Executive Summary & Key Takeaways
**Policy Analysis Report: Acquisition of Land for Coal Mining in Govindpur Phase II OCP, District Bokaro, Jharkhand**
**1. Executive Summary:**
This report analyzes a government notification regarding the acquisition of land for coal mining in the Govindpur Phase II OCP area of District Bokaro, Jharkhand. The notification, issued by the Ministry of Coal, declares the government's intention to acquire approximately 440.63 acres (178.31 hectares) of land and all rights associated with it. The key finding is that this notification initiates the formal acquisition process under the Coal Bearing Areas Acquisition and Development Act, 1957, potentially affecting landowners and tenants in the Armo village. The report also highlights the process for objections and the identified responsible authorities.
**2. Introduction:**
This report provides an analysis of a notification published by the Government of India, Ministry of Coal, concerning the intended acquisition of land in the Govindpur Phase II OCP area, District Bokaro, Jharkhand. The analysis is based solely on the provided text of the notification. Its purpose is to inform affected industry stakeholders.
**3. Policy Overview:**
* This document is part of a process governed by the Coal Bearing Areas Acquisition and Development Act, 1957. It references a previous notification, S.O 1041, dated the 1st December, 2020, which declared the intention to prospect for coal in the area.
* **Core Objective:** The core objective, as stated in the text, is to acquire approximately 440.63 acres (178.31 hectares) of land, as well as all rights in or over the land, for coal mining activities.
**4. Background and Rationale:**
The provided text indicates that the rationale for this land acquisition stems from the Central Government's satisfaction that coal is obtainable in the specified lands. The earlier notification (S.O. 1041, dated December 1, 2020) signifies a prior intention to prospect for coal, suggesting positive findings that led to this acquisition notice. The underlying issue is the need for land to facilitate coal extraction.
**5. Key Provisions / Changes:**
* This notification serves as a formal notice of the Central Government's *intention* to acquire the land.
* **Land Details:** It specifies the area to be acquired (440.63 acres / 178.31 hectares) and identifies the land parcels by village (Armo), thana (Bermo), district (Bokaro), khata numbers, and plot numbers. The land includes various classifications, such as Forest, DhanI, Parti, TandIII, etc., and lists recorded tenants.
* **Objection Mechanism:** The notification explicitly refers to Section 8 of the Coal Bearing Areas Acquisition and Development Act, 1957, outlining the process for landowners to object to the acquisition within thirty days of the notification's issue. It clarifies that objections based on the objector desiring to conduct their own mining operations will not be considered.
* **Inspection:** The notification states that the plan bearing number Rev022022, dated the 21st January, 2022, the area covered by this notification may be inspected at the office of the Deputy Commissioner, District Bokaro Jharkhand or at the office of the Coal Controller, 1, Council House Street, Kolkata 700 001 or at the office of the General Manager, Kathara Area, District Bokaro Jharkhand or General Manager Land and Revenue, Central Coalfields Limited, Darbhanga, House, Ranchi 834001, Jharkhand or General Manager Exploration Division, Central Mine Planning and Design Institute Limited, Gondwana Palace, Kanke Road, Ranchi834008, Jharkhand.
**6. Target Audience and Stakeholders:**
The primary target audience and stakeholders are:
* Landowners and tenants within the identified land parcels in Armo village, Bermo thana, Bokaro district.
* The Deputy Commissioner of District Bokaro, Jharkhand
* Coal Controller, Kolkata
* General Manager, Kathara Area, District Bokaro, Jharkhand
* General Manager Land and Revenue, Central Coalfields Limited, Darbhanga, House, Ranchi
* General Manager Exploration Division, Central Mine Planning and Design Institute Limited, Gondwana Palace, Kanke Road, Ranchi
* Central Coalfields Limited (CCL).
* Central Mine Planning and Design Institute Limited (CMPDI).
* The Coal industry
**7. Implementation Aspects (Inferred):**
* **Responsible Agency/Bodies:** The Ministry of Coal is the issuing authority. The Coal Controller in Kolkata is identified as the "competent authority" for handling objections. Central Coalfields Limited (CCL) and Central Mine Planning and Design Institute Limited (CMPDI) are involved in the planning and execution. The Deputy Commissioner, District Bokaro Jharkhand, is involved with the inspection of the plan.
* **Timelines/Procedures:** A 30-day window is provided for affected parties to submit objections to the Coal Controller. The competent authority (Coal Controller) must provide objectors with an opportunity to be heard before making a report to the Central Government. The next step is the Central Government's decision based on the report and recommendations.
**8. Expected Outcomes / Impact of Changes:**
The likely intended outcome is the successful acquisition of the identified land for coal mining. This will enable the expansion or continuation of coal extraction activities in the Govindpur Phase II OCP. This acquisition will likely result in displacement and/or loss of land for the affected landowners and tenants, potentially impacting their livelihoods.
**9. Conclusion:**
The notification analyzed represents a critical step in the process of land acquisition for coal mining in the Govindpur Phase II OCP area. It formally declares the government's intention to acquire the land and outlines the process for objections. The notification has significant implications for landowners and tenants in the Armo village and sets the stage for potential changes in land use and economic activities in the region. The notification also clarifies the process and responsible parties regarding objections to the acquisition.
Key Entities Referenced
NEW DELHI : Location where the gazette was published.
Government of India : Refers to the government under which the Ministry of Coal operates.
Ministry of Coal : The government ministry issuing the notification regarding land acquisition for coal prospecting.
Coal Bearing Areas Acquisition and Development Act, 1957 : Act under which the land acquisition is being carried out.
Central Government : The governing body exercising powers under the Coal Bearing Areas Acquisition and Development Act, 1957.
Coal Controller : Office where the plan of the area covered by the notification may be inspected.
Council House Street, Kolkata : Address of the Coal Controller's office in Kolkata, West Bengal.
District Bokaro Jharkhand : District and State where the land acquisition is taking place; the Deputy Commissioner's office and the Kathara Area General Manager's office are located here.
Kathara Area : Area under a General Manager, located in District Bokaro, Jharkhand. The plan can be inspected at this office.
Central Coalfields Limited : Organisation with a General Manager of Land and Revenue, whose office is located in Ranchi, Jharkhand, where the plan can be inspected.
Darbhanga House, Ranchi : Location of Central Coalfields Limited office in Ranchi, Jharkhand
Central Mine Planning and Design Institute Limited : Organisation with a General Manager of Exploration Division, whose office is located in Ranchi, Jharkhand, where the plan can be inspected.
Gondwana Palace, Kanke Road, Ranchi : Location of Central Mine Planning and Design Institute Limited office in Ranchi, Jharkhand
Govindpur Phase II OCP : The project or area name relevant to the land acquisition in District Bokaro, Jharkhand.
