See Full Document Text
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
STATUTORY INSTRUMENTS
2026 No. 151
INFRASTRUCTURE PLANNING
The Fenwick Solar Farm Order 2026
Made - - - - 18th February 2026
Coming into force - - 11th March 2026
An application has been made to the Secretary of State for an order granting development consent
under section 37 of the Planning Act 2008 (“the 2008 Act”)(1) in accordance with the Infrastructure
Planning (Applications: Prescribed Forms and Procedure) Regulations 2009(2).
The application has been examined by the Examining Authority appointed by the Secretary of State
pursuant to chapter 2 of Part 6 of the 2008 Act and carried out in accordance with Chapter 4 of Part
6 of the Infrastructure Planning (Examination Procedure) Rules 2010(3).
The Examining Authority, having considered the application together with the documents that
accompanied it, and the representations made and not withdrawn, has, in accordance with
section 74(2)(4) of the 2008 Act made a report and recommendation to the Secretary of State.
The Secretary of State has considered the report and recommendation of the Examining Authority,
has taken into account the environmental information in accordance with regulation 4 of the
Infrastructure Planning (Environmental Impact Assessment) Regulations 2017(5) and has had regard
to the documents and matters referred to in section 104(2) of the 2008 Act.
The Secretary of State, having decided the application, has determined to make an Order giving
effect to the proposals comprised in the application on the terms that in the opinion of the Secretary
of State are not materially different from those proposed in the application.
The Secretary of State, in exercise of the powers conferred by sections 114(6), 115(7), 117 (8),
120(9), 122(10) 123(11) and 140 of the 2008 Act, makes the following Order.
(1) 2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act 2011 (c. 20). Section 37 was amended by
sections 128(2) and 137 of, and paragraphs 1 and 5 of Part 1 of Schedule 13 to, the Localism Act 2011 (c. 20).
(2) S.I. 2009/2264, amended by S.I. 2010/439, S.I. 2010/602, S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522,
S.I. 2013/755, S.I. 2014/469, S.I. 2014/2381, S.I. 2015/377, S.I. 2015/1682, S.I. 2017/524, S.I. 2017/572 and S.I. 2018/378.
(3) S.I. 2010/103, amended by S.I. 2012/635.
(4) As amended by paragraph 29(1) and (3) of Part 1 of Schedule 13 to the Localism Act 2011 (c. 20).
(5) S.I. 2017/572.
(6) As amended by paragraph 55 of Part 1 of Schedule 13 to the Localism Act 2011 (c. 20).
(7) As amended by paragraph 56 of Part 1 of Schedule 13 and Part 20 of Schedule 25 to the Localism Act 2011, section 160 of
the Housing and Planning Act 2016 (c. 22) and section 43 of the Wales Act 2017 (c. 4).
(8) As amended by paragraph 58 of Part 1 of Schedule 13 to the Localism Act 2011 (c. 20).
(9) As amended by section 140 and paragraph 60 of Part 1 of Schedule 13 to the Localism Act 2011 (c. 20).
(10) As amended by paragraph 62 of Part 1 of Schedule 13 to the Localism Act 2011 (c. 20).
(11) Ibid.Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
PART 1
PRELIMINARY
Citation and commencement
1. This Order may be cited as the Fenwick Solar Farm Order 2026 and comes into force on 11th
March 2026.
Interpretation
2.—(1) In this Order—
“the 1961 Act” means the Land Compensation Act 1961(12);
“the 1965 Act” means the Compulsory Purchase Act 1965(13);
“the 1980 Act” means the Highways Act 1980(14);
“the 1981 Act” means the Compulsory Purchase (Vesting Declarations) Act 1981(15);
“the 1984 Act” means the Road Traffic Regulation Act 1984(16);
“the 1989 Act” means the Electricity Act 1989(17);
“the 1990 Act” means the Town and Country Planning Act 1990(18);
“the 1991 Act” means the New Roads and Street Works Act 1991(19);
“the 2008 Act” means the Planning Act 2008(20);
“address” includes any number or address used for the purposes of electronic transmission;
“apparatus” has the same meaning as in Part 3 (street works in England and Wales) of the 1991
Act except that, unless otherwise provided, it further includes pipelines (and parts of them),
aerial markers, cathodic protection test posts, field boundary markers, transformer rectifier
kiosks, electricity cables, telecommunications equipment and electricity cabinets;
“authorised development” means the development and associated development, which is
development within the meaning of section 32 (meaning of “development”) of the 2008 Act,
authorised by this Order and as described in Schedule 1 (authorised development);
“book of reference” means the document of that name identified in the table at Schedule 12
(documents and plans to be certified) and which is certified by the Secretary of State as the
book of reference for the purposes of this Order;
“building” includes any structure or erection or any part of a building, structure or erection;
“carriageway” has the same meaning as in the 1980 Act;
“commence” means beginning to carry out a material operation, as defined in section 155
(when development begins) of the 2008 Act, comprised in or carried out or for the purposes
of the authorised development other than the permitted preliminary works (except where
stated to the contrary) and “commencement”, “commenced” and cognate expressions are to
be construed accordingly;
(12) 1961 c. 33.
(13) 1965 c. 56.
(14) 1980 c. 66.
(15) 1981 c. 66.
(16) 1984 c. 27.
(17) 1989 c. 29.
(18) 1990 c. 8.
(19) 1991 c. 22. Section 48(3A) was inserted by section 124 of the Local Transport Act 2008 (c. 26). Sections 78(4), 80(4) and
83(4) were amended by section 40 of, and Schedule 1 to, the Traffic Management Act 2004 (c. 18).
(20) 2008 c. 29.
2Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
“date of final commissioning” means the date on which the authorised development
commences operation by generating electricity on a commercial basis but excluding the
generation of electricity during commissioning and testing;
“electronic transmission” means a communication transmitted—
(a) by means of an electronic communications network; or
(b) by other means but while in electronic form;
“environmental statement” means the document of that name identified in the table at
Schedule 12 and which is certified by the Secretary of State as the environmental statement
for the purposes of this Order;
“footpath” and “footway” have the same meaning as in the 1980 Act;
“framework archaeological mitigation strategy” means the document of that name identified
in the table at Schedule 12 and which is certified by the Secretary of State as the framework
archaeological mitigation strategy for the purposes of this Order;
“framework construction environmental management plan” means the document of that name
identified in the table at Schedule 12 and which is certified by the Secretary of State as the
framework construction environmental management plan for the purposes of this Order;
“framework construction traffic management plan” means the document of that name
identified in the table at Schedule 12 and which is certified by the Secretary of State as the
framework construction traffic management plan for the purposes of this Order;
“framework decommissioning environmental management plan” means the document of that
name identified in the table at Schedule 12 and which is certified by the Secretary of State as the
framework decommissioning environmental management plan for the purposes of this Order;
“framework drainage strategy” means the document of that name identified in the table at
Schedule 12 and which is certified by the Secretary of State as the framework drainage strategy
for the purposes of this Order;
“framework landscape and ecological management plan” means the document of that name
identified in the table at Schedule 12 and which is certified by the Secretary of State as the
framework landscape and ecological management plan for the purposes of this Order;
“framework operational environmental management plan” means the document of that name
identified in the table at Schedule 12 and which is certified by the Secretary of State as the
framework operational environmental management plan for the purposes of this Order;
“framework public rights of way management plan” means the document of that name
identified in the table at Schedule 12 and which is certified by the Secretary of State as the
framework public rights of way management plan for the purposes of this Order;
“framework skills, supply chain and employment plan” means the plan of that name identified
in the table at Schedule 12 and which is certified by the Secretary of State as the framework
skills, supply chain and employment plan for the purposes of this Order;
“framework soil management plan” means the document of that name identified in the table at
Schedule 12 and which is certified by the Secretary of State as the framework soil management
plan for the purposes of this Order;
“highway” and “highway authority” have the same meaning as in the 1980 Act(21);
“holding company” has the same meaning as in section 1159 of the Companies Act 2006(22);
“land plans” means the plans of that name identified in the table at Schedule 12 and which are
certified by the Secretary of State as the land plans for the purposes of this Order;
(21) “highway” is defined in section 328(1). For “highway authority” see section 1.
(22) 2006 c. 46.
3Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
“maintain” includes inspect, repair, adjust, alter, remove, refurbish, reconstruct, replace and
improve any part of, but not remove, reconstruct or replace the whole of, the authorised
development and “maintenance” and “maintaining” are to be construed accordingly;
“National Grid” means National Grid Electricity Transmission plc (company number 2366977)
whose registered office is at 1-3 Strand, London, WC2N 5EH or any successor as a licence
holder within the meaning of Part 1 of the Electricity Act 1989;
“Order land” means the land which is required for, or is required to facilitate, or is incidental
to, or is affected by the authorised development shown coloured pink, blue, yellow or green
on the land plans and described in the book of reference;
“Order limits” means the limits shown on the land plans within which the authorised
development may be carried out and land acquired or used;
“outline design parameters statement” means the document of that name identified in the table
at Schedule 12 and which is certified by the Secretary of State as the outline design principles
for the purposes of this Order;
“owner”, in relation to land, has the same meaning as in section 7 (Interpretation) of the
Acquisition of Land Act 1981(23);
“permit scheme” means The Traffic Management (Doncaster Borough Council) Permit
Scheme Order 2019, or any subsequent Permit Scheme Order made by the City of Doncaster
Council to vary or replace that Order as may be relevant and which is made under Part 3 of the
Traffic Management Act 2004, as applicable for the location of the relevant works;
“permitted preliminary works” means all or any of—
(a) environmental surveys, geotechnical surveys, intrusive archaeological surveys and other
investigations for the purpose of assessing ground conditions;
(b) removal of plant and machinery;
(c) above ground site preparation for temporary facilities for the use of contractors during
construction;
(d) remedial work in respect of any contamination or other adverse ground conditions;
(e) diversion and laying of apparatus;
(f) the provision of temporary means of enclosure and site security for construction;
(g) the temporary display of site notices or advertisements;
(h) site clearance (including vegetation removal, demolition of existing structures); or
(i) advanced planting to allow for an early establishment of protective screening;
“plot” means any plot as may be identified by reference to a number and which is listed in the
book of reference and shown on the land plans;
“relevant planning authority” means the City of Doncaster Council or any successor to it as
local planning authority for the land to which the provisions of this Order apply;
“requirements” means those matters set out in Schedule 2 (requirements) and any reference to
a numbered requirement is to be construed accordingly;
“statutory undertaker” means any person falling within section 127(8) (statutory undertakers’
land) of the 2008 Act and includes a public communications provider defined by section 151(1)
(interpretation of chapter 1) of the Communications Act 2003(24);
(23) 1981 c. 67.
(24) 2003 c. 21.
4Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
“street” means a street within the meaning of section 48 (streets, street works and undertakers)
of the 1991 Act, together with land on the verge of a street or between two carriageways, and
includes any footpath and part of a street;
“street authority”, in relation to a street, has the same meaning as in Part 3 of the 1991 Act(25);
“streets, access and rights of way plans” means the plans of that name identified in the table at
Schedule 12 and which are certified by the Secretary of State as the streets, access and rights
of way plans for the purposes of this Order;
“street works” means the works listed in article 8(1) (street works);
“subsidiary” has the same meaning as in section 1159 of the Companies Act 2006(26);
“traffic authority” has the same meaning as in section 121A (traffic authorities) of the 1984
Act(27);
“traffic regulation measures plan” means the document of that name identified in the table at
Schedule 12 and which is certified by the Secretary of State as the traffic regulation measures
plan for the purposes of this Order;
“undertaker” means Fenwick Solar Project Limited (company number 13705886) and any
other person who for the time being has the benefit of this Order in accordance with article 35
(benefit of the Order) or article 36 (consent to transfer the benefit of the Order);
“Upper Tribunal” means the Lands Chamber of the Upper Tribunal;
“watercourse” includes every river, stream, creek, ditch, drain, canal, cut, culvert, dyke, sluice,
sewer and passage through which water flows except a public sewer or drain (except where
stated to the contrary);
“working day” means any day apart from Saturday, Sunday or any statutory bank or public
holiday; and
“works plans” means the plans of that name identified in the table at Schedule 12 and which
are certified by the Secretary of State as the works plans for the purposes of this Order.
(2) References in this Order to rights over land include references to rights to do or restrain or to
place and maintain anything in, on or under land or in the airspace above its surface and to any trusts
or incidents (including restrictive covenants) to which the land is subject and references in this Order
to the imposition of restrictive covenants are references to the creation of rights over land which
interfere with the interests or rights of another and are for the benefit of land which is acquired under
this Order or over which rights are created and acquired under this Order or is otherwise comprised
in this Order.
(3) All distances, directions, capacities and lengths referred to in this Order are approximate and
distances between lines or points on a numbered work comprised in the authorised development and
shown on the works plans and streets, access and rights of way plans are to be taken to be measured
along that work.
(4) References in this Order to numbered works are references to the works comprising the
authorised development as numbered in Schedule 1 and shown on the works plans and a reference in
this Order to a work designated by a number is a reference to the work so designated in that Schedule.
(5) In this Order, the expression “includes” is to be construed without limitation.
(6) In this Order, references to any statutory body include that body’s successor bodies.
(25) “street authority” is defined in section 49 which was amended by paragraph 117 of Schedule 1 to the Infrastructure Act 2015
(c. 7).
(26) 2006 c. 46.
(27) Section 121A was inserted by paragraph 70 of Schedule 8 to the 1991 Act, and subsequently amended by section 271 of the
Greater London Authority Act 1999 (c. 29); section 1(6) of, and paragraphs 70 and 95 of Schedule 1 to, the Infrastructure
Act 2015; and S.I. 1999/1920 and S.I. 2001/1400.
5Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(7) In this Order, all references to the singular is a reference to the plural, and vice versa, except
where explicitly stated.
(8) All areas described in square metres in the book of reference are approximate.
(9) In this Order, references to materially new or materially different environmental effects in
comparison with those reported in the environmental statement are not to be construed so as to
include the avoidance, removal or reduction of an assessed adverse environmental effect or a positive
environmental effect, or the increase of an assessed positive environmental effect.
PART 2
PRINCIPAL POWERS
Development consent etc. granted by this Order
3.—(1) Subject to the provisions of this Order and the requirements in Schedule 2 (requirements),
the undertaker is granted development consent for the authorised development in Schedule 1
(authorised development) to be carried out within the Order limits.
(2) Each numbered work must be situated within the corresponding numbered area shown on
the works plans.
(3) The development consent granted under sub-paragraph (1) authorises the carrying out within
the Order limits of either Work No. 4 or Work No. 5(b) but not both.
Operation of generating station
4.—(1) The undertaker is authorised to use and operate the generating station comprised in the
authorised development.
(2) This article does not relieve the undertaker of any requirement to obtain any permit or licence
under any other legislation that may be required from time to time to authorise the operation of an
electricity generating station.
Power to maintain the authorised development
5.—(1) The undertaker may at any time maintain the authorised development, except to the extent
that this Order, or an agreement made under this Order, provides otherwise.
(2) This article only authorises the carrying out of maintenance works within the Order limits.
(3) This article does not authorise the carrying out of any works which are likely to give rise to
any materially new or materially different effects that have not been assessed in the environmental
statement.
Disapplication and modification of statutory provisions
6.—(1) The following provisions do not apply in relation to the construction of any work or the
carrying out of any operation required for the purposes of, or in connection with, the construction,
operation or maintenance of any part of the authorised development—
(a) section 23 (prohibition of obstructions, etc. in watercourses) of the Land Drainage Act
1991(28);
(28) 1991 c. 59. Section 23 was amended by paragraph 192(2) of Schedule 22 to the Environment Act 1995 (c. 25), paragraphs 25
and 32 of Schedule 2 to the Flood and Water Management Act 2010 (c. 29) and S.I. 2013/755.
6Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(b) section 32 (variation of awards)(29) of the Land Drainage Act 1991;
(c) the provisions of any byelaws made under section 66 (powers to make byelaws)(30) of
the Land Drainage Act 1991;
(d) the provisions of any byelaws made under, or having effect as if made under, paragraphs
5, 6 or 6A of Schedule 25 (byelaw making powers of the appropriate agency) to the Water
Resources Act 1991(31);
(e) section 118 (consent request for discharge of trade effluent into public sewer) of the Water
Industry Act 1991(32);
(f) regulation 12 (requirement for environmental permit) of the Environmental Permitting
(England and Wales) Regulations 2016(33) in respect of a flood risk activity only except
in respect of the construction of any work or the carrying out of any operation required for
the purposes of, or in connection with, the construction, operation or maintenance of any
part of the authorised development undertaken within Plots 9/09, 9/12, 9/13, 9/14, 9/15,
10/01, 10/02, 10/03, 10/04, 10/05, 10/06, 10/07, 10/08, 10/09, 10/10, 10/11, 10/12, 10/13
and 10/14 as marked within the land plans;
(g) the legislation listed in Schedule 3 (legislation to be disapplied) in so far as the provisions
still in force are incompatible with the powers contained within this Order; and
(h) the provisions of the Neighbourhood Planning Act 2017(34) insofar as they relate to the
temporary possession of land under articles 30 (temporary use of land for constructing
the authorised development) and 31 (temporary use of land for maintaining the authorised
development) of this Order.
(2) For the purposes of section 9 (requirement of licence for felling) of the Forestry Act 1967(35)
any felling comprised in the carrying out of any work or operation required for the purposes of, or
in connection with, the construction of the authorised development is deemed to be immediately
required for the purpose of carrying out development authorised by planning permission granted
under the 1990 Act.
(3) Notwithstanding the provisions of section 208 (liability) of the 2008 Act, for the purposes
of regulation 6 (meaning of “development”) of the Community Infrastructure Levy Regulations
2010(36) any building comprised in the authorised development is deemed to be—
(a) a building into which people do not normally go; or
(b) a building into which people go only intermittently for the purpose of inspecting or
maintaining fixed plant or machinery.
(29) Section 32 was amended by S.I. 2013/755.
(30) Section 66 was amended by paragraphs 25 and 38 of Schedule 2 to the Flood and Water Management Act 2010 and section 86
of the Water Act 2014 (c. 21).
(31) Paragraph 5 was amended by section 100 of the Natural Environment and Rural Communities Act 2006 (c. 16), section 84
of, and paragraph 3 of Schedule 11 to, the 2009 Act and S.I. 2013/755. Paragraph 6 was amended by section 105 of, and
paragraph 26 of Schedule 15 to, the Environment Act 1995, sections 224, 233 and 321 of, and paragraphs 20 and 24 of
Schedule 16 and Part 5(B) of Schedule 22 to, the 2009 Act and S.I. 2013/755. Paragraph 6A was inserted by section 103(3)
of the Environment Act 1995.
(32) 1991 c. 56. Section 118 was amended by sections 2(2)(b) and 5(5)(f) of the Environment Act 1995 (c. 25) and sections 66(2)
(a) and (b) of the Environment (Wales) Act 2016 (anaw 3).
(33) S.I. 2016/1154. Regulation 12 was amended by S.I. 2018/110.
(34) 2017 c. 20.
(35) Section 9 was amended by section 4 of, and paragraph 141 of Schedule 2 to, the Planning (Consequential Provisions) Act
1990 (c. 11) and S.I. 2013/755. There are other amendments to section 9 that are not relevant to this Order.
(36) S.I. 2010/948, amended by S.I. 2011/987. There are other amending instruments but none are relevant to this Order.
7Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Defence to proceedings in respect of statutory nuisance
7.—(1) Where proceedings are brought under section 82(1) (summary proceedings by a person
aggrieved by statutory nuisance) of the Environmental Protection Act 1990(37) in relation to a
nuisance falling within paragraph (g) of section 79(1) (noise emitted from premises so as to be
prejudicial to health or a nuisance) of that Act no order may be made, and no fine may be imposed,
under section 82(2) of that Act if—
(a) the defendant shows that the nuisance—
(i)relates to premises used by the undertaker for the purposes of or in connection with
the construction, maintenance or decommissioning of the authorised development
and that the nuisance is attributable to the construction, maintenance or
decommissioning of the authorised development in accordance with a notice served
under section 60 (control of noise on construction site) of the Control of Pollution Act
1974(38), or a consent given under section 61 (prior consent for work on construction
sites) of that Act;
(ii)is a consequence of the construction or maintenance of the authorised development
and that it cannot reasonably be avoided; or
(b) the nuisance is a consequence of the use of the authorised development and that it cannot
be reasonably avoided.
(2) Section 61(9) (prior consent for work on construction sites) of the Control of Pollution Act
1974, does not apply where the consent relates to the use of the premises by the undertaker for the
purposes of, or in connection with, the construction or maintenance of the authorised development.
PART 3
STREETS
Street works
8.—(1) The undertaker may, for the purposes of the authorised development, enter on so much
of any of the streets specified in Schedule 4 (streets subject to street works) and may—
(a) break up or open the street, or any sewer, drain or tunnel under it;
(b) drill, tunnel or bore under the street;
(c) place and keep apparatus in the street;
(d) maintain apparatus in the street, change its position or remove it;
(e) repair, replace or otherwise alter the surface or structure of the street or any culvert under
the street; and
(f) execute any works required for or incidental to any works referred to in sub-paragraphs (a)
to (e).
(2) The authority given by paragraph (1) is a statutory right or licence for the purposes of sections
48(3) (streets, street works and undertakers) and 51(1) (prohibition of unauthorised street works)
of the 1991 Act.
(3) Where the undertaker is not the street authority, the provisions of sections 54 (notice of certain
works) to 106 (index of defined expressions) of the 1991 Act apply to any street works carried out
under paragraph (1).
(37) 1990 c. 43. Section 82 was amended by section 103 of the Clean Neighbourhoods and Environment Act 2005 (c. 16); section 79
was amended by sections 101 and 102 of the same Act. There are other amendments not relevant to this Order.
(38) 1974 c. 40.
8Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Application of permit scheme
9.—(1) The permit scheme applies with the modifications set out in this article to street works
carried out under the powers conferred by article 8 (street works), article 10 (power to alter layout,
etc., of streets), article 11 (construction and maintenance of altered streets) and article 15 (access
to works) of this Order.
(2) For the purposes of this Order—
(a) a permit may not be refused or granted subject to conditions which relate to the imposition
of moratoria;
(b) a permit may not be granted subject to conditions where compliance with those conditions
would constitute a breach of this Order or where the undertaker would be unable to comply
with those conditions through the exercise of the powers conferred by this Order;
(c) a permit may not be refused where the proposed reason for refusal is the inability to impose
a condition where that condition would not comply with sub-paragraph(b); and
(d) where a provisional advance authorisation has been granted to the undertaker in advance
of the grant of a permit in relation to the construction of the authorised development, the
highway authority may not grant a permit for any other works in the location during the
time period to which that provisional advance authorisation relates save that nothing will
restrict the ability of the highway authority to grant a permit for immediate works.
(3) Irrespective of anything which is stated to the contrary within the permit scheme, where the
undertaker submits an application for a permit in relation to street works carried out under article 8
(street works) of this Order subject to proposed conditions and the highway authority wishes for
different conditions to be imposed on the permit, the highway authority must seek to reach agreement
with the undertaker on the conditions subject to which the permit is to be granted and provide
alternative permit conditions, as appropriate, to the undertaker within 10 working days following
the date on which the application for the permit is made by the undertaker and must not refuse an
application for a permit before the end of the period which is five working days following the date
on which the alternative permit conditions are provided to the undertaker.
(4) Where the undertaker confirms its agreement to the alternative permit conditions provided
by the relevant highway authority pursuant to paragraph (3) before the expiry of five working days
following the date on which any such alternative permit conditions are provided to the undertaker,
the relevant highway authority must grant the permit subject to those conditions.
(5) Any alternative permit conditions provided by the highway authority in accordance with
paragraph (3) must comply with paragraph (2).
(6) References to moratoria in paragraph (2) mean restrictions imposed under section 58
(restrictions on works following substantial road works) or section 58A (restrictions on works
following substantial street works) of the 1991 Act.
(7) Reference to immediate works in paragraph (2)(d) means emergency works as that term is
defined in section 52 (emergency works) of the 1991 Act and urgent works as that term is defined
in regulation 3(1) of the Street Works (Registers, Notices, Directions and Designations) (England)
Regulations 2007.
(8) Without restricting the undertaker’s recourse to any alternative appeal mechanism which
may be available under the permit scheme or otherwise, the undertaker may appeal any decision to
refuse to grant a permit or to grant a permit subject to conditions pursuant to the permit scheme in
accordance with the mechanism set out in Schedule 15 (Discharge of Requirements) of this Order
in the same way as if it were a requirement.
9Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Power to alter layout, etc., of streets
10.—(1) The undertaker may for the purposes of the authorised development alter the layout of
or carry out any works in the street—
(a) in the case of the streets specified in column 2 of the table in Part 1 (permanent alteration of
layout) of Schedule 5 (alteration of streets) permanently in the manner specified in relation
to that street in column 3; and
(b) in the case of the streets as specified in column 2 of the table in Part 2 (temporary alteration
of layout) of Schedule 5 temporarily in the manner specified in relation to that street in
column 3.
(2) Without prejudice to the specific powers conferred by paragraph (1), but subject to
paragraphs (3) and (4), the undertaker may, for the purposes of constructing, operating or maintaining
the authorised development, alter the layout of any street and, without limitation on the scope of this
paragraph, the undertaker may—
(a) alter the level or increase the width of any kerb, footway, cycle track or verge;
(b) make and maintain passing places; and
(c) alter, remove, replace and relocate any street furniture, including bollards, lighting
columns, road signs and chevron signs.
(3) The undertaker must restore any street that has been temporarily altered under this Order to
the reasonable satisfaction of the street authority.
(4) The powers conferred by paragraph (2) must not be exercised without the prior consent of the
street authority, such consent to be in a form reasonably required by the street authority who may
attach reasonable conditions to any such consent.
(5) Paragraphs (3) and (4) do not apply where the undertaker is the street authority for a street
in which the works are being carried out.
Construction and maintenance of altered streets
11.—(1) The permanent alterations to each of the streets specified in Part 1 (permanent alteration
of layout) of Schedule 5 (alteration of streets) to this Order must be completed to the reasonable
satisfaction of the highway or street authority (as relevant) and, unless otherwise agreed by the
highway or street authority, the alterations must be maintained by and at the expense of the undertaker
for a period of 12 months from their completion and from the expiry of that period by and at the
expense of the highway or street authority (as relevant).
(2) Subject to paragraph (3), the temporary alterations to each of the streets specified in Part 2
(temporary alteration of layout) of Schedule 5 must be completed to the reasonable satisfaction of
the street authority and the temporary alterations must be maintained by and at the expense of the
undertaker for the duration that the temporary alterations are used by the undertaker for the purposes
of construction or decommissioning of the authorised development.
(3) Those restoration works carried out pursuant to article 10(3) (power to alter layout, etc.,
of streets) must be completed to the reasonable satisfaction of the street authority and must be
maintained by the undertaker for a period of 12 months from their completion and from the expiry
of that period by and at the expense of the street authority.
(4) In any action against the undertaker in respect of loss or damage resulting from any failure
by it to maintain a street under this article, it is a defence (without prejudice to any other defence or
the application of the law relating to contributory negligence) to prove that the undertaker had taken
such care as in all the circumstances was reasonably required to secure that the part of the street to
which the action relates was not dangerous to traffic.
10Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(5) For the purposes of a defence under paragraph (4), a court must in particular have regard to
the following matters—
(a) the character of the street including the traffic which was reasonably to be expected to
use it;
(b) the standard of maintenance appropriate for a street of that character and used by such
traffic;
(c) the state of repair in which a reasonable person would have expected to find the street;
(d) whether the undertaker knew, or could reasonably have been expected to know, that the
condition of the part of the street to which the action relates was likely to cause danger
to users of the street; and
(e) where the undertaker could not reasonably have been expected to repair that part of the
street before the cause of action arose, what warning notices of its condition had been
displayed,
but for the purposes of such a defence it is not relevant that the undertaker had arranged for a
competent person to carry out or supervise the maintenance of that part of the street to which the
action relates unless it is also proved that the undertaker had given that person proper instructions
with regard to the maintenance of the street and that those instructions had been carried out.
(6) Paragraphs (2) to (5) do not apply where the undertaker is the street authority for a street in
which the works are being carried out.
Temporary closure of streets and public rights of way
12.—(1) The undertaker, during and for the purposes of constructing or maintaining the
authorised development, may temporarily close, prohibit the use of, restrict the use of, authorise the
use of, alter or divert any street or public right of way and may for any reasonable time—
(a) divert the traffic or a class of traffic from the street or public right of way;
(b) authorise the use of motor vehicles on classes of public rights of way where,
notwithstanding the provisions of this article, there is otherwise no public right to use
motor vehicles; and
(c) subject to paragraph (2), prevent all persons from passing along the street or public right
of way.
(2) The undertaker must provide reasonable access for pedestrians going to or from premises
abutting a street or public right of way affected by the temporary closure, prohibition, restriction,
alteration or diversion of a street or public right of way under this article if there would otherwise
be no such access.
(3) Without prejudice to the generality of paragraph (1), the undertaker may temporarily close,
prohibit the use of, authorise the use of, restrict the use of, alter or divert—
(a) the streets specified in column 2 of the table in Part 1 (streets to be temporarily closed)
of Schedule 6 (streets and public rights of way) to the extent specified in column 3 of
that table;
(b) the public rights of way specified in column 2 of the table in Part 2 (public rights of way
to be temporarily closed and diverted) of Schedule 6 to the extent specified in column 3
of that table;
(c) the public rights of way specified in column 2 of the table in Part 3 (permanent use of
motor vehicles on public rights of way) of Schedule 6 to the extent specified in column
3 of that table;
(d) the public rights of way specified in column 2 of the table in Part 4 (temporary management
of public rights of way) of Schedule 6 to the extent specified in column 3 of that table; and
11Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(e) the public rights of way specified in column 2 of the table in Part 5 (temporary use of
motor vehicles on public rights of way) of Schedule 6 to the extent specified in column
3 of that table.
(4) The undertaker must not temporarily close, prohibit the use of, authorise the use of, restrict
the use of, alter or divert—
(a) any street or public right of way specified in paragraph (3) without first consulting the
street authority; and
(b) any other street or public right of way without the consent of the street authority, and the
street authority may attach reasonable conditions to any such consent.
(5) Any person who suffers loss by the suspension of any private right of way under this article
is entitled to compensation to be determined, in case of dispute, under Part 1 (determination of
questions of disputed compensation) of the 1961 Act.
(6) Without prejudice to the scope of paragraph (1), the undertaker may use any street or public
right of way which has been temporarily closed under the powers conferred by this article and within
the Order limits as a temporary working site.
(7) In this article expressions used in this article and in the 1984 Act have the same meaning.
(8) Nothing in this article prevents the undertaker from temporarily closing, prohibiting the use
of, authorising the use of, restricting the use of, altering or diverting a street or public right of way
under this article more than once.
(9) The undertaker, during and for the purposes of carrying out the authorised development, may
close, prohibit the use of, restrict the use of, alter or divert any public right of way within the Order
limits which is added to the definitive map and statement (within the meaning of the Wildlife and
Countryside Act 1981) on or after 31 October 2024.
Stopping up of public rights of way
13.—(1) Subject to the provisions of this article, the undertaker may close the public rights of
way shown on the rights of way and access plans and specified in Part 6 (stopping up and diversion
of public rights of way) of Schedule 6 (streets and public rights of way) to the extent specified and
described in column (3) of that Part of that Schedule.
(2) No public right of way specified in Part 6 of Schedule 6 is to be wholly or partly stopped
up under this article unless—
(a) the new public right of way to be constructed and substituted for it, which is specified in
column (4) of that Part of that Schedule, has been completed to the reasonable satisfaction
of the street authority and is open for use; or
(b) an appropriate temporary alternative route for the passage of such traffic as could have
used the public right of way to be stopped up is first provided and subsequently maintained
by the undertaker, to the reasonable satisfaction of the street authority, between the
commencement and termination points for that public right of way until the completion
and opening of the new public right of way in accordance with sub-paragraph (a).
(3) Where a public right of way has been stopped up and the new permanent route completed
under sub-paragraph (2)—
(a) all rights of way over or along the public right of way so stopped up are extinguished; and
(b) the undertaker may appropriate and use for the purposes of the authorised development
the site of that public right of way only where that public right of way is bounded on both
sides by land owned by the undertaker.
(4) Following the opening for public use of the new route of a public right of way once the
previous route has been stopped up and diverted under the powers conferred by this article, the
12Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
undertaker must supply the surveying authority with plans of the new route of the public right of
way together with a statement of the modifications required to the definitive map and statement.
(5) The plans and statement of modifications to the definitive statement referred to in
paragraph (4) are deemed to be an order modifying the definitive map and statement made under
section 53(3)(a) (duty to keep definitive map and statement under continuous review) of the Wildlife
and Countryside Act 1981.
(6) This article is subject to article 33 (apparatus and rights of statutory undertakers in closed
streets).
(7) In this article “surveying authority” has the meaning given to it by section 66(1) (interpretation
of Part III) of the Wildlife and Countryside Act 1981.
Use of private roads
14.—(1) The undertaker may use the private roads within the Order limits as specified on the
streets, rights of way and access plans for the passage of persons or vehicles (with or without
materials, plant and machinery) for the purposes of, or in connection with, the construction or
maintenance of the authorised development.
(2) The undertaker must compensate the person liable for the repair of a road to which
paragraph (1) applies for any loss or damage which that person may suffer by reason of the exercise
of the power conferred by paragraph (1).
(3) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the
amount of such compensation, is to be determined under Part 1 (determination of questions of
disputed compensation) of the 1961 Act.
Access to works
15. The undertaker may, for the purposes of the authorised development—
(a) form and lay out the permanent means of access, or improve existing means of access,
in the locations specified in Part 1 (permanent means of access to works) of Schedule 7
(means of access to works);
(b) form and lay out the temporary means of access, or improve existing means of access, in
the locations specified in Part 2 (temporary means of access to works) of Schedule 7; and
(c) with the approval of the relevant planning authority after consultation with the highway
authority, form and lay out such other means of access or improve existing means of access,
at such locations within the Order limits as the undertaker reasonably requires for the
purposes of the authorised development.
Agreements with street authorities
16.—(1) A street authority and the undertaker may enter into agreements with respect to—
(a) the strengthening, improvement, repair or reconstruction of any street under the powers
conferred by this Order;
(b) any closure, prohibition, restriction, alteration or diversion of a street authorised by this
Order;
(c) the undertaking in the street of any of the works referred to in article 8 (street works),
article 10 (power to alter layout, etc., of streets), article 11 (construction and maintenance
of altered streets) and article 15 (access to works); or
(d) the adoption by a street authority which is the highway authority of works—
(i)undertaken on a street which is existing public maintainable highway; or
13Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(ii)which the undertaker and highway authority agree to be adopted as public
maintainable highway.
(2) If such agreement provides that the street authority must undertake works on behalf of the
undertaker the agreement may, without prejudice to the generality of paragraph (1)—
(a) make provision for the street authority to carry out any function under this Order which
relates to the street in question;
(b) specify a reasonable time for the completion of the works; and
(c) contain such terms as to payment and otherwise as the parties consider appropriate.
(3) Prior to the commencement of any works under Part 3 of this Order, the undertaker must
enter into an agreement which is substantially in accordance with the framework highways works
agreement between the City of Doncaster Council and the undertaker dated 20 August 2025, or any
subsequent replacement agreement as to highways works.
Traffic regulation measures
17.—(1) Subject to the provisions of this article the undertaker may at any time, in the interests of
safety and for the purposes of, or in connection with, the construction of the authorised development,
temporarily place traffic signs and signals in the extents of the road specified in column 2 of the
table in Schedule 8 (traffic regulation measures) and the placing of those traffic signs and signals is
deemed to have been permitted by the traffic authority for the purposes of section 65 of the 1984
Act and the Traffic Signs Regulations and General Directions 2016(39).
(2) Subject to the provisions of this article and without limitation to the exercise of the powers
conferred by paragraph (1), the undertaker may make temporary provision for the purposes of the
construction of the authorised development—
(a) as to the speed at which vehicles may proceed along any road;
(b) permitting, prohibiting or restricting the stopping, waiting, loading or unloading of
vehicles on any road;
(c) as to the prescribed routes for vehicular traffic or the direction or priority of vehicular
traffic on any road;
(d) permitting, prohibiting or restricting the use by vehicular traffic or non-vehicular traffic
of any road; and
(e) suspending or amending in whole or in part any order made, or having effect as if made,
under the 1984 Act.
(3) No speed limit imposed by or under this Order applies to vehicles falling within regulation 3(4)
of the Road Traffic Exemptions (Special Forces) (Variation and Amendment) Regulations 2011(40)
when in accordance with regulation 3(5) of those regulations.
(4) Before exercising the power conferred by paragraph (2) the undertaker must—
(a) consult with the chief officer of police in whose area the road is situated; and
(b) obtain the written consent of the traffic authority and the street authority may attach
reasonable conditions to any such consent.
(5) The undertaker must not exercise the powers in paragraph (1) or (2) unless it has—
(a) given not less than four weeks’ notice in writing of its intention so to do to the chief officer
of police and to the traffic authority in whose area the road is situated;
(39) S.I. 2016/362.
(40) S.I. 2011/935.
14Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(b) not less than five working days before the provision is to take effect published the
undertaker’s intention to make the provision in one or more newspapers circulating in the
area in which any road to which the provision relates is situated; and
(c) not less than five working days before the provision is to take effect, displayed a site notice
containing the same information as in the newspaper notices specified at sub-paragraph (b)
at each end of the length of road affected.
(6) Any provision made under the powers conferred by paragraph (1) or (2) of this article may
be suspended, varied or revoked by the undertaker from time to time by subsequent exercise of the
powers conferred by paragraph (1) or (2).
(7) Any provision made by the undertaker under paragraph (1) or (2)—
(a) must be made by written instrument in such form as the undertaker considers appropriate;
(b) has effect as if duly made by the traffic authority in whose area the road is situated as a
traffic regulation order under the 1984 Act and the instrument by which it is effected may
specify specific savings and exemptions to which the provision is subject; and
(c) is deemed to be a traffic order for the purposes of Schedule 7 to the Traffic Management
Act 2004(41) (road traffic contraventions subject to civil enforcement).
(8) A copy of the instrument referred to in paragraph (7)(a) must be served on the traffic authority
as soon as reasonably practicable after being made.
PART 4
SUPPLEMENTAL POWERS
Discharge of water
18.—(1) Subject to paragraphs (3), (4) and (8) the undertaker may use any watercourse or any
public sewer or drain for the drainage of water in connection with the construction or maintenance
of the authorised development and for that purpose may lay down, take up and alter pipes and may,
on any land within the Order limits, make openings into, and connections with, the watercourse,
public sewer or drain.
