## Policy Analysis Report: Acquisition of Right of User for Natural Gas Pipeline in Tamil Nadu
**1. Executive Summary:**
This report analyzes a notification from the Ministry of Petroleum and Natural Gas regarding the acquisition of the right of user in land for laying a natural gas pipeline by Indian Oil Corporation Limited in Tamil Nadu. The core purpose of this policy is to facilitate the transportation of natural gas in the region by enabling the construction of the Ennore-Thiruvallur-Bengaluru-Puducherry-Nagapattinam-Madurai-Tuticorin pipeline. Key findings indicate a formal process for land acquisition, including a provision for objections from interested parties.
**2. Introduction:**
This report aims to provide a comprehensive overview of a notification issued by the Ministry of Petroleum and Natural Gas concerning the acquisition of the right of user in land for a natural gas pipeline project in Tamil Nadu. This analysis is based solely on the information provided in the policy text.
**3. Policy Overview:**
This is a *new policy* initiative, not an amendment.
* **Core Objective(s):** The core objective of this policy, as stated in the text, is to enable the transportation of Natural Gas in the State of Tamil Nadu by facilitating the laying of the Ennore Thiruvallur Bengaluru Puducherry Nagapattinam Madurai Tuticorin pipeline by Indian Oil Corporation Limited. A secondary objective is the acquisition of the right of user in land necessary for this pipeline construction.
**4. Background and Rationale:**
This policy addresses the need for infrastructure development to support the transportation of natural gas. The text states that the Central Government deems it necessary in the public interest to lay the specified pipeline. This suggests that increased availability and accessibility of natural gas are considered beneficial for the region and the nation.
**5. Key Provisions / Changes:**
This is a new policy. The main components and rules mandated by the policy are as follows:
* **Declaration of Intent:** The Central Government declares its intention to acquire the right of user in land for laying the pipeline.
* **Geographic Scope:** The policy focuses on land in Tamil Nadu specifically for the Ennore Thiruvallur Bengaluru Puducherry Nagapattinam Madurai Tuticorin pipeline project.
* **Implementing Agency:** Indian Oil Corporation Limited is designated as the entity responsible for laying the pipeline.
* **Objection Process:** Individuals with an interest in the affected land are granted a 21-day period to object in writing to the acquisition. This objection must be submitted to the designated Competent Authority, Land Acquisition Officer at Indian Oil Corporation Limited in Tiruvallur, Tamil Nadu.
* **Legal Basis:** The policy is enacted under the powers conferred by subsection 1 of section 3 of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962 (50 of 1962).
* **Schedule:** A schedule is annexed to the notification, describing the land in which the right of user is to be acquired, including specifics like district, taluk, village, and survey number (e.g., Thiruvallur, Uthukkottai, Panayancheri).
**6. Target Audience and Stakeholders:**
Based on the text, the directly affected target audience and stakeholders are:
* Landowners in the specified areas (Tamil Nadu, particularly in Thiruvallur district, Uthukkottai taluk, Panayancheri village) through which the pipeline will pass.
* Indian Oil Corporation Limited, as the entity responsible for the pipeline construction.
* The Competent Authority, Land Acquisition Officer at Indian Oil Corporation Limited, tasked with receiving and addressing objections.
* The Central Government (Ministry of Petroleum and Natural Gas) which is responsible for setting the policy and declaring the acquisition intention.
**7. Implementation Aspects (Inferred):**
* **Responsible Agency/Bodies:** The primary responsible bodies are the Ministry of Petroleum and Natural Gas and Indian Oil Corporation Limited. The Land Acquisition Officer at IOCL is directly responsible for the initial stages of land acquisition.
* **Timelines:** The text specifies a 21-day window for affected parties to submit written objections following the publication of the notification in the Gazette of India. Further timelines for the project's implementation are not specified within this document.
* **Procedures:** The text outlines the procedure for objecting to the land acquisition. The gazette publication serves as the trigger for the 21-day objection window.