Armo : Village in District Bokaro, Jharkhand where the land is being acquired.
Bermo : Thana (police station) in District Bokaro, Jharkhand where the village Armo is located.
See Full Document Text
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
xxxGIDHxxx
ससीी..जजीी..--डडीी..एएललxx..x--GअअID..--E22x11x00x 7722002222--223377440055
CCGG--DDLL--EE--2211007722002222--223377440055
ऄसाधारण
EXTRAORDINARY
भाग II—खण् ड 3—ईप-खण्ड (ii)
PART II—Section 3—Sub-section (ii)
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 3061] नइ ददल्ली, सोमिार, िुलाइ 18, 2022/अषाढ़ 27, 1944
No. 3061] NEW DELHI, MONDAY, JULY 18, 2022/ASHADHA 27, 1944
कोयला मत्रं ालय
ऄजधसचू ना
नइ ददल्ली, 18 िलु ाइ, 2022
का.अ. 3221(ऄ).—केन्द्रीय सरकार ने कोयला धारक क्षेत्र (ऄिजन और जिकास) ऄजधजनयम, 1957 (1957 का
20) (जिसे आसम ें आसके पश्चात ् ईक्त ऄजधजनयम कहा गया ह)ै की धारा 4 की ईप-धारा (1) के ऄधीन भारत सरकार के
कोयला मंत्रालय द्वारा िारी की गइ ऄजधसूचना संखयांक का.अ. 1041, तारीख 1 ददसम्बर, 2020 िो भारत के रािपत्र,
भाग II, खण्ड 3, ईप–खण्ड (ii) , तारीख 5 ददसंबर, 2020 में प्रकाजित की गइ थी, ईस ऄजधसूचना से ईपाबद्ध ऄनुसूची
में जिजनर्ददष्ट पररक्षत्रे की भूजम में जिसका माप 459.05 एकड़ (लगभग) ऄथिा 185.85 हक्े टेयर (लगभग) ह,ै कोयले का
पूिेक्षण करने के ऄपने अिय की सूचना दी थी;
और केन्द्रीय सरकार का यह समाधान हो गया ह ै दक आस ऄजधसूचना में संलग्न ऄनुसूची म ें जिजनर्ददष्ट की गइ ईक्त
भूजम के भाग म ेंकोयला ऄजभप्राप्य ह;ै
ऄतः ऄब केन्द्रीय सरकार, ईक्त ऄजधजनयम की धारा 7 की ईप-धारा (1) द्वारा प्रदत्त िजक्तयों का प्रयोग करत े हुए
आससे संलग्न ऄनुसूची म ें िर्णणत 440.63 एकड़ (लगभग) ऄथिा 178.31 हक्े टेयर (लगभग) माप की ईक्त भूजम म ें या ईस
पर के सभी ऄजधकार के ऄिनज करने के ऄपने अिय दक सूचना देती ह;ै
रटप्पण 1 : आस ऄजधसूचना के ऄधीन अने िाले क्षेत्र के रेखांक संखया अरइिी/02/2022, तारीख 21 िनिरी, 2022 का
जनरीक्षण ईपायुक्त, जिला – बोकारो (झारखडं ) के कायाजलय म ें या कोयला जनयंत्रक, 1, काईंजसल हाईस स्ट्रीट, कोलकाता –
700001 के कायाजलय म ें या महाप्रबंधक कथारा क्षत्रे , जिला –बोकारो (झारखंड) के कायाजलय म ें या महाप्रबंधक (भूजम और
रािस्ट्ि), सेंरल कोलफील््स जलजमटेड, दरभगं ा हाईस, रााँची(झारखंड) – 834001 या मुखय महाप्रबंधक (गिेषण जिभाग),
सेंरल माआन प्लाननग एडं जडिाआन आंस्ट्टीच्यूट जलजमटेड, गोंडिाना पैलेस, कांके रोड, रााँची (झारखंड)– 834008 में दकया
िा सकता ह।ै
4747 GI/2022 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
रटप्पण 2: ईक्त ऄजधजनयम की धारा 8 के ईपबंधों की ओर ध्यान अकृष्ट दकया िाता है, जिसमें जनम्नजलजखत ईपबंध ह ैं:-
''8. ऄिजन की बाबत् अपजत्तयां.– (1) कोइ व्यजक्त, िो दकसी भूजम में जिसकी बाबत् धारा 7 के ऄधीन ऄजधसूचना जनकाली
गइ ह,ै जहतबद्ध ह,ै ऄजधसूचना के जनकाले िाने के तीस ददनों के भीतर सम्पूण ज भूजम या ईसके दकसी भाग या ऐसी भूजम म ें
या ईस पर के दकन्द्हीं ऄजधकारों का ऄिजन दकए िान े के बारे म ेंअपजत्त कर सकेगा।
स्ट्पष्टीकरण.- आस धारा के ऄथाजन्द्तगजत यह अपजत्त नहीं मानी िाएगी दक कोइ व्यजक्त दकसी भूजम में कोयला ईत्पादन के जलए
स्ट्ियं खनन संदियाएाँ करना चाहता ह ैऔर ऐसी संदियाएाँ केन्द्रीय सरकार या दकसी ऄन्द्य व्यजक्त को नहीं करनी चाजहए।
(2) ईपधारा (1) के ऄधीन प्रत्येक अपजत्त सक्षम प्राजधकारी को जलजखत रूप में की िाएगी और सक्षम प्राजधकारी
अपजत्तकताज को स्ट्ियं सुने िाने का या जिजध व्यिसायी द्वारा सुनिाइ का ऄिसर देगा और ऐसी सभी ऄपजत्तयों को सुनने के
पश्चात और ऐसी ऄजतररक्त िाचाँ , यदद कोइ हो, करन े के पश्चात िो िह अिश्यक समझता ह,ै िह या तो धारा 7 की ईप-
धारा (1) के ऄधीन ऄजधसूजचत भूजम के या ऐसी भूजम म ें या ईस पर के ऄजधकारो के संबंध म ें एक ररपोट ज या ऐसी भूजम के
जिजभन्न ट़कड़ों या ऐसी भूजम में या ईस पर के ऄजधकारों के सबं ंध में अपजत्तयों पर ऄपनी जसफ़ाररिों और ईसके द्वारा की
गइ कारजिाइ के ऄजभलेख सजहत जिजभन्न ररपोटज केन्द्रीय सरकार को ईसके जिजनश्चय के जलए दगे ा।
(3) आस धारा के प्रयोिनों के जलए िह व्यजक्त दकसी भूजम म ें जहतबद्ध समझा िाएगा, िो प्रजतकर म ें जहत का दािा करन े का
हकदार होता, यदद भूजम या दकसी ऐसी भूजम में या ईस पर के ऄजधकार आस ऄजधजनयम के ऄधीन ऄर्णित कर जलए िाते।''
रटप्पण 3: केन्द्रीय सरकार न े कोयला जनयंत्रक, 1, काईंजसल हाईस स्ट्रीट, कोलकाता -700001 को ईक्त ऄजधजनयम की
धारा 3 के ऄधीन ऄजधसूचना संखया का.अ. 2518, तारीख 27 मइ 1983, िो भारत के रािपत्र, भाग II, खण्ड 3,
ईप–खण्ड (ii) में 11 िनू , 1983 में प्रकाजित की गइ, सक्षम प्राजधकारी जनयुक्त दकया ह।ै
ऄनसु चू ी
गोनिदपरु फेि –II ओसीपी
जिला - बोकारो (झारखण्ड)
