Call for Proposals (CfP) for Selection
of an Executing Agency(ies) for
Preparation of Detailed Project
Reports (DPRs) for Green Hydrogen
Hubs in India under Component-B1
of the National Green Hydrogen
Mission
CfP No.: SECI/C&P/EOI/17/0002/25-26 Dated 17.09.2025
Tender Search Code on ISN-ETS: SECI-2025-TN000021
Solar Energy Corporation of India Limited
(A Government of India Enterprise)
6th Floor, Plate-B, NBCC Office Block Tower-2,
East Kidwai Nagar, New Delhi – 110023
Tel: 011 - 24666200, e-mail: contracts@seci.co.inBID INFORMATION SHEET
The brief details of the CfP are as under:
NAME OF WORK/ Selection of Executing Agency(ies) for Preparation of
(A) BRIEF SCOPE OF Detailed Project Reports (DPRs) under Component-B1 of
WORK/ JOB NGHM for Establishing Green Hydrogen Hubs in India
(B) CfP NO. & DATE SECI/C&P/EOI/17/0002/25-26 dated 17.09.2025
SINGLE BID SYSTEM
Yes
TYPE OF BIDDING
(C)
SYSTEM
TWO BID SYSTEM
E-TENDER Yes
(D) TYPE OF TENDER
MANUAL
COMPLETION/
(E) As mentioned in CfP Document
CONTRACT PERIOD
APPLICABLE Yes
DOCUMENT FEE/
NOT APPLICABLE
COST OF CfP
(F)
DOCUMENT Amount: INR 5000/- (Indian Rupees Five Thousand only)
(NON-REFUNDABLE) + applicable GST, for each applicant, to be submitted
through NEFT/ RTGS transfer in the account of SECI
along with the response to CfP
APPLICABLE
Yes
NOT APPLICABLE
TENDER
(G)
MANAGEMENT FEE
Rs. 25,000/- (Indian Rupees Twenty-five Thousand only)
+ applicable GST, for each applicant, to be submitted
through NEFT/RTGS transfer in the account of SECI,
along with the response to CfP.
APPLICABLE
EARNEST MONEY
(H)
DEPOSIT (EMD)
NOT APPLICABLE Yes
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 1 of 53
for Preparation of Detailed Project Reports (DPRs)APPLICABLE
PERFORMANCE
(I)
BANK GUARANTEE
NOT APPLICABLE Yes
DATE, TIME &
Scheduled as per NIT on ISN-ETS portal and/or SECI
(J) VENUE OF PRE-BID
website.
MEETING
OFFLINE & ONLINE
PROPOSAL-
(K) As per NIT on ISN-ETS portal
SUBMISSION
DEADLINE
PROPOSAL
(L) As per NIT on ISN-ETS portal
OPENING
M/s Electronic Tender.com (India) Pvt. Ltd.
Gurugram
Contact Person: ISN-ETS Support Team
CONTACT DETAILS
(M) Customer Support: +91-124-4229071,4229072
OF ISN-ETS PORTAL
(From 10:00 Hrs. to 18:00 Hrs. on all working Days i.e.
Monday to Friday except Govt. Holidays)
Email: support@isn-ets.com
NAME, Sh. Atulya Kumar Naik
DESIGNATION, Executive Director (Contracts & Procurement)
ADDRESS AND Solar Energy Corporation of India Limited
(N) OTHER DETAILS 6th Floor, Plate-B, NBCC Office Block Tower-2, East
(FOR SUBMISSION Kidwai Nagar, New Delhi - 110 023
OF RESPONSE TO Contact No.: 011 24666200
CfP) Email: contracts@seci.co.in
1) Sh. Pratik Prasun
DETAILS OF DGM (C&P)
PERSONS TO BE Contact No.: 011-24666237
CONTACTED IN pratikpr@seci.co.in
(O)
CASE OF ANY 2) Sh. Biblesh Meena
ASSISTANCE Sr. Manager (C&P)
REQUIRED Contact No.: 011-24666270
biblesh@seci.co.in
▪ Proposals must be submitted strictly in accordance with Section-2 and 3 of the CfP,
depending upon Type of Tender as mentioned at Clause no. (D) of Bid Information Sheet.
▪ Applicants are required to quote strictly as per terms and conditions of the CfP documents
and not to stipulate any deviations/ exceptions.
▪ Any applicant, who meets the Qualifying Requirement and wishes to submit their
proposal against this CfP, may download the complete CfP document along with its
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 2 of 53
for Preparation of Detailed Project Reports (DPRs)amendment(s) and clarifications if any, from ISN-ETS Portal (https://www.bharat-
electronictender.com) and/or SECI website (www.seci.co.in) and submit their Proposal
complete in all respect as per terms & conditions of CfP Document on or before the due
date of Proposal submission.
▪ Clarification(s)/ Corrigendum(s), if any, shall also be available on the above referred
websites.
Applicants are requested to remain updated for any notices/ amendments/ clarifications
etc. to the CfP document through the websites https://www.bharat-electronictender.com
and www.seci.co.in. No separate notifications will be issued for such notices/ amendments/
clarifications etc. in the print media or individually. Intimation regarding notification on
the above shall be updated on www.seci.co.in and the details will be available only from
https://www.bharat-electronictender.com.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 3 of 53
for Preparation of Detailed Project Reports (DPRs)SECTION 1. INTRODUCTION AND INVITATION FOR PROPOSALS
1. Background and Introduction
1.1. Solar Energy Corporation of India Limited (hereinafter referred as “SECI” or as
“Owner”) is a “Navratna” CPSU under the administrative control of the Ministry of New
and Renewable Energy (MNRE), Government of India (GoI), to facilitate the
implementation of the National Solar Mission (NSM) and achievement of targets set
therein. It is the only CPSU solely dedicated to the renewable energy (RE) sector. In the
present outlook of the RE sector, especially solar energy, SECI has a major role to play
in the sector’s development. The Company is responsible for implementation of a number
of schemes of GoI for large-scale grid-connected projects under NSM, solar park scheme
and grid-connected solar rooftop scheme along with a host of other specialised schemes.
In addition, SECI is also developing its own Solar, Floating & Hybrid innovative RE
Projects & is providing consultancy services to various major CPSUs for developing
turnkey basis RE Projects. The company also has Category I Power Trading License and
is active in this domain through trading of RE power from projects set up under the
schemes being implemented by it.
1.2. The National Green Hydrogen Mission was launched on 4th January 2023 with an outlay
of Rs. 19,744 Crore with an aim to make India a Global Hub for production, usage and
export of Green hydrogen (GH2) and its derivatives.
1.3. Major components of the Mission include inter – alia Incentives for Electrolyser
Manufacturing and Green Hydrogen Production under the Strategic Interventions for
Green Hydrogen Transition (SIGHT) Programme, Pilot Projects, Research &
Development, Framework of Regulations, Codes and Standards, and Skill Development
Programme, etc.
1.4. Along with other initiatives, the Mission envisages to develop large scale Hydrogen Hubs
which will act as a foundation for development of Hydrogen eco-system and will act as
backbone of the decarbonisation efforts in the country.
1.5. Given the technical and logistical challenges inherent in transporting hydrogen over long
distances, a cluster-based production and utilization model would enhance the viability
of Green Hydrogen projects in the initial years. This would, in turn, enable economies of
scale and convergence of key infrastructure requirements in geographically
proximate areas.
1.6. In line with the above, MNRE has issued “ Revised Scheme Guidelines for setting up
Hydrogen Valley Innovation Cluster (HVIC) and Green Hydrogen Hubs in India under
the National Green Hydrogen Mission” vide F No. 353/12/2025-NT dated 27.06.2025.
SECI has been nominated as the Implementing Agency for Component-B1 of the above
referred Scheme.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 4 of 53
for Preparation of Detailed Project Reports (DPRs)1.7. Under Component-B1 of referred guidelines under the National Green Hydrogen
Mission, the MNRE intends to support States/UTs in preparing Detailed Project Reports
(DPRs) for the development of Green Hydrogen Hubs. If any State Government/Central
Govt. has any proposal for preparation of a DPR by a PSU or Autonomous Body under
Component-B1, the Proposal. It may kindly be submitted to SECI under this CfP.
Alternatively, If a proposal is received from a project proponent, it should have the
endorsement of the concerned state government
1.8. This document has been prepared in line with the above Guidelines, including subsequent
amendments and clarifications issued thereof, until the last date of proposal submission.
1.9. As part of the above scheme, SECI hereby invites proposals from the prospective
Applicants to become the Executing Agency (EA) for Preparation of Detailed Project
Reports (DPRs) for Green Hydrogen Hubs under Component-B1 of the National Green
Hydrogen Mission. The selection of Executing Agencies (EA) shall be done in a
transparent manner as per the criteria laid down in the Guidelines and this document. In
case of any discrepancies, provisions mentioned in the scheme Guidelines shall prevail.
1.10. The salient features of this scheme are as follows:
i. Hydrogen hub is an identified geographical region where there exists a network of
Hydrogen producers, end use (domestic or export) with sufficient supporting
infrastructure of Hydrogen storage, processing and transportation.
ii. Hydrogen hub might be located in land or near ports to enable exports of Green
Hydrogen (GH ) and its derivatives. Potential locations for such hubs would be
2
regions having cluster of refineries/fertilizer production plants and other end use
industries in close vicinity.
iii. The Hydrogen hub should have a planned/announced capacity of at least 1, 00,000
Metric Tonnes per annum. Higher production capacity will get priority.
iv. Leveraging existing infrastructure for Hydrogen production, transportation, storage
and utilization will be encouraged.
2. Objective of the CfP
2.1. SECI hereby invites proposals from the prospective applicants to become the EA,
preferably having proven track record / prior experience in preparation of DPRs for
renewable energy, hydrogen, or industrial projects and clear understanding of how to
develop a successful hydrogen hub.
2.2. The objective of this CfP is to engage a competent Executing Agency to support the
formulation of comprehensive DPRs covering technical, commercial, financial,
environmental, and regulatory aspects required for the establishment of Green Hydrogen
Hubs across selected locations in India.
2.3. The selected agency shall be responsible for preparing a DPR as Scope of work
mentioned in clause 4 under section 2:
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 5 of 53
for Preparation of Detailed Project Reports (DPRs)2.4. Under Component-B1 of the National Green Hydrogen Mission, the Ministry of New
and Renewable Energy (MNRE) intends to support States/UTs in preparing Detailed
Project Reports (DPRs) for the development of Green Hydrogen Hubs. The objective is
to identify potential clusters and infrastructure needs for demand creation and supply
linkages of green hydrogen and its derivatives, including integration with renewable
energy sources.
2.5. Preparation of DPRs for Green Hydrogen Hubs proposed to be set up in each state shall
be supported with a cap of Rs. 3 Crore per DPR per state.
3. Invitation for Proposals
3.1. A Single Stage, Single Envelope Bidding Procedure will be adopted and will proceed as
detailed in this CfP Document. Bidding will be conducted through the competitive
bidding procedures as per the provisions of this CfP. The respective rights of SECI and
the Applicants shall be governed by the CfP Documents.
3.2. SECI has issued this document in the capacity of Implementing Agency as mentioned in
the Guidelines. As per the Guidelines, a Steering Committee under the chairmanship of
Secretary MNRE and comprising members viz., Mission Director-NGHM and any other
members as nominated, shall be responsible for overall monitoring and implementation
of the scheme and shall suggest modification and course corrections for its successful
implementation. In case of any ambiguity in the interpretation of any of the provisions
of the scheme, the decision of MNRE shall be final. The Steering Committee will also
facilitate/ recommend measures to resolve difficulties if any.
3.3. Interested applicants have to necessarily register themselves on the portal
https://www.bharat-electronictender.com (“ETS portal”) through M/s Electronic
Tender.com (India) Pvt. Limited to participate in the bidding under this CfP. It shall be
the sole responsibility of the interested applicants to get themselves registered at the
aforesaid portal for which they are required to contact M/s Electronic Tender.com (India)
Pvt. Limited, Gurugram to complete the registration formalities. Contact details of ISN-
ETS is mentioned on the Proposal Information Sheet. All required documents and
formalities for registering on ISN-ETS are mentioned in the subsequent CfP documents.
