See Full Document Text
फा. स. ऐरा/20010/एमवाईटीपी/जीआईएएल/मोपा गोवा/सीपी-I/2023-24
F.N. AERA/20010/MYTP/GIAL/MOPA GOA/CP-I/2023-24
परामर्श पत्र सख्ं या 11/2023-24
Consultation Paper No.11/2023-24
भारतीय ववमानपत् तन आवथशक वववनयामक प्राविकरण
Airports Economic Regulatory Authority of India
मनोहर अंतराशष्ट्रीय हवाईअड्डा, मोपा, गोवा (जीओएक् स) के वलए प्रथम वनयंत्रण अववि (01 अप्रैल,
2023 से 31 मार्श, 2028) के वलए वैमावनक टैररफ वनिाशररत करने के मामले में
IN THE MATTER OF
DETERMINATION OF AERONAUTICAL TARIFF FOR
MANOHAR INTERNATIONAL AIRPORT, MOPA, GOA (GOX)
FOR THE FIRST CONTROL PERIOD
(01ST APRIL 2023 TO 31ST MARCH 2028)
जारी करने की तारीख: 31.08.2023
Date of Issue: 31.08.2023
ऐरा भवन/AERA Building
प्रर्ासवनक कॉम् पलेक् स/Administrative Complex
सफदरजंग हवाईअड्डा/Safdarjung Airport
नई वदल्ल ी/New Delhi – 110003Stakeholders’ Comments
Stakeholders’ Comments
GMR Airports Limited (GAL) won the bid for development of the new greenfield airport at Mopa, Goa and
signed the Concession Agreement (CA) on 8th November 2016 via a special purpose vehicle namely Goa
International Airport Limited (GIAL) at Mopa, Goa. As per the Concession Agreement, GIAL, Mopa, Goa will
develop the airport under the DBFOT (Design, Build, Finance, Operate and Transfer) model for an initial period
of 40 years from the appointment date (4th September 2017), which is extendable by another 20 years (based on
bidding process) with the First Right of Refusal available to the Concessionaire.
Manohar International Airport, a greenfield airport at Mopa, Goa is categorized as a Major Airport in accordance
with the provisions of the AERA Act 2008 read with AERA (Amendment) Act 2019 and 2021, designed to
operate with designated capacity of more than 3.5 MPPA as stipulated under clause 12.2.1 (Refer Annexure 1)
of Concession agreement executed between GoG and GIAL, Mopa, Goa.
The Airport was inaugurated on 11th December 2022. Operations in Manohar International Airport, Mopa, Goa
commenced from 5th January 2023 (COD). With the commencement of operations at Manohar International
Airport, Mopa, Goa (IATA: GOX), Goa has 2 International Airports in the state.
As the operations have commenced in the last quarter of FY 2022-23, in order to consider a full 5-year Regulatory
Period, the Authority proposes to consider 1st April 2023 to 31st March 2028 as the First Control period for the
Airport, together with considering the results for the period commencing from COD (5th January 2023) to 31st
March 2023.
In adherence to the regulatory requirements, GIAL, Mopa, Goa has submitted MYTP for aeronautical tariff
determination for the period from 7th December 2022 to 31st March 2023 and First Control Period in the following
manner:
• Determination of Tariff from 7th December 2022 to 31st March 2023.
• Multi Year Tariff Proposal (MYTP) for First Control Period (FCP) starting from FY 2023-24 to FY 2027-
28.
For this Consultation Paper, the Authority has considered the audited figures submitted by GIAL, Mopa, Goa
for the period ended 31st March 2023.
The Authority, after considering all information currently available and analysing various scenarios and the
views of the Airport Operators, Expert Agency appointed by the Airport Operator and Independent Consultant
appointed by the Authority, has reviewed the necessary adjustments in traffic and other regulatory building
blocks. However, these adjustments would be finalized only after consideration of the comments from the
stakeholders.
The Authority has released this Consultation Paper, after considering various assumptions stipulated in the Multi-
Year Tariff Proposal (MYTP) submitted by GIAL, Mopa, Goa in respect of Manohar International Airport,
Mopa, Goa. Accordingly, the Authority’s proposals on the various aspects of the Tariff determination process
have been explained in detail in this Consultation Paper.
Consultation Paper No. 11/2023-24 Page 2 of 156Stakeholders’ Comments
Thus, in accordance with the provisions of Section 13(4) of the AERA Act, 2008, the written comments on
Consultation Paper No. 11/2023-24 dated 31st August 2023 are invited from the Stakeholders, preferably in
electronic form, at the following address:
Director (P&S, Tariff)
Airports Economic Regulatory Authority of India (AERA),
AERA Administrative Complex,
Safdarjung Airport, New Delhi – 110003, India
Email: director-ps@aera.gov.in, rajan.gupta1@aera.gov.in, secretary@aera.gov.in
Stakeholders’ Consultation Meeting (Virtual) 15th September 2023
Last Date for submission of comments 29th September 2023
Last Date for submission of counter comments 09th October 2023
Comments and Counter Comments will be posted on AERA website www.aera.gov.in
For any clarification/information, Director (P&S, Tariff) may be contacted at Telephone Number: 011-24695043.
Consultation Paper No. 11/2023-24 Page 3 of 156Table of Contents
Table of Contents
List of Annexures .............................................................................................................................................................. 6
List of Appendix ............................................................................................................................................................... 7
List of Tables ..................................................................................................................................................................... 8
List of Abbreviations ...................................................................................................................................................... 11
1. BACKGROUND ...................................................................................................................................................... 14
1.1 Introduction ..................................................................................................................................................... 14
1.2 Concession Agreement for development of Manohar International Airport, Mopa, Goa ............................... 14
1.3 Development of Greenfield Airport through Public Private Partnership (PPP) .............................................. 15
1.4 Cargo, Ground handling and Fuel Farm (CGF) Operations ............................................................................ 17
2. METHODOLOGY OF TARIFF DETERMINATION OF MANOHAR INTERNATIONAL AIRPORT ..... 19
2.1 Tariff setting principles ................................................................................................................................... 19
2.2 Authority’s Order applied in Tariff Proposals in this Consultation Paper....................................................... 20
2.3 Control Period .................................................................................................................................................. 21
2.4 Past tariff determination history ...................................................................................................................... 21
2.5 MYTP submissions by GIAL, Mopa, Goa ...................................................................................................... 22
2.6 Construct of this Consultation Paper ............................................................................................................... 25
2.7 Study Commissioned by the Authority ............................................................................................................ 26
3. DETERMINATION OF TARIFF FOR THE PERIOD FROM COD (5TH JANUARY) TO 31ST MARCH
2023. .................................................................................................................................................................. 27
3.1 GIAL’s submissions regarding Tariff for the period from 7th December 2022 to 31st March 2023 ................ 27
3.2 Authority’s examination regarding Tariff for the period from COD (5th January) to 31st March 2023 .......... 27
3.3 Authority’s proposals regarding Tariff for the period from COD to 31st March 2023 .................................... 34
4. TRAFFIC FOR THE FIRST CONTROL PERIOD ............................................................................................ 35
4.1 GIAL’s submissions regarding Traffic for the First Control Period ................................................................ 35
4.2 Authority’s examination regarding Traffic for the First Control Period ......................................................... 36
4.3 Authority’s proposals regarding Traffic for the First Control Period .............................................................. 44
5. CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR
THE FIRST CONTROL PERIOD ................................................................................................................ 45
5.1 Background ...................................................................................................................................................... 45
5.2 GIAL’s submission regarding Capital Expenditure (CAPEX) for the First Control Period ........................... 47
5.3 Authority’s examination regarding Capital expenditure (CAPEX) for the First Control Period .................... 49
5.4 Aeronautical Allocation of CAPEX for the First Control Period .................................................................... 77
5.5 Depreciation for the First Control Period ........................................................................................................ 80
5.6 Regulatory Asset Base (RAB) for the First Control Period ............................................................................. 82
5.7 Authority’s proposals regarding Capital Expenditure (CAPEX), Depreciation, and Regulatory Asset Base
(RAB) for the First Control Period .................................................................................................................. 83
6. FAIR RATE OF RETURN FOR THE FIRST CONTROL PERIOD ................................................................ 84
6.1 GIAL’s submission regarding Fair Rate of Return for the First Control Period ............................................. 84
6.2 Authority’s examinations regarding Fair Rate of Return for the First Control Period .................................... 86
6.3 Authority’s proposals regarding Fair Rate of Return for the First Control Period .......................................... 88
7. INFLATION FOR THE FIRST CONTROL PERIOD ........................................................................................ 90
Consultation Paper No. 11/2023-24 Page 4 of 156Table of Contents
7.1 GIAL’s submission regarding Inflation for the First Control Period .............................................................. 90
7.2 Authority’s examination regarding Inflation for the First Control Period ....................................................... 90
7.3 Authority’s proposal regarding Inflation for the First Control period ............................................................. 90
8. OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD ............................. 91
8.1 GIAL’s submission regarding Operating and Maintenance Expenses for the First Control Period ................ 91
8.2 Authority’s examination regarding Operating and Maintenance Expenses for the First Control Period ........ 97
8.3 Authority’s proposals regarding Operating and Maintenance Expenses for the First Control Period........... 122
9. NON-AERONAUTICAL REVENUE FOR THE FIRST CONTROL PERIOD ............................................. 123
9.1 GIAL’s submission regarding Non-Aeronautical Revenue (NAR) for the First Control Period .................. 123
9.2 Authority’s examination regarding Non-Aeronautical Revenue for the First Control Period ....................... 126
9.3 Authority’s proposals regarding Non-Aeronautical Revenues for the First Control Period .......................... 134
10. TAXATION FOR THE FIRST CONTROL PERIOD ....................................................................................... 135
10.1 GIAL’s submission regarding Aeronautical Taxation for the First Control Period ...................................... 135
10.2 Authority’s examination regarding Aeronautical taxation for the First Control Period ................................ 135
10.3 Authority’s proposals regarding Aeronautical taxation for the First Control Period .................................... 137
11. QUALITY OF SERVICE FOR THE FIRST CONTROL PERIOD ................................................................ 138
11.1 GIAL’s submission regarding Quality of Service for the First Control Period ............................................. 138
11.2 Authority’s examination regarding Quality of Service for the First Control Period ..................................... 138
11.3 Authority’s proposals regarding Quality of Service for the First Control Period .......................................... 139
12. AGGREGATE REVENUE REQUIREMENT FOR THE FIRST CONTROL PERIOD .............................. 140
12.1 GIAL’s submission regarding ARR for the First Control Period .................................................................. 140
12.2 Authority’s examination regarding ARR for the First Control Period .......................................................... 140
12.3 Authority’s proposal regarding ARR for the First Control Period ................................................................ 142
13. SUMMARY OF AUTHORITY’S PROPOSALS PUT FORTH FOR STAKEHOLDER CONSULTATIONS
......................................................................................................................................................................... 143
14. STAKEHOLDER CONSULTATION TIMELINE ............................................................................................ 146
15. ANNEXURES ......................................................................................................................................................... 147
15.1 Annexure 1: Key clauses of Concession Agreement ..................................................................................... 147
15.2 Annexure 2: Consultancy and Legal Charges for FY 2023-24 submitted by GIAL, Mopa, Goa and proposed
by the Authority ............................................................................................................................................. 152
15.3 Annexure 3: Operating & Maintenance Expense for the period from COD to 31st March 2023 .................. 154
15.4 Annexure 4: Revenue from Operations for the period from COD to 31st March 2023 ................................. 155
16. APPENDICES ........................................................................................................................................................ 156
16.1 Appendix 1 - Independent Study on Capital Expenditure for Development of Greenfield Airport Facilities at
Mopa, Goa ..................................................................................................................................................... 156
16.2 Appendix 2 - Minutes of AUCC meeting ...................................................................................................... 156
Consultation Paper No. 11/2023-24 Page 5 of 156List of Annexures
List of Annexures
Annexure 1 Key clauses of Concession Agreement
Consultancy and Legal Charges for FY 2023-24 submitted by GIAL, Mopa, Goa and proposed
Annexure 2
by the Authority
Annexure 3 Operating & Maintenance Expense for the period from COD to 31st March 2023
Annexure 4 Revenue from Operations for the period from COD to 31st March 2023
Consultation Paper No. 11/2023-24 Page 6 of 156List of Appendix
List of Appendix
Independent Study on Capital Expenditure for Development of Greenfield Airport Facilities at
Appendix 1
Mopa, Goa
Appendix 2 Minutes of AUCC meeting
Consultation Paper No. 11/2023-24 Page 7 of 156List of Tables
List of Tables
Table 1: Phase-wise Airport Development proposed in Annex-II of CA ........................................................................ 14
Table 2: Key Highlights of the Concession Agreement ................................................................................................... 15
Table 3: Revised Phase-wise Airport Development proposed as per GIAL, Mopa, Goa Business Plan ......................... 16
Table 4: Technical and Terminal Building details submitted by GIAL, Mopa, Goa ....................................................... 16
Table 5: Services provided to GIAL by related parties .................................................................................................... 24
Table 6: MYTP submissions by GIAL, Mopa, Goa ......................................................................................................... 25
Table 7: Details of building blocks of ARR for the period from 7th December 2022 to 31st March 2023 submitted by
GIAL, Mopa, Goa .............................................................................................................................................. 27
Table 8: Traffic for Period from COD to 31st March 2023 .............................................................................................. 28
Table 9: Computation of Addition to RAB for the period from COD to 31st March 2023 by the Authority ................... 29
Table 10: Useful Life to be considered for Land Development ....................................................................................... 29
Table 11: Asset Category wise additions for the period from COD to 31st March 2023 proposed by the Authority ...... 30
Table 12: Regulatory Asset Base for the period from COD to 31st March 2023 computed by the Authority ................. 30
Table 13: Operating Expenditure for the period from COD to 31st March 2023 proposed by the Authority .................. 31
Table 14: Non-Aeronautical Revenue for the period from COD to 31st March 2023 proposed by the Authority ........... 32
Table 15: Aeronautical taxes for the period from COD to 31st March 2023 proposed by the Authority ......................... 32
Table 16: Aeronautical Revenue for the period from 7th December 2022 to 31st March 2023 proposed by GIAL, Mopa,
Goa ..................................................................................................................................................................... 33
Table 17: Aeronautical Revenue for the period from COD to 31st March 2023 proposed by the Authority ................... 33
Table 18: ARR and shortfall for the period from COD to 31st March 2023 proposed by the Authority .......................... 34
Table 19: Traffic for the First Control Period submitted by GIAL, Mopa, Goa for Manohar International Airport,
Mopa, Goa ......................................................................................................................................................... 35
Table 20: GIAL, Mopa, Goa’s submission of market share estimate in the state of Goa for Manohar International
Airport, Mopa, Goa ............................................................................................................................................ 36
Table 21: Share of Passenger Traffic at Dabolim Airport as decided by the Authority ................................................... 36