( रेखांक संखयांक अरइिी/ 02/2022, तारीख 21 िनिरी, 2022 )
सभी ऄजधकार:
रकबा
ि.स.ं ग्राम थाना सखं या थाना जिला रटप्पजणया ं
एकड़ म ें हेक्टेयर म ें
1. ऄरमो 11 बेरमो बोकारो 440.63 178.31 भाग
कुल रकबा: 440.63 एकड़ 178.31 हक्े टेयर
(लगभग) (लगभग)
भ ू – ऄजभलखे के ऄनसु ार ऄर्णित दकए िान ेिाल ेप्लॉट की जििरणी:
मौज़ा/ ऄंचल/ रकबा ऄजभजलजखत भस्ट्ू िामी का
थाना सं. जिला खाता सं॰ प्लॉट सं॰ भूजम का प्रकार
ग्राम थाना (एकड़ में) नाम और जपता का नाम
(1) (2) (3) (4) (5) (6) (7) (8) (9)
िन भूजम (गैर
ऄरमो 11 बेरमो बोकारो 1 355(भाग) 0.515 सरकारी भूजम
मिरुिा खास)
ऄरमो 11 बेरमो बोकारो 39 451(भाग) 0.440 धान -I (रैयती) बुधन गंझू , जपता- खैरु गंझू
परती अर
ऄरमो 11 बेरमो बोकारो 39 452 0.090 बुधन गंझू , जपता- खैरु गंझू
(रैयती)
ऄरमो 11 बेरमो बोकारो 39 453 0.350 धान -I (रैयती) बुधन गंझू , जपता- खैरु गंझू
परतीक़दीम
ऄरमो 11 बेरमो बोकारो 3 454 0.390 धुमा गंझू , जपता- खुली गंझू
(रैयती)
ऄरमो 11 बेरमो बोकारो 3 455 0.510 धान -I (रैयती) धुमा गंझू , जपता- खुली गंझू[भाग II—खण् ड 3(ii)] भारत का रािपत्र : ऄसाधारण 3
दीपक गंझू , जपता- लुनदर
ऄरमो 11 बेरमो बोकारो 7 457 0.290 टांड़ - III (रैयती)
गंझू िगैरह
ऄरमो 11 बेरमो बोकारो 39 458 0.380 धान -III (रैयती) बुधन गंझू , जपता- खैरु गंझू
दीपक गंझू , जपता- लुनदर
ऄरमो 11 बेरमो बोकारो 7 459 0.590 टांड़ - III (रैयती)
गंझू िगैरह
ऄरमो 11 बेरमो बोकारो 2 460 1.450 टांड़ - III (रैयती) मंगल राम , जपता- ईजचत
ऄरमो 11 बेरमो बोकारो 48 461 0.800 टांड़ - III (रैयती) सोना गंझू , जपता- अनंद गंझू
दीपक गंझू , जपता- लुनदर
ऄरमो 11 बेरमो बोकारो 7 462 0.460 टांड़ - III (रैयती)
गंझू िगैरह
दीपक गंझू , जपता- लुनदर
ऄरमो 11 बेरमो बोकारो 7 463 0.310 टांड़ - III (रैयती)
गंझू िगैरह
परतीक़दीम
ऄरमो 11 बेरमो बोकारो 48 464 0.390 सोना गंझू , जपता- अनंद गंझू
(रैयती)
465 िन भूजम (गैर
ऄरमो 11 बेरमो बोकारो 1 51.400 सरकारी भूजम
(भाग) मिरुिा खास)
ऄरमो 11 बेरमो बोकारो 3 466 0.960 टांड़ - III (रैयती) धुमा गंझू , जपता- खुली गंझू
िानकी गंझू , जपता- रामलाल
ऄरमो 11 बेरमो बोकारो 4 467 0.150 टांड़ - III (रैयती)
गंझू
रास्ट्ता (गैर
ऄरमो 11 बेरमो बोकारो 58 468 0.170 सरकारी भूजम
मिरुिा अम)
सोना िगैरह, जपता- दकिुन
ऄरमो 11 बेरमो बोकारो 10 469 0.980 टांड़ - III (रैयती)
राम गंझू
िानकी गंझू , जपता- राम
ऄरमो 11 बेरमो बोकारो 4 470 0.480 टांड़ - III (रैयती)
लाल गंझू
सोना िगैरह, जपता- दकिुन
ऄरमो 11 बेरमो बोकारो 10 471 1.000 टांड़ - III (रैयती)
राम गंझू
िानकी गंझू , जपता- रामलाल
ऄरमो 11 बेरमो बोकारो 4 472 0.290 टांड़ - III (रैयती)
गंझू
िन भूजम (गैर
ऄरमो 11 बेरमो बोकारो 1 473 106.550 सरकारी भूजम
मिरुिा खास)
रीगन नसह गंझू जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 475 1.460 धान - II (रैयती)
राम गंझू
ऄरमो 11 बेरमो बोकारो 2 476 1.020 टांड़ - III (रैयती) मंगल राम , जपता- ईजचत
ऄरमो 11 बेरमो बोकारो 2 477 0.300 टांड़ - III (रैयती) मंगल राम , जपता- ईजचत
ऄरमो 11 बेरमो बोकारो 48 478 0.260 टांड़ - III (रैयती) सोना गंझू , जपता- अनंद गंझू
बन्द्डा गंझू िगैरह, जपता-
ऄरमो 11 बेरमो बोकारो 35 479 0.590 टांड़ - III (रैयती)
रोमा गंझू
बन्द्डा गंझू िगैरह, जपता-
ऄरमो 11 बेरमो बोकारो 35 480 0.650 टांड़ - III (रैयती)
रोमा गंझू
ऄरमो 11 बेरमो बोकारो 48 481 0.180 धान -III (रैयती) सोना गंझू , जपता- अनंद गंझू
ऄरमो 11 बेरमो बोकारो 48 482 0.560 धान -III (रैयती) सोना गंझू , जपता- अनंद गंझू
ऄरमो 11 बेरमो बोकारो 48 483 0.390 टांड़ - III (रैयती) सोना गंझू , जपता- अनंद गंझू
सोना िगैरह, जपता- दकिुन
ऄरमो 11 बेरमो बोकारो 10 484 0.970 टांड़ - III (रैयती)
राम गंझू4 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
परतीक़दीम
ऄरमो 11 बेरमो बोकारो 48 485 0.320 सोना गंझू , जपता- अनंदगंझू
(रैयती)
रीगन नसह गंझू जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 486 4.300 टांड़ - II (रैयती)
राम गंझू
ऄरमो 11 बेरमो बोकारो 39 487 1.330 टांड़ - III (रैयती) बुधनगंझू , जपता- खैरु गंझू
िन भूजम (गैर
ऄरमो 11 बेरमो बोकारो 1 488(भाग) 133.780 सरकारी भूजम
मिरुिा खास)
ऄरमो 11 बेरमो बोकारो 39 489 2.360 टांड़ - III (रैयती) बुधन गंझू , जपता- खैरु गंझू
ऄरमो 11 बेरमो बोकारो 6 490(भाग) 0.100 टांड़ - III (रैयती) फागु गंझू , जपता- धनी गंझू
रीगन नसह गंझू जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 504(भाग) 0.220 धान II (रैयती)
राम गंझू
िंकर गंझू िगैरह, जपता- धुनी
ऄरमो 11 बेरमो बोकारो 9 505(भाग) 0.100 धान II (रैयती)
गंझू
ऄरमो 11 बेरमो बोकारो 6 506 0.060 धान -III (रैयती) बुधन गंझू , जपता- खैरु गंझू
िंकर गंझू िगैरह, जपता- धुनी
ऄरमो 11 बेरमो बोकारो 9 507 0.030 धान -III (रैयती)
