## Policy Analysis Report: Acquisition of Right of User for Petroleum Pipeline (Tundla to Kanpur)
**1. Executive Summary:**
This report analyzes a notification from the Ministry of Petroleum and Natural Gas, Government of India, regarding the acquisition of the right of user in land for the purpose of laying a petroleum product pipeline from Tundla Terminal to Kanpur Terminal by Indian Oil Corporation Limited (IOCL). The notification declares the Central Government's intention to acquire the right of user in specific lands described in the schedule. Affected parties are provided a window to raise objections. This analysis focuses solely on the provided notification text and infers potential implications for landowners and IOCL.
**2. Introduction:**
The purpose of this report is to provide an informative analysis of a notification published by the Ministry of Petroleum and Natural Gas, concerning the acquisition of the right of user in land for a petroleum pipeline. The report will outline the policy's objectives, key provisions, affected stakeholders, inferred implementation aspects, and expected outcomes based *solely* on the provided notification text.
**3. Policy Overview:**
This is a new policy declaration concerning the intention to acquire Right of User.
* **Core Objective(s):** The core objective, as stated in the text, is to facilitate the transportation of petroleum products from Tundla Terminal to Kanpur Terminal by laying a pipeline. This necessitates acquiring the right of user in the land required for the pipeline construction.
**4. Background and Rationale:**
This is a new policy; therefore, the following applies: The notification indicates that the Central Government deems it necessary, in the public interest, to establish a pipeline for transporting petroleum products between Tundla and Kanpur. This suggests a need to improve or expand the existing infrastructure for petroleum product distribution in the region, potentially addressing issues related to transportation efficiency, cost, or security of supply.
**5. Key Provisions / Changes:**
As this is a new policy declaration, the following applies:
The notification establishes the following key provisions:
* **Declaration of Intent:** The Central Government formally declares its intention to acquire the right of user in land for the specified pipeline project.
* **Project Executioner:** The project will be executed by the Indian Oil Corporation Limited (IOCL).
* **Land Acquisition:** The right of user acquisition pertains to specific parcels of land described in the attached schedule, including their Khasara numbers, location (villages, tehsil, district, state), and area (in Hectares, Are, and Sq. Mtrs).
* **Objection Mechanism:** Individuals with an interest in the affected land have 21 days from the date the notification is made available to the public to submit written objections to the Competent Authority, Indian Oil Corporation Limited Pipelines Division, Construction Office, Northern Region Pipelines, TundlaGawria Pipeline Project, E160, 1st 2nd floor, Kamlanagar, Agra U.P. 282 004.
* **Legal Basis:** The action is taken under the powers conferred by Sub-section 1 of Section 3 of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962.
**6. Target Audience and Stakeholders:**
Based on the text, the directly affected stakeholders include:
* **Landowners:** Individuals or entities owning land within the specified areas (villages of Banvirpur Kundhi and Dakhinara) as listed in the schedule.
* **Indian Oil Corporation Limited (IOCL):** The implementing agency responsible for laying the pipeline and managing the land acquisition process.
* **General Public:** May be affected through improved petroleum product availability in the region.
**7. Implementation Aspects (Inferred):**
The following implementation aspects can be inferred from the text:
* **Responsible Agency:** Indian Oil Corporation Limited (IOCL) is the primary responsible agency for executing the pipeline project and managing the land acquisition. The Ministry of Petroleum and Natural Gas provides oversight and authorization.
* **Timeline:** A 21-day window is provided for landowners to raise objections from the date of public availability of the notification. The overall project timeline is not specified in the text.
* **Procedure:** The procedure involves publishing the notification in the Gazette of India, making copies available to the public, allowing for objections, and ultimately acquiring the right of user in the land.
**8. Expected Outcomes / Impact of Changes:**
The likely intended outcomes, based on the notification text, are:
* **Enhanced Petroleum Product Transportation:** Improved and efficient transportation of petroleum products from Tundla to Kanpur via the new pipeline.
* **Infrastructure Development:** Development of pipeline infrastructure in the region.
* **Potential Economic Benefits:** Potential economic benefits associated with improved petroleum product availability and distribution, although not explicitly stated.
**9. Conclusion:**
The notification analyzed represents the Central Government's intention to acquire the right of user in land for the Tundla-Kanpur petroleum pipeline project, to be executed by IOCL. This policy declaration initiates a process that directly affects landowners in the specified areas, granting them a limited window to raise objections. The successful implementation of this policy is expected to improve petroleum product transportation infrastructure, with potential benefits for the wider region. The significance of this policy lies in its potential to enhance the efficiency and security of petroleum product distribution.
Key Entities Referenced
Ministry of Petroleum and Natural Gas: The ministry responsible for the notification.
Indian Oil Corporation Limited: The organization responsible for laying the pipeline from Tundla Terminal to Kanpur Terminal.
Petroleum and Minerals Pipelines Acquisition of Right of User in land Act, 1962: The law under which the Central Government declares its intention to acquire the right of user for laying the pipeline.
Tundla Terminal: The origin point of the petroleum products pipeline.
Kanpur Terminal: The destination point of the petroleum products pipeline.
Tundla-Gawria Pipeline Project: The specific pipeline project being undertaken by Indian Oil Corporation Limited.
Kamlanagar, Agra, Uttar Pradesh: The location of the Construction Office for the Northern Region Pipelines of Indian Oil Corporation Limited.
Shikohabad, Firozabad, Uttar Pradesh: The Tehsil and District in Uttar Pradesh where the land acquisition is taking place.
Uttar Pradesh: The State in which the land acquisition is taking place.