(2) Any dispute arising from the making of connections to or the use of a public sewer or drain
by the undertaker under paragraph (1) is to be determined as if it were a dispute under section 106
(right to communicate with public sewers) of the Water Industry Act 1991(42).
(3) The undertaker must not discharge any water into any watercourse, public sewer or drain
except with the consent of the person to whom it belongs whose consent may be given subject to
terms and conditions as that person may reasonably impose.
(4) The undertaker must not carry out any works to or make any opening into any public sewer
or drain except—
(a) in accordance with plans approved by the person to whom the sewer or drain belongs; and
(b) where that person has been given the opportunity to supervise the making of the opening.
(5) Subject to paragraph (6) the undertaker must not, in carrying out or maintaining works
pursuant to this article, damage or interfere with the bed or banks of, or construct any works in, under,
over or within eight metres of, any watercourse forming part of a main river, or within 16 metres of
a tidally influenced main river without the prior written consent of the Environment Agency.
(41) 2004 c. 18.
(42) 1991 c. 56.
15Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(6) Where the undertaker discharges water into, or makes any opening into, a watercourse, public
sewer or drain belonging to or under the control of a drainage authority (as defined in Part 3 of
Schedule 14 (protective provisions)), the provisions of Part 3 of Schedule 14 apply in substitution
for the provisions of paragraphs (3) and (4).
(7) The undertaker must take such steps as are reasonably practicable to secure that any water
discharged into a watercourse or public sewer or drain pursuant to this article is as free as may be
practicable from gravel, soil or other solid substance, oil or matter in suspension.
(8) This article does not authorise the entry into controlled waters (within the meaning given
by section 104 of the Water Resources Act 1991(43)) of any matter whose entry or discharge into
controlled waters requires a licence pursuant to the Environmental Permitting (England and Wales)
Regulations 2016(44).
(9) In this article—
(a) “public sewer or drain” means a sewer or drain which belongs to Homes England, the
Environment Agency, an internal drainage board, a joint planning board, a local authority,
a National Park Authority, a sewerage undertaker or an urban development corporation;
and
(b) other expressions, excluding watercourse, used both in this article and in the Water
Resources Act 1991(45) have the same meaning as in that Act.
Protective works to buildings
19.—(1) Subject to the following provisions of this article, the undertaker may at its own expense
carry out such protective works to any building lying within the Order land as the undertaker
considers necessary or expedient.
(2) Protective works may be carried out—
(a) at any time before or during the construction of any part of the authorised development
in the vicinity of the building; or
(b) after the completion of that part of the authorised development in the vicinity of the
building at any time up to the end of the period of five years beginning with the date of
final commissioning.
(3) For the purpose of determining how the powers under this article are to be exercised, the
undertaker may enter and survey any building falling within paragraph (1) and any land within its
curtilage.
(4) For the purpose of carrying out protective works under this article to a building, the undertaker
may (subject to paragraphs (5) and (6))—
(a) enter the building and any land within its curtilage; and
(b) where the works cannot be carried out reasonably conveniently without entering land
which is adjacent to the building but outside its curtilage, enter the adjacent land (but not
any building erected on it).
(5) Before exercising—
(a) a right under paragraph (1) to carry out protective works to a building;
(b) a right under paragraph (3) to enter a building and land within its curtilage;
(c) a right under paragraph (4)(a) to enter a building and land within its curtilage; or
(d) a right under paragraph (4)(b) to enter land,
(43) 1991 c. 57.
(44) S.I. 2016/1154.
(45) 1991 c. 57
16Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
the undertaker must, except in the case of emergency, serve on the owners and occupiers of the
building or land not less than 14 days’ notice of its intention to exercise that right and, in a case falling
within sub-paragraph (a), (c) or (d), specifying the protective works proposed to be carried out.
(6) Where a notice is served under paragraph (5)(a), (5)(c) or (5)(d), the owner or occupier of the
building or land concerned may, by serving a counter-notice within the period of 10 days beginning
with the day on which the notice was served, question whether it is necessary or expedient to carry
out the protective works or to enter the building or land to be referred to arbitration under article 43
(arbitration).
(7) The undertaker must compensate the owners and occupiers of any building or land in relation
to which powers under this article have been exercised for any loss or damage arising to them by
reason of the exercise of those powers.
(8) W here—
(a) protective works are carried out under this article to a building; and
(b) within the period of five years beginning with the date of final commissioning it appears
protective works are inadequate to protect the building against damage caused by the
construction or use of that part of the authorised development, the undertaker must
compensate the owners and occupiers of the building for any loss or damage sustained
by them.
(9) Nothing in this article relieves the undertaker from any liability to pay compensation under
section 10(2) (compensation for injurious affection) of the 1965 Act.
(10) Any compensation payable under paragraph (7) or (8) must be determined, in case of dispute,
under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
(11) Section 13 (refusal to give possession to acquiring authority)(46) of the 1965 Act applies
to the entry onto, or possession of, land under this article to the same extent as it applies to the
compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory
acquisition provisions) of the 2008 Act.
(12) In this article “protective works” in relation to a building means—
(a) underpinning, strengthening and any other works the purpose of which is to prevent
damage which may be caused to the building by the construction, maintenance or use of
the authorised development; and
(b) any works the purpose of which is to remedy any damage which has been caused to the
building by the construction, maintenance or use of the authorised development.
Authority to survey and investigate the land
20.—(1) The undertaker may for the purposes of this Order enter on any land shown within the
Order limits or enter on any land which may be affected by the authorised development or enter on
any land upon which entry is required in order to carry out monitoring or surveys in respect of the
authorised development and—
(a) survey or investigate the land;
(b) without prejudice to the generality of sub-paragraph (a), make trial holes or bore holes
in such positions on the land as the undertaker thinks fit to investigate the nature of the
surface layer and subsoil and groundwater and remove soil and groundwater samples;
(c) without prejudice to the generality of sub-paragraph (a), carry out ecological or
archaeological investigations on such land, including the digging of trenches; and
(46) Section 13 was amended by sections 62(3), 139(4) to (9) and 146 of, and paragraphs 27 and 28 of Schedule 13 and Part 3 of
Schedule 23 to, the Tribunals, Courts and Enforcement Act 2007 (c. 15).
17Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(d) place on, leave on and remove from the land apparatus for use in connection with the
survey and investigation of land and making of trial holes, bore holes or trenches.
(2) No land may be entered or equipment placed or left on or removed from the land under
paragraph (1) unless at least 14 days’ notice has been served on every owner and occupier of the land.
(3) Any person entering land under this article on behalf of the undertaker—
(a) must, if so required before entering the land, produce written evidence of their authority
to do so; and
(b) may take with them such vehicles and equipment as are necessary to carry out the survey
or investigation or to make the trial holes.
(4) No trial holes are to be made under this article—
(a) in land located within the highway boundary without the consent of the highway authority;
or
(b) in a private street without the consent of the street authority.
(5) The undertaker must compensate the owners and occupiers of the land for any loss or damage
arising by reason of the exercise of the authority conferred by this article, such compensation to be
determined, in case of dispute, under Part 1 (determination of questions of disputed compensation)
of the 1961 Act.
(6) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the
entry onto, or possession of, land under this article to the same extent as it applies to the compulsory
acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition
provisions) of the 2008 Act.
PART 5
POWERS OF ACQUISITION
Compulsory acquisition of land
21.—(1) The undertaker may—
(a) acquire compulsorily so much of the Order land as is required for the authorised
development or to facilitate it, or as is incidental, to it; and
(b) use any land so acquired for the purpose authorised by this Order or for any other purposes
in connection with or ancillary to the authorised development.
(2) Paragraph (1) does not apply in relation to any mine or minerals rights.
(3) This article is subject to article 22 (time limit for exercise of authority to acquire land
compulsorily), article 23 (compulsory acquisition of rights), article 24 (private rights), article 26
(acquisition of subsoil only), article 27 (power to override easements and other rights), article 30
(temporary use of land for constructing the authorised development), and article 32 (statutory
undertakers).
Time limit for exercise of authority to acquire land compulsorily
22.—(1) The applicable period for the purposes of section 4 of the 1965 Act (time limit for giving
notice to treat) and section 5A of the 1981 Act (time limit for general vesting declaration) is five
years beginning on the day on which this Order is made.
(2) No notice to treat is to be served under Part 1 (compulsory purchase under Acquisition of
Land Act 1946) of the 1965 Act and no declaration is to be executed under section 4 (execution of
18Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
declaration) of the 1981 Act as applied by article 25 (application of the 1981 Act) after the end of
the applicable period, including any extension to the applicable period pursuant to those Acts.
(3) The authority conferred by article 30 (temporary use of land for constructing the authorised
development) ceases after the end of the applicable period referred to in paragraph (1), save that if
an application is made under section 118 of the 2008 Act (legal challenges relating to applications
for orders granting development consent) the applicable period is to be extended by—
(a) a period equivalent to the period beginning on the day the application is made and ending
on the day it is withdrawn or finally determined; or
(b) if shorter, one year.
(4) An application is not finally determined for the purposes of paragraph (3)(a) if an appeal in
respect of the application—
(a) could be brought (ignoring any possibility of an appeal out of time with permission); or
(b) has been made and not withdrawn or finally determined.
(5) Nothing in paragraph (3) prevents the undertaker remaining in possession of land after the
end of that period, if the land was entered and possession was taken before the end of that period.
Compulsory acquisition of rights
23.—(1) Subject to paragraph (2) and article 30 (temporary use of land for constructing the
authorised development), the undertaker may acquire compulsorily such rights over the Order land
or impose such restrictive covenants over the Order land as may be required for any purpose for
which that land may be acquired under article 21 (compulsory acquisition of land), by creating them
as well as by acquiring rights already in existence.
(2) Subject to the provisions of this paragraph, article 24 (private rights) and article 32 (statutory
undertakers), in the case of the Order land specified in column 1 of Schedule 9 (land in which only
new rights etc. may be acquired) the undertaker’s powers of compulsory acquisition are limited to the
acquisition of existing rights and benefit of restrictive covenants over that land and the creation and
acquisition of such new rights and the imposition of restrictive covenants for the purpose specified
in relation to that land in column 2 of that Schedule.
(3) Subject to section 8 (other provisions as to divided land) and Schedule 2A (counter-notice
requiring purchase of land) of the 1965 Act (as substituted by paragraph 5(8) of Schedule 10
(modification of compensation and compulsory purchase enactments for the creation of new rights
and imposition of new restrictive covenants)), where the undertaker creates or acquires an existing
right over land or the benefit of a restrictive covenant under paragraph (1) or (2), the undertaker is
not required to acquire a greater interest in that land.
(4) Schedule 10 has effect for the purpose of modifying the enactments relating to compensation
and the provisions of the 1965 Act in their application in relation to the compulsory acquisition
under this article of a right over land by the creation of a new right or the imposition of restrictive
covenants.
(5) In any case where the acquisition of new rights or imposition of a restriction under
paragraph (1) or (2) is required for the purpose of diverting, replacing or protecting apparatus of
a statutory undertaker, the undertaker may, with the consent of the Secretary of State, transfer the
power to acquire such rights to the statutory undertaker in question.
(6) The exercise by a statutory undertaker of any power in accordance with a transfer under
paragraph (5) is subject to the same restrictions, liabilities and obligations as would apply under this
Order if that power were exercised by the undertaker.
19Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Private rights
24.—(1) Subject to the provisions of this article, all private rights and restrictive covenants over
land subject to compulsory acquisition under article 21 (compulsory acquisition of land) cease to
have effect in so far as their continuance would be inconsistent with the exercise of the powers under
article 21—
(a) from the date of acquisition of the land by the undertaker, whether compulsorily or by
agreement; or
(b) on the date of entry on the land by the undertaker under section 11(1) (power of entry)
of the 1965 Act,
whichever is the earliest.
(2) Subject to the provisions of this article, all private rights or restrictive covenants over land
subject to the compulsory acquisition of rights or the imposition of restrictive covenants under
article 23 (compulsory acquisition of rights) cease to have effect in so far as their continuance would
be inconsistent with the exercise of the right or compliance with the restrictive covenant—
(a) as from the date of the acquisition of the right or imposition of the restrictive covenant by
the undertaker (whether the right is acquired compulsorily, by agreement or through the
grant of a lease of the land by agreement); or
(b) on the date of entry on the land by the undertaker under section 11(1) (power of entry) of
the 1965 Act in pursuance of the right,
whichever is the earliest.
(3) Subject to the provisions of this article, all private rights or restrictive covenants over land of
which the undertaker takes temporary possession under this Order are suspended and unenforceable,
in so far as their continuance would be inconsistent with the purpose for which temporary possession
is taken, for as long as the undertaker remains in lawful possession of the land.
(4) Any person who suffers loss by the extinguishment or suspension of any private right or
restrictive covenant under this article is entitled to compensation in accordance with the terms of
section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act to be
determined, in case of dispute, under Part 1 (determination of questions of disputed compensation)
of the 1961 Act.
(5) This article does not apply in relation to any right to which section 138 (extinguishment of
rights, and removal of apparatus, of statutory undertakers etc.) of the 2008 Act or article 32 (statutory
undertakers) applies.
(6) Paragraphs (1) to (3) have effect subject to—
(a) any notice given by the undertaker before—
(i)the completion of the acquisition of the land or the acquisition of rights or the
imposition of restrictive covenants over or affecting the land;
(ii)the undertaker’s appropriation of the land;
(iii)the undertaker’s entry onto the land; or
(iv)the undertaker’s taking temporary possession of the land,
that any or all of those paragraphs do not apply to any right specified in the notice; or
(b) any agreement made at any time between the undertaker and the person in or to whom the
right in question is vested or belongs.
(7) If an agreement referred to in paragraph (6)(b)—
(a) is made with a person in or to whom the right is vested or belongs; and
20Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(b) is expressed to have effect also for the benefit of those deriving title from or under that
person,
the agreement is effective in respect of the persons so deriving title, whether that title was derived
before or after the making of the agreement.
(8) References in this article to private rights over land include any right of way, trust, incident,
restrictive covenant, easement, liberty, privilege, right or advantage annexed to land and adversely
affecting other land, including any natural right to support; and include restrictions as to the user of
land arising by virtue of a contract, agreement or undertaking having that effect.
Application of the 1981 Act
25.—(1) The 1981 Act applies as if this Order were a compulsory purchase order.
(2) The 1981 Act, as applied by paragraph (1), has effect with the following modifications.
(3) In section 1 (application of the Act), for subsection 2 substitute—
“(2) This section applies to any Minister, any local or other public authority or any other
body or person authorised to acquire land by means of a compulsory purchase order.”.
(4) In section 5(2) (earliest date for execution of declaration) omit the words from “and this
subsection” to the end.
(5) In section 5B(1)(47) (extension of time limit during challenge) for “section 23 of the
Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase
order), the three year period mentioned in 5A” substitute “section 118 (legal challenges relating to
applications for orders granting development consent) of the 2008 Act”.
(6) In section 6 (notices after extension of declaration), in subsection (1)(b) for “section 15 of,
or paragraph 6 of Schedule 1 to, the Acquisition of Land Act 1981” substitute “section 134 (notice
of authorisation of compulsory acquisition) of the Planning Act 2008”.
(7) In section 7 (constructive notice to treat), in subsection (1)(a) omit the words “(as modified
by section 4 of the Acquisition of Land Act 1981)”.
(8) In Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration),
for paragraph 1(2) substitute—
“(2) But see article 26(3) (acquisition of subsoil only) of the Fenwick Solar Farm Order
2026, which excludes the acquisition of subsoil only from this Schedule.”.
(9) References to the 1965 Act in the 1981 Act must be construed as references to the 1965 Act
as applied by section 125 (application of compulsory acquisition provisions) of the 2008 Act (and
as modified by article 28 (modification of Part 1 of the Compulsory Purchase Act 1965)) to the
compulsory acquisition of land under this Order.
Acquisition of subsoil only
26.—(1) The undertaker may acquire compulsorily so much of, or such rights in, the subsoil
of the land referred to in paragraph (1) of article 21 (compulsory acquisition of land) or article 23
(compulsory acquisition of rights) as may be required for any purpose for which that land may be
acquired under that provision instead of acquiring the whole of the land.
(2) Where the undertaker acquires any part of, or rights in, the subsoil of land, the undertaker is
not required to acquire an interest in any other part of the land.
(3) The following do not apply in connection with the exercise of the power under paragraph (1)
in relation to subsoil only—
(47) 1981 c. 66. As amended by section 202(2) of the Housing and Planning Act 2016 (c. 22) and section 185(3)(b) of the Levelling-
up and Regeneration Act 2023 (c. 55).
21Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(a) Schedule 2A (counter-notice requiring purchase of land not in notice to treat) to the 1965
Act;
(b) Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration)
to the 1981 Act; and
(c) section 153(4A) (blighted land: proposed acquisition of part interest; material detriment
test) of the 1990 Act.
(4) Paragraphs (2) and (3) are to be disregarded where the undertaker acquires a cellar, vault,
arch or other construction forming part of a house, building or manufactory.
Power to override easements and other rights
27.—(1) Any authorised activity which takes place on land within the Order land (whether the
activity is undertaken by the undertaker or by any person deriving title from the undertaker or by
any contractors, servants or agents of the undertaker) is authorised by this Order if it is done in
accordance with the terms of this Order, notwithstanding that it involves—
(a) an interference with an interest or right to which this article applies; or
(b) a breach of a restriction as to the user of land arising by virtue of a contract.
(2) In this article “authorised activity” means—
(a) the erection, construction or maintenance of any part of the authorised development;
(b) the exercise of any power authorised by the Order; or
(c) the use of any land within the Order land (including the temporary use of land).
(3) The interests and rights to which this article applies include any easement, liberty, privilege,
right or advantage annexed to land and adversely affecting other land, including any natural right to
support and include restrictions as to the user of land arising by virtue of a contract.
(4) Where an interest, right or restriction is overridden by paragraph (1), compensation—
(a) is payable under section 7 (measure of compensation in case of severance) or 10 (further
provision as to compensation for injurious affection) of the 1965 Act; and
(b) is to be assessed in the same manner and subject to the same rules as in the case of other
compensation under those sections where—
(i)the compensation is to be estimated in connection with a purchase under that Act; or
(ii)the injury arises from the execution of works on or use of land acquired under that
Act.
(5) Where a person deriving title under the undertaker by whom the land in question was
acquired—
(a) is liable to pay compensation by virtue of paragraph (4); and
(b) fails to discharge that liability,
the liability is enforceable against the undertaker.
(6) Nothing in this article is to be construed as authorising any act or omission on the part of any
person which is actionable at the suit of any person on any grounds other than such an interference
or breach as is mentioned in paragraph (1).
Modification of Part 1 of the Compulsory Purchase Act 1965
28.—(1) Part 1 (compulsory acquisition under the Acquisition of Land Act 1981) of the 1965
Act, as applied to this Order by section 125 (application of compulsory acquisition provisions) of
the 2008 Act, is modified as follows.
22Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(2) In section 4A(1) (extension of time limit during challenge) for “section 23 of the Acquisition
of Land Act 1981 (application to the High Court in respect of compulsory purchase order)” substitute
“section 118 (legal challenges relating to applications for orders granting development consent) of
the 2008 Act”.
(3) In section 11A (powers of entry: further notice of entry)—
(a) in subsection (1)(a), after “land” insert “under that provision”; and
(b) in subsection (2), after “land” insert “under that provision”.
(4) In section 22(2) (interests omitted from purchase), for “section 4 of this Act” substitute “article
22 (time limit for exercise of authority to acquire land compulsorily) of the Fenwick Solar Farm
Order 2026”.
(5) In Schedule 2A (counter-notice requiring purchase of land not in notice to treat)—
(a) for paragraphs 1(2) and 14(2) substitute—
“(2) But see article 26(3) (acquisition of subsoil only) of the Fenwick Solar Farm Order
2026, which excludes the acquisition of subsoil only from this Schedule.”; and
(b) after paragraph 29 insert—
“PART 4
INTERPRETATION
30. In this Schedule, references to entering on and taking possession of land do not
include doing so under article 19 (protective works to buildings), article 30 (temporary use
of land for constructing the authorised development) or article 31 (temporary use of land
for maintaining the authorised development) of the Fenwick Solar Farm Order 2026.”.
Rights under or over streets
29.—(1) The undertaker may enter on, appropriate and use so much of the subsoil of or airspace
over any street within the Order limits as may be required for the purposes of the authorised
development and may use the subsoil or airspace for those purposes or any other purpose ancillary
to the authorised development.
(2) Subject to paragraph (3), the undertaker may exercise any power conferred by paragraph (1)
in relation to a street without being required to acquire any part of the street or any easement or
right in the street.
(3) Paragraph (2) does not apply in relation to—
(a) any subway or underground building; or
(b) any cellar, vault, arch or other construction in, on or under a street which forms part of a
building fronting onto the street.
(4) Subject to paragraph (5), any person who is an owner or occupier of land appropriated under
paragraph (1) without the undertaker acquiring any part of that person’s interest in the land, and who
suffers loss as a result, is entitled to compensation to be determined, in case of dispute, under Part 1
(determination of questions of disputed compensation) of the 1961 Act.
(5) Compensation is not payable under paragraph (4) to any person who is an undertaker to whom
section 85 (sharing cost of necessary measures) of the 1991 Act applies in respect of measures of
which the allowable costs are to be borne in accordance with that section.
23Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Temporary use of land for constructing the authorised development
30.—(1) The undertaker may, in connection with the construction of the authorised
development—
(a) enter on and take temporary possession of—
(i)so much of the land specified in column (1) of the table in Schedule 11 (land of
which temporary possession may be taken) for the purpose specified in relation to
the land in column (2) of that table; and
(ii)any other Order land in respect of which no notice of entry has been served under
section 11 (powers of entry) of the 1965 Act(48) and no declaration has been made
under section 4 (execution of declaration) of the 1981 Act;
(b) remove any agricultural plant and apparatus, drainage, fences, debris and vegetation from
that land;
(c) construct temporary works (including means of access), haul roads, security fencing,
bridges, structures and buildings on that land;
(d) use the land for the purposes of a temporary working site with access to the working site
in connection with the authorised development;
(e) construct any works on that land as are mentioned in Schedule 1 (authorised development);
and
(f) carry out mitigation works required under the requirements in Schedule 2 (requirements).
(2) Paragraph (1) does not authorise the undertaker to take temporary possession of—
(a) any house or garden belonging to a house; or
(b) any building (other than a house) if it is for the time being occupied.
(3) Not less than 28 days before entering on and taking temporary possession of land under this
article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.
(4) The undertaker must not, without the agreement of the owners of the land, remain in
possession of any land under this article—
(a) in the case of the land referred to in paragraph (1)(a)(i) after the end of the period of
one year beginning with the date of final commissioning of the part of the authorised
development for which temporary possession of the land was taken; or
(b) in the case of land referred to in paragraph (1)(a)(ii) after the end of the period of one year
beginning with the date of final commissioning of the part of the authorised development
for which temporary possession of the land was taken unless the undertaker has, before
the end of that period, served a notice of entry under section 11 of the 1965 Act or made
a declaration under section 4 of the 1981 Act in relation to that land.
(5) Unless the undertaker has served notice of entry under section 11 of the 1965 Act or made
a declaration under section 4 of the 1981 Act or otherwise acquired the land or rights over land
subject to temporary possession, the undertaker must before giving up possession of land of which
temporary possession has been taken under this article, remove all works and restore the land to the
reasonable satisfaction of the owners of the land; but the undertaker is not required to—
(a) replace any building, structure, debris, drain or electric line removed under this article;
(b) remove any drainage works installed by the undertaker under this article;
(48) Section 11 was amended by section 34(1) of, and Schedule 4 to, the Acquisition of Land 1981 (c. 67), section 3 of, and Part 1 of
Schedule 1 to, the Housing (Consequential Provisions) Act 1985 (c. 71), section 14 of, and paragraph 12(1) of Schedule 5 to,
the Church of England (Miscellaneous Provisions) Measure 2006 (No. 1), sections 186(2), 187(2) and 188 of, and paragraph
6 of Schedule 14 and paragraph 3 of Schedule 16 to, the Housing and Planning Act 2016 (c. 22) and S.I. 2009/1307.
24Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(c) remove any new road surface or other improvements carried out under this article to any
street specified in Schedule 4 (streets subject to street works), Schedule 5 (alteration of
streets) or Schedule 7 (means of access to works);
(d) remove any fencing or boundary treatments installed by the undertaker under this article
to replace or enhance existing fencing or boundary treatments; or
(e) restore the land on which any works have been carried out under paragraph (1)(f) insofar as
the works relate to mitigation works identified in the environmental statement or required
pursuant to the requirements in Schedule 2.
(6) The undertaker must pay compensation to the owners and occupiers of land of which
temporary possession is taken under this article for any loss or damage arising from the exercise in
relation to the land of the provisions of any power conferred by this article.
(7) Any dispute as to a person’s entitlement to compensation under paragraph (6), or as to the
amount of compensation, must be determined under Part 1 (determination of questions of disputed
compensation) of the 1961 Act.
(8) Nothing in this article affects any liability to pay compensation under section 152
(compensation in case where no right to claim in nuisance) of the 2008 Act or under any other
enactment in respect of loss or damage arising from the carrying out of the authorised development,
other than loss or damage for which compensation is payable under paragraph (6).
(9) Where the undertaker takes possession of land under this article, the undertaker is not required
to acquire the land or any interest in it.
(10) The undertaker must not compulsorily acquire, acquire new rights over or impose restrictive
covenants over, the land referred to in paragraph (1)(a)(i) under this Order.
(11) Nothing in this article precludes the undertaker from—
(a) creating and acquiring new rights or imposing restrictions over any part of the Order land
identified in Schedule 9 (land in which only new rights etc. may be acquired); or
(b) acquiring any part of the subsoil of (or rights in the subsoil of) that land under article 26
(acquisition of subsoil only) or any part of the subsoil of or airspace over that land under
article 29 (rights under or over streets).
(12) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the
temporary use of land under this article to the same extent as it applies to the compulsory acquisition
of land under this Order by virtue of section 125 (application of compulsory acquisition provisions)
of the 2008 Act.
(13) Nothing in this article prevents the taking of temporary possession more than once in relation
to any land that the undertaker takes temporary possession of under this article.
Temporary use of land for maintaining the authorised development
31.—(1) Subject to paragraph (2), at any time during the maintenance period relating to any part
of the authorised development, the undertaker may—
(a) enter on and take temporary possession of any land within the Order land if such possession
is reasonably required for the purpose of maintaining the authorised development;
(b) enter on any land within the Order land for the purpose of gaining such access as is
reasonably required for the purpose of maintaining the authorised development; and
(c) construct such temporary works (including the provision of means of access) and buildings
on the land as may be reasonably necessary for that purpose.
(2) Paragraph (1) does not authorise the undertaker to take temporary possession of—
(a) any house or garden belonging to a house; or
25Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(b) any building (other than a house) if it is for the time being occupied.
(3) Not less than 28 days before entering on and taking temporary possession of land under this
article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.
(4) The undertaker may only remain in possession of land under this article for so long as may
be reasonably necessary to carry out the maintenance of the part of the authorised development for
which possession of the land was taken.
(5) Before giving up possession of land of which temporary possession has been taken under
this article, the undertaker must remove all temporary works and restore the land to the reasonable
satisfaction of the owners of the land.
(6) The undertaker must pay compensation to the owners and occupiers of land of which
temporary possession is taken under this article for any loss or damage arising from the exercise in
relation to the land of the provisions of this article.
(7) Any dispute as to a person’s entitlement to compensation under paragraph (6), or as to the
amount of compensation, must be determined under Part 1 (determination of questions of disputed
compensation) of the 1961 Act.
(8) Nothing in this article affects any liability to pay compensation under section 152
(compensation in case where no right to claim in nuisance) of the 2008 Act or under any other
enactment in respect of loss or damage arising from the maintenance of the authorised development,
other than loss or damage for which compensation is payable under paragraph (6).
(9) Where the undertaker takes possession of land under this article, the undertaker is not required
to acquire the land or any interest in it.
(10) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the
temporary use of land under this article to the same extent as it applies to the compulsory acquisition
of land under this Order by virtue of section 125 (application of compulsory acquisition provisions)
of the 2008 Act.
(11) In this article “the maintenance period” means the period of five years beginning with
the date of final commissioning of the part of the authorised development for which temporary
possession is required under this article except in relation to landscaping where “the maintenance
period” means such period as set out in the landscape and ecological management plan which is
approved by the relevant planning authority pursuant to requirement 6 (landscape and ecological
management plan) beginning with the date on which that part of the landscaping is completed.
Statutory undertakers
32. Subject to the provisions of Schedule 14 (protective provisions) the undertaker may—
(a) acquire compulsorily, or acquire new rights or impose restrictive covenants over, the land
belonging to statutory undertakers shown on the land plans (as certified by the Secretary
of State in accordance with article 41) within the Order land; and
(b) extinguish the rights of, remove, relocate the rights of or reposition the apparatus belonging
to statutory undertakers over or within the Order land.
Apparatus and rights of statutory undertakers in closed streets
33. Where a street is altered or diverted, or its use is temporarily prohibited or restricted, or it
is stopped up and diverted, under article 8 (street works), article 10 (power to alter layout, etc., of
streets), article 11 (construction and maintenance of altered streets), article 12 (temporary closure
of streets and public rights of way) or article 13 (stopping up of public rights of way) any statutory
undertaker whose apparatus is under, in, on, along or across the street has the same powers and
26Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
rights in respect of that apparatus, subject to Schedule 14 (protective provisions), as if this Order
had not been made.
Recovery of costs of new connections
34.—(1) Where any apparatus of a public utility undertaker or of a public communications
provider is removed under article 32 (statutory undertakers) any person who is the owner or occupier
of premises to which a supply was given from that apparatus is entitled to recover from the undertaker
compensation in respect of expenditure reasonably incurred by that person, in consequence of the
removal, for the purpose of effecting a connection between the premises and any other apparatus
from which a supply is given.
(2) Paragraph (1) does not apply in the case of the removal of a public sewer but where such a
sewer is removed under article 32, any person who is—
(a) the owner or occupier of premises the drains of which communicated with that sewer; or
(b) the owner of a private sewer which communicated with that sewer,
is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred
by that person, in consequence of the removal, for the purpose of making the drain or sewer belonging
to that person communicate with any other public sewer or with a private sewerage disposal plant.
(3) This article does not have effect in relation to apparatus to which Part 3 (street works in
England and Wales) of the 1991 Act applies.
(4) In this article—
“public communications provider” has the same meaning as in section 151(1) (interpretation
of Chapter 1) of the Communications Act 2003(49); and
“public utility undertaker” has the same meaning as in the 1980 Act.
PART 6
MISCELLANEOUS AND GENERAL
Benefit of the Order
35.—(1) Subject to article 36 (consent to transfer the benefit of the Order), the provisions of this
Order have effect solely for the benefit of the undertaker.
(2) Paragraph (1) does not apply to Work No. 4(b) in respect of which the provisions of this Order
are for the benefit of the undertaker and National Grid.
Consent to transfer the benefit of the Order
36.—(1) Subject to paragraph (3), the undertaker may—
(a) transfer to another person (“the transferee”) any or all of the benefit of the provisions of
this Order and such related statutory rights as may be agreed between the undertaker and
the transferee; and
(b) grant to another person (“the lessee”) for a period agreed between the undertaker and the
lessee any or all of the benefit of the provisions of this Order and such related statutory
rights as may be so agreed.
(49) 2003 c. 21.
27Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(2) Where a transfer or grant has been made references in this Order to the undertaker, except in
paragraphs (7) and (9), are to include references to the transferee or lessee.
(3) The consent of the Secretary of State is required for the exercise of the powers of paragraph (1)
except where—
(a) the transferee or lessee is the holder of a licence under section 6 (licences authorising
supply etc.) of the 1989 Act; or
(b) the time limits for claims for compensation in respect of the acquisition of land or effects
upon land under this Order have elapsed and—
(i)no such claims have been made;
(ii)any such claim has been made and has been compromised or withdrawn;
(iii)compensation has been paid in full and final settlement of any such claim;
(iv)payment of compensation into court has taken place in lieu of settlement of any such
claim; or
(v)it has been determined by a tribunal or court of competent jurisdiction in respect of
any such claim that no compensation is payable.
(4) Where the consent of the Secretary of State is not required, the undertaker must notify the
Secretary of State in writing before transferring or granting a benefit referred to in paragraph (1).
(5) The notification referred to in paragraph (4) must state—
(a) the name and contact details of the person to whom the benefit of the powers will be
transferred or granted;
(b) subject to paragraph (6), the date on which the transfer will take effect;
(c) the powers to be transferred or granted;
(d) pursuant to paragraph (9), the restrictions, liabilities and obligations that will apply to the
person exercising the powers transferred or granted;
(e) where relevant, a plan showing the works or areas to which the transfer or grant relates; and
(f) a copy of the document effecting the transfer or grant.
(6) The date specified under paragraph (5)(b) must not be earlier than the expiry of 14 working
days from the date of the receipt of the notification.
(7) The notification given must be signed by the undertaker and the person to whom the benefit
of the powers will be transferred or granted as specified in that notification.
(8) A copy of any decision by the Secretary of State to approve a transfer or grant under
paragraph (3) or the notification of a transfer or grant issues under paragraph (4) shall be provided
by the undertaker to the relevant planning authority as soon as reasonably practicable following
issuance.
(9) Where the undertaker has transferred any benefit, or for the duration of any period during
which the undertaker has granted any benefit—
(a) the benefit transferred or granted (“the transferred benefit”) must include any rights that
are conferred, and any obligations that are imposed, by virtue of the provisions to which
the benefit relates;
(b) the transferred benefit will reside exclusively with the transferee or, as the case may be,
the lessee and the transferred benefit will not be enforceable against the undertaker; and
(c) the exercise by a person of any benefits or rights conferred in accordance with any transfer
or grant is subject to the same restrictions, liabilities and obligations as would apply under
this Order if those benefits or rights were exercised by the undertaker.
28Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Application of landlord and tenant law
37.—(1) This article applies to—
(a) any agreement for leasing to any person the whole or any part of the authorised
development or the right to operate the same; and
(b) any agreement entered into by the undertaker with any person for the construction,
maintenance, use or operation of the authorised development, or any part of it,
so far as any such agreement relates to the terms on which any land which is the subject of a lease
granted by or under that agreement is to be provided for that person’s use.
(2) No enactment or rule of law regulating the rights and obligations of landlords and tenants
prejudices the operation of any agreement to which this article applies.
(3) Accordingly, no such enactment or rule of law to which paragraph (2) applies in relation to the
rights and obligations of the parties to any lease granted by or under any such agreement, so as to—
(a) exclude or in any respect modify any of the rights and obligations of those parties under
the terms of the lease, whether with respect to the termination of the tenancy or any other
matter;
(b) confer or impose on any such party any right or obligation arising out of or connected
with anything done or omitted on or in relation to land which is the subject of the lease,
in addition to any such right or obligation provided for by the terms of the lease; or
(c) restrict the enforcement (whether by action for damages or otherwise) by any party to the
lease of any obligation of any other party under the lease.
Operational land for the purposes of the 1990 Act
38. Development consent granted by this Order is to be treated as specific planning permission
for the purposes of section 264(3) (cases in which land is to be treated as not being operational land)
of the 1990 Act.
Felling or lopping of trees and removal of hedgerows
39.—(1) Subject to paragraph (2) and article 40 (trees subject to tree preservation orders) the
undertaker may fell or lop any tree or shrub within or overhanging the Order limits or cut back its
roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub from—
(a) obstructing or interfering with the construction, maintenance or operation of the authorised
development or any apparatus used in connection with the authorised development;
(b) constituting a danger to persons using the authorised development; or
(c) obstructing or interfering with the passage of construction vehicles to the extent necessary
for the purposes of construction of the authorised development.
(2) In carrying out any activity authorised by paragraph (1) the undertaker must do no unnecessary
damage to any tree or shrub and must pay compensation to any person for any loss or damage arising
from such activity.
(3) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the
amount of compensation, is to be determined under Part 1 (determination of questions of disputed
compensation) of the 1961 Act.
(4) The undertaker may, for the purposes of the authorised development, or in connection with
the authorised development, subject to paragraph (2), undertake works to or remove any hedgerows
within the Order limits that may be required.
29Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(5) The undertaker may not pursuant to paragraphs (1) and (4) fell or lop a tree or remove
hedgerows within the extent of the publicly maintainable highway without the prior consent of the
highway authority, and the highway authority may attach reasonable conditions to any such consent.
(6) In this article “hedgerow” has the same meaning as in the Hedgerows Regulations 1997(50).
Trees subject to tree preservation orders
40.—(1) Subject to paragraph (2), the undertaker must not under the powers of this article fell,
lop, prune, or cut back the roots of any tree which is the subject of a tree preservation order.
(2) The undertaker may fell or lop any tree which is within or overhanging land within the Order
limits that is subject to a tree preservation order which was made after 31 October 2024, or cut back its
roots, if it reasonably believes it to be necessary to do so in order to prevent the tree from obstructing
or interfering with the construction, maintenance or operation of the authorised development or any
apparatus used in connection with the authorised development.
(3) In carrying out any activity authorised by paragraph (2)—
(a) the undertaker must do no unnecessary damage to any tree and must pay compensation to
any person for any loss or damage arising from such activity; and
(b) the duty contained in section 206(1) (replacement of trees) of the 1990 Act does not apply.
(4) The authority given by paragraph (2) constitutes a deemed consent under the relevant tree
preservation order.
(5) Any dispute as to a person’s entitlement to compensation under paragraph (3), or as to the
amount of compensation, must be determined under Part 1 (determination of questions of disputed
compensation) of the 1961 Act.
Certification of plans and documents, etc.
41.—(1) The undertaker must, as soon as practicable after the making of this Order, submit to the
Secretary of State copies of all documents and plans listed in the table at Schedule 12 (documents
and plans to be certified) for certification that they are true copies of the documents referred to in
this Order.
(2) A plan or document so certified is admissible in any proceedings as evidence of the contents
of the document of which it is a copy.
No double recovery
42. Compensation is not payable in respect of the same matter both under this Order and under
any enactment, any contract or any rule of law.
Arbitration
43.—(1) Any difference under any provision of this Order, unless otherwise provided for, is to be
referred to and settled in arbitration in accordance with the rules set out in Schedule 13 (arbitration
rules) of this Order, by a single arbitrator to be agreed upon by the parties, within 10 working days of
receipt of the notice of arbitration, or if the parties fail to agree within the time period stipulated, to
be appointed on application of either party (after giving written notice to the other) by the Secretary
of State.