**8. Expected Outcomes / Impact of Changes:**
Since this is a new policy, the expected outcomes are:
* **Facilitated Pipeline Construction:** The primary intended outcome is to enable the construction of the Ennore-Thiruvallur-Bengaluru-Puducherry-Nagapattinam-Madurai-Tuticorin natural gas pipeline.
* **Increased Natural Gas Transportation Capacity:** The pipeline is expected to increase the transportation capacity of natural gas in Tamil Nadu.
* **Economic Development:** Improved natural gas infrastructure can contribute to economic development in the region by providing access to a vital energy source for industries and households.
* **Potential Land Use Changes:** There will be an alteration of land use due to the easement required for the pipeline. Compensation and proper procedure for objection are provided to mitigate negative impacts of this change.
**9. Conclusion:**
The notification from the Ministry of Petroleum and Natural Gas signifies a crucial step towards expanding the natural gas infrastructure in Tamil Nadu. It outlines the government's intention to acquire the necessary land rights for the Ennore-Thiruvallur-Bengaluru-Puducherry-Nagapattinam-Madurai-Tuticorin pipeline project. By establishing a clear process for land acquisition and providing a mechanism for addressing objections, the policy aims to balance the public interest with the rights of affected landowners, thus enabling an important energy infrastructure project.
Key Entities Referenced
Ministry of Petroleum and Natural Gas: The Indian government ministry issuing the notification.
New Delhi: The location where the notification was issued.
2nd August, 2021: Date of the notification.
Ennore Thiruvallur Bengaluru Puducherry Nagapattinam Madurai Tuticorin pipeline: The name of the natural gas pipeline to be laid.
Indian Oil Corporation Limited: The company responsible for laying the natural gas pipeline.
Petroleum and Minerals Pipelines Acquisition of Right of User in Land Act, 1962: The law under which the land is being acquired for the pipeline.
Shri K.S.A.Mohamed Jaghir Hussain: Competent Authority, Land Acquisition Officer, Indian Oil Corporation Limited.
V.G.P. Nagar, Rajajipuram, Tiruvallur, Tamil Nadu: Address for communication regarding land acquisition objections.
Tamil Nadu: The state where the pipeline is to be laid and where the land acquisition is taking place.
Thiruvallur: District in Tamil Nadu affected by the land acquisition.
Uthukkottai: Taluk in Thiruvallur district, Tamil Nadu affected by the land acquisition.
Panayancheri: Village in Uthukkottai taluk, Thiruvallur district, Tamil Nadu affected by the land acquisition.
RAKESH MISHRA: Under Secretary.
रजजस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
xxxGIDHxxx
सी.जी.-डी.एल.-अ.-04082021-228748
xxxGIDExxx
CG-DL-E-04082021-228748
असाधारण
EXTRAORDINARY
भाग II—खण्ड 3—उप-खण्ड (ii)
PART II—Section 3—Sub-section (ii)
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 2907] नई ददल्ली, बधु वार, अगस्ट्त 4, 2021/श्रावण 13, 1943
No. 2907] NEW DELHI, WEDNESDAY, AUGUST 4, 2021/SHRAVANA 13, 1943
परे ोजलयम और प्राकृजतक गसै मत्रं ालय
अजधसचू ना
नई ददल्ली, 2 अगस्ट् त, 2021
का.आ. 3133(अ).—केन्द्रीय सरकार को लोकजहत में यह आवश्यक प्रतीत होता ह ै दक तजमलनाडु राज्य में नेचुरल