3.4. They may obtain further information regarding this IFB from the registered office of
SECI at the address given on the Proposal Information Sheet from 10:00 hours to 17:00
hours on all working days.
3.5. For proper uploading of the Proposals on the ETS portal, it shall be the sole responsibility
of the applicants to apprise themselves adequately regarding all the relevant procedures
and provisions as detailed in the portal as well as by contacting M/s Electronic
Tender.com (India) Pvt. Limited (ETI) directly, as and when required, for which contact
details are also mentioned on the Proposal Information Sheet. SECI in no case shall be
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 6 of 53
for Preparation of Detailed Project Reports (DPRs)responsible for any issues related to timely or properly uploading/ submission of the bid
in accordance with the relevant provisions of the Bidding Documents.
3.6. Applicants should submit their proposal complete in all aspect on or before last date and
time of Proposal Submission as mentioned on ISN-ETS Portal (https://www.bharat-
electronictender.com), SECI website http://www.seci.co.in and as indicated in the
Proposal Information Sheet.
3.7. Applicants shall submit their proposal along with non-refundable CfP Document Fee and
Tender Management Fee, complete in all respect, as per the Bid Information Sheet.
Proposals received without the prescribed CfP Document Fee and Tender Management
Fee will be rejected, with certain exceptions as provided in the CfP. In the event of any
date indicated being declared a holiday, the next working day shall become
operative for the respective purpose mentioned in this CfP document.
3.8. CfP documents can be downloaded from the ISN-ETS Portal or from SECI’s website. It
is mandatory to download official copy of the CfP Document from Electronic Tender
System (ISN-ETS) Portal to participate in the CfP. Any
amendment(s)/corrigendum(s)/clarification(s) with respect to this CfP shall be uploaded
on ISN-ETS website. The Applicant should regularly check for any
Amendment(s)/Corrigendum(s)/Clarification(s) on the above mentioned ISN-ETS
website. The same may also be uploaded on SECI website also. However, in case of any
discrepancy, the information available on ISN-ETS website shall prevail.
3.9. SECI reserves the right to cancel/ withdraw/ defer this invitation for proposals without
assigning any reason and shall bear no liability whatsoever consequent upon such a
decision.
3.10. Interpretations
i. Words comprising the singular shall include the plural & vice versa.
ii. An applicable law shall be construed as reference to such applicable law including
its amendments or re-enactments from time to time.
iii. A time of day shall save as otherwise provided in any agreement or document be
construed as a reference to Indian Standard Time.
iv. Different parts of this contract are to be taken as mutually explanatory and
supplementary to each other and if there is any differentiation between or among the
parts of this contract, they shall be interpreted in a harmonious manner so as to give
effect to each part.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 7 of 53
for Preparation of Detailed Project Reports (DPRs)SECTION 2. SPECIAL CONDITIONS OF CONTRACT
4. Scope of Work
The broad scope of work for preparation of Detailed Project Report (DPR) specified here
under outlines the works / services generally expected from the EA. The prospective
bidder is required to perform the mentioned functions and activities as set out expressly
in these documents and any other activities which may be essential and incidental thereto
for meeting the intent of specification of scheme. Accordingly, all the items/services
which are required for setting up of Hydrogen Hubs are deemed to be included while
preparing the DPR whether specifically mentioned or not. As per the DPR, the Green
Hydrogen Hub Developer (GHHD) shall render necessary, comprehensive and effective
services in all respect for smooth and timely development of a Hydrogen Hubs, which is
included but not limited to the following scope of work under the component B1
4.1. Assessment and Identification:
i. Identify and assess potential Green Hydrogen hub locations.
ii. Evaluate industrial clusters and existing infrastructure for green hydrogen and its
derivative’s production, storage, and utilization. Storage and transportation facilities for
Green Hydrogen/its derivatives.
iii. Identifying suitable locations based on techno-commercial viability, demand centers,
and infrastructure readiness.
4.2. Data Collection & Situation Analysis:
i. Gather baseline data including renewable energy potential, water availability, existing
industrial load, pipeline infrastructure and logistics infrastructure.
ii. Analyse the techno-commercial feasibility of developing a hub in the proposed area
iii. A financial analysis of the proposed Hydrogen Hub, including the expected costs and
revenues, and an Assessment of the project's and hub’s profitability.
4.3. Stakeholder Consultation
i. Engage with State Nodal Agencies, Industries, Power Utilities (Discoms), relevant
ministries and R&D institutions.
ii. Facilitate workshops and discussions to align stakeholder interests.
4.4. Detailed Project Report (DPR) Preparation
The Executing Agency shall submit its proposal, covering its planned activities to
provide the facilities/services envisaged as above. The scope of work as indicated by the
EA in the DPR, and as accepted by the Project Appraisal Committee, will be the final
scope of work against which, the EA’s performance will be evaluated for ascertaining
“Project completion”. The DPRs must include but not limited to following details:
i. Potential demand and supply centres for Green Hydrogen and its derivatives.
ii. Feasibility of co-located renewable energy capacity.
iii. Development or up gradation of existing pipeline infrastructure
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 8 of 53
for Preparation of Detailed Project Reports (DPRs)iv. Availability of land, Water treatment facility including desalination plant, Effluent
treatment plants and other utilities along with redevelopment plan of such requirements,
as required.
v. Grid connectivity existing as well as proposed and energy storage options to manage
Renewable Energy’s intermittency.
vi. Green Hydrogen powered vehicle re-fuelling facility
vii. Proposed project structure and financial models.
viii. Hydrogen compression and/or liquefaction technologies, as required
ix. Hydrogen storage systems, including bulk liquid, gaseous, materials-based
technologies or subsurface options (e.g., salt caverns, depleted oils and gas fields, un-
used coal mines etc.)
x. Development of bunkering facilities in case of ports including provisions of bunker
barges for handling large vessels such as Very Large Crude Carriers (VLCC)
xi. Infrastructure up gradation for shipping including expansion of port/jetty infrastructure
for exports, if required.
xii. Preparation of detailed layout plans, CAPEX/OPEX estimation, implementation
phasing, and risk assessment.
xiii. Identification of public and private stakeholders.
xiv. Regulatory and clearance requirements.
xv. Phase-wise implementation roadmap
xvi. Environmental and social impact.
xvii. Risk mitigation and legal considerations.
4.5. Roadmap & Implementation Plan
i. Provide an actionable roadmap with timelines, milestones, and responsibilities for
setting up the Hydrogen Hub.
ii. Provide technical support for any queries or appraisals required during project sanction.
4.6. Compliance:
i. Ensure alignment of DPRs with the objectives and implementation framework for
development of Green Hydrogen Hubs under Component-B1 of the NGHM.
ii. Regulatory feasibility and integration into state energy policies.
iii. A review of the relevant laws, regulations, and permits required for the construction
and operation of the Hydrogen Hubs.
4.7. Risk Analysis:
An evaluation of the potential risks associated with the Project and Hydrogen Hub,
including technical, financial, environmental, and social risks.
4.8. Social impact analysis: An assessment of the social impact of the project, including its
effect on the local community, employment opportunities, and social welfare.
4.9. Skill Development
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 9 of 53
for Preparation of Detailed Project Reports (DPRs)I. To ensure a robust and capable workforce in Green Hydrogen ecosystem, it is
crucial to focus on skilling and capacity building activities in alignment with the
evolving requirement of the industry. In this reference, Guidelines for Scheme on
skilling, up-skilling and re-skilling under the National Green Hydrogen Mission
were notified on 16th March 2024. The concerned guidelines have a focus on
several key actions to build a sustainable and knowledgeable Green Hydrogen
workforce. National Skill Development Corporation (NSDC) has been notified
as the Scheme Implementing Agency (SIA) under the guidelines on 7th June
2024. The scheme will be implemented through the Skill India Digital hub
developed by the Ministry of Skill Development and Entrepreneurship (MSDE).
II. In order to promote the skilling and capacity building necessary for the efficient
installation, operation and management of Green Hydrogen and Green Ammonia
plants established with the support and various incentives including under SIGHT
scheme in India, the concerned industry may routinely undertake comprehensive
skilling programs in coordination with the Ministry of Skill Development and
Entrepreneurship (MSDE), and otherwise. These programs may encompass both
theoretical and practical trainings across the Green Hydrogen value chain
including in Green Hydrogen production installation & operation, integration of
renewable energy, Electrolyser manufacturing, storage, transportation, safety,
utilization of Green Hydrogen and its derivatives, etc.
III. In this reference, it is pertinent that the successful bidders may engage actively in
implementation of suitable skilling and capacity building activities across their
concerned production and other facilities, in coordination with MSDE and
otherwise. Suitable focus may be provided on provision of required practical
trainings and on the Job Training (OJT) along with undertaking various
internships/ apprenticeship activities, as applicable.
4.10. Additional Services:
At the specific request of the PAC, the EA shall provide such additional services not
listed in the specifications in relation to the CfP work activities but felt necessary by the
PAC to be included in the DPR for development of a Green Hydrogen Hub. Reports &
Presentations of each Hub Location shall be submitted in editable MS OFFICE formats
for review (with the list of changes in each version). Final PAC approved reports shall
be submitted 3 nos. of colour printed hard copies and one non-editable soft copies in
static drive.
5. Central Financial Assistance
An amount of Rs. 28 crores have been allocated for the preparation of Detailed Project
Reports (DPRs) for Green Hydrogen Hubs under Component B1, with a cap of Rs. 3
crores per DPR per state. Funds shall be disbursed to EA in following manner for
preparation of DPRs for Green Hydrogen Hubs under Component B1;
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 10 of 53
for Preparation of Detailed Project Reports (DPRs)Percentage of CFA to be
Sl.
Stages of Disbursement released
No.
30%
Date of issue of administrative approval/sanction
1
Submission and acceptance draft DPR by the 40%
2 PAC/ (as per their comments, as applicable)
upon acceptance of final DPR by the State Govt. 30%
3 or its designated agency
100%
Total
6. Maximum Eligibility for Central Financial Assistance to an Applicant
Following conditions shall be applicable to the applicants for submission of proposal
against this CfP:
6.1. An Applicant, including its Parent, Affiliate or Ultimate Parent or any Group Company
shall submit a single Proposal undertaking to prepare a Detailed Project Report for setting
up of Green Hydrogen Hubs to be setup in each state, by submitting its proposal for
maximum 1 DPR.
6.2. The maximum CFA that will be allocated to an Applicant including its Parent, Affiliate
or Ultimate Parent or any Group Company shall be limited to Rs 3 Crore Per DPR.
Applicants shall be required to quote the CFA as per Price Schedule provided along
with the CfP. Maximum CFA that can be quoted in price schedule is Rs 3 Crore.
6.3. If the cost of DPR is more than the cap provided under the guidelines (i.e., Rs 3 crore per
DPR per state), then the additional cost of DPR may be met by the developer or the
concerned State Government.
6.4. The evaluation of proposal shall be carried out as described in Section-5 of the CfP.
6.5. Multiple proposals from same company including its Parent/ Ultimate
Parent/Affiliates/Group Companies shall make all the proposals submitted by the group
invalid. In case of Joint Venture Company/ Consortium, a partner/ company will be
allowed to tie up with another partner/company for one proposal only.
7. Timelines for Submission of DPRs
The Executing Agency will be required to execute works as per the approved Scope of
Work given under the Letter of Award/Notification of Award. The EA shall submit the
Final DPR, in all aspects as per following tables
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 11 of 53
for Preparation of Detailed Project Reports (DPRs)Sl. Services Nomenclature Timeline
No.
1 Issuance of LoA/NoA D0 Date of LoA/NoA
Submission of draft DPR to Project
2 D1 D0+ 12 Weeks
Appraisal Committee at MNRE
Presentation on draft DPR
3 submitted to Project Appraisal D2 D1+1 Week
Committee at MNRE
Observations
Submission of Final DPR to Project offered by PAC on
4 D3
Appraisal Committee at MNRE Draft DPR + 1
Week
Presentation on final DPR to PAC
5 D4 D3+1 Week
MNRE
Submission of Final Detailed
6 Project Development Report based D5 D4+1 Week
on observations during presentation
8. Penalty for Delay
8.1. Any delay that may take place in Submission of DPR beyond contractual cut-off
date/stipulated period in the order shall be subjected to penalty (not liquidated damages)
at the rate of ½ % of the sanctioned CFA per week or part thereof subject to a maximum
of 5 % of the total CFA value.
