Whereas the Central Government is engaged in creating an enabling policy and regulatory environment for the orderly

Issued by Ministry of Power · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

Executive Summary: This document outlines guidelines for the procurement of electricity for the medium term from power stations set up on a Finance, Own, and Operate (FOO) basis. It aims to promote competition and transparency in electricity procurement. These guidelines are effective from the date of publication in the official gazette, January 17, 2017. Key Points / Main Content: * **General Provisions:** * The guidelines are for power procurement agreements between one and five years, with possible extensions. * The Central Government issued a single "Standard Bidding Document" comprising the Model Request for Qualification (MRFQ), the Model Request for Proposal (MRFP), and the Model Agreement for Procurement of Power (MAPP). * These documents are to be adopted by distribution licensees for electricity procurement from power producers/traders/Discoms. * Procurement should occur through open, transparent competitive bidding on the DEEP eBidding Portal, selecting the lowest tariff from FOO-based power generating stations. * The eBidding portal can be found at www.mstcecommerce.com, as well as the Ministry of Power website and PFC Consulting Limited website. * **Tariff and Deviations:** * The tariff determined through the electronic bidding process will be adopted by the Appropriate Commission. * Deviations from the Model Bidding Documents require prior approval from the Appropriate Commission, unless they are project-specific modifications expressly permitted. * **Amendments and Repeals:** * Amendments related to coal block auctions for Thermal Power Stations set up on Design, Build, Finance, Own and Operate (DBFOO) basis also apply to these guidelines. * Guidelines issued on February 10, 2014, and amended on August 20, 2015, along with associated Model Bidding Documents issued on January 29, 2014, are repealed. * Agreements signed or actions taken before this date are not affected by the repeal and remain governed by the previous guidelines. Impact Analysis: * **Central Government:** * Impact: Responsible for creating policies and regulations to promote orderly growth and competition in electricity generation. * Action Required: Enforce and oversee the implementation of these guidelines. * **State Governments:** * Impact: Expected to support and facilitate the implementation of the guidelines within their respective jurisdictions. * Action Required: Ensure compliance with the guidelines by distribution licensees. * **Electricity Regulatory Commissions:** * Impact: Responsible for promoting competition in electricity procurement and approving tariffs. * Action Required: Adopt tariffs determined through the electronic bidding process and approve or reject deviations from the Model Bidding Documents. * **Distribution Licensees:** * Impact: Required to procure electricity through a competitive and transparent bidding process using the Standard Bidding Document. * Action Required: Adopt the Model Bidding Documents for power procurement, conduct bidding through the DEEP eBidding Portal, and seek approval for any deviations from the Model Bidding Documents. * **Power Producers/Traders/Discoms:** * Impact: Can participate in the bidding process to supply electricity to distribution licensees. * Action Required: Prepare and submit bids through the DEEP eBidding Portal, adhering to the terms and conditions of the Standard Bidding Document.

Key Entities Referenced

Electricity Act, 2003: An act of the Parliament of India to consolidate the laws relating to generation, transmission, distribution, trading and use of electricity Central Government: The Union Government of India. State Governments: The governments of the individual states within India. Electricity Regulatory Commissions: Commissions established to regulate the electricity sector. Finance, Own and Operate FOO: A model for power generating stations. Model Request for Qualification (MRFQ): Model document for qualification in power procurement. Model Request for Proposal (MRFP): Model document for proposal in power procurement. Model Agreement for Procurement of Power (MAPP): Model agreement for power procurement.
