This notification from the Ministry of Petroleum and Natural Gas declares the Central Government's intention to acquire the right of user for land in Rajasthan. This is for laying a pipeline by the Indian Oil Corporation for the Jaipur-Panipat Naphta Pipeline Project. Objections to the land acquisition can be submitted within 21 days of the notification's publication to Shri Nitendra Pal Singh in Jaipur.
Key Points / Main Content:
* **Purpose:** To declare the intention to acquire the right of user in land for the Jaipur-Panipat Naphta Pipeline Project.
* **Project Implementation:** Indian Oil Corporation (IOC) will lay the pipeline.
* **Legal Basis:** The declaration is made under Section 3(1) of the Petroleum and Minerals Pipeline (Acquisition of Right of User in Land) Act, 1962.
* **Objection Mechanism:** Any person interested in the land described in the schedule can submit written objections.
* **Objection Deadline:** Objections must be submitted within 21 days of the notification's publication.
* **Objection Submission:** Objections should be sent to Shri Nitendra Pal Singh, Competent Authority, at the specified address in Jaipur.
* **Land Details:** The schedule lists specific Khasra numbers and land areas in various villages of the Jamwaramgarh Tehsil, Jaipur District, Rajasthan.
Impact Analysis:
Landowners in Affected Areas:
* Impact: Potential acquisition of right of user of their land for the pipeline project.
* Action Required: Submit written objections to Shri Nitendra Pal Singh within 21 days if they have concerns regarding the land acquisition.
Indian Oil Corporation (IOC):
* Impact: Responsible for implementing the Jaipur-Panipat Naphta Pipeline Project.
* Action Required: Proceed with laying the pipeline in accordance with the legal framework and address any objections raised during the objection period.
Key Entities Referenced
Rajasthan: State of Rajasthan, India where the Naphta pipeline is proposed to be laid.
Jaipur-Panipat Naptha Pipeline Project: The specific pipeline project for which land acquisition is being declared.
Indian Oil Corporation: The company responsible for laying the Jaipur-Panipat Naptha Pipeline.
Petroleum and Minerals Pipeline Acquisition of Right of User in Land Act, 1962: The legal basis for the notification regarding land acquisition for the pipeline.
Nitendra Pal Singh: Competent Authority Rajasthan, Indian Oil Corporation Limited Pipelines Division Construction Office, responsible for receiving objections to the land acquisition.
Jamwaramgarh: Tehsil in Rajasthan, India where part of the land acquisition is taking place.
Jaipur: District in Rajasthan, India where part of the land acquisition is taking place.
Ministry of Petroleum and Natural Gas: The ministry issuing the notification