Due consideration will be given in the levy of penalty for reasons absolutely beyond
control of EA for which necessary evidences has to be produced by the EA to the
satisfaction of the Steering Committee/PAC of MNRE.
8.2. SECI reserves the right to forfeit Bid security/ Security Deposit (If applicable) or deduct
payment from allocated CFA or applicable penality from the EA if during tendering or
during DPR Submission stage it is found that Bidder/EA has violated any terms and
condition as stipulated in this CfP, the grants released under this CfP shall be exclusively
earmarked for the preparation of DPR and should not be diverted for any other purpose.
8.3. The Executing Agency shall abide by the timeline specified in clause 7 above. Any
extension beyond stipulated timelines will be granted for submission of DPR on the basis
of adequate justification, with the approval of Steering committee of MNRE, without any
penalty.
8.4. MNRE/SECI reserves the right to retract sanction/cancel/short close the Projects in
consultation with the Steering Committee/PAC in cases where the Executing Agency
faces unreasonable delays or fails to comply with the objectives/provisions of this scheme
or the Mission.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 12 of 53
for Preparation of Detailed Project Reports (DPRs)9. Funding and disbursement
9.1. The Preparation of DPRs for Green Hydrogen Hubs proposed to be set up in each state
shall be supported with a cap of Rs. 3 Crore per DPR per state.
9.2. CFA/Funds shall be disbursed in following manner for preparation of DPRs for Green
Hydrogen Hubs under Component B1;
Percentage of CFA to be
Sl.
Stages of Disbursement released
No.
Date of issue of administrative approval/sanction 30%
1
Submission and acceptance draft DPR by the 40%
2 PAC/ (as per their comments, as applicable)
upon acceptance of final DPR by the State Govt. 30%
3 or its designated agency
100%
Total
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 13 of 53
for Preparation of Detailed Project Reports (DPRs)SECTION 3. STANDARD CONDITIONS OF CONTRACT
10. Obtaining CfP Documents
Interested Applicants have to download the official copy of CfP & other documents after
login into the ISN-ETS portal by using the Login ID & Password provided by ISN-ETS
during registration (Refer Annexure - B). The Applicants shall be eligible to submit/
upload the Proposal document only after logging into the ISN-ETS portal and
downloading the official copy of CfP.
11. Cost of Documents and Tender Management fees
Prospective Applicants are required to submit their proposals in response to this CfP
document along with a non-refundable cost of CfP document and Tender Management
Fees as mentioned in the Bid Information Sheet. An Applicant will be eligible to
participate in the selection process only on submission of all the applicable financial
amounts as per the Proposal Information Sheet. Payments against Cost of CfP document
and Tender Management Fee shall be done only through NEFT/RTGS (electronic
transfer), and the Applicants shall submit the transaction receipt, as part of the online
proposal submission.
The bank details of SECI are available at SECI’s website, www.seci.co.in, under the
“Financials” tab. Upon making the necessary payments, the prospective Bidders shall
immediately write to SECI (mailing to finance@seci.co.in), providing the payment
details along with name and registered address of the Bidder (with GSTIN of the paying
entity), to enable seamless issuance of payment invoices for taxation purpose. SECI will
not be liable for any delay in issuing necessary invoices in this regard.
Proposals submitted without Cost of CfP document and/or Tender Management
Fee (including partial submission of any one of the respective amounts), may be
liable for rejection by SECI.
MSEs (Micro and Small Enterprises) having valid UDYAM registration on the last date
of submission of proposals only are exempted from submission of Cost of CfP Document,
and Tender Management Fees. For a Consortium to be eligible for exemption from
submission of Cost of CfP Document, and Tender Management Fees, all the members of
the Consortium shall be registered as MSE.
12. Instructions to Applicants for Structuring of Proposals in Response to CfP
The Applicant, including its Parent, Affiliate or Ultimate Parent or any Group Company
shall submit single response to CfP. Submission of proposals by Applicants in response
to CfP shall be done in the manner described below:
a. Checklist for Proposal Submission as per Annexure-A
b. Covering Letter as per Format 7.1.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 14 of 53
for Preparation of Detailed Project Reports (DPRs)c. In case of a Consortium/Joint Venture, a Power of Attorney in favour of the Lead
Member issued by the other Members of the Consortium/Joint Venture shall be
provided in original as per format attached hereto as Format 7.2.
In the event any Member of the Bidding Consortium (other than Lead Member) is a
foreign entity, it may submit Board Resolutions in place of Power of Attorney for
the purpose of fulfilling the requirements under this clause. Provided that such Board
Resolutions shall be supported by an unqualified opinion issued by the legal counsel
of such foreign entity stating that the Board Resolutions are in compliance with the
applicable laws of the respective jurisdictions of the issuing Company and the
authorizations granted therein are true and valid.
d. Board Resolutions, as per prescribed formats enclosed as per Format 7.3 duly
certified by the Company Secretary or the Director of the relevant applicant, as
applicable to the applicant and mentioned hereunder:
i. Board Resolution from the Applicant Company or the Lead Member of the
Consortium/JV, as the case may be, in favour of the person signing the response
to CfP and in the event of selection of the Project. Board Resolution from each
of the Consortium/JV Members in favour of the person signing Consortium/JV
Agreement.
e. In case of a Consortium/JV, the Consortium/JV Agreement between the Members in
the Consortium/JV as per Format 7.4, along with Board resolution from each
Member of the Consortium/JV for participating in Consortium/JV.
f. Undertaking as per Format 7.5.
g. A disclosure statement as per Format 7.6 regarding participation of any related
companies in the selection process.
h. Attachments
i. Memorandum of Association, Article of Association needs to be attached along
with the Proposal. The bidder should also highlight the relevant provision which
highlights the objects relating to Special Economic Zone (SEZ)/Industrial
Hub/Power/Energy/Renewable Energy/ Green Hydrogen/Hydrogen
project/park/hub consultancy or development.
ii. Certificate of Incorporation of Applicant Company/ all member companies of
Consortium/JV.
iii. A certificate of shareholding of the Applicant company, its Parent and Ultimate
Parent (if any) duly certified by a practicing Chartered Accountant/ Company
Secretary as on a date within 30 days prior to the last date of Proposal
submission. SECI reserves the right to seek additional information relating to
shareholding in promoter companies, their Parents/ Ultimate Parents/ Affiliates
and other Group Companies to satisfy themselves that CfP conditions have been
complied with and the applicant will ensure submission of the same within the
required time lines.
iv. Certified copies of annual audited accounts for the last 3 financial years, i.e. FY
2025-24,2024-23, 2023-22, along with certified copies of Balance Sheet, Profit
& Loss Account, Schedules and Cash Flow Statement supported with bank
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 15 of 53
for Preparation of Detailed Project Reports (DPRs)statements shall be required to be submitted.
v. Details of all types of securities/instruments which are pending conversion into
equity whether optionally or mandatorily.
i. Any other documents required for evaluation of proposals as per Section 5.
13. Important Notes and Instructions to Applicants
13.1. Wherever information has been sought in specified formats, the Applicants shall fill in
the details as per the prescribed formats and shall refrain from any deviations and
referring to any other document for providing any information required in the prescribed
format.
13.2. The Applicants shall be shortlisted based on the declarations made by them in relevant
schedules of CfP. The documents submitted online may be verified before the
Administrative Approval in terms of Section 5 of the CfP and at any point of time during
the Project implementation period.
13.3. If the Applicant/Member in a Applicant Consortium/JV conceals any material
information or makes a wrong statement or misrepresents facts or makes a misleading
statement in its response to CfP, in any manner whatsoever, SECI reserves the right to
reject such response to CfP and/or cancel the Letter of Award. Applicant shall be solely
responsible for disqualification based on their declaration in the submission of response
to CfP.
13.4. Response submitted by the Applicant shall become the property of the SECI and SECI
shall have no obligation to return the same to the Applicant.
Also, the confidential information/data pertaining to the Green Hydrogen Hub, including
but not limited to execution plan, will not be shared by SECI to any third party without
prior consent of the Applicant, unless sought by the Government or required to be given
under law.
13.5. All documents of the response to CfP (including CfP and subsequent Amendments/
Clarifications/ Addenda) submitted online must be digitally signed by the person
authorized by the Board as per Format 7.3.
13.6. The response to CfP shall be submitted as mentioned in Clause 14 of the CfP. No change
or supplemental information to a response to CfP will be accepted after the scheduled
date and time of submission of response to CfP. However, SECI reserves the right to seek
additional information from the Applicants, if found necessary, during the course of
evaluation of the response to CfP.
13.7. The Applicant shall make sure that the correct, valid and operative Pass-Phrase to decrypt
the relevant proposal is submitted into the ‘Time Locked Electronic Key Box (EKB)’
before the commencement of the Online Tender Opening Event (TOE).
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 16 of 53
for Preparation of Detailed Project Reports (DPRs)13.8. All the information should be submitted in English language only. In case of foreign
Applicants having documents in other than English language, then the documents shall
be translated in English language by certified translator and submitted.
13.9. Applicants shall mention the name of the contact person and complete address and
contact details of the Applicant in the covering letter.
13.10. Response to CfP that are incomplete, which do not substantially meet the requirements
prescribed in this CfP, will be liable for rejection by SECI.
13.11. Response to CfP not submitted in the specified formats will be liable for rejection by
SECI.
13.12. Applicants delaying in submission of additional information or clarifications sought
will be liable for rejection.
13.13. Non-submission and/ or submission of incomplete data/ information required under the
provisions of CfP shall not be construed as waiver on the part of SECI of the obligation
of the Applicant to furnish the said data/ information unless the waiver is in writing.
13.14. Only New Delhi Courts shall have exclusive jurisdiction in all matters pertaining to this
CfP.
13.15. All the financial transactions to be made with SECI including any additional charges (if
required), shall attract 18% GST on each transaction, irrespective of the same being
mentioned in the CfP.
14. Non-Responsive Proposal
The electronic response to CfP submitted by the Applicant along with the documents
submitted online to SECI shall be scrutinized to establish “Responsiveness of the
Proposal”. Each Applicant’s response to CfP shall be checked for compliance with the
submission requirements set forth in this CfP.
Any of the following conditions shall cause the Proposal to be “Non-responsive”:
(a) Non-submission of the requisite Cost of CfP and/ or Tender Management Fee as
mentioned in the Proposal Information Sheet.
(b) Response to CfP not received by the due date and time of Proposal submission.
(c) Non-submission of correct, valid and operative Pass-Phrases for Envelop before the
commencement of the Online Tender Opening Event (TOE).
(d) In case it is found that the Applicant Company including Ultimate Parent Company/
Parent Company/Affiliate/Group Companies have submitted more than one
response to this CfP, then all these proposals submitted shall be treated as non-
responsive and rejected.
In any of the above cases, the Proposal shall not be considered for opening and evaluation
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 17 of 53
for Preparation of Detailed Project Reports (DPRs)process.
15. Method of Submission of Response to CfP by the Applicant
15.1. Documents to be Submitted Online
No document is required to be submitted offline, except of Bid Processing Fee, EMD
(if applicable) and Pass Phrase. Detailed instructions to be followed by the Applicants
for online submission of response to CfP are stated as Annexure-B. The Applicants shall
strictly follow the instructions mentioned in the electronic form in Envelope while filling
the form.
All documents of the response to CfP submitted online must be digitally signed and
uploaded on the website, https://www.bharat-electronictender.com which should
contain the following:
i. Techno-commercial Proposal
The Applicant shall upload the single proposal containing scanned copies of the
following documents duly signed and stamped on each page or digitally signed by the
authorized signatory as mentioned below.
i. Annexure-A
ii. Formats - 7.1, 7.2 (if applicable), 7.3, 7.4 (if applicable), 7.5 and 7.6 as elaborated
in Clause 14 of the CfP.
iii. All attachments elaborated in Clause 14 of the CfP, under the sub-clause i:
Attachments, with proper file names.
iv. All supporting documents regarding meeting the eligibility criteria and scoring
during the evaluation of proposal
v. Scanned Copies of NEFT/RTGS details towards Cost of CfP document and Tender
Management Fee as mentioned in Proposal Information Sheet.