गंझू
िंकर गंझू िगैरह, जपता- धुनी
ऄरमो 11 बेरमो बोकारो 9 508 0.300 धान -III (रैयती)
गंझू
िंकर गंझू िगैरह, जपता- धुनी
ऄरमो 11 बेरमो बोकारो 9 509 0.060 परतीअर (रैयती)
गंझू
ऄरमो 11 बेरमो बोकारो 39 510 0.120 धान -III (रैयती) बुधन गंझू , जपता- खैरु गंझू
बन्द्डा गंझू िगैरह, जपता-
ऄरमो 11 बेरमो बोकारो 35 511 0.150 धान -III (रैयती)
रोमा गंझू
ऄरमो 11 बेरमो बोकारो 39 512 0.460 टांड़ - III (रैयती) बुधन गंझू , जपता- खैरु गंझू
ऄरमो 11 बेरमो बोकारो 2 513(भाग) 0.870 टांड़ - III (रैयती) मंगल राम , जपता- ईजचत
ऄरमो 11 बेरमो बोकारो 39 514 0.330 टांड़ - III (रैयती) बुधन गंझू , जपता- खैरु गंझू
परतीक़दीम (गैर
ऄरमो 11 बेरमो बोकारो 57 517(भाग) 1.240 सरकारी भूजम
मिरुिा खास)
ऄरमो 11 बेरमो बोकारो 39 518 0.030 धान -III (रैयती) बुधन गंझू , जपता- खैरु गंझू
ऄरमो 11 बेरमो बोकारो 6 519(भाग) 0.050 धान -III (रैयती) फागु गंझू , जपता- धनीगंझू
दीपक गंझू , जपता- लुनदर
ऄरमो 11 बेरमो बोकारो 7 623(भाग) 0.090 टांड़ - III (रैयती)
गंझू िगैरह
सोना िगैरह, जपता- दकिुन
ऄरमो 11 बेरमो बोकारो 10 625(भाग) 0.010 टांड़ - II (रैयती)
राम गंझू
दीपक गंझू , जपता- लुनदर
ऄरमो 11 बेरमो बोकारो 7 626(भाग) 0.095 टांड़ - III (रैयती)
गंझू िगैरह
ऄरमो 11 बेरमो बोकारो 39 627(भाग) 0.155 टांड़ - III (रैयती) बुधन गंझू , जपता- खैरु गंझू
ऄरमो 11 बेरमो बोकारो 39 628(भाग) 0.090 टांड़ - II (रैयती) बुधन गंझू , जपता- खैरु गंझू
ऄरमो 11 बेरमो बोकारो 3 629 0.300 टांड़ - III (रैयती) धुमा गंझू , जपता- खुली गंझू
परतीक़दीम (गैर
ऄरमो 11 बेरमो बोकारो 57 630(भाग) 4.600 सरकारी भूजम
मिरुिा खास)
ऄजभलेख ऄजभलेख
ऄरमो 11 बेरमो बोकारो 631 0.110 ऄजभलेख ऄनुपलब्द्द्ध
ऄनुपलब्द्द्ध ऄनुपलब्द्द्ध
ऄरमो 11 बेरमो बोकारो 2 632 0.770 धान -III (रैयती) मंगल राम , जपता- ईजचत[भाग II—खण् ड 3(ii)] भारत का रािपत्र : ऄसाधारण 5
िंकर गंझू िगैरह, जपता- धुनी
ऄरमो 11 बेरमो बोकारो 9 633 0.230 धान -III (रैयती)
गंझू
दीपक गंझू , जपता- लुनदर
ऄरमो 11 बेरमो बोकारो 7 634(भाग) 0.990 टांड़ - II (रैयती)
गंझू िगैरह
परतीक़दीम (गैर
ऄरमो 11 बेरमो बोकारो 57 635 0.110 सरकारी भूजम
मिरुिा खास)
िानकी गंझू जपता- राम लाल
ऄरमो 11 बेरमो बोकारो 4 636(भाग) 0.695 टांड़ - II (रैयती)
गंझू
परतीक़दीम (गैर
ऄरमो 11 बेरमो बोकारो 57 708(भाग) 0.750 सरकारी भूजम
मिरुिा खास)
िानकी गंझू , जपता- राम
ऄरमो 11 बेरमो बोकारो 4 709 0.110 धान -III (रैयती)
लाल गंझू
ऄरमो 11 बेरमो बोकारो 2 710 0.110 धान -II (रैयती) मंगल राम , जपता- ईजचत
ऄरमो 11 बेरमो बोकारो 2 711 1.130 धान -I (रैयती) मंगल राम , जपता- ईजचत
रीगन नसह गंझू , जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 712 1.830 धान -I (रैयती)
राम गंझू
िानकी गंझू , जपता- राम
ऄरमो 11 बेरमो बोकारो 4 713 0.610 धान -I (रैयती)
लाल गंझू
िानकी गंझू , जपता- राम
ऄरमो 11 बेरमो बोकारो 4 714 0.090 परतीअर (रैयती)
लाल गंझू
िानकी गंझू , जपता- राम
ऄरमो 11 बेरमो बोकारो 4 715 0.390 धान -I (रैयती)
लाल गंझू
ऄरमो 11 बेरमो बोकारो 48 716 0.650 धान -I (रैयती) बुधन गंझू , जपता- खैरु गंझू
ऄरमो 11 बेरमो बोकारो 48 717 0.500 टांड़ - III (रैयती) सोना गंझू , जपता- अनंद गंझू
िानकी गंझू , जपता- राम
ऄरमो 11 बेरमो बोकारो 4 718 1.300 टांड़ - III (रैयती)
लाल गंझू
ऄरमो 11 बेरमो बोकारो 27 719 0.860 टांड़ - III (रैयती) देिा गंझू , जपता-महादेि गंझू
सोना िगैरह, जपता- दकिुन
ऄरमो 11 बेरमो बोकारो 10 720 1.350 टांड़ - III (रैयती)
राम गंझू
दीपक गंझू , जपता- लुनदर
ऄरमो 11 बेरमो बोकारो 7 721 0.640 टांड़ - II (रैयती)
गंझू िगैरह
रीगन नसह गंझू , जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 722 0.880 टांड़ - III (रैयती)
राम गंझू
रीगन नसह गंझू , जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 723 0.890 टांड़ - III (रैयती)
राम गंझू
रीगन नसह गंझू , जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 724 0.150 धान -I (रैयती)
राम गंझू
रीगन नसह गंझू , जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 725 0.180 परतीअर (रैयती)
राम गंझू
रीगन नसह गंझू , जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 726 0.090 धान -I (रैयती)
राम गंझू
रीगन नसह गंझू , जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 727 0.260 परतीगड्ढा (रैयती)
राम गंझू
ऄरमो 11 बेरमो बोकारो 8 728(भाग) 1.000 धान -I (रैयती) रीगन नसह गंझू , जपता- गंगा6 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
राम गंझू
सोना िगैरह, जपता- दकिुन
ऄरमो 11 बेरमो बोकारो 10 736(भाग) 0.035 धान -III (रैयती)
राम गंझू
रीगन नसह गंझू , जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 752 0.010 धान -III (रैयती)
राम गंझू