(2) Any matter for which the consent or approval of the Secretary of State is required under any
provision of this Order is not subject to arbitration.
(50) S.I. 1997/1160.
30Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Protective provisions
44. Schedule 14 (protective provisions) has effect.
Service of notices
45.—(1) A notice or other document required or authorised to be served for the purposes of this
Order may be served—
(a) by post;
(b) by delivering it to the person on whom it is to be served or to whom it is to be given or
supplied; or
(c) with the consent of the recipient and subject to paragraphs (5) to (8), by electronic
transmission.
(2) Where the person on whom a notice or other document to be served for the purposes of this
Order is a body corporate, the notice or document is duly served if it is served on the secretary or
clerk of that body.
(3) For the purposes of section 7 (references to service by post) of the Interpretation Act 1978(51)
as it applies for the purposes of this article, the proper address of any person in relation to the service
on that person of a notice or document under paragraph (1) is, if that person has given an address
for service, that address and otherwise—
(a) in the case of the secretary or clerk of a body corporate, the registered or principal office
of that body; and
(b) in any other case, the last known address of that person at that time of service.
(4) Where for the purpose of this Order a notice or other document is required or authorised to
be served on a person as having an interest in, or as the occupier of, land and the name or address of
that person cannot be ascertained after reasonable enquiry, the notice may be served by—
(a) addressing it to that person by the description of “owner”, or as the case may be “occupier”
of the land (describing it); and
(b) either leaving it in the hands of the person who is or appears to be resident or employed on
the land or leaving it conspicuously affixed to some building or object on or near the land.
(5) Where a notice or other document required to be served or sent for the purposes of this Order
is served or sent by electronic transmission the requirement is to be taken to be fulfilled only where—
(a) the recipient of the notice or other document to be transmitted has given consent to the use
of electronic transmission in writing or by electronic transmission;
(b) the notice or document is capable of being accessed by the recipient;
(c) the notice or document is legible in all material respects; and
(d) the notice or document is in a form sufficiently permanent to be used for subsequent
reference.
(6) Where the recipient of a notice or other document served or sent by electronic transmission
notifies the sender within seven days of receipt that the recipient requires a paper copy of all or any
part of that notice or other document the sender must provide such a copy as soon as reasonably
practicable.
(7) Any consent to the use of an electronic transmission by a person may be revoked by that
person in accordance with paragraph (8).
(8) Where a person is no longer willing to accept the use of electronic transmission for any of
the purposes of this Order—
(51) 1978 c. 30.
31Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(a) that person must give notice in writing or by electronic transmission revoking any consent
given by that person for that purpose; and
(b) such revocation is final and takes effect on a date specified by the person in the notice but
that date must not be less than seven days after the date on which the notice is given.
(9) This article does not exclude the employment of any method of service not expressly provided
for by it.
(10) In this article “legible in all material respects” means that the information contained in the
notice or document is available to that person to no lesser extent that it would be if served, given or
supplied by means of a notice or document in printed form.
Procedure in relation to certain approvals etc.
46.—(1) Where an application is made to or request is made of, a consenting authority for any
consent, agreement or approval required or contemplated by any of the provisions of the Order (not
including the requirements), such consent, agreement or approval to be validly given, must be given
in writing.
(2) Where paragraph (1) applies to any consent, agreement or approval, such consent, agreement
or approval must not be unreasonably withheld or delayed.
(3) Schedule 15 (procedure for discharge of requirements) has effect in relation to all consents,
agreements or approvals required, granted, refused or withheld in relation to the requirements.
(4) Save for applications made pursuant to Schedule 15 and where stated to the contrary if,
within eight weeks (or such longer period as may be agreed between the undertaker and the relevant
consenting authority in writing) after the application or request has been submitted to a consenting
authority it has not notified the undertaker of its disapproval and the grounds of disapproval, it is
deemed to have approved the application or request.
(5) Where any application is made as described in paragraph (1), the undertaker must include a
statement in such application that refers to the timeframe for consideration of the application and
the consequences of failure to meet that timeframe as prescribed by paragraph (4).
(6) Schedule 15 does not apply in respect of any consents, agreements or approvals contemplated
by the provisions of Schedule 14 (protective provisions) or any dispute under article 19(6) (protective
work to buildings) to which paragraph (4) applies.
(7) In this article “consenting authority” means the relevant planning authority, highway
authority, traffic authority, street authority, the owner of a watercourse, sewer or drain or the
beneficiary of any of the protective provisions contained in Schedule 14.
Guarantees in respect of payment of compensation
47.—(1) The undertaker must not exercise the powers conferred by the provisions referred to in
paragraph (2) in relation to any part of the Order land unless it has first put in place either—
(a) a guarantee, the form and amount of which has been approved by the Secretary of State in
respect of the liabilities of the undertaker to pay compensation pursuant to the provisions
referred to in paragraph (2) in respect of the exercise of the relevant provision in relation
to that part of the Order land; or
(b) an alternative form of security, the form and amount of which has been approved by
the Secretary of State in respect of the liabilities of the undertaker to pay compensation
pursuant to the provisions referred to in paragraph (2) in respect of the exercise of the
relevant provision in relation to that part of the Order land.
(2) The provisions are—
(a) article 21 (compulsory acquisition of land);
32Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(b) article 23 (compulsory acquisition of rights);
(c) article 24 (private rights);
(d) article 26 (acquisition of subsoil only);
(e) article 29 (rights under or over streets);
(f) article 30 (temporary use of land for constructing the authorised development);
(g) article 31 (temporary use of land for maintaining the authorised development); and
(h) article 32 (statutory undertakers).
(3) A guarantee or alternative form of security given in respect of any liability of the undertaker
to pay compensation under this Order is to be treated as enforceable against the guarantor or person
providing the alternative form of security by any person to whom such compensation is payable and
must be in such a form as to be capable of enforcement by such a person.
(4) Nothing in this article requires a guarantee or alternative form of security to be in place for
more than 15 years after the date on which the relevant power is exercised.
Compulsory acquisition of land – incorporation of the mineral code
48. Parts 2 and 3 of Schedule 2 (minerals) to the Acquisition of Land Act 1981(52) are
incorporated into this Order subject to the modifications that—
(a) for “the acquiring authority” substitute “the undertaker”;
(b) for the “undertaking” substitute “authorised development”; and
(c) paragraph 8(3) is not incorporated.
Signed by authority of the Secretary of State for Energy Security and Net Zero
David Wagstaff
Deputy Director, Energy Infrastructure Planning
18th February 2026 Department for Energy Security and Net Zero
(52) 1981 c. 67.
33Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
SCHED ULES
SCHEDULE 1 Article 3
AUTHORISED DEVELOPMENT
Interpretation
1. In this Schedule—
“electrical cables” means—
(a) cables of differing types and voltages installed for the purposes of conducting electricity,
auxiliary cables, cables connecting to direct current (DC) boxes, earthing cables and
optical fibre cables; and
(b) works associated with cable laying including jointing bays, hardstanding adjoining the
jointing pits, combiner boxes, fibre bays, cable ducts, cable protection, joint protection,
manholes, kiosks, marker posts, underground cable marker, tiles and tape, send and
receive pits for horizontal directional drilling, trenching, lighting, and a pit or container
to capture fluids associated with drilling;
“field stations” means inverters, transformers and switchgear comprising either—
(a) a configuration where transformers, inverters and switchgear will be housed in a single
container located on a concrete beam or block foundation; or screw piles, rammed piles
or compacted hardcore foundation. There will be a perimeter of stone or gravel around
the container; or
(b) a configuration where transformers and switchgear will be housed in a single container
and inverters provided in either a separate single container or inverters provided
separately and mounted on a ground mounted frame which is parallel to the mounting
structure. Each container will be located on a concrete beam or block foundation; or
screw piles, rammed piles or compacted hardcore foundation. There will be a perimeter
of stone or gravel around each container; or
(c) a configuration where transformers, switchgear and inverters will be provided separately,
which may be in one or more containers. Inverters may also be provided separately
and mounted on a ground mounted frame which is parallel to the mounting structure.
Any container will be located on a concrete beam or block foundation; or screw piles,
rammed piles or compacted hardcore foundation. There will be a perimeter of stone or
gravel around any container; and inverters provided separately and mounted on a ground
mounted frame which is parallel to the mounting structure;
“inverter” means electrical equipment required to convert direct current power to alternating
current;
“mounting structure” means a frame or rack made of galvanised steel or other material designed
to support the solar panels and mounted on piles driven into the ground, piles rammed into
bare ground, a pillar attaching to a steel ground screw, pillars fixed to a concrete foundation
or feet, or pillars set in concrete in a pre-made hole in the ground;
“National Grid Thorpe Marsh Substation” means the existing 400kV substation at Thorpe
Marsh, owned and operated by National Grid;
34Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
“solar panel” means a solar photovoltaic panel or module designed to convert solar irradiance
to electrical energy;
“substation” means a compound containing electrical equipment required to switch, transform
and convert electricity;
“switchgear” means a combination of electrical disconnect switches, fuses or circuit breakers
used to control, protect and isolate electrical equipment; and
“transformer” means a structure containing an electrical device to transform electricity to a
different voltage.
Authorised development
2.—(1) In the unitary authority of Doncaster a nationally significant infrastructure project as
defined in sections 14 and 15 of the 2008 Act and associated development under section 115(1)(b)
of the 2008 Act.
(2) Subject to paragraph (3), the nationally significant infrastructure project comprises up to one
generating station with a gross electrical output capacity of over 50 megawatts (alternating current)
comprising all or any of the work numbers in this Schedule or any part of any work number in this
Schedule.
(3) The nationally significant infrastructure project must only comprise of either Work No. 4 or
Work No. 5(b).
Work No. 1 – a ground mounted solar photovoltaic generating station with a gross electrical output
capacity of over 50 megawatts (alternating current) including—
(a) solar panels fitted to mounting structures; and
(b) field stations;
and associated development within the meaning of section 115(2) of the 2008 Act including—
Work No. 2 – battery energy storage systems including—
(a) battery energy storage system (BESS) units each comprising an enclosure for BESS
electro-chemical components and associated equipment, with the enclosure being of metal
façade, joined or close coupled to each other, mounted on one or more of reinforced
concrete foundation slab, concrete piles, ground screws, metal piles or compacted stone/
gravel;
(b) transformers and associated bunding;
(c) inverters, switch gear, power conversion systems (PCS) and ancillary equipment;
(d) containers or enclosures housing all or any of Work Nos. 2(b) and (c) and ancillary
equipment;
(e) monitoring and control systems housed within the containers or enclosures comprised in
Work Nos. 2(a) or (d) or located separately in its own container or enclosure;
(f) heating, ventilation and air conditioning (HVAC) systems either housed on or within each
of the containers or enclosures comprised in Work Nos. 2(a), (d) and (e), attached to the
side or top of each of the containers or enclosures, or located separate to but near to each
of the containers or enclosures;
(g) electrical cables including electrical cables connecting to Work No. 3;
(h) bunded impermeable surface to manage surface water drainage;
(i) fire safety infrastructure including water storage tanks, impermeable water capture basins
and a shut-off valve for containment of fire water and hard standing to accommodate
emergency vehicles; and
35Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(j) containers or similar structures to house spare parts and materials required for the day to
day operation of the BESS facility.
Work No. 3 – development of onsite substation and associated works including—
(a) substation, switch room buildings and ancillary equipment including reactive power units
and harmonic filters; and
(b) monitoring and control systems housed within a control building or located separately in
their own containers or control rooms, with welfare facilities.
Work No. 4 – works to lay electrical cables and compounds for the electrical cables including—
(a) works to lay 400kV electrical cables connecting Work No. 3 to the National Grid Thorpe
Marsh Substation, including link boxes and tunnelling, boring and drilling works for
trenchless crossings;
(b) electrical engineering works within or around the National Grid Thorpe Marsh Substation
including the laying and terminating of the electrical cables and ancillary equipment; and
(c) construction and decommissioning compounds, including site and welfare offices and
areas to store materials and equipment.
Work No. 5 – works including—
(a) electrical cables, including but not limited to electrical cables connecting Work Nos. 1, 2,
3 and 4 to one another and connecting solar panels to one another and the field stations
including tunnelling, boring and drilling works for trenchless crossings;
(b) works to lay electrical cables connecting Work No. 3 to an existing on site 400kV overhead
line tower including the laying and terminating of the electrical cables and ancillary
equipment;
(c) landscaping, biodiversity and heritage mitigation and enhancement measures including
planting;
(d) earthworks;
(e) laying down of temporary footpath diversions, permissive paths, signage and information
boards;
(f) hardstanding and parking areas;
(g) sustainable drainage systems including ponds, runoff outfalls, general drainage and
irrigation infrastructure, systems and improvements or extensions to existing drainage and
irrigation systems;
(h) fencing, gates, boundary treatment and other means of enclosure;
(i) works for the provision of security and monitoring measures such as CCTV columns,
cameras, lighting columns and lighting, weather stations, perimeter fencing and
communication infrastructure;
(j) improvement, maintenance and use of existing private tracks;
(k) laying down of internal access tracks, ramps, means of access, footpaths, crossing of
watercourses and roads, including the laying and construction of drainage infrastructure,
signage and information boards;
(l) construction and decommissioning compounds, including site and welfare offices and
areas to store materials and equipment; and
(m) works to divert and underground existing electrical overhead lines.
Work No. 6 – construction and decommissioning compounds including—
(a) areas of hardstanding;
36Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(b) parking areas;
(c) site and welfare offices, canteens and workshops;
(d) security infrastructure, including cameras, perimeter fencing and lighting;
(e) areas to store materials and equipment and waste skips;
(f) site drainage and waste management infrastructure (including sewerage); and
(g) electricity, water, waste water and telecommunications connections.
Work No. 7 – works to develop operations and maintenance buildings including—
(a) alteration and maintenance of existing structures;
(b) offices, security and welfare facilities;
(c) storage facilities; and
(d) parking areas.
Work No. 8 – works to facilitate access to Work Nos. 1 to 9 including—
(a) creation of accesses from the public highway;
(b) creation of visibility splays;
(c) works to widen and surface the public highway and private means of access; and
(d) works adjacent to highways and accesses including those to structures, boundary features,
drainage features on private land required for the facilitation of movement of abnormal
indivisible loads associated with the authorised development.
Work No. 9 – areas of habitat management including—
(a) landscape and biodiversity enhancement measures;
(b) habitat creation and management including earthworks and landscaping, signage and
information boards;
(c) construction of drainage infrastructure and means of access;
(d) laying down of internal access tracks, means of access and crossing of watercourses,
permissive paths; and
(e) fencing, gates, boundary treatment and other means of enclosure.
In connection with and in addition to Work Nos. 1 to 9 further associated development within the
Order limits, including—
(a) works for the provision of fencing and security measures such as CCTV, columns, lighting
and communication boxes;
(b) laying down of internal access tracks, ramps and span bridges, means of access, non-
motorised links, footpaths and footways, laying and surfacing of permissive paths;
(c) laying down of temporary footpath diversions, permissive paths and construction of
drainage infrastructure, signage and information boards;
(d) bunds, embankments, trenching and swales;
(e) boundary treatments, including means of enclosure;
(f) habitat creation and management including earthworks, landscaping, means of enclosure
and the laying and construction of drainage infrastructure;
(g) landscaping and other works to mitigate any adverse effects of construction, maintenance
or operation of the authorised development;
37Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(h) electrical, gas, water, foul water drainage and telecommunications infrastructure
connections, diversions and works to alter the position of, such services and utilities
connections;
(i) works to alter the course of, or otherwise interfere with, non-navigable rivers, streams or
watercourses;
(j) works to the existing irrigation system and works to alter the position and extent of such
irrigation system;
(k) surface water drainage systems, storm water attenuation systems including storage basins,
oil water separators, including channelling and culverting and works to existing drainage
systems;
(l) site establishments and preparation works including site clearance (including vegetation
removal, demolition of existing buildings and structures); earthworks (including soil
stripping and storage and site levelling) and excavations; the alteration of the position of
services and utilities; and works for the protection of buildings and land;
(m) tunnelling, boring and drilling works;
(n) working sites in connection with the construction and decommissioning of the authorised
development and its restoration; and
(o) other works to mitigate any adverse effects of the construction, maintenance, operation or
decommissioning of the authorised development,
and further associated development comprising such other works or operations as may be necessary
or expedient for the purposes of or in connection with the construction, operation and maintenance
or decommissioning of the authorised development but only within the Order limits and insofar as
they fall within the scope of work assessed in the environmental statement.
SCHEDULE 2 Article 2
REQUIREMENTS
Commencement of the authorised development
1. The authorised development must not commence after the expiration of five years from the
date this Order comes into force.
Notice of date of final commissioning
2. Within 10 working days of the date of final commissioning the undertaker must serve written
notice of the date of final commissioning on the relevant planning authority.
Approved details and amendments to them
3.—(1) With respect to the documents certified under article 41 (certification of plans and
documents, etc.) and any plans, details or schemes which have been approved pursuant to any
requirement (together the “Approved Documents, Plans, Details or Schemes”), the undertaker
may submit to the relevant planning authority for approval of any amendments to any of the
Approved Documents, Plans, Details or Schemes and, following approval by the relevant planning
authority, the relevant Approved Documents, Plans, Details or Schemes is to be taken to include the
amendments as so approved pursuant to this paragraph.
38Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(2) Approval under sub-paragraph (1) for the amendments to any of the Approved Documents,
Plans, Details or Schemes must not be given except where it has been demonstrated to the satisfaction
of the relevant planning authority that the subject matter of the approval sought is unlikely to give
rise to any materially new or materially different environmental effects from those assessed in the
environmental statement.
(3) Where under any of the requirements the approval, agreement or confirmation of the relevant
planning authority is required, that approval, agreement or confirmation must be provided in writing.
Community liaison group
4.—(1) Prior to the commencement of the authorised development the undertaker must submit
to the relevant planning authority for approval the terms of reference for a community liaison group
whose aim is to facilitate liaison between representatives of people living in the vicinity of the Order
limits and other relevant organisations in relation to the construction of the authorised development.
(2) The community liaison group must be established prior to commencement of the authorised
development and must be administered by the undertaker, and operated, in accordance with the
approved terms of reference.
(3) The community liaison group is to continue to meet until the date of final commissioning
of the final part of the authorised development unless otherwise agreed with the relevant planning
authority.
Detailed design approval
5.—(1) No part of the authorised development may commence until details of—
(a) layout;
(b) scale;
(c) proposed finished ground levels;
(d) external appearance;
(e) hard surfacing materials;
(f) vehicular and pedestrian access, parking, fencing and circulation areas;
(g) refuse or other storage units, signs and lighting;
(h) drainage, water, power and communications cables and pipelines;
(i) programme for landscaping works;
(j) fencing;
(k) security measures; and
(l) any mitigation measures necessary to address noise impacts
relating to that part have been submitted and approved by the relevant planning authority.
(2) The details submitted must accord with—
(a) the location and order limits plan;
(b) the works plans;
(c) the principles and assessments set out in the environmental statement; and
(d) the outline design parameters statement.
(3) The details submitted must confirm if the authorised development will include the
construction and operation of either Work No. 4 or Work No. 5(b) but not both.
(4) The authorised development must be carried out in accordance with the approved details.
39Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Battery safety management
6.—(1) Work No. 2 must not commence until a battery safety management plan has been
submitted to and approved by the relevant planning authority.
(2) The battery safety management plan must be substantially in accordance with the framework
battery safety management plan.
(3) The relevant planning authority must consult with the South Yorkshire Fire Service and
the Environment Agency before determining an application for approval of the battery safety
management plan.
(4) The battery safety management plan must be implemented as approved and maintained
throughout the construction, operation and decommissioning of Work No. 2.
Landscape and Ecological management plan
7.—(1) No part of the authorised development may commence until a written landscape and
ecological management plan for that part has been submitted to and approved by the relevant
planning authority.
(2) The landscape and ecological management plan must be substantially in accordance with the
framework landscape and ecological management plan and must be implemented as approved and
maintained throughout the operation of the relevant part of the authorised development to which
the plan relates.
(3) For the purposes of sub-paragraph (1), “commence” includes part (h) (site clearance
(including vegetation removal, demolition of existing buildings and structures)) and part (i)
(advanced planting to allow for an early establishment of protective screening) of the permitted
preliminary works, as defined in article 1 (interpretation) of this Order.
Biodiversity net gain
8.—(1) No part of the authorised development may commence until a biodiversity net gain
strategy has been submitted to and approved by the relevant planning authority for that part, in
consultation with the relevant statutory nature conservation body.
(2) The biodiversity net gain strategy must include details of how the strategy will secure a
minimum of 20% biodiversity net gain for habitat units, a minimum of 20% biodiversity net gain
for hedgerow units and a minimum of 10% biodiversity net gain for watercourse units, calculated
using the Department of the Environment, Food and Rural Affairs’ Statutory Metric (July 2025), or
if this is withdrawn or replaced, a biodiversity metric approved by the relevant planning authority
in consultation with the relevant statutory nature conservation body and must be implemented as
approved.
(3) The biodiversity net gain strategy must be substantially in accordance with the framework
landscape and ecological management plan and must be implemented as approved and maintained
throughout the operation of the relevant part of the authorised development to which the plan relates.
Fencing and other means of enclosure
9.—(1) No part of the authorised development may commence until details of all proposed
temporary fences, walls or other means of enclosure, including those set out in the construction
environmental management plan, for that part have been submitted to and approved by the relevant
planning authority.
(2) No part of the authorised development may commence until details of all permanent
fences, walls or other means of enclosure, including those set out in the construction environmental
40Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
management plan, for that part have been submitted to and approved by the relevant planning
authority.
(3) For the purposes of sub-paragraph (1), “commence” includes any permitted preliminary
works.
(4) Any construction site must remain securely fenced in accordance with the approved details
under requirement 12(1) at all times during construction of the authorised development.
(5) Any temporary fencing must be removed on completion of the part of construction of the
authorised development for which it was used.
Surface and foul water drainage
10.—(1) No part of the authorised development may commence until details of the surface water
drainage strategy and (if any) foul water drainage system (including means of pollution control) for
that part have been submitted to and approved by the relevant planning authority in consultation
with the Environment Agency.
(2) The approved drainage strategy must be substantially in accordance with the framework
drainage strategy.
(3) Any strategy approved pursuant to sub-paragraph (1) must be implemented as approved and
maintained throughout the construction and operation of the authorised development.
(4) For the purposes of sub-paragraph (1), “commence” includes any site preparation works.
Archaeology
11.—(1) No part of the authorised development may commence, and no part of the permitted
preliminary works for that part may commence, until the final Archaeological Mitigation Strategy
and site-specific written scheme of investigation for that part have been submitted to and approved
by the relevant planning authority.
(2) The final Archaeological Mitigation Strategy and site-specific written scheme of investigation
must be substantially in accordance with the framework Archaeological Mitigation Strategy and
must be implemented as approved.
(3) Any archaeological works or programme of archaeological investigation carried out under
the approved written scheme for investigation must be carried out by an organisation registered with
the Chartered Institute for Archaeologists or by a member of that institute.
(4) Any archaeological works or programme of archaeological investigation must be carried out
in accordance with the approved final Archaeological Mitigation Strategy and written scheme of
investigation.
Construction environmental management plan
12.—(1) No part of the authorised development may commence until a construction
environmental management plan for that part has been submitted to and approved by the relevant
planning authority. Such approval to be in consultation with the relevant highway authority and the
Environment Agency.
(2) The construction environmental management plan must be substantially in accordance with
the framework construction environmental management plan and must be implemented as approved.
(3) The plan submitted and approved pursuant to sub-paragraph (1) must include a site
waste management plan that must be substantially in accordance with the framework site waste
management plan and must be implemented as approved.
41Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Operational environmental management plan
13.—(1) Prior to the date of final commissioning for any part of the authorised development, an
operational environmental management plan for that part must be submitted to and approved by the
relevant planning authority in consultation with the highway authority and the Environment Agency.
(2) The operational environmental management plan must be substantially in accordance with
the framework operational environmental management plan and must include a waste management
strategy.
(3) The operational environmental management plan must be implemented as approved and
maintained throughout the operation of the relevant part of the authorised development to which
the plan relates.
Construction traffic management plan
14.—(1) No part of the authorised development may commence until a construction traffic
management plan for that part has been submitted to and approved by the relevant planning authority.
Such approval to be in consultation with Network Rail Infrastructure Limited, the relevant highway
authority and National Highways Limited.
(2) The construction traffic management plan must be substantially in accordance with the
framework construction traffic management plan and must be implemented as approved.
Operational noise
15.—(1) No part of Work No. 1, Work No. 2 or Work No. 3 may commence until an
operational noise assessment containing details of how the design of the authorised development has
incorporated mitigation to ensure the operational noise rating levels as set out in the environmental
statement will be complied with for that part has been submitted to and approved by the relevant
planning authority for that part.
(2) The mitigation measures described in the operational noise assessment for each part of the
authorised development must be implemented as approved and maintained throughout the operation
of the relevant part of the authorised development to which the plan relates.
Soil management plan
16.—(1) No part of the authorised development may commence until a soil management plan
for that part has been submitted to and approved by the relevant planning authority.
(2) The soils management plan must be substantially in accordance with the framework soil
management plan and must be implemented as approved.
Skills, supply chain and employment
17.—(1) No part of the authorised development may commence until a skills, supply chain and
employment plan in relation to that part has been submitted to and approved by the relevant planning
authority.
(2) The skills, supply chain and employment plan must be substantially in accordance with the
framework skills, supply chain and employment plan and must be implemented as approved and
maintained throughout the operation of the relevant part of the authorised development to which
the plan relates.
(3) The skills, supply chain and employment plan must identify opportunities for individuals and
businesses to access employment, skills and supply chain opportunities associated with that part of
the authorised development, and the means for publicising such opportunities.
42Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Public rights of way
18.—(1) No part of the authorised development may commence until a public rights of way
management plan for any sections of public rights of way shown to be temporarily closed or stopped
up within Schedule 6 (streets and public rights of way) for that part has been submitted to and
approved by the relevant planning authority. Such approval to be in consultation with the relevant
highway authority.
(2) The public rights of way management plan must be substantially in accordance with the
framework public rights of way management plan and must be implemented as approved.
(3) The public rights of way management plan must be implemented as approved unless otherwise
agreed with the relevant planning authority in consultation with the relevant highway authority.
Decommissioning and restoration
19.—(1) No later than 12 months, or such time period as agreed with the relevant planning
authority, prior to the date that the undertaker intends to decommission any part of the authorised
development, the undertaker must submit to the relevant planning authority for approval in
consultation with the Environment Agency, Network Rail Infrastructure Limited, the relevant
highway authority and National Highways Limited, a decommissioning environmental management
plan for that part.
(2) Decommissioning must commence no later than 40 years following the date of final
commissioning.
(3) The plan submitted and approved pursuant to sub-paragraph (1) must be substantially in
accordance with the framework decommissioning environmental management plan and must be
implemented as approved.
(4) The plan submitted and approved pursuant to sub-paragraph (1) must include a resource
management plan that includes details of proposals to minimise the use of natural resources and
unnecessary materials.
(5) No decommissioning works must be carried out until the relevant planning authority
approves, in consultation with the Environment Agency, Network Rail Infrastructure Limited, the
relevant highway authority, and National Highways Limited, the plans submitted pursuant to sub-
paragraph (1).
(6) This requirement is without prejudice to any other consents or permissions which may be
required to decommission any part of the authorised development.
Requirement for written approval
20. Where the approval, agreement or confirmation of the Secretary of State, relevant planning
authority or another person is required under a requirement that approval, agreement or confirmation
must be given in writing.
SCHEDULE 3 Article 6
LEGISLATION TO BE DISAPPLIED
1. The following provisions do not apply in so far as they relate to the construction of any
numbered work or the carrying out of any operation required for the purpose of, or in connection
with, the construction, operation, maintenance or decommissioning of the authorised development—
43Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(a) River Dun Navigation Act 1821(53);
(b) River Dun Navigation Act 1826(54);
(c) River Dun Drainage Act 1827(55);
(d) West Yorkshire Drainage Act 1831(56);
(e) Road from Doncaster to Selby Act 1832(57);
(f) Great Northern Railway Amendment and Isle of Axholme Extension Act 1848(58);
(g) Doncaster Corporation Waterworks Act 1873(59);
(h) Dun Drainage Act 1873(60);
(i) Doncaster Corporation Waterworks Act 1880(61);
(j) Aire and Calder and River Dun Navigation Junction Canal Act 1891(62);
(k) Aire and Calder Navigation Act 1899(63);
(l) Land Drainage (Braithwaite Moss) Provisional Order Confirmation Act 1912(64);
(m) Aire and Calder Navigation Act 1914(65);
(n) Doncaster Area Drainage Act 1929(66);
(o) Doncaster Area Drainage Act 1933(67); and
(p) Aire and Calder Navigation Act 1992(68).
SCHEDULE 4 Article 8
STREETS SUBJECT TO STREET WORKS
Interpretation
1. In this Schedule—
“cable works” means works to place, retain and maintain underground electrical and
communications apparatus.
(53) 1821 c. xlvi.
(54) 1826 c. xcvii.
(55) 1827 c. xciv.
(56) 1831 c. xxxvi.
(57) 1832 c. lxxxvi.
(58) 1848 c. cxiv.
(59) 1873 c. cxxix.
(60) 1873 c. cxcv.
(61) 1880 c. xxix.
(62) 1891 c. clxx.
(63) 1899 c. cvi.
(64) 1912 c. clxviii.
(65) 1914 c. xxxiii.
(66) 1929 c. xvii.
(67) 1933 c. x.
(68) 1992 c. iv.
44Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3)
Area Street Description of the street
works
City of Doncaster Council Lawn Lane Street works to facilitate
cable works and carriageway
surface repairs for the length
shown in green patterned
hatching within proximity of
access 3/08 on Sheet 3 of
the streets, rights of way and
access plans
City of Doncaster Council Fenwick Common Lane Street works to facilitate
carriageway surface repairs
for the length shown in green
patterned hatching within
proximity of access 3/14 and
5/15 on Sheets 3 and 5 of
the streets, rights of way and
access plans
City of Doncaster Council West Lane Street works to facilitate
carriageway surface repairs
for the length shown in green
patterned hatching within
proximity of access 4/03 on
Sheet 4 of the streets, rights of
way and access plans
City of Doncaster Council Moss Road Street works to facilitate
carriageway surface repairs
for the length shown in green
patterned hatching within
proximity of access 5/25 on
Sheet 5 of the streets, rights of
way and access plans
City of Doncaster Council Moss Road Street works to facilitate
cable works and carriageway
surface repairs for the length
shown in green patterned
hatching within proximity of
access 6/14 on Sheet 6 of
the streets, rights of way and
access plans
City of Doncaster Council Brick Kiln Lane Street works to facilitate
cable works and carriageway
surface repairs for the length
shown in green patterned
hatching within proximity of
access 7/04 on Sheet 7 of
45Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3)
Area Street Description of the street
works
the streets, rights of way and
access plans
City of Doncaster Council Trumfleet Lane Street works to facilitate
cable works and carriageway
surface repairs for the length
shown in green patterned
hatching within proximity of
access 7/07 on Sheet 7 of
the streets, rights of way and
access plans
City of Doncaster Council Trumfleet Lane Street works to facilitate
cable works and carriageway
surface repairs for the length
shown in green patterned
hatching within proximity of
access 8/03 on Sheet 8 of
the streets, rights of way and
access plans
City of Doncaster Council Marsh Road Street works to facilitate
cable works and carriageway
surface repairs for the length
shown in green patterned
hatching within proximity of
access 8/08 on Sheet 8 of
the streets, rights of way and
access plans
City of Doncaster Council Thorpe Lane Street works to facilitate
cable works for the length
shown in green patterned
hatching within proximity of
access 9/01 on Sheet 9 of
the streets, rights of way and
access plans
City of Doncaster Council Thorpe Bank Street works to facilitate
cable works and carriageway
surface repairs for the length
shown in green patterned
hatching within proximity of
access 9/02 and 10/06 on
Sheets 9 and 10 of the streets,
rights of way and access plans
City of Doncaster Council Fordstead Lane Street works to facilitate
carriageway surface repairs
for the length shown in green
patterned hatching within
46Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3)
Area Street Description of the street
works
proximity of access 10/15 on
Sheet 10 of the streets, rights
of way and access plans
City of Doncaster Council Marsh Lane Street works to facilitate
carriageway surface repairs
for the length shown in green
patterned hatching within
proximity of access 10/13 on
Sheet 10 of the streets, rights
of way and access plans
City of Doncaster Council South Road Street works to facilitate
carriageway surface repairs
for the length shown in green
patterned hatching within
proximity of access 10/10 on
Sheet 10 of the streets, rights
of way and access plans
City of Doncaster Council High Street Street works to facilitate
carriageway surface repairs
for the length shown in green
patterned hatching within
proximity of access 11/01 on
Sheet 11 of the streets, rights
of way and access plans
City of Doncaster Council Station Road Street works to facilitate
carriageway surface repairs
for the length shown in green
patterned hatching within
proximity of access 11/04 on
Sheet 11 of the streets, rights
of way and access plans
City of Doncaster Council Moss Road Street works to facilitate
carriageway surface repairs
for the length shown in green
patterned hatching within
proximity of access 11/15 on
Sheet 11 of the streets, rights
of way and access plans
47Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
SCHEDULE 5 Articles 10 and 11
ALTERATION OF STREETS
PART 1
PERMANENT ALTERATION OF LAYOUT
(1) (2) (3)
Area Street Description of the Alteration
City of Doncaster Council Lawn Lane Alteration of layout of Lawn
Lane in the area depicted in
solid green hatching at the
points marked 3/07 and 3/08 as
shown on Sheet 3 of the streets,
rights of way and access plans
subsequent to improvements to
adjoining field access.
City of Doncaster Council Moss Road Alteration of layout of Moss
Road in the area depicted in
solid green hatching at the point
marked 6/14 as shown on Sheet
6 of the streets, rights of way
and access plans subsequent
to improvements to adjoining
field access.
PART 2
TEMPORARY ALTERATION OF LAYOUT
(1) (2) (3)
Area Street Description of the Alteration
City of Doncaster Council Moss Road Alteration of layout to Moss
Road in the area depicted in
solid green hatching adjacent
to the point marked 6/17 as
shown on Sheet 6 of the streets,
rights of way and access plans
subsequent to improvements to
adjoining field access.
City of Doncaster Council Brick Kiln Lane Alteration of layout to Brick
Kiln Lane in the area depicted
in solid green hatching adjacent
to the point marked 7/04 as
shown on Sheet 7 of the streets,
48Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3)
Area Street Description of the Alteration
rights of way and access plans
subsequent to improvements to
adjoining field access.
City of Doncaster Council Trumfleet Lane Alteration of layout to
Trumfleet Lane in the area
depicted in solid green hatching
adjacent to the point marked
7/07 as shown on Sheet 7
of the streets, rights of way
and access plans subsequent
to improvements to adjoining
field access.
City of Doncaster Council Trumfleet Lane Alteration of layout to
Trumfleet Lane in the area
depicted in solid green hatching
adjacent to the point marked
8/02 as shown on Sheet 8
of the streets, rights of way
and access plans subsequent to
construction of adjoining new
access.
City of Doncaster Council Marsh Road Alteration of layout to Marsh
Road in the area depicted in
solid green hatching adjacent
to the point marked 8/08 and
8/11 as shown on Sheet 8
of the streets, rights of way
and access plans subsequent
to improvements to adjoining
field access.
City of Doncaster Council Thorpe Bank Alteration of layout to Marsh
Road in the area depicted in
solid green hatching adjacent
to the point marked 9/02 as
shown on Sheet 9 of the streets,
rights of way and access plans
subsequent to improvements to
adjoining private access.
City of Doncaster Council Thorpe Bank Alteration of layout to Thorpe
Bank in the area depicted in
solid green hatching adjacent
to the point marked 10/05
as shown on Sheet 10 of
the streets, rights of way
and access plans subsequent
to improvements to adjoining
private access.
49Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3)
Area Street Description of the Alteration
City of Doncaster Council Fordstead Lane Alteration of layout to
Fordstead Lane in the area
depicted in solid green hatching
adjacent to the point marked
10/15 as shown on Sheet 10
of the streets, rights of way
and access plans subsequent to
improvement to Fordstead Lane
and Marsh Lane.
City of Doncaster Council High Street Alteration of layout to High
Street in the area depicted in
solid green hatching adjacent
to the point marked 11/01 as
shown on Sheet 11 of the
streets, rights of way and access
plans subsequent to alteration
to accommodate abnormal load
manoeuvre.
SCHEDULE 6 Article 12 and 13
STREETS AND PUBLIC RIGHTS OF WAY
PART 1
STREETS TO BE TEMPORARILY CLOSED
(SINGLE LANE CLOSURES / STREET CLOSURE)
(1) (2) (3)
Area Street Measures
City of Doncaster Council Lawn Lane Temporary street closure to all
traffic save for traffic under
the direction of the undertaker
for the width of the street
to facilitate the alteration of
layout and street works for the
lengths shown in green solid
and patterned hatching on Sheet
3 of the streets, rights of way
and access plans.
City of Doncaster Council Fenwick Common Lane Temporary single lane closure
to all traffic save for traffic
under the direction of the
50Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3)
Area Street Measures
undertaker for the width of the
street to facilitate the street
works for the lengths shown
in green patterned hatching on
Sheets 3 and 5 of the streets,
rights of way and access plans.
City of Doncaster Council West Lane Temporary single lane closure
to all traffic save for traffic
under the direction of the
undertaker for the width of the
street to facilitate the street
works for the length shown
in green patterned hatching on
Sheet 4 of the streets, rights of
way and access plans.
City of Doncaster Council Moss Road Temporary single lane closure
to all traffic save for traffic
under the direction of the
undertaker for the width of the
street to facilitate the street
works for the length shown
in green patterned hatching on
Sheet 5 of the streets, rights of
way and access plans.
City of Doncaster Council Moss Road Temporary single lane closure
to all traffic save for traffic
under the direction of the
undertaker for the width of the
street to facilitate the alteration
of layout and street works for
the lengths shown in green solid
and patterned hatching on Sheet
6 of the streets, rights of way
and access plans.
City of Doncaster Council Brick Kiln Lane Temporary street closure to all
traffic save for traffic under
the direction of the undertaker
for the width of the street
to facilitate the alteration of
layout and street works for the
lengths shown in green solid
and patterned hatching on Sheet
7 of the streets, rights of way
and access plans.