The applicant will have to fill the Electronic Form provided at the ISN-ETS portal
as part of Envelope.
Submission of Pass-phrase: The Applicant shall be required to submit the Pass-Phrase to
decrypt the proposal into the ‘Time Locked Electronic Key Box (EKB)’ before the
commencement of the Tender Opening Event (TOE).
Important Note:
• The Applicants shall not deviate from the naming and the numbering formats of
envelop mentioned above, in any manner.
• In case an Applicant has paid cost of CfP document and Tender Management Fee
for this CfP and chooses not to participate in the selection process (i.e. the Applicant
does not submit any Proposal to SECI), the respective amounts paid to SECI will be
refunded without any interest payment, to the respective Applicant.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 18 of 53
for Preparation of Detailed Project Reports (DPRs)16. Not Used
17. Validity of the Proposals
The Applicant shall submit the proposal which shall remain valid up to the date as on 12
months from the last date of submission of response to this CfP (“Proposal Validity”).
SECI reserves the right to reject any response to this CfP which does not meet the
aforementioned validity requirement.
18. Proposal Preparation Cost
The Applicant shall be responsible for all the costs associated with the preparation of the
response to CfP and participation in discussions and attending pre-bid meeting(s) etc.
SECI shall not be responsible in any way for such costs, regardless of the conduct or
outcome of the selection process.
19. Clarifications/ Pre-Bid Meeting/ Enquiries/ Amendments
Clarifications/ doubts, if any, on CfP document may be emailed and/ or submitted
through ISN-ETS portal. The format for submission of clarifications is available on the
portal. A Pre-Bid Meeting shall be held as mentioned in the Bid Information Sheet
(Venue to be notified later on SECI’s website). SECI will make efforts to respond to the
same in the Pre-Bid Meeting. A compiled list of such questionnaire and SECI’s response
will be uploaded in the ISN-ETS portal. If necessary, amendments, clarifications,
elaborations shall be issued by SECI which will be notified on the same portal and SECI’s
website. No separate reply/ intimation will be given for the above, elsewhere. In the event
of the issuance of any revision or amendment of the CfP documents, the Applicant shall
be provided a period of at least 7 days there from, for submission of proposal.
20. Right of SECI to Reject a Proposal
SECI reserves the right to reject any or all of the responses to CfP or cancel the CfP or
annul the selection process for any project at any stage without assigning any reasons
whatsoever and without thereby any liability. In the event of the CfP being cancelled
prior to opening of proposals, the Tender Management Fee (excluding GST, if amount
credited to SECI’s account), without any interests, submitted by the Applicants shall be
returned to the respective Applicants. In the event of opening of proposals, Tender
Management Fee will not be refunded, irrespective of the outcome of this selection
process.
21. Post Award Compliances
Timely completion of all the milestones will be the sole responsibility of the EA.
SECI/MNRE shall not be liable for issuing any intimations/ reminders to Applicants for
timely completion of milestones and/ or submission of compliance documents.
Any checklist shared with Applicant by SECI for compliance of above-mentioned
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 19 of 53
for Preparation of Detailed Project Reports (DPRs)milestones to be considered for the purpose of facilitation only. Any additional
documents required as per the conditions of Guidelines and CfP must be timely submitted
by the EA.
22. Points of Contact in SECI
Following officers/departments are to be contacted by the Applicants/EAs based on the
stage of bidding and project implementation under this CfP:
i) Proposal submission up to issuance of LoA: - Details as per Bid Information Sheet
ii) Subsequent to issuance of LoA: -
Sh. Piyush Verma Phone (Off): 011-24666292
Dy. Manager Email: pverma.09@seci.co.in
Sh. Abhishek Kumar Ambasta Phone (Off): 011-24666252
DGM Email: akambasta@seci.co.in
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 20 of 53
for Preparation of Detailed Project Reports (DPRs)SECTION 4. QUALIFICATION REQUIRMENTS FOR APPLICANTS
Short listing of Bidders will be based on the following Criteria:
23. Prospective Applicants:
23.1. The following agencies are eligible for submitting their project proposals under this
scheme:
i. Central Public Sector Undertakings (CPSUs)
ii. State-PSUs
iii. Private Sector Companies
iv. State-Owned Corporations/Organizations
v. Autonomous Bodies
vi. JV/Consortiums of above stated agencies
23.2. Bidding Consortium with one of the Companies as the Lead Member.
23.3. Individual persons, Proprietorships, Partnerships, Trusts, NGOs, and Limited Liability
Partnership (LLPs) are not eligible for participation on an individual basis or as a part of
a Consortium.
23.4. The necessary capabilities need to exist with the EAs for taking forward the project
towards completion and commercialization.
23.5. If any State Government has any proposal for preparation of a DPR by a PSU or
Autonomous Body under Component-B1, the Proposal. It may kindly be submitted to
SECI under this CfP.
23.6. If a proposal is received from a project proponent (CPSUs/PSUs/Private Sector
Companies/Govt. Owned Corporations/Autonomous Bodies), it should have the
endorsement of the concerned state Govt.
23.7. If more than two DPR proposals are submitted for a state, then the state government or
its designated authority may club those proposals or prioritize them. In the absence of a
clear-cut recommendation from the state government regarding prioritizing or clubbing
the proposals, only the proposal/Application scoring the highest marks post techno-
commercial evaluation will be considered for award.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 21 of 53
for Preparation of Detailed Project Reports (DPRs)SECTION 5. PROPOSAL EVALUATION AND AWARD
24. Project Proposal Evaluation:
i. Proposal evaluation will be carried out considering the information furnished by
Applicants as per provisions of this CfP. The detailed evaluation procedure and
selection of Applicants are described in subsequent clauses in this Section. The purpose
of this section is only to provide the applicants an idea of the evaluation process that
the SECI and PAC may adopt. However, SECI/PAC reserves the right to modify the
evaluation process at any time during the Tender process, without assigning any reason,
whatsoever but with prior intimation to Bidders for such changes.
ii. A two-stage procedure shall be adopted for evaluation of proposals i.e. Techno-
commercial evaluation followed by a presentation. Selection of EA/Consultant shall be
based on Quality Based Selection (QBS) criteria. This takes into account both the
technical capability of the Bidder as well as the availability of Land. The Technical
(Quality points Q ) and Availability of Land will be given 90:10 weightage
p
respectively.
iii. The selection of project proposals will be done based on the following scoring matrix:
S.no. Criteria Weightage
1 Evaluation of Proposals on past Techno- 60%
commercial experience (Q ) at 90% and 10%
p
weightage to Availability of land
2 Presentation by the Applicant on proposed 40%
DPR to PAC/Sub-Committee to PAC
Total 100%
24.1. Evaluation of proposal:
i. The Techno-commercial Proposals submitted online of only those Applicants will be
opened by SECI whose required documents as mentioned at Clause 12 and Clause 14
of the CfP are received by SECI on or before the bid submission deadline.
ii. The Applicant will be required to submit the following documents along with project
proposal, in addition to the documents listed at Clause 12 and Clause 14 above:
➢ Registration Certificate, MOA & AOA
➢ Brief profile of Organization and Organizational chart
➢ CA certificate for Liquidity and Turnover
➢ Authorization / Board Resolution (as applicable) for the signatory to the project
proposal
iii. PAC/Sub-Committee (as designated) will review the technical bids to determine
whether the technical bids are substantially responsive as per clause 23. Bids that are
not substantially responsive are liable to be disqualified.
iv. PAC/ Sub-Committee (as designated) will assign Points to the technically qualified
bidders based on the technical evaluation criterion given in the bid document.
Conditional bids are liable to be rejected.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 22 of 53
for Preparation of Detailed Project Reports (DPRs)v. Technical Bids of the bidders shall be scrutinized based on qualifying criteria and
evaluated as per QBS. The selection shall be done on 90% weightage of quality points
(Q ) and 10% weightage to availability of land. Marks/rating will be considered for
p
authentic established items only.
vi. The Q (Technical / Quality Points) for the selection/merit criteria for QBS will be
p
evaluated in accordance with the detailed criteria mentioned :
Maximu
m Points Criteria For Po
S. No. Criteria (Quality assigning int Remarks
Points- Points s
Qp)
1 General Criteria 10
> 100 Crore 6
Financial: Average Annual
Turnover during previous 3
10
FYs (FY 2024-25, 2023-24 &
2022-23) > 500 Crore 8
≥ 1000 Crore 10
2 Technical Criteria 44
Experience in Experience for
DEVELOPMENT OF only
Hydrogen Commissioned
Projects/park/SEZ/hub/HVI /completed
No. of Po
C/ Export-Oriented Units 44 Hydrogen
Projects int
(EOUs)/Industrial Hub projects or
s
(number of such Park/Hubs/HV
Projects/parks/similar IC/SEZ/Indust
2.1 facilities rial Hub
development/
5 44 Export-
Oriented Units
3 34 (EOUs) for
General
Criteria will be
considered for
assigning
#Minimum Project Cost should not be less
scores.
than the INR 500 Crores duly certified by a
practitioner CA
1 24 • Valid
documentary
proof shall be
submitted
along with the
bid to justify
and support
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 23 of 53
for Preparation of Detailed Project Reports (DPRs)claim for
marks against
each
Technical/
Quality
Evaluation
criteria.
• For validity
of proof,
SECI/PAC
judgment shall
be final and
binding to the
bidder.
Note:
i. Bidder/Applicant will have Max Eligible Quality Points if evaluated quality
points for particular Sr no are greater than Max Eligible Quality Points.
ii. Each Technical Proposal will receive a technical merit score based on the
above-mentioned evaluation criteria.
vii. Availability of Land with the Hydrogen Hub developer: demonstrated land by
Bidder will be considered for the Evaluation of Bids and ranking. The weightage on
Land availability shall be considered as 10% of 60%. of Marking against availability
of land for the selection/merit criteria for QBS will be evaluated in accordance with the
detailed criteria mentioned below
Sl. Criteria (Percentage of acquisition) Maximum Points
No. Points
1 A confirmation letter from the 6 2
State/Central Government indicates that
land will be allocated for Hydrogen Hub
development
2 A confirmation letter/D.O. Letter from 4
state govt stating more than 50% land is
identified for Hydrogen Hub
Development
3 A confirmation letter/D.O. Letter from 6
state govt stating more than 50% land is
identified, acquired and under possession
for Hydrogen Hub Development
viii. The interested Applicants are required to submit duly signed documents (as per
requirements mentioned above). The Proposals submitted will be evaluated by the
Project Appraisal Committee (PAC)/ Sub-Committee (as designated).
ix. Subject to Clause 12 & 14 of the CfP, SECI/PAC will examine all the documents
submitted by the Applicants and ascertain meeting of eligibility conditions prescribed
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 24 of 53
for Preparation of Detailed Project Reports (DPRs)in the CfP. During the examination of proposals, SECI/PAC may seek
clarifications/additional documents to the documents submitted etc. from the
Applicants if required to satisfy themselves for meeting the eligibility conditions by the
Applicants. Applicants will be required to respond to any clarifications/additional
documents sought by SECI/PAC within 07 (seven) days from the date of such
intimation from SECI/PAC. All correspondence in this regard shall be made through
email/ISN-ETS portal only. It shall be the responsibility of the Applicant to ensure that
the email id of the authorized signatory of the Applicant is functional. The Applicant
may provide an additional email id of the authorized signatory in the covering letter.
No reminders in this case shall be sent. It shall be the sole responsibility of the
Applicants to remove all the discrepancies and furnish additional documents as
requested. SECI shall not be responsible for rejection of any proposal on account of the
above.
24.2. Presentation:
The applicant will be required to present the proposal in front of the Evaluation
Committee/ Project Appraisal Committee. The Committee will assess the preparedness
of the applicant and check and rectify any incongruence/gaps in the proposal. The
weightage of Presentation shall be considered as 40%.
Evaluation Committee/Project Appraisal Committee’s decision regarding the scores
provided and selection of Applicant shall be final and binding on all participating
Applicants.
