Date: 2026-03-10Category: Press ReleaseState: Union GovernmentCountry: India
Cabinet approves Revised Cost estimate for the Construction of Greenfield Connectivity to Jewar International Airport from Delhi-Faridabad-Ballabhgarh-Sohna Spur of the Delhi-Mumbai Expressway on Hybrid Annuity Mode in Uttar Pradesh and Haryana
**Executive Summary**
The Cabinet Committee on Economic Affairs (CCEA) has approved a revised total capital cost of Rs. 3630.77 crore for the construction of Greenfield Connectivity to Jewar International Airport. This 31.42 km project, to be executed on a Hybrid Annuity Mode in Uttar Pradesh and Haryana, aims to provide high-speed connectivity to the airport, enhancing economic growth and logistics efficiency in the National Capital Region. Approximately 11 km will be an elevated highway, with the Haryana Government contributing Rs. 450 crore towards its cost.
**Key Points / Main Content**
* **Project Approval and Cost:**
* The CCEA has approved a revised total capital cost of Rs. 3630.77 crore for the Greenfield Connectivity to Jewar International Airport.
* The project will be implemented on a Hybrid Annuity Mode.
* **Project Scope and Connectivity:**
* The project involves the construction of a 31.42 km long corridor providing direct and high-speed connectivity from South Delhi, Faridabad, and Gurugram to Jewar International Airport.
* This corridor is designed to promote economic growth and logistics efficiency within the National Capital Region (NCR).
* Approximately 11 km of the project will be developed as an elevated highway.
* **Strategic Importance and Integration:**
* The corridor intersects with the Eastern Peripheral Expressway, Yamuna Expressway, and Dedicated Freight Corridor (DFC), facilitating multimodal transport convergence.
* It is considered a strategic enabler for urban transformation, regional connectivity, and national logistics efficiency.
* Construction is deemed imperative to unlock the full potential of the Jewar Airport-Delhi-Mumbai Expressway corridor and ensure sustainable urban development in Faridabad.
* The elevated highway segment forms a critical link between DND-Ballabhgarh Bypass and Jewar International Airport, connecting it to the Delhi-Mumbai Expressway.
* The corridor passes through an area designated for high-density urban development and future infrastructure expansion under the Faridabad Master Plan 2031.
* **Financial Contribution:**
* The additional cost for the proposed elevated corridor is Rs. 689.24 crore.
* The Government of Haryana has agreed to bear Rs. 450 crore of the cost for the elevated corridor.
**Impact Analysis**
**Stakeholder:** National Capital Region (NCR)
* **Impact:** Enhanced economic growth and improved logistics efficiency due to direct, high-speed connectivity to Jewar International Airport. Facilitates urban transformation and regional connectivity.
* **Action Required:** None explicitly stated in the document.
**Stakeholder:** Jewar International Airport
* **Impact:** Improved accessibility and passenger/cargo movement, thereby unlocking its full potential.
* **Action Required:** None explicitly stated in the document.
**Stakeholder:** Faridabad
* **Impact:** Contributes to sustainable urban development and is positioned to benefit from future infrastructure expansion under the Faridabad Master Plan 2031.
* **Action Required:** None explicitly stated in the document.
**Stakeholder:** Government of Haryana
* **Impact:** Financial commitment of Rs. 450 crore towards the elevated corridor.
* **Action Required:** Bear Rs. 450 crore for the elevated corridor, as agreed.
**Stakeholder:** Uttar Pradesh
* **Impact:** Benefits from the Greenfield connectivity project to Jewar International Airport within its state.
* **Action Required:** None explicitly stated in the document.
Key Entities Referenced
Cabinet Committee on Economic Affairs (CCEA): The approving body for the revised cost estimate of the project.
Delhi-Mumbai Expressway: The main expressway which the new connectivity spur is part of.
Jewar International Airport: The destination airport for the Greenfield Connectivity project.
Uttar Pradesh and Haryana: The states where the project corridor will be implemented.
Dedicated Freight Corridor (DFC): An existing infrastructure that the new corridor intersects, indicating multimodal integration.
Cabinet Committee on Economic Affairs (CCEA)
Cabinet approves Revised Cost estimate for the
Construction of Greenfield Connectivity to Jewar
International Airport from Delhi-Faridabad-
Ballabhgarh-Sohna Spur of the Delhi-Mumbai
Expressway on Hybrid Annuity Mode in Uttar
Pradesh and Haryana
Posted On: 10 MAR 2026 4:29PM by PIB Delhi
The Cabinet Committee on Economic Affairs, chaired by the Prime Minister Shri Narendra Modi, today
has approved the Revised Total Capital Cost of Rs.3630.77 crore for the Construction of Greenfield
Connectivity to Jewar International Airport from Delhi-Faridabad-Ballabhgarh-Sohna Spur of the Delhi-
Mumbai Expressway on Hybrid Annuity Mode in the States of Uttar Pradesh and Haryana.
This 31.42 km long project corridor will provide direct and high-speed connectivity from South Delhi,
Faridabad and Gurugram to Jewar International Airport, thereby promoting economic growth and logistics
efficiency across National Capital Region (NCR).
The corridor intersects Eastern Peripheral Expressway, Yamuna Expressway, and Dedicated Freight
Corridor (DFC), enabling multimodal transport convergence. The elevated corridor is not merely a
structural enhancement but a strategic enabler for urban transformation, regional connectivity, and
national logistics efficiency. Its construction is imperative to unlock the full potential of the Jewar
Airport–Delhi–Mumbai Expressway corridor and to ensure sustainable urban development in Faridabad.
About 11 km length of this project is to be developed as elevated highway which forms a critical segment
of the Greenfield connectivity between DND-Ballabhgarh Bypass and Jewar International Airport, linking
it to the Delhi-Mumbai Expressway. This corridor traverses the area earmarked for high-density urban
development and future infrastructure expansion under the Faridabad Master Plan, 2031. The additional
cost of the proposed elevated corridor is Rs.689.24 crore and the Government of Haryana has agreed to
bear Rs.450 crore for elevated corridor.
Project Alignment Map for Greenfield Connectivity to Jewar International Airport from Delhi-
Faridabad-Ballabhgarh-Sohna Spur of the Delhi-Mumbai***
MJPS/ST
(Release ID: 2237576) Visitor Counter : 864