City of Doncaster Council Trumfleet Lane Temporary single lane closure
to all traffic save for traffic
under the direction of the
51Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3)
Area Street Measures
undertaker for the width of the
street to facilitate the alteration
of layout and street works for
the lengths shown in green solid
and patterned hatching on Sheet
7 of the streets, rights of way
and access plans.
City of Doncaster Council Trumfleet Lane Temporary single lane closure
to all traffic save for traffic
under the direction of the
undertaker for the width of the
street to facilitate the alteration
of layout and street works for
the lengths shown in green solid
and patterned hatching on Sheet
8 of the streets, rights of way
and access plans.
City of Doncaster Council Marsh Road Temporary single lane closure
to all traffic save for traffic
under the direction of the
undertaker for the width of the
street to facilitate the alteration
of layout and street works for
the lengths shown in green solid
and patterned hatching on Sheet
8 of the streets, rights of way
and access plans.
City of Doncaster Council Thorpe Bank Temporary single lane closure
to all traffic save for traffic
under the direction of the
undertaker for the width of the
street to facilitate the alteration
of layout and street works for
the lengths shown in green
solid and patterned hatching on
Sheets 9 and 10 of the streets,
rights of way and access plans.
City of Doncaster Council Thorpe Lane Temporary single lane closure
to all traffic save for traffic
under the direction of the
undertaker for the width of the
street to facilitate the street
works for the length shown
in green patterned hatching on
Sheet 9 of the streets, rights of
way and access plans.
52Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3)
Area Street Measures
City of Doncaster Council Fordstead Lane Temporary single lane closure
to all traffic save for traffic
under the direction of the
undertaker for the width of the
street to facilitate the alteration
of layout and street works for
the length shown in green solid
and patterned hatching on Sheet
10 of the streets, rights of way
and access plans.
City of Doncaster Council Marsh Lane Temporary single lane closure
to all traffic save for traffic
under the direction of the
undertaker for the width of the
street to facilitate the street
works for the length shown
in green patterned hatching on
Sheet 10 of the streets, rights of
way and access plans.
City of Doncaster Council South Lane Temporary single lane closure
to all traffic save for traffic
under the direction of the
undertaker for the width of the
street to facilitate the street
works for the length shown
in green patterned hatching on
Sheet 10 of the streets, rights of
way and access plans.
City of Doncaster Council High Street Temporary single lane closure
to all traffic save for traffic
under the direction of the
undertaker for the width of the
street to facilitate the alteration
of layout and street works for
the lengths shown in green solid
and patterned hatching on Sheet
11 of the streets, rights of way
and access plans.
City of Doncaster Council Station Road Temporary single lane closure
to all traffic save for traffic
under the direction of the
undertaker for the width of the
street to facilitate the street
works for the length shown
in green patterned hatching on
Sheet 11 of the streets, rights of
way and access plans.
53Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3)
Area Street Measures
City of Doncaster Council Moss Road Temporary single lane closure
to all traffic save for traffic
under the direction of the
undertaker for the width of the
street to facilitate the street
works for the length shown
in green patterned hatching on
Sheet 11 of the streets, rights of
way and access plans.
PART 2
PUBLIC RIGHTS OF WAY TO BE TEMPORARILY CLOSED AND DIVERTED
(1) (2) (3)
Area Public right of way Measures
City of Doncaster Council Fenwick-16 Public Right of Way to be
temporarily closed and diverted
between PRoW 03/06 and
PRoW 03/10 as shown on
Sheet 3 of the streets, access
and rights of way plans, to
facilitate the construction of the
authorised development.
City of Doncaster Council Moss-6 Public Right of Way to be
temporarily closed and diverted
between PRoW 06/05 and
PRoW 06/06 as shown on
Sheet 6 of the streets, access
and rights of way plans, to
facilitate the construction of the
authorised development.
City of Doncaster Council Fenwick-14 Public Right of Way to be
temporarily closed and diverted
between PRoW 06/02 and
PRoW 06/05 as shown on
Sheet 6 of the streets, access
and rights of way plans, to
facilitate the construction of the
authorised development.
54Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
PART 3
PERMANENT USE OF MOTOR VEHICLES ON PUBLIC RIGHT OF WAY
(1) (2) (3)
Area Public right of way Measures
City of Doncaster Council Fenwick-10 between PRoW Permanent use of motor
03/02 and PRoW 04/05 vehicles under the direction
of the undertaker at location
PRoW 03/02 and PRoW 04/05
as shown on Sheets 3 and 4
of the streets, access and rights
of way plans to facilitate the
construction and operation of
the Scheme.
City of Doncaster Council Fenwick-14 between PRoW Permanent use of motor
03/03 and PRoW 06/02 vehicles under the direction
of the undertaker at location
PRoW 03/03 and PRoW 06/02
as shown on Sheets 3 and 6
of the streets, access and rights
of way plans to facilitate the
construction and operation of
the Scheme.
City of Doncaster Council Fenwick-15 between PRoW Permanent use of motor
03/04 and PRoW 04/07 vehicles under the direction
of the undertaker at location
PRoW 03/04 and PRoW 04/07
as shown on Sheets 3 and 4
of the streets, access and rights
of way plans to facilitate the
construction and operation of
the Scheme.
City of Doncaster Council Fenwick-16 between PRoW Permanent use of motor
03/06 and PRoW 03/10 vehicles under the direction
of the undertaker at location
PRoW 03/06 and PRoW 03/10
as shown on Sheet 3 of the
streets, access and rights of
way plans to facilitate the
construction and operation of
the Scheme.
City of Doncaster Council Fenwick-11 between PRoW Permanent use of motor
03/07 and PRoW 03/08 vehicles under the direction
of the undertaker at location
PRoW 03/07 and PRoW 03/08
as shown on Sheet 3 of the
streets, access and rights of
way plans to facilitate the
55Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3)
Area Public right of way Measures
construction and operation of
the Scheme.
City of Doncaster Council Fenwick-11 between PRoW Permanent use of motor
03/09 and PRoW 05/01 vehicles under the direction
of the undertaker at location
PRoW 03/09 and PRoW 05/01
as shown on Sheets 3 and 5
of the streets, access and rights
of way plans to facilitate the
construction and operation of
the Scheme.
City of Doncaster Council Fenwick-13 between PRoW Permanent use of motor
04/06 and PRoW 06/03 vehicles under the direction
of the undertaker at location
PRoW 04/06 and PRoW 06/03
as shown on Sheets 4 and 6
of the streets, access and rights
of way plans to facilitate the
construction and operation of
the Scheme.
City of Doncaster Council Fenwick-11 between PRoW Permanent use of motor
05/02 and PRoW 05/03 vehicles under the direction
of the undertaker at location
PRoW 05/02 and PRoW 05/03
as shown on Sheet 5 of the
streets, access and rights of
way plans to facilitate the
construction and operation of
the Scheme.
City of Doncaster Council Moss-5 between PRoW 05/03 Permanent use of motor
and PRoW 05/04 vehicles under the direction
of the undertaker at location
PRoW 05/03 and PRoW 05/04
as shown on Sheet 5 of the
streets, access and rights of
way plans to facilitate the
construction and operation of
the Scheme.
City of Doncaster Council Moss-6 between PRoW 06/01 Permanent use of motor
and PRoW 06/02 vehicles under the direction
of the undertaker at location
PRoW 06/01 and PRoW 06/02
as shown on Sheet 6 of the
streets, access and rights of
way plans to facilitate the
construction and operation of
the Scheme.
56Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
PART 4
TEMPORARY MANAGEMENT OF PUBLIC RIGHTS OF WAY
(1) (2) (3)
Area Public right of way Measure
City of Doncaster Council Fenwick-12 between PRoW Public Right of Way between
03/01 and PRoW 04/01 PRoW 03/01 and PRoW 04/01
as shown on Sheets 3 and 4 of
the streets, access and rights of
way plans to be managed during
construction of the authorised
development
City of Doncaster Council Fenwick-10 between PRoW Public Right of Way between
03/02 and PRoW 04/05 PRoW 03/02 and PRoW 04/05
as shown on Sheets 3 and 4 of
the streets, access and rights of
way plans to be managed during
construction of the authorised
development
City of Doncaster Council Fenwick-14 between PRoW Public Right of Way between
03/03 and PRoW 06/02 PRoW 03/03 and PRoW 06/02
as shown on Sheets 3 and 6 of
the streets, access and rights of
way plans to be managed during
construction of the authorised
development
City of Doncaster Council Fenwick-15 between PRoW Public Right of Way between
03/04 and PRoW 04/07 PRoW 03/04 and PRoW 04/07
as shown on Sheets 3 and 4 of
the streets, access and rights of
way plans to be managed during
construction of the authorised
development
City of Doncaster Council Fenwick-16 between 03/05 and Public Right of Way between
03/10 PRoW 03/05 and PRoW 03/10
as shown on Sheet 3 of the
streets, access and rights of way
plans to be managed during
construction of the authorised
development
City of Doncaster Council Fenwick-11 between PRoW Public Right of Way between
03/07 and PRoW 03/08 PRoW 03/07 and PRoW 03/08
as shown on Sheet 3 of the
streets, access and rights of way
plans to be managed during
construction of the authorised
development
57Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3)
Area Public right of way Measure
City of Doncaster Council Fenwick-11 between PRoW Public Right of Way between
03/09 and PRoW 05/01 PRoW 03/09 and PRoW 05/01
as shown on Sheets 3 and 5 of
the streets, access and rights of
way plans to be managed during
construction of the authorised
development
City of Doncaster Council Fenwick-12 between PRoW Public Right of Way between
04/02 and PRoW 04/03 PRoW 04/02 and PRoW 04/03
as shown on Sheet 4 of the
streets, access and rights of way
plans to be managed during
construction of the authorised
development
City of Doncaster Council Fenwick-13 between PRoW Public Right of Way between
04/06 and PRoW 06/03 PRoW 04/06 and PRoW 06/03
as shown on Sheets 4 and 6 of
the streets, access and rights of
way plans to be managed during
construction of the authorised
development
City of Doncaster Council Fenwick-11 between PRoW Public Right of Way between
05/02 and PRoW 05/03 PRoW 05/02 and PRoW 05/03
as shown on Sheet 5 of the
streets, access and rights of way
plans to be managed during
construction of the authorised
development
City of Doncaster Council Moss-5 between PRoW 05/03 Public Right of Way between
and PRoW 05/04 PRoW 05/03 and PRoW 05/04
as shown on Sheet 5 of the
streets, access and rights of way
plans to be managed during
construction of the authorised
development
City of Doncaster Council Moss-6 between PRoW 06/01 Public Right of Way between
and PRoW 06/02 PRoW 06/01 and PRoW 06/02
as shown on Sheet 6 of the
streets, access and rights of way
plans to be managed during
construction of the authorised
development
City of Doncaster Council Moss-20 between PRoW 07/01 Public Right of Way between
and PRoW 07/02 PRoW 07/01 and PRoW 07/02
as shown on Sheet 7 of the
streets, access and rights of way
58Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3)
Area Public right of way Measure
plans to be managed during
construction of the authorised
development
City of Doncaster Council Thorpe in Balne-6 between Public Right of Way between
PRoW 08/01 and PRoW 08/02 PRoW 08/01 and PRoW 08/02
as shown on Sheet 8 of the
streets, access and rights of way
plans to be managed during
construction of the authorised
development
City of Doncaster Council Thorpe in Balne-7 between Public Right of Way between
PRoW 08/03 and PRoW 08/04 PRoW 08/03 and PRoW 08/04
as shown on Sheet 8 of the
streets, access and rights of way
plans to be managed during
construction of the authorised
development
City of Doncaster Council Thorpe in Balne-8 between Public Right of Way between
PRoW 09/01 and PRoW 09/02 PRoW 09/01 and PRoW 09/02
as shown on Sheet 9 of the
streets, access and rights of way
plans to be managed during
construction of the authorised
development
City of Doncaster Council Thorpe in Balne-13 between Public Right of Way between
PRoW 09/03 and PRoW 09/04 PRoW 09/03 and PRoW 09/04
as shown on Sheet 9 of the
streets, access and rights of way
plans to be managed during
construction of the authorised
development
PART 5
TEMPORARY USE OF MOTOR VEHICLES ON PUBLIC RIGHTS OF WAY
(1) (2) (3)
Area Public right of way Measures
City of Doncaster Council Thorpe in Balne-7 between Temporary use of motor
PRoW 08/03 and PRoW 08/04 vehicles under the direction
of the undertaker at location
PRoW 08/03 and PRoW 08/04
as shown on Sheet 8 of the
streets, access and rights of
59Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3)
Area Public right of way Measures
way plans to facilitate the
construction of the Scheme.
City of Doncaster Council Thorpe in Balne-8 between Temporary use of motor
PRoW 09/01 and PRoW 09/02 vehicles under the direction
of the undertaker at location
PRoW 09/01 and PRoW 09/02
as shown on Sheet 9 of the
streets, access and rights of
way plans to facilitate the
construction of the Scheme.
City of Doncaster Council Thorpe in Balne-13 between Temporary use of motor
PRoW 09/03 and PRoW 09/04 vehicles under the direction
of the undertaker at location
PRoW 09/03 and PRoW 09/04
as shown on Sheet 9 of the
streets, access and rights of
way plans to facilitate the
construction of the Scheme.
PART 6
STOPPING UP AND DIVERSION OF PUBLIC RIGHTS OF WAY
(1) (2) (3) (4)
Area Public right of Extent of New public right of way to be
way to be closed closure substituted/provided
City of Sykehouse-29 The Public The Public Right of Way between PRoW
Doncaster Right of Way 04/05 and PRoW 04/08 on sheet 4 of the
Council between PRoW streets, rights of way and access plans.
04/04 and
PRoW 04/08 on
sheet 4 of the
streets, rights of
way and access
plans.
City of Moss-6 The Public The Public Right of Way between PRoW
Doncaster Right of Way 06/01 and PRoW 06/07 on sheet 6 of the
Council between PRoW streets, rights of way and access plans.
06/01 and
PRoW 06/02 on
sheet 6 of the
streets, rights of
way and access
plans.
60Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3) (4)
Area Public right of Extent of New public right of way to be
way to be closed closure substituted/provided
City of Fenwick-14 The Public The Public Right of Way between PRoW
Doncaster Right of Way 06/04 and PRoW 06/07 on sheet 6 of the
Council between PRoW streets, rights of way and access plans.
06/02 and
PRoW 06/04 on
sheet 6 of the
streets, rights of
way and access
plans.
City of Fenwick-12 The Public The Public Right of Way between PRoW
Doncaster Right of Way 04/05 and PRoW 04/08 on sheet 4 of the
Council between PRoW streets, rights of way and access plans.
04/04 and
PRoW 04/05 on
sheet 4 of the
streets, rights of
way and access
plans.
SCHEDULE 7 Article 15
MEANS OF ACCESS TO WORKS
PART 1
PERMANENT MEANS OF ACCESS TO WORKS
(1) (2) (3)
Area Public right of way Description of Means of
Access
City of Doncaster Council Existing Field Access off Lawn Existing field access to be
Lane Eastbound improved at the point marked
3/07 on Sheet 3 of the streets,
rights of way and access plans.
City of Doncaster Council Existing Field Access off West Existing field access at the point
Lane Eastbound marked 4/01 on Sheet 3 of the
streets, rights of way and access
plans.
City of Doncaster Council Existing Field Access off Lawn Existing field access to be
Lane Westbound improved at the point marked
3/08 on Sheet 3 of the streets,
rights of way and access plans.
61Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3)
Area Public right of way Description of Means of
Access
City of Doncaster Council Existing Field Access off Moss Existing field access to be
Road Eastbound improved at the point marked
6/14 on Sheet 6 of the streets,
rights of way and access plans.
PART 2
TEMPORARY MEANS OF ACCESS TO WORKS
(1) (2) (3)
Area Public right of way Description of Means of
Access
City of Doncaster Council Existing Field Access off Moss Existing field access to be
Road Westbound improved at the point marked
6/17 on Sheet 6 of the streets,
rights of way and access plans.
City of Doncaster Council Existing Field Access off Brick Existing field access to be
Kiln Lane Westbound improved at the point marked
7/04 on Sheet 7 of the streets,
rights of way and access plans
City of Doncaster Council Existing Field Access off Existing field access to be
Trumfleet Lane Southbound improved at the point marked
7/07 on Sheet 7 of the streets,
rights of way and access plans
City of Doncaster Council Proposed Access off Trumfleet Proposed new access to be
Lane Eastbound constructed at the point marked
08/02 on Sheet 8 of the streets,
rights of way and access plans
City of Doncaster Council Existing Field Access off Existing field access to be
Marsh Road Eastbound improved at the point marked
8/08 on Sheet 8 of the streets,
rights of way and access plans
City of Doncaster Council Existing Field Access off Existing field access to be
Marsh Road Westbound improved at the point marked
8/11 on Sheet 8 of the streets,
rights of way and access plans
City of Doncaster Council Existing Access off Thorpe Existing access to be improved
Bank Northbound at the point marked 9/02 on
Sheet 9 of the streets, rights of
way and access plans
City of Doncaster Council Existing Access off Thorpe Existing access to be improved
Bank Northbound at the point marked 10/05 on
62Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3)
Area Public right of way Description of Means of
Access
Sheet 10 of the streets, rights of
way and access plans
City of Doncaster Council Existing Access off Fordstead Existing access to be improved
Lane to Marsh Lane at the point marked 10/15 on
Sheet 10 of the streets, rights of
way and access plans
SCHEDULE 8 Article 17
TRAFFIC REGULATION MEASURES
(1) (2)
Area Extent of temporary traffic signal and
banksman control area
Lawn Lane Eastbound and Westbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 3 of the traffic
authorised development. regulation measures plans.
Haggs Lane Eastbound and Westbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 3 of the traffic
authorised development. regulation measures plans.
Fenwick Common Lane Northbound and Extents of traffic signals and banksperson
Southbound Carriageway to facilitate the control presented on Sheets 3 and 5 of the traffic
construction of the authorised development. regulation measures plans.
West Lane Eastbound and Westbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 4 of the traffic
authorised development. regulation measures plans.
Moss Road Eastbound and Westbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 5 of the traffic
authorised development. regulation measures plans.
Moss Road Eastbound and Westbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 6 of the traffic
authorised development. regulation measures plans.
Trumfleet Lane Northbound and Southbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 7 of the traffic
authorised development. regulation measures plans.
Brick Kiln Lane Eastbound and Westbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 7 of the traffic
authorised development. regulation measures plans.
63Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2)
Area Extent of temporary traffic signal and
banksman control area
Trumfleet Lane Eastbound and Westbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 8 of the traffic
authorised development. regulation measures plans.
Marsh Road Eastbound and Westbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 8 of the traffic
authorised development. regulation measures plans.
Thorpe Bank Northbound and Southbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheets 9 and 10 of the
authorised development. traffic regulation measures plans.
Thorpe Lane Eastbound and Westbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 9 of the traffic
authorised development. regulation measures plans.
Ash Road Eastbound and Westbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 10 of the traffic
authorised development. regulation measures plans.
Fordstead Lane Eastbound and Westbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 10 of the traffic
authorised development. regulation measures plans.
South Road Northbound and Southbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 10 of the traffic
authorised development. regulation measures plans.
Marsh Lane Northbound and Southbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 10 of the traffic
authorised development. regulation measures plans.
High Street Northbound and Southbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 11 of the traffic
authorised development. regulation measures plans.
Station Road Eastbound and Westbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 11 of the traffic
authorised development. regulation measures plans.
Moss Road Eastbound and Westbound Extents of traffic signals and banksperson
Carriageway to facilitate the construction of the control presented on Sheet 11 of the traffic
authorised development. regulation measures plans.
SCHEDULE 9 Article 23
LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED
Interpretation
1. In this Schedule—
64Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
“access rights” means rights over land to—
(a) alter, improve, form, maintain, retain, use (with or without vehicles, plant and
machinery), remove, reinstate means of access to the authorised development including
visibility splays, bridges and road widening and to remove impediments (including
vegetation) to such access;
(b) remain, pass and repass on foot, with or without vehicles, plant and machinery (including
rights to lay and use any temporary surface) for all purposes in connection with the
authorised development;
(c) install, use, support, protect, inspect, alter, remove, replace, refurbish, reconstruct, retain,
renew, improve and maintain security fencing, gates, boundary treatment, public rights
of way and any other ancillary apparatus and any other works as necessary;
(d) install, execute, implement, retain, repair, improve, renew, remove, relocate and
plant trees, woodlands, shrubs, hedgerows, seeding, landscaping and other ecological
measures together with the right to maintain, inspect and replant such trees, shrubs,
hedgerows, landscaping and other ecological measures the right to pass and repass
on foot, with or without vehicles, plant and machinery for all purposes in connection
with the implementation and maintenance of landscaping and ecological mitigation or
enhancement works;
(e) restrict and remove the erection of buildings or structures, restrict the altering of ground
levels, restrict and remove the planting of trees or carrying out operations or actions
(including but not limited to blasting and piling) which may obstruct, interrupt or
interfere with the exercise of the rights or damage the authorised development; and
(f) install, use, support, protect, inspect, alter, remove, replace, refurbish, reconstruct, retain,
renew, improve and maintain sewers, drains, pipes, ducts, mains, conduits, services, flues
and to drain into and manage waterflows in any drains, watercourses and culverts; and
“cable rights” means rights over land to—
(a) install, use, support, protect, inspect, alter, remove, replace, refurbish, reconstruct, retain,
renew, improve and maintain electrical underground cables, earthing cables, optical fibre
cables, data cables, telecommunications cables and other services, works associated with
such cables including bays, ducts, protection and safety measures and equipment, and
other ancillary apparatus and structures (including but not limited to access chambers,
manholes and marker posts) and any other works necessary together with the right to
fell, trim or lop trees and bushes which may obstruct or interfere with the said cables,
telecommunications and other ancillary apparatus;
(b) remain, pass and repass on foot, with or without vehicles, plant and machinery (including
rights to lay and use any temporary surface or form a temporary compound) for all
purposes in connection with the authorised development;
(c) continuous vertical and lateral support for the authorised development;
(d) install, use, support, protect, inspect, alter, remove, replace, refurbish, reconstruct, retain,
renew, improve and maintain sewers, drains, pipes, ducts, mains, conduits, services, flues
and to drain into and manage waterflows in any drains, watercourses and culverts;
(e) install, execute, implement, retain, repair, improve, renew, remove, relocate and
plant trees, woodlands, shrubs, hedgerows, seeding, landscaping and other ecological
measures together with the right to maintain, inspect and replant such trees, shrubs,
hedgerows, landscaping and other ecological measures the right to pass and repass
on foot, with or without vehicles, plant and machinery for all purposes in connection
with the implementation and maintenance of landscaping and ecological mitigation or
enhancement works;
65Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(f) install, use, support, protect, inspect, alter, remove, replace, refurbish, reconstruct, retain,
renew, improve and maintain security fencing, gates, boundary treatment, public rights
of way and any other ancillary apparatus and any other works as necessary; and
(g) restrict and remove the erection of buildings or structures, restrict the altering of ground
levels, restrict and remove vegetation and restrict the planting of trees or carrying
out operations or actions (including but not limited to blasting and piling) which may
obstruct, interrupt or interfere with the exercise of the rights or damage the authorised
development.
(1) (2)
Plot reference number shown on the Purposes for which rights over land
Land Plans may be required and restrictive
covenants imposed
2/04 Access rights
3/01 Cable rights and access rights
3/05 Cable rights and access rights
3/06 Cable rights
4/03 Access rights
4/04 Access rights
4/06 Access rights
4/07 Access rights
5/01 Access rights
5/03 Access rights
6/03 Access rights
6/04 Cable rights and access rights
6/05 Access rights
6/06 Access rights
6/07 Cable rights
6/08 Cable rights
7/01 Access rights
7/02 Cable rights and access rights
7/03 Cable rights
7/05 Cable rights
7/06 Access rights
7/07 Access rights
7/08 Cable rights and access rights
7/09 Access rights
7/10 Cable rights and access rights
66Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2)
Plot reference number shown on the Purposes for which rights over land
Land Plans may be required and restrictive
covenants imposed
8/01 Cable rights
8/02 Cable rights
8/03 Access rights
8/04 Cable rights and access rights
8/05 Access rights
8/06 Cable rights
8/07 Cable rights
8/08 Cable rights
8/09 Cable rights
8/10 Cable rights
8/11 Access rights
8/12 Access rights
8/13 Cable rights and access rights
8/14 Access rights
8/15 Cable rights
8/16 Cable rights
9/01 Cable rights
9/02 Cable rights
9/03 Cable rights
9/04 Cable rights
9/05 Access rights
9/06 Cable rights
9/07 Cable rights
9/08 Cable rights
9/09 Cable rights and access rights
9/10 Cable rights
9/11 Cable rights
9/12 Cable rights
9/13 Cable rights
9/14 Cable rights
9/15 Cable rights
67Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2)
Plot reference number shown on the Purposes for which rights over land
Land Plans may be required and restrictive
covenants imposed
10/01 Cable rights
10/02 Cable rights
10/03 Cable rights and access rights
10/04 Cable rights and access rights
10/05 Cable rights
10/06 Cable rights
10/07 Cable rights
10/08 Cable rights
10/09 Cable rights and access rights
10/10 Access rights
10/11 Access rights
10/12 Access rights
10/13 Access rights
10/14 Access rights
11/01 Access rights
11/02 Access rights
11/03 Access rights
11/04 Access rights
11/05 Access rights
11/06 Access rights
11/07 Access rights
SCHEDULE 10 Article 23
MODIFICATION OF COMPENSATION AND COMPULSORY
PURCHASE ENACTMENTS FOR THE CREATION OF NEW
RIGHTS AND IMPOSITION OF NEW RESTRICTIVE COVENANTS
Compensation enactments
1. The enactments for the time being in force with respect to compensation for the compulsory
purchase of land are to apply, with the necessary modifications as respects compensation, in the case
of a compulsory acquisition under this Order of a right by the creation of a new right or the imposition
68Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
of a restrictive covenant as they apply as respects compensation on the compulsory purchase of land
and interests in land.
2.—(1) Without limitation on the scope of paragraph 1, the Land Compensation Act 1973(69)
has effect subject to the modifications set out in sub-paragraph (2).
(2) In section 44(1) (compensation for injurious affection), as it applies to compensation for
injurious affection under section 7 (measure of compensation in case of severance) of the 1965 Act
as substituted by paragraph 5—
(a) for the words “land is acquired or taken from” substitute “a right or restrictive covenant
over land is purchased from or imposed on”, and
(b) for the words “acquired or taken from him” substitute “over which the right is exercisable
or the restrictive covenant enforceable”.
3.—(1) Without limitation on the scope of paragraph 1, the 1961 Act has effect subject to the
modifications set out in sub-paragraph (2).
(2) In section 5A(5A) (relevant valuation date), omit the words after “if—” and substitute—
(a) the acquiring authority enters on land for the purpose of exercising a right in pursuant of
a notice of entry under section 11(1) of the 1965 Act (as modified by paragraph 5(5) of
Schedule 10 to the Fenwick Solar Farm Order 2026);
(b) the acquiring authority is subsequently required by a determination under paragraph 12
of Schedule 2A to the 1965 Act (as substituted by paragraph 5(8) of Schedule 10 to the
Fenwick Solar Farm Order 2026) to acquire an interest in the land; and
(c) the acquiring authority enters on and takes possession of that land,
the authority is deemed for the purposes of subsection (3)(a) to have entered on that land where it
entered on that land for the purpose of exercising that right.
Application of Part 1 of the 1965 Act
4. Part 1 (compulsory purchase under Acquisition of Land Act 1946) of the 1965 Act, as applied
by section 125 (application of compulsory acquisition provisions) of the 2008 Act to the acquisition
of land under article 21 (compulsory acquisition of land) and as modified by article 28 (modification
of Part 1 of the Compulsory Purchase Act 1965), applies to the compulsory acquisition of a right by
the creation of a new right under article 23 (compulsory acquisition of rights)—
(a) with the modifications specified in paragraph 5; and
(b) with such other modifications as may be necessary.
5.—(1) The modifications referred to in paragraph 4(a) are as follows—
(2) References in the 1965 Act to land are, in the appropriate contexts, to be read (according to
the requirements of the particular context) as referring to, or as including references to—
(a) the right acquired or to be acquired, or the restriction imposed or to be imposed; or
(b) the land over which the right is or is to be exercisable, or the restriction is to be enforceable.
(3) For section 7 of the 1965 Act (measure of compensation in case of severance) substitute—
“7. In assessing the compensation to be paid by the acquiring authority under this Act,
regard must be had not only to the extent (if any) to which the value of the land over which
the right is to be acquired or the restrictive covenant is to be imposed is depreciated by the
acquisition of the right or the imposition of the covenant but also to the damage (if any)
(69) 1973 c. 26.
69Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
to be sustained by the owner of the land by reason of its severance from other land of the
owner, or injuriously affecting that other land by the exercise of the powers conferred by
this or the special Act.”.
(4) The following provisions of the 1965 Act (which state the effect of a deed poll executed in
various circumstances where there is no conveyance by persons with interests in the land), that is
to say—
(a) section 9(4) (failure by owners to convey);
(b) paragraph 10(3) of Schedule 1 (owners under incapacity);
(c) paragraph 2(3) of Schedule 2 (absent and untraced owners); and
(d) paragraphs 2(3) and 7(2) of Schedule 4 (common land),
are modified to secure that, as against persons with interests in the land which are expressed to be
overridden by the deed, the right which is to be compulsorily acquired or the restrictive covenant
which is to be imposed is vested absolutely in the acquiring authority.
(5) Section 11 (powers of entry) of the 1965 Act is modified to secure that, as from the date on
which the acquiring authority has served notice to treat in respect of any right or restrictive covenant,
as well as the notice of entry required by subsection (1) of that section (as it applies to compulsory
acquisition under article 21 (compulsory acquisition of land)), it has power, exercisable in equivalent
circumstances and subject to equivalent conditions, to enter for the purpose of exercising that right
or enforcing that restrictive covenant (which is deemed for this purpose to have been created on the
date of service of the notice); and sections 11A (powers of entry: further notices of entry)(70), 11B
(counter-notice requiring possession to be taken on specified date)(71), 12 (penalty for unauthorised
entry)(72) and 13 (refusal to give possession to acquiring authority) of the 1965 Act are modified
correspondingly.
(6) Section 20(73) (tenants at will, etc.) of the 1965 Act applies with the modifications necessary
to secure that persons with such interests in land as are mentioned in that section are compensated in
a manner corresponding to that in which they would be compensated on a compulsory acquisition
under this Order of that land, but taking into account only the extent (if any) of such interference
with such an interest as is actually caused, or likely to be caused, by the exercise of the right or
enforcement of the restrictive covenant in question.
(7) Section 22 (interests omitted from purchase) of the 1965 Act as modified by article 28(4)
(modification of Part 1 of the Compulsory Purchase Act 1965) is so modified as to enable the
acquiring authority, in circumstances corresponding to those referred to in that section, to continue
to be entitled to exercise the right acquired or restrictive covenant imposed, subject to compliance
with that section as respects compensation.
(8) For Schedule 2A to the 1965 Act (counter notice requiring purchase of land not in notice
to treat) substitute—
“SCHEDULE 2A
COUNTER-NOTICE REQUIRING PURCHASE OF LAND
1.—(1) This Schedule applies where an acquiring authority serves a notice to treat in respect
of a right over, or restrictive covenant affecting, the whole or part of a house, building or factory
and have not executed a general vesting declaration under section 4 of the 1981 Act as applied by
(70) Section 11A was inserted by section 186(3) of the Housing and Planning Act 2016.
(71) Section 11B was inserted by section 187(3) of the Housing and Planning Act 2016.
(72) Section 12 was amended by section 56(2) of, and Part 1 of Schedule 9 to, the Court Act 1971 (c. 23) and paragraphs (2) and
(4) of Schedule 16 to the Housing and Planning Act 2016.
(73) Section 20 was amended by paragraph 4 of Schedule 15 to the Planning and Compensation Act 1991 (c. 34) and S.I. 2009/1307.
70Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
article 25 (application of the 1981 Act) of the Fenwick Solar Farm Order 2026 in respect of the land
to which the notice to treat relates.
(2) But see article 26(3) (acquisition of subsoil only) of the Fenwick Solar Farm Order 2026
which excludes the acquisition of subsoil only from this Schedule
2. In this Schedule, “house” includes any park or garden belonging to a house.
Counter-notice requiring purchase of land
3. A person who is able to sell the house, building or factory (“the owner”) may serve a counter-
notice requiring the authority to purchase the owner’s interest in the house, building or factory.
4. A counter-notice under paragraph 3 must be served within the period of 28 days beginning
with the day on which the notice to treat was served.
Response to counter-notice
5. On receiving a counter-notice, the acquiring authority must decide whether to—
(a) withdraw the notice to treat,
(b) accept the counter-notice, or
(c) refer the counter notice to the Upper Tribunal.
6. The authority must serve notice of their decision on the owner within the period of three months
beginning with the day on which the counter-notice is served (“the decision period”).
7. If the authority decides to refer the counter-notice to the Upper Tribunal they must do so within
the decision period.
8. If the authority does not serve notice of a decision within the decision period they are to be
treated as if they had served notice of a decision to withdraw the notice to treat at the end of that
period.
9. If the authority serves notice of a decision to accept the counter-notice, the compulsory
purchase order and the notice to treat are to have effect as if they included the owner’s interest in
the house, building or factory.
Determination by the Upper Tribunal
10. On a referral under paragraph 7, the Upper Tribunal must determine whether the acquisition
of the right or the imposition of the restrictive covenant would—
(a) in the case of a house, building or factory; cause material detriment to the house, building
or factory, or
(b) in the case of a park or garden, seriously affect the amenity or convenience of the house
to which the park or garden belongs.
11. In making its determination, the Upper Tribunal must take into account—
(a) the effect of the acquisition of the right or the imposition of the covenant,
(b) the use to be made of the right or covenant proposed to be acquired or imposed, and
(c) if the right or covenant is proposed to be acquired or imposed for works or other purposes
extending to other land, the effect of the whole of the works and the use of the other land.
12. If the Upper Tribunal determines that the acquisition of the right or the imposition of the
covenant would have either of the consequences described in paragraph 10, it must determine how
much of the house, building or factory the authority ought to be required to take.
71Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
13. If the Upper Tribunal determines that the authority ought to be required to take some or all
of the house, building or factory, the compulsory purchase order and the notice to treat are to have
effect as if they included the owner’s interest in that land.
14.—(1) If the Upper Tribunal determines that the authority ought to be required to take some
or all of the house, building or factory, the authority may at any time within the period of six weeks
beginning with the day on which the Upper Tribunal makes its determination withdraw the notice
to treat in relation to that land.
(2) If the acquiring authority withdraws the notice to treat under this paragraph they must pay
the person on whom the notice was served compensation for any loss or expense cause by the giving
and withdrawal of the notice.
(3) Any dispute as to the compensation is to be determined by the Upper Tribunal.”.
SCHEDULE 11 Article 30
LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
(1) (2)
Plot reference number shown on the Land Purpose for which temporary possession may
Plans be taken
7/04 Temporary use to facilitate the construction of
Work No. 6
SCHEDULE 12 Article 41
DOCUMENTS AND PLANS TO BE CERTIFIED
PART 1
DOCUMENTS FORMING THE ENVIRONMENTAL
STATEMENT TO BE CERTIFIED
(1) (2) (3) (4) (5)
Document name Document Revision Date Examination
reference number Library
Reference
Environmental EN010152/APP/6.1 0 31 October 2024 APP-052 to
Statement APP-068
Figures EN010152/APP/6.2 0 31 October 2024 APP-069 to
APP-131
Technical EN010152/APP/6.3 0 31 October 2024 APP-132 to
Appendices APP-187
72Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
PART 2
EXAMINATION DOCUMENTS FORMING PART OF THE
ENVIRONMENTAL STATEMENT TO BE CERTIFIED
(1) (2) (3) (4) (5)
Document name Document Revision Date Examination
reference number Library
Reference
Chapter 6 – EN010152/APP/6.1 1 12 December APP-224
Climate Change 2024
Chapter 7 – EN010152/APP/6.1 1 30 April 2025 REP1-011
Cultural Heritage
Chapter 8 – EN010152/APP/6.1 1 23 July 2025 REP4-010
Ecology and
Nature
Conservation
Chapter 10 – EN010152/APP/6.1 1 28 May 2025 REP2-007
Landscape and
Visual Amenity
Chapter 11 – Noise EN010152/APP/6.1 1 23 July 2025 REP4-012
and Vibration
Chapter 12 – EN010152/APP/6.1 2 30 April 2025 REP1-013
Socio-Economics
and Land Use
Chapter 13 – EN010152/APP/6.1 1 30 April 2025 REP1-015
Transport and
Access
Figure 1-3 EN010152/APP/6.2 1 12 December APP-228
Elements of the 2024
Site
Figure 10-6 EN010152/APP/6.2 1 (labelled 30 April 2025 REP2-009
Screened Zone revision 0)
of Theoretical
Visibility Solar PV
Site
Figure 10-7 EN010152/APP/6.2 1 (labelled 30 April 2025 REP2-010
Screened ZTV On revision 0)
Site Substation and
BESS
Figure 10-8 EN010152/APP/6.2 1 (labelled 30 April 2025 REP2-011
Screened ZTV All revision 0)
Features
Figure 10-9 EN010152/APP/6.2 1 (labelled 8 April 2025 REP2-012
Representative revision 0)
73Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3) (4) (5)
Document name Document Revision Date Examination
reference number Library
Reference
Viewpoint
Locations
Figure 10-10 EN010152/APP/6.2 1 28 May 2025 REP2-013
Viewpoint
Photography
Figure 10-14 Bare EN01152/APP/8.24 0 28 May 2025 REP2-062
Earth ZTV All
Features
Figure 11-1 Noise EN010152/APP/6.2 1 5 December 2024 APP-229
Monitoring and
Receptor Locations
Figure 13-3 EN010152/APP/6.2 1 12 December APP-230
Indicative HGV 2024
Routing
Figure 14-1 Dust EN010152/APP/6.2 1 28 May 2025 REP2-014
Risk Assessment
Appendix 1-3 EIA EN010152/APP/6.3 1 12 December APP-231
Scoping Opinion 2024
Responses
Appendix 7-2 Desk EN010152/APP/6.3 1 30 April 2025 REP1-017
Based Assessment
Appendix 8-3 Bat EN010152/APP/6.3 1 12 December APP-235
Report 2024
Appendix 8-5 EN010152/APP/6.3 1 2 July 2025 REP3-010
Hedgerow Report
Appendix 9-3 EN010152/APP/6.3 1 28 May 2025 REP2-015
Flood Risk
Assessment
Appendix 10-2 EN010152/APP/6.3 1 28 May 2025 REP2-019
Landscape and
Visual Impact
Assessment
Methodology
Appendix 10-5 EN010152/APP/6.3 2 28 May 2025 REP2-021
Landscape
Assessment Tables
Appendix 10-7 EN010152/APP/6.3 1 12 December APP-236
Arboricultural 2024
Impact Assessment
(Part 1 of 2)
74Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3) (4) (5)
Document name Document Revision Date Examination
reference number Library
Reference
Appendix 10-7 EN010152/APP/6.3 1 12 December APP-240
Arboricultural 2024
Impact Assessment
(Part 2 of 2)
Appendix 13-2 EN010152/APP/6.3 1 23 July 2025 REP4-014
Traffic Flow
Diagrams
Appendix 14-2 EN010152/APP/6.3 2 28 May 2025 REP2-023
Glint and Glare
Assessment (Part 1
of 2)
Appendix 14-2 EN010152/APP/6.3 2 28 May 2025 REP2-025
Glint and Glare
Assessment (Part 2
of 2)
PART 3
OTHER DOCUMENTS TO BE CERTIFIED
(1) (2) (3) (4) (5)
Document name Document reference Revision Date Examination
number Library
Reference
Land Plan EN010152/APP/2.1 0 31 October 2024 APP-006
Works Plan EN010152/APP/2.2 1 12 December APP-214
2024
Streets, Rights of EN010152/APP/2.3 4 2 July 2025 REP3-004 and
Way and Access REP3-005
Plan
Traffic Regulation EN010152/APP/2.4 0 31 October 2024 APP-009
Measures Plan
Book of Reference EN010152/APP/4.3 2 30 April 2025 REP1-009
Outline Design EN010152/APP/7.4 1 28 May 2025 REP2-027
Parameters
Statement
Framework EN010152/APP/7.7 3 2 July 2025 REP3-013
Construction
Environmental
Management Plan
75Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) (2) (3) (4) (5)
Document name Document reference Revision Date Examination
number Library
Reference
Framework EN010152/APP/7.8 3 21 August 2025 REP5-007
Operational
Environmental
Management Plan
Framework EN010152/APP/7.9 3 23 July 2025 REP4-019
Decommissioning
Environmental
Management Plan
Framework Soil EN010152/APP/7.10 2 23 July 2025 REP4-021
Management Plan
Framework Public EN010152/APP/7.13 4 21 August 2025 REP5-009
Rights of Way
Management Plan
Framework EN010152/APP/7.14 3 2 July 2025 REP3-017
Landscape and
Ecological
Management Plan
Framework skills, EN010152/APP/7.15 0 31 October 2024 APP-204
supply chain and
employment plan
Framework Battery EN010152/APP/7.16 0 31 October 2024 APP-205
Safety
Management Plan
Framework EN010152/APP/7.17 2 23 July 2025 REP4-027
Construction
Traffic
Management Plan
Framework Site EN010152/APP/7.18 0 31 October 2024 APP-208
Waste
Management Plan
Framework EN010152/APP/8.16 1 28 May 2025 REP2-054
Archaeological
Mitigation Strategy
76Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
SCHEDULE 13 Article 43
ARBITRATION RULES
Commencing an arbitration
1. The arbitration is deemed to have commenced when a party (“the claimant”) serves a written
notice of arbitration on the other party (“the respondent”).