Banvirpur Kundhi: Name of the Village in Uttar Pradesh where the land acquisition is taking place.
Dakhinara: Name of the Village in Uttar Pradesh where the land acquisition is taking place.
New Delhi: Place of notification issuance.
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
सी.जी.-डी.एल.-अ.-30062021-228008
xxxGIDHxxx
CG-DL-E-30062021-228008
xxxGIDExxx
असाधारण
EXTRAORDINARY
भाग II—खण् ड 3—उप-खण्ड (ii)
PART II—Section 3—Sub-section (ii)
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 2432] नई दिल्ली, िुधवार, िनू 30, 2021/आषाढ़ 9, 1943
No. 2432] NEW DELHI, WEDNESDAY, JUNE 30, 2021/ASHADHA 9, 1943
पेरोजलयम और प्राकृजतक गसै मंत्रालय
अजधसचू ना
नई दिल्ली, 18 िून, 2021
का.आ. 2623(अ).—केन्द्रीय सरकार को लोकजित म ें यि आवश्यक प्रतीत िोता ि ैदक उत्तर प्रिेि राज्य म ें टूण्डला
टर्मिनल स े कानपरु टर्मिनल तक पेरोजलयम उत्पािों के पररविन के जलय े इंजडयन ऑयल कॉपोरेिन जलजमटेड द्वारा
पाइपलाइन जिछाई िानी चाजिए।
और केन्द्रीय सरकार को ऐसी पाइपलाइन जिछाने के प्रयोिन के जलय े यि आवश्यक प्रतीत िोता ि ै दक ऐसी भूजम
म ें िो इस स े उपािद्ध अनुसूची म े वर्णित ि,ै और जिसम ें उक्त पाइपलाइन जिछाई िान े का प्रस्ट्ताव ि,ै उपयोग के अजधकार
का अििन दकया िाए ।
अतः अि, केन्द्रीय सरकार, पेरोजलयम और खजनि पाइपलाइन (भूजम म ें उपयोग के अजधकार का अििन)
अजधजनयम, 1962 (1962 का 50) की धारा 3 की उपधारा (1) द्वारा प्रित्त िजक्तयों का प्रयोग करत े हुए उस भूजम म ें
उपयोग के अजधकार का अििन करने के अपने आिय की घोषणा करती ि ै।
कोई व्यजक्त, िो उक्त अनुसूची म ें वर्णित भूजम म ें जितिद्ध ि,ै उस तारीख से, जिसको इस अजधसूचना म ें युक्त
भारत के रािपत्र की प्रजतयााँ साधारण िनता को उपलब्ध करा िी िाती ि,ै इक्कीस दिन के भीतर, भूजम के नीच े पाइपलाइन
जिछाए िाने के जलए उसम ें उपयोग के अजधकार के संिंध म ें सक्षम प्राजधकारी, इंजडयन ऑयल कॉपोरेिन जलजमटेड
पाइपलाइन्द्स प्रभाग, जनमािण कायािलय, उत्तरी क्षत्रे पाइपलाइन्द्स, टूण्डला - गौररया पाइपलाइन पररयोिना, ई-160,
प्रथम व जद्वतीय तल, कमला नगर, आगरा (यू.पी.) – 282004 को जलजखत रूप म ेंआक्षेप भिे सकेगा।
3601 GI/2021 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
अनसु चू ी
तिसील – जिकोिािाि जिला – दिरोिािाि राज्य – उत्तर प्रदेश
क्रम क्षत्रे फल
ग वं क न म खसर स.ं
स.ं हक्े टेयर एयर वर्ग मीटर
1 2 3 4 5 6
1. िनवीरपुर कुढ़ी 424 00 07 20
2. िजखनारा 18 00 13 08
15 00 18 18
1427 00 11 38
[िा. सं. आर 11025(11)/20/2018- ओ आर -1/ ई 27595]
पी. सोमाकुमार, अवर सजचव
MINISTRY OF PETROLEUM AND NATURAL GAS
NOTIFICATION
New Delhi, the 18th June, 2021
S.O. 2623(E).—Whereas, it appears to the Central Government that it is necessary in the public
interest that for the transportation of petroleum products from Tundla Terminal to Kanpur Terminal should
be laid by Indian Oil Corporation Limited. And whereas, it appears to the Central Government that for the
purpose of laying the said pipeline, it is necessary to acquire the right of user in the land described in the
schedule annexed to this notification;
Now, therefore, in exercise of the powers conferred by Sub section (1) of section 3 of the
Petroleum and Minerals Pipelines (Acquisition of Right of User in land ) Act, 1962 (50 of 1962), the
Central Government hereby declares its intention to acquire the right of user therein;
Any person interested in the land described in the said schedule may, within twenty–one days from
the date on which the copies of this notification, as published in the Gazette of India, are made available to
the General Public, object in writing to the acquisition of the right of user therein or laying of the pipeline
under the land to Competent Authority, Indian Oil Corporation Limited (Pipelines Division), Construction
Office, Northern Region Pipelines, Tundla-Gawria Pipeline Project, E-160, 1st & 2nd floor, Kamlanagar,
Agra (U.P.) – 282 004.
SCHEDULE
Tehsil:- Shikohabad District:- Firozabad State :- Uttar Pradesh
Sl. Area
Name of the Village Khasara No.
No. Hectare Are Sq.mtr.
1 2 3 4 5 6
1. Banvirpur Kundhi 424 00 07 20
2. Dakhinara 18 00 13 08
15 00 18 18
1427 00 11 38
[F. No. R-11025(11)/20/2018-OR-1/E 27595]
P. SOMAKUMAR, Under Secy.
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.