Official Source Record View Original Source →
See Full Document Text
jftLVªh laö Mhö ,yö&33004@99 REGD. NO. D. L.-33004/99 vlk/kj.k EXTRAORDINARY Hkkx I—[k.M 1 PART I—Section 1 izkf/dkj ls izdkf'kr PUBLISHED BY AUTHORITY la- 17] ubZ fnYyh] eaxyokj] tuojh 17] 2017@ ikS"k 27] 1938 No. 17] NEW DELHI, TUESDAY, JANUARY 17, 2017/PAUSA 27, 1938 ििििवववव(cid:3)(cid:3)(cid:3)(cid:3)ततुुततुु मममम(cid:9)(cid:9)ंं(cid:9)(cid:9)ंं ााााललललयययय ससससककंंककंं (cid:15)(cid:15)(cid:15)(cid:15)पपपप नई (cid:4)द(cid:6)ली, 17 जनवरी, 2017 ििििवववव(cid:3)(cid:3)(cid:3)(cid:3),,,, (cid:6)(cid:6)(cid:6)(cid:6)ववववााााििििमममम(cid:9)(cid:9)(cid:9)(cid:9)वववव औऔऔऔरररर (cid:12)(cid:12)(cid:12)(cid:12)चचचचााााललललनननन ((((एएएएफफफफओओओओओओओओ)))) आआआआधधधधाााारररर पपपपरररर (cid:6)(cid:6)(cid:6)(cid:6)थथथथााााििििपपपपतततत ििििवववव(cid:26)(cid:26)(cid:26)(cid:26)ततुुततुु (cid:6)(cid:6)(cid:6)(cid:6)टटटटेेशशेेशशनननन(cid:31)(cid:31)(cid:31)(cid:31) सससस ेे ेेमममम!!!!ययययााााववववििििधधधध ििििवववव(cid:26)(cid:26)(cid:26)(cid:26)ततुुततुु कककक$$$$ अअअअििििधधधध(cid:12)(cid:12)(cid:12)(cid:12)ाााािििि&&&& ककककेेेे ििििललललएएएए ''''ददददशशशशाााा---- ििििननननदददद)श)श)श)श सससस..ंं..ंं 22223333////11117777////2222000011113333----आआआआररररएएएएंडंडंडंडआआआआरररर((((खखखखडडंंडडंं ----VVVV))))....————जब(cid:3)क क(cid:6)(cid:7) सरकार िव(cid:13)ुत अिधिनयम, 2003 (""""अअअअििििधधधधििििननननययययमममम"""") के (cid:27)ावधान(cid:28) के अनुसार िव(cid:13)ुत उ(cid:30)पादन के सु!वि"थत िवकास के िलए एक स&म नीित और िविनयामक वातावरण तैयार करने के िलए (cid:27)ितब+ ह;ै जब(cid:3)क (cid:27)ित"प+ा-(cid:30)मक और पारदश/ (cid:27)(cid:3)0या1 के मा2यम स े िव(cid:13)ुत क3 अिध(cid:27)ाि4 म(cid:6) (cid:27)ित"प+ा- को बढ़ावा दने ा क(cid:6)(cid:7) सरकार, रा7य सरकार(cid:28), िव(cid:13)ुत िविनयामक आयोग(cid:28) और िवतरण लाइस(cid:6)सधारक(cid:28) के िलए आव;यक ह;ै जब(cid:3)क क(cid:6)(cid:7) सरकार न े िविभ= पणधारक(cid:28) और िवशेष?(cid:28) के साथ िव"तृत परामश- के बाद, उन िव(cid:13)ुत उ(cid:30)पादक(cid:28) से, जो म2याविध के िलए "िवA, "वािम(cid:30)व और (cid:27)चालन" (""""एएएएफफफफओओओओओओओओ"""")' के आधार पर अथवा िव(cid:13)ुत उ(cid:30)पादक(cid:28) के साथ बैक-टू-बैक (cid:27)बंध रखने वाल े !ापाEरय(cid:28)/िड"कॉम से ताप िव(cid:13)ुत "टेशन(cid:28) का िनमा-ण और/अथवा (cid:27)चालन करने के िलए सहमत ह(cid:28), िवतरण लाइस(cid:6)सधारक(cid:28) Jारा िव(cid:13)ुत क3 अिध(cid:27)ाि4 के िलए एक आदश - संिवदा(cid:30)मक ढांचा तैयार (cid:3)कया ह;ै जब(cid:3)क क(cid:6)(cid:7) सरकार ने अपने पL सं. 23/17/2013-आरएडं आर (खडं -II) (cid:3)दनांक 29 जनवरी, 2014, के मा2यम से मॉडल द"तावेज जारी (cid:3)कए ह S िजसम(cid:6) मॉडल पाLता अनरु ोध (""""एएएएममममआआआआररररएएएएफफफफ****यययय""""ूूूू ) मॉडल (cid:27)"ताव अनुरोध (""""एएएएममममआआआआररररएएएएफफफफपपपपीीीी"""") और मॉडल िव(cid:13)ुत अिध(cid:27)ाि4 करार (""""एएएएममममएएएएपपपपीीीीपपपपीीीी"""") (संयTु Uप से, """"ममममााााननननकककक बबबबोोोोललललीीीी दददद(cid:6)(cid:6)(cid:6)(cid:6)ततततााााववववजजेेजजेे """") शािमल ह S िजसे िबजली क3 अिध(cid:27)ाि4 के िलए िवतरण लाइस(cid:6)सधारक(cid:28) Jारा अपनाया जाना ह।ै 265 GI/2017 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART I—SEC. 1] उपयु-T के आधार पर, भारत सरकार ने 10 फरवरी, 2014 क3 संकXप सं. 