Time periods
2.—(1) All time periods in these arbitration rules are measured in days and include weekends,
but not bank or public holidays.
(2) Time periods are calculated from the day after the arbitrator is appointed which is either—
(a) the date the arbitrator notifies the parties in writing of his/her acceptance of an appointment
by agreement of the parties; or
(b) the date the arbitrator is appointed by the Secretary of State.
Timetable
3.—(1) The timetable for the arbitration is that which is set out in sub-paragraphs (2) to (4) below
unless amended in accordance with paragraph 5(3).
(2) Within 14 days of the arbitrator being appointed, the claimant must provide both the
respondent and the arbitrator with—
(a) a written statement of claim which describes the nature of the difference between the
parties, the legal and factual issues, the claimant’s contentions as to those issues, the
amount of its claim or the remedy it is seeking;
(b) all statements of evidence and copies of all documents on which it relies, including
contractual documentation, correspondence (including electronic documents), legal
precedents and expert witness reports.
(3) Within 14 days of receipt of the claimant’s statements under sub-paragraph (2) by the
arbitrator and respondent, the respondent must provide the claimant and the arbitrator with—
(a) a written statement of defence consisting of a response to the claimant’s statement of claim,
its statement in respect of the nature of the difference, the legal and factual issues in the
claimant’s claim, its acceptance of any elements of the claimant’s claim and its contentions
as to those elements of the claimant’s claim it does not accept;
(b) all statements of evidence and copies of all documents on which it relies, including
contractual documentation, correspondence (including electronic documents), legal
precedents and expert witness reports;
(c) any objection it wishes to make to the claimant’s statements, comments on the claimant’s
expert reports (if submitted by the claimant) and explanations of the objections.
(4) Within seven days of the respondent serving its statements under sub-paragraph (3) the
claimant may make a statement of reply by providing both the respondent and the arbitrator with—
(a) a written statement responding to the respondent’s submissions, including its reply in
respect of the nature of the difference, the issues (both factual and legal) and its contentions
in relation to the issues;
(b) all statements of evidence and copies of documents in response to the respondent’s
submissions;
(c) any expert report in response to the respondent’s submissions;
77Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(d) any objections to the statements of evidence, expert reports or other documents submitted
by the respondent; and
(e) its written submissions in response to the legal and factual issues involved.
Procedure
4.—(1) The parties’ pleadings, witness statements and expert reports (if any) must be concise. A
single pleading must not exceed 30 single-sided A4 pages using 10pt Arial font.
(2) The arbitrator will make an award on the substantive differences based solely on the written
material submitted by the parties unless the arbitrator decides that a hearing is necessary to explain
or resolve any matters.
(3) Either party may, within two days of delivery of the last submission, request a hearing giving
specific reasons why it considers a hearing is required.
(4) Within seven days of receiving the last submission, the arbitrator must notify the parties
whether a hearing is to be held and the length of that hearing.
(5) Within 10 days of the arbitrator advising the parties that a hearing is to be held, the date and
venue for the hearing are to be fixed by agreement with the parties, save that if there is no agreement
the arbitrator must direct a date and venue which the arbitrator considers is fair and reasonable in
all the circumstances. The date for the hearing must not be less than 35 days from the date of the
arbitrator’s direction confirming the date and venue of the hearing.
(6) A decision must be made by the arbitrator on whether there is any need for expert evidence
to be submitted orally at the hearing. If oral expert evidence is required by the arbitrator, then any
experts attending the hearing may be asked questions by the arbitrator.
(7) There is to be no examination or cross examination of experts, but the arbitrator must invite
the parties to ask questions of the experts by way of clarification of any answers given by the experts
in response to the arbitrator’s questions. Prior to the hearing in relation to the experts—
(a) at least 28 days before a hearing, the arbitrator must provide a list of issues to be addressed
by the experts;
(b) if more than one expert is called, they will jointly confer and produce a joint report or
reports within 14 days of the issues being provided; and
(c) the form and content of a joint report must be as directed by the arbitrator and must be
provided at least seven days before the hearing.
(8) Within 14 days of a hearing or a decision by the arbitrator that no hearing is to be held the
parties may by way of exchange provide the arbitrator with a final submission in connection with
the matters in dispute and any submissions on costs. The arbitrator must take these submissions into
account in the award.
(9) The arbitrator may make other directions or rulings as considered appropriate in order
to ensure that the parties comply with the timetable and procedures to achieve an award on the
substantive difference within four months of the date on which the arbitrator is appointed, unless
both parties otherwise agree to an extension to the date for the award.
(10) If a party fails to comply with the timetable, procedure or any other direction then the
arbitrator may continue in the absence of a party or submission or document, and may make a
decision on the information before the arbitrator attaching the appropriate weight to any evidence
submitted beyond any timetable or in breach of any procedure or direction.
(11) The arbitrator’s award must include reasons. The parties must accept that the extent to which
reasons are given must be proportionate to the issues in dispute and the time available to the arbitrator
to deliver the award.
78Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Arbitrator’s powers
5.—(1) The arbitrator has all the powers of the Arbitration Act 1996, save where modified in
this Schedule.
(2) There must be no discovery or disclosure, except that the arbitrator is to have the power
to order the parties to produce such documents as are reasonably requested by another party no
later than the statement of reply, or by the arbitrator, where the documents are manifestly relevant,
specifically identified and the burden of production is not excessive. Any application and orders
should be made by way of a Redfern Schedule without any hearing.
(3) Any time limits fixed in accordance with this procedure or by the arbitrator may be varied by
agreement between the parties, subject to any such variation being acceptable to and approved by
the arbitrator. In the absence of agreement, the arbitrator may vary the timescales or procedure—
(a) if the arbitrator is satisfied that a variation of any fixed time limit is reasonably necessary
to avoid a breach of the rules of natural justice and then;
(b) only for such a period that is necessary to achieve fairness between the parties.
(4) On the date the award is made, the arbitrator will notify the parties that the award is completed,
signed and dated, and that it will be issued to the parties on receipt of cleared funds for the arbitrator’s
fees and expenses.
Costs
6.—(1) The costs of the arbitration must include the fees and expenses of the arbitrator, the
reasonable fees and expenses of any experts and the reasonable legal and other costs incurred by
the parties for the arbitration.
(2) Where the difference involves connected or interrelated issues, the arbitrator must consider
the relevant costs collectively.
(3) The final award must fix the costs of the arbitration and decide which of the parties are to
bear them or in what proportion they are to be borne by the parties.
(4) The arbitrator must award recoverable costs on the general principle that each party should
bear its own costs, having regard to all material circumstances, including such matters as exaggerated
claims or defences, the degree of success for different elements of the claims, claims that have
incurred substantial costs, the conduct of the parties and the degree of success of a party.
Confidentiality
7.—(1) Subject to sub-paragraphs (2) and (3), any arbitration hearing and documentation will
be open to and accessible by the public.
(2) The arbitrator may direct that the whole or part of a hearing is to be private or any
documentation to be confidential where it is necessary in order to protect commercially sensitive
information.
(3) Nothing in this paragraph will prevent any disclosure of a document by a party pursuant to
an order of a court in England and Wales or where disclosure is required under any enactment.
79Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
SCHEDULE 14 Article 44
PROTECTIVE PROVISIONS
PART 1
FOR THE PROTECTION OF ELECTRICITY,
GAS, WATER AND SEWERAGE UNDERTAKERS
1. For the protection of the utility undertakers referred to in this Part of this Schedule (save for
any utility undertakers which are specifically protected by any other Part of this Schedule, which will
take precedence), the following provisions have effect, unless otherwise agreed in writing between
the undertaker and the utility undertakers concerned.
2. In this Part of this Schedule—
“alternative apparatus” means alternative apparatus adequate to enable the utility undertaker
in question to fulfil its statutory functions in a manner not less efficient than previously;
“apparatus” means—
(a) in the case of an electricity undertaker, electric lines or electrical plant (as defined in the
Electricity Act 1989(74)), belonging to or maintained by that utility undertaker;
(b) in the case of a gas undertaker, any mains, pipes or other apparatus belonging to or
maintained by a gas transporter for the purposes of gas supply;
(c) in the case of a water undertaker—
(i) mains, pipes or other apparatus belonging to or maintained by that utility undertaker
for the purposes of water supply; and
(ii) any water mains or service pipes (or part of a water main or service pipe) that is
the subject of an agreement to adopt made under section 51A of the Water Industry
Act 1991;
(d) in the case of a sewerage undertaker—
(i) any drain or works vested in the utility undertaker under the Water Industry Act
1991(75); and
(ii) any sewer which is so vested or is the subject of a notice of intention to adopt given
under section 102(4) of that Act or an agreement to adopt made under section 104
of that Act,
and includes a sludge main, disposal main (within the meaning of section 219 of that Act) or
sewer outfall and any manholes, ventilating shafts, pumps or other accessories forming part
of any such sewer, drain or works, and includes any structure in which apparatus is or is to be
lodged or which gives or will give access to apparatus; and
(e) any other mains, pipelines or cables that are not the subject of the protective provisions
in Parts 2 to 6 of this Schedule;
“functions” includes powers and duties;
“in”, in a context referring to apparatus or alternative apparatus in land, includes a reference
to apparatus or alternative apparatus under, over or upon land; and
“utility undertaker” means—
(74) 1989 c. 29.
(75) 1991 c. 56.
80Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(a) any licence holder within the meaning of Part 1 of the Electricity Act 1989;
(b) a gas transporter within the meaning of Part 1 of the Gas Act 1986(76);
(c) water undertaker within the meaning of the Water Industry Act 1991;
(d) a sewerage undertaker within the meaning of Part 1 of the Water Industry Act 1991; and
(e) an owner or operator of apparatus within paragraph (e) of the definition of that term,
for the area of the authorised development, and in relation to any apparatus, means the utility
undertaker to whom it belongs or by whom it is maintained.
3. This Part of this Schedule does not apply to apparatus in respect of which the relations between
the undertaker and the utility undertaker are regulated by the provisions of Part 3 of the 1991 Act.
4. Regardless of the temporary prohibition or restriction of use of streets under the powers
conferred by article 12 (temporary closure of streets and public rights of way), a utility undertaker
is at liberty at all times to take all necessary access across any such street and to execute and do all
such works and things in, upon or under any such street as may be reasonably necessary or desirable
to enable it to maintain any apparatus which at the time of the prohibition or restriction was in that
street.
5. Regardless of any provision in this Order or anything shown on the land plans, the undertaker
must not acquire any apparatus otherwise than by agreement.
6.—(1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any
interest in any land in which any apparatus is placed or over which access to any apparatus is enjoyed
or requires that the utility undertaker’s apparatus is relocated or diverted, that apparatus must not
be removed under this Part of this Schedule, and any right of a utility undertaker to maintain that
apparatus in that land and to gain access to it must not be extinguished, until alternative apparatus has
been constructed and is in operation, and access to it has been provided, to the reasonable satisfaction
of the utility undertaker in question in accordance with sub-paragraphs (2) to (7).
(2) If, for the purpose of executing any works in, on or under any land purchased, held,
appropriated or used under this Order, the undertaker requires the removal of any apparatus placed
in that land, the undertaker must give to the utility undertaker in question written notice of that
requirement, together with a plan and section of the work proposed, and of the proposed position
of the alternative apparatus to be provided or constructed and in that case (or if in consequence of
the exercise of any of the powers conferred by this Order a utility undertaker reasonably needs to
remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), afford to the utility
undertaker the necessary facilities and rights for the construction of alternative apparatus in other
land of the undertaker and subsequently for the maintenance of that apparatus.
(3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than
in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as
are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such
apparatus is to be constructed, the utility undertaker in question must, on receipt of a written notice to
that effect from the undertaker, as soon as reasonably possible use reasonable endeavours to obtain
the necessary facilities and rights in the land in which the alternative apparatus is to be constructed.
(4) Any alternative apparatus to be constructed in land of the undertaker under this Part of this
Schedule must be constructed in such manner and in such line or situation as may be agreed between
the utility undertaker in question and the undertaker or in default of agreement settled by arbitration
in accordance with article 43 (arbitration).
(76) 1986 c. 44. A new section 7 was substituted by section 5 of the Gas Act 1995 (c. 45) and was further amended by section 76
of the Utilities Act 2000 (c. 27).
81Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(5) The utility undertaker in question must, after the alternative apparatus to be provided or
constructed has been agreed or settled by arbitration in accordance with article 43, and after the grant
to the utility undertaker of any such facilities and rights as are referred to in sub-paragraph (2) or (3),
proceed without unnecessary delay to construct and bring into operation the alternative apparatus and
subsequently to remove any apparatus required by the undertaker to be removed under the provisions
of this Part of this Schedule.
(6) Regardless of anything in sub-paragraph (5), if the undertaker gives notice in writing to
the utility undertaker in question that it desires itself to execute any work, or part of any work, in
connection with the construction or removal of apparatus in any land controlled by the undertaker,
that work, instead of being executed by the utility undertaker, must be executed by the undertaker
without unnecessary delay under the superintendence, if given, and to the reasonable satisfaction
of the utility undertaker.
(7) Nothing in sub-paragraph (6) authorises the undertaker to execute the placing, installation,
bedding, packing, removal, connection or disconnection of any apparatus, or execute any filling
around the apparatus (where the apparatus is laid in a trench) within 300 millimetres of the apparatus.
7.—(1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker
affords to a utility undertaker facilities and rights for the construction and maintenance in land of
the undertaker of alternative apparatus in substitution for apparatus to be removed, those facilities
and rights must be granted upon such terms and conditions as may be agreed between the undertaker
and the utility undertaker in question or in default of agreement settled by arbitration in accordance
with article 43 (arbitration).
(2) If the facilities and rights to be afforded by the undertaker in respect of any alternative
apparatus, and the terms and conditions subject to which those facilities and rights are to be granted,
are in the opinion of the arbitrator less favourable on the whole to the utility undertaker in question
than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and
conditions to which those facilities and rights are subject, the arbitrator must make such provision for
the payment of compensation by the undertaker to that utility undertaker as appears to the arbitrator
to be reasonable having regard to all the circumstances of the particular case.
8.—(1) Not less than 28 days before starting the execution of any works in, on or under any land
purchased, held, appropriated or used under this Order that are near to, or will or may affect, any
apparatus the removal of which has not been required by the undertaker under paragraph 6(2), the
undertaker must submit to the utility undertaker in question a plan, section and description of the
works to be executed.
(2) Those works must be executed only in accordance with the plan, section and description
submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be
made in accordance with sub-paragraph (3) by the utility undertaker for the alteration or otherwise
for the protection of the apparatus, or for securing access to it, and the utility undertaker is entitled
to watch and inspect the execution of those works.
(3) Any requirements made by a utility undertaker under sub-paragraph (2) must be made within
a period of 21 days beginning with the date on which a plan, section and description under sub-
paragraph (1) are submitted to it.
(4) If a utility undertaker in accordance with sub-paragraph (3) and in consequence of the works
proposed by the undertaker, reasonably requires the removal of any apparatus and gives written
notice to the undertaker of that requirement, paragraphs 1 to 7 apply as if the removal of the apparatus
had been required by the undertaker under paragraph 6(2).
(5) Nothing in this paragraph precludes the undertaker from submitting at any time or from time
to time, but in no case less than 28 days before commencing the execution of any works, a new
plan, section and description instead of the plan, section and description previously submitted, and
82Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
having done so the provisions of this paragraph apply to and in respect of the new plan, section and
description.
(6) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in
that case it must give to the utility undertaker in question notice as soon as is reasonably practicable
and a plan, section and description of those works as soon as reasonably practicable subsequently
and must comply with sub-paragraph (2) in so far as is reasonably practicable in the circumstances.
9.—(1) Subject to the following provisions of this paragraph, the undertaker must repay to a
utility undertaker the reasonable expenses incurred by that utility undertaker in, or in connection
with, the inspection, removal, alteration or protection of any apparatus or the construction of any
new apparatus which may be required in consequence of the execution of any such works as are
referred to in paragraph 6(2).
(2) There is to be deducted from any sum payable under sub-paragraph (1) the value of any
apparatus removed under the provisions of this Part of this Schedule, that value being calculated
after removal.
(3) If in accordance with the provisions of this Part of this Schedule—
(a) apparatus of better type, of greater capacity or of greater dimensions is placed in
substitution for existing apparatus of worse type, of smaller capacity or of smaller
dimensions; or
(b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is
placed at a depth greater than the depth at which the existing apparatus was,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus
at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not
determined by arbitration in accordance with article 43 (arbitration) to be necessary, then, if such
placing involves cost in the construction of works under this Part of this Schedule exceeding that
which would have been involved if the apparatus placed had been of the existing type, capacity or
dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-
paragraph would be payable to the utility undertaker in question by virtue of sub-paragraph (1) is
to be reduced by the amount of that excess.
(4) For the purposes of sub-paragraph (3)—
(a) an extension of apparatus to a length greater than the length of existing apparatus is not
to be treated as a placing of apparatus of greater dimensions than those of the existing
apparatus where such extension is required in consequence of the execution of any such
works as are referred to in paragraph 6(2); and
(b) where the provision of a joint in a cable is agreed, or is determined to be necessary, the
consequential provision of a jointing chamber or of a manhole is to be treated as if it also
had been agreed or had been so determined.
(5) An amount which apart from this sub-paragraph would be payable to a utility undertaker
in respect of works by virtue of sub-paragraph (1), if the works include the placing of apparatus
provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer
on the utility undertaker any financial benefit by deferment of the time for renewal of the apparatus
in the ordinary course is to be reduced by the amount which represents that benefit.
10.—(1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction
of any of the works referred to in paragraph 6(2), any damage is caused to any apparatus (other
than apparatus the repair of which is not reasonably necessary in view of its intended removal for
the purposes of those works) or property of a utility undertaker, or there is any interruption in any
service provided, or in the supply of any goods, by any utility undertaker, the undertaker must—
83Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(a) bear and pay the cost reasonably incurred by that utility undertaker in making good such
damage or restoring the supply; and
(b) make reasonable compensation to that utility undertaker for any other expenses, loss,
damages, penalty or costs incurred by the utility undertaker,
by reason or in consequence of any such damage or interruption.
(2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any
damage or interruption to the extent that it is attributable to the act, neglect or default of a utility
undertaker, its officers, servants, contractors or agents.
(3) A utility undertaker must give the undertaker reasonable notice of any such claim or demand
and no settlement or compromise is to be made without the consent of the undertaker which, if it
withholds such consent, has the sole conduct of any settlement or compromise or of any proceedings
necessary to resist the claim or demand.
11. Nothing in this Part of this Schedule affects the provisions of any enactment or agreement
regulating the relations between the undertaker and a utility undertaking in respect of any apparatus
laid or erected in land belonging to the undertaker on the date on which this Order is made.
PART 2
FOR THE PROTECTION OF OPERATORS OF
ELECTRONIC COMMUNICATIONS CODE NETWORKS
12. For the protection of any operator, the following provisions have effect, unless otherwise
agreed in writing between the undertaker and the operator.
13. In this Part of this Schedule—
“the 2003 Act” means the Communications Act 2003(77);
“electronic communications apparatus” has the same meaning as in the electronic
communications code;
“the electronic communications code” has the same meaning as in section 106 (application of
the electronic communications code) of the 2003 Act;
“electronic communications code network” means—
(a) so much of an electronic communications network or conduit system provided by an
electronic communications code operator as is not excluded from the application of the
electronic communications code by a direction under section 106 of the 2003 Act; and
(b) an electronic communications network which the Secretary of State is providing or
proposing to provide;
“electronic communications code operator” means a person in whose case the electronic
communications code is applied by a direction under section 106 of the 2003 Act; and
“operator” means the operator of an electronic communications code network.
14. The exercise of the powers of article 32 (statutory undertakers) is subject to Part
10 (undertakers’ works affecting electronic communications apparatus) of the electronic
communications code.
15.—(1) Subject to sub-paragraphs (2) to (4), if as the result of the authorised development or
its construction, or of any subsidence resulting from any of those works—
(77) 2003 c. 21.
84Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(a) any damage is caused to any electronic communications apparatus belonging to an
operator (other than apparatus the repair of which is not reasonably necessary in view of
its intended removal for the purposes of those works), or other property of an operator; or
(b) there is any interruption in the supply of the service provided by an operator,
the undertaker must bear and pay the cost reasonably incurred by the operator in making good such
damage or restoring the supply and make reasonable compensation to that operator for any other
expenses, loss, damages, penalty or costs incurred by it, by reason, or in consequence of, any such
damage or interruption.
(2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any
damage or interruption to the extent that it is attributable to the act, neglect or default of an operator,
its officers, servants, contractors or agents.
(3) The operator must give the undertaker reasonable notice of any such claim or demand and no
settlement or compromise of the claim or demand is to be made without the consent of the undertaker
which, if it withholds such consent, has the sole conduct of any settlement or compromise or of any
proceedings necessary to resist the claim or demand.
(4) Any difference arising between the undertaker and the operator under this Part of this Schedule
must be referred to and settled by arbitration under article 43 (arbitration).
16. This Part of this Schedule does not apply to—
(a) any apparatus in respect of which the relations between the undertaker and an operator
are regulated by the provisions of Part 3 (street works in England and Wales) of the 1991
Act; or
(b) any damage, or any interruption, caused by electro-magnetic interference arising from the
construction or use of the authorised development.
17. Nothing in this Part of this Schedule affects the provisions of any enactment or agreement
regulating the relations between the undertaker and an operator in respect of any apparatus laid or
erected in land belonging to the undertaker on the date on which this Order is made.
PART 3
FOR THE PROTECTION OF DRAINAGE AUTHORITIES
18. The provisions of this Part of this Schedule have effect for the protection of the drainage
authority unless otherwise agreed in writing between the undertaker and the drainage authority.
19. In this Part of this Schedule—
“authorised development” has the same meaning as in article 2(1) (interpretation) of this Order
and (unless otherwise specified) for the purposes of this Part of this Schedule includes the
operation and maintenance of the authorised development and the construction of any works
authorised by this Part of this Schedule;
“construction” includes execution, placing, altering, replacing, relaying and removal, and
“construct” and “constructed” must be construed accordingly;
“drainage authority” means in relation to an ordinary watercourse—
(a) the drainage board concerned within the meaning of section 23 (prohibition on
obstructions etc. in watercourses) of the Land Drainage Act 1991; or
(b) in the case of any area for which there is no such drainage board, the lead local flood
authority within the meaning of section 6 (other definitions) of the Flood and Water
Management Act 2010;
85Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
“drainage work” means any ordinary watercourse and includes any bank, wall, embankment
or other structure, or any appliance constructed for land drainage or flood defence which is the
responsibility of the drainage authority;
“ordinary watercourse” has the meaning given by section 72 (interpretation) of the Land
Drainage Act 1991;
“plans” includes sections, drawings, specifications and method statements; and
“specified work” means so much of the authorised development as is in, on, under, over or
within 9 metres of a drainage work or is otherwise likely to affect the flow of water in any
watercourse.
20.—(1) Before commencing construction of a specified work, the undertaker must submit to
the drainage authority plans of the specified work and such further particulars available to it as the
drainage authority may reasonably require within 28 days of the submission of the plans.
(2) A specified work must not be constructed except in accordance with such plans as may be
approved in writing by the drainage authority or determined under paragraph 28.
(3) Any approval of the drainage authority required under this paragraph—
(a) must not be unreasonably withheld or delayed;
(b) is deemed to have been given if it is neither given nor refused within 56 days of the
submission of the plans for approval, or submission of further particulars (where required
by the drainage authority under sub-paragraph (1)) whichever is the later; and
(c) may be given subject to such reasonable requirements as the drainage authority may make
for the protection of any drainage work or for the prevention of flooding or pollution or
discharge of its environmental function.
(4) Any refusal under this paragraph must be accompanied by a statement of the reasons for
refusal.
21. Without limiting the scope of paragraph 20, the requirements which the drainage authority
may make under that paragraph include conditions requiring the undertaker at its own expense to
construct such protective works, whether temporary or permanent, during the construction of the
specified work (including the provision of flood banks, walls or embankments or other new works
and the strengthening, repair or renewal of existing banks, walls or embankments) as are reasonably
necessary taking account of the terms of this Order—
(a) to safeguard any drainage work against damage by reason of any specified work; or
(b) to secure that the efficiency of any drainage work for flood defence and land drainage
purposes is not impaired, and that the risk of flooding is not otherwise increased beyond
the level of flood risk that was assessed in the environmental statement, by reason of any
specified work.
22.—(1) Subject to sub-paragraph (2), any specified work, and all protective works required by
the drainage authority under paragraph 21, must be constructed—
(a) without unreasonable delay in accordance with the plans approved or deemed to have been
approved or settled under this Part of this Schedule; and
(b) to the reasonable satisfaction of the drainage authority,
and an officer of the drainage authority is entitled to watch and inspect the construction of such
works.
(2) The undertaker must give to the drainage authority—
(a) not less than 14 days’ notice in writing of its intention to commence construction of any
specified work; and
86Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(b) notice in writing of its completion not later than 7 days after the date on which it is brought
into use.
(3) If the drainage authority reasonably requires, the undertaker must construct all or part of the
protective works so that they are in place prior to the construction of the specified work to which
the protective works relate.
(4) If any part of a specified work or any protective work required by the drainage authority is
constructed other than in accordance with the requirements of this Part of this Schedule, the drainage
authority may by notice in writing require the undertaker at the undertaker’s expense to comply with
the requirements of this Part of this Schedule or (if the undertaker so elects and the drainage authority
in writing consents, such consent not to be unreasonably withheld or delayed) to remove, alter or
pull down the work and, where removal is required, to restore the site to its former condition to the
reasonable satisfaction of the drainage authority.
(5) Subject to sub-paragraph (6) and paragraph 27 if, within a reasonable period, being not
less than 56 days beginning with the date when a notice under sub-paragraph (4) is served on the
undertaker, the undertaker has failed to begin taking steps to comply with the requirements of the
notice and has not subsequently made reasonably expeditious progress towards their implementation,
the drainage authority may execute the works specified in the notice and any expenditure reasonably
incurred by the drainage authority in so doing is recoverable from the undertaker.
(6) In the event of any dispute as to whether sub-paragraph (4) is properly applicable to any work
in respect of which notice has been served under that sub-paragraph, or as to the reasonableness of
any requirement of such a notice, the drainage authority must not except in the case of an emergency
exercise the powers conferred by sub-paragraph (5) until the dispute has been finally determined in
accordance with paragraph 28.
23.—(1) Subject to sub-paragraph (5), the undertaker must from the commencement of the
construction of the specified work as constructed in accordance with paragraph 22 and protective
work as constructed in accordance with paragraph 10, maintain in good repair and condition and free
from obstruction any drainage work which is situated within the Order Limits on land held by the
undertaker for the purposes of or in connection with the specified work, whether or not the drainage
work is constructed under the powers conferred by this Order or is already in existence.
(2) If any such specified work or protective work which the undertaker is liable to maintain is
not maintained to the reasonable satisfaction of the drainage authority, the drainage authority may
by notice in writing require the undertaker to repair and restore the work, or any part of such work,
or (if the undertaker so elects and the drainage authority in writing consents, such consent not to
be unreasonably withheld or delayed), to remove the specified work and any protective work and
restore the site to its former condition, to such extent and within such limits as the drainage authority
reasonably requires.
(3) Subject to sub-paragraph (4), if, within a reasonable period, being not less than 28 days
beginning with the date on which a notice in respect of any specified work or protective work is
served under sub-paragraph (2) on the undertaker, the undertaker has failed to begin taking steps to
comply with the reasonable requirements of the notice and has not subsequently made reasonably
expeditious progress towards their implementation, the drainage authority may do what is reasonably
necessary for such compliance and any reasonable expenditure incurred by the drainage authority
in so doing is recoverable from the undertaker.
(4) In the event of any dispute as to the reasonableness of any requirement of a notice served under
sub-paragraph (2), the drainage authority must not, except in the case of an emergency, exercise the
powers conferred by sub-paragraph (3) until the dispute has been finally determined in accordance
with paragraph 28.
(5) This paragraph does not apply to—
87Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(a) drainage works that are vested in the drainage authority or that the drainage authority or
another person is liable to maintain and is not prevented by this Order from so doing; and
(b) any obstruction of a drainage work for the purpose of a work or operation authorised by
this Order and carried out in accordance with the provisions of this Part.
24. If by reason of the construction of a specified work or of the failure of any specified work
the efficiency of any drainage work for flood defence purposes or land drainage is impaired, or
that drainage work is otherwise damaged, the impairment or damage must be made good by the
undertaker as soon as reasonably practicable to the reasonable satisfaction of the drainage authority
and, if the undertaker fails to do so, the drainage authority may make good the impairment or damage
and recover from the undertaker the expense reasonably incurred by it in doing so.
25. If by reason of the construction of the specified work the drainage authority’s access to
land drainage infrastructure, flood defences or equipment maintained for flood defence purposes
is materially obstructed, the undertaker must provide such alternative means of access that will
allow the drainage authority to maintain the land drainage infrastructure, flood defence or use the
equipment no less effectively than was possible before the obstruction within 24 hours of or as soon
as reasonably practicable after the undertaker becoming aware of such obstruction.
26. The undertaker must make reasonable compensation for costs, charges and expenses which
the drainage authority may reasonably incur—
(a) in the examination or approval of plans under this Part of this Schedule;
(b) in inspecting the construction of the specified work or any protective works required by
the drainage authority under this Part of this Schedule; and
(c) in carrying out any surveys or tests by the drainage authority which are reasonably required
in connection with the construction of the specified work or protective work.
27.—(1) The undertaker must make reasonable compensation for liabilities, costs and losses
which may be reasonably incurred or suffered by reason of—
(a) the construction of any specified works or protective works comprised within the
authorised development; or
(b) any act or omission of the undertaker, its employees, contractors or agents or others while
engaged upon the construction of the authorised development.
(2) The drainage authority must give to the undertaker reasonable notice of any such claim or
demand.
(3) The undertaker may at its own expense conduct all negotiations for the settlement of the same
and any litigation that may arise therefrom.
(4) The drainage authority must not compromise or settle any such claim or make any admission
which might be prejudicial to the claim without the agreement of the undertaker which agreement
must not be unreasonably withheld or delayed.
(5) The drainage authority will, having regard to its statutory functions, at all times take
reasonable steps to prevent and mitigate any such claims, demands, proceedings, costs, damages,
expenses or loss.
(6) The drainage authority will, at the request of the undertaker and having regard to its statutory
functions, afford all reasonable assistance for the purpose of contesting any such claim or action,
and is entitled to be repaid its reasonable expenses reasonably incurred in so doing.
(7) The fact that any work or thing has been executed or done by the undertaker in accordance
with a plan approved or deemed to be approved by the drainage authority, or to its satisfaction, or in
accordance with any directions or award of an arbitrator, does not relieve the undertaker from any
liability under this Part of this Schedule.
88Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(8) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any
damage to the extent that it is attributable to the act, neglect or default of the drainage authority or
the breach of a statutory duty of the drainage authority, its officers, servants, contractors or agents.
28. Any dispute arising between the undertaker and the drainage authority under this Part of this
Schedule, if the parties agree, is to be determined by arbitration under article 43 (arbitration).
PART 4
FOR THE PROTECTION OF RAILWAY INTERESTS
29. The provisions of this Part of this Schedule have effect, unless otherwise agreed in writing
between the undertaker and Network Rail and, in the case of paragraph 43 of this Part of this
Schedule, any other person on whom rights or obligations are conferred by that paragraph.
30. In this Part of this Schedule—
“asset protection agreement” means an agreement to regulate the construction and maintenance
of the specified work in a form prescribed from time to time by Network Rail;
“construction” includes execution, placing, alteration and reconstruction and “construct” and
“constructed” have corresponding meanings;
“the engineer” means an engineer appointed by Network Rail for the purposes of this Order;
“network licence” means the network licence, as the same is amended from time to time,
granted to Network Rail Infrastructure Limited by the Secretary of State in exercise of their
powers under section 8 (licences) of the Railways Act 1993;
“Network Rail” means Network Rail Infrastructure Limited (company number 02904587,
whose registered office is at Waterloo General Office, London SE1 8SW) and any associated
company of Network Rail Infrastructure Limited which holds property for railway purposes,
and for the purpose of this definition “associated company” means any company which is
(within the meaning of section 1159 of the Companies Act 2006 the holding company of
Network Rail Infrastructure Limited, a subsidiary of Network Rail Infrastructure Limited or
another subsidiary of the holding company of Network Rail Infrastructure Limited and any
successor to Network Rail Infrastructure Limited’s railway undertaking;
“plans” includes sections, designs, design data, software, drawings, specifications, soil
reports, calculations, descriptions (including descriptions of methods of construction), staging
proposals, programmes and details of the extent, timing and duration of any proposed
occupation of railway property;
“railway operational procedures” means procedures specified under any access agreement (as
defined in the Railways Act 1993) or station lease;
“railway property” means any railway belonging to Network Rail and—
(a) any station, land, works, apparatus and equipment belonging to Network Rail or
connected with any such railway; and
(b) any easement or other property interest held or used by Network Rail or a tenant
or licensee of Network Rail for the purposes of such railway or works, apparatus or
equipment;
“regulatory consents” means any consent or approval required under—
(a) the Railways Act 1993;
(b) the network licence; and/or
(c) any other relevant statutory or regulatory provisions,
89Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
by either the Office of Rail and Road or the Secretary of State for Transport or any other
competent body including change procedures and any other consents, approvals of any access
or beneficiary that may be required in relation to the authorised development;
“specified work” means so much of any of the authorised development as is situated upon,
across, under, over or within 15 metres of, or may in any way adversely affect, railway property
and, for the avoidance of doubt, includes the maintenance of such works under the powers
conferred by article 5 (power to maintain the authorised development) in respect of such works.
31.—(1) Where under this Part of this Schedule Network Rail is required to give its consent
or approval in respect of any matter, that consent or approval is subject to the condition that
Network Rail complies with any relevant railway operational procedures and any obligations under
its network licence or under statute.
(2) In so far as any specified work or the acquisition or use of railway property is or may be
subject to railway operational procedures, Network Rail must—
(a) co-operate with the undertaker with a view to avoiding undue delay and securing
conformity as between any plans approved by the engineer and requirements emanating
from those procedures; and
(b) use their reasonable endeavours to avoid any conflict arising between the application of
those procedures and the proper implementation of the authorised development pursuant
to this Order.
32.—(1) The undertaker must not exercise the powers conferred by—
(a) article 3 (development consent etc granted by this Order);
(b) article 5 (power to maintain the authorised development);
(c) article 18 (discharge of water);
(d) article 20 (authority to survey and investigate the land);
(e) article 21 (compulsory acquisition of land);
(f) article 23 (compulsory acquisition of rights);
(g) article 24 (private rights);
(h) article 26 (acquisition of subsoil only);
(i) article 27 (power to override easements and other rights);
(j) article 30 (temporary use of land for constructing the authorised development);
(k) article 31 (temporary use of land for maintaining the authorised development);
(l) article 32 (statutory undertakers);
(m) article 39 (felling or lopping of trees and removal of hedgerows);
(n) article 40 (trees subject to tree preservation orders);
(o) section 11(3) (power of entry) of the Compulsory Purchase Act 1965;
(p) section 203 (power to override easements and rights) of the Housing and Planning Act
2016;
(q) section 172 (right to enter and survey land) of the Housing and Planning Act 2016;
(r) any powers in respect of the temporary possession of land under the Neighbourhood
Planning Act 2017,
in respect of any railway property unless the exercise of such powers is with the consent of Network
Rail.
90Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(2) The undertaker must not in the exercise of the powers conferred by this Order prevent
pedestrian or vehicular access to any railway property, unless preventing such access is with the
consent of Network Rail.
(3) The undertaker must not exercise the powers conferred by sections 271 or 272 of the 1990
Act, article 32 (statutory undertakers), article 27 (power to override easements and other rights) or
article 24 (private rights), in relation to any right of access of Network Rail to railway property, but
such right of access may be diverted with the consent of Network Rail.
(4) The undertaker must not under the powers of this Order acquire or use or acquire new
rights over, or seek to impose any restrictive covenants over, any railway property or extinguish any
existing rights of Network Rail in respect of any third party property, except with the consent of
Network Rail.
(5) The undertaker must not under the powers of this Order do anything which would result in
railway property being incapable of being used or maintained or which would affect the safe running
of trains on the railway.
(6) Where Network Rail is asked to give its consent pursuant to this paragraph, such consent
must not be unreasonably withheld but may be given subject to reasonable conditions but it shall
never be unreasonable to withhold consent for reasons of operational or railway safety (such matters
to be in Network Rail’s absolute discretion).
(7) The undertaker must enter into an asset protection agreement prior to the carrying out of any
specified work.
33.—(1) The undertaker must before commencing construction of any specified work supply to
Network Rail proper and sufficient plans of that work for the reasonable approval of the engineer
and the specified work must not be commenced except in accordance with such plans as have been
approved in writing by the engineer or settled by arbitration.
(2) The approval of the engineer under sub-paragraph (1) must not be unreasonably withheld,
and if by the end of the period of 28 days beginning with the date on which such plans have been
supplied to Network Rail the engineer has not intimated their disapproval of those plans and the
grounds of such disapproval the undertaker may serve upon the engineer written notice requiring
the engineer to intimate approval or disapproval within a further period of 28 days beginning with
the date upon which the engineer receives written notice from the undertaker. If by the expiry of the
further 28 days the engineer has not intimated approval or disapproval, the engineer shall be deemed
to have approved the plans as submitted.
(3) If by the end of the period of 28 days beginning with the date on which written notice was
served upon the engineer under sub-paragraph (2), Network Rail gives notice to the undertaker
that Network Rail desires itself to construct any part of a specified work which in the opinion of
the engineer will or may affect the stability of railway property or the safe operation of traffic
on the railways of Network Rail then, if the undertaker desires such part of the specified work to
be constructed, Network Rail must construct it without unnecessary delay on behalf of and to the
reasonable satisfaction of the undertaker in accordance with the plans approved or deemed to be
approved or settled under this paragraph, and under the supervision (where appropriate and if given)
of the undertaker.
(4) When signifying their approval of the plans the engineer may specify any protective works
(whether temporary or permanent) which in the engineer’s opinion should be carried out before the
commencement of the construction of a specified work to ensure the safety or stability of railway
property or the continuation of safe and efficient operation of the railways of Network Rail or the
services of operators using the same (including any relocation, de-commissioning and removal of
works, apparatus and equipment necessitated by a specified work and the comfort and safety of
passengers who may be affected by the specified works), and such protective works as may be
reasonably necessary for those purposes must be constructed by Network Rail or by the undertaker,
91Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
if Network Rail so desires, and such protective works must be carried out at the expense of the
undertaker in either case without unnecessary delay and the undertaker must not commence the
construction of the specified works until the engineer has notified the undertaker that the protective
works have been completed to their reasonable satisfaction.
34.—(1) Any specified work and any protective works to be constructed by virtue of paragraph
33(4) must, when commenced, be constructed—
(a) without unnecessary delay in accordance with the plans approved or deemed to have been
approved or settled under paragraph 33;
(b) under the supervision (where appropriate and if given) and to the reasonable satisfaction
of the engineer;
(c) in such manner as to cause as little damage as is possible to railway property; and
(d) so far as is reasonably practicable, so as not to interfere with or obstruct the free,
uninterrupted and safe use of any railway of Network Rail or the traffic thereon and the
use by passengers of railway property.
(2) If any damage to railway property or any such interference or obstruction shall be caused
by the carrying out of, or in consequence of the construction of a specified work, the undertaker
must, notwithstanding any such approval, make good such damage and must pay to Network Rail
all reasonable expenses to which Network Rail may be put and compensation for any loss which it
may sustain by reason of any such damage, interference or obstruction.
(3) Nothing in this Part of this Schedule imposes any liability on the undertaker with respect to
any damage, costs, expenses or loss attributable to the negligence of Network Rail or its servants,
contractors or agents or any liability on Network Rail with respect of any damage, costs, expenses
or loss attributable to the negligence of the undertaker or its servants, contractors or agents.
35. The undertaker must—
(a) at all times afford reasonable facilities to the engineer for access to a specified work during
its construction; and
(b) supply the engineer with all such information as they may reasonably require with regard
to a specified work or the method of constructing it.
36. Network Rail must at all times afford reasonable facilities to the undertaker and its agents
for access to any works carried out by Network Rail under this Part of this Schedule during their
construction and must supply the undertaker with such information as it may reasonably require with
regard to such works or the method of constructing them.
37.—(1) If any permanent or temporary alterations or additions to railway property are reasonably
necessary in consequence of the construction or completion of a specified work in order to ensure
the safety of railway property or the continued safe operation of the railway of Network Rail, such
alterations and additions may be carried out by Network Rail and if Network Rail gives to the
undertaker 56 days’ notice (or in the event of an emergency or safety critical issue such notice as
is reasonable in the circumstances) of its intention to carry out such alterations or additions (which
must be specified in the notice), the undertaker must pay to Network Rail the reasonable cost of
those alterations or additions including, in respect of any such alterations and additions as are to be
permanent, a capitalised sum representing the increase of the costs which may be expected to be
reasonably incurred by Network Rail in maintaining, working and, when necessary, renewing any
such alterations or additions.
(2) If during the construction of a specified work by the undertaker, Network Rail gives notice to
the undertaker that Network Rail desires itself to construct that part of the specified work which in
the opinion of the engineer is endangering the stability of railway property or the safe operation of
traffic on the railways of Network Rail then, if the undertaker decides that part of the specified work
92Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
is to be constructed, Network Rail must assume construction of that part of the specified work and
the undertaker must, notwithstanding any such approval of a specified work under paragraph 33(3),
pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation
for any loss which it may suffer by reason of the execution by Network Rail of that specified work.
(3) The engineer must, in respect of the capitalised sums referred to in this paragraph and
paragraph 38(a) provide such details of the formula by which those sums have been calculated as
the undertaker may reasonably require.
(4) If the cost of maintaining, working or renewing railway property is reduced in consequence of
any such alterations or additions a capitalised sum representing such saving must be set off against
any sum payable by the undertaker to Network Rail under this paragraph.
38. The undertaker must repay to Network Rail all reasonable fees, costs, charges and expenses
reasonably incurred by Network Rail—
(a) in constructing any part of a specified work on behalf of the undertaker as provided
by paragraph 33(3) or in constructing any protective works under the provisions of
paragraph 33(4) including, in respect of any permanent protective works, a capitalised sum
representing the cost of maintaining and renewing those works;
(b) in respect of the approval by the engineer of plans submitted by the undertaker and the
supervision by the engineer of the construction of a specified work;
(c) in respect of the employment or procurement of the services of any inspectors, signallers,
watch-persons and other persons whom it shall be reasonably necessary to appoint for
inspecting, signalling, watching and lighting railway property and for preventing, so far as
may be reasonably practicable, interference, obstruction, danger or accident arising from
the construction or failure of a specified work;
(d) in respect of any special traffic working resulting from any speed restrictions which may
in the opinion of the engineer, require to be imposed by reason or in consequence of the
construction or failure of a specified work or from the substitution or diversion of services
which may be reasonably necessary for the same reason; and
(e) in respect of any additional temporary lighting of railway property in the vicinity of the
specified works, being lighting made reasonably necessary by reason or in consequence
of the construction or failure of a specified work.
39.—(1) In this paragraph—
“EMI” means, subject to sub-paragraph (2), electromagnetic interference with Network Rail
apparatus generated by the operation of the authorised development where such interference
is of a level which adversely affects the safe operation of Network Rail’s apparatus; and
“Network Rail’s apparatus” means any lines, circuits, wires, apparatus or equipment (whether
or not modified or installed as part of the authorised development) which are owned or
used by Network Rail for the purpose of transmitting or receiving electrical energy or of
radio, telegraphic, telephonic, electric, electronic or other like means of signalling or other
communications.
(2) This paragraph applies to EMI only to the extent that such EMI is not attributable to any
change to Network Rail’s apparatus carried out after approval of plans under paragraph 33(1) for
the relevant part of the authorised development giving rise to EMI (unless the undertaker has been
given notice in writing before the approval of those plans of the intention to make such change).
(3) Subject to sub-paragraph (5), the undertaker must in the design and construction of the
authorised development take all measures necessary to prevent EMI and must establish with Network
Rail (both parties acting reasonably) appropriate arrangements to verify their effectiveness.
(4) In order to facilitate the undertaker’s compliance with sub-paragraph (3)—
93Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(a) the undertaker must consult with Network Rail as early as reasonably practicable to
identify all Network Rail’s apparatus which may be at risk of EMI, and thereafter must
continue to consult with Network Rail (both before and after formal submission of plans
under paragraph 33(1)) in order to identify all potential causes of EMI and the measures
required to eliminate them;
(b) Network Rail must make available to the undertaker all information in the possession
of Network Rail reasonably requested by the undertaker in respect of Network Rail’s
apparatus identified pursuant to sub-paragraph (a); and
(c) Network Rail must allow the undertaker reasonable facilities for the inspection of Network
Rail’s apparatus identified pursuant to sub-paragraph (a).
(5) In any case where it is established that EMI can only reasonably be prevented by
modifications to Network Rail’s apparatus, Network Rail must not withhold its consent unreasonably
to modifications of Network Rail’s apparatus, but the means of prevention and the method of their
execution must be selected in the reasonable discretion of Network Rail, and in relation to such
modifications paragraph 33(1) has effect subject to the sub-paragraph.
(6) Prior to the commencement of operation of the authorised development the undertaker shall
test the use of the authorised development in a manner that shall first have been agreed with Network
Rail and if, notwithstanding any measures adopted pursuant to sub-paragraph (3), the testing of
the authorised development causes EMI then the undertaker must immediately upon receipt of
notification by Network Rail of such EMI either in writing or communicated orally (such oral
communication to be confirmed in writing as soon as reasonably practicable after it has been issued)
forthwith cease to use (or procure the cessation of use of) the undertaker’s apparatus causing such
EMI until all measures necessary have been taken to remedy such EMI by way of modification
to the source of such EMI or (in the circumstances, and subject to the consent, specified in sub-
paragraph (5)) to Network Rail’s apparatus.
(7) In the event of EMI having occurred—
(a) the undertaker must afford reasonable facilities to Network Rail for access to the
undertaker’s apparatus in the investigation of such EMI;
(b) Network Rail must afford reasonable facilities to the undertaker for access to Network
Rail’s apparatus in the investigation of such EMI;
(c) Network Rail must make available to the undertaker any additional material information
in its possession reasonably requested by the undertaker in respect of Network Rail’s
apparatus or such EMI; and
(d) the undertaker shall not allow the use or operation of the authorised development in a
manner that has caused or will cause EMI until measures have been taken in accordance
with this paragraph to prevent EMI occurring.
(8) Where Network Rail approves modifications to Network Rail’s apparatus pursuant to sub-
paragraphs (5) or (6)—
(a) Network Rail must allow the undertaker reasonable facilities for the inspection of the
relevant part of Network Rail’s apparatus; and
(b) any modifications to Network Rail’s apparatus approved pursuant to those sub-paragraphs
must be carried out and completed by the undertaker in accordance with paragraph 34.
(9) To the extent that it would not otherwise do so, the indemnity in paragraph 43(1) applies
to the costs and expenses reasonably incurred or losses suffered by Network Rail through the
implementation of the provisions of this paragraph (including costs incurred in connection with the
consideration of proposals, approval of plans, supervision and inspection of works and facilitating
access to Network Rail’s apparatus) or in consequence of any EMI to which sub-paragraph (6)
applies.
94Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(10) For the purpose of paragraph 38(a) any modifications to Network Rail’s apparatus under
this paragraph shall be deemed to be protective works referred to in that paragraph.
40. If at any time after the completion of a specified work, not being a work vested in Network
Rail, Network Rail gives notice to the undertaker informing it that the state of maintenance of any
part of the specified work appears to be such as adversely affects the operation of railway property,
the undertaker must, on receipt of such notice, take such steps as may be reasonably necessary to
put that specified work in such state of maintenance as not adversely to affect railway property.
41. The undertaker must not provide any illumination or illuminated sign or signal on or in
connection with a specified work in the vicinity of any railway belonging to Network Rail unless it
has first consulted Network Rail and it must comply with Network Rail’s reasonable requirements
for preventing confusion between such illumination or illuminated sign or signal and any railway
signal or other light used for controlling, directing or securing the safety of traffic on the railway.
42. Any additional expenses which Network Rail may reasonably incur in altering, reconstructing
or maintaining railway property under any powers existing at the making of this Order by reason of
the existence of a specified work must, provided that 56 days’ previous notice of the commencement
of such alteration, reconstruction or maintenance has been given to the undertaker, be repaid by the
undertaker to Network Rail.
43.—(1) The undertaker must pay to Network Rail all reasonable costs, charges, damages and
expenses not otherwise provided for in this Part of this Schedule (subject to article 42 (no double
recovery)) which may be occasioned to or reasonably incurred by Network Rail—
(a) by reason of the construction, maintenance or operation of a specified work or the failure
thereof; or
(b) by reason of any act or omission of the undertaker or of any person in its employ or of its
contractors or others whilst engaged upon a specified work;
(c) by reason of any act or omission of the undertaker or any person in its employ or of its
contractors or others whilst accessing to or egressing from the authorised development;
(d) in respect of any damage caused to or additional maintenance required to, railway property
or any such interference or obstruction or delay to the operation of the railway as a result
of access to or egress from the authorised development by the undertaker or any person
in its employ or of its contractors or others;
(e) in respect of costs incurred by Network Rail in complying with any railway operational
procedures or obtaining any regulatory consents which procedures are required to be
followed or consents obtained to facilitate the carrying out or operation of the authorised
development,
and the undertaker must indemnify and keep indemnified Network Rail from and against all claims
and demands arising out of or in connection with a specified work or any such failure, act or omission:
and the fact that any act or thing may have been done by Network Rail on behalf of the undertaker
or in accordance with plans approved by the engineer or in accordance with any requirement of the
engineer or under the engineer’s supervision shall not (if it was done without negligence on the part
of Network Rail or of any person in its employ or of its contractors or agents) excuse the undertaker
from any liability under the provisions of this sub-paragraph.
(2) Network Rail must—
(a) give the undertaker reasonable written notice of any such claims or demands;
(b) not make any settlement or compromise of such a claim or demand without the prior
consent of the undertaker; and
(c) take such steps as are within its control and are reasonable in the circumstances to mitigate
any liabilities relating to such claims or demands.
95Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(3) The sums payable by the undertaker under sub-paragraph (1) shall if relevant include a sum
equivalent to the relevant costs.
(4) Subject to the terms of any agreement between Network Rail and a train operator regarding
the timing or method of payment of the relevant costs in respect of that train operator, Network Rail
must promptly pay to each train operator the amount of any sums which Network Rail receives under
sub-paragraph (3) which relates to the relevant costs of that train operator.
(5) The obligation under sub-paragraph (3) to pay Network Rail the relevant costs shall, in the
event of default, be enforceable directly by any train operator concerned to the extent that such sums
would be payable to that operator pursuant to sub-paragraph (4).
(6) In this paragraph—
“the relevant costs” means the costs, losses and expenses (including loss of revenue) reasonably
incurred by each train operator as a consequence of any specified work including but not
limited to any restriction of the use of Network Rail’s railway network as a result of the
construction, maintenance or failure of a specified work or any such act or omission as
mentioned in sub-paragraph (1); and
“train operator” means any person who is authorised to act as the operator of a train by a licence
under section 8 of the Railways Act 1993.
44. Network Rail must, on receipt of a request from the undertaker, from time to time provide
the undertaker free of charge with written estimates of the costs, charges, expenses and other
liabilities for which the undertaker is or will become liable under this Part of this Schedule (including
the amount of the relevant costs mentioned in paragraph 43) and with such information as may
reasonably enable the undertaker to assess the reasonableness of any such estimate or claim made or
to be made pursuant to this Part of this Schedule (including any claim relating to those relevant costs).
45. In the assessment of any sums payable to Network Rail under this Part of this Schedule there
must not be taken into account any increase in the sums claimed that is attributable to any action taken
by or any agreement entered into by Network Rail if that action or agreement was not reasonably
necessary and was taken or entered into with a view to obtaining the payment of those sums by the
undertaker under this Part of this Schedule or increasing the sums so payable.
46. The undertaker and Network Rail may, subject in the case of Network Rail to compliance
with the terms of its network licence, enter into, and carry into effect, agreements for the transfer
to the undertaker of—
(a) any railway property shown on the works and land plans and described in the book of
reference;
(b) any lands, works or other property held in connection with any such railway property; and
(c) any rights and obligations (whether or not statutory) of Network Rail relating to any
railway property or any lands, works or other property referred to in this paragraph.
47. Nothing in this Order, or in any enactment incorporated with or applied by this Order,
prejudices or affects the operation of Part I of the Railways Act 1993.
48. The undertaker must give written notice to Network Rail if any application is proposed to be
made by the undertaker for the Secretary of State’s consent, under article 36 (consent to transfer the
benefit of the Order) of this Order and any such notice must be given no later than 28 days before
any such application is made and must describe or give (as appropriate)—
(a) the nature of the application to be made;
(b) the extent of the geographical area to which the application relates; and
(c) the name and address of the person acting for the Secretary of State to whom the
application is to be made.
96Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
49. The undertaker must no later than 28 days from the date that the plans submitted to and
certified by the Secretary of State in accordance with article 41 (certification of plans and documents,
etc.) are certified by the Secretary of State, provide a set of those plans to Network Rail in a format
specified by Network Rail.
50. Any dispute arising under this Part of this Schedule, unless otherwise provided for, must
be referred to and settled by arbitration in accordance with article 43 (arbitration) and the Rules at
Schedule 13 (Arbitration Rules).
PART 5
FOR THE PROTECTION OF THE ENVIRONMENT AGENCY
51.—(1) The following provisions apply for the protection of the Agency, except in respect
of the construction of any work or the carrying out of any operation required for the purposes of,
or in connection with, the construction, operation or maintenance of any part of the authorised
development undertaken within Plots 9/09, 9/12, 9/13, 9/14, 9/15, 10/01, 10/02, 10/03, 10/04, 10/05,
10/06, 10/07, 10/08, 10/09, 10/10, 10/11, 10/12, 10/13, and 10/14 as marked within the land plans
or unless otherwise agreed in writing between the undertaker and the Agency.
(2) In this Part of this Schedule—
“Agency” means the Environment Agency;
“construction” includes execution, placing, altering, replacing, relaying and removal and
excavation and “construct” and “constructed” is construed accordingly;
“drainage work” means any main river and includes any land which provides or is expected
to provide flood storage capacity for any main river and any bank, wall, embankment or
other structure, or any appliance, constructed or used for land drainage, flood defence or tidal
monitoring;
“emergency” means an occurrence which presents a risk of—
(a) serious flooding;
(b) serious detrimental impact on drainage; or
(c) serious harm to the environment;
“fishery” means any waters containing fish and fish in, or migrating to or from, such waters
and the spawn, spawning ground, habitat or food of such fish;
“main river” has the same meaning given in section 113 of the Water Resources Act 1991;
“non-tidal main river” has the meaning given in paragraph 2(1) of Part 1 of Schedule 25 to the
Environmental Permitting (England and Wales) Regulations 2016;
“plans” includes plans, sections, elevations, drawings, specifications, programmes, proposals,
calculations, method statements and descriptions;
“remote defence” means any berm, wall or embankment that is constructed for the purposes
of preventing or alleviating flooding from, or in connection with, any main river;
“sea defence” means any bank, wall, embankment (any berm, counterwall or cross-wall
connected to any such bank, wall or embankment), barrier, tidal sluice and other defence,
whether natural or artificial, against the inundation of land by sea water or tidal water, including
natural or artificial high ground which forms part of or makes a contribution to the efficiency of
the defences of the Agency’s area against flooding, but excludes any sea defence works which
are for the time being maintained by a coast protection authority under the provisions of the
Coast Protection Act 1949 or by any local authority or any navigation, harbour or conservancy
authority;
97Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
“specified work” means so much of any work or operation authorised by this Order as is in,
on, under, over or within—
(a) 16 metres of the base of a sea defence which is likely to—
(i) endanger the stability of, cause damage or reduce the effectiveness of that sea
defence, or
(ii) interfere with the Agency’s access to or along that sea defence or the Agency’s
ability to undertake works to ensure the efficacy of that sea defence;
(b) 8 metres of the base of a remote defence which is likely to—
(i) endanger the stability of, cause damage or reduce the effectiveness of that remote
defence, or
(ii) interfere with the Agency’s access to or along that remote defence;
(c) 16 metres of a drainage work involving a tidal main river;
(d) 8 metres of a drainage work involving a non-tidal main river;
(e) any distance of a drainage work and is otherwise likely to—
(i) affect any drainage work or the volumetric rate of flow of water in or flowing to
or from any drainage work;
(ii) affect the flow, purity or quality of water in any main river or other surface waters;
(iii) cause obstruction to the free passage of fish or damage to any fishery;
(iv) affect the conservation, distribution or use of water resources; or
(v) affect the conservation value of the main river and habitats in its immediate vicinity;
or which involves—
(f) an activity that includes dredging, raising or taking of any sand, silt, ballast, clay, gravel or
other materials from or off the bed or banks of a drainage work (or causing such materials
to be dredged, raised or taken), including hydrodynamic dredging or desilting; and
(g) any quarrying or excavation within 16 metres of a drainage work which is likely to cause
damage to or endanger the stability of the banks or structure of that drainage work;
“tidal main river” has the meaning given in paragraph 2(1) of Part 1 of Schedule 25 to the
Environmental Permitting (England and Wales) Regulations 2016.
Submission and approval of plans
52.—(1) Before beginning to construct any specified work, the undertaker must submit to the
Agency plans of the specified work and such further particulars available to it as the Agency may
within 28 days of the receipt of the plans reasonably request.
(2) Any such specified work must not be constructed except in accordance with such plans as
may be approved in writing by the Agency, or determined under paragraph 62.
(3) Any approval of the Agency required under this paragraph—
(a) must not be unreasonably withheld or delayed;
(b) subject to sub-paragraph (5), is deemed to have been refused if it is neither given nor
refused within 2 months of the submission of the plans or such later date as is agreed
between the Agency and the undertaker and if further particulars have been requested
pursuant to sub-paragraph (1) the period between the making of this request and the
provision of further particulars in response to it shall not be taken into account in the
calculation of the 2 months for the purposes of this sub-paragraph; and
98Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(c) may be given subject to such reasonable requirements as the Agency may have for the
protection of any drainage work or the fishery or for the protection of water resources, or
for the prevention of flooding or pollution or for nature conservation or the prevention of
environmental harm in the discharge of its environmental duties.
(4) The Agency must use its reasonable endeavours to respond to the submission of any plans
before the expiration of the period mentioned in sub-paragraph (3)(b).
(5) In the case of a refusal, the Agency must provide reasons for the grounds of that refusal.
Construction of protective works
53. Without limiting paragraph 52 the requirements which the Agency may have under that
paragraph include conditions requiring the undertaker, at its own expense, to construct such
protective works, whether temporary or permanent, before or during the construction of the specified
works (including the provision of flood banks, walls or embankments or other new works and
the strengthening, repair or renewal of existing banks, walls or embankments) as are reasonably
necessary—
(a) to safeguard any drainage work against damage; or
(b) to secure that its efficiency for flood defence purposes is not impaired and that the risk of
flooding is not otherwise increased,
by reason of any specified work.
Timing of works and service of notices
54.—(1) Subject to sub-paragraph (2), any specified work, and all protective works required by
the Agency under paragraph 53, must be constructed—
(a) without unreasonable delay in accordance with the plans approved under this Part of this
Schedule; and
(b) to the reasonable satisfaction of the Agency,
and the Agency is entitled by its officer to watch and inspect the construction of such works.
(2) The undertaker must give to the Agency not less than 14 days’ notice in writing of its intention
to commence construction of any specified work and notice in writing of its completion not later
than 7 days after the date on which it is completed.
(3) If the Agency reasonably requires, the undertaker must construct all or part of the protective
works so that they are in place prior to the construction of any specified work to which the protective
works relate.
Works not in accordance with this Schedule
55.—(1) If there is any failure by the undertaker to obtain consent or comply with conditions
imposed by the Agency in accordance with these protective provisions and where the Agency acting
reasonably considers it necessary to avoid any of the risks specified in sub-paragraph (2), the Agency
may serve written notice requiring the undertaker to cease all or part of the specified works as may
be specified within the notice within the period specified in the notice, and the undertaker must cease
constructing the specified works or part thereof until such time as it has obtained the consent or
complied with the condition specified within the notice served.
(2) The risks specified in sub-paragraph (1) are—
(a) risk of flooding;
(b) risk of harm to the environment;
99Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(c) risk of detrimental impact on drainage; and
(d) damage to the fishery.
(3) If any part of a specified work or any protective work required by the Agency is constructed
otherwise than in accordance with the requirements of this Part of this Schedule, the Agency may
by notice in writing require the undertaker at the undertaker’s own expense to comply with the
requirements of this Part of this Schedule or (if the undertaker so elects and the Agency in writing
consents, such consent not to be unreasonably withheld or delayed) to remove, alter or pull down
the work and, where removal is required, to restore the site to its former condition to such extent
and within such limits as the Agency reasonably requires.
(4) Subject to sub-paragraph (5) if, within a reasonable period, being not less than 28 days
beginning with the date when a notice under sub-paragraph (3) is served upon the undertaker, the
undertaker has failed to begin taking steps to comply with the requirements of the notice and has not
subsequently made reasonably expeditious progress towards their implementation, the Agency may
execute the works specified in the notice and any reasonable expenditure incurred by the Agency in
so doing is recoverable from the undertaker.
(5) In the event of any dispute as to whether sub-paragraph (3) is properly applicable to any work
in respect of which notice has been served under that sub-paragraph, or as to the reasonableness
of any requirement of such a notice, the Agency must not, except in the case of an emergency,
exercise the powers conferred by sub-paragraph (4) until the dispute has been finally determined in
accordance with paragraph 62.
Maintenance of works
56.—(1) Subject to sub-paragraph (5) the undertaker must from the commencement of the
construction of the specified works maintain in good repair and condition and free from obstruction
any drainage work which is situated within the Order limits and on land held by the undertaker
for the purposes of or in connection with the specified works, whether or not the drainage work is
constructed under the powers conferred by this Order or is already in existence.
(2) If any such drainage work which the undertaker is liable to maintain is not maintained to the
reasonable satisfaction of the Agency, the Agency may by notice in writing require the undertaker to
repair and restore the work, or any part of such work, or (if the undertaker so elects and the Agency
in writing consents, such consent not to be unreasonably withheld or delayed), to remove the work
and restore the site to its former condition, to such extent and within such limits as the Agency
reasonably requires.
(3) Subject to sub-paragraph (4) if, within a reasonable period, being not less than 28 days
beginning with the date on which a notice in respect of any drainage work is served under sub-
paragraph (2) on the undertaker, the undertaker has failed to begin taking steps to comply with the
requirements of the notice and has not subsequently made reasonably expeditious progress towards
their implementation, the Agency may do what is necessary for such compliance and any reasonable
expenditure incurred by the Agency in so doing is recoverable from the undertaker.
(4) In the event of any dispute as to the reasonableness of any requirement of a notice served
under sub-paragraph (2), the Agency must not, except in the case of an emergency, exercise the
powers conferred by sub-paragraph (3) until the dispute has been finally determined in accordance
with paragraph 62.
(5) This paragraph does not apply to—
(a) drainage works which are vested in the Agency, or which the Agency or another person is
liable to maintain and is not proscribed by the powers of the Order from doing so; and
(b) any obstruction of a drainage work expressly authorised in the approval of specified works
plans and carried out in accordance with the provisions of this Part of this Schedule
provided that any obstruction is removed as soon as reasonably practicable.
100Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Remediating impaired drainage work
57. If by reason of the construction of any specified work or of the failure of any such work,
the efficiency of any drainage work for flood defence purposes is impaired, or that drainage work
is otherwise damaged, such impairment or damage must be made good by the undertaker to the
reasonable satisfaction of the Agency and if the undertaker fails to do so, the Agency may make
good the impairment or damage and recover any expenditure incurred by the Agency in so doing
from the undertaker.
Agency access
58. If by reason of the construction of any specified work or the failure of any such work, the
Agency’s access to flood defences or equipment maintained for flood defence purposes is materially
obstructed, the undertaker must notify the Agency immediately and provide suitable alternative
means of access that will allow the Agency to maintain the flood defence or use the equipment no
less effectively than was possible before the obstruction occurred and such alternative access must
be made available as soon as reasonably practicable after the undertaker becomes aware of such
obstruction, except in the case of an emergency in which case the undertaker must provide such
alternative means of access on demand.
Free passage of fish
59.—(1) The undertaker must take all such measures as may be reasonably practicable to prevent
any interruption of the free passage of fish in the fishery during the construction of any specified
work.
(2) If by reason of—
(a) the construction of any specified work; or
(b) the failure of any such work,
damage to the fishery is caused, or the Agency has reason to expect that such damage may be caused,
the Agency may serve notice on the undertaker requiring it to take such steps as may be reasonably
practicable to make good the damage, or, as the case may be, to protect the fishery against such
damage within the period specified in the notice.
(3) If the undertaker fails to take such steps as are described in the notice served under sub-
paragraph (2), the Agency may take those steps and any expenditure incurred by the Agency in so
doing is recoverable from the undertaker.
(4) In any case where immediate action by the Agency is reasonably required in order to secure
that the risk of damage to the fishery is avoided or reduced, the Agency may take such steps as are
reasonable for the purpose, and may recover from the undertaker any expenditure incurred in so
doing provided that notice specifying those steps is served on the undertaker as soon as reasonably
practicable after the Agency has taken, or commenced to take, the steps specified in the notice.
Indemnity
60. The undertaker indemnifies the Agency in respect of all costs, charges and expenses which
the Agency may reasonably incur—
(a) in the examination or approval of plans under this Part of this Schedule;
(b) in the inspection of the construction of the specified works or any protective works
required by the Agency under this Part of this Schedule; and
(c) in the carrying out of any surveys or tests by the Agency which are reasonably required
in connection with the construction of the specified works.
101Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
61.—(1) The undertaker is responsible for and indemnifies the Agency against all costs and
losses, liabilities, claims and demands not otherwise provided for in this Schedule which may be
reasonably incurred or suffered by the Agency by reason of, or arising out of—
(a) the construction, operation or maintenance of any specified works comprised within the
authorised development or the failure of any such works comprised within them; or
(b) any act or omission of the undertaker, its employees, contractors or agents or others whilst
engaged upon the construction, operation, or maintenance of the authorised development
or dealing with any failure of the authorised development.
(2) For the avoidance of doubt, in sub-paragraph (1)—
“costs” includes—
(a) expenses and charges;
(b) staff costs and overheads; and
(c) legal costs;
“losses” includes physical damage;
“claims” and “demands” include as applicable—
(a) costs (within the meaning of sub-paragraph (2)) incurred in connection with any claim
or demand; and
(b) any interest element of sums claimed or demanded;
“liabilities” includes—
(a) contractual liabilities;
(b) tortious liabilities (including liabilities for negligence or nuisance);
(c) liabilities to pay statutory compensation or for breach of statutory duty;
(d) liabilities to pay statutory penalties imposed on the basis of strict liability (but does not
include liabilities to pay other statutory penalties.
(3) The Agency must give to the undertaker reasonable notice of any such claim or demand and
must not settle or compromise a claim without the agreement of the undertaker and that agreement
must not be unreasonably withheld or delayed.
(4) The Agency must, at all times, take reasonable steps to prevent and mitigate any such claims,
demands, proceedings, costs, damages, expenses or loss.
(5) The fact that any work or thing has been executed or done by the undertaker in accordance
with a plan approved by the Agency, or to its satisfaction, or in accordance with any directions or
award of an arbitrator, must not relieve the undertaker from any liability under the provisions of this
Part of this Schedule.
(6) Nothing in this paragraph imposes any liability on the undertaker with respect to any costs,
charges, expenses, damages, claims, demands or losses to the extent that they are attributable to the
neglect or default of the Agency, its officers, servants, contractors or agents.
Disputes
62. Any dispute arising between the undertaker and the Agency under this Part of this Schedule
must, if the parties agree, be determined by arbitration under article 43 (arbitration), but failing
agreement be determined by the Secretary of State for Environment, Food and Rural Affairs or its
successor and the Secretary of State for Energy Security and Net Zero or its successor acting jointly
on a reference to them by the undertaker or the Agency, after notice in writing by one to the other.
102Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
PART 6
FOR THE PROTECTION OF EXOLUM PIPELINE SYSTEM LTD
Application
63. For the protection of Exolum the following provisions, unless otherwise agreed in writing at
any time between the undertaker and Exolum, have effect.
Interpretation
64. In this Part of this Schedule, the following terms shall have the following meanings—
“Additional Rights” means rights for the construction and for access to and for the use,
protection, inspection, maintenance, repair and renewal of retained Apparatus including any
restrictions on the landowner and occupiers for the protection of the retained Apparatus and
to allow Exolum to perform its functions;
“Alternative Apparatus” means alternative apparatus adequate to enable Exolum to fulfil its
functions as a pipeline operator in a manner not less efficient than previously;
“Alternative Rights” means rights for the construction and for access to and for the use,
protection, inspection, maintenance, repair and renewal of Alternative Apparatus including
any restrictions on the landowner and occupiers for the protection of the Alternative Apparatus
and to allow Exolum to perform its functions;
“Apparatus” means the pipeline and storage system and any ancillary apparatus owned or
operated by Exolum and includes—
(a) any structure in which apparatus is or is to be lodged or which gives or will give access
to apparatus;
(b) any ancillary works, all protective wrappings, valves, sleeves and slabs, cathodic
protection units, together with ancillary cables and markers;
(c) such legal interest, and benefit of property rights and covenants as are vested in respect
of these items,
and, where the context requires, includes Alternative Apparatus;
“Exolum” means Exolum Pipeline System Ltd and for the purpose of enforcing the benefit of
any provisions in this Part of this Schedule, any group company of Exolum Pipeline System
Ltd and in all cases any successor in title;
“functions” includes powers and duties;
“in” in a context referring to Apparatus in land includes a reference to Apparatus under, over
or upon land;
“Plan” includes all designs, drawings, sections, specifications, method statements, soil reports,
programmes, calculations, risk assessments and other documents that are reasonably necessary
to allow Exolum to assess the Restricted Works to be executed properly and sufficiently and
in particular must describe—
(a) the position of the works as proposed to be constructed or renewed;
(b) the level at which the works are proposed to be constructed or renewed;
(c) the manner of the works’ construction or renewal including details of excavation,
positioning of plant etc.;
(d) the position of the affected Apparatus and/or Premises and any other apparatus belonging
to another undertaker that may also be affected by the Restricted Works;
103Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(e) by way of detailed drawings, every alteration proposed to be made to or close to any
such Apparatus;
(f) any intended maintenance regime;
(g) details of the proposed method of working and timing of execution of works; and
(h) details of vehicle access routes for construction and operational traffic;
“Premises” means land that Exolum owns, occupies or otherwise has rights to use including
but not limited to storage facilities, administrative buildings and jetties;
“Protective Works” means any works for the inspection and protection of Apparatus; and
“Restricted Works” means works that or will or may affect any Apparatus or Premises
including—
(a) all works within 15 metres measured in any direction of any Apparatus including
embankment works and those that involve a physical connection or attachment to any
Apparatus;
(b) the crossing of Apparatus by other utilities;
(c) the use of explosives within 400 metres of any Apparatus or Premises;
(d) piling, undertaking of a 3D seismic survey or the sinking boreholes within 30 metres of
any Apparatus or Premises;
(e) all works that impose a load directly upon the Apparatus, wherever situated,
whether carried out by the undertaker or any third party in connection with the Authorised
Development.
Acquisition of Apparatus
65. Regardless of any other provision in the Order or anything shown on the land plans—
(a) the undertaker must not, otherwise than by agreement with Exolum, acquire any
Apparatus, Exolum’s rights in respect of Apparatus or any of Exolum’s interests in the
Order land;
(b) where the undertaker acquires the freehold of any land in which Exolum holds an interest,
the undertaker must afford to or secure for Exolum such rights in land in substitution
for any right which would be extinguished by that acquisition (the replacement rights).
These replacement rights must be no less favourable than the rights to be extinguished
and must be granted upon substantially the same terms and conditions as the rights to be
extinguished, unless otherwise agreed between the undertaker and Exolum, and must be
granted or put in place contemporaneously with the extinguishment of the right which
they replace;
(c) the undertaker must not, otherwise than in accordance with this Part of this Schedule—
(i)obstruct or render less convenient the access to any Apparatus;
(ii)interfere with or affect Exolum’s ability to carry out its functions as an oil pipeline
operator;
(iii)require that Apparatus is relocated or diverted; or
(iv)remove or required to be removed any Apparatus;
(d) any right of Exolum to maintain, repair, renew, adjust, alter or inspect Apparatus must
not be extinguished under this Order until any necessary Alternative Apparatus has been
constructed and it is in operation and the Alternative Rights have been granted, all to the
reasonable satisfaction of Exolum; and
104Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(e) any right of Exolum to access the Exolum operations must not be extinguished until
necessary alternative access has been provided to Exolum’s reasonable satisfaction.
66. Prior to the carrying out of any Restricted Works or any works authorised by this Order that
will affect the Apparatus of Exolum, the parties must use their reasonable endeavours to negotiate
and enter into such deeds of consent (crossing consent) and (if necessary) variations to the existing
rights upon such terms and conditions as may be agreed between Exolum and the undertaker acting
reasonably and which must be no less favourable on the whole to Exolum than this Part of this
Schedule, and it will be the responsibility of the undertaker to use all reasonable endeavours to
procure and secure the consent and entering into of such deeds and variations by all other third
parties with an interest in the land at that time who are affected by such works.