रीगन नसह गंझू , जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 753 0.030 धान -III (रैयती)
राम गंझू
ऄरमो 11 बेरमो बोकारो 6 754 0.500 टांड़ - III (रैयती) फागु गंझू , जपता- धनीगंझू
बन्द्डा गंझू िगैरह, जपता-
ऄरमो 11 बेरमो बोकारो 35 755 1.550 टांड़ - III (रैयती)
रोमा गंझू
परतीक़दीम (गैर
ऄरमो 11 बेरमो बोकारो 57 756 0.240 सरकारी भूजम
मिरुिा खास)
ऄरमो 11 बेरमो बोकारो 27 757 0.500 टांड़ - III (रैयती) देिा गंझू , जपता-महादेि गंझू
िन भूजम (गैर
ऄरमो 11 बेरमो बोकारो 1 758(भाग) 83.630 सरकारी भूजम
मिरुिा खास)
परतीक़दीम (गैर
ऄरमो 11 बेरमो बोकारो 57 759(भाग) 0.255 सरकारी भूजम
मिरुिा खास)
रीगन नसह गंझू , जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 760 2.660 टांड़ - III (रैयती)
राम गंझू
दीपक गंझू , जपता- लुनदर
ऄरमो 11 बेरमो बोकारो 7 761 0.030 टांड़ - III (रैयती)
गंझू िगैरह
परती क़दीम (गैर
ऄरमो 11 बेरमो बोकारो 57 762 0.170 सरकारी भूजम
मिरुिा खास)
िंकर गंझू िगैरह, जपता- धुनी
ऄरमो 11 बेरमो बोकारो 9 763 1.110 टांड़ - III (रैयती)
गंझू
दीपक गंझू , जपता- लुनदर
ऄरमो 11 बेरमो बोकारो 7 764 0.820 टांड़ - III (रैयती)
गंझू िगैरह
ऄरमो 11 बेरमो बोकारो 3 765 0.640 धान -III (रैयती) धुमा गंझू , जपता- खुली गंझू
रास्ट्ता (गैर
ऄरमो 11 बेरमो बोकारो 58 766 0.050 सरकारी भूजम
मिरुिा अम)
ऄरमो 11 बेरमो बोकारो 6 767 1.080 टांड़ - III (रैयती) फागु गंझू , जपता- धनी गंझू
ऄजभलेख
ऄरमो 11 बेरमो बोकारो 39 768 0.800 बुधन गंझू , जपता- खैरु गंझू
ऄनुपलब्द्द्ध
ऄजभलेख
ऄरमो 11 बेरमो बोकारो NA 769 0.210 सरकारी भूजम
ऄनुपलब्द्द्ध
परती क़दीम
ऄरमो 11 बेरमो बोकारो 39 770 0.260 बुधन गंझू , जपता- खैरु गझं ू
(रैयती)
परती क़दीम रीगन नसह गंझू , जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 771 0.330
(रैयती) राम गंझू
रीगन नसह गंझू , जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 772 0.090 परतीअर (रैयती)
राम गंझू
रीगन नसह गंझू , जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 773 1.200 धान II (रैयती)
राम गंझू
ऄरमो 11 बेरमो बोकारो 35 774 0.490 ऄजभलेख ऄजभलेख ऄनुपलब्द्द्ध[भाग II—खण् ड 3(ii)] भारत का रािपत्र : ऄसाधारण 7
ऄनुपलब्द्द्ध
रीगन नसह गंझू , जपता- गंगा
ऄरमो 11 बेरमो बोकारो 8 775 0.390 धान II (रैयती)
राम गंझू
440.630
कुल रकबा
एकड़
सीमा िणनज :
सीमा रेखा सीमा िणनज :
ए-बी-सी-डी-इ-एफ-िी-एच-अइ-िे-के-एल-एम- रेखा जबन्द्द ु 'ए' से अरंभ होकर जबन्द्द ु बी,सी,डी,इ,एफ, िी, एच, अइ,
एन-ओ-पी-ए. िे,के,एल,एम,एन.ओ. और 'पी' से गुिरते हुए अरंजभक जबन्द्द ु'ए' पर जमलती ह।ै
[फा. सं. 43015/19/2020-एलएअइअर]
भबानी प्रसाद पजत, संयुक्त सजचि
MINISTRY OF COAL
NOTIFICATION
New Delhi the 18th July, 2022
S.O. 3221(E).—Whereas by the notification of Government of India in the Ministry of Coal number S.O
1041, dated the 1st December, 2020, issued under sub-section(1) of section 4 of the Coal Bearing Areas (Acquisition
and Development) Act, 1957 (20 of 1957) (hereinafter referred to as the said Act) and published in the Gazette of
India, Part II, Section 3, Sub-section (ii), dated the 5th December, 2020, the Central Government gave notice of its
intention to prospect for coal in 459.05 acres(approximately) or 185.85 hectares (approximately) of the land in the
locality specified in the Schedule annexed to that notification;
And, whereas, the Central Government is satisfied that coal is obtainable in a part of the said lands specified in the
Schedule appended to this notification;
Now, therefore, in exercise of the powers conferred by sub-section (1) of section 7 of the said Act, the Central
Government hereby gives notice of its intention to acquire the land measuring 440.63 acres (approximately) or 178.31
hectares (approximately) and all rights in or over the said lands as described in the Schedule appended hereto;
Note 1: The plan bearing number Rev/02/2022, dated the 21st January, 2022, the area covered by this notification
may be inspected at the office of the Deputy Commissioner, District Bokaro (Jharkhand) or at the office of the Coal
Controller, 1, Council House Street, Kolkata -700 001 or at the office of the General Manager, Kathara Area, District
Bokaro (Jharkhand) or General Manager (Land and Revenue), Central Coalfields Limited, Darbhanga, House, Ranchi-
834001, Jharkhand or General Manager (Exploration Division), Central Mine Planning and Design Institute Limited,
Gondwana Palace, Kanke Road, Ranchi-834008, Jharkhand.