25. Selection of the EA and Issuance of LoAs
25.1. The selection of EA shall be done based on the scores received by the Applicant as
defined in clause 24 above. In case two or more applicants secured the exact same scores,
such tied proposals would be prioritized based on the decision of state govt. The top
Applicants for each state, receiving the highest score as a result of the above evaluation,
will be eligible for issuance of Letters of Award (LoA)/Notification of Award by SECI
upon recommendation of PAC/Sub-committee.
25.2. At the end of selection process, for each State, LoAs will be issued to the Successful
Applicants after the Administrative Approval by MNRE, for its respective proposal for
preparation of DPR for setting up of Hydrogen Hub. In case of a Consortium/JV being
selected as the successful Applicant, the NoA shall be issued to the Lead Member of the
Consortium/JV.
25.3. SECI reserves the right to annul the bid process without any financial implications to any
of the parties concerned.
25.4. In all cases, SECI’s decision regarding selection of Applicant or annulment of tender
process shall be final and binding on all participating Applicants.
26. Miscellaneous Provisions
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 25 of 53
for Preparation of Detailed Project Reports (DPRs)The following miscellaneous provisions shall be applicable in this Call for Proposal:
26.1. Charges & Cost: Unless otherwise agreed, all charges and cost shall be borne by the
applicants for preparing DPR for development of Green Hydrogen Hubs. Till the
issuance of Letter of Award, under no circumstances, SECI/MNRE shall be liable for
any cost and charges whatsoever for the activities under taken by the Executing Agencies.
26.2. Compliance with Applicable Laws / Regulations / Guidelines and
Technical/Regulatory Approvals: Project Developer shall comply with all applicable
laws, regulations and guidelines. The EA shall be solely responsible for obtaining the
safety, environmental and other approvals as required.
26.3. Testing and Certification: The Hydrogen Hub Developers shall get necessary testing
and certification compliance from the concerned agencies.
26.4. Indemnity: EA/ Hydrogen Hub Developers shall indemnify, defend and hold SECI and
MNRE harmless against any claims, losses, damages, cost, expenses, penalty, fines
arising out of any of act, omission, breach, actions and deeds of the EA.
26.5. Confidentiality: The Parties undertake to hold in confidence information / data /
documents exchanged during course of execution of the project (and subsequently) and
not to disclose the terms and conditions of the transaction contemplated hereby to third
parties without the prior written consent of the other Party, except:
a) to their professional advisors;
b) to their officers, contractors, employees, agents or representatives, financiers, who
need to have access to such information for the proper performance of their
activities; or
c) Disclosures required under Law
26.6. Adherence to the Highest Degree of Standards: The Applicants and their respective
officers, employees, agents and advisers shall observe the highest standard of ethics
during the Execution Process and subsequently. The Authority may reject any
Application without being liable in any manner whatsoever to the applicant if it
determines that the applicant has, directly or indirectly or through an agent engaged in
misrepresentation, intellectual property (IP) right violation, corrupt practice, fraudulent
practice, coercive practice, undesirable practice or restrictive practice. In such case, SECI
will withdraw the application of such agency immediately and further SECI reserves right
to debar such agency from participation in any of SECI’s tenders for a further period of
two (2) years from the date of such debarment.
26.7. Steering Committee: Overall monitoring of the scheme and evaluation of projects
undertaken will be done by the Steering Committee under the chairmanship of Secretary
MNRE and comprising of members viz., Mission Director-NGHM and any other
members as nominated. The Steering Committee shall be responsible for overall
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 26 of 53
for Preparation of Detailed Project Reports (DPRs)monitoring and implementation of the scheme and suggest modification and course
corrections for its successful implementation.
In case of any ambiguity in the interpretation of any of the provisions of the scheme, the
decision of MNRE shall be final. The Steering Committee will also facilitate/ recommend
measures to resolve difficulties if any.
26.8. Project Appraisal Committee: A Project Appraisal Committee (PAC) through a sub-
committee (as designated) shall monitor/review/evaluate the project proposals and
recommended projects for sanction of CFA. The PAC through a sub-committee (as
designated) shall monitor sanctioned projects on quarterly basis for the allocation of
funds based upon the progress of the project. Based on the recommendation of PAC,
MNRE through SECI shall release the CFA to the EA.
26.9. Progress Report: The EA shall submit bi-weekly progress reports to PAC/SECI.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 27 of 53
for Preparation of Detailed Project Reports (DPRs)SECTION 6. DEFINITIONS
27. Definitions of Terms: Following terms used in the documents will carry the meaning
and interpretations as described below:
i. “AFFILIATE” shall mean a company that, directly or indirectly,
a) controls, or
b) is controlled by, or
c) is under common control with, a company developing a Project or a Member in a
Consortium developing the Project and control means ownership, directly or
indirectly, of more than 50% (fifty percent) of the voting shares of such company or
right to appoint majority Directors.
ii. “BID” or “PROPOSAL” shall mean the documents submitted by the Applicant
towards meeting the qualifying requirements, along with the Detailed Project Report
submitted by the Applicant as part of its response to the CfP issued by SECI.
iii. “Applicant” shall mean the Company/organization (including a foreign company) or a
Consortium/Joint Venture (JV) submitting the Proposal. Any reference to the Applicant
includes Company/Consortium/ JV, Member of a Consortium/JV including its
successors, executors and permitted assigns and Lead Member of the Consortium/JV
jointly and severally, as the context may require; foreign companies participating in this
process shall be registered as companies as per the rules of their country of origin.
iv. “BIDDING CONSORTIUM” or “CONSORTIUM” shall refer to a group of
Companies that collectively submit the response in accordance with the provisions of this
CfP under a Consortium Agreement.
v. “CfP” or “CfP DOCUMENT” or “BIDDING DOCUMENT(S)” or “TENDER
DOCUMENTS” shall mean the “Call for Proposal” document issued by SECI along
with subsequent clarifications and amendments thereof, vide CfP No.
SECI/C&P/EOI/17/0002/25-26 dated 17.09.2025.
vi. “CHARTERED ACCOUNTANT” shall mean a person practicing in India or a firm
whereof all the partners practicing in India as a Chartered Accountant(s) within the
meaning of the Chartered Accountants Act, 1949.
For Applicants incorporated in countries other than India, “Chartered Accountant” shall
mean a person or a firm practicing in the respective country and designated/ registered
under the corresponding Statutes/ laws of the respective country.
vii. “CHARTERED ENGINEER” shall mean a person practicing in India or a firm whereof
all the partners practicing in India is/are registered as “Professional Engineer(s)/
Chartered Engineer(s)” under the Indian Institute of Engineers or other recognized
institution in India.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 28 of 53
for Preparation of Detailed Project Reports (DPRs)viii. “COMPANY” shall mean a body corporate incorporated in India under the Companies
Act, 2013 or any law in India prior thereto relating to Companies, as applicable.
ix. “CONTROL” shall mean the ownership, directly or indirectly, of more than 50% (fifty
percent) of the voting shares of such Company or right to appoint majority Directors.
x. “DAY” shall mean calendar day.
xi. “EQUITY” shall mean Net Worth as defined in Companies Act, 2013.
xii. “EXECUTING AGENCY” or “EA” shall mean the Bidding Company or a Bidding
Consortium/JV participating in the bid and having been selected by PAC (through a
competitive bidding process).
xiii. “GREEN HYDROGEN HUB” shall mean a dedicated zone as proposed by the EA for
setting up of the assets providing facilities and services identified as per Clauses 2 and 5
of this CfP.
xiv. “GUIDELINES” shall mean “Scheme Guidelines for setting up Hydrogen Hubs in India
under the National Green Hydrogen Mission” vide OM No. 353/12/2025-NT dated
27.06.2025, including subsequent amendments and clarification thereof, if any, issued
until the last date of proposal submission of this CfP.
xv. “GROUP COMPANY” of a Company means
a) a Company which, directly or indirectly, holds 10% (Ten Percent) or more of the
share capital of the Company or;
b) a Company in which the Company, directly or indirectly, holds 10% (Ten Percent)
or more of the share capital of such Company or;
c) a Company in which the Company, directly or indirectly, has the power to direct or
cause to be directed the management and policies of such Company whether through
the ownership of securities or agreement or any other arrangement or otherwise or;
d) a Company which, directly or indirectly, has the power to direct or cause to be
directed the management and policies of the Company whether through the
ownership of securities or agreement or any other arrangement or otherwise or;
e) a Company which is under common control with the Company, and control means
ownership by one Company of at least 10% (Ten Percent) of the share capital of the
other Company or power to direct or cause to be directed the management and
policies of such Company whether through the ownership of securities or agreement
or any other arrangement or otherwise;
Provided that entities which have Government shareholding, financial institution,
scheduled bank, foreign institutional investor, Non-Banking Financial Company, and any
mutual fund, pension funds, sovereign funds and funds managed by National Investment
and Infrastructure Fund Limited shall not be deemed to be Group Company, and its
shareholding and the power to direct or cause to be directed the management and policies
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 29 of 53
for Preparation of Detailed Project Reports (DPRs)of a Company shall not be considered for the purposes of this definition unless it is the
Project Company or a Member of the Consortium developing the Project.
xvi. “INTERESTED PARTIES” shall mean a situation where control is equally distributed
among interested parties in the Group Company or Bidding Consortium;
xvii. “JOINT CONTROL” shall mean a situation where a company has multiple promoters
(but none of the shareholders has more than 50% of voting rights and paid up share
capital).
xviii. “JOINT VENTURE” or “JV” shall mean a joint agreement, whereby the parties that
have joint control of the arrangement have the right to its net assets, which collectively
submit the response in accordance with the provisions of this CfP under a JV Agreement.
xix. “LEAD MEMBER OF THE BIDDING CONSORTIUM/JV” or “LEAD
MEMBER”: There shall be only one Lead Member, who shall be authorized to act as
the Lead Member by all the other members in the Bidding Consortium/JV.
xx. “LETTER OF AWARD” or “LoA” shall mean the letter issued by Solar Energy
Corporation of India Limited (SECI) to the selected Bidder(s) for award of the Project.
xxi. “LIMITED LIABILITY PARTNERSHIP” or “LLP” shall mean a Company
governed by Limited Liability Partnership Act 2008 or as amended.
xxii. “LLC” shall mean Limited Liability Company.
xxiii. “MEMBER IN A BIDDING CONSORTIUM/JV” or “MEMBER” shall mean each
Company in a Bidding Consortium. In case of a Technology Partner being a member in
the Consortium, it has to be a Company.
xxiv. “MISSION” shall mean the National Green Hydrogen Mission.
xxv. “MONTH” shall mean calendar month.
xxvi. “NET-WORTH” shall mean the Net-Worth as defined in section 2 of the Companies
Act, 2013.
xxvii. “PAID-UP SHARE CAPITAL” shall mean the paid-up share capital as defined in
Section 2 of the Companies Act, 2013.
xxviii. “PARENT” shall mean a Company, which holds more than 50% voting rights and paid
up share capital, either directly or indirectly in the Project Company or a Member in a
Consortium developing the Project.
xxix. “PROJECT” shall mean the Green Hydrogen Hub, comprising all the assets required
to set up the Hub under this CfP.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 30 of 53
for Preparation of Detailed Project Reports (DPRs)xxx. “PROJECT LOCATION” shall mean the area identified by the EA, comprising
village(s), Tehsil(s)/Taluk(s) and District(s) within a State, where the hydrogen
Hub/Project is being set up.
xxxi. “PROMOTER” shall mean Promoter as defined in the Companies Act, 2013.
xxxii. “SECI” shall mean Solar Energy Corporation of India Limited.
xxxiii. “SELECTED APPLICANT” or “SUCCESSFUL APPLICANT” shall mean the
Applicant selected pursuant to this CfP to set up the Project as per the terms of CfP/LoA.
xxxiv. “STATUTORY AUDITOR” shall be as defined in the Companies Act, 2013.
xxxv. “TOE” shall mean Tender Opening Event.
xxxvi. “ULTIMATE PARENT” shall mean a Company, which owns more than 50% (Fifty
Percent) voting rights and paid up share capital, either directly or indirectly in the Parent
and Affiliates.
xxxvii. “WEEK” shall mean calendar week.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 31 of 53
for Preparation of Detailed Project Reports (DPRs)SECTION 7. SAMPLE FORMS & FORMATS FOR PROPOSAL
SUBMISSION
The following formats are required to be submitted as part of the CfP. These formats are
designed to demonstrate the Applicant’s compliance with the Qualification Requirements set
forth in Section 4 and other submission requirements specified in the CfP.