67.—(1) Where the undertaker acquires land which is subject to any existing rights of Exolum
and the provisions of paragraph 68(1) do not apply, the undertaker must—
(a) retain any notice of the existing rights of Exolum on the title to the relevant land when
registering the undertaker’s title to such acquired land; and
(b) in instances where no such notice of the existing rights or other interest exists in relation
to such acquired land or any such notice is registered only on the Land Charges Register
include with its application to register title to the undertaker’s interest in such acquired
land at the Land Registry a notice of the existing rights or other interest in relation to such
acquired land; and
(c) provide up to date official entry copies to Exolum within 20 working days of receipt of
such up to date official entry copies.
(2) Where the undertaker takes temporary possession of any land or carries out survey works on
land in respect of which Exolum has Apparatus or Premises—
(a) where reasonably necessary, Exolum may exercise its rights to access such land—
(i)in an emergency, without notice; and
(ii)in non-emergency circumstances, having first given not less than 14 days’ written
notice to the undertaker in order to allow the parties to agree the timing of their
respective works during the period of temporary possession; and
(b) the undertaker must not remove or in any way alter Exolum’s rights in such land, unless
in accordance with the provisions of this Order.
Removal of Apparatus and Rights for Alternative Apparatus
68.—(1) If having used all reasonable endeavours to implement the Authorised Development
without the removal of any Apparatus—
(a) the undertaker reasonably requires the removal of any Apparatus; or
(b) Exolum reasonably requires the removal of any Apparatus,
then the relevant party must give written notice of that requirement to the other.
(2) The parties must use their reasonable endeavours to produce a plan of the work proposed and
a plan of the proposed position of the Alternative Apparatus to be provided or constructed.
(3) The undertaker must afford to Exolum the necessary facilities and rights for the construction
of Alternative Apparatus and subsequently the grant of Alternative Rights in accordance with
paragraphs 69 to 70.
(4) Any Alternative Apparatus is to be constructed in land owned by the undertaker or in land
in respect of which Alternative Rights have been or are guaranteed to be granted to Exolum. The
Alternative Apparatus must be constructed in such manner and in such line or situation as may
105Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
be agreed between Exolum and the undertaker or in default of agreement settled by arbitration in
accordance with article 43 (arbitration).
(5) After the details for the works for Alternative Apparatus to be provided or constructed have
been agreed or settled in accordance with article 43 (arbitration), and after the grant to Exolum
of any such facilities and rights as are referred to in sub-paragraph (3), Exolum must proceed as
soon as reasonably practicable using reasonable endeavours to construct and bring into operation
the Alternative Apparatus and subsequently to remove (or if agreed between the parties to allow the
undertaker to remove) any redundant Apparatus required by the undertaker to be removed under the
provisions of this Part of this Schedule.
(6) The following sub-paragraphs (7) and (8) shall only apply if—
(a) Exolum fails to comply with its obligations under sub-paragraph (5) to remove any
redundant Apparatus; and
(b) the undertaker has served notice on Exolum specifying the default; and
(c) Exolum has failed to remedy the default within 28 days of the notice being served.
(7) In the circumstances set out in sub-paragraph (6), if the undertaker then gives notice in
writing to Exolum that it desires itself to remove the redundant Apparatus, that work, instead of
being executed by Exolum, must be executed by the undertaker without unnecessary delay under
the superintendence, if given, and to the reasonable satisfaction of Exolum.
(8) Nothing in sub-paragraph (7) shall authorise the undertaker to execute the placing, installation,
bedding, packing, removal, connection or disconnection of any Apparatus, or execute any filling
around the Apparatus (where the Apparatus is laid in a trench) within 3000 millimetres of the
Apparatus unless that Apparatus is redundant and disconnected from Exolum’s remaining system.
Facilities and Rights for Alternative Apparatus
69.—(1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker
affords to Exolum facilities and rights for the construction of Alternative Apparatus and the grant
of Alternative Rights, in substitution for Apparatus to be removed, those facilities and rights must
be granted upon such terms and conditions as may be agreed between the undertaker and Exolum
in accordance with this Part of this Schedule or in default of agreement settled by arbitration in
accordance with article 43 (arbitration).
(2) Alternative Rights must be granted before any Alternative Apparatus is brought into use.
(3) The parties agree that the undertaker must use reasonable endeavours to procure the grant
of Alternative Rights by way of a 999 year sub-soil lease, substantially in the form of Exolum’s
precedent from time to time, as amended by written agreement between the parties acting reasonably,
or such other form of agreement as the parties otherwise agree acting reasonably.
(4) Nothing in this Part of this Schedule or contained in the Alternative Rights shall require
Exolum to divert or remove any Alternative Apparatus.
(5) If the facilities and rights to be afforded by the undertaker in respect of any Alternative
Apparatus, and the terms and conditions subject to which those facilities and rights are to be granted,
are in the opinion of Exolum less favourable on the whole to Exolum than the facilities and rights
enjoyed by it in respect of the Apparatus to be removed and the terms and conditions to which those
facilities and rights are subject, the Exolum may refer the matter to arbitration in accordance with
article 43 (arbitration).
106Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Retained Apparatus and Alternative Apparatus: protection
70.—(1) Before commencing the execution of any Restricted Works, the undertaker must submit
to Exolum a Plan of the works to be executed and any other information that Exolum may reasonably
require to allow Exolum to assess the works.
(2) No Restricted Works are to be commenced until the Plan to be submitted to Exolum under
sub-paragraph (1) has been approved by Exolum (acting reasonably) in writing and are to be carried
out only in accordance with the details submitted under sub-paragraph (1) and in accordance with
such reasonable requirements as may be notified to the undertaker in writing in accordance with
sub-paragraph (3) by Exolum.
(3) Any approval of Exolum in respect of Restricted Works may be given subject to such
reasonable requirements as Exolum may require to be made for—
(a) the continuing safety and operational viability of any Apparatus and/or Premises; and
(b) the requirement for Exolum to have reasonable access with or without vehicles to inspect,
repair, replace, maintain and ensure the continuing safety and operation or viability of any
Apparatus; and
(c) the requirement for Exolum to be entitled to watch and inspect the execution of Restricted
Works at any time,
providing such reasonable requirements shall be notified to the undertaker in writing.
(4) Where reasonably required by either party, in view of the complexity of any proposed works,
timescales, phasing or costs, the parties must with due diligence and good faith negotiate a works
agreement for the carrying out of Protective Works or the installation of Alternative Apparatus.
(5) If in consequence of the works notified to Exolum by the undertaker under sub-paragraph (1),
the circumstances in paragraph 68(1) apply, then the parties must follow the procedure in paragraph
68(1) onwards.
(6) Nothing in sub-paragraphs (1) to (6) precludes the undertaker from submitting prior to the
commencement of works to protect retained Apparatus or to construct Alternative Apparatus (unless
otherwise agreed in writing between the undertaker and Exolum) a new Plan, instead of the Plan
previously submitted, in which case the parties must re-run the procedure from sub-paragraph (1)
onwards.
(7) Where Exolum reasonably requires Protective Works, the parties must use their reasonable
endeavours to produce a plan of the work proposed and a plan of the proposed position of any
physical features to be provided or constructed.
(8) The undertaker must afford to Exolum the necessary facilities and rights for the construction of
Protective Works and subsequently the grant of Additional Rights in accordance with paragraph 69.
(9) Any Protective Works are to be constructed in land owned by the undertaker or in land
in respect of which Additional Rights have been or are guaranteed to be granted to Exolum. The
Protective Works must be constructed in such manner and in such line or situation as may be agreed
between Exolum and the undertaker or in default of agreement settled by expert determination in
accordance with article 43 (arbitration).
(10) After the details for the Protective Works to be provided or constructed have been agreed
or settled in accordance with article 43 (arbitration), and after the grant to Exolum of any such
facilities and rights as are referred to in paragraph 68(3), Exolum must proceed as soon as reasonably
practicable using reasonable endeavours to construct and bring into operation the Protective Works.
Cathodic protection testing
71.—(1) Where in the reasonable opinion of Exolum or the undertaker—
107Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(a) the Authorised Development might interfere with the cathodic protection forming part of
the Apparatus; or
(b) any Apparatus might interfere with the proposed or existing cathodic protection forming
part of the Authorised Development,
Exolum and the undertaker must co-operate in undertaking the tests which they consider reasonably
necessary for ascertaining the nature and extent of such interference and measures for providing or
preserving cathodic protection.
(2) The parties must carry out the works and enter into such agreements as are necessary to
implement the measures for providing or preserving cathodic protection.
Expenses
72.—(1) Subject to the following provisions of this paragraph, the undertaker must pay to Exolum
the reasonable and properly incurred costs and expenses (including reasonable staffing costs if work
is carried out in-house) incurred by Exolum in, or in connection with—
(a) undertaking its obligations under this Schedule including—
(i)the installation, inspection, removal, alteration, testing, or protection of any
Apparatus, Alternative Apparatus, and/or Protective Works;
(ii)the execution of any other works under this Part of this Schedule; and
(iii)the review and assessment of Plans;
(b) the watching of and inspecting the execution of the Authorised Development, any
Restricted Works and any works undertaken by third parties as a result of Authorised
Development (including the assessment of Plans); and
(c) imposing reasonable requirements for the protection or alteration of Apparatus affected by
the Authorised Development or works as a consequence of the Authorised Development
in accordance with paragraph 70(3),
together with any administrative costs properly and reasonably incurred by Exolum.
(2) There will be no deduction from any sum payable under sub-paragraph (1) as a result of—
(a) the placing of apparatus of a better type, greater capacity or of greater dimensions, or at
a greater depth than the existing Apparatus, to the extent Exolum has acted reasonably in
procuring such Apparatus;
(b) the placing of apparatus in substitution of the existing Apparatus that may defer the time
for renewal of the existing Apparatus in the ordinary course; or
(c) the scrap value (if any) of any Apparatus removed.
(3) Upon the submission of proper and reasonable estimates of costs and expenses to be incurred
by Exolum, the undertaker must pay Exolum sufficiently in advance to enable Exolum to undertake
its obligations under this Schedule in a manner that is neutral to its cash flow provided that in the
event that the costs incurred by Exolum are less than the amount paid by the undertaker pursuant
to this sub-paragraph then Exolum must, within 35 days of payment being made by Exolum for the
costs anticipated in the costs and expenses estimates, repay any overpayment to the undertaker.
Damage to property and other losses
73. Subject to paragraph 74 the undertaker must—
(a) indemnify Exolum for all loss, damage, liability, costs and expenses suffered or reasonably
incurred by Exolum arising out of—
(i)the carrying out of works under this Part of this Schedule;
108Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(ii)the carrying out of the Authorised Development;
(iii)the use or occupation of land over or in the vicinity of any Apparatus or in the vicinity
of any Premises in connection with the carrying out of the Authorised Development;
(iv)any injury or damage whatsoever to any property, real or personal, including the
property of Exolum; and
(v)any matters arising out of or in connection with this Order,
(b) indemnify Exolum against any claim made against, or loss suffered by, Exolum as a result
of any act or omission committed by the undertaker’s officers, employees, contractors
or agents whilst on or in the vicinity of any Apparatus or Premises for the purposes of
carrying out any activity authorised by this Order;
(c) pay to Exolum in accordance with the provisions of this Part of this Schedule, the cost
reasonably incurred by Exolum in making good any damage to the Apparatus (other than
Apparatus the repair of which is not reasonably necessary in view of its intended removal
or abandonment) arising out of the carrying out of works under this Part of this Schedule
and arising out of the carrying out of the Authorised Development; and
(d) pay to Exolum the cost reasonably incurred by Exolum in stopping, suspending and
restoring the supply through its Apparatus in consequence of the carrying out of works
under this Schedule or the carrying out of the Authorised Development,
and make reasonable compensation to Exolum for any other expenses, losses, damages, penalty or
costs incurred by Exolum by reason or in consequence of any such damage or interruption including
all claims by third parties.
74.—(1) Nothing in paragraph 73, imposes any liability on the undertaker with respect to any
indirect or consequential loss of any third party (including but not limited to loss of use, revenue,
profit, contract, production, increased cost of working or business interruption) arising from any
such damage or interruption which is not reasonably foreseeable.
(2) The fact that any act or thing may have been done by Exolum on behalf of the undertaker or
in accordance with a Plan approved by Exolum or in accordance with any requirement of Exolum
or under its supervision shall not, subject to sub-paragraph (4), excuse the undertaker from liability
under the provisions of paragraph 73.
(3) Nothing in paragraph 73 imposes any liability on the undertaker with respect to any damage
or interruption to the extent that it is attributable to the negligent act, neglect or default of Exolum,
its officers, servants, contractors or agents.
(4) The undertaker and Exolum must at all times take reasonable steps to prevent and mitigate
any loss, damage, liability, claim, cost or expense (whether indemnified or not) which either suffers
in connection with this Part of this Schedule.
(5) The undertaker warrants that it will use reasonable endeavours to ensure—
(a) the information it or any of its employees, agents or contractors provide to Exolum about
the Plans or the Authorised Development and on which Exolum relies in the design of and
carrying out of any works is accurate; and
(b) the undertaker or any of its employees, agents or contractors have exercised all the
reasonable skill, care and diligence to be expected of a qualified and experienced member
of their respective profession.
(6) Exolum must give to the undertaker reasonable notice of any claim or demand to which
paragraph 73 applies.
109Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Insurance
75.—(1) The undertaker must not carry out any Restricted Works unless and until Exolum
has confirmed to the undertaker in writing that it is satisfied acting reasonably (but subject to all
necessary regulatory constraints) that the undertaker (or its contractor) has procured acceptable
professional indemnity insurance and public liability insurance with minimum cover of £25 million
per event, with respect to the carrying out of the works.
(2) The undertaker must maintain such insurance for the construction period of the Authorised
Development from the proposed date of Commencement of the Authorised Development.
Co-operation and reasonableness
76.—(1) Where Apparatus is required to be protected, altered, diverted or removed under this
Schedule, the undertaker must use its all reasonable endeavours to co-ordinate the execution of any
works under this Part of this Schedule—
(a) in the interests of safety;
(b) in the interest of the efficient and economic execution of both Exolum’s works and the
Authorised Development; and
(c) taking into account the need to ensure the safe and efficient operation of Apparatus and
carrying out of Exolum’s functions.
(2) Exolum must use its reasonable endeavours to co-operate with the undertaker for the purposes
outlined in sub-paragraph (1).
(3) The undertaker and Exolum must act reasonably in respect of any given term of this Part
of this Schedule and, in particular, (without prejudice to generality) where any approval, consent
or expression of satisfaction is required by this Part of this Schedule it must not be unreasonably
withheld or delayed.
Emergency circumstances
77.—(1) The undertaker acknowledges that Exolum provides services to His Majesty’s
Government, using the Apparatus, which may affect any works to be carried under this Part of this
Schedule and the Authorised Development.
(2) In the following circumstances, Exolum may on written notice to the undertaker immediately
suspend all works that necessitate the stopping or suspending of the supply of product through
any Apparatus under this Schedule and Exolum shall not be in breach of its obligations under this
Schedule—
(a) circumstances in which in the determination of the Government, there subsists a material
threat to national security, or a threat or state of hostility or war or other crisis or national
emergency (whether or not involving hostility or war); or
(b) circumstances in which a request has been received, and a decision to act upon such
request has been taken, by the Government for assistance in relation to the occurrence or
anticipated occurrence of a major accident, crisis or natural disaster; or
(c) circumstances in which a request has been received from or on behalf of NATO, the EU, the
UN, the International Energy Agency (or any successor agency thereof) or the government
of any other state for support or assistance pursuant to the United Kingdom’s international
obligations and a decision to act upon such request has been taken by the Government; or
(d) any circumstances identified as such by the COBRA committee of the Government (or
any successor committee thereof); or
110Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(e) any situation in connection with which the Government requires fuel capacity, including
where the United Kingdom is engaged in any planned or unplanned military operations
within the United Kingdom or overseas.
(3) The parties agree to act in good faith and in all reasonableness to agree any revisions to any
schedule, programme or costs estimate (which shall include costs of demobilising and remobilising
of any workforce, and any costs to protect the Apparatus “mid-works”) to account for the suspension.
(4) Exolum shall not be liable for any costs, expenses, losses or liabilities the undertaker incurs
as a result of the suspension of any activities under sub-paragraphs (1) to (3) or delays caused by it.
Dispute resolution
78.—(1) The undertaker and Exolum must use their reasonable endeavours to secure the amicable
resolution of any dispute or difference arising between them out of or in connection with this Part
of this Schedule in accordance with the following provisions.
(2) The undertaker and Exolum must each nominate a representative who must meet to try to
resolve the matter. If the matter is not resolved at that level within 10 working days of either the
undertaker or Exolum requesting such a meeting (or such longer period as may be agreed between
the undertaker and Exolum) the matter may at the request of either the undertaker or Exolum be
referred for discussion at a meeting to be attended by a senior executive from each party.
(3) If the meeting between senior executives fails to result in a settlement within 20 working days
of the date of the request for such a meeting (or if it is not possible to convene a meeting within this
period) then, unless otherwise agreed in writing between the undertaker and Exolum, the dispute or
difference will be determined by arbitration in accordance with article 43 (arbitration).
Miscellaneous
79. No failure or delay by a party to exercise any right or remedy provided under this Part of this
Schedule or by law shall constitute a waiver of that or any other right or remedy, nor shall it prevent
or restrict the further exercise of that or any other right or remedy. No single or partial exercise of
such right or remedy shall prevent or restrict the further exercise of that or any other right or remedy.
PART 7
FOR THE PROTECTION OF NATIONAL GRID ELECTRICITY
TRANSMISSION PLC AS ELECTRICITY UNDERTAKER
Application
80.—(1) For the protection of National Grid Electricity Transmission Plc as referred to in this Part
of this Schedule the following provisions have effect, unless otherwise agreed in writing between
the undertaker and National Grid Electricity Transmission Plc.
(2) Subject to sub-paragraph (3) or to the extent otherwise agreed in writing between the
undertaker and National Grid Electricity Transmission Plc, where the benefit of this Order is
transferred or granted to another person under article 36 (consent to transfer the benefit of the Order)
—
(a) any agreement of the type mentioned in sub-paragraph (1) has effect as if it had been made
between National Grid Electricity Transmission Plc and the transferee or grantee (as the
case may be); and
(b) written notice of the transfer or grant must be given to National Grid Electricity
Transmission Plc on or before the date of that transfer or grant.
111Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(3) Sub-paragraph (2) does not apply where the benefit of the Order is transferred or granted to
National Grid Electricity Transmission Plc (but without prejudice to paragraph 94(3)(b)).
Interpretation
81. In this Part of this Schedule—
“1991 Act” means the New Roads and Street Works Act 1991;
“acceptable credit provider” means a bank or financial institution with a credit rating that is
not lower than: (i) “A-” if the rating is assigned by Standard & Poor’s Ratings Group or Fitch
Ratings; and “A3” if the rating is assigned by Moody’s Investors Services Inc.;
“acceptable insurance” means general third party liability insurance effected and maintained
by the undertaker with a combined property damage and bodily injury limit of indemnity of
not less than £50,000,000.00 (fifty million pounds) per occurrence or series of occurrences
arising out of one event. Such insurance shall be maintained (a) during the construction period
of the authorised works; and (b) after the construction period of the authorised works in respect
of any use and maintenance of the authorised works by or on behalf of the undertaker which
constitute specified works and arranged with an insurer whose security/credit rating meets the
same requirements as an “acceptable credit provider”, such insurance shall include (without
limitation)—
(a) a waiver of subrogation and an indemnity to principal clause in favour of National Grid
Electricity Transmission Plc; and
(b) pollution liability for third party property damage and third party bodily damage arising
from any pollution/contamination event with a (sub)limit of indemnity of not less than
£10,000,000.00 (ten million pounds) per occurrence or a series of occurrences arising
out of one event or £20,000,000.00 (twenty million pounds) in aggregate;
“acceptable security” means either—
(a) a parent company guarantee from a parent company in favour of National Grid Electricity
Transmission Plc to cover the undertaker’s liability to National Grid Electricity
Transmission Plc to a total liability cap of £50,000,000.00 (fifty million pounds) (in a
form reasonably satisfactory to National Grid Electricity Transmission Plc and where
required by National Grid Electricity Transmission Plc, accompanied with a legal opinion
confirming the due capacity and authorisation of the parent company to enter into and
be bound by the terms of such guarantee); or
(b) a bank bond or letter of credit from an acceptable credit provider in favour of National
Grid Electricity Transmission Plc to cover the undertaker’s liability to National Grid
Electricity Transmission Plc for an amount of not less than £10,000,000.00 (ten million
pounds) per asset per event up to a total liability cap of £50,000,000.00 (fifty million
pounds) (in a form reasonably satisfactory to National Grid Electricity Transmission Plc);
“alternative apparatus” means appropriate alternative apparatus to the satisfaction of National
Grid Electricity Transmission Plc to enable National Grid Electricity Transmission Plc to fulfil
its statutory functions in a manner no less efficient than previously;
“apparatus” means any electric lines or electrical plant as defined in the Electricity Act
1989(78), belonging to or maintained by National Grid Electricity Transmission Plc together
with any replacement apparatus and such other apparatus constructed pursuant to the Order that
becomes operational apparatus of National Grid Electricity Transmission Plc for the purposes
of transmission, distribution and/or supply and includes any structure in which apparatus is or
will be lodged or which gives or will give access to apparatus;
(78) 1989 c. 29.
112Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
“authorised works” has the same meaning as is given to the term “authorised development”
in article 2(1) of this Order and includes any associated development authorised by the Order
and for the purposes of this Part of this Schedule includes the use and maintenance of the
authorised works and construction of any works authorised by this Schedule;
“commence” and “commencement” in this Part of this Schedule shall include any below
ground surveys, monitoring, ground work operations or the receipt and erection of construction
plant and equipment;
“deed of consent” means a deed of consent, crossing agreement, deed of variation or new
deed of grant agreed between the parties acting reasonably in order to vary or replace existing
easements, agreements, enactments and other such interests so as to secure land rights and
interests as are necessary to carry out, maintain, operate and use the apparatus in a manner
consistent with the terms of this Part of this Schedule;
“functions” includes powers and duties;
“ground mitigation scheme” means a scheme approved by National Grid Electricity
Transmission Plc (such approval not to be unreasonably withheld or delayed) setting out the
necessary measures (if any) for a ground subsidence event;
“ground monitoring scheme” means a scheme for monitoring ground subsidence which sets out
the apparatus which is to be subject to such monitoring, the extent of land to be monitored, the
manner in which ground levels are to be monitored, the timescales of any monitoring activities
and the extent of ground subsidence which, if exceeded, shall require the undertaker to submit
for National Grid Electricity Transmission Plc’s approval a ground mitigation scheme;
“ground subsidence event” means any ground subsidence identified by the monitoring
activities set out in the ground monitoring scheme that has exceeded the level described in the
ground monitoring scheme as requiring a ground mitigation scheme;
“in” in a context referring to apparatus or alternative apparatus in land includes a reference to
apparatus or alternative apparatus under, over, across, along or upon such land;
“Incentive Deduction” means any incentive deduction National Grid Electricity Transmission
Plc receives under its electricity transmission licence which is caused by an event on its
transmission system that causes electricity not to be supplied to a demand customer and which
arises as a result of the authorised works;
“maintain” and “maintenance” shall include the ability and right to do any of the following
in relation to any apparatus or alternative apparatus of National Grid Electricity Transmission
Plc: construct, use, repair, alter, inspect, renew or remove the apparatus;
“National Grid Electricity Transmission Plc” means National Grid Electricity Transmission Plc
(Company Number 2366977) whose registered office is at 1-3 Strand, London, WC2N 5EH
or any successor as a licence holder within the meaning of Part 1 of the Electricity Act 1989;
“National Grid Connection Works” means any part of Work No 4 as described in Schedule 1 of
this Order (authorised development) and shown on sheets 3, 6, 7, 8, 9 and 10 of the works plans;
“NGESO” means as defined in the STC;
“plan or plans” include all designs, drawings, specifications, method statements, soil reports,
programmes, calculations, risk assessments and other documents that are reasonably necessary
properly and sufficiently to describe and assess the works to be executed;
“parent company” means a parent company of the undertaker acceptable to and which shall
have been approved by National Grid Electricity Transmission Plc acting reasonably;
“specified works” means any of the authorised works or activities undertaken in association
with the authorised works which—
113Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(a) will or may be situated over, or within 15 metres measured in any direction of any
apparatus the removal of which has not been required by the undertaker under paragraph
90(2) or otherwise; and/or
(b) may in any way adversely affect any apparatus the removal of which has not been
required by the undertaker under paragraph 90(2) or otherwise; and/or
(c) includes any of the activities that are referred to in development near overhead lines
EN43-8 and HSE’s guidance note 6 “Avoidance of Danger from Overhead Lines”;
“STC” means the System Operator Transmission Owner Code prepared by the electricity
Transmission Owners and NGESO as modified from time to time;
“STC Claims” means any claim made under the STC against National Grid Electricity
Transmission Plc arising out of or in connection with the de-energisation (whereby no
electricity can flow to or from the relevant system through the generator or interconnector’s
equipment) of a generator or interconnector party solely as a result of the de-energisation of
plant and apparatus forming part of National Grid Electricity Transmission Plc’s transmission
system which arises as a result of the authorised works;
“Transmission Owner” means as defined in the STC; and
“undertaker” means the undertaker as defined in article 2(1) of this Order.
National Grid Connection Works
82. The undertaker must not carry out the National Grid Connection Works, or any part of it
except with the approval of National Grid Electricity Transmission Plc in accordance with paragraph
91.
83.—(1) Before beginning to construct any National Grid Connection Works, or any part of it, the
undertaker must submit to National Grid Electricity Transmission Plc plans of the relevant National
Grid Connection Works (or part of it) and such further particulars available to it as National Grid
Electricity Transmission Plc may reasonably request within 21 days of receipt of the plans.
(2) The undertaker must not commence any works to which sub-paragraph (1) applies until
National Grid Electricity Transmission Plc has given written approval of the plan so submitted.
(3) Any approval of National Grid Electricity Transmission Plc requested under paragraph 90
or sub-paragraph (2)—
(a) may be given subject to reasonable conditions; and
(b) must not be unreasonably withheld or delayed.
(4) Any National Grid Connection Works must not be constructed except in accordance with such
plans as may be approved in writing by National Grid Electricity Transmission Plc or as amended
from time to time by agreement between the undertaker and National Grid Electricity Transmission
Plc.
(5) The undertaker will not be required to comply with sub-paragraph (1) where it needs to
carry out emergency works as defined in the 1991 Act but in that case it must give to National
Grid Electricity Transmission Plc notice as soon as is reasonably practicable and a plan of those
works and must comply with sub-paragraphs (2) and (3) insofar as is reasonably practicable in the
circumstances.
84. The undertaker must give to National Grid Electricity Transmission Plc not less than 14 days’
notice in writing of its intention to commence construction of any National Grid Connection Works
and notice in writing of its completion not later than 7 days after the date on which it is completed
and National Grid Electricity Transmission Plc will be entitled by its officer to watch and inspect
the construction of such works.
114Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
85.—(1) If any part of the National Grid Connection Works is constructed otherwise than in
accordance with paragraph 83(4) above National Grid Electricity Transmission Plc may by notice
in writing identify the extent to which the National Grid Connection Works do not comply with
the approved details and request the undertaker at the undertaker’s own expense carry out remedial
works so as to comply with the requirements of paragraph 83(4) of this Part of this Schedule or such
alternative works as may be agreed with National Grid Electricity Transmission Plc or as otherwise
may be agreed between the parties.
(2) Subject to sub-paragraph (3), if within a reasonable period, being not less than 28 days
beginning with the date when a notice under sub-paragraph (1) is served upon the undertaker, the
undertaker has failed to begin taking steps to comply with the requirements of the notice and has not
subsequently made reasonably expeditious progress towards their implementation, National Grid
Electricity Transmission Plc may execute the works specified in the notice and any reasonable
expenditure incurred by National Grid Electricity Transmission Plc in so doing will be recoverable
from the undertaker.
(3) In the event of any dispute as to whether sub-paragraph (1) is properly applicable to any work
in respect of which notice has been served under that sub-paragraph, or as to the reasonableness of
any requirement of such a notice, National Grid Electricity Transmission Plc will not, except in the
case of an emergency, exercise the powers conferred by sub-paragraph (2) until the dispute has been
finally determined in accordance with paragraph 98.
On Street Apparatus
86. Except for paragraphs 87, 92, 93 and 94 of this Schedule which will apply in respect of
the exercise of all or any powers under the Order affecting the rights and apparatus of National
Grid Electricity Transmission Plc, the other provisions of this Schedule do not apply to apparatus
in respect of which the relations between the undertaker and National Grid Electricity Transmission
Plc are regulated by the provisions of Part 3 of the 1991 Act.
Apparatus of National Grid Electricity Transmission Plc in stopped up and temporarily
closed streets
87.—(1) Where any street is temporarily closed under article 12 (temporary closure of streets and
public rights of way) or article 13 (stopping up of public rights of way), if National Grid Electricity
Transmission Plc has any apparatus in the street or accessed via that street National Grid Electricity
Transmission Plc has the same rights in respect of that apparatus as it enjoyed immediately before the
stopping up or closure and the undertaker must grant to National Grid Electricity Transmission Plc,
or procure the granting to National Grid Electricity Transmission Plc of, legal easements reasonably
satisfactory to National Grid Electricity Transmission Plc in respect of such apparatus and access
to it prior to the stopping up or closure of any such street but nothing in this paragraph affects any
right of the undertaker or National Grid Electricity Transmission Plc to require the removal of that
apparatus under paragraph 90 or the power of the undertaker, subject to compliance with this sub-
paragraph, to carry out works under paragraph 92.
(2) Notwithstanding the temporary closure or diversion of any street under the powers of article 12
(temporary closure of streets and public rights of way), National Grid Electricity Transmission Plc
is at liberty at all times to take all necessary access across any such temporarily closed street and to
execute and do all such works and things in, upon or under any such street as may be reasonably
necessary or desirable to enable it to maintain any apparatus which at the time of the closure or
diversion was in that street.
115Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Protective works to buildings
88. The undertaker, in the case of the powers conferred by article 19 (protective works to
buildings), must exercise those powers so as not to obstruct or render less convenient the access to
any apparatus without the written consent of National Grid Electricity Transmission Plc which must
not unreasonably be withheld.
Acquisition of land
89.—(1) Regardless of any provision in this Order or anything shown on the land plans or
contained in the book of reference to the Order, the undertaker may not—
(a) appropriate or acquire or take temporary possession of any land or apparatus; or
(b) appropriate, acquire, extinguish, interfere with or override any easement, other interest
or right and/or apparatus of National Grid Electricity Transmission Plc otherwise than by
agreement.
(2) As a condition of an agreement between the parties in sub-paragraph (1), prior to the carrying
out of any part of the authorised works (or in such other timeframe as may be agreed between
National Grid Electricity Transmission Plc and the undertaker) that is subject to the requirements of
this Part of this Schedule that will cause any conflict with or breach the terms of any easement or other
legal or land interest of National Grid Electricity Transmission Plc or affect the provisions of any
enactment or agreement regulating the relations between National Grid Electricity Transmission Plc
and the undertaker in respect of any apparatus laid or erected in land belonging to or secured by the
undertaker, the undertaker must as National Grid Electricity Transmission Plc reasonably requires
enter into such deeds of consent upon such terms and conditions as may be agreed between National
Grid Electricity Transmission Plc and the undertaker acting reasonably and which must be no less
favourable on the whole to National Grid Electricity Transmission Plc unless otherwise agreed by
National Grid Electricity Transmission Plc, and it will be the responsibility of the undertaker to
procure and/or secure the consent and entering into of such deeds and variations by all other third
parties with an interest in the land at that time who are affected by such authorised works.
(3) Save where otherwise agreed in writing between National Grid Electricity Transmission Plc
and the undertaker, the undertaker and National Grid Electricity Transmission Plc agree that where
there is any inconsistency or duplication between the provisions set out in this Part of this Schedule
relating to the relocation and/or removal of apparatus/including but not limited to the payment of
costs and expenses relating to such relocation and/or removal of apparatus) and the provisions of any
existing easement, rights, agreements and licences granted, used, enjoyed or exercised by National
Grid Electricity Transmission Plc and/or other enactments relied upon by National Grid Electricity
Transmission Plc as of right or other use in relation to the apparatus, then the provisions in this
Schedule shall prevail.
(4) Any agreement or consent granted by National Grid Electricity Transmission Plc under
paragraph 91 or any other paragraph of this Part of this Schedule, shall not be taken to constitute
agreement under sub-paragraph (1).
Removal of apparatus
90.—(1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any
interest in or possesses temporarily any land in which any apparatus is placed, that apparatus must not
be removed under this Part of this Schedule and any right of National Grid Electricity Transmission
Plc to maintain that apparatus in that land must not be extinguished until alternative apparatus has
been constructed, and is in operation to the reasonable satisfaction of National Grid Electricity
Transmission Plc in accordance with sub-paragraphs (2) to (5).
(2) If, for the purpose of executing any works in, on, under or over any land purchased, held,
appropriated or used under this Order, the undertaker requires the removal of any apparatus placed
116Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
in that land, it must give to National Grid Electricity Transmission Plc advance written notice of
that requirement, together with a plan of the work proposed, and of the proposed position of the
alternative apparatus to be provided or constructed and in that case (or if in consequence of the
exercise of any of the powers conferred by this Order National Grid Electricity Transmission Plc
reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3),
secure any necessary consents for the alternative apparatus and afford to National Grid Electricity
Transmission Plc to its satisfaction (taking into account paragraph 91(1) below) the necessary
facilities and rights—
(a) for the construction of alternative apparatus in other land of or land secured by the
undertaker; and
(b) subsequently for the maintenance of that apparatus.
(3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in
other land of or land secured by the undertaker, or the undertaker is unable to afford such facilities
and rights as are mentioned in sub-paragraph (2) in the land in which the alternative apparatus or
part of such apparatus is to be constructed, National Grid Electricity Transmission Plc may in its
sole discretion, on receipt of a written notice to that effect from the undertaker, take such steps as
are reasonable in the circumstances to assist the undertaker to obtain the necessary facilities and
rights in the land in which the alternative apparatus is to be constructed save that this obligation shall
not extend to the requirement for National Grid Electricity Transmission Plc to use its compulsory
purchase powers to this end unless it elects to so do.
(4) Any alternative apparatus to be constructed in land of or land secured by the undertaker under
this Part of this Schedule must be constructed in such manner and in such line or situation as may
be agreed between National Grid Electricity Transmission Plc and the undertaker.
(5) National Grid Electricity Transmission Plc must, after the alternative apparatus to be provided
or constructed has been agreed, and subject to a written diversion agreement having been entered
into between the parties and the grant to National Grid Electricity Transmission Plc of any such
facilities and rights as are referred to in sub-paragraphs (2) or (3), proceed without unnecessary
delay to construct and bring into operation the alternative apparatus and subsequently to remove any
apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
Facilities and rights for alternative apparatus
91.—(1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker
affords to or secures for National Grid Electricity Transmission Plc facilities and rights in land for the
construction, use, maintenance and protection of alternative apparatus in substitution for apparatus
to be removed, those facilities and rights must be granted upon such terms and conditions as may
be agreed between the undertaker and National Grid Electricity Transmission Plc and must be no
less favourable on the whole to National Grid Electricity Transmission Plc than the facilities and
rights enjoyed by it in respect of the apparatus to be removed unless otherwise agreed by National
Grid Electricity Transmission Plc.
(2) If the facilities and rights to be afforded by the undertaker in respect of any alternative
apparatus, and the terms and conditions subject to which those facilities and rights are to be granted,
are less favourable on the whole to National Grid Electricity Transmission Plc than the facilities
and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to
which those facilities and rights are subject the matter may be referred to arbitration in accordance
with paragraph 98 of this Part of this Schedule and the arbitrator must make such provision for the
payment of compensation by the undertaker to National Grid Electricity Transmission Plc as appears
to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
117Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Retained apparatus: protection
92.—(1) Not less than 56 days before the commencement of any specified works the undertaker
must submit to National Grid Electricity Transmission Plc a plan of the works to be executed and seek
from National Grid Electricity Transmission Plc details of the underground extent of their electricity
assets.
(2) In relation to the specified works the plan to be submitted to National Grid Electricity
Transmission Plc under sub-paragraph (1) must include a method statement and describe—
(a) the exact position of the works;
(b) the level at which these are proposed to be constructed or renewed;
(c) the manner of their construction or renewal including details of excavation, positioning
of plant;
(d) the position of all apparatus;
(e) by way of detailed drawings, every alteration proposed to be made to or close to any such
apparatus;
(f) any intended maintenance regimes;
(g) an assessment of risks of rise of earth issues; and
(h) a ground monitoring scheme, where required.
(3) In relation to any works which will or may be situated on, over, under or within 10 metres
of any part of the foundations of an electricity tower or between any two or more electricity towers,
the plan to be submitted under sub-paragraph (1) must, in addition to the matters set out in sub-
paragraph (2), include a method statement describing—
(a) details of any cable trench design including route, dimensions, clearance to pylon
foundations;
(b) demonstration that pylon foundations will not be affected prior to, during and post
construction;
(c) details of load bearing capacities of trenches;
(d) details of any cable installation methodology including access arrangements, jointing bays
and backfill methodology;
(e) a written management plan for high voltage hazard during construction and ongoing
maintenance of any cable route;
(f) written details of the operations and maintenance regime for any cable, including
frequency and method of access;
(g) assessment of earth rise potential if reasonably required by National Grid Electricity
Transmission Plc’s engineers; and
(h) evidence that trench bearing capacity is to be designed to support overhead line
construction traffic of up to and including 26 tonnes in weight.
(4) The undertaker must not commence any works to which sub-paragraphs (2) or (3) apply until
National Grid Electricity Transmission Plc has given written approval of the plan so submitted.
(5) Any approval of National Grid Electricity Transmission Plc required under sub-
paragraph (4)—
(a) may be given subject to reasonable conditions for any purpose mentioned in sub-
paragraphs (6) or (8); and
(b) must not be unreasonably withheld or delayed.
(6) In relation to any work to which sub-paragraphs (2) or (3) apply, National Grid Electricity
Transmission Plc may require such modifications to be made to the plans as may be reasonably
118Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
necessary for the purpose of securing its apparatus against interference or risk of damage, for the
provision of protective works or for the purpose of providing or securing proper and convenient
means of access to any apparatus.