Note 2: Attention is hereby invited to the provisions of section 8 of the said Act which provides as follows:-
"8. Objections to acquisition.- (1) Any person interested in any land in respect of which a notification under section 7
has been issued, may within thirty days of the issue of the notification, object to the acquisition of the whole or any
part of the land or any rights in or over such land.
Explanation.- It shall not be an objection within the meaning of this section for any person to say that he himself
desires to undertake mining operations in the land for the production of coal and that such operations should not be
undertaken by the Central Government or by any other person.
(2) Every objection under sub-section (1) shall be made to the competent authority in writing, and the competent
authority shall give the objector an opportunity of being heard either in person or by a legal practitioner and shall after
hearing all such objections and after making such further inquiry if any, as he thinks necessary either make a report in
respect of the land which has been notified under sub-section (1) of section 7 or of rights in or over such land or make
different reports in respect of different parcels of such land or of rights in or over such land to the Central
Government, containing his recommendations on the objections, together with the record of the proceeding held by
him, for the decision of the Government.8 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
(3) For the purposes of this section, a person shall be deemed to be interested in land, who would be entitled to claim
an interest in compensation if the land or any rights in or over such land were acquired under this Act.”
Note 3: The Coal Controller, 1, Council House Street, Kolkata-700 001 has been appointed by the Central
Government as the competent authority under section 3 of the said Act, vide notification number S.O. 2518, dated the
27th May,1983 published in the Gazette of India, Part II, Section 3, Sub-section (ii), dated the 11th June, 1983.
SCHEDULE
Govindpur Phase – II OCP
District- Bokaro (Jharkhand)
(Plan bearing number Rev/02/2022, dated the 21st January, 2022)
All Rights:
Serial Village Thana Thana District Area Remarks
number number
in acres in hectares
1. Armo 11 Bermo Bokaro 440.63 178.31 Part
440.63 acres 178.31 hectares
Total Area:
(approxi-mately) (approxi-mately)
Details of plots to be acquired as per land record:
Area under Name of Recorded
Mouza / Thana Circle /
District Khata No. Plot No. acquisition Class of Land Tenant and Father's
Village No. Thana
(in acres) Name
(1) (2) (3) (4) (5) (6) (7) (8) (9)
Armo 11 Bermo Bokaro 1 355(P) 0.515 Forest (GMK) Government Land
Armo 11 Bermo Bokaro 39 451(P) 0.440
Dhan-I Budhan Ganjhu,
(Tenancy) S/O Khairu Ganjhu
Armo 11 Bermo Bokaro 39 452 0.090
Parti Aar Budhan Ganjhu,
(Tenancy) S/O Khairu Ganjhu
Armo 11 Bermo Bokaro 39 453 0.350
Dhan-I Budhan Ganjhu,
(Tenancy) S/O Khairu Ganjhu
Armo 11 Bermo Bokaro 3 454 0.390
PartiKadim Dhuma Ganjhu,
(Tenancy) S/O Khuli Ganjhu
Armo 11 Bermo Bokaro 3 455 0.510
Dhan-I Dhuma Ganjhu,
(Tenancy) S/O Khuli Ganjhu
Armo 11 Bermo Bokaro 7 457 0.290
Tand-III Dipak Ganjhu, S/O
(Tenancy) Lundar Ganjhu, etc.
Armo 11 Bermo Bokaro 39 458 0.380
Dhan-III Budhan Ganjhu,
(Tenancy) S/O Khairu Ganjhu
Armo 11 Bermo Bokaro 7 459 0.590
Tand-III Dipak Ganjhu, S/O
(Tenancy) Lundar Ganjhu, etc.
Armo 11 Bermo Bokaro 2 460 1.450
Tand-III Mangal Ram, S/O
(Tenancy) Uchit
Armo 11 Bermo Bokaro 48 461 0.800
Tand-III Sona Ganjhu, S/O
(Tenancy) Anand Ganjhu
Armo 11 Bermo Bokaro 7 462 0.460
Tand-III Dipak Ganjhu, S/O
(Tenancy) Lundar Ganjhu, etc.
Armo 11 Bermo Bokaro 7 463 0.310
Tand-III Dipak Ganjhu, S/O
(Tenancy) Lundar Ganjhu, etc.