Table 22: 4-Year and 8-Year CAGR of Passenger Traffic at Dabolim Airport ............................................................... 37
Table 23: Air Passenger Traffic growth rates submitted by GIAL, Mopa, Goa .............................................................. 37
Table 24: Actual Domestic Passenger and ATM traffic for FY 2019-20 (Pre-COVID period) and FY 2022-23 for
Dabolim and Manohar International Airport, Mopa, Goa ................................................................................. 38
Table 25: Air Passenger traffic as proposed by the Authority for the state of Goa .......................................................... 38
Table 26: Actual Traffic for Dabolim and Manohar International Airport, Mopa, Goa .................................................. 38
Table 27: Percentage share of total Goa passenger traffic to be handled by Manohar International Airport, Mopa, Goa
........................................................................................................................................................................... 40
Table 28: Passenger traffic proposed by the Authority to be handled at Manohar International Airport, Mopa, Goa .... 40
Table 29: ATM as proposed by the Authority for the First Control Period ..................................................................... 41
Table 30: Cargo traffic proposed by the Authority for the First Control Period .............................................................. 42
Table 31: Traffic proposed by the Authority for the First Control Period ....................................................................... 42
Table 32: Project wise revised Capital Expenditure submitted by GIAL, Mopa, Goa for the First Control Period ........ 47
Table 33: Financing Allowance as submitted by GIAL, Mopa, Goa for the First Control Period ................................... 48
Table 34: Project Means & Finance as submitted by GIAL, Mopa, Goa for the First Control Period ............................ 48
Table 35: Reconciliation between the Capex submitted by GIAL, Mopa, Goa and CAPEX analyzed by M/s KITCO .. 49
Table 36: Inflation Adjusted Normative Cost for Apron ................................................................................................. 50
Table 37: Inflation Adjusted Normative Cost for Pavement ............................................................................................ 50
Table 38: Inflation Indexed Rate considered for Phase III- Airside Pavement ................................................................ 50
Table 39: Cost Proposed by M/s KITCO for Airside Pavement for the First Control Period .......................................... 51
Table 40: Inflation Indexed rate considered for Phase III - PTB ..................................................................................... 52
Table 41: Cost Proposed by M/s KITCO for PTB for the First Control Period ............................................................... 52
Table 42: Cost Proposed by M/s KITCO for Airside Buildings, Roads and Drainage Systems for the First Control
period ................................................................................................................................................................. 54
Consultation Paper No. 11/2023-24 Page 8 of 156List of Tables
Table 43: Cost proposed by M/s KITCO for Site Preparation/Earth Work for the First Control Period ......................... 56
Table 44: Cost proposed by M/s KITCO for Administrative Office Building and Site Office for the First Control Period
........................................................................................................................................................................... 58
Table 45: Cost proposed by M/s KITCO for ATC Technical block & ATC tower for the First Control Period ............. 59
Table 46: Breakup of cost assessed by M/s KITCO for ATC Technical block and ATC Tower .................................... 60
Table 47: Cost proposed by M/s KITCO for Main Access Road & Car Park for the First Control Period ..................... 61
Table 48: Cost proposed by M/s KITCO for Additional Works for the First Control period .......................................... 62
Table 49: Cost proposed by M/s KITCO for Design consultancy & PMC expenses ....................................................... 64
Table 50: Cost proposed by M/s KITCO for Pre-Operative expenses ............................................................................. 65
Table 51: Financing Allowance as submitted by GIAL, Mopa, Goa for the First Control Period ................................... 66
Table 52: Financing Allowance calculation proposed by M/s KITCO for the First Control Period ................................ 66
Table 53: KITCO recommendations on Project wise capital expenditure ....................................................................... 66
Table 54: Inflation Indexed rate considered by the Authority for calculating cost for Airside Pavement (Runway,
Taxiways and Apron) ........................................................................................................................................ 68
Table 55: Cost Proposed by Authority for Airside Pavement (Runway, Taxiways and Apron) ...................................... 68
Table 56: Inflation Indexed rate considered by the Authority for calculating cost for Passenger Terminal Building ..... 69
Table 57: Cost proposed by the Authority for PTB .......................................................................................................... 69
Table 58: PMC expenses computed by the Authority ...................................................................................................... 70
Table 59: Cost proposed by the Authority for Design Consultancy and PMC expenses ................................................. 70
Table 60: Cost of Debt considered by the Authority for calculating the Financing Allowance ....................................... 70
Table 61: Financing Allowance as proposed by the Authority for Phase I ...................................................................... 71
Table 62: Capex comparison between M/s KITCO and the Authority’s proposal for the First Control Period (includes
Phase I, II &II) ................................................................................................................................................... 75
Table 63: CAPEX proposed by the Authority for the First Control Period ..................................................................... 75
Table 64: Year Wise Capital Expenditure proposed by the Authority ............................................................................. 77
Table 65: Category wise asset values of total additions as submitted by GIAL, Mopa, Goa .......................................... 77
Table 66: Detail of package wise cost and allocation as submitted by GIAL, Mopa, Goa .............................................. 78
Table 67: Aeronautical Capital Additions proposed by the Authority for the First Control Period ................................. 79
Table 68: Asset category wise Aeronautical additions proposed by the Authority for the First Control Period ............. 80
Table 69: Useful life adopted by GIAL, Mopa, Goa ........................................................................................................ 81
Table 70: Aeronautical Depreciation submitted by GIAL, Mopa, Goa for the First Control Period ............................... 81
Table 71: Useful life adopted by the Authority ................................................................................................................ 81
Table 72: Total Aeronautical depreciation proposed by the Authority for the First Control Period ................................ 82
Table 73: RAB submitted by GIAL, Mopa, Goa for the First Control Period ................................................................. 82
Table 74: RAB proposed by the Authority for the First Control Period .......................................................................... 83
Table 75: Cost of equity computation as per GIAL, Mopa, Goa’s submission ................................................................ 85
Table 76 : Weighted average cost of capital computation submitted by GIAL, Mopa, Goa for FRoR ........................... 86
Table 77: Fair Rate of Return proposed by the Authority for the First Control Period.................................................... 88
Table 78: Inflation rates submitted by GIAL, Mopa, Goa for the First control period .................................................... 90
Table 79: Inflation rates proposed by the Authority for the First control period ............................................................. 90
Table 80: Total Operating and Maintenance Expenses submitted by GIAL, Mopa, Goa for the First Control Period.... 91
Table 81: Department wise manpower details submitted by GIAL, Mopa, Goa together with its classification ............ 92
Table 82: Breakup and basis of Admin and General expenses as submitted by GIAL, Mopa, Goa ................................ 93
Table 83: Details of IT service contract ........................................................................................................................... 95
Table 84: Basis for Operating Expense as submitted by GIAL, Mopa, Goa .................................................................... 95
Table 85: Classification and Allocation of O&M expenses submitted by GIAL, Mopa, Goa for the First Control Period
........................................................................................................................................................................... 96
Table 86: GIAL, Mopa, Goa’s submission of Aeronautical Operating and Maintenance expenditure for the First
Control Period .................................................................................................................................................... 96
Table 87: Gross Block ratio proposed by the Authority for the First Control Period ...................................................... 98
Table 88: Employee Head Count Ratio proposed by the Authority for the First Control Period .................................... 99
Consultation Paper No. 11/2023-24 Page 9 of 156List of Tables
Table 89: Allocation Ratios proposed by the Authority for the First Control Period .................................................... 100
Table 90: Classification and Allocation of O&M expenses proposed by the Authority for the First Control Period .... 100
Table 91: Expansion Increase % proposed by the Authority for the First Control Period ............................................. 102
Table 92: Manpower Expenses proposed by the Authority for the First Control Period ............................................... 103
Table 93: Aeronautical Manpower Expenses proposed by the Authority for the First Control Period.......................... 103
Table 94:Admin and General expenses proposed by the Authority for the First Control Period ................................... 104
Table 95: Aeronautical Rates and Taxes for FY 2023-24 proposed by the Authority ................................................... 107
Table 96: Aeronautical Admin and General Expenses proposed by the Authority for the First Control Period ........... 109
Table 97: Power Charges proposed by the Authority for the First Control Period ........................................................ 110
Table 98: Total Utility Expenses proposed by the Authority for the First Control Period ............................................. 111
Table 99: Aeronautical Utility Expenses proposed by the Authority for the First Control Period ................................ 111
Table 100: Misc. Expenses analysis and observations by the Authority ........................................................................ 114
Table 101: Operating Expenses proposed by the Authority for the First Control Period .............................................. 118
Table 102: Aeronautical Operating Expenses proposed by the Authority for the First Control Period ......................... 118
Table 103: Total O&M expenses proposed by the Authority for the First Control Period ............................................ 119
Table 104: Aeronautical O&M expenses proposed by the Authority for the First Control Period ................................ 121
Table 105: Non-Aeronautical Revenue submitted by GIAL, Mopa, Goa for the First Control Period.......................... 123
Table 106: Revenues per passenger of In-Flight Kitchen of Comparable Airports to Manohar International Airport,
Mopa, Goa ....................................................................................................................................................... 127
Table 107: In Flight Kitchen Revenue for FY 2023-24 for Manohar International Airport, Mopa, Goa proposed by the
Authority .......................................................................................................................................................... 127
Table 108: In Flight Kitchen Revenue proposed by the Authority for the First Control Period for Manohar International
Airport, Mopa, Goa .......................................................................................................................................... 127
Table 109: Revenues per passenger (FY 2022-24) for the six services of comparable Airports to Manohar International
Airport, Mopa, Goa .......................................................................................................................................... 129
Table 110: Revenue for Six services for FY 2023-24 of Manohar International Airport, Mopa, Goa .......................... 130
Table 111: Revenue for six services proposed by the Authority for the First Control Period ....................................... 130
Table 112: Area Let out with purpose and rent per sqm per month ............................................................................... 131
Table 113: Area let out for Master Services and rent per sqm per month ...................................................................... 132
Table 114: Revenue from Land and Space proposed by the Authority for the First Control Period ............................. 132
Table 115: Non-Aeronautical Revenue proposed by the Authority for First Control Period ......................................... 134
Table 116: Aeronautical taxes submitted by GIAL, Mopa, Goa for First Control Period ............................................. 135
Table 117: Interest cost as per MYTP submission and Interest cost considered in Aeronautical P&L by GIAL, Mopa,
Goa ................................................................................................................................................................... 136
Table 118: Aeronautical taxes proposed to be considered by the Authority for First Control Period ........................... 137
Table 119: ASQ rating for Goa International Airport, Dabolim for the years 2021-2023 Q1 ....................................... 138
Table 120: Aggregate revenue requirement (ARR) submitted by GIAL, Mopa, Goa for the First Control Period ....... 140
Table 121: Aggregate Revenue Requirement proposed by Authority for the First Control Period ............................... 140
Consultation Paper No. 11/2023-24 Page 10 of 156List of Abbreviations
List of Abbreviations
Abbreviation Expansion
AAI Airports Authority of India
ACI Airports Council International
AERA/ Authority Airports Economic Regulatory Authority of India
AEMB Airline Engineering and Maintenance Building
AGL Aeronautical Ground Lighting
ANS Air Navigation Services
AO Airport Operator
AOCC Airports Operations Control Centre
ARFF Aviation Rescue and Fire Fighting
ARR Aggregate Revenue Requirement
ASDC Aviation Skill Development Center
ASQ Airport Service Quality
ATC Air Traffic Control
ATM Air Traffic Movement
ATV Average Ticket Value
AUCC Airport User Consultative Committee
BHS Baggage Handling System
BIAL Bangalore International Airport Limited
BOQ Bill of Quantity
BPCL Bharat Petroleum Corporation Limited
BSE Bombay Stock Exchange
CA Concession Agreement
CAGR Compounded Annual Growth Rate
CAPEX Capital Expenditure
CAPM Capital Asset Pricing Model
CCTV Closed Circuit Television
CGF Cargo, Ground handling and Fuel Farm
CIAL Cochin International Airport Limited
CISF Central Industrial Security Force
COD Commercial Operation Date
COVID-19 Corona Virus Disease-2019
CP Consultation Paper
CPI Consumer Price Index
CPWD Central Public Works Department
CSR Corporate Social Responsibility
CUTE Common User Terminal Equipment
CWIP Capital Work in Progress
DBFOT Design, Build, Finance, Operate and Transfer
DGCA Directorate General of Civil Aviation
DGU Double Glazing Unit
DIAL Delhi International Airport Limited
DSRA Debt Service Reserve Account
EC Environment Clearance
EHCR Employee Headcount Ratio
EHS Environment, Health & Safety
Consultation Paper No. 11/2023-24 Page 11 of 156List of Abbreviations
Abbreviation Expansion
EPC Engineering, Procurement and Construction
F&B Food and Beverages
FA Financing Allowance
FCP First Control Period
FRoR Fair Rate of Return
GAL GMR Airports Limited
GDP Gross Domestic Product
GIAL Goa International Airport Limited
GoG Government of Goa
GoI Government of India
GOI Goa International Airport, Dabolim (IATA Code)
GOX Manohar International Airport, Mopa, Goa (IATA Code)
GST Goods and Services Tax
HIAL Hyderabad International Airport Limited
HVAC Heating, Ventilation and Air Conditioning
IATA International Air Transport Association
ICAO International Civil Aviation Organization
IDC Interest During Construction
IFK In-Flight Kitchen
IMG Inter-Ministerial Group
IPP Income Per Passenger
IT Information Technology
MAG Management Assurance Group
MAT Minimum Alternate Tax
MCLR Marginal Cost of Funds based Lending Rate
MEP Mechanical, Electrical and Plumbing
MIAL Mumbai International Airport Limited
MRO Maintenance, Repair and Overhaul
MYTP Multi Year Tariff Proposal
NAR Non-Aeronautical Revenue
NGT National Green Tribunal
PBB Passenger Boarding Bridges
PBG Performance Bank Guarantee
PBT Profit Before Tax
PH&E Public Health & Engineering
PMC Project Management Consultancy
PO Purchase Order
PPP Public Private Partnership
PTB Passenger Terminal Building
PV Present Value
R&M Repairs and Maintenance
RAB Regulatory Asset Base
RBI Reserve Bank of India
RFP Request for Proposal
SCI Hon’ble Supreme Court of India
SCP Second Control Period
Consultation Paper No. 11/2023-24 Page 12 of 156List of Abbreviations
Abbreviation Expansion
SPP Sales Per Passenger
TB Terminal Building
TBLR Terminal Building Ratio
TOPS Terminal Operations
UDF User Development Fee
WACC Weighted Average Cost of Capital
WDV Written Down Value
WIP Work in Progress
WPI Wholesale Price Index
Unit of Measurement
Cr Crore
FY Financial Year
Mn Million
MPPA Million Passenger Per Annum
MT Metric Tonne
Nos Number
Rs. Rupees
Sq.m. Square meter
YoY Year on Year
Consultation Paper No. 11/2023-24 Page 13 of 156BACKGROUND
1. BACKGROUND
1.1 Introduction
1.1.1 Goa, located on the western coast in the Konkan region, is one of the most popular tourist destinations in the
country. It is the fourth smallest state by population and has only two districts – North Goa and South Goa.