23/17/2013-आरएडं आर (खडं -II) के मा2यम से (cid:3)दशा-िनदYश जारी (cid:3)कए थे िजZह (cid:6)आग े 20 अग"त, 2015 के संकXप के तहत संशोिधत (cid:3)कया गया था। जब(cid:3)क क(cid:6)(cid:7) सरकार ने, (cid:3)दनांक 16 जनवरी, 2017 के पL सं.23/17/2013-आरएंडआर(खंड-V)के तहत \सगल द"तावेज "मानक बोली द"तावेज" जारी (cid:3)कया ह ै िजसम(cid:6) दोन(cid:28) पाLता हते ु मॉडल अनरु ोध (""""एएएएममममआआआआररररएएएएफफफफ****यययय""ूू""ूू ) तथा (cid:27)"ताव हते ु मॉडल अनुरोध (""""एएएएममममआआआआररररएएएएफफफफपपपपीीीी""""), तथा िव(cid:13)ुत क3 अिध(cid:27)ाि4 हते ु मॉडल करार (""""एएएएममममएएएएपपपपीीीीपपपपीीीी"""") शािमल ह ै (संयTु Uप से, """"ममममााााननननकककक बबबबोोोोललललीीीी दददद(cid:6)(cid:6)(cid:6)(cid:6)ततततााााववववजजेेजजेे " तथा एमएपीपी को मॉडल बोली द"तावेज के Uप म (cid:6) संद]भत (cid:3)कया गया ह)ै और जो िवतरण लाइस(cid:6)िसय(cid:28) Jारा िव(cid:13)ुत के (cid:27)ापण के िलए एफओओ आधार पर िन]मत और/अथवा (cid:27)चािलत िव(cid:13)ुत उ(cid:30)पादन "टेशन(cid:28) से Zयूनतम (cid:27)शुXक के ऑफर पर आधाEरत वै(cid:13)ुत मचं (डीईईपी ई-िब\डग पोट-ल) के मा2यम स े खुली एवं पारदश/ (cid:27)ित"प+/ बोली Jारा िव(cid:13)ुत उ(cid:30)पादक(cid:28)/!ापाEरय(cid:28)/िड"कॉम(cid:28) से (cid:27)ा4 (cid:3)कए जान े ह।S िब\डग पोट-ल हते ु \लक wwwwwwwwwwww....mmmmssssttttcccceeeeccccoooommmmmmmmeeeerrrrcccceeee....ccccoooommmm,,,,ह ै तथा यह िव(cid:13)ुत मंLालय ((((wwwwwwwwwwww....ppppoooowwwweeeerrrrmmmmiiiinnnn....nnnniiiicccc....iiiinnnn)))) और पीएफसी कंस\Xटग िलिमटेड ((((wwwwwwwwwwww....ppppffffcccccccclllliiiinnnnddddiiiiaaaa....ccccoooommmm)))) पर भी उपलbध ह।ै इसिलए अब िव(cid:13)ुत अिधिनयम, 2003 क3 धारा 63 के अंतगत- (cid:27)दA शिTय(cid:28) का (cid:27)योग करत े dए क(cid:6)(cid:7) सरकार इन (cid:3)दशा-िनदYश(cid:28) को अिधसूिचत करती ह S िजZह (cid:6) िवA, "वािम(cid:30)व, (cid:27)चालन (एफओओ) आधार पर "थािपत िव(cid:13)ुत "टेशन(cid:28) से म2याविध के िलए िव(cid:13)ुत क3 अिध(cid:27)ाि4 हते ु (cid:3)दशा-िनदYश (""""''''ददददशशशशााााििििननननदददद)श)श)श)श"""") के Uप म (cid:6) जाना जाएगा। ये (cid:3)दशा-िनदYश शासक3य राजपL के (cid:27)काशन क3 तारीख से िनeिलिखत िनबंधन एवं शतf के अधीन रहत े dए इसक3 तारीख से (cid:27)भावी ह(cid:28)गेः 1. उपरोT मॉडल बोली द"तावेज(cid:28) म(cid:6) िनhदi िनबंधन एवं शतj, संदभ- Jारा इन (cid:3)दशा-िनदYश(cid:28) का भाग होगी और इZह (cid:6) इसी Uप म (cid:6) माना जाएगा। 2. इन (cid:3)दशा-िनदYश(cid:28) का लागू (cid:3)कया जाना उन पEरयोजना1 तक ही सीिमत होगा जहां से एक और पांच वषf क3 अविध के िलए पार"पEरक सहमित से आरंिभक करार अविध 25% तक अथवा एक वष-, जो भी कम हो, के िलए इस अविध को बढ़ाने के (cid:27)ावधान सिहत िव(cid:13)ुत क3 अिध(cid:27)ाि4 के करार के अनुसार िव(cid:13)ुत अिध(cid:27)ाि4 क3 जाती ह।ै 3. मॉडल बोली द"तावेज(cid:28) को शािमल करते dए इन (cid:3)दशा-िनदYश(cid:28) के आधार पर िव(cid:13)ुत बोली (cid:27)(cid:3)0या के मा2यम स े िनधा-Eरत (cid:27)शुXक अिधिनयम क3 धारा 63 के (cid:27)ावधान(cid:28) के अनसु रण म (cid:6) उपयुT आयोग Jारा अपनाया जाएगा। 4. िवतरण लाइस(cid:6)िसय(cid:28) Jारा मॉडल बोली द"तावेज(cid:28) से कोई िवचलन उपयुT आयोग के पूव- अनुमोदन स े ही (cid:3)कया जाएगा। बशतY यह (cid:3)क मॉडल बोली द"तावेज(cid:28) म (cid:6) अिभ!T Uप से अनुमित (cid:3)दए गए (cid:3)कसी पEरयोजना िवशेष संशोधन(cid:28) का अथ- मॉडल बोली द"तावेज(cid:28) से िवचलन के Uप म (cid:6) नहk लगाया जाएगा। 5. नई कोयला bलॉक नीलामी नीित को 2यान म (cid:6) रखते dए िव(cid:13)ुत मंLालय के (cid:3)दनांक 16 अ(cid:27)लै , 2015 के संकXप सं. 