Format 7.1
COVERING LETTER
(The Covering Letter should be submitted on the Letter Head of the Applicant/Lead
Member of Consortium/JV)
Ref. No. _________ Date: ___________
From: ____________ (Insert name and address of Applicant Company/ Lead Member of
Consortium/JV)
Tel.#:
E-mail address#
To,
Solar Energy Corporation of India Limited
6th Floor, Plate-B, NBCC Office Block Tower-2,
East Kidwai Nagar, New Delhi - 110 023
Sub: Response to CfP No. ………... dated …………... for …………………….(Insert title of
the CfP)
Dear Sir/ Madam,
We, the undersigned ……. [insert name of the ‘Applicant’] having read, examined and
understood in detail the CfP including the Qualification Requirements in particular, terms and
conditions, hereby submit our response to CfP.
We confirm that we, including our Ultimate Parent Company/ Parent Company/ Affiliate/
Group Companies, directly or indirectly, have not submitted response to ‘ Call for Proposals
(CfP) for Selection of Executing Agency for Preparation of Detailed Project Reports (DPRs)’,
other than this response to CfP.
We are submitting the proposal against this CfP for submission of DPR for development of
Hydrogen Hub following Project: -
Name of
Location of the Capacity of the Green
Name of the Green Hydrogen Hub
Green Hydrogen Hydrogen Hub
Hydrogen Hub Developer (If
Hub (Proposed)
decided)
City:
District:
State:
Area Covered:
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 32 of 53
for Preparation of Detailed Project Reports (DPRs)1. We give our unconditional acceptance to the CfP, dated …………….…. [Insert date in
dd/mm/yyyy], issued by SECI. In token of our acceptance to the CfP document along
with the amendments and clarifications issued by SECI, the same have been digitally
signed by us and enclosed with the response to CfP. We shall ensure that provisions of
CfP shall be binding on us. Further, we confirm that we shall submit the DPR within the
deadline as per Clause 7 of section II of the CfP.
2. We will provide all the information/ documents as requested by SECI/MNRE or its
representative (individual or firm) during the period of implementation of this scheme.
We also undertake to provide unrestricted access to the SECI/MNRE or its representative
(individual or firm) for physical inspection for implementation of the scheme.
3. We have submitted our response to CfP strictly as per Section 7 (Sample Forms and
Formats) of this CfP, without any deviations, conditions and without mentioning any
assumptions or notes in the said Formats.
4. We understand that MNRE/SECI will also be entitled to make provisions for adequate
safeguards, including for periodical special audits and appointing technical organizations
to conduct sample checks to verify claims of Executing Agency.
5. We undertake to submit necessary documents to SECI/MNRE in support of the CFA
claimed for the milestone achieved.
6. We undertake that the decision of SECI/MNRE would be final and binding upon us with
respect to release of incentives.
7. Acceptance:-
We hereby unconditionally and irrevocably agree and accept that the decision made by
SECI in respect of any matter regarding or arising out of the CfP shall be binding on us.
We hereby expressly waive and withdraw any deviations from the provisions of the CfP
and all claims in respect of this process.
We also unconditionally and irrevocably agree and accept that the decision made by
SECI in respect of award of Projects in line with the provisions of the CfP, shall be
binding on us.
8. Familiarity with Relevant Indian Laws & Regulations:-
We confirm that we have studied the provisions of the relevant Indian Laws and
Regulations as required to enable us to submit this response to CfP and execute the
project, in the event of our selection as Successful Applicant.
9. We are submitting our response to the CfP with formats duly signed as desired by you in
the CfP online for your consideration.
10. It is confirmed that our response to the CfP is consistent with all the requirements of
submission as stated in the CfP, including all clarifications and amendments and
subsequent communications from SECI.
11. The information submitted in our response to the CfP is correct to the best of our
knowledge and understanding. We would be solely responsible for any errors or
omissions in our response to the CfP.
12. We confirm that all the terms and conditions of our proposal are valid up to 12 months
from the last date of submission under this CfP.
13. Contact Person
Details of the representative to be contacted by SECI are furnished as under:
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 33 of 53
for Preparation of Detailed Project Reports (DPRs)Name : ……………………………………
Designation : ……………………………………
Company : ……………………………………
Address : ……………………………………
Phone Nos. : ……………………………………
Mobile Nos. : ……………………………………
E-mail address : ……………………………………
14. We have neither made any statement nor provided any information in this proposal,
which to the best of our knowledge is materially inaccurate or misleading. Further, all
the confirmations, declarations and representations made in our Proposal are true and
accurate. In case this is found to be incorrect after our selection as Successful Applicant,
we agree that the LoA will be terminated and incentive disbursed, if any shall be
recovered from us.
Dated the _____________ day of________, 20….
Thanking you,
We remain,
Yours faithfully,
Name, Designation, Seal and Signature of Authorized Person in whose name Power of
Attorney/ Board Resolution/ Declaration.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 34 of 53
for Preparation of Detailed Project Reports (DPRs)Format 7.2
FORMAT FOR POWER OF ATTORNEY
(Applicable Only in case of Consortium/JV)
(To be provided by each of the other members of the Consortium/JV in favor of the Lead
Member)
(To be stamped in accordance with Stamp Act, the Non-Judicial Stamp Paper of
Appropriate Value)
(The term “Consortium” in this draft may be replaced with “Joint Venture” in case of
Applicants participating in a JV)
KNOW ALL MEN BY THESE PRESENTS THAT M/s…………….……………. having
its registered office at ………………………….……., …., and M/s …………………….….
having its registered office at …………………………………., (Insert names and
registered offices of all Members of the Consortium) the Members of Consortium have
formed a Consortium named ……………………. (Insert name of the Consortium if
finalized) (hereinafter called the ‘Consortium’) vide Consortium Agreement
dated……….……………… and having agreed to appoint
M/s……………………………..…as the Lead Member of the said Consortium do hereby
constitute, nominate and appoint M/s…………….…………..a company incorporated under
the laws of ……….………and having its Registered/ Head Office at
……………………..……….as our duly constituted lawful Attorney (hereinafter called as
Lead Member) to exercise all or any of the powers for and on behalf of the Consortium in
regard to submission of the response to CfP No……………..
We also authorize the said Lead Member to undertake the following acts:
1. To submit on behalf of Consortium Members response to CfP.
2. To do any other act or submit any information and document related to the above
response to CfP.
It is expressly understood that in the event of the Consortium being selected as Successful
Applicant, this Power of Attorney shall remain valid, binding and irrevocable until the
Consortium achieves execution of the Project.
We, as the Member of the Consortium, agree and undertake to ratify and confirm all
whatsoever the said Attorney/ Lead Member has done on behalf of the Consortium Members
pursuant to this Power of Attorney and the same shall bind us and deemed to have been
done by us.
IN WITNESS WHEREOF M/s ………………………………………….……., as the
Member of the Consortium have executed these presents on this………. day of ........under
the Common Seal of our company.
For and on behalf of Consortium Member
M/s………………………….
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 35 of 53
for Preparation of Detailed Project Reports (DPRs)-------------------------------- (Signature of person authorized by the board)
(Name
Designation
Place:
Date:)
Accepted
---------------------------------
(Signature, Name, Designation and Address
of the person authorized by the board of the Lead Member)
Attested
---------------------
(Signature of the executant)
------------------------------
(Signature & stamp of Notary of the place of execution)
Place: ----------------
Date: ------------------
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 36 of 53
for Preparation of Detailed Project Reports (DPRs)Format 7.3
FORMAT FOR BOARD RESOLUTIONS
The Board, after discussion, at the duly convened Meeting on ………… [Insert date], with
the consent of all the Directors present and in compliance of the provisions of the Companies
Act, 1956 or Companies Act 2013, as applicable, passed the following Resolution:
1. RESOLVED THAT Mr/ Ms.………………., be and is/are hereby authorized to do on
our behalf, all such acts, deeds and things necessary in connection with or incidental to our
response to CfP vide CfP No. ______________for ____________(Insert title of the CfP),
including signing and submission of all documents and providing information/ response to
CfP to Solar Energy Corporation of India Limited (SECI), representing us in all matters
before SECI, and generally dealing with SECI in all matters in connection with our proposal
for the said Project. (To be provided by the Applicant or the Lead Member of the
Consortium/JV)
FURTHER RESOLVED THAT approval of the Board be and is hereby accorded to
participate in consortium with M/s ------------ [Insert the name of other Members in the
Consortium/JV] and Mr/ Ms………………., be and is hereby authorized to execute the
Consortium/JV Agreement. (To be provided by each Member of the Consortium/JV
including Lead Member)
Certified True Copy
----------------------------
(Signature, Name and Stamp of Company Secretary)
Notes:
1. This certified true copy should be submitted on the letterhead of the Company, signed by
the Company Secretary/ Director.
2. The contents of the format may be suitably re-worded indicating the identity of the entity
passing the resolution.
3. This format may be modified only to the limited extent required to comply with the local
regulations and laws applicable to a foreign entity submitting this resolution. For
example, reference to Companies Act, 1956 or Companies Act, 2013 as applicable may
be suitably modified to refer to the law applicable to the entity submitting the resolution.
However, in such case, the foreign entity shall submit an unqualified opinion issued by
the legal counsel of such foreign entity, stating that the Board resolutions are in
compliance with the applicable laws of the respective jurisdictions of the issuing
Company and the authorizations granted therein are true and valid.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 37 of 53
for Preparation of Detailed Project Reports (DPRs)Format 7.4
FORMAT FOR CONSORTIUM/JOINT VENTURE AGREEMENT
(To be stamped in accordance with Stamp Act, the Non-Judicial Stamp Paper of Appropriate
Value)
(The term “Consortium” in this draft may be replaced with “Joint Venture” in case of
Applicants participating in a JV)
THIS Consortium/Joint Venture (JV) Agreement (“Agreement”) executed on this ___ Day of
___________ Two Thousand _____ between M/s _____________________________ [Insert
name of Lead Member] a Company incorporated under the laws of _______ and having its
Registered Office at _________________________________ (hereinafter called the
“Member-1”, which expression shall include its successors, executors and permitted assigns)
and M/s ________________________________ a Company incorporated under the laws
of _______ and having its Registered Office at
____________________________________ (hereinafter called the “Member-2”, which
expression shall include its successors, executors and permitted assigns), M/s
____________________________________ a Company incorporated under the laws of
_________ and having its Registered Office at ________________________________
(hereinafter called the “Member-n”, which expression shall include its successors,
executors and permitted assigns), [The Consortium/JV should list the details of all the
Consortium/JV Members] for the purpose of submitting response to CfP, against CfP No.
___________dated _______issued by Solar Energy Corporation of India Limited (SECI) a
Company incorporated under the Companies Act, 2013, and having its Registered Office
at 6th Floor, Plate-B, NBCC Office Block Tower-2, East Kidwai Nagar, New Delhi – 110023.
WHEREAS, each Member individually shall be referred to as the “Member” and all of the
Members shall be collectively referred to as the “Members” in this Agreement.
WHEREAS, SECI had invited response to CfP vide its CfP dated ____________.
WHEREAS the CfP stipulates that in case response to CfP is being submitted by a
Consortium/JV, the Members of the Consortium/JV will have to submit a legally enforceable
Consortium/JV Agreement in a format specified by SECI wherein the Consortium/JV
Members have to commit equity investment of a specific percentage for the Project.
NOW THEREFORE, THIS AGREEMENT WITNESSTH AS UNDER:
In consideration of the above premises and agreements all the Members in this Consortium/JV
do hereby mutually agree as follows:
1. We, the Members of the Consortium/JV and Members to the Agreement do hereby
unequivocally agree that Member-1 (M/s_______________), shall act as the Lead
Member as defined in the CfP for self and agent for and on behalf of Member-2, _____,
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 38 of 53
for Preparation of Detailed Project Reports (DPRs)Member-n and to submit the response to the CfP.