Tourism is one of the major industry providing direct and indirect employment in the state. Goa witnessed
more than 80 lakhs tourist arrivals in the year 2019 including 9 lakh foreign tourists.
1.1.2 Goa International Airport (known as “Dabolim Airport” or “GOI”) is an airport existing in Dabolim, Goa,
which is operated by Airports Authority of India (AAI) and the Indian Navy. Being a civil enclave, Dabolim
Airport is constrained with operational restrictions resulting in congestion and non-availability of slots for
airlines during daytime. Considering the difficulties and the future economic growth of the state, the
Government of Goa (GoG) decided to develop a greenfield airport at Mopa, Goa through a Public Private
Partnership (PPP) mode.
1.1.3 With the commencement of operations at Manohar International Airport, Mopa, Goa (IATA: GOX), Goa has
2 International Airports in the state.
1.2 Concession Agreement for development of Manohar International Airport, Mopa, Goa
1.2.1 GMR Airports Limited (GAL) won the bid for development of the new airport at Mopa, Goa and signed the
Concession Agreement on 8th November 2016 via a special purpose vehicle named “Goa International Airport
Limited (GIAL)”. GIAL, Mopa, Goa was incorporated on 14th October 2016 with 99.99% holding by GAL
and one Golden share (Non-transferable equity share with various rights) in favor of GoG.
1.2.2 As per the agreement, GIAL, Mopa, Goa, will develop the airport under the DBFOT (Design, Build, Finance,
Operate and Transfer) model for an initial period of 40 years from the appointment date (4th September 2017),
which is extendable by another 20 years (based on bidding process) with the First Right of Refusal available
to the Concessionaire, i.e., GIAL, Mopa, Goa.
1.2.3 Concession Agreement (CA) envisaged development of Manohar International Airport, Mopa, Goa as an
integrated international and domestic airport in a phased manner based on a traffic-trigger principle.
Accordingly, the Concession Agreement stipulated the capacity for different phases of development. The
following table indicates the capacities as per CA (Refer Clause 12.2.1 under Annexure 1).
Table 1: Phase-wise Airport Development proposed in Annex-II of CA
Phasing Traffic Design Capacity (In MPPA) Trigger for Phasing
Phase I 4.4 On the date of COD
Phase II 5.8 80% of Phase 1 Capacity
Phase III 9.4 80% of Phase II Capacity
Phase IV 13.1 80% of Phase III Capacity
1.2.4 Key clauses from the CA are as detailed below. A summary of clauses from the CA are listed in Annexure 1.
Consultation Paper No. 11/2023-24 Page 14 of 156BACKGROUND
Table 2: Key Highlights of the Concession Agreement
Clause
Headings Description
No.
Concession Construction and procurement of the Aeronautical Assets including Runways,
3.1.(i)
requirement taxiways, apron, aircraft parking bays and other associated facilities.
Level of service for Terminal Building – IATA Level of Service “C” (optimum
standards) compliant. The total area of the Terminal Building should be based on 25
3.1.(ii) &
Construction and to 40 square meter per peak hour passenger for the design year.
Annexure
procurement of 80% (eighty per cent) of each of the international and domestic aircrafts B737/ A320
II of
the Terminal or larger aircrafts shall be served by the boarding bridges.
Schedule
Building Provide international standard range of retail and other passenger services.
A
Terminal design must be capable of incremental expansion with minimum impact
on current operations.
5.1 381 acres out of 2093 acres is earmarked for city side development.
City side For avoidance of doubt, revenues of the Concessionaire from City Side Development
development 3.6.2 shall be excluded from the Shared-Till framework for the determination and
regulation of the Aeronautical Charges.
Defense area 6.1 5 acres out of 2093 acres shall be carved out for the use of Defense forces
Cargo facilities
The Concessionaire shall earmark land within the site for the development of a Cargo
(Schedule B of 7.1
Facility in the Airport.
CA)
Maintenance,
Repair and
The Concessionaire shall earmark minimum 26 acres of land within the Site for the
Overhaul (MRO)
8.1 development of an MRO Facility in the Airport as per the applicable Standards and
Facilities
Specifications.
(Schedule B of
CA)
Concessionaire agrees to pay to the Authority for each year commencing from the
30.2.1 6th (sixth) year of the occurrence of the Appointed Date, a premium (the "Annual
Premium") equal to 36.99 % of Gross Revenue.
Annual premium The Annual Premium shall not be considered as a part of the capital outlay for the
Airport or the regulatory asset base or operating expense for the purpose of the
32.3.3
determination of the Aeronautical Charges and shall always be excluded from being
considered as a part of the cost for the determination of the Aeronautical Charges.
1.3 Development of Greenfield Airport through Public Private Partnership (PPP)
1.3.1 On 28th October 2015, Environment Clearance was granted for the project. Construction of Manohar
International Airport, Mopa, Goa commenced in FY 2015-16. The airport was expected to be commissioned
by November 2019 as per the CA.
1.3.2 The construction activities in the airport were suspended for an interim period due to certain orders issued by
the Hon’ble courts. Following orders were issued by Hon’ble courts relating to the Airport Project:
• On 8th March 2018, an order was issued by the Hon’ble High Court of Bombay to stay tree cutting in the
region, as a response to concerns about environmental degradation and the loss of greenery in the area.
Consultation Paper No. 11/2023-24 Page 15 of 156BACKGROUND
• On 19th March 2019, the Hon’ble Supreme Court of India (SCI) suspended the Environment Clearance
that had been granted for the project, due to concerns about the environmental impact of the project and
the need for a more thorough assessment of the potential consequences.
• By 16th January 2020, the petition related to the suspension of the Environment Clearance was dismissed
by the Hon’ble Supreme Court of India. As a result, the suspension of the Environment Clearance was
removed but with certain conditions attached to ensure that the project would not have an undue impact
on the environment.
1.3.3 Due to the Hon’ble Supreme Court status quo order which prevailed for about one year against Environment
clearance of the project, the completion date got postponed to August 2022. Based on the change in
commencement date, GIAL, Mopa, Goa proposed a revised phasing of construction, which was approved by
GoG. The phasing of construction and the revised phase-wise capacity planned at the Airport is as indicated
below:
Table 3: Revised Phase-wise Airport Development proposed as per GIAL, Mopa, Goa Business Plan
Phase Capacity in MPPA Financial Year
Phase 1 4.40 FY 2022-23
Phase 2 7.70 FY 2023-24
Phase 3 11.10 FY 2025-26
Phase 4 16.00 FY 2030-31
Phase 5 21.60 FY 2042-43
1.3.4 Manohar International Airport, Mopa, Goa is presently connected with NH66 via a 2-lane operational access
road. As per the terms of CA, GoG has to complete four-lane expressway (6.59 kms) connecting NH-66 with
airport in 5 years from the appointed date. The 6.59 kms connecting road has been declared as a National
Highway (NH-166S) under the Bharat Mala Pariyojna and would be developed by National Highways
Authority of India (NHAI). The land acquisition and other activities have started as per the NH Act and
expressway is expected to be operational in FY 2023-24.
1.3.5 The Airport was inaugurated on 11th December 2022 and the operations commenced on 5th January 2023.
1.3.6 Technical and Terminal Building details submitted by GIAL, Mopa, Goa for Phase I, II & III are as detailed
below:
Table 4: Technical and Terminal Building details submitted by GIAL, Mopa, Goa
Particulars Phase I Phase II Phase III
Airside
3500X 45 m+7.5 m Shoulder each side,
Runway
Flexible Pavement
57150 Sqm, Rigid Pavement + Isolation
Apron ~20,000 Sqm ~35,000 Sqm
Bay of 19,100 sqm
5 Nos (3 for code C, 1 MARS, 1 code E
Total In contact Aircraft Stands 4 Nos (Code C)
or 2 code C)
Remote stands 9 Nos
VDGS 6 Nos 2 Nos
Consultation Paper No. 11/2023-24 Page 16 of 156BACKGROUND
Particulars Phase I Phase II Phase III
Landside
5 Lane (3 movement + 2 parking);
Departure Forecourt
Carriage width: 14.5 m
5 Lane (3 movement +2 parking);
Arrival Forecourt
Carriage width: 14.5 m
Height 46.8 M, Tech. Bldg. G+3 (Area
ATC & ATCTB
3865 Sq. m)
Passenger Terminal Building
Capacity 4.4 MPPA (Shell built for 7.7 MPPA) 7.7 MPPA 11.1 MPPA
Total Built-up 67,726 Sqm. ~25,000 Sqm
Entry Gates (Check -in Hall) 3 Nos
Check-in-Island 1 No 1 No
Check-in counters 22 (4 nos. for Self-Baggage Drop) 20 Nos
ATRS 7 in nos. (~300 Bags / hr.) 2 Nos
Baggage reclaim belt 2(Domestic) + 1(International)
Passenger Boarding Bridges 5 Nos 2 Nos
Extension for 2nd
Baggage Screening Capacity 2 Lines (2400-3000 bags / hr.)
island
Bus Gate Domestic 3 Nos.
Bus Gate International 2 Nos.
Bus Gate VIP 1 No.
Emigration counters 8 Nos. (Departure) 4 Nos.
Immigration counters 12 Nos. (Arrival) 8 Nos.
1.4 Cargo, Ground handling and Fuel Farm (CGF) Operations
1.4.1 The Concession Agreement details the provision of Cargo, Ground Handling and Fuel facilities at the Airport.
The Concession Agreement also states that Aeronautical Services have the meaning as set forth in AERA Act
in relation to the services to be provided at the Airport. Aeronautical Services defined in AERA Act include
services relating to Cargo, Ground Handling and Fuel facilities. The Authority’s responsibilities defined in
AERA Act also provide for determination of charges for Aeronautical activities of Cargo, Ground Handling
and Fuel facilities at the Airport.
Cargo Operations
1.4.2 Over the past decade, Cargo traffic at Goa's Dabolim airport had remained constant at approximately 4,500
metric tonnes per annum due to limited cargo handling infrastructure. Furthermore, the lack of adequate
infrastructure has prevented the airport from attracting dedicated freight carriers, resulting in all cargo being
transported in civilian aircraft’s belly holds.
1.4.3 The Concession Agreement has included provisions for the development of a cargo facility within the site.
Once completed, the cargo facilities at Manohar International Airport, Mopa, Goa are expected to contribute
to increase in the capacity from 4,500 to 25,000 metric tonnes per annum across the 2 airports in Goa.
1.4.4 On 16th November 2021, GIAL, Mopa, Goa awarded the cargo license through a bidding process, resulting
in a 15.3% revenue share. The license has an initial period of 20 years effective from 16th November 2021.
Consultation Paper No. 11/2023-24 Page 17 of 156BACKGROUND
Ground Handling (GH) Operations
1.4.5 Clause 18.2 of the Concession Agreement (Refer Annexure 1) details GIAL, Mopa, Goa’s obligations
towards provision of infrastructure required for ground handling services at Manohar International Airport,
Mopa, Goa.
1.4.6 Subject to the provisions of the Concession Agreement, GIAL, Mopa, Goa has the right to grant License to
any entity for providing Ground Handling Services at Manohar International Airport, Mopa, Goa on such
terms and conditions to be mentioned in the License Agreement between GIAL, Mopa, Goa and the potential
service provider.
