See Full Document Text
S T A T U T O R Y I N S T R U M E N T S
2026 No. 441
INFRASTRUCTURE PLANNING
The Morgan Offshore Wind Project Generation Assets
(Correction) Order 2026
Made - - - - 8th April 2026
Coming into force 9th April 2026
The Morgan Offshore Wind Project Generation Assets Order 2025(a) (“the Morgan Offshore
Wind Project Generation Assets Order 2025”) which granted development consent within the
meaning of the Planning Act 2008(b) (“the Act”) contains correctable errors within the meaning
of paragraph 1 of Schedule 4 to the Act.
In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant
period(c), the Secretary of State received a written request from the applicant(d) for the correction
of errors and omissions in the Morgan Offshore Wind Project Generation Assets Order 2025.
In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed
each relevant local planning authority(e) for the area in which the land to which the Morgan
Offshore Wind Project Generation Assets Order 2025 relates is situated that the request has been
received.
The Secretary of State in exercise of the powers conferred by paragraphs 1(4) and (8) of Schedule
4 to the Act makes the following Order.
Citation and commencement
1. This Order may be cited as the Morgan Offshore Wind Project Generation Assets
(Correction) Order 2026 and comes into force on 9th April 2026.
Correction of original order
2. The Morgan Offshore Wind Project Generation Assets Order 2025 is corrected as set out in
the table in the Schedule to this Order, in which—
(a) column 1 sets out where the correction is to be made;
(b) column 2 sets out how the correction is to be made; and
(a) S.I. 2025/1012.
(b) 2008 c. 29. Paragraph 1 of Schedule 4 was amended by paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the
Localism Act 2011 (c. 20). There are other amendments to paragraph 1 that are not relevant to this Order.
(c) The relevant period is defined in paragraph 1(6)(a) of Schedule 4 to the Act.
(d) The term “applicant” is defined in paragraph 4 of Schedule 4 to the Act.
(e) As defined in paragraph 4 of Schedule 4 to the Act.(c) column 3 sets out the text to be substituted, inserted, or omitted.
Signed by authority of the Secretary of State for Energy Security and Net Zero
John Wheadon
Head of Energy Infrastructure Planning Delivery
8th April 2026 Department for Energy Security and Net Zero
2SCHEDULE
Article 2
(1) Where the correction (2) How the correction (3) Text to be substituted, inserted, or
is to be made is to be made omitted
Article 7(11) After “may amend” for “deemed marine licence 1 or licence 2”
“the deemed marine
licence” substitute
Schedule 2, paragraph For “parameters in “undertaker may not undertake Work No. 1
2(4) Table 1 do not allow in a manner which would”
works in relation to
wind turbine generators
that” substitute
Schedule 2, paragraph For “two assessed” “maximum design”
2(4) substitute
Schedule 2, paragraph After “the maximum “and”
3(2)(d) heights of any wind
turbine generator, and
offshore substation
platform to be
constructed;” insert
Schedule 2, paragraph For “constructed.” “constructed;”
3(2)(e) substitute
Schedule 2, paragraph For “the Defence “(3) The Defence Infrastructure
3(2) Infrastructure Organisation must be notified”
Organisation must be
notified” substitute
Schedule 2, paragraph After “turbine “or any offshore substation platform”
5(3)(a) generator” omit
Schedule 2, paragraph For “operator.” “operator; and”
5(4)(a)(iii) substitute
Schedule 2, paragraph In the definition of “other”
5(4)(b) “operator” after “or
any” omit
Schedule 2, paragraph After “in accordance “(4)”
6(2)(c) with sub-paragraph” for
“(5)” substitute
Schedule 2, paragraph In the definition of “company number”
6(5) “operator” for
“Company Number”
substitute
Schedule 2, paragraph In the definition of “other”
6(5) “operator” after “or
any” omit
Schedule 2, paragraph For “Approved ATS “approved ATS mitigation scheme”
7(2) Mitigation Scheme”
substitute
Schedule 2, paragraph After “turbine “or any offshore substation platform”
7(3)(a) generator” omit
Schedule 2, paragraph After “communication “such scheme to remain in place
7(4)(b) systems” omit throughout the lifetime of the authorised
development and for so long as any part of
the authorised development remains in
3situ”
Schedule 2, paragraph For “Operator” “operator”
9(1) substitute
Schedule 2, paragraph After “approved” omit “appropriate”
9(2)
Schedule 3, Part 1, In the definition of “and”
paragraph 1(1) “wind turbine
generator” after
“foundation or
transition piece;” insert
Schedule 3, Part 2, For “parameters in “undertaker may not undertake Work No. 1
paragraph 10(2) Table 2 do not allow in a manner which would”
works in relation to
wind turbine generators
that” substitute
Schedule 3, Part 2, For “two assessed” “maximum design”
paragraph 10(2) substitute
Schedule 3, Part 2, After “with condition “and”
paragraph 15(1)(a)(ii) 26;” insert
Schedule 3, Part 2, For “(ee)” – “(hh)” “(iv)” – “(vii)”
Condition 20(1)(e)(iii) substitute
Schedule 4, Part 2, After “detail on “; and”
Condition 20(1)(c)(ii) construction
monitoring” insert
Schedule 4, Part 2, For “(ee)” – “(hh)” “(iv)” – “(vii)”
Condition 20(1)(e)(iii) substitute
Schedule 4, Part 2, After “if required;” “and”
Condition 20(1)(c)(iii) omit
EXPLANATORY NOTE
(This note is not part of the Order)
This Order corrects errors in the Morgan Offshore Wind Project Generation Assets Order 2025
(S.I. 2025/870), a development consent order made under the Planning Act 2008, following a
request made under paragraph 1(5)(a) of Schedule 4 to that Act.
4