2. The Lead Member is hereby authorized by the Members of the Consortium/JV and
Members to the Agreement to bind the Consortium and receive instructions for and on
their behalf.
3. Notwithstanding anything contrary contained in this Agreement, the Lead Member shall
always be liable for the equity investment obligations of all the Consortium/JV Members
i.e. for both its own liability as well as the liability of other Members.
4. The Lead Member shall be liable and responsible for ensuring the individual and
collective commitment of each of the Members of the Consortium/JV in discharging all
of their respective equity obligations. Each Member further undertakes to be individually
liable for the performance of its part of the obligations without in any way limiting the
scope of collective liability envisaged in this Agreement.
5. Subject to the terms of this Agreement, the share of each Member of the Consortium/JV
in the issued equity share capital of the Project Company is/shall be in the following
proportion:
Name Percentage
Member 1 ---
Member 2 ---
Member n ---
Total 100%
6. The Lead Member, on behalf of the Consortium, shall inter alia undertake full
responsibility for liaising with Lenders or through internal accruals and mobilizing debt
resources for the Project, and ensuring that the Executing Agency achieves Financial
Closure and commission the Project as per the terms of CFP.
7. In case of any breach of any equity investment commitment by any of the Consortium/JV
Members, the Lead Member shall be liable for the consequences thereof.
8. Except as specified in the Agreement, it is agreed that sharing of responsibilities as
aforesaid and equity investment obligations thereto shall not in any way be a limitation
of responsibility of the Lead Member under these presents.
9. It is further specifically agreed that the financial liability for equity contribution of the
Lead Member shall not be limited in any way so as to restrict or limit its liabilities. The
Lead Member shall be liable irrespective of its scope of work or financial commitments.
10. This Agreement shall be construed and interpreted in accordance with the Laws of India
and courts at New Delhi alone shall have the exclusive jurisdiction in all matters relating
thereto and arising thereunder.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 39 of 53
for Preparation of Detailed Project Reports (DPRs)11. It is further expressly agreed that the Agreement shall be irrevocable and shall form an
integral part of the contract and shall remain valid until the expiration or early termination
of the LoA in terms hereof, unless expressly agreed to the contrary by SECI.
12. The Lead Member is authorized and shall be fully responsible for the accuracy and
veracity of the representations and information submitted by the Members respectively
from time to time in the response to CfP.
13. It is hereby expressly understood between the Members that no Member at any given
point of time, may assign or delegate its rights, duties or obligations under the CfP except
with prior written consent of SECI.
14. This Agreement
a) has been duly executed and delivered on behalf of each Member hereto and
constitutes the legal, valid, binding and enforceable obligation of each such Member;
b) sets forth the entire understanding of the Members hereto with respect to the subject
matter hereof; and
c) may not be amended or modified except in writing signed by each of the Members
and with prior written consent of SECI.
15. All the terms used in capitals in this Agreement but not defined herein shall have the
meaning as per the CfP.
IN WITNESS WHEREOF, the Members have, through their authorized representatives,
executed these present on the Day, Month and Year first mentioned above.
For M/s----------------------------- [Member 1]
-----------------------------------------
(Signature, Name & Designation of the person authorized vide Board Resolution Dated
_________)
Witnesses:
1) Signature----------------------- 2) Signature ---------------------
Name: Name:
Address: Address:
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 40 of 53
for Preparation of Detailed Project Reports (DPRs)For M/s----------------------------- [Member 2]
-----------------------------------------
(Signature, Name & Designation of the person authorized vide Board Resolution Dated
_________)
Witnesses:
1) Signature ----------------------- 2) Signature ----------------------
Name: Name:
Address: Address:
For M/s----------------------------- [Member n]
-----------------------------------------
(Signature, Name & Designation of the person authorized vide Board Resolution Dated
_________)
Witnesses:
1) Signature ----------------------- (2) Signature ----------------------
Name: Name:
Address: Address:
__________________________________________
Signature and stamp of Notary of the place of execution
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 41 of 53
for Preparation of Detailed Project Reports (DPRs)FORMAT 7.5
UNDERTAKING
(To be submitted on the letterhead of the Applicant/each member of Consortium/JV)
We, hereby provide this undertaking to Solar Energy Corporation of India Limited, in respect
to our response to CfP vide CfP No. _____________dated___________, that as on the last date
of proposal submission, M/s ___________________ (insert name of the Applicant), or any of
its Affiliates is not a wilful defaulter to any lender. We further undertake that as on the last date
of proposal submission, M/s _______ (Insert name of the Applicant) & any of its Affiliate,
including any Consortium/JV Member & any of its Affiliate, their directors have not been
barred or included in the blacklist, by any government agency or authority in India, the
government of the jurisdiction of the Applicant or Members where they are incorporated or the
jurisdiction of their principal place of business, any international financial institution such as
the World Bank Group, Asian Development Bank, African Development Bank, Inter-
American Development Bank, Asian Infrastructure Investment Bank etc. or the United Nations
or any of its agencies.
We further declare that the above statement is true & correct. We undertake that if at any stage
it is found to be incorrect for our DPR for setting up of Green Hydrogen Hubs under the
scheme, SECI/PAC will be entitled to cancel sanctioned CFA and we agree to pay any charges
towards penalties/recoveries as imposed by SECI.
(Signature, Name & Designation of the Authorized Signatory)
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 42 of 53
for Preparation of Detailed Project Reports (DPRs)Format 7.6
FORMAT FOR DISCLOSURE
(To be submitted on the Letter Head of the Applicant/ Each Member of Consortium/JV)
DISCLOSURE
Ref. No. _________ Date:
___________
From: ________ (Insert name and address of Applicant/ Lead Member of Consortium/JV)
Tel. #:
E-mail address#
To
(Enter Address of SECI)
Sub: Response to CfP No. _____________ dated ________ for _____________.
Dear Sir/ Madam,
We hereby declare and confirm that only we are participating in the CfP Selection process for
the CfP No.____________ and that our Parent, Affiliate or Ultimate Parent or any Group
Company with which we have direct or indirect relationship are not separately participating in
this selection process.
We further declare and confirm that in terms of the definitions of the CfP, M/s
_________________ (enter name of the Promoter/Promoters) is/are our Promoter(s), and
has/have a direct/indirect Control in the Applicant company as per the Companies Act 2013.
No other entity has a direct/indirect control in the Applicant except the entity(ies) mentioned
above.
We further declare that the above statement is true & correct. We undertake that if at any stage
it is found to be incorrect, in addition to actions applicable under the CfP including but not
limited to cancellation of our response to this CfP and LoA as applicable, we, i.e. M/s
______________(enter name of the Applicant company/member in a consortium), including
our Parent, Ultimate Parent, and our Affiliates shall be suspended/debarred from participating
in any of the upcoming tenders issued by SECI for a period of 2 years from the date of default
as notified by SECI.
We also understand that the above is in addition to the penal consequences that may follow
from the relevant laws for the time being in force.
Dated the _____________ day of________, 20___.
Thanking you,
We remain,
Yours faithfully,
Name, Designation, Seal and Signature of Authorized Person in whose name Power of
Attorney/ Board Resolution/ Declaration.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 43 of 53
for Preparation of Detailed Project Reports (DPRs)PRICE SCHEDULE
(On Applicant’s/Bidder’s letter head)
PRICE SCHEDULE
Call for Proposals (CfP) for Selection of Executing Agency for Preparation of
Detailed Project Reports (DPRs)
NOTE:
a) The bidder has to quote CFA only on electronic form on
https://www.bharatelectronictender.com . Quoting in any other manner will summarily
be liable for rejection.
b) Payment will be made as mentioned in the payment terms.
c) Bidder confirms that he has noted the contents of the Preamble to Price Schedule, Bid
Document and quoted his CFA accordingly without any deviation.
d) Maximum CFA that can be quoted in price schedule is Rs 3 Crore per DPR.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 44 of 53
for Preparation of Detailed Project Reports (DPRs)CERTIFICATE REGARDING ANNUAL TURNOVER
(To be issued on the letterhead of a practicing Chartered Accountant)
This is to certify that the Annual Turnover of M/s. ……. [Name of the Applicant], having its
registered office at ………. [Address], for the last three financial years is as follows:
Financial Year Annual Turnover (INR in
Crores)
2024-25
2023-24
2022-23
Total Turnover (3 Years):………. [Amount]
Average Annual Turnover:……… [Amount]
The above figures have been verified from the audited financial statements/records of the
Applicant and are true and correct to the best of our knowledge.
Seal & Signature of Chartered Accountant
Name: _______________________
Membership No.: _____________
Firm Registration No.: ________
UDIN Number:______________
Date: ________________________
Place: _______________________
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 45 of 53
for Preparation of Detailed Project Reports (DPRs)Annexure – A
CHECKLIST FOR SUBMISSION OF PROPOSAL
Name of the Applicant:
(In case of JV/ Consortium, name of all the members to be indicated and lead member to be
identified)
Type of the Applicant:
(Company, CPSU, State-PSU, Private Sector, State Corporation, Autonomous bodies, JV/
Partnerships/ Consortiums of above stated agencies)
Submitted
S.no. Name of document Page no. Remarks (if any)
or not
1 Format 7.1 (Covering Letter)
2 Format 7.2 (Power of Attorney)
3 Format 7.3 (Board Resolution)
4 Format 7.4 (Consortium
Agreement)
5 Format 7.5 (Undertaking)
6 Format 7.6 (Disclosure)
7 Certificate of Incorporation
8 Article of Association
9 Memorandum of Association
10 Brief profile of Organization and
Organizational chart
11 CA certificate for Liquidity and
Turnover
12 A certificate of shareholding of the
Applicant company duly certified
by a practicing Chartered
Accountant/ Company Secretary as
on a date within 30 days prior to the
last date of Proposal submission
13 Certified copies of annual audited
accounts for the last financial year
14 Certified copies of Balance Sheet,
Profit & Loss Account, Schedules
and Cash Flow Statement supported
with bank statements for last 3
Financial years
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 46 of 53
for Preparation of Detailed Project Reports (DPRs)15 Details of all types of
securities/instruments which are
pending conversion into equity
whether optionally or mandatorily
16 Documents for scoring
a Green Hydrogen Production
approved/ agreement signed or
under process/MoU
b
Infrastructure available and planned
c Natural Resource availability
i RE Sourcing
ii Water Sourcing
iii Land availability
d Presence of multiple end-use
industries and current H2 demand in
the region and projections for next 5
years
e Proximity to an export
terminal/demand centre of
minimum capacity of 50,000 MT
f Firm off-take agreements signed (in
MT of H2 or H2 derivatives)
g Financial viability of the proposed
hub
h Equity investment by the Hydrogen
Hub developer
i Debt tied up with the financial
institutions out of total debt required
for the project
j Any other fact deemed relevant in
development of Green hydrogen
hub
Date: Name, designation and signature
of Authorized Signatory
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 47 of 53
for Preparation of Detailed Project Reports (DPRs)Annexure – B
SPECIAL INSTRUCTIONS TO BIDDERS FOR e-TENDERING
For participating in this tender online, the following instructions are to be read carefully. These
instructions are supplemented with more detailed guidelines on the relevant screens of the ETS.
GENERAL
The Special Instructions (for e-Tendering) supplement ‘Instructions to Bidders’, as given in
these CfP Documents. Submission of Online Bids is mandatory for this CfP.
e-Tendering is a new methodology for conducting Public Procurement in a transparent and
secured manner. Now, the Government of India has made e-Tendering mandatory. Suppliers/
Vendors will be the biggest beneficiaries of this new system of procurement. For conducting
electronic tendering, Solar Energy Corporation of India Limited (SECI) has adopted a secured
and user-friendly e-tender system enabling bidders to Search, View, Download tender
document(s) directly from the e-tendering portal of M/s Electronic Tender.com (India) Pvt.
Limited https://www.bharat-electronictender.com through ISN-ETS. This portal is based on
the world’s most ‘secure’ and ‘user friendly’ software from ElectronicTender®. A portal built
using ElectronicTender’s software is also referred to as ElectronicTender System® (ETS).
Benefits to Suppliers are outlined on the Home-page of the portal.