1.4.7 Pursuant to above terms of the Concession Agreement, GIAL, Mopa, Goa has engaged Celebi Airport
Services (India) Private Limited (CASIPL) for provision of such Ground Handling services at Manohar
International Airport, Mopa, Goa through a bidding process, resulting in a revenue share of 5% in case of
domestic and 30.5% in case of international and other services.
Fuel Facility Operations
1.4.8 GIAL, Mopa, Goa's obligations to provide aircraft fueling services are detailed in clause 18.3 of the
Concession Agreement (Refer Annexure 1).
1.4.9 Subject to the terms of the Concession Agreement, GIAL, Mopa, Goa has the right to grant a license to any
entity for the provision of Aircraft Fueling Services at Manohar International Airport, Mopa, Goa on terms
and conditions specified in the License Agreement between GIAL, Mopa, Goa and the potential service
providers.
1.4.10 According to the conditions of the Concession Agreement, GIAL, Mopa, Goa has sub-licensed Aircraft
Fueling Services to Bharat Petroleum Corporation Limited for a period of 20 years under the framework of
designing, building, financing, operation, maintenance, and transfer. The Fuel Farm will operate on an "open
access" basis with a 15% & 5% revenue share to GIAL, Mopa, Goa from the gross revenue earned on account
of Fuel Infrastructure Charges (FIC) and Into Plane charges respectively.
Consultation Paper No. 11/2023-24 Page 18 of 156METHODOLOGY OF TARIFF DETERMINATION OF MANOHAR INTERNATIONAL AIRPORT
2. METHODOLOGY OF TARIFF DETERMINATION OF MANOHAR INTERNATIONAL
AIRPORT
2.1 Tariff setting principles
2.1.1 AERA was established by the Government of India vide notification No. GSR 317(E) dated 12th May 2009.
The functions of AERA, in respect of Major Airports, are specified in section 13(1) of The Airports Economic
Regulatory Authority of India Act, 2008 (‘AERA Act’ or ‘the Act’) read with AERA (Amendment) Act 2019
and 2021, which are as below:
a) To determine the tariff for aeronautical services taking into consideration.
i. The capital expenditure incurred and timely investment in improvement of airport facilities;
ii. The service provided, its quality and other relevant factors;
iii. The cost for improving efficiency;
iv. Economic and viable operation of major airports;
v. Revenue received from services other than aeronautical services;
vi. Any Concession offered by the Central Government in any agreement or memorandum of
understanding or otherwise;
vii. Any other factor which may be relevant for the purposes of the Act:
Provided that different tariff structures may be determined for different airports having regard to all or
any of the above considerations specified at sub-clauses (i) to (vii).
b) To determine the amount of development fees in respect of major airports;
c) To determine the amount of passenger service fee levied under rule 88 of the Aircraft Rules, 1937 made
under Aircraft Act, 1934;
d) To monitor the set performance standards relating to quality, continuity and reliability of service as may
be specified by the Central Government or any Authority authorized by it in this behalf;
e) To call for such information as may be necessary to determine the tariff under clause 13(1)(a).
f) To perform such other functions relating to tariff, as may be entrusted to it by the Central Government or
as may be necessary to carry out the provisions of this Act.
2.1.2 As per the AERA Act, 2008 the following are the Aeronautical services:
i. Aeronautical Services Provided by the Airport Operators
ii. Cargo, Ground Handling and Fuel Supply Services; and
iii. Air Navigation Services
2.1.3 AAI shall be handling the Air Navigation Systems (ANS) at Manohar International Airport, Mopa, Goa.
Tariff for ANS is presently regulated by the Ministry of Civil Aviation. All the assets, expenses and revenues
pertaining to ANS are considered separately by the Ministry while determining tariff for ANS services.
Further, the tariff for ANS services is determined at the Central level by the Ministry of Civil Aviation to
Consultation Paper No. 11/2023-24 Page 19 of 156METHODOLOGY OF TARIFF DETERMINATION OF MANOHAR INTERNATIONAL AIRPORT
ensure uniformity across the Airports in India. Hence, AERA determines tariff for Aeronautical services of
the Airport Operator, by excluding the assets, expenses and revenues from ANS.
2.1.4 The Methodology adopted by the Authority to determine Aggregate Revenue Requirement (ARR) is based
on AERA Act, 2008 read with AERA (Amendment) Act 2019 and 2021, the AERA (Terms and Conditions
for determination of Tariff for Airport Operators) Guidelines, 2011 and further Guidelines issued by AERA
from time to time.
2.1.5 The Authority has adopted the Hybrid-Till mechanism for tariff determination for the First Control Period
wherein, 30% of the non-aeronautical revenues is to be used for cross-subsidizing the aeronautical charges.
2.1.6 The ARR for a given Control Period, under Hybrid Till, is calculated as
5
𝐴𝑅𝑅 =∑ 𝐴𝑅𝑅
𝑡
𝑡=1
𝐴𝑅𝑅 = (𝐹𝑅𝑜𝑅 𝑥 𝑅𝐴𝐵 )+𝐷 +𝑂 +𝑇 −𝑠 𝑥 𝑁𝐴𝑅
𝑡 𝑡 𝑡 𝑡 𝑡
Where,
t is the tariff year in the control period, ranging from 1 to 5
𝐴𝑅𝑅 is the Aggregate Revenue Requirement for tariff year ‘t’
𝑡
FRoR is the Fair Rate of Return for the Control Period
𝑅𝐴𝐵 is the Aeronautical Regulatory Asset Base for tariff year ‘t’
𝑡
𝐷 is the Depreciation corresponding to the Regulatory Asset Base for tariff year ‘t’
𝑡
𝑂 is the Aeronautical Operation and Maintenance expenditure for the tariff year ‘t’
𝑡
𝑇 is the Aeronautical taxation expense for the tariff year ‘t’
𝑡
s is the cross-subsidy factor for revenue from services other than Aeronautical services under the Hybrid
Till methodology followed by the Authority, s = 30%.
𝑁𝐴𝑅 is the Non-Aeronautical Revenue in tariff year ‘t’.
𝑡
2.1.7 Based on ARR, Yield per passenger (Y) is calculated as per the formula given below:
∑5 𝑃𝑉(𝐴𝑅𝑅 )
𝑡=1 𝑡
𝑌𝑖𝑒𝑙𝑑 𝑝𝑒𝑟 𝑝𝑎𝑠𝑠𝑒𝑛𝑔𝑒𝑟 (𝑌) =
∑5 𝑉𝐸
𝑡=1 𝑡
Where,
PV (ARR) is the Present Value of ARR. All cash flows are assumed to occur at the end of the year. The
t
Authority has considered discounting cash flows, one year from the start of the Control Period.
VE is the passenger traffic in year ‘t’.
t
2.2 Authority’s Order applied in Tariff Proposals in this Consultation Paper
2.2.1 The Authority’s Orders applied in the tariff proposals in this Consultation Paper (CP) are:
Consultation Paper No. 11/2023-24 Page 20 of 156METHODOLOGY OF TARIFF DETERMINATION OF MANOHAR INTERNATIONAL AIRPORT
i. Order No. 13 dated 12th January 2011 (Regulatory philosophy and approach in Economic Regulation of
Airport Operators) and Direction No. 5 dated 28th February 2011 (Terms and conditions for
determination of tariff for Airport Operators);
ii. Order No. 05 dated 02nd August 2010 ((Regulatory philosophy and approach in Economic Regulation
of the services provided for Cargo facility, Ground Handling and Supply of Fuel to aircrafts); Order No.
12 dated 10th January 2011 and Direction No. 4 dated 10th January 2011 (Terms and conditions for
determination of tariff for services provided for Cargo facility, Ground Handling and Supply of Fuel to
aircrafts).
iii. Order No. 07/2016-17 dated 13th June 2016 (Normative Approach to Building Blocks in Economic
Regulation of Major Airports).
iv. Order No. 14/2016-17 dated 23rd January 2017 in the matter of aligning certain aspects of AERA’s
Regulatory Approach (Adoption of Regulatory Till) with the provisions of the National Civil Aviation
Policy – 2016 (NCAP-2016) approved by the Government of India.
v. Order No. 20/2016-17 dated 31st March 2017 in the matter of allowing Concession to Regional
Connectivity Scheme (RCS) Flights under RCS – Ude Desh ka Aam Nagarik (UDAN) at Major Airports.
vi. Order No. 35/2017-18 dated 12th January 2018 and Amendment No. 01 to Order No. 35/2017-18 dated
09th April 2018 in the matter of determination of useful life of Airport assets.
vii. Order No. 42/2018-19 dated 5th March 2019 in the matter of Determination of Fair Rate of Return
(FRoR) to be provided on Cost of Land incurred by various Airport Operators in India.
2.3 Control Period
2.3.1 The Authority notes that GIAL, Mopa, Goa has submitted the MYTP for the initial period starting from 7th
December 2022 to 31st March 2023 together with 5-year period from FY 2023-24 to FY 2027-28.
2.3.2 The Authority notes that the Airport was commissioned on 7th December 2022 and commenced its
commercial operations on 5th January 2023. Further, the Authority notes that the first financial year only
contains under 3 months of operations. To give effect of a full term of 5 years, the Authority proposes to
consider the Control Period as effective from FY 2023-24 to FY 2027-28 together with considering the results
of the period from 5th January 2023 i.e. COD to 31st March 2023
2.3.3 Accordingly, Authority has reviewed the actuals for the period ended 31st March 2023 in Chapter 3 and
considered the same appropriately in the computation of Aggregate Revenue Requirement in Chapter 12.
2.4 Past tariff determination history
2.4.1 The Authority vide Order No. 19/2022-23 dated 26th August 2022 allowed GIAL, Mopa, Goa to levy and
collect the tariff for Aeronautical Services on an Ad-hoc basis w.e.f. Commercial Date of Operation (COD)
to 31st March 2023 or till the determination of the regular Aeronautical Tariff for the First Control Period,
whichever is earlier. The Authority noted that the regular tariff determination was under process and since
this will take some time, the Authority further extended the existing tariff order for a period of six (06) months
w.e.f 01.04.2023 to 30.09.2023 or till the determination of regular tariffs for the relevant Control Period,
whichever is earlier, vide Order No. 41/2022-23 dated 22nd March 2023.
2.4.2 Order No. 25/2022-23 dated 7th October 2022 was issued granting approval to M/s Celebi Airport Services
(India) Pvt. Ltd. (CASPIL) to levy and collect on an Ad-hoc basis, tariff for Ground Handling Services at the
Consultation Paper No. 11/2023-24 Page 21 of 156METHODOLOGY OF TARIFF DETERMINATION OF MANOHAR INTERNATIONAL AIRPORT
airport w.e.f. COD till 31st March 2023 or till the determination of the regular Tariff, whichever is earlier.
Vide Order No. 11/2023-24 dated 15th June 2023, the Authority decided to determine the regular tariff for
CASPIL, under the ‘Light Touch Approach” for the First Control Period (FY 2023-24 to FY 2027-28) and
has approved the tariff rate card.
2.4.3 GIAL, Mopa, Goa had sub-licensed the designing, building, financing, operation, maintenance and transfer
of Cargo Terminal Facilities and Services at the Airport to GMR Airports Limited (GAL) for an initial period
of 20 years as approved by GoG. GAL vide letter dated 14th July 2022 had requested the authority to allow it
to levy Ad-hoc tariff as proposed. Pursuant to the letter, the Authority vide Order No. 28/2022-23 dated 14th
November 2022 had allowed GAL to levy and collect tariff on an Ad-hoc basis for Cargo Handling Services
at the airport w.e.f. COD till 30th September 2023 or till the determination of the regular Tariff, whichever is
earlier.
2.4.4 As requested by ISP, the Authority vide the Order No. 29/2022-23 dated 30th November 2022 has allowed
Bharat Petroleum Corporation Limited (BPCL) to levy and collect, on an Ad-hoc basis, tariff for Fuel Farm
& Into Plane (ITP) Services w.e.f. COD till 30th September 2023 or till the determination of the regular Tariff,
whichever is earlier.
2.4.5 In response to GIAL, Mopa, Goa letter dated 6th March 2023 regarding levy of Ad-hoc tariff for Bridge
Mounted Equipment Service, the Authority issued Order No. 01/2023-24 on 18th April 2023. Vide the Order,
the Authority allowed GIAL, Mopa, Goa to levy and collect the tariff on Ad-hoc basis w.e.f. 24th April 2023
to 30th September 2023 or till the determination of the regular Aeronautical Tariff for the First Control Period,
whichever is earlier.
2.5 MYTP submissions by GIAL, Mopa, Goa
2.5.1 On 7th January 2022, GIAL, Mopa, Goa submitted its Multi-Year Tariff Proposal (MYTP) for the period from
September 2022 to 31st March 2023, and the First Control Period from FY 2023-24 to FY 2027-28. The initial
submission contained provisional figures for the period from September 2022 to 31st March 2023.
2.5.2 GIAL, Mopa, Goa upon commissioning of airport on 7th December 2022 and on commencement of
commercial operations from 5th January 2023, submitted the revised MYTP vide letter dated 29th March 2023.
GIAL, Mopa, Goa incorporated adjustments related to various factors such as Revenues, FRoR and Operating
Expenditure in the revised MYTP submitted. This revised MYTP has been taken up by the Authority for
review and evaluation. The MYTP is made available on the Airports Economic Regulatory Authority (AERA)
website.
2.5.3 GIAL, Mopa, Goa was subsequently requested to provide the actual financials for the period ended 31st March
2023.