23/9/2015-आरएंडआर के मा2यम से िडजाइन, िनमा-ण, िवA, "वािम(cid:30)व और (cid:27)चालन (डीबीएफओओ) आधार पर "थािपत ताप िव(cid:13)ुत क(cid:6)(cid:7)(cid:28) से िव(cid:13)ुत क3 अिध(cid:27)ाि4 के (cid:3)दशा-िनदYश(cid:28) म (cid:6) (cid:3)कए गए संशोधन ययययथथथथााााआआआआवववव0000ययययकककक पपपप1111ररररववववततततनन22नन22 (cid:31)(cid:31)(cid:31)(cid:31) सिहत, िवA, "वािम(cid:30)व और (cid:27)चालन (एफओओ) आधार पर "थािपत िव(cid:13)ुत "टेशन(cid:28) स े म2यकािलक अविध के िलए िव(cid:13)ुत क3 अिध(cid:27)ाि4 पर भी लागू ह(cid:28)गे। िवतरण लाइस(cid:6)िसय(cid:28) Jारा, 29 जनवरी, 2014 को जारी मानक बोली द"तावेज(cid:28) सिहत िव(cid:13)तु क3 अिध(cid:27)ाि4 के िलए बोली (cid:27)(cid:3)0या Jारा (cid:27)शXु क के िनधा-रण हते ु 10 फरवरी, 2014 को जारी व 20 अग"त, 2015 को यथासंशोिधत (cid:3)दशा-िनदशY (cid:28) तथा उसके अतं गत- संशोधन(cid:28) को िनरिसत (cid:3)कया जाता ह।ै बशतY यह (cid:3)क इस तारीख से पूव- ह"ता&र (cid:3)कया गया कोई भी करार या क3 गई कोई भी कार-वाई उT (cid:3)दशा-िनदYश(cid:28) के ऐसे िनरसन Jारा (cid:27)भािवत नहk होगी और इसके अतं गत- िनरिसत (cid:3)दशा- िनदYश(cid:28) Jारा शािसत होती रहग(cid:6) ी। 7योित अरोरा, संयुT सिचव¹Hkkx IIIµ[k.M 4º Hkkjr dk jkti=k % vlk/kj.k 3 MINISTRY OF POWER RESOLUTION New Delhi, the 17th January, 2017 Guidelines for Procurement of Electricity for Medium Term from Power Stations set up on Finance, Own and Operate (FOO) basis No. 23/17/2013-R&R(Vol-V).—Whereas the Central Government is engaged in creating an enabling policy and regulatory environment for the orderly growth of generation of electricity in accordance with the provisions of the Electricity Act, 2003 (the “Act”); Whereas it is incumbent upon the Central Government, State Governments, Electricity Regulatory Commissions and the distribution licensees to promote competition in the procurement of electricity through competitive and transparent processes; Whereas the Central Government has, after extensive consultations with various stakeholders and experts, evolved a model contractual framework for procurement of electricity by the distribution licensees from power producers who agree to construct and/or operate power generating stations set up on ‘Finance, Own and Operate’ (“FOO”) basis for medium term power or from Traders/Discoms having back to back arrangements with power producers. Whereas the Central Government had, therefore issued vide its letter No. [No.23/17/2013-R&R] (Vol-II) dated 29th January 2014, the model documents comprising the Model Request for Qualification (the “MRFQ”) and the Model Request for Proposal (the “MRFP”), and Model Agreement for Procurement of Power (the 'MAPP') (collectively, the "Modal Bidding Documents") to be adopted by the distribution licensees for procurement of power from the power producers. Based on the above, the Government of India had notified the Guidelines vide resolution No. 23/17/2013-R&R (Vol-II) dated 10th February 2014, which were further amended vide resolution dated 20th August, 2015. Whereas, the Central Government has, vide its letter No. 23/17/2013-R&R (Vol-V) dated 16th January, 2017 issued a single document as the "Standard Bidding Document" comprising both the Model Request for Qualification (the “MRFQ”) and the Model Request for Proposal (the “MRFP”), and the Model Agreement for Procurement of Power (the “MAPP”) (collectively, the ‘Standard Bidding