INSTRUCTIONS
Tender Bidding Methodology:
Sealed Bid System
Single Stage One Envelope
Broad Outline of Activities from Bidder’s Perspective:
1. Procure a Class III Digital Signing Certificate (DSC).
2. Register on ElectronicTender System® (ETS)
3. Create Marketing Authorities (MAs), Users and assign roles on ETS. It is mandatory to
create at least one MA
4. View Notice Inviting Tender (NIT) on ETS
5. For this tender -- Assign Tender Search Code (TSC) to a MA
6. Download Official Copy of Tender Documents from ETS. Note: Official copy of
Tender Documents is distinct from downloading ‘Free Copy of Tender Documents’. To
participate in a tender, it is mandatory to procure official copy of Tender Documents
for that tender.
7. Clarification to Tender Documents on ETS
i. Query to SECI (Optional)
ii. View response to queries posted by SECI
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 48 of 53
for Preparation of Detailed Project Reports (DPRs)8. Bid-Submission on ETS
9. Post-TOE clarification on ETS (optional)
10. Respond to SECI Post-TOE queries
For participating in this tender online, the following instructions are to be read carefully. These
instructions are supplemented with more detailed guidelines on the relevant screens of the ETS.
Digital Certificates
For integrity of data and authenticity/ non-repudiation of electronic records, and to be compliant
with IT Act 2000, it is necessary for each user to have a Digital Certificate (DC), also referred
to as Digital Signature Certificate (DSC), of Class III, issued by a Certifying Authority (CA)
licensed by Controller of Certifying Authorities (CCA) [refer http://www.cca.gov.in].
Registration
To use the ElectronicTender® portal https://www.bharat-electronictender.com, vendors need
to register on the portal. Registration of each organization is to be done by one of its senior
persons who will be the main person coordinating for the e-tendering activities. In ETS
terminology, this person will be referred to as the Super User (SU) of that organization. For
further details, please visit the website/ portal, and click on the ‘Supplier Organization’ link
under ‘Registration’ (on the Home Page), and follow further instructions as given on the site.
Pay Annual Registration Fee as applicable.
After successful submission of Registration details and payment of Annual Registration Fee,
please contact ISN-ETS Helpdesk (as given below), to get your registration accepted/ activated.
Important Note:
1. Interested bidders have to download official copy of the CfP & other documents after login
into the e-tendering Portal of ISN-ETS https://www.bharat-electronictender.com. If the
official copy of the documents is not downloaded from e-tendering Portal of ISN-ETS within
the specified period of downloading of CfP and other documents, bidder will not be able to
participate in the tender.
2. To minimize teething problems during the use of ETS (including the Registration process),
it is recommended that the user should peruse the instructions given under ‘ETS User-
Guidance Centre’ located on ETS Home Page, including instructions for timely registration
on ETS. The instructions relating to ‘Essential Computer Security Settings for Use of ETS’
and ‘Important Functionality Checks’ should be especially taken into cognizance.
Please note that even after acceptance of your registration by the Service Provider, to
respond to a tender you will also require time to complete activities related to your
organization, such as creation of users, assigning roles to them, etc.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 49 of 53
for Preparation of Detailed Project Reports (DPRs)ISN-ETS/
Helpdesk
Customer Support: +91-124-4229071, 4229072
Telephone/
( From 1000 HRS to 1800 HRS on all Working Days i.e. Monday
Mobile
to Friday except Government Holidays)
support@isn-ets.com
Email-ID
[Please mark CC: support@electronictender.com]
Some Bidding Related Information for this Tender (Sealed Bid)
The entire bid-submission would be online on ETS (unless specified for Offline Submissions).
Broad outline of submissions are as follows:
1. Submission of Proposal
2. Submission of digitally signed copy of Tender Documents/ Addendum
Note: The Bidder should also upload the scanned copies of all the above mentioned original
documents as Bid-Annexures during Online Bid-Submission.
Internet Connectivity
If bidders are unable to access ISN-ETS’s e-tender portal or Bid Documents, the bidders may
please check whether they are using proxy to connect to internet or their PC is behind any
firewall and may contact their system administrator to enable connectivity. Please note that
Port SSL/ 443 should be enabled on proxy/firewall for HTTPS connectivity. Dial-up/ Broad
and internet connectivity without Proxy settings is another option
SPECIAL NOTE ON SECURITY AND TRANSPARENCY OF BIDS
Security related functionality has been rigorously implemented in ETS in a multidimensional
manner. Starting with 'Acceptance of Registration by the Service Provider', provision for
security has been made at various stages in Electronic Tender’s software. Specifically, for Bid
Submission, some security related aspects are outlined below:
As part of the Electronic Encrypted® functionality, the contents of both the ‘ElectronicForms®’
and the ‘Main-Bid’ are securely encrypted using a Pass-Phrase created by the Bidder himself.
Unlike a ‘password’, a Pass-Phrase can be a multi-word sentence with spaces between words
(e.g. I love this World). A Pass-Phrase is easier to remember, and more difficult to break. It is
mandatory that a separate Pass-Phrase be created for each Bid-Part. This method of bid-
encryption does not have the security and data-integrity related vulnerabilities which are
inherent in e-tendering systems which use Public-Key of the specified officer of a Buyer
organization for bid-encryption. Bid-encryption in ETS is such that the Bids cannot be
decrypted before the Public Online Tender Opening Event (TOE), even if there is connivance
between the concerned tender-opening officers of the Buyer organization and the personnel of
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 50 of 53
for Preparation of Detailed Project Reports (DPRs)e-tendering service provider.
CAUTION: All bidders must fill ElectronicForms® for each bid-part sincerely and carefully,
and avoid any discrepancy between information given in the ElectronicForms® and the
corresponding Main-Bid. For transparency, the information submitted by a bidder in the
ElectronicForms® is made available to other bidders during the Online Public TOE. If it is
found during the Online Public TOE that a bidder has not filled in the complete information in
the ElectronicForms®, the TOE officer may make available for downloading the corresponding
Main-Bid of that bidder at the risk of the bidder. If variation is noted between the
information contained in the ElectronicForms® and the ‘Main-Bid’, the contents of the
ElectronicForms® shall prevail.
In case of any discrepancy between the values mentioned in figures and in words, the value
mentioned in words will prevail.
The bidder shall make sure that the Pass-Phrase to decrypt the relevant Bid-Part is
submitted into the ‘Time Locked Electronic Key Box (EKB)’ after the deadline of Bid
Submission, and before the commencement of the Online TOE of Technical Bid. The
process of submission of this Pass-Phrase in the ‘Time Locked Electronic Key Box’ is done in
a secure manner by first encrypting this Pass-Phrase with the designated keys provided by
SECI.
Additionally, the bidder shall make sure that the Pass-Phrase to decrypt the relevant Bid-Part
is submitted to SECI in a sealed envelope before the start date and time of the Tender Opening
Event (TOE).
There is an additional protection with SSL Encryption during transit from the client-end
computer of a Supplier organization to the e-Tendering Server/ Portal.
OTHER INSTRUCTIONS
For further instructions, the vendor should visit the home-page of the portal
https://www.bharat-electronictender.com, and go to the User-Guidance Center
The help information provided through ‘ETS User-Guidance Center’ is available in three
categories – Users intending to Register/ First-Time Users, Logged-in users of Buyer
organizations, and Logged-in users of Supplier organizations. Various links (including links
for User Manuals) are provided under each of the three categories.
Important Note: It is strongly recommended that all authorized users of Supplier organizations
should thoroughly peruse the information provided under the relevant links, and take
appropriate action. This will prevent hiccups, and minimize teething problems during the use
of ETS.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 51 of 53
for Preparation of Detailed Project Reports (DPRs)SEVEN CRITICAL DO’S AND DON’TS FOR BIDDERS
Specifically, for Supplier organizations, the following 'SEVEN KEY INSTRUCTIONS for
BIDDERS' must be assiduously adhered to:
1. Obtain individual Digital Signing Certificate (DSC or DC) of Class III well in advance
of your tender submission deadline on ETS.
2. Register your organization on ETS well in advance of the important deadlines for your
first tender on ETS viz ‘Date and Time of Closure of Procurement of Tender Documents’
and ‘Last Date and Time of Receipt of Bids’. Please note that even after acceptance of
your registration by the Service Provider, to respond to a tender you will also require
time to complete activities related to your organization, such as creation of -- Marketing
Authority (MA) [ie a department within the Supplier/ Bidder Organization responsible
for responding to tenders], users for one or more such MAs, assigning roles to them, etc.
It is mandatory to create at least one MA. This unique feature of creating an MA enhances
security and accountability within the Supplier/ Bidder Organization
3. Get your organization's concerned executives trained on ETS well in advance of your
first tender submission deadline on ETS.
4. For responding to any particular tender, the tender (i.e. its Tender Search Code or TSC)
has to be assigned to an MA. Further, an ‘Official Copy of Tender Documents’ should
be procured/ downloaded before the expiry of Date and Time of Closure of Procurement
of Tender Documents. Note: Official copy of Tender Documents is distinct from
downloading ‘Free Copy of Tender Documents’. Official copy of Tender Documents is
the equivalent of procuring physical copy of Tender Documents with official receipt in
the paper-based manual tendering system.
5. Submit your bids well in advance of tender submission deadline on ETS (There could be
last minute problems due to internet timeout, breakdown, etc.)
Note: Bid-submission in ETS can consist of submission of multiple bid-components,
which vary depending upon the situation and requirements of the Buyer. Successful
receipt of a bid in an e-tendering scenario takes place if all the required bid-components
are successfully ‘received and validated’ in the system (ETS) within the scheduled date
and time of closure of bidding. ETS/ Service Provider is not responsible for what happens
at an end-user’s end, or while a submission made by an end-user is in transit, until the
submission is successfully ‘received and validated’ in ETS.
6. It is the responsibility of each bidder to remember and securely store the Pass-Phrase for
each Bid-Part submitted by that bidder. The bidders are required to submit correct, valid
and operative Pass-Phrase to decrypt either Technical Bid Part or Financial Bid Part in a
separate sealed envelope before due date and time of submission of bid. In the event, the
bids are not opened with the pass-phrase submitted by bidder, SECI may ask for re-
submission/ clarification for correct pass-phrase. In the event of a bidder forgetting the
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 52 of 53
for Preparation of Detailed Project Reports (DPRs)Pass-Phrase before the expiry of deadline for Bid-Submission, facility is provided to the
bidder to ‘Annul Previous Submission’ from the Bid-Submission Overview page and
start afresh with new Pass-Phrase(s). If bidder fails to submit correct pass-phrase
immediately as requested by SECI, the Bid Processing Fee and Cost of CfP Document,
if applicable, shall be forfeited and bid shall not be opened, and EMD shall be refunded.
No request on this account shall be entertained by SECI.
7. ETS will make your bid available for opening during the Online Public Tender Opening
Event (TOE) ‘ONLY IF’ the status pertaining Overall Bid-Submission is ‘COMPLETE’.
For the purpose of record, the bidder can generate and save a copy of ‘Final Submission
Receipt’. This receipt can be generated from 'Bid-Submission Overview Page' only if the
status pertaining overall Bid-Submission’ is ‘COMPLETE’
NOTE:
While the first three instructions mentioned above are especially relevant to first-time users of
ETS, the fourth, fifth, sixth and seventh instructions are relevant at all times.
Pre-requisite for participation in bidding process
1. Bidder must possess a PC/ Laptop with Windows 7 professional operating system and
Internet Explorer 8 or 9 for hassle free bidding. Bidder is essentially required to effect
the security settings as defined in the portal.
2. The Bidder must have a high-speed internet connectivity (preferably Broadband) with
internet explorer to access ISN-ETS’s e-Tender Portal for downloading the Tender
document and uploading/ submitting the Bids.
3. A valid e-mail ID of the Organization/ Firm
Vendors Training Program
One day online training (10:00 to 17:00) is provided by ISN-ETS. Training is optional. In case,
any bidder is interested, he may send a request to support@isn-ets.com. Vendors are requested
to arrange their own Laptop, Digital Certificate and Wireless Connectivity to the Internet.
Call for Proposals (CfP) for Selection of Executing Agency
CfP No. SECI/C&P/EOI/17/0002/25-26 Page 53 of 53
for Preparation of Detailed Project Reports (DPRs)