(7) Works executed under sub-paragraphs (2) or (3) must be executed in accordance with the
plan, submitted under sub-paragraph (1) or as relevant sub-paragraph (6), as approved or as amended
from time to time by agreement between the undertaker and National Grid Electricity Transmission
Plc and in accordance with such reasonable requirements as may be made in accordance with sub-
paragraphs (6) or (8) by National Grid Electricity Transmission Plc for the alteration or otherwise
for the protection of the apparatus, or for securing access to it, and National Grid Electricity
Transmission Plc will be entitled to watch and inspect the execution of those works.
(8) Where National Grid Electricity Transmission Plc requires any protective works to be carried
out by itself or by the undertaker (whether of a temporary or permanent nature) such protective
works, inclusive of any measures or schemes required and approved as part of the plan approved
pursuant to this paragraph, must be carried out to National Grid Electricity Transmission Plc’s
satisfaction prior to the commencement of any authorised works for which protective works are
required and National Grid Electricity Transmission Plc shall give notice its requirement for such
works within 42 days of the date of submission of a plan pursuant to this paragraph (except in an
emergency).
(9) If National Grid Electricity Transmission Plc in accordance with sub-paragraphs (6) or (8)
and in consequence of the works proposed by the undertaker, reasonably requires the removal of any
apparatus and gives written notice to the undertaker of that requirement, sub-paragraphs (1) to (3)
and (6) to (8) apply as if the removal of the apparatus had been required by the undertaker under
paragraph 90(2).
(10) Nothing in this paragraph precludes the undertaker from submitting at any time or from
time to time, but in no case less than 56 days before commencing the execution of any authorised
works, a new plan, instead of the plan previously submitted, and having done so the provisions of
this paragraph shall apply to and in respect of the new plan.
(11) The undertaker will not be required to comply with sub-paragraph (1) where it needs to
carry out emergency works as defined in the 1991 Act but in that case it must give to National Grid
Electricity Transmission Plc notice as soon as is reasonably practicable and a plan of those works
and must comply with sub-paragraphs (6), (7) and (8) insofar as is reasonably practicable in the
circumstances and comply with sub-paragraph (11) at all times.
(12) At all times when carrying out any works authorised under the Order, the undertaker must
comply with National Grid Electricity Transmission Plc’s policies for development near overhead
lines EN43-8 and HSE’s guidance note 6 “Avoidance of Danger from Overhead Lines”.
Expenses
93.—(1) Save where otherwise agreed in writing between National Grid Electricity Transmission
Plc and the undertaker and subject to the following provisions of this paragraph, the undertaker must
pay to National Grid Electricity Transmission Plc within 30 days of receipt of an itemised invoice
or claim from National Grid Electricity Transmission Plc all charges, costs and expenses reasonably
anticipated within the following 3 months or reasonably and properly incurred by National Grid
Electricity Transmission Plc in, or in connection with, the inspection, removal, relaying or replacing,
alteration or protection of any apparatus or the construction of any new or alternative apparatus
which may be required in consequence of the execution of any authorised works including without
limitation—
(a) any costs reasonably incurred by or compensation properly paid by National Grid
Electricity Transmission Plc in connection with the acquisition of rights or the exercise
of statutory powers for such apparatus including without limitation all costs incurred by
119Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
National Grid Electricity Transmission Plc as a consequence of National Grid Electricity
Transmission Plc—
(i)using its own compulsory purchase powers to acquire any necessary rights under
paragraph 90(3); or
(ii)exercising any compulsory purchase powers in the Order transferred to or benefitting
National Grid Electricity Transmission Plc;
(b) in connection with the cost of the carrying out of any diversion work or the provision of
any alternative apparatus, where no written diversion agreement is otherwise in place;
(c) the cutting off of any apparatus from any other apparatus or the making safe of redundant
apparatus;
(d) the approval of plans;
(e) the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining
and renewing permanent protective works; and
(f) the survey of any land, apparatus or works, the inspection and monitoring of works or the
installation or removal of any temporary works reasonably necessary in consequence of
the execution of any such works referred to in this Part of this Schedule.
(2) There will be deducted from any sum payable under sub-paragraph (1) the value of any
apparatus removed under the provisions of this Part of this Schedule and which is not re-used as part
of the alternative apparatus, that value being calculated after removal.
(3) If in accordance with the provisions of this Part of this Schedule—
(a) apparatus of better type, of greater capacity or of greater dimensions is placed in
substitution for existing apparatus of worse type, of smaller capacity or of smaller
dimensions; or
(b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is
placed at a depth greater than the depth at which the existing apparatus was situated,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus
at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement,
is not determined by arbitration in accordance with paragraph 98 to be necessary, then, if such
placing involves cost in the construction of works under this Part of this Schedule exceeding that
which would have been involved if the apparatus placed had been of the existing type, capacity
or dimensions, or at the existing depth, as the case may be, the amount which apart from this
sub-paragraph would be payable to National Grid Electricity Transmission Plc by virtue of sub-
paragraph (1) will be reduced by the amount of that excess save to the extent that it is not possible
in the circumstances to obtain the existing type of apparatus at the same capacity and dimensions or
place at the existing depth in which case full costs will be borne by the undertaker.
(4) For the purposes of sub-paragraph (3)—
(a) an extension of apparatus to a length greater than the length of existing apparatus will
not be treated as a placing of apparatus of greater dimensions than those of the existing
apparatus; and
(b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary,
the consequential provision of a jointing chamber or of a manhole will be treated as if it
also had been agreed or had been so determined.
(5) Any amount which apart from this sub-paragraph would be payable to National Grid
Electricity Transmission Plc in respect of works by virtue of sub-paragraph (1) will, if the works
include the placing of apparatus provided in substitution for apparatus placed more than 7 years and
6 months earlier so as to confer on National Grid Electricity Transmission Plc any financial benefit
120Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the
amount which represents that benefit.
Indemnity
94.—(1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction
of any works authorised by this Part of this Schedule or in consequence of the construction, use,
maintenance or failure of any of the authorised works by or on behalf of the undertaker or in
consequence of any act or default of the undertaker (or any person employed or authorised by him)
in the course of carrying out such works, including without limitation works carried out by the
undertaker under this Part of this Schedule or any subsidence resulting from any of these works,
any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of
which is not reasonably necessary in view of its intended removal for the purposes of the authorised
works) or property of National Grid Electricity Transmission Plc, or there is any interruption in any
service provided, or in the supply of any goods, by National Grid Electricity Transmission Plc, or
National Grid Electricity Transmission Plc becomes liable to pay any amount to any third party, the
undertaker will—
(a) bear and pay on demand accompanied by an invoice or claim from National Grid
Electricity Transmission Plc the cost reasonably and properly incurred by National Grid
Electricity Transmission Plc in making good such damage or restoring the supply; and
(b) indemnify National Grid Electricity Transmission Plc for any other expenses, loss,
demands, proceedings, damages, claims, penalty or costs incurred by or recovered from
National Grid Electricity Transmission Plc, by reason or in consequence of any such
damage or interruption or National Grid Electricity Transmission Plc becoming liable to
any third party and including STC Claims or an Incentive Deduction other than arising
from any default of National Grid Electricity Transmission Plc.
(2) The fact that any act or thing may have been done by National Grid Electricity Transmission
Plc on behalf of the undertaker or in accordance with a plan approved by National Grid Electricity
Transmission Plc or in accordance with any requirement of National Grid Electricity Transmission
Plc or under its supervision will not (unless sub-paragraph (3) applies), excuse the undertaker from
liability under the provisions of sub-paragraph (1) unless National Grid Electricity Transmission Plc
fails to carry out and execute the works properly with due care and attention and in a skilful and
workman like manner or in a manner that does not accord with the approved plan.
(3) Nothing in sub-paragraph (1) shall impose any liability on the undertaker in respect of—
(a) any damage or interruption to the extent that it is attributable to the neglect or default of
National Grid Electricity Transmission Plc, its officers, servants, contractors or agents;
(b) any authorised works and/or any other works authorised by this Part of this Schedule
carried out by National Grid Electricity Transmission Plc as an assignee, transferee or
lessee of the undertaker with the benefit of the Order pursuant to section 156 of the
Planning Act 2008 or article 36 (consent to transfer the benefit of the Order) subject to the
proviso that once such works become apparatus (“new apparatus”), any authorised works
yet to be executed and not falling within this sub-paragraph 3(b) will be subject to the full
terms of this Part of this Schedule including this paragraph 94; and/or
(c) any indirect or consequential loss of any third party (including but not limited to loss of use,
revenue, profit, contract, production, increased cost of working or business interruption)
arising from any such damage or interruption, which is not reasonably foreseeable.
(4) National Grid Electricity Transmission Plc must give the undertaker reasonable notice of any
such third party claim or demand and no settlement, admission of liability or compromise must,
unless payment is required in connection with a statutory compensation scheme, be made without
first consulting the undertaker and considering their representations.
121Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(5) National Grid Electricity Transmission Plc must, in respect of any matter covered by the
indemnity given by the undertaker in this paragraph, at all times act reasonably and in the same
manner as it would as if settling third party claims on its own behalf from its own funds.
(6) National Grid Electricity Transmission Plc must use its reasonable endeavours to mitigate
and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under
this paragraph applies where it is within National Grid Electricity Transmission Plc’s reasonable
ability and control to do so and which expressly excludes any obligation to mitigate liability arising
from third parties which is outside of National Grid Electricity Transmission Plc’s control and if
reasonably requested to do so by the undertaker National Grid Electricity Transmission Plc must
provide an explanation of how the claim has been minimised, where relevant.
(7) Not to commence construction (and not to permit the commencement of such construction)
of the authorised works on any land owned by National Grid Electricity Transmission Plc or in
respect of which National Grid Electricity Transmission Plc has an easement or wayleave for its
apparatus or any other interest or to carry out any works within 15 metres of National Grid Electricity
Transmission Plc’s apparatus until the following conditions are satisfied—
(a) unless and until National Grid Electricity Transmission Plc is satisfied acting reasonably
(but subject to all necessary regulatory constraints) that the undertaker has first provided
the acceptable security (and provided evidence that it shall maintain such acceptable
security for the construction period of the authorised works referred to in sub-paragraph (7)
from the proposed date of commencement of construction of those works) and National
Grid Electricity Transmission Plc has confirmed the same to the undertaker in writing; and
(b) unless and until National Grid Electricity Transmission Plc is satisfied acting reasonably
(but subject to all necessary regulatory constraints) that the undertaker has procured
acceptable insurance (and provided evidence to National Grid Electricity Transmission
Plc that it shall maintain such acceptable insurance for the construction period
of the authorised works referred to in sub-paragraph (7) from the proposed date
of commencement of construction of those works) and National Grid Electricity
Transmission Plc has confirmed the same in writing to the undertaker.
(8) In the event that the undertaker fails to comply with sub-paragraph (7) of this Part of this
Schedule, nothing in this Part of this Schedule shall prevent National Grid Electricity Transmission
Plc from seeking injunctive relief (or any other equitable remedy) in any court of competent
jurisdiction.
Enactments and agreements
95. Save to the extent provided for to the contrary elsewhere in this Part of this Schedule or by
agreement in writing between National Grid Electricity Transmission Plc and the undertaker nothing
in this Part of this Schedule affects the provisions of any enactment or agreement regulating the
relations between the undertaker and National Grid Electricity Transmission Plc in respect of any
apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
Co-operation
96.—(1) Where in consequence of the proposed construction of any part of the authorised works,
the undertaker or National Grid Electricity Transmission Plc requires the removal of apparatus under
paragraph 90(2) or National Grid Electricity Transmission Plc makes requirements for the protection
or alteration of apparatus under paragraph 92, the undertaker shall use its best endeavours to co-
ordinate the execution of the works in the interests of safety and the efficient and economic execution
of the authorised works and taking into account the need to ensure the safe and efficient operation of
National Grid Electricity Transmission Plc’s undertaking and National Grid Electricity Transmission
Plc shall use its best endeavours to co-operate with the undertaker for that purpose.
122Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(2) For the avoidance of doubt whenever National Grid Electricity Transmission Plc’s consent,
agreement or approval is required in relation to plans, documents or other information submitted
by the undertaker or the taking of action by the undertaker, it must not be unreasonably withheld
or delayed.
Access
97. If in consequence of the agreement reached in accordance with paragraph 89(1) or the powers
granted under this Order the access to any apparatus is materially obstructed, the undertaker must
provide such alternative means of access to such apparatus as will enable National Grid Electricity
Transmission Plc to maintain or use the apparatus no less effectively than was possible before such
obstruction.
Arbitration
98. Save for differences or disputes arising under paragraphs 90(2), 90(4), 91(1) and 92 any
difference or dispute arising between the undertaker and National Grid Electricity Transmission
under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker
and National Grid Electricity Transmission Plc, be determined by arbitration in accordance with
article 43 (arbitration).
Notices
99. Notwithstanding article 45 (service of notices), any plans submitted to National Grid
Electricity Transmission Plc by the undertaker pursuant to paragraph 92 must be submitted using
the LSBUD system (https://lsbud.co.uk/) or to such other address as National Grid Electricity
Transmission Plc may from time to time appoint instead for that purpose and notify to the undertaker
in writing.
PART 8
FOR THE PROTECTION OF NORTHERN POWERGRID (YORKSHIRE) PLC
100. For the protection of Northern Powergrid (Yorkshire) Plc the following provisions have
effect, unless otherwise agreed in writing between the undertaker and Northern Powergrid.
101. In this Part of this Schedule—
“1991 Act” means the New Roads and Street Works Act 1991;
“alternative apparatus” means alternative apparatus adequate to enable Northern Powergrid to
fulfil its statutory functions in a manner not less efficient than previously;
“apparatus” means apparatus (as defined in article 2(1) (interpretation) of the Order) belonging
to or maintained by Northern Powergrid and includes any structure in which apparatus is or is
to be lodged or which gives or will give access to apparatus;
“authorised works” means so much of the works authorised by this Order which affect existing
Northern Powergrid’s apparatus within the Order limits;
“functions” includes powers and duties;
“in”, in a context referring to apparatus or alternative apparatus in land, includes a reference
to apparatus or alternative apparatus under, over or upon land;
“Order” means the Fenwick Solar Farm Order 2026;
“Order limits” means as defined in article 2(1) of the Order;
123Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
“Northern Powergrid” means Northern Powergrid (Yorkshire) Plc (Company Number
04112320) whose registered office is at Lloyds Court, 78 Grey Street, Newcastle upon Tyne,
NE1 6AF; and
“plan” includes all designs, drawings, specifications, method statements, soil reports,
programmes, calculations, risk assessments and other documents that are reasonably necessary
properly and sufficiently to describe the works to be executed and must include any measures
proposed by the undertaker to ensure the grant of sufficient land or rights in land necessary
to mitigate the impacts of the works on the apparatus or Northern Powergrid’s undertaking
within the Order limits.
102. This Part of this Schedule does not apply to apparatus in respect of which the relations
between the undertaker and Northern Powergrid are regulated by the provisions of Part 3 (street
works in England and Wales) of the 1991 Act.
103. Regardless of the temporary prohibition or restriction of use of streets under the powers
conferred by article 12 (temporary closure of streets and public rights of way), the undertaker must
not prevent Northern Powergrid from taking all necessary access across any such street and to
execute and do all such works and things in, upon or under any such street as may be reasonably
necessary or desirable to enable it to maintain any apparatus which at the time of the prohibition or
restriction was in that street.
104. Regardless of any provision in the Order or anything shown on the land plans, or contained
in the book of reference, the undertaker must not acquire any apparatus, or override any easement
or other interest of Northern Powergrid otherwise than by agreement with Northern Powergrid, such
agreement not to be unreasonably withheld or delayed.
105. Regardless of any provision in the Order or anything shown on the land plans or contained
in the book of reference, the undertaker must not interfere with any communications cables or
equipment used by Northern Powergrid in relation to its apparatus or acquire or interfere with rights
or interests supporting the use, maintenance or renewal of such equipment including any easements
other than by agreement of Northern Powergrid (such agreement not to be unreasonably withheld
or delayed) and having regard to Northern Powergrid’s existing and known future requirements for
such land or interests.
106.—(1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any
interest in any land in which any apparatus is placed or over which access to any apparatus is enjoyed
or requires that Northern Powergrid’s apparatus is relocated or diverted, that apparatus must not
be removed under this Part of this Schedule, and any right of Northern Powergrid to maintain that
apparatus in that land and to gain access to it must not be extinguished, until alternative apparatus
has been constructed and is in operation, and access to it has been provided pursuant to a completed
easement, or other form of written agreement in a form reasonably acceptable to Northern Powergrid
which shall include rights to retain and subsequently maintain the apparatus being replaced or
diverted for the lifetime of that alternative apparatus, all to the reasonable satisfaction of Northern
Powergrid in accordance with sub-paragraphs (2) to (5).
(2) If, for the purpose of executing any works in, on or under any land purchased, held,
appropriated or used under this Order, the undertaker requires the removal of any apparatus placed
in that land, the undertaker must give to Northern Powergrid 42 days’ advance written notice of that
requirement, together with a plan and section of the work proposed, and of the proposed position
of the alternative apparatus to be provided or constructed and in that case (or if in consequence of
the exercise of any of the powers conferred by this Order Northern Powergrid reasonably needs to
remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), afford to Northern
Powergrid the necessary facilities and rights for the construction of alternative apparatus in other
land of the undertaker and subsequently for the maintenance of that apparatus.
124Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than
in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as
are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such
apparatus is to be constructed—
(a) the undertaker must in the first instance use reasonable endeavours to acquire through
voluntary negotiations all necessary land interests or rights as Northern Powergrid may
reasonably require for the relocation and construction of alternative apparatus and must
use reasonable endeavours to procure through voluntary negotiations all necessary rights
to access and maintain Northern Powergrid’s apparatus and alternative apparatus thereafter
the terms of such access and maintenance to be agreed by Northern Powergrid (acting
reasonably);
(b) in the event that the undertaker is not able to procure the necessary land interest or
rights referred to in the sub-paragraph 106(3)(a) Northern Powergrid must, on receipt of
a written notice to that effect from the undertaker and subject to paragraph 109, as soon
as reasonably practicable use reasonable endeavours to procure the necessary facilities
and rights in the land in which the alternative apparatus is to be constructed save that
this obligation shall not extend to the requirement for Northern Powergrid to use its
compulsory purchase powers to this end; and
(c) in the event that neither the undertaker nor Northern Powergrid can acquire all necessary
land interest or rights which Northern Powergrid may reasonably require for the relocation
and construction of alternative apparatus pursuant to paragraph 106(3)(a) and/or (b), the
undertaker shall use its compulsory purchase powers under the Order (where available)
unless otherwise agreed by arbitration.
(4) Any alternative apparatus to be constructed in land of the undertaker under this Part of this
Schedule must be constructed in such manner and in such line or situation as may be agreed between
Northern Powergrid and the undertaker or in default of agreement settled by arbitration in accordance
with article 43 (arbitration) of the Order.
(5) Northern Powergrid must, after the alternative apparatus to be provided or constructed has
been agreed or settled by arbitration in accordance with article 43 (arbitration) of the Order, and
after the grant to Northern Powergrid of any such facilities and rights as are referred to in sub-
paragraphs (2) or (3), proceed without unnecessary delay to construct and bring into operation the
alternative apparatus and subsequently to remove any apparatus required by the undertaker to be
removed under the provisions of this Part of this Schedule.
107.—(1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker
affords to Northern Powergrid facilities and rights for the construction and maintenance in land of the
undertaker of alternative apparatus in substitution for apparatus to be removed, those facilities and
rights must be granted upon such terms and conditions as may be agreed between the undertaker and
Northern Powergrid or in default of agreement settled by arbitration in accordance with article 43
(arbitration) of the Order.
(2) If the facilities and rights to be afforded by the undertaker in respect of any alternative
apparatus, and the terms and conditions subject to which those facilities and rights are to be granted,
are in the opinion of the arbitrator less favourable on the whole to Northern Powergrid than the
facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and
conditions to which those facilities and rights are subject, the arbitrator must make such provision for
the payment of compensation by the undertaker to Northern Powergrid as appears to the arbitrator
to be reasonable having regard to all the circumstances of the particular case.
108.—(1) Not less than 56 days before starting the execution of any works in, on or under any
land purchased, held, appropriated or used under the Order that are near to (including conducting
any activities whether intentionally or unintentionally, through for example ground or machinery
125Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
collapse, which may affect Northern Powergrid’s apparatus or encroach on safety distances to live
equipment) or will or may affect, any apparatus the removal of which has not been required by
the undertaker under paragraph 106(2), the undertaker must submit to Northern Powergrid a plan,
section and description of the works to be executed and any such information as Northern Powergrid
reasonably requires relating to those works.
(2) Those works must be executed only in accordance with the plan, section and description
submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be
made in accordance with sub-paragraph (3) by Northern Powergrid for the alteration or otherwise
for the protection of the apparatus, or for securing access to it, and Northern Powergrid is entitled
to watch and inspect the execution of those works.
(3) Any requirements made by Northern Powergrid under sub-paragraph (2) must be made within
a period of 35 days beginning with the date on which a plan, section and description under sub-
paragraph (1) are submitted to it.
(4) If Northern Powergrid in accordance with sub-paragraph (2) and in consequence of the works
proposed by the undertaker, reasonably requires the removal of any apparatus and gives written
notice to the undertaker of that requirement, sub-paragraphs (1) to (3) apply as if the removal of the
apparatus had been required by the undertaker under paragraph 106.
(5) Nothing in this paragraph precludes the undertaker from submitting at any time or from time
to time, but in no case less than 35 days before commencing the execution of any works, a new
plan, section and description instead of the plan, section and description previously submitted, and
having done so the provisions of this paragraph apply to and in respect of the new plan, section and
description.
(6) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency
but in that case it must give to Northern Powergrid notice as soon as is reasonably practicable and
a plan, section and description of those works as soon as reasonably practicable subsequently and
must comply with sub-paragraph (2) in so far as is reasonably practicable in the circumstances.
109.—(1) Subject to the following provisions of this paragraph, the undertaker must repay
to Northern Powergrid within 51 days of receipt of an itemised invoice or claim the reasonable
and proper expenses, costs or charges incurred by Northern Powergrid in, or in connection with,
the inspection, removal, alteration or protection of any apparatus or the construction of any new
apparatus which may be required in consequence of the execution of any such works as are referred
to in paragraphs 106(2) and 106(3) including within limitation—
(a) any costs reasonably incurred or compensation properly paid in connection with the
acquisition of rights or the exercise of statutory powers for such apparatus including
without limitation in the event that it is agreed Northern Powergrid elects to use
compulsory purchase powers to acquire any necessary rights under paragraph 106(3) all
costs reasonably incurred as a result of such action;
(b) in connection with the cost of the carrying out of any diversion work or the provision of
any alternative apparatus;
(c) the cutting off of any apparatus from any other apparatus or the making safe of redundant
apparatus;
(d) the approval of plans;
(e) the carrying out of protective works, plus a capitalised sum to cover the reasonable cost
of adequately maintaining and renewing permanent protective works; and
(f) the survey of any land, apparatus or works, the inspection and monitoring of works or the
installation or removal of any temporary works reasonably necessary in consequence of
the execution of any such works referred to in this Part of this Schedule.
(2) Where any payment falls due pursuant to paragraph 109(1), Northern Powergrid must—
126Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(a) provide an itemised invoice or reasonable expenses claim to the undertaker;
(b) provide “reminder letters” to the undertaker for payment to be made within the 50 days
on the following days after the invoice or reasonable expenses claim to the undertaker—
(i)15 days (“reminder letter 1”);
(ii)29 days (“reminder letter 2”);
(iii)43 days (“reminder letter 3”);
(c) be entitled to commence debt proceedings to recover any unpaid itemised invoice or
reasonable expenses claim after 51 days of receipt of the same where payment has not
been made.
(3) There is to be deducted from any sum payable under sub-paragraph (1) the value of any
apparatus removed under the provisions of this Part of this Schedule, that value being calculated
after removal and for the avoidance of doubt, if the apparatus removed under the provisions of this
Part of this Schedule has nil value, no sum will be deducted from the amount payable under sub-
paragraph (1) if in accordance with the provisions of this Part of this Schedule—
(a) apparatus of better type, of greater capacity or of greater dimensions is placed in
substitution for existing apparatus of worse type, of smaller capacity or of smaller
dimensions; or
(b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is
placed at a depth greater than the depth at which the existing apparatus was,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus
at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not
determined by arbitration in accordance with article 43 (arbitration) of the Order to be necessary,
then, if such placing involves cost in the construction of works under this Part of this Schedule
exceeding that which would have been involved if the apparatus placed had been of the existing
type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart
from this sub-paragraph would be payable to Northern Powergrid by virtue of sub-paragraph (1) is
to be reduced by the amount of that excess, save where it is not possible on account of reasonable
project time limits communicated in a reasonable timeframe to the undertaker and/or supply issues
to obtain the existing type of operations, capacity, dimensions or place at the existing depth in which
case full costs shall be borne by the undertaker.
(4) For the purposes of sub-paragraph (3)—
(a) an extension of apparatus to a length greater than the length of existing apparatus is not
to be treated as a placing of apparatus of greater dimensions than those of the existing
apparatus where such extension is required in consequence of the execution of any such
works as are referred to in paragraph 106(2); and
(b) where the provision of a joint in a cable is agreed, or is determined to be necessary, the
consequential provision of a jointing chamber or of a manhole is to be treated as if it also
had been agreed or had been so determined.
110.—(1) Subject to sub-paragraph (2) and (3), if by reason or in consequence of the construction
of any of the works referred to in paragraph 106(2), or in consequence of the maintenance or failure
of any of the authorised works by or on behalf of the undertaker or in consequence of any act or
default of the undertaker (or any person employed or authorised by it) in the course of carrying out
such works, including without limitation works carried out by the undertaker under this Part of this
Schedule or any subsidence resulting from any of these works any damage is caused to any apparatus
or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view
of its intended removal for the purposes of those works) or property of Northern Powergrid, or there
is any interruption in any service provided by Northern Powergrid, or Northern Powergrid becomes
127Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
liable to pay any amount to a third party as a consequence of any default, negligence or omission by
the undertaker in carrying out the authorised works, the undertaker must—
(a) bear and pay the cost reasonably incurred by Northern Powergrid in making good such
damage or restoring the supply; and
(b) indemnify Northern Powergrid for other reasonable expenses, loss, damages, penalty,
proceedings, claims or costs incurred by or recovered from Northern Powergrid,
by reason or in consequence of any such damage or interruption or Northern Powergrid becoming
liable to any third party.
(2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any
damage or interruption to the extent that it is attributable to the act, neglect or default of Northern
Powergrid, its officers, employees, servants, contractors or agents.
(3) Northern Powergrid must give the undertaker reasonable notice of any such claim or demand
and no settlement or compromise is to be made without the consent of the undertaker which, if it
withholds such consent, has the sole conduct of any settlement or compromise or of any proceedings
necessary to resist the claim or demand.
(4) Northern Powergrid must use its reasonable endeavours to mitigate in whole or in part and
to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this
paragraph 110 applies. If requested to do so by the undertaker, Northern Powergrid must provide an
explanation of how the claim has been minimised or details to substantiate any cost or compensation
claimed pursuant to sub-paragraph (1). The undertaker shall only be liable under this paragraph 110
for claims reasonably incurred by Northern Powergrid.
(5) Subject to sub-paragraphs (3) and (4), the fact that any act or thing may have been done by
Northern Powergrid on behalf of the undertaker or in accordance with a plan approved by Northern
Powergrid or in accordance with any requirement of Northern Powergrid as a consequence of the
authorised development or under its supervision will not (unless sub-paragraph (2) applies), excuse
the undertaker from liability under the provisions of this sub-paragraph (5) where the undertaker
fails to carry out and execute the works properly with due care and attention and in a skilful and
workman like manner or in a manner that does not materially accord with the approved plan or as
otherwise agreed between the undertaker and Northern Powergrid.
111. Nothing in this Part of this Schedule affects the provisions of any enactment or agreement
regulating the relations between the undertaker and Northern Powergrid in respect of any apparatus
laid or erected in land belonging to the undertaker on the date on which the Order is made.
112. Any difference under the provisions of this Part of this Schedule, unless otherwise agreed
is to be referred to and settled by arbitration in accordance with article 43 (arbitration) of the Order.
113. Where in consequence of the proposed construction of any of the authorised development,
the undertaker or Northern Powergrid requires the removal of apparatus under paragraph 106 or
otherwise or Northern Powergrid makes requirements for the protection or alteration of apparatus
under paragraph 108, the undertaker shall use reasonable endeavours to co-ordinate the execution
of the works in the interests of safety and the need to ensure the safe and efficient operation of
Northern Powergrid’s apparatus taking into account the undertaker’s desire for the efficient and
economic execution of the authorised development and the undertaker and Northern Powergrid shall
use reasonable endeavours to co-operate with each other for those purposes.
114. If in consequence of an agreement reached in accordance with paragraph 103 or the powers
granted under this Order the access to any apparatus or alternative apparatus is materially obstructed,
the undertaker shall provide such alternative means of access to such apparatus or alternative
apparatus as will enable Northern Powergrid to maintain or use the said apparatus no less effectively
than was possible before such obstruction.
128Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
115. The plans submitted to Northern Powergrid by the undertaker pursuant to this Part of this
Schedule must be sent to Northern Powergrid at property@northernpowergrid.com or such other
address as Northern Powergrid may from time to time appoint instead for that purpose and notify
to the undertaker in writing.
116. Prior to carrying out any works within the Order limits, Northern Powergrid must give
written notice of the proposed works to the undertaker, such notice to include full details of the
location of the proposed works, their anticipated duration, access arrangements, depths of the works,
and any other information that may impact upon the works consented by the Order.
117. Where practicable, the Undertaker and Northern Powergrid will make reasonable efforts to
liaise and co-operate in respect of information that is relevant to the safe and efficient construction,
operation and maintenance of the authorised development. Such liaison shall be carried out where
any works are—
(a) within 15m of any above ground apparatus; or
(b) within 15m of any apparatus and are to a depth of between 0-4m below ground level.
SCHEDULE 15 Article 46
PROCEDURE FOR DISCHARGE OF REQUIREMENTS
Interpretation
1. In this Schedule—
“requirement consultee” means any body or authority named in a requirement as a body to be
consulted by the relevant planning authority in discharging that requirement;
“start date” means the date of the notification given by the Secretary of State under
paragraph 4(2)(c); and
“working day” means any day other than a Saturday, Sunday or English bank or public holiday.
Applications made under requirement
2.—(1) Where an application has been made to the relevant planning authority for any consent,
agreement or approval required by a requirement, the undertaker must also simultaneously submit
a copy of that application to any requirement consultee.
(2) Where an application has been made to the relevant planning authority for any consent,
agreement or approval required by a requirement the relevant planning authority must give notice
to the undertaker of its decision on the application within a period of eight weeks beginning with
the later of—
(a) the day immediately following that on which the application is received by the authority;
(b) the day immediately following that on which further information has been supplied by the
undertaker under paragraph 3; or
(c) such longer period that is agreed in writing by the undertaker and the relevant planning
authority.
(3) Subject to paragraph 4, in the event that the relevant planning authority does not determine
an application within the period set out in sub-paragraph (2), the relevant planning authority is to
be taken to have granted all parts of the application (without any condition or qualification) at the
end of that period.
129Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(4) Any application made to the relevant planning authority pursuant to sub-paragraph (2) must
include a statement to confirm whether it is likely that the subject matter of the application will give
rise to any materially new or materially different environmental effects compared to those in the
environmental statement and if it will then it must be accompanied by information setting out what
those effects are.
(5) Where an application has been made to the relevant planning authority for any consent,
agreement or approval required by a requirement included in this Order and the relevant planning
authority does not determine the application within the period set out in sub-paragraph (2) and is
accompanied by a report pursuant to sub-paragraph (4) which states that the subject matter of such
application is likely to give rise to any materially new or materially different environmental effects
compared to those in the environmental statement then the application is to be taken to have been
refused by the relevant planning authority at the end of that period.
Further information and consultation
3.—(1) In relation to any application to which this Schedule applies, the relevant planning
authority may request such reasonable further information from the undertaker as is necessary to
enable it to consider the application.
(2) In the event that the relevant planning authority considers such further information to be
necessary and the provision governing or requiring the application does not specify that consultation
with a requirement consultee is required, the relevant planning authority must, within 20 working
days of receipt of the application, notify the undertaker in writing specifying the further information
required.
(3) If the provision governing or requiring the application specifies that consultation with a
requirement consultee is required, the relevant planning authority must issue the consultation to the
requirement consultee within 10 working days of receipt of the application, and must notify the
undertaker in writing specifying any further information the relevant planning authority considers
necessary or that is requested by the requirement consultee within 10 working days of receipt of
such a request and in any event within 20 working days of receipt of the application (or such other
period as is agreed in writing between the undertaker and the relevant planning authority).
(4) In the event that the relevant planning authority does not give notification as specified in sub-
paragraph (2) or (3) it is deemed to have sufficient information to consider the application and is not
thereafter entitled to request further information without the prior agreement of the undertaker.
(5) Where further information is requested under this paragraph in relation to part only of an
application, that part is to be treated as separate from the remainder of the application for the purposes
of calculating time periods in paragraph 2 and paragraph 3.
Appeals
4.—(1) The undertaker may appeal in the event that—
(a) the relevant planning authority refuses an application for any consent, agreement or
approval required by a requirement included in this Order or grants it subject to conditions;
(b) the relevant planning authority is deemed to have refused an application pursuant to
paragraph 2(5);
(c) on receipt of a request for further information pursuant to paragraph 3 the undertaker
considers that either the whole or part of the specified information requested by the
relevant planning authority is not necessary for consideration of the application; or
(d) on receipt of any further information requested, the relevant planning authority notifies the
undertaker that the information provided is inadequate and requests additional information
which the undertaker considers is not necessary for consideration of the application.
130Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(2) The steps to be followed in the appeal process are as follows—
(a) any appeal by the undertaker must be made within 30 working days of the date of the
notice of the decision or determination, or (where no determination has been made) the
expiry of the time period set out in paragraph (2), giving rise to the appeal referred to in
sub-paragraph (1);
(b) the undertaker must submit the appeal documentation to the Secretary of State and must on
the same day provide copies of the appeal documentation to the relevant planning authority
and any requirement consultee;
(c) as soon as is practicable after receiving the appeal documentation, the Secretary of State
must appoint a person to consider the appeal (“the appointed person”) and must notify
the appeal parties of the identity of the appointed person and the address to which all
correspondence for the attention of the appointed person should be sent;
(d) the discharging authority and any consultee (if applicable) must submit their written
representations together with any other representations to the appointed person in respect
of the appeal within 14 days of the start date and must ensure that copies of their written
representations and any other representations as sent to the appointed person are sent to
each other and to the applicant on the day on which they are submitted to the appointed
person; the undertaker may make any counter-submissions to the appointed person within
10 working days of receipt of written representations pursuant to sub-paragraph (d);
(e) the appointed person must make their decision and notify it to the appeal parties, with
reasons, as soon as reasonably practicable and in any event within 30 working days of the
deadline for the receipt of counter-submissions pursuant to sub-paragraph (e); and
(f) the appointment of the person pursuant to sub-paragraph (c) may be undertaken by a person
appointed by the Secretary of State for this purpose instead of by the Secretary of State.
(3) In the event that the appointed person considers that further information is necessary to enable
the appointed person to consider the appeal they must, within five working days of the appointed
person’s appointment, notify the appeal parties in writing specifying the further information required.
(4) Any further information required pursuant to sub-paragraph (3) must be provided by the
relevant party to the appointed person and the other appeal parties on the date specified by the
appointed person (the “specified date”), and the appointed person must notify the appeal parties of
the revised timetable for the appeal on or before that day. The revised timetable for the appeal must
require submission of written representations to the appointed person within 10 working days of the
specified date, but otherwise the process and time limits set out in sub-paragraphs (d) to (f) of sub-
paragraph (2) apply.
(5) The appointed person may—
(a) allow or dismiss the appeal; or
(b) reverse or vary any part of the decision of the relevant planning authority (whether the
appeal relates to that part of it or not),
and may deal with the application as if it had been made to them in the first instance.
(6) The appointed person may proceed to a decision on an appeal taking into account only such
written representations as have been sent within the relevant time limits.
(7) The appointed person may proceed to a decision even though no written representations have
been made within the relevant time limits, if it appears to them that there is sufficient material to
enable a decision to be made on the merits of the case.
(8) The decision of the appointed person on an appeal is to be final and binding on the parties,
unless proceedings are brought by a claim for judicial review.
131Document Generated: 2026-03-11
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(9) If an approval is given by the appointed person pursuant to this Schedule, it is to be deemed
to be an approval for the purpose of Schedule 2 (requirements) as if it had been given by the relevant
planning authority. The relevant planning authority may confirm any determination given by the
appointed person in identical form in writing but a failure to give such confirmation (or a failure to
give it in identical form) is not to be taken to affect or invalidate the effect of the appointed person’s
determination.
(10) Save where a direction is given pursuant to sub-paragraph (11) requiring the costs of the
appointed person to be paid by the relevant planning authority, the reasonable costs of the appointed
person must be met by the undertaker.
(11) On application by the relevant planning authority or the undertaker, the appointed person
may give directions as to the costs of the appeal parties and as to the parties by whom the costs of
the appeal are to be paid. In considering whether to make any such direction and the terms on which
it is to be made, the appointed person must have regard to advice on planning appeals and award
costs published in Planning Practice Guidance: Appeals (March 2014) or any circular or guidance
which may from time to time replace it.
Fees
5.—(1) Where an application is made to the relevant planning authority for written consent,
agreement or approval in respect of a requirement, or any other consent or approval under the articles
of the Order, the applicant shall pay the costs in accordance with the agreement entered into by
the undertaker and City of Doncaster Council on 20 August 2025, or any subsequent replacement
agreement as to costs.
EXPLANATORY NOTE
(This note is not part of the Order)
This Order authorises Fenwick Solar Project Limited (company number 13705886) (referred to in
this Order as the undertaker) to construct, operate, maintain and decommission a ground mounted
solar photovoltaic generating station with a gross electrical output capacity over 50 megawatts and
associated development. The Order would permit the undertaker to acquire, compulsorily or by
agreement, land and rights in land and to use land for this purpose.
A copy of the Order plans and the book of reference mentioned in the Order and certified in
accordance with article 41 (certification of plans and documents, etc) of this Order may be inspected
free of charge during working hours at City of Doncaster Council at Civic Building, Waterdale,
Doncaster, DN1 3BU.
132