**Executive Summary**
The Union Cabinet has approved Phase 2A of the Ahmedabad Metro Rail Project, spanning 6.032 km from Koteshwar Road to the Airport at an estimated cost of Rs. 2,169.04 crore. Announced on June 10, 2026, the project includes five new stations and aims to expand the active Ahmedabad-Gandhinagar metro network to 77.63 km. This expansion is designed to enhance urban connectivity, support upcoming international sporting events in 2029 and 2030, and stimulate regional economic growth.
**Key Points / Main Content**
**Project Specifications**
* **Corridor Scope:** Development of a 6.032 km corridor connecting Koteshwar Road to the Airport.
* **Station Details:** Total of 05 stations, consisting of 04 elevated stations and 01 underground station.
* **Station Names:** Ashram Road, Koteshwar Prachin Mandir, Sabarmati River, Sardar Nagar, and Airport.
* **Network Expansion:** On completion, the total active Ahmedabad-Gandhinagar Metro Rail Network will reach 77.63 km.
**Financial and Employment Outlook**
* **Completion Cost:** Total cost is Rs. 2,169.04 crore, which includes Interest during Construction (IDC).
* **Job Creation:** The project will generate approximately 2,000 jobs during peak construction and 500 jobs for Operation & Maintenance.
**Strategic Benefits**
* **Connectivity:** Provides seamless transit access to the airport, residential areas, and commercial hubs.
* **Urban Mobility:** Reduces traffic congestion, travel times, and improves overall road safety.
* **Environmental Impact:** Aims to significantly reduce carbon emissions by providing an alternative to fossil fuel-based transport.
* **Event Support:** Enhances infrastructure near planned sports facilities for the World Police Games 2029 and Commonwealth Games 2030.
**Impact Analysis**
**Commuters and Residents**
**Impact:**
Residents gain more equitable access to public transport, reduced commute times, and improved safety. The extension provides a direct, efficient link to the airport and railway stations.
**Action Required:**
Transition from traditional road transport to the metro network to benefit from reduced travel times and enhanced mobility.
**Local Businesses and Investors**
**Impact:**
Increased connectivity is expected to stimulate local economic activity and attract investment into previously less accessible regions near the new stations.
**Action Required:**
Identify and leverage development and investment opportunities in commercial hubs situated along the new corridor.
**Labor Force and Job Seekers**
**Impact:**
Creation of 2,000 temporary construction roles and 500 permanent positions in operation and maintenance.
**Action Required:**
Monitor and apply for employment opportunities arising during the peak construction phase and subsequent operational stages.
**Event Organizers (World Police Games 2029 / Commonwealth Games 2030)**
**Impact:**
The project provides critical transit infrastructure to support the logistics and visitor influx associated with these international events.
**Action Required:**
Incorporate the Phase 2A metro corridor into transport and logistics planning for the upcoming games.
Key Entities Referenced
Ahmedabad Metro Rail Project Phase 2(A): The primary infrastructure initiative approved to develop a 6.032 km metro corridor connecting Koteshwar Road to the Airport with five stations.
Ahmedabad and Gandhinagar: The central urban locations in Gujarat where the metro rail network is being expanded to integrate residential, commercial, and transit hubs.
World Police Games 2029 and Commonwealth Games 2030: Key international sporting events for which the metro expansion aims to provide seamless transit and infrastructure support.
Cabinet
Cabinet approves Ahmedabad Metro Rail project
Phase 2A (Koteshwar Road to Airport corridor)
प्रव तथ: 10 JUN 2026 1:59PM by PIB Delhi
The Union Cabinet chaired by the Prime Minister Shri Narendra Modi has approved Phase 2(A) of
Ahmedabad Metro Rail Project with corridor for a length of 6.032 Km with 05 stations (04 Elevated and
01 underground). On operationalisation of Phase 2(A), Ahmedabad-Gandhinagar will have 77.63 Km of
active Metro Rail Network. The names of stations in the Phase 2(A) Corridor are- Ashram Road,
Koteshwar Prachin Mandir, Sabarmati River, Sardar Nagar and Airport.
The total completion cost including IDC (Interest during Construction) for the project will be Rs.2,169.04
crore.
Benefits and Bolstering Growth:
The Phase 2(A) of Ahmedabad Metro Rail Project represents a significant advancement in the city’s
infrastructure development. Phase 2(A) acts as a major expansion of the Metro Rail Network in the city.
Enhanced Connectivity:
Phase 2(A) of the Ahmedabad Metro Project envisages the development of approximately 6.032 km of
new metro corridor, aimed at substantially enhancing public transportation by providing seamless
connectivity to the airport and linking key residential and commercial areas that presently lack efficient
transit access.
This phase aims to seamlessly integrate key zones, including residential & Commercial hubs with existing
Ahmedabad-Gandhinagar corridor. Further, likelihood of sports facilities also being developed in the
vicinity for the World Police Games 2029 and Commonwealth Games 2030.
By bridging these vital areas with the metro network, Phase 2(A) will not only enhance connectivity but
also stimulate economic activity, tourism, and ease urban mobility for both residents and visitors.
Reduction in Traffic Congestion: Metro Rail as an efficient alternate road transport and with Phase 2(A)
as an extension of the Metro Rail network to the Airport, will be particularly impactful inside Ahmedabad.
Reduction in road traffic can lead to smoother movement of vehicles, reduction in travel time, increasing
overall road safety etc.
Environmental Benefits: With the addition of Phase 2(A) of Ahmedabad Metro Rail Project and increase
in overall Metro Rail Network in Ahmedabad & Gandhinagar cities, can significantly reduce carbon
emissions compared to traditional fossil fuel-based transport.
Economic Growth: Reduced travel times and improved access to different parts of the city such as
Airport, Railway Stations and Bus Depots can enhance productivity by allowing individuals to reach their
workplaces and destinations more efficiently. Also, the enhanced connectivity can stimulate local
businesses, especially in areas near new metro stations which can also attract investment and development
in previously less accessible regions.Social Impact: The expansion of Phase 2(A) Metro Rail network in Ahmedabad will provide more
equitable access to public transport, benefiting diverse socio-economic groups and reducing transport
disparities which will contribute to a higher quality of life by reducing commute times and improving
access to essential services.
The Phase 2(A) of Ahmedabad Metro Rail Project is set to be a transformative development for the city. It
promises to deliver enhanced connectivity, reduced traffic congestion, environmental benefits, economic
growth, and improved quality of life. By addressing key urban challenges and providing a foundation for
future expansion, Phase 2(A) will play a crucial role in shaping the city's development trajectory and
sustainability.
The Ahmedabad Metro Phase 2A will generate employment of around 2,000 persons during the peak
period of construction activity and 500 persons are likely to work during Operation & Maintenance of the
system.
Route Map:
***