2.5.4 The Authority has appointed M/s PKF Sridhar and Santhanam LLP (M/s PKF S&S LLP), an independent
consultant, to assess the MYTP submitted by GIAL for Manohar International Airport, Mopa, Goa. M/s PKF
S&S LLP assisted AERA in verifying the data from various supporting documents submitted by GIAL, Mopa,
Goa such as audited Financial Statements, contracts awarded for expenses and revenues (mainly non
aeronautical revenues) for examining the building blocks in tariff determination of COD till 31st March and
First Control Period and also ensuring that the treatment given to it is consistent with the Authority's
methodology, approach etc.
Consultation Paper No. 11/2023-24 Page 22 of 156METHODOLOGY OF TARIFF DETERMINATION OF MANOHAR INTERNATIONAL AIRPORT
2.5.5 The Authority through its Independent Consultant has examined the revised MYTP submitted by GIAL,
Mopa, Goa and verified the data and the projections. The Authority requested various clarifications on the
information shared by GIAL, Mopa, Goa to assess the reasonableness of the proposed capital expenditure,
operating expenditure, non-aeronautical revenue, FRoR, etc., for finalizing this Consultation Paper. GIAL,
Mopa, Goa provided additional information based on clarifications sought and queries raised by the AERA
from time to time. All of this information has been used to finalize this Consultation Paper.
Financing Allowance
2.5.6 The Authority, through its Independent Consultant (M/s PKF S&S LLP), examined the computation and
application of the Financing Allowance to be given to GIAL, Mopa, Goa, as being a Greenfield Airport. The
Consultant has also taken cognizance of the Independent Study report conducted by M/s KITCO in this
regard. Furthermore, the Consultant has done thorough review while computing the financing allowance to
be provided during the first tariff cycle for GIAL, Mopa, Goa. The detailed computation in this regard has
been provided in para 5.3.17.
Related Party Transactions
2.5.7 The Authority through its Independent Consultant conducted an analysis of the tendering procedures
implemented by the Goa International Airport Limited (GIAL, Mopa, Goa) and has reviewed the associated
contract agreements concerning operating expenses and revenues entered with related parties. The
Concession Agreement entered by GIAL, Mopa, Goa details the process to be followed for award of contracts
to related parties as given below:
“5.6.2 For procurement of goods, works or services and for award of leases, licenses, sub-licenses or any
other rights or privilege where the consideration exceeds Rs. 25,00,00,000 (Rupees twenty-five crores)
in any Accounting Year (collectively the “Contracts”), the Concessionaire shall invite offers through
open competitive bidding by means of e-tendering and shall select the awardees in accordance with the
policy specified under Clause 5.6.1. For the avoidance of doubt, the Parties agree that the
Concessionaire may, in its discretion, pre-qualify and short-list the applicants in a fair and transparent
manner for ensuring that only experienced and qualified applicants are finally selected on arm's length
in a manner that is commercially prudent and protects the interests of the Users. The Parties further
agree that the Concessionaire shall not enter into any Related Party Transaction or Contract with any
Related Party except with (a) with the prior written consent of the Authority, which consent shall not
be unreasonably withheld as a reserved item/affirmative action in accordance with the terms of the
Shareholders' Agreement; and (b) such transaction is on arm's length basis and is in compliance with
the provisions of the Companies Act, 2013. The Parties also agree that before granting any consent
hereunder, the Authority shall be entitled to seek such information as it may reasonably require in
relation to the Contract and the Related Party with whom the Contract is proposed to be executed and
in the event the Authority does not approve or reject the proposal within 30 (thirty) days of the date on
which the required information has been provided, it shall be deemed that the Authority has no-
objection to such Contract.
5.6.3 Notwithstanding anything contained contrary elsewhere, the Concessionaire shall adhere to the
following contracting principles in respect of any of the Related Party Transactions:
(a) No shareholder of the Concessionaire, and/or Key Managerial Person that has an interest in the
contract, can be involved in the design of the contract, or the contracting process or decision-making;
Consultation Paper No. 11/2023-24 Page 23 of 156METHODOLOGY OF TARIFF DETERMINATION OF MANOHAR INTERNATIONAL AIRPORT
(b) Where a shareholder of the Concessionaire, Key Managerial Person or any Related Party intends
to tender for the contract, an independent probity auditor must be appointed to review and monitor the
tender to ensure a complete arms' length arrangement. It is clarified that the independent probity
auditor shall not be a Related Party of the Concessionaire or any of its shareholders. Concessionaire
shall agree to the appropriate terms of reference and the selection procedure of the independent probity
auditor as laid down by the Authority; and
(c) The Concessionaire shall constitute an audit committee headed by a nominee of the Authority which
would be responsible for auditing all the Related Party Transactions. The Board of the Concessionaire
shall provide the terms of reference of the audit committee at the time of its constitution. The
Concessionaire shall enter into any Related Party Transaction only after obtaining approval of audit
committee in writing. Any amendment / modification in the terms and conditions of the Related Party
Transaction shall also require prior approval of the audit committee.”
The Authority notes that GIAL, Mopa, Goa has engaged various Related Parties for providing various
services as mentioned in the below:
Table 5: Services provided to GIAL by related parties
S. No. Nature of Service Name of the Related Party Description of Relationship
1 Cargo Operations GMR Airports Limited Holding Company
Celebi Delhi Cargo Terminal Joint Venture of Fellow
2 Ground Handling Services
Management India Private Limited Subsidiary
Master Service Agreement to
3 operate and manage Non- GMR Airports Limited Holding Company
Aeronautical Facilities
4 Project Management Consultancy GMR Airport Developers Limited Fellow Subsidiary
Engineering & Maintenance
5 GMR Airport Developers Limited Fellow Subsidiary
Services (R&M)
6 Security Services Raxa Security Services Limited Fellow Subsidiary
Solar Power on Build, own,
7 GMR Solar Energy Private Limited Companies in the same group
operate and transfer basis
The Authority has sought confirmation from GIAL, Mopa, Goa that due process has been followed as per
appropriate governance practices and that Probity audit reports have been submitted to GoG and approved by
GoG. GIAL, Mopa, Goa has confirmed the same.
The Authority expects that GIAL will comply with the defined requirements of the Concession Agreement
without any deviations and that contracts are awarded with a view to ensure protection of interest of all
stakeholders. This compliance will be reviewed by the Authority during the review and true up to be carried
out in the next control period.
2.5.8 Timeline of various submissions made by GIAL, Mopa, Goa are as given below.
Consultation Paper No. 11/2023-24 Page 24 of 156METHODOLOGY OF TARIFF DETERMINATION OF MANOHAR INTERNATIONAL AIRPORT
Table 6: MYTP submissions by GIAL, Mopa, Goa
Activity Date
MYTP submission 7th January 2022
Initial Requirement List 14th December 2022
Discussion of queries and responses with GIAL, Mopa, Goa 24th January 2023
Data receipt based on additional queries and clarifications 4th February 2023
Updated MYTP submission 29th March 2023
Data Receipt based on queries and responses after analyzing the revised MYTP
April 2023 – May 2023
submission
Audited Financial Statement for the year ended 31st March 2023 26th June 2023
Clarifications for various building blocks June 2023 – August 2023
2.6 Construct of this Consultation Paper
2.6.1 This Consultation Paper has been developed in the following order as explained below. Chapter-wise details
have been summarized as follows:
• The background of the Airport is explained in Chapter 1.
• Methodology of Tariff determination has been detailed in this chapter i.e. Chapter 2.
• Chapter 3 presents the submission of GIAL, Mopa, Goa regarding period from 7th December 2022 to 31st
March 2023 and Authority’s Proposals from COD to 31st March 2023.
• Chapter 4 presents the submissions of GIAL, Mopa, Goa regarding Traffic Projections for the First
Control Period and the Authority’s proposals on the same.
• Chapter 5 includes the submissions of GIAL, Mopa, Goa regarding Capital Expenditure (CAPEX),
Depreciation and RAB for the First Control Period along with the Authority’s detailed examination,
adjustments, rationalization and proposals on the Aeronautical capital expenditure, useful lives and RAB
for the First Control Period.
• Chapter 6-11 includes the submissions of GIAL, Mopa, Goa regarding various building blocks pertaining
to the First Control Period including Fair Rate of Return, Inflation, Operating Expenses, Non-aeronautical
Revenue, Taxation and Quality of Service along with Authority's examination and proposals on each
matter.
• Chapter 12 presents the Aggregate Revenue Requirement as determined by the Authority based on the
proposals for the First Control Period.
• Chapter 13 summarizes Authority’s proposals put forward for consultation.
• In Chapter 14 the Authority invites views of all the stakeholders regarding proposals put forward for tariff
determination for the First Control Period in the Consultation Paper.
• Chapter 15 contains Annexures.
• Chapter 16 contains Appendices.
Consultation Paper No. 11/2023-24 Page 25 of 156METHODOLOGY OF TARIFF DETERMINATION OF MANOHAR INTERNATIONAL AIRPORT
2.7 Study Commissioned by the Authority
2.7.1 The Authority commissioned a study through its Independent Consultant, for detailed analysis of Capital
Expenditure incurred by GIAL, Mopa, Goa.
2.7.2 The Study has carried out a detailed analysis of the Capital Expenditure incurred by GIAL, Mopa, Goa and
provided details of expenditure that can be considered allowable for the purpose of inclusion in RAB for
Tariff Determination.
2.7.3 The recommendations of the independent study conducted by M/s KITCO have been used in this Consultation
Paper. The details of the Study is discussed in Chapter 5 of this Consultation Paper and the study is attached
as Appendix 1 of this Consultation Paper.
Consultation Paper No. 11/2023-24 Page 26 of 156DETERMINATION OF TARIFF FOR THE PERIOD FROM COD (5TH JANUARY) TO 31ST MARCH 2023.
3. DETERMINATION OF TARIFF FOR THE PERIOD FROM COD (5TH JANUARY) TO 31ST
MARCH 2023.
3.1 GIAL’s submissions regarding Tariff for the period from 7th December 2022 to 31st March 2023
3.1.1 GIAL, Mopa, Goa had, together with the projections for the First Control period, submitted the details for the
period from 7th December 2022 till 31st March 2023.
3.1.2 Details for various building blocks submitted by GIAL, Mopa, Goa for the period from 7th December 2022
to 31st March 2023, as part of its Tariff calculations, are as detailed below.
Table 7: Details of building blocks of ARR for the period from 7th December 2022 to 31st March 2023
submitted by GIAL, Mopa, Goa
(Rs. in crores)
Particulars Reference Amount
Average RAB A 3,483.72
Fair Rate of Return B 15.89%
Return on RAB C=A*B*115/365 175.34
Aeronautical Operating Expenditure D 93.74
Aeronautical Depreciation E 49.25
Taxation F 0.00
Aggregate Revenue Requirement G=C+D+E+F 318.34
Non-Aeronautical Revenue H 5.39
Less: 30% of Non-Aeronautical Revenue I=H*30% 1.62
Net Aggregate Revenue Requirement J=G-I 316.72
Discount factor K 1.05
PV of ARR L=J*K 331.87
Aeronautical Revenue
Landing, Parking M 4.02
UDF N 15.44
Others O 0.32
Total of Aeronautical Revenue P=M+N+O 19.78
PV of Aeronautical Revenue Q=P*K 20.73
Shortfall R=L-Q 311.14
3.1.3 GIAL, Mopa, Goa has considered the ARR for the period from 7th December 2022 to 31st March 2023 along
with the estimation of ARR for the First Control Period in its MYTP submission.
3.2 Authority’s examination regarding Tariff for the period from COD (5th January) to 31st March
2023
3.2.1 The Authority has, in the ensuing Chapters, detailed its principles and analysis with respect to different
building blocks. The same principles, to the extent applicable, have been used for computing the ARR and
shortfall for the period from COD to 31st March 2023 also.
Consultation Paper No. 11/2023-24 Page 27 of 156DETERMINATION OF TARIFF FOR THE PERIOD FROM COD (5TH JANUARY) TO 31ST MARCH 2023.
3.2.2 The Authority had sought financial statements for the year ended 31st March 2023. Audited Financial
Statements have been provided by GIAL, Mopa, Goa. The Authority proposes to consider the same as the
basis for the computation for the period from COD to 31st March 2023.
Traffic
3.2.3 The Authority has considered the actual traffic for Manohar International Airport, Mopa, Goa available from
the AAI website for the period from COD to 31st March 2023 which is as presented below:
Table 8: Traffic for Period from COD to 31st March 2023
Domestic Passenger Traffic
Particulars (in Nos) Jan-23 Feb-23 Mar-23 Total
Manohar International Airport, Mopa, Goa 154,422 229,431 280,307 664,160
Domestic ATM
Particulars (in Nos) Jan-23 Feb-23 Mar-23 Total
Manohar International Airport, Mopa, Goa 1,108 1,646 2,087 4,841
3.2.4 The Authority notes that the traffic volume in Manohar International Airport, Mopa, Goa has been steadily
increasing on a monthly basis.
Capital Expenditure, Regulatory Asset Base and Depreciation
3.2.5 The Authority notes that the Airport was commissioned on 7th December 2022 and commenced its
commercial operations on 5th January 2023.
3.2.6 The Authority had commissioned an Independent Study for evaluation of Capital Expenditure. Details of the
study and its findings are elaborated in para 5.3.4. Based on the details of cost evaluation as detailed in para
5.3.4 and the adjustments proposed to be made by the Authority, the Authority has tabulated the amount
proposed to be added to Regulatory Asset Base for the Period from COD to 31st March 2023 and First Control
Period in Table 68.
3.2.7 The Authority notes from MYTP submission that Phase I capital expenditure proposed by GIAL, Mopa, Goa
has been considered to be fully capitalized in FY 2022-23. The Authority, while examining the Audited
Financial Statements submitted by GIAL, Mopa, Goa for March 2023 and certificate from statutory auditors,
notes that the amount capitalized in FY 2022-23 for Phase I is Rs. 2,742.20 crores as against Rs. 3,375.29
crores (proposed by GIAL, Mopa, Goa for Phase I excluding FA and including IDC) which is 81.24% of the
total Phase-I cost being capitalized in the books.