Armo 11 Bermo Bokaro 48 464 0.390
PartiKadim Sona Ganjhu, S/O
(Tenancy) Anand Ganjhu
Armo 11 Bermo Bokaro 1 465(P) 51.400 Forest (GMK) Governent Land
Armo 11 Bermo Bokaro 3 466 0.960
Tand-III Dhuma Ganjhu,
(Tenancy) S/O Khuli Ganjhu
Armo 11 Bermo Bokaro 4 467 0.150
Tand-III Janki Ganjhu, S/O
(Tenancy) Ramlal Ganjhu
Armo 11 Bermo Bokaro 58 468 0.170 Rasta(GMA) Governent Land
Armo 11 Bermo Bokaro 10 469 0.980
Tand-III SonaWagairah, S/O
(Tenancy) Kishun Ram[भाग II—खण् ड 3(ii)] भारत का रािपत्र : ऄसाधारण 9
Ganjhu
Armo 11 Bermo Bokaro 4 470 0.480
Tand-III Janki Ganjhu, S/O
(Tenancy) Ramlal Ganjhu
SonaWagairah,
Armo 11 Bermo Bokaro 10 471 1.000
Tand-III
S/O Kishun Ram
(Tenancy)
Ganjhu
Armo 11 Bermo Bokaro 4 472 0.290
Tand-III Janki Ganjhu, S/O
(Tenancy) Ramlal Ganjhu
Armo 11 Bermo Bokaro 1 473 106.550 Forest(GMK) Governent Land
Rigan Singh
Armo 11 Bermo Bokaro 8 475 1.460
Dhan-II
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Armo 11 Bermo Bokaro 2 476 1.020
Tand-III Mangal Ram, S/O
(Tenancy) Uchit
Armo 11 Bermo Bokaro 2 477 0.300
Tand-III Mangal Ram, S/O
(Tenancy) Uchit
Armo 11 Bermo Bokaro 48 478 0.260
Tand-III Sona Ganjhu, S/O
(Tenancy) Anand Ganjhu
Banda Ganjhu
Armo 11 Bermo Bokaro 35 479 0.590
Dhan-III
wagairah, S/O
(Tenancy)
Roma Ganjhu
Banda Ganjhu
Armo 11 Bermo Bokaro 35 480 0.650
Tand-III
wagairah,
(Tenancy)
S/O Roma Ganjhu
Armo 11 Bermo Bokaro 48 481 0.180
Dhan-III Sona Ganjhu, S/O
(Tenancy) Anand Ganjhu
Armo 11 Bermo Bokaro 48 482 0.560
Dhan-III Sona Ganjhu, S/O
(Tenancy) Anand Ganjhu
Armo 11 Bermo Bokaro 48 483 0.390
Tand-III Sona Ganjhu, S/O
(Tenancy) Anand Ganjhu
Armo 11 Bermo Bokaro 10 484 0.970
Tand-III SonaWagairah, S/O
(Tenancy) Kisun Ram Ganjhu
Armo 11 Bermo Bokaro 48 485 0.320
PartiKadim Sona Ganjhu, S/O
(Tenancy) Anand Ganjhu
Rigan Singh
Armo 11 Bermo Bokaro 8 486 4.300
Tand-II
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Armo 11 Bermo Bokaro 39 487 1.330
Tand-III Budhan Ganjhu,
(Tenancy) S/O Khairu Ganjhu
Armo 11 Bermo Bokaro 1 488(P) 133.780 Forest (GMK) Governent Land
Armo 11 Bermo Bokaro 39 489 2.360
Tand-III Budhan Ganjhu,
(Tenancy) S/O Khairu Ganjhu
Armo 11 Bermo Bokaro 6 490(P) 0.100
Tand-III Fagu Ganjhu, S/O
(Tenancy) Dhani Ganjhu
Rigan Singh
Armo 11 Bermo Bokaro 8 504(P) 0.220
Dhan-II
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Sankar Ganjhu
Armo 11 Bermo Bokaro 9 505(P) 0.100
Dhan-II
Wagairah, S/O
(Tenancy)
Dhani Ganjhu
Armo 11 Bermo Bokaro 6 506 0.060
Dhan-III Budhan Ganjhu,
(Tenancy) S/O Khairu Ganjhu
Sankar Ganjhu
Armo 11 Bermo Bokaro 9 507 0.030
Dhan-III
Wagairah, S/O
(Tenancy)
Dhani Ganjhu
Sankar Ganjhu
Armo 11 Bermo Bokaro 9 508 0.300
Dhan-III
Wagairah, S/O
(Tenancy)
Dhani Ganjhu
Sankar Ganjhu
Armo 11 Bermo Bokaro 9 509 0.060
Parti Aar
Wagairah, S/O
(Tenancy)
Dhani Ganjhu
Armo 11 Bermo Bokaro 39 510 0.120 Dhan-III Budhan Ganjhu,10 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
(Tenancy) S/O Khairu Ganjhu
Banda Ganjhu
Armo 11 Bermo Bokaro 35 511 0.150
Dhan-III
wagairah, S/O
(Tenancy)
Roma Ganjhu
Armo 11 Bermo Bokaro 39 512 0.460
Dhan-III Budhan Ganjhu,
(Tenancy) S/O Khairu Ganjhu
Armo 11 Bermo Bokaro 2 513(P) 0.870
Tand-III Mangal Ram, S/O
(Tenancy) Uchit
Armo 11 Bermo Bokaro 39 514 0.330
Tand-III Budhan Ganjhu,
(Tenancy) S/O Khairu Ganjhu
Armo 11 Bermo Bokaro 57 517(P) 1.240
PartiKadim
Governent Land
(GMK)
Armo 11 Bermo Bokaro 39 518 0.030 Dhan-III
Budhan Ganjhu,
S/O Khairu Ganjhu
Armo 11 Bermo Bokaro 6 519(P) 0.050
Dhan-III Fagu Ganjhu, S/O
(Tenancy) Dhani Ganjhu
Armo 11 Bermo Bokaro 7 623(P) 0.090
Tand-III Dipak Ganjhu, S/O
(Tenancy) Lundar Ganjhu, etc.
SonaWagairah, S/O
Armo 11 Bermo Bokaro 10 625(P) 0.010
Tand-II
Kishun Ram
(Tenancy)
Ganjhu
Armo 11 Bermo Bokaro 7 626(P) 0.095
Tand-III Dipak Ganjhu, S/O
(Tenancy) Lundar Ganjhu, etc.
Armo 11 Bermo Bokaro 39 627(P) 0.155
Tand-III Budhan Ganjhu,
(Tenancy) S/O Khairu Ganjhu
Armo 11 Bermo Bokaro 39 628(P) 0.090
Tand-II Budhan Ganjhu,
(Tenancy) S/O Khairu Ganjhu
Armo 11 Bermo Bokaro 3 629 0.300
Tand-III Dhuma Ganjhu,
(Tenancy) S/O Khuli Ganjhu
Armo 11 Bermo Bokaro 57 630(P) 4.600
PartiKadim
Governent Land
(GMK)
Record
Armo 11 Bermo Bokaro Not 631 0.110
Record Not Record Not
Available Available
Available
Armo 11 Bermo Bokaro 2 632 0.770
Dhan-III Mangal Ram, S/O
(Tenancy) Uchit
Sankar Ganjhu
Armo 11 Bermo Bokaro 9 633 0.230
Dhan-III
Wagairah, S/O
(Tenancy)
Dhani Ganjhu
Armo 11 Bermo Bokaro 7 634(P) 0.990
Tand-II Dipak Ganjhu, S/O
(Tenancy) Lundar Ganjhu, etc.
