppe –
Deepanjali Nagar - Mysore Road
Depot for Corridor-I Depot at Baiyappanahalli
Corridor-II (North – South) Nagasandra – Dasarahalli – Jalahalli -Peenya Industry – Peenya – Goraguntepalya
Metro Station - Yeshwanthpur – Sandal Soap Factory – Mahalakshmi –
Rajajinagar – Mahakavi Kuvempu Road – Srirampura - Mantri Square Sampige
Road Station –Nadaprabhu Kempegowda Station Majestic – Chickpete -Krishna
Rajendra Market - National College – Lalbagh - South End Circle – Jayanagar –
Rashtreeya Vidyalaya Road – Banashankari – Jaya Prakash Nagar – Yelachenahalli
Station
Depot for Corridor-II Depot at Peenya
Bangalore Metro Rail Project, Phase-2
Corridor-I East side Baiyappanahalli – Benniganahalli - K.R. Puram – Mahadevapura –
(Phase-1 Extension of East – Garudacharpalya - Hoodi Junction-Seetharam Palya – Kundalahalli – Nallur Halli -
West Corridor) Sri Sathya Sai Hospital Metro Station – Pattandur Agrahara - Kadugodi –
Channasandra - Whitefield
Depot for Corridor-I East side Depot at Kadugodi.
Corridor-I West side Mysore Road – Nayandahalli - Rajarajeshwari Nagar –Jnanabharathi - Pattanagere
(Phase-1 Extension of East – - Kengeri Bus Terminal – Kengeri – Challaghatta
West Corridor)
Depot for Corridor-I West side Depot at Challaghatta.
Corridor-II North side Nagasandra - Manjunatha Nagar – Chikkabidarakallu - Madavara
(Phase-1 Extension of North –
South Corridor)
Corridor-II South side Yelachenahalli - Konanakunte Cross – Doddakallasandra –Vajarahalli –
(Phase-1 Extension of North – Talaghattapura - Silk Institute
South Corridor)
Depot for Corridor-II South Depot at Anjanapura
side
Corridor-III New Line R.V. Road – Ragigudda - Jayadeva Hospital - BTM Layout - Central Silk Board –
Bommanahalli – Hongasandra - Kudlu Gate – Singasandra - Hosa Road – Beratena
Agrahara - Electronic City - Infosys Foundation Konappana Agrahara -Huskur
Road – Hebbagodi - Bommasandra
Depot for Corridor-III New Depot at Hebbagodi
Line[भाग II—खण् ड 3(ii)] भारत का रािपत्र : ऄसाधारण 7
Corridor-IV New Line Kalena Agrahara – Hulimavu - I.I.M.B - J.P. Nagar 4th Phase - Jayadeva Hospital–
Tavarekere - Dairy Circle – Lakkasandra -Langford Town - Rashtriya Military
School - M.G. Road -Shivaji Nagar - Cantonment Railway Station - Pottery Town -
Tannery Road – Venkateshpura – Kadugondanahalli - Nagawara
Depot for Corridor-IV New Depot at Kothanur
Line
Bangalore Metro Rail Project, Phase-2A and 2B
Corridor-I (Phase 2A – ORR Central Silk Board - HSR Layout – Agara – Ibbalur – Bellandur –
Line) Kadubeesanahalli – Kodibeesanahalli – Marathahalli – ISRO – Doddanekundi -
DRDO Sports Complex - Saraswathi Nagar - K.R. Puram
Corridor-II (Phase 2B – Airport Kasturi Nagar – Horamavu - HRBR Layout - Kalyan Nagar - HBR Layout –
Line) Nagawara – Veeranna Palya – Kempapura –Hebbal – Kodigehalli - Jakkur Cross –
Yelahanka - Bagalur Cross – Bettahalasuru – Doddajala - Airport City - KIA
Terminal
Depot for Corridor-I & II
(Phase 2A – ORR Line & Phase Depot at Shettigere
2B – Airport Line)8 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)][भाग II—खण् ड 3(ii)] भारत का रािपत्र : ऄसाधारण 9
[F.No. K-14011/26/2021-MRTS-II]]
JAIDEEP, OSD(UT) & Ex-Officio Jt. Secy.
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.