3.2.8 Based on the above, the Authority proposes to consider the ratio of actual to total capital expenditure of GIAL,
Mopa, Goa as base for capitalizing the cost proposed by the Authority for Phase I in FY 2022-23 and the
remaining cost of Phase-I to be capitalized in the FY 2023-24. Accordingly, 81.24% of the total Capital
Expenditure (Table 63) for Phase 1 is capitalized in FY 2022-23 as shown in the table below:
Consultation Paper No. 11/2023-24 Page 28 of 156DETERMINATION OF TARIFF FOR THE PERIOD FROM COD (5TH JANUARY) TO 31ST MARCH 2023.
Table 9: Computation of Addition to RAB for the period from COD to 31st March 2023 by the
Authority
(Rs. in crores)
Particulars Reference Amount
3.2.9 Total addition for Phase 1 as per Authority (Table 63) A 3,225.79
Total addition for Phase 1 as per GIAL, Mopa, Goa (Table 32) B 3,603.29
Add: Interest during construction (IDC) C 220.00
Less: Financing Allowance (FA) D 448.00
Total Capitalization to be in financial statement E = B+C-D 3,375.29
Addition to Gross Block as per Financial Statement for FY 2022-23 F 2,742.20
% of Capitalization done G = F/E 81.24%
Proportionate addition to RAB for FY 2022-23 by Authority H = A * G 2,620.74
3.2.10 The Authority notes that GIAL, Mopa, Goa has undertaken development activities on the land provided by
the GoG on lease for the construction of Manohar International Airport, Mopa, Goa. These activities have
been done across the area of land, to prepare the same for further construction activities.
The Authority notes the details mentioned in the Order 35/2017-18 dated 12th January 2018 as presented
below:
“Land development activities in relation to Airports comprise of preparing and leveling the land to be fit for
further development activities relating to Airside works, Buildings, Roads etc. Land development activities
carried out before further construction works are done, are permanent in nature and do not need to be altered
/ changed in any time in future and do not have a determinate useful life. Where Land is owned by the
company, these are generally to be treated as part of the Land value and is not to be depreciated. In cases
where the development activities are carried out on land which is leased to the Airport Operator, the
development charges are generally to be charged off over the period of the lease rentals.
Land Development related costs should be identified and accounted as a separate line item under a sub-head
of “Land Development” cost. If the land is leased to the Airport Operator, Land development cost shall be
depreciated over the balance period of lease term.”
As per Annexure 1 of Order 35/2017-18 dated 12th January 2018, Land Development Cost incurred on Leased
land is to be amortized over the lease period. The Authority notes that this practice has also been followed in
Authority’s Order No. 11/2021-22 dated 28th August 2021 on determination of Aeronautical tariff for third
control period for BIAL.
3.2.11 Accordingly, the cost of Rs.792.73 crores incurred on Land Development (including loading of FA and other
indirect cost) is proposed to be considered as a separate line item which will be depreciated over the balance
lease period of 36.5 years. The balance lease period has been computed as given below.
Table 10: Useful Life to be considered for Land Development
Particulars Reference Date/Year
Appointed date as per Concession Agreement (para 1.2.2) A 4-Sep-17
Completion of 40 years lease period (para 1.2.2) B 3-Sep-57
Consultation Paper No. 11/2023-24 Page 29 of 156DETERMINATION OF TARIFF FOR THE PERIOD FROM COD (5TH JANUARY) TO 31ST MARCH 2023.
Particulars Reference Date/Year
Extended completion of Concession period i.e. 40 years C 30-May-59*
Date of capitalization (para 3.2.5) D 7-Dec-22
Lease period for Depreciation (In years) (Useful life) E= (C - D+1)/365 36.50
Depreciation rate 2.74%
*Upon seeking clarification on the extended timeline, GIAL, Mopa, Goa submitted that Government of Goa (GoG) decided to extend
the Concession Period for the Manohar International Airport, Mopa, Goa. This extension was granted due to the delays in
construction and development activities caused by the adverse impact of the Covid-19 pandemic. The original Concession Period,
which was supposed to end on 3rd September 2057, has now been extended, and the airport's operations under the concession will
continue until 30th May 2059.
3.2.12 Based on the above, the category wise capital additions proposed to be considered for FY 2022-23 is as
presented below:
Table 11: Asset Category wise additions for the period from COD to 31st March 2023 proposed by the
Authority
(Rs. in crores)
Particulars Amount
Building 760.63
Roads 172.84
Runway 505.19
Plant & Machinery 300.49
Apron 78.79
Furniture & Fixtures other than trolley 10.07
Land Development (Refer para 3.2.10 for explanation on Land Development) 792.73
Total 2,620.74
3.2.13 The Authority proposes to use the allocation ratio for assets as detailed in para 5.4.6 and 5.4.8 for the additions
to RAB. Accordingly, the total Aeronautical addition to RAB for FY 2022-23 is computed to be Rs. 2,507.92
crores (Refer Table 68).
3.2.14 The Authority notes that GIAL, Mopa, Goa has submitted that the detailed Fixed Asset Register has not yet
been prepared and this could have an impact on the depreciation values, together with Authority’s proposal
for considering Land Development cost as a separate line item. The Authority proposes to consider the
depreciation as per the financial statement submitted by GIAL, Mopa, Goa, which will be reviewed at the
time of determination of aeronautical tariff for the second control period.
3.2.15 Based on the above, the Regulatory Asset Base for FY 2022-23 is computed as follows:
Table 12: Regulatory Asset Base for the period from COD to 31st March 2023 computed by the
Authority
(Rs. in crores)
Particulars Reference Amount
Opening RAB A -
Additions to RAB B 2,507.92
Depreciation C 31.49
Closing RAB D = A+B-C 2,476.43
Average RAB E = (A+D)/2 1,238.21
Consultation Paper No. 11/2023-24 Page 30 of 156DETERMINATION OF TARIFF FOR THE PERIOD FROM COD (5TH JANUARY) TO 31ST MARCH 2023.
3.2.16 The Authority notes that the Regulatory Asset Base has been commissioned for a period of 115 days in FY
2022-23. Accordingly, the Authority proposes to provide a return for 115 days for FY 2022-23 on the closing
RAB.
Fair Rate of Return
3.2.17 The Authority has detailed its analysis for estimation of Fair Rate of Return in Chapter 6. The Authority
proposes to consider the same Fair Rate of return calculated and considered for the First Control Period (refer
Table 77) i.e. 12.21% for the period from COD to 31st March 2023 also.
Operating Expenditure
3.2.18 The Authority notes from the financial statement of March 2023 that GIAL, Mopa, Goa has incurred a total
Expenditure of Rs. 55.79 crores for the period from COD to 31st March 2023 as against the estimated
expenditure of Rs. 93.74 crores submitted by it in MYTP.
3.2.19 Further, the Authority notes that GIAL, Mopa, Goa has prepared Financial Statements following Indian
Accounting Standards (IND AS)1 on 31st March 2023. Accordingly, certain notional entries have been passed
relating to Finance cost, Security deposit etc. to ensure IND AS compliance on security deposit and lease.
The Authority proposes to exclude such notional IND AS adjustments from Operating expenditure for the
purpose of true up exercise.
3.2.20 The Authority has explained its analysis on allocation ratios for Aeronautical expenses in para 8.2.1 (I). The
Authority proposes to use the same and accordingly consider Rs. 55.43 crores as Aeronautical expenses for
the period from COD to 31st March 2023 as presented below:
Table 13: Operating Expenditure for the period from COD to 31st March 2023 proposed by the
Authority
(Rs. in crores)
Particulars Reference Amount
Operating Expenditure as per Financial Statement (Refer Annexure 3) A 55.79
IND AS adjustment (Lease rentals on equipment was capitalized as B
Asset under IND AS, this has been treated as Operating expenditure) 2.99
(Refer Annexure 3)
Amount proposed to be considered by the Authority C = A+B 58.78
Impact of Allocation Ratio D 3.35
Aeronautical Opex E = C-D 55.43
Non-Aeronautical Revenue
3.2.21 The Authority notes that GIAL, Mopa, Goa has earned Rs. 4.38 crores as Non-Aeronautical Revenue as per
the break-up of Actual Revenues provided by GIAL, Mopa, Goa.
3.2.22 The Authority noted in para 3.2.19 that GIAL, Mopa, Goa has prepared IND AS Financial Statements as on
31st March 2023. Accordingly, certain notional entries have been passed relating to Fair valuation gain from
security deposits etc. The Authority proposes to exclude such notional IND AS adjustments from Non-
Aeronautical Revenues.
________________________________________________________________________________________
1 Indian Accounting Standards (IND AS) as notified by Ministry of Company Affairs under Companies (Indian Accounting Standard (IND AS) Rules 2015
Consultation Paper No. 11/2023-24 Page 31 of 156DETERMINATION OF TARIFF FOR THE PERIOD FROM COD (5TH JANUARY) TO 31ST MARCH 2023.
3.2.23 The Authority has detailed its proposal to consider the rental income earned from Aeronautical Service
providers as Aeronautical, in para 9.2.23. Considering the same, the recomputed Non-Aeronautical Revenue
for FY 2022-23 proposed to be considered by the Authority is as follows:
Table 14: Non-Aeronautical Revenue for the period from COD to 31st March 2023 proposed by the
Authority
(Rs. in crores)
Particulars Reference Amount
Non-Aeronautical Revenue as per break-up provided by GIAL, Mopa, Goa A
4.38
(Refer Annexure 4)
IND AS Adjustment (Notional Income on Fair value of Security Deposit as per B
0.86
IND AS) (Refer Annexure 4)
Lease rentals from Airlines and Aeronautical concessionaires* C 1.05
Non-Aeronautical Revenue proposed to be considered by Authority D = A+B-C 4.19
*refer para 9.2.23 for explanation
Taxation
3.2.24 The Authority has noted that GIAL, Mopa, Goa has incurred losses in FY 22-23 and hence no tax is due to
be paid by it. The carry forward loss benefits available, which can be utilized to set off against future profit
will be considered appropriately in the tariff determination for the First Control Period.
3.2.25 The Authority had asked GIAL, Mopa, Goa to provide details of Income tax loss carry forward already
available as of 1st April 2022. GIAL, Mopa, Goa has submitted that the tax loss carried forward and available
as of 1st April 2022 is Rs. 2.80 crores as per the Income Tax Returns.
3.2.26 Based on the workings below, there is no Aeronautical Taxation for FY 2022-23. Accordingly, the Authority
does not propose to consider any Taxation payment in the estimation of ARR.
Table 15: Aeronautical taxes for the period from COD to 31st March 2023 proposed by the Authority
(Rs. in crores)
Particulars Reference Amount
Aero Revenue (Table 17) A 20.74
Aero Opex (Table 13) B 55.43
Depreciation as per Income Tax * C 132.34
Interest cost estimate** D 45.85
Aero PBT E = A – (B+C+D) (212.88)
B/f loss of previous years (para 3.2.25) F (2.80)
Losses Added/Utilized G=E (212.88)
C/f losses H=F+G (215.68)
Tax rate I 25.17%
Income Tax J -
*Computed using Written Down Value (WDV) method considering useful lives as per IT Act
**Interest Cost estimated are based on the actuals from the audited financial statement proportionate to Gross Block Ratio for
Aeronautical assets
Consultation Paper No. 11/2023-24 Page 32 of 156DETERMINATION OF TARIFF FOR THE PERIOD FROM COD (5TH JANUARY) TO 31ST MARCH 2023.
Aeronautical Revenues
3.2.27 The Authority notes from the break-up of Revenues provided by GIAL, Mopa, Goa that it has earned the
following Aeronautical Revenue from COD (5th January 2023) till 31st March 2023.
Table 16: Aeronautical Revenue for the period from 7th December 2022 to 31st March 2023 proposed
by GIAL, Mopa, Goa
(Rs. in crores)
Particulars Reference Amount
Landing and parking charges A 3.33
User Development Fee (UDF) B 15.07
Fuel farm C 1.39
Ground handling D 1.37
Cargo E 0.29
Total Aeronautical Revenue F= A+B+C+D+E 21.44
3.2.28 The Authority noted in para 3.2.19 that GIAL, Mopa, Goa has prepared IND AS Financial Statements as on
31st March 2023. Accordingly, certain notional entries have been passed relating to Fair valuation gain from
security deposits etc. The Authority proposes to exclude such notional IND AS adjustments from
Aeronautical Revenues.
3.2.29 The Authority further proposes to consider lease rentals from Airlines and Aeronautical concessionaires as
Aeronautical (refer Table 14). Considering the same, the Aeronautical Revenue proposed to be considered by
the Authority is as given below:
Table 17: Aeronautical Revenue for the period from COD to 31st March 2023 proposed by the
Authority
(Rs. in crores)
Particulars Reference Amount
Aeronautical Revenue as per GIAL, Mopa, Goa (Table 16) A 21.44
IND AS Adjustment (Notional Income on Fair value of Security
B 1.75
Deposit as per IND AS)
Lease rentals from Airlines and Aeronautical concessionaires C 1.05
Aeronautical Revenue proposed to be considered by Authority
D=A-B+C 20.74
(refer Annexure 4)
Aggregate Revenue Requirement and Shortfall
3.2.30 GIAL, Mopa, Goa had submitted a shortfall of Rs. 311.34 Crores for the period from 7th December 2022 to
31st March 2023. The Authority has recomputed the Aggregate Revenue Requirement, based on the
evaluation of the individual building blocks detailed above, as below, which the Authority proposes to
consider in the determination of ARR for the first control period.
Consultation Paper No. 11/2023-24 Page 33 of 156DETERMINATION OF TARIFF FOR THE PERIOD FROM COD (5TH JANUARY) TO 31ST MARCH 2023.