Armo 11 Bermo Bokaro 57 635 0.110
PartiKadim
Governent Land
(GMK)
Armo 11 Bermo Bokaro 4 636(P) 0.695
Tand-II Janki Ganjhu, S/O
(Tenancy) Ramlal Ganjhu
Armo 11 Bermo Bokaro 57 708(P) 0.750
PartiKadim
Governent Land
(GMK)
Armo 11 Bermo Bokaro 4 709 0.110
Dhan-III Janki Ganjhu, S/O
(Tenancy) Ramlal Ganjhu
Armo 11 Bermo Bokaro 2 710 0.110
Dhan-II Mangal Ram, S/O
(Tenancy) Uchit
Armo 11 Bermo Bokaro 2 711 1.130
Dhan-I Mangal Ram, S/O
(Tenancy) Uchit
Rigan Singh
Armo 11 Bermo Bokaro 8 712 1.830
Dhan-I
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Armo 11 Bermo Bokaro 4 713 0.610
Dhan-I Janki Ganjhu, S/O
(Tenancy) Ramlal Ganjhu
Armo 11 Bermo Bokaro 4 714 0.090
Parti Aar Janki Ganjhu, S/O
(Tenancy) Ramlal Ganjhu
Armo 11 Bermo Bokaro 4 715 0.390 Dhan-I Janki Ganjhu, S/O[भाग II—खण् ड 3(ii)] भारत का रािपत्र : ऄसाधारण 11
(Tenancy) Ramlal Ganjhu
Armo 11 Bermo Bokaro 48 716 0.650
Dhan-I Budhan Ganjhu,
(Tenancy) S/O Khairu Ganjhu
Armo 11 Bermo Bokaro 48 717 0.500
Tand-III Sona Ganjhu, S/O
(Tenancy) Anand Ganjhu
Armo 11 Bermo Bokaro 4 718 1.300
Tand-III Janki Ganjhu, S/O
(Tenancy) Ramlal Ganjhu
Armo 11 Bermo Bokaro 27 719 0.860
Tand-III Dewa Ganjhu, S/O
(Tenancy) Mahadew Ganjhu
Armo 11 Bermo Bokaro 10 720 1.350
Tand-III SonaWagairah, S/O
(Tenancy) Kisun Ram Ganjhu
Armo 11 Bermo Bokaro 7 721 0.640
Tand-II Dipak Ganjhu, S/O
(Tenancy) Lundar Ganjhu, etc.
Rigan Singh
Armo 11 Bermo Bokaro 8 722 0.880
Tand-III
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Rigan Singh
Armo 11 Bermo Bokaro 8 723 0.890
Tand-III
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Rigan Singh
Armo 11 Bermo Bokaro 8 724 0.150
Dhan-
Ganjhu S/O Ganga
I(Tenancy)
Ram Ganjhu
Rigan Singh
Armo 11 Bermo Bokaro 8 725 0.180
Parti Aar
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Rigan Singh
Armo 11 Bermo Bokaro 8 726 0.090
Dhan-I
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Rigan Singh
Armo 11 Bermo Bokaro 8 727 0.260
PartiGarha
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Rigan Singh
Armo 11 Bermo Bokaro 8 728(P) 1.000
Dhan-I
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
SonaWagairah S/O
Armo 11 Bermo Bokaro 10 736(P) 0.035
Dhan-III
Kishun Ram
(Tenancy)
Ganjhu
Rigan Singh
Armo 11 Bermo Bokaro 8 752 0.010
Dhan-III
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Rigan Singh
Armo 11 Bermo Bokaro 8 753 0.030
Dhan-III
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Armo 11 Bermo Bokaro 6 754 0.500
Tand-III Fagu Ganjhu, S/O
(Tenancy) Dhani Ganjhu
Banda Ganjhu
Armo 11 Bermo Bokaro 35 755 1.550
Tand-III
wagairah, S/O
(Tenancy)
Roma Ganjhu
Armo 11 Bermo Bokaro 57 756 0.240
PartiKadim
Governent Land
(GMK)
Armo 11 Bermo Bokaro 27 757 0.500
Tand- Dewa Ganjhu, S/O
III(Tenancy) Mahadew Ganjhu
Armo 11 Bermo Bokaro 1 758(P) 83.630 Forest (GMK) Governent Land
Armo 11 Bermo Bokaro 57 759(P) 0.255
PartiKadim
Governent Land
(GMK)
Rigan Singh
Armo 11 Bermo Bokaro 8 760 2.660
Tand-III
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Armo 11 Bermo Bokaro 7 761 0.030
Tand-III Dipak Ganjhu, S/O
(Tenancy) Lundar Ganjhu, etc.
Armo 11 Bermo Bokaro 57 762 0.170
PartiKadim
Governent Land
(GMK)12 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
Sankar Ganjhu
Armo 11 Bermo Bokaro 9 763 1.110
Tand-III
Wagairah, S/O
(Tenancy)
Dhani Ganjhu
Armo 11 Bermo Bokaro 7 764 0.820
Tand-III Dipak Ganjhu, S/O
(Tenancy) Lundar Ganjhu, etc.
Armo 11 Bermo Bokaro 3 765 0.640
Dhan-III Dhuma Ganjhu,
(Tenancy) S/O Khuli Ganjhu
Armo 11 Bermo Bokaro 58 766 0.050 Rasta (GMA) Governent Land
Armo 11 Bermo Bokaro 6 767 1.080
Tand-III Fagu Ganjhu, S/O
(Tenancy) Dhani Ganjhu
Armo 11 Bermo Bokaro 39 768 0.800
Record Not Budhan Ganjhu,
Available S/O Khairu Ganjhu
Record
Armo 11 Bermo Bokaro Not 769 0.210
Record Not
Governent Land
Available
Available
Armo 11 Bermo Bokaro 39 770 0.260
Parti Kadim Budhan Ganjhu,
(Tenancy) S/O Khairu Ganjhu
Rigan Singh
Armo 11 Bermo Bokaro 8 771 0.330
Parti Kadim
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Rigan Singh
Armo 11 Bermo Bokaro 8 772 0.090
Parti Aar
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Rigan Singh
Armo 11 Bermo Bokaro 8 773 1.200
Dhan-II
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Armo 11 Bermo Bokaro 35 774 0.490
Record Not Record Not
Available Available
Rigan Singh
Armo 11 Bermo Bokaro 8 775 0.390
Dhan-II
Ganjhu S/O Ganga
(Tenancy)
Ram Ganjhu
Total Area: 440.630 acres
Boundary description :
Boundary Line Boundary description
A-B-C-D-E-F-G-H-I-J-K-L-M-N-O-P-A. Line starts from point ‘A’and passes through points B, C, D, E, F, G, H, I,
J, K, L, M, N, O and 'P' and meets at starting point ‘A’.
[F. No. 43015/19/2020-LAIR]
BHABANI PRASAD PATI, Jt. Secy.
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.