Document’ and the MAPP are referred to as the “Model Bidding Documents”) to be adopted by distribution licensees for procurement of electricity from the power producers/Traders/Discoms through a process of open and transparent competitive bidding through an electronic platform (DEEP e-Bidding Portal) based on offer of the lowest tariff from power generating stations constructed and/or operated on FOO basis. The link for the e-Bidding portal is www.mstcecommerce.com, and is also available on the website of Ministry of Power (www.powermin.nic.in) and PFC Consulting Limited (www.pfcclindia.com). Now, therefore, in exercise of the powers conferred under section 63 of the Electricity Act, 2003, the Central Government hereby notifies these guidelines to be known as the ‘Guidelines for Procurement of Electricity for medium term from Power Stations set up on Finance, Own and Operate (FOO) basis (the “Guidelines”). These Guidelines shall come into effect from the date of publication in the official gazette subject to the following terms and conditions: 1. The terms and conditions specified in the Model Bidding Documents referred to hereinabove shall, by reference, form part of these Guidelines and shall be treated as such. 2. The application of these Guidelines shall be restricted to projects from which power is procured in accordance with an Agreement for Procurement of Power for a period between one and five years, with a provision for extension of this period upto 25% of the initial contract period or one year whichever is lower, with mutual consent.4 THE GAZETTE OF INDIA : EXTRAORDINARY [PART I—SEC. 1] 3. The tariff determined through the electronic bidding process based on these Guidelines comprising the Model Bidding Documents shall be adopted by the Appropriate Commission in pursuance of the provisions of section 63 of the Act. 4. Any deviation from the Model Bidding Documents shall be made by the Distribution Licensees only with the prior approval of the Appropriate Commission. Provided, however, that any project specific modifications expressly permitted in the Model Bidding Documents shall not be construed as deviations from the Model Bidding Documents. 5. The amendments made in the Guidelines for Procurement of Electricity from Thermal Power Stations set up on Design, Build, Finance, Own and Operate (DBFOO) basis vide Ministry of Power Resolution No. 23/9/2015- R&R dated 16th April 2015 in view of new coal block auction policy, shall also apply, mutatis mutandis, for procurement of electricity for Medium Term from Power Stations set up on Finance, Own and Operate (FOO) basis. The ‘Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees’ issued on 10th February, 2014, as amended on 20th August 2015, including the Model Bidding Documents issued on 29th January 2014 and the amendment thereof are hereby repealed. Provided, however, that any agreements signed or actions taken prior to the date hereof shall not be affected by such repeal of the said guidelines and shall continue to be governed by the guidelines repealed hereunder. JYOTI ARORA, Jt. Secy. Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064 and Published by the Controller of Publications, Delhi-110054.