Table 18: ARR and shortfall for the period from COD to 31st March 2023 proposed by the Authority
(Rs. in crores)
Particulars Ref Amount
Closing RAB* (Table 12) A 2,476.43
Fair Rate of Return (para 3.2.17) B 12.21%
Return on RAB for 115 days C=A*B*115/365 95.27
Aeronautical Operating Expenditure (Table 13) D 55.43
Aeronautical Depreciation (Table 12) E 31.49
Taxation F 0
Aggregate Revenue Requirement G=C+D+E+F 182.19
Non-Aeronautical Revenue (Table 14) H 4.19
Less: 30% of Non-Aeronautical Revenue I=H*30% 1.26
Net Aggregate Revenue Requirement J=G-I 180.93
Less: Aeronautical Revenues (Table 17) K 20.74
Shortfall L=J-K 160.19
Discount factor (@ 12.21%) M 1.12
PV of Under-recovery as on 31st March 2024 N=L*M 179.75
* Being initial commissioning, to calculate the return on RAB (Regulatory Asset Base), the approach of using the closing RAB has
been adopted instead of the average RAB. The assets were put to use on 7th December 2022 within the financial year 2022-23. The
return is adjusted for 115 days, corresponding to the period from the commissioning of the assets on 7th December 2022.
3.3 Authority’s proposals regarding Tariff for the period from COD to 31st March 2023
Based on the material before it and its examination, the Authority proposes the following with regard to tariff
for the period from COD to 31st March 2023 for Manohar International Airport, Mopa, Goa:
3.3.1 To consider Traffic as per Table 8
3.3.2 To consider RAB and depreciation as per Table 12.
3.3.3 To consider FRoR as per para 3.2.17.
3.3.4 To consider Aeronautical O&M expenses as per Table 13.
3.3.5 To consider Non-aeronautical revenue as per Table 14.
3.3.6 To consider the Aeronautical tax as per Table 15.
3.3.7 To consider Aeronautical revenue as per Table 17.
3.3.8 To consider under recovery of Rs. 179.75 crores as per Table 18 and adjust the same in the ARR for the First
Control Period.
3.3.9 To true up the additions to RAB and depreciation for the year based on the total completed cost for Phase I
and the Fixed Asset Register to be submitted by GIAL in the next control period.
Consultation Paper No. 11/2023-24 Page 34 of 156TRAFFIC FOR THE FIRST CONTROL PERIOD
4. TRAFFIC FOR THE FIRST CONTROL PERIOD
4.1 GIAL’s submissions regarding Traffic for the First Control Period
4.1.1 GIAL, Mopa, Goa has appointed M/s CRISIL, an independent agency to study the traffic at Manohar
International Airport, Mopa, Goa. M/s CRISIL has undertaken market scan, historical trend analysis,
assessment of ongoing COVID condition and economic scenario to forecast traffic for Manohar International
Airport, Mopa, Goa for the First Control Period.
4.1.2 Basis of determination of traffic as per M/s CRISIL is as detailed below:
• M/s CRISIL has predicted the passenger traffic movement for domestic and international flights at Goa
airport using an econometric model approach.
• For domestic passenger forecasting, the Consolidated Gross Domestic Product (GDP) variable was used,
while the Blended GDP variable was used for international passenger forecasting.
• Regression analysis using the Ordinary Least Square method was conducted to arrive at the results, which
showed that for every 1% increase in income level, the domestic and international air passenger traffic
demand at the Goa airport will grow by 2% and 1.23% respectively. The data was corrected using a
correction factor of 2.24% to reverse the impact of COVID-19 on air passenger movement.
4.1.3 Traffic forecast was revised by GIAL, Mopa, Goa in the MYTP submission made on 29th March 2023.
Forecast of traffic along with the market share in the state of Goa for Manohar International Airport, Mopa,
Goa submitted by GIAL, Mopa, Goa has been presented below:
Table 19: Traffic for the First Control Period submitted by GIAL, Mopa, Goa for Manohar
International Airport, Mopa, Goa
Passenger (In Mn) ATM (in Nos) Cargo (in MT)
Year
Domestic Int’l Total Domestic Int’l Total Domestic Int’l Total
Traffic
FY 24 6.09 0.79 6.88 40,620 4,798 45,418 5,397 5,814 11,211
FY 25 6.91 0.94 7.85 46,079 5,668 51,747 7,058 8,592 15,650
FY 26 8.62 0.98 9.6 57,499 5,951 63,450 7,806 9,384 17,190
FY 27 10.67 1.12 11.79 71,156 6,784 77,940 9,560 14,742 24,302
FY 28 12.11 1.21 13.32 80,719 7,327 88,046 10,474 15,116 25,590
Total
(FY24 to 44.40 5.04 49.44 296,073 30,528 326,601 40,295 53,648 93,943
FY28)
Growth (%)
FY 25* 13.40% 18.99% 14.10% 13.44% 18.13% 13.94% 30.78% 47.78% 39.60%
FY 26 24.77% 4.26% 22.29% 24.78% 4.99% 22.62% 10.60% 9.22% 9.84%
FY 27 23.80% 14.29% 22.81% 23.75% 14.00% 22.84% 22.47% 57.10% 41.37%
FY 28 13.49% 8.04% 12.98% 13.44% 8.00% 12.97% 9.56% 2.54% 5.30%
*Growth rates are computed based on FY 2023-24
Consultation Paper No. 11/2023-24 Page 35 of 156TRAFFIC FOR THE FIRST CONTROL PERIOD
Table 20: GIAL, Mopa, Goa’s submission of market share estimate in the state of Goa for Manohar
International Airport, Mopa, Goa
Particulars FY 24 FY 25 FY 26 FY 27 FY 28
Domestic 50% 50% 55% 60% 60%
International 80% 90% 90% 95% 95%
4.2 Authority’s examination regarding Traffic for the First Control Period
4.2.1 The Authority has taken note of the fact that the state of Goa has the privilege of having two airports, which
are competing with each other to meet the increasing demand of tourism in the state. The traffic projection
for Dabolim Goa has been decided by the Authority in clause 4.5.4 of Order No. 04/2022-23 for the Third
Control Period, after taking into consideration the then impending airport’s (Manohar International Airport,
Mopa, Goa) expected traffic capacity and demand. The share of traffic as decided by the Authority in Dabolim
Goa is presented below:
Table 21: Share of Passenger Traffic at Dabolim Airport as decided by the Authority
Particulars (in Mn) FY 24 FY 25 FY 26 Total
Passengers decided by the Authority for Dabolim Airport 8.02 9.36 10.80 28.18
% of Passengers for Dabolim Airport 61% 63% 64% -
% Remaining passengers in Manohar International Airport, Mopa, Goa 39% 37% 36% -
4.2.2 Based on M/s CRISIL's Traffic Forecast report issued in December 2021, the total passenger traffic in Goa is
predicted to grow to 21 MPPA by FY 2027-28, which will be handled together by Dabolim Airport and
Manohar International Airport, Mopa, Goa.
Passenger Traffic
4.2.3 The Authority notes that GIAL, Mopa, Goa has only considered billable domestic passengers, excluding 2%
of domestic passenger traffic. The Authority notes that Government of India has allowed exemption of UDF
to certain categories of passengers through Order No. AIC 14/ 2019 read with AIC 20/ 2019. GIAL, Mopa,
Goa cannot claim any passthrough regarding UDF on such categories and this is followed by AERA across
at all Major Airports. Therefore, there is no reason to consider the billable PAX traffic separately, as the
Authority follows a consistent approach across all Major Airports, that naturally accounts for such
considerations while projecting aeronautical revenues. The Authority notes that if this has been considered
differently in any of the recent tariff orders, the same will be changed at the time of true up.
4.2.4 The Authority has reviewed the estimated Compounded Annual Growth Rate (CAGR) of Dabolim Airport
in Goa, for both domestic and international passenger traffic. The data indicates that for the past 4 years (FY
2015-16 to FY 2018-19), the domestic passenger traffic grew at a CAGR of 12.90%, while for the past 8
years (FY 2011-12 to FY 2018-19), it grew at a CAGR of 12.74%. Similarly, for international passenger
traffic, the CAGR for the past 4 years was 4.89%, and for the past 8 years, it was 3.84%.
Consultation Paper No. 11/2023-24 Page 36 of 156TRAFFIC FOR THE FIRST CONTROL PERIOD
Table 22: 4-Year and 8-Year CAGR of Passenger Traffic at Dabolim Airport
Particulars (in %) 4 Year (FY16-FY19) 8 Year (FY12-FY19)
Goa Dabolim
Domestic Pax 12.90% 12.74%
International Pax 4.89% 3.84%
4.2.5 In order to project the air traffic demand for Goa as a whole, the Authority analyzed various factors such as
the new Manohar International Airport, Mopa, Goa and the impact of the COVID-19 pandemic. After
considering these factors, the Authority concluded that using a single growth factor such as Compound
Annual Growth Rate (CAGR) would not be appropriate to project the traffic for Goa as a whole.
4.2.6 The Authority reviewed the study conducted by M/s CRISIL for Manohar International Airport, Mopa, Goa
traffic. The study employed an econometric model to estimate the demand for air traffic among passengers
in the state of Goa. A new variable, named "consolidated GDP," has been developed for this purpose which
is the sum of states’ highest share of passengers at the Goa airport (Gujarat, Maharashtra, Delhi, Telangana,
Karnataka, Andhra Pradesh, and Goa). The consolidated GDP is kept as the explanatory variable and the
domestic passenger demand at the Goa airports as the dependent variable.
4.2.7 Based on this study, growth of the consolidated Gross Domestic Product (GDP) over the forecast period and
the consolidated GDP elasticity of passenger demand has been considered as the growth factor for projecting
passenger traffic. The growth factor calculated by M/s CRISIL for domestic passenger traffic is 13.40% and
for international passenger traffic is 5% from FY 2024-25 to FY 2025-26 and thereafter 8.00% for the further
years of the Control Period as presented below.
Table 23: Air Passenger Traffic growth rates submitted by GIAL, Mopa, Goa
Particulars (in %) FY24 FY25 FY26 FY27 FY28
Domestic 13.40% 13.40% 13.40% 13.40% 13.40%
International 5.00% 5.00% 5.00% 8.00% 8.00%
4.2.8 The Authority notes that this is an uncommon situation of 2 airports within the same vicinity which may
attract passengers from nearby areas including adjacent states. The Authority proposes to use, for the current
estimation, the growth of consolidated GDP and its elasticity with passenger demand as the growth factor, as
calculated by M/s CRISIL as an indicator in its estimation of traffic for Manohar International Airport, Mopa,
Goa.
4.2.9 The Authority compared the actual traffic achieved during the FY 2022-23 with that of the corresponding
period in FY 2019-20 (Pre-COVID period) and noted that the actual domestic passenger and ATM traffic has
already surpassed the Pre-COVID levels of FY 2019-20. The details of the same are as follows:
Consultation Paper No. 11/2023-24 Page 37 of 156TRAFFIC FOR THE FIRST CONTROL PERIOD
Table 24: Actual Domestic Passenger and ATM traffic for FY 2019-20 (Pre-COVID period) and FY
2022-23 for Dabolim and Manohar International Airport, Mopa, Goa
FY 20 FY 23
Manohar
Manohar International
Particulars International Total Total
Dabolim Dabolim Airport, Mopa, Goa (5th
(in Nos) Airport, Domestic Domestic
Jan- 31st March 2023)
Mopa, Goa
Passenger 7,651,362 - 7,651,362 7,891,983 664,160 8,556,143
ATM 53,636 - 53,636 53,889 4,841 58,730
4.2.10 The government has clarified that the commissioning of the new greenfield International Airport at Mopa, in
North Goa will not result in the shutdown of the existing airport at Dabolim in South Goa. Instead, both
airports will co-exist and handle air traffic in the state.
4.2.11 As the restrictions of the COVID-19 pandemic are removed and tourism increases, it is expected that the air
traffic demand in Goa will also increase.
4.2.12 The Authority after observing the actual passenger traffic for FY 2022-23, notes that the traffic at Goa is
increasing. The traffic forecasts provided by M/s CRISIL in their studies align with the views of the Authority.
Therefore, the Authority proposes to consider the traffic for Goa as a whole, as suggested by the M/s CRISIL
study:
Table 25: Air Passenger traffic as proposed by the Authority for the state of Goa
Particulars (in Mn) FY 24 FY 25 FY 26 FY 27 FY 28 Total
Domestic 12.19 13.82 15.68 17.79 20.18 79.66
International 0.99 1.04 1.09 1.18 1.27 5.57
Total 13.18 14.86 16.77 18.97 21.45 85.23
4.2.13 Due to existing operational restrictions at Dabolim airport, such as no night parking availability and
operational restrictions during the daytime, it is expected that domestic airlines will initially shift to Manohar
International Airport, Mopa, Goa. The Authority notes that the % share of Manohar International Airport,
Mopa, Goa projected by M/s CRISIL report appear reasonable considering the actual domestic traffic from
January 2023 (Commencement Operation Date) to May 2023 of Manohar International Airport, Mopa, Goa.
It can be observed that Manohar International Airport, Mopa, Goa has achieved approximately 35% of market
share in domestic traffic for both passenger and ATM.