गैस पररवहन के जलए इंजडयन ऑइल कॉपोरेिन जलजमटेड के द्वारा एन्नोर– जतरुवल्लूर – बेंगलुरु – पुदचु ेरी – नागपरिनम –
मदरु ै – टूरटकोररन पाइपलाइन जबछाई जानी चाजहए I
और केन्द्रीय सरकार को ऐसी पाइपलाइन जबछाने के प्रयोजन के जलए यह आवश्यक प्रतीत होता ह ै दक ऐसी भूजम
म े जो इस से उपाबद्ध अनुसूची में वर्णणत ह ै और जजसम ें उक्त पाइपलाइन जबछाए जाने का प्रस्ट्ताव ह,ै उपयोग के अजधकार
का अजजन दकया जाए I
अत: अब, केन्द्रीय सरकार, पेरोजलयम और खजनज पाइपलाइन्द्स (भूजम में उपयोग के अजधकार का अजजन)
अजधजनयम, 1962 (1962 का 50) की धारा 3 की उपधारा (1) द्वारा प्रदत्त िजक्तयों का प्रयोग करते हुए, उस भूजम में
उपयोग के अजधकार का अजजन करने के अपने आिय की घोषणा करती ह ैI
कोई व्यजक्त, जो उक्त अनुसूची म ें वर्णणत भूजम में जहतबद्ध ह,ै उस तारीख से जजसको इस अजधसूचना से युक्त भारत
के राजपत्र की प्रजतया ाँ साधारण जनता को उपलब्ध करा दी जाती ह,ै इक्कीस ददन के भीतर भूजम के नीच े पाइपलाइन
जबछाए जाने के जलए उसमें उपयोग के अजधकार के अजजन के सम्बन्द्ध में श्री के.एस.ए. मोहम्मद जगीर हुसैन, सक्षम
प्राजधकारी, भूजम अजजन अजधकारी, इंजडयन ऑयल कॉपोरेिन जलजमटेड, पाइपलाइन पररयोजना, प्लाट सं-14, जयप्रकाि
स्ट्रीट, वी. जी. पी नगर, राजाजजपुरम, जतरुवल्लुर, तजमलनाडु - 602001 को जलजखत रूप में आक्षेप भजे सकेग I
4309 GI/2021 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
अनसु चू ी
राज्य : तजमलनाडु
क्षत्रे फल
उप खण्ड
जजला तालकु ा गावाँ का नाम सवक्षे ण स.ं- खण्ड स.ं
स.ं
हक्े टरे एयर वग जमीटर
1 2 3 4 5 6 7 8
जतरुवल्लूर ऊथ्थुक्कोिै 85. पनयनचेरर 232 3 00 06 00
[फा. सं. एल-14014/52/2021-जीपी-II]
राकेि जमश्रा, अवर सजचव
MINISTRY OF PETROLEUM AND NATURAL GAS
NOTIFICATION
New Delhi, the 2nd August, 2021
S.O. 3133(E).—Whereas, it appears to the Central Government that it is necessary in the public
interest that, for the transportation of Natural Gas in the State of Tamil Nadu, ―Ennore- Thiruvallur -
Bengaluru -Puducherry -Nagapattinam –Madurai- Tuticorin pipeline‖ should be laid by Indian Oil
Corporation Limited.
And whereas, it appears to the Central Government that for the purpose of laying such pipeline, it
is necessary to acquire the right of user in land under which the said pipeline is proposed to be laid and
which is described in the Schedule annexed hereto;
Now, therefore, in exercise of the powers conferred by sub-section (1) of section 3 of the Petroleum
and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962 (50 of 1962), the Central
Government hereby declares its intention to acquire the right of user therein;
Any person interested in the land described in the said schedule may, within twenty one days from
the date on which copies of the Gazette of India containing this notification are made available to the
general public, object in writing to the acquisition of the right of user therein for laying of the pipeline
under the land to Shri K.S.A.Mohamed Jaghir Hussain, Competent Authority, Land Acquisition Officer
Indian Oil Corporation Limited, Pipeline Projects, Plot No.14, Jayaprakash Street, V.G.P. Nagar,
Rajajipuram, Tiruvallur, Tamil Nadu – 602 001.
SCHEDULE
State : Tamil Nadu
Sub Area
Survey
District Taluk Name of the Village Division Square
No. Hectare Are
No. Meter
1 2 3 4 5 6 7 8
Thiruvallur Uthukkottai 85.Panayancheri 232 3 00 06 00
[F. No.L-14014/52/2021-GP-II]
RAKESH MISHRA, Under Secy.