Table 26: Actual Traffic for Dabolim and Manohar International Airport, Mopa, Goa
Domestic Passenger Traffic
Particulars (in Nos) Jan-23 Feb-23 Mar-23 Total Apr-23 May-23 Total
Dabolim Airport 782,573 673,740 691,960 2,148,273 641,551 585,182 1,226,733
Manohar International
154,422 229,431 280,307 664,160 332,695 335,265 667,960
Airport, Mopa, Goa
Total 936,995 903,171 972,267 2,812,433 974,246 920,447 1,894,693
Market Share (PAX)
Consultation Paper No. 11/2023-24 Page 38 of 156TRAFFIC FOR THE FIRST CONTROL PERIOD
Domestic Passenger Traffic
Dabolim Airport 83.52% 74.60% 71.17% 76.38% 65.85% 63.58% 64.75%
Manohar International
16.48% 25.40% 28.83% 23.62% 34.15% 36.42% 35.25%
Airport, Mopa, Goa
Total 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Domestic ATM
Particulars (in Nos) Jan-23 Feb-23 Mar-23 Total Apr-23 May-23 Total
Dabolim Airport 5,095 4,259 4,530 13,884 4,204 3,716 7,920
Manohar International
1,108 1,646 2,087 4,841 2,298 2,200 4,498
Airport, Mopa, Goa
Total 6,203 5,905 6,617 18,725 6,502 5,916 12,418
Market Share (ATM)
Dabolim Airport 82.14% 72.13% 68.46% 74.15% 64.66% 62.81% 63.78%
Manohar International
17.86% 27.87% 31.54% 25.85% 35.34% 37.19% 36.22%
Airport, Mopa, Goa
Total 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
4.2.14 According to the factors considered by the Independent consultant appointed by the Authority for review of
the Capital Expenditure, M/s KITCO, the latest statistics from the AAI indicate that the Manohar International
Airport, Mopa, Goa has shown significant growth in domestic passenger traffic. In January 2023, Manohar
International Airport, Mopa, Goa recorded 1.54 lakh passengers (compared to 7.83 lakh at Dabolim), which
increased to 2.29 lakh in February 2023 (compared to 6.74 lakh at Dabolim), and further rose to 2.80 lakh in
March 2023 (compared to 6.92 lakh at Dabolim). This indicates that with the presence of the new airport at
Mopa, Goa has created additional demand and attracted new passengers, rather than relying solely on
passengers shifting from Dabolim. Consequently, both airports operating simultaneously has resulted in
increased domestic passenger numbers compared to the previous year. These trends suggest that the air
passenger capacity of the state is on track to meet the forecasted figures submitted by M/s CRISIL.
4.2.15 Considering the views presented by M/s KITCO and based on its own analysis, the Authority proposes to
adopt the market share for domestic traffic at Manohar International Airport, Mopa, Goa as estimated by the
M/s CRISIL report submitted by GIAL, Mopa, Goa. The shift in domestic passengers from Dabolim to
Manohar International Airport, Mopa, Goa is expected to enhance the operational efficiency of both airports,
enabling them to handle air traffic more effectively.
4.2.16 Most international passengers, except chartered flights, are expected to shift to the new Manohar International
Airport, Mopa, Goa by FY 2025-26, as the majority of tourist destinations in Goa are located in the vicinity
of the new airport in the Northern part of the state. Dabolim airport is expected to handle mainly domestic
passengers and chartered flights in FY 2025-26.
4.2.17 Based on the above proposals, the % share of passenger traffic proposed to be considered for Manohar
International Airport, Mopa, Goa is presented below:
Consultation Paper No. 11/2023-24 Page 39 of 156TRAFFIC FOR THE FIRST CONTROL PERIOD
Table 27: Percentage share of total Goa passenger traffic to be handled by Manohar International
Airport, Mopa, Goa
Particulars (in %) FY 24 FY 25 FY 26 FY 27 FY 28
Domestic
Proposed by GIAL, Mopa, Goa 50% 50% 55% 60% 60%
Proposed by Authority for Manohar International Airport,
50% 50% 55% 60% 60%
Mopa, Goa
International
Proposed by GIAL, Mopa, Goa 80% 90% 90% 95% 95%
Proposed by Authority for Manohar International Airport,
80% 90% 90% 95% 95%
Mopa, Goa
4.2.18 After analyzing the percentage share and growth rate, the Authority proposes to adopt the traffic projections
put forth by GIAL, Mopa, Goa for Manohar International Airport, Mopa, Goa. The proposed traffic figures
are as follows:
Table 28: Passenger traffic proposed by the Authority to be handled at Manohar International Airport,
Mopa, Goa
Particulars (in Mn) FY 24 FY 25 FY 26 FY 27 FY 28 Total
Domestic 6.09 6.91 8.62 10.67 12.11 44.40
International 0.79 0.94 0.98 1.12 1.21 5.04
Total 6.88 7.85 9.6 11.79 13.32 49.44
4.2.19 In summary, the new Manohar International Airport, Mopa, Goa in Goa is expected to gradually attract a
significant portion of passenger traffic, particularly international passengers, due to its location near popular
tourist destinations. The existing Dabolim airport will continue to handle domestic passengers and chartered
flights and both airports will co-exist and handle air traffic in the state.
ATM Traffic
4.2.20 According to estimates provided by GIAL, Mopa, Goa, the number of passengers per ATM (Air Traffic
Movement) at Manohar International Airport, Mopa, Goa is expected to be 150 for the domestic segment and
165 for the international segment. This is because Manohar International Airport, Mopa, Goa is expected to
mostly handle Code C Aircrafts for domestic flights, which are generally designed to handle up to 150
passengers. For international travel, a mix of Code C and Code E aircraft will be used, with an average
capacity of 165 passengers.
4.2.21 The Authority estimates that Manohar International Airport, Mopa, Goa will experience growth and
improvement over time, in contrast to other airports where passenger numbers tend to remain stagnant due to
their operational maturity. As a new airport, it is expected that there will be an increase in the passenger load
factor in the subsequent control periods.
4.2.22 As more airlines start operating at Manohar International Airport, Mopa, Goa, the demand for air travel is
likely to increase, resulting in more passengers per ATM. Furthermore, improvements in airport infrastructure
and services can help attract more passengers and airlines, further increasing the number of passengers per
ATM.
Consultation Paper No. 11/2023-24 Page 40 of 156TRAFFIC FOR THE FIRST CONTROL PERIOD
4.2.23 In line with the proposal to consider the passenger traffic submitted by GIAL, for Manohar International
Airport, Mopa, Goa, the Authority also proposes to consider the ATM traffic as suggested by GIAL, Mopa,
Goa. It is anticipated that the number of passengers per ATM will increase gradually as the airport becomes
more established and the demand for air travel continue to grow.
Table 29: ATM as proposed by the Authority for the First Control Period
Particulars (in Nos) FY 24 FY 25 FY 26 FY 27 FY 28 Total
Domestic 40,620 46,079 57,499 71,156 80,719 296,073
International 4,798 5,668 5,951 6,784 7,327 30,528
Total 45,418 51,747 63,450 77,940 88,046 326,601
Cargo Freight
4.2.24 The Authority notes that GIAL, Mopa, Goa, through a bidding process, has appointed GMR Airports Limited
(GAL) to provide cargo handling services at the upcoming Manohar International Airport, Mopa, Goa in Goa.
GIAL, Mopa, Goa has entered into a license agreement with its holding company GAL, on 16th November
2021, granting them the right to design, build, finance, operate, maintain, and transfer the cargo facilities for
an initial period of 20 years through a tendering process. GIAL, Mopa, Goa has confirmed that the contract
was awarded in accordance with the defined process mentioned in the Concession Agreement, and that the
contract received approval from the GOG (Government of Goa) after undergoing a probity check, including
an assessment of related party transactions.
4.2.25 Under the license agreement, the licensee (GAL) will pay a land license fee to GIAL, Mopa, Goa, which will
increase on a yearly basis based on the notified Consumer Price Index (CPI). Additionally, the licensee will
share 15.30% of its gross revenue with GIAL, Mopa, Goa during the license period.
4.2.26 Currently, the Dabolim airport in Goa does not have adequate cargo handling facilities, limiting the freight
traffic to between 4,000 MT to 5,000 MT per annum. As the economy of Goa grows, the demand for cargo
movement is increasing, which cannot be solely handled by the Dabolim airport.
4.2.27 M/s CRISIL study on freight traffic projections shows that the cargo movement demand in Goa is currently
being spilled over to nearby major airports like Mumbai and Bangalore due to the lack of dedicated cargo
handling infrastructure at the Dabolim airport. Almost 50,000 MT of international cargo comprising of
pharmaceutical products is spilled over to Mumbai Airport as well as other international airports. Similarly,
almost 30,000 MT of domestic cargo is moved via road to other airports due to lack of infrastructure and
space availability at current airport in Goa.
4.2.28 With Cargo facilities built at Manohar International Airport, Mopa, Goa, the capacity restrictions present at
Dabolim airport will no longer exist, and the dedicated cargo handling facility at Manohar International
Airport, Mopa, Goa will act as a supporting infrastructure for the growth of cargo freight demand in the state
of Goa.
4.2.29 Based on this information, the Authority proposes that the cargo projections as submitted by GIAL, Mopa,
Goa can be considered for the current control period.
Consultation Paper No. 11/2023-24 Page 41 of 156TRAFFIC FOR THE FIRST CONTROL PERIOD
Table 30: Cargo traffic proposed by the Authority for the First Control Period
Particulars FY 24 FY 25 FY 26 FY 27 FY 28 Total
Domestic 5,397 7,058 7,806 9,560 10,474 40,295
Market Share % 50% 50% 60% 60% 70% -
International 5,814 8,592 9,384 14,742 15,116 53,648
Market Share % 80% 80% 90% 90% 90% -
Total 11,211 15,650 17,190 24,302 25,590 93,943
4.2.30 Based on the overall above analysis, the traffic proposed by the Authority for Manohar International Airport,
Mopa, Goa for the First control period is as follows:
Table 31: Traffic proposed by the Authority for the First Control Period
Domestic Passengers (in Mn) FY 24 FY 25 FY 26 FY 27 FY 28 Total
Domestic PAX submitted by GIAL, Mopa, Goa
6.09 6.91 8.62 10.67 12.11 44.40
(Table 19)
Domestic PAX proposed by the Authority (A)
6.09 6.91 8.62 10.67 12.11 44.40
(Table 28)
GIAL, Mopa, Goa’s submission Y-o-Y % growth
- 13.46% 24.75% 23.78% 13.50% -
in traffic
Authority’s Proposal Y-o-Y % growth in traffic - 13.46% 24.75% 23.78% 13.50% -
Domestic exempted PAX % FY 24 FY 25 FY 26 FY 27 FY 28 Average
Submitted by GIAL, Mopa, Goa 2% 2% 2% 2% 2% 2%
As per the Authority (B) - - - - - -
Billable Domestic Passengers (in Mn) FY 24 FY 25 FY 26 FY 27 FY 28 Total
Submitted by GIAL, Mopa, Goa 5.97 6.77 8.45 10.46 11.87 43.51
As per the Authority (C=A*(1-B)) 6.09 6.91 8.62 10.67 12.11 44.40
International Passengers (in Mn) FY 24 FY 25 FY 26 FY 27 FY 28 Total
International PAX submitted by GIAL, Mopa,
0.79 0.94 0.98 1.12 1.21 5.04
Goa (Table 19)
International PAX proposed by the Authority (D)
0.79 0.94 0.98 1.12 1.21 5.04
(Table 28)
GIAL, Mopa, Goa’s submission Y-o-Y % growth
- 18.99% 4.26% 14.29% 8.04% -
in traffic
Authority’s Proposal Y-o-Y % growth in traffic - 18.99% 4.26% 14.29% 8.04% -
Total passengers (in Mn) FY 24 FY 25 FY 26 FY 27 FY 28 Total
Total PAX as per GIAL, Mopa, Goa's submission 6.88 7.85 9.60 11.79 13.32 49.44
Total PAX proposed by the Authority 6.88 7.85 9.60 11.79 13.32 49.44
GIAL, Mopa, Goa’s submission Y-o-Y % growth
- 14.10% 22.29% 22.81% 12.98% -
in traffic
Authority’s Proposal Y-o-Y % growth in traffic - 14.10% 22.29% 22.81% 12.98% -
Total Billable Passengers (in Mn) FY 24 FY 25 FY 26 FY 27 FY 28 Total
Submitted by GIAL, Mopa, Goa 6.76 7.71 9.43 11.58 13.08 48.55
As per the Authority (E=C+D) 6.88 7.85 9.60 11.79 13.32 49.44
Consultation Paper No. 11/2023-24 Page 42 of 156TRAFFIC FOR THE FIRST CONTROL PERIOD
Domestic ATM (in Nos) FY 24 FY 25 FY 26 FY 27 FY 28 Total
Domestic ATM submitted by GIAL, Mopa, Goa
40,620 46,079 57,499 71,156 80,719 296,073
(Table 19)
Domestic ATM proposed by the Authority (F)
40,620 46,079 57,499 71,156 80,719 296,073
(Table 29)
GIAL, Mopa, Goa’s submission Y-o-Y % growth
- 13.44% 28.11% 33.62% 23.54% -
in traffic
Authority’s Proposal Y-o-Y % growth in traffic - 13.44% 28.11% 33.62% 23.54% -
International ATM (in Nos) FY 24 FY 25 FY 26 FY 27 FY 28 Total
International ATM submitted by GIAL, Mopa,
4,798 5,668 5,951 6,784 7,327 30,528
Goa (Table 19)
International ATM proposed by the Authority (G)
4,798 5,668 5,951 6,784 7,327 30,528
(Table 29)
GIAL, Mopa, Goa’s submission Y-o-Y % growth
- 18.13% 4.99% 14.00% 8.00% -
in traffic
Authority’s Proposal Y-o-Y % growth in traffic - 18.13% 4.99% 14.00% 8.00% -
Total ATM (in Nos) FY 24 FY 25 FY 26 FY 27 FY 28 Total
Total ATM as per GIAL, Mopa, Goa's submission 45,418 51,747 63,450 77,940 88,046 326,601
Total ATM proposed by the Authority (H=G+F) 45,418 51,747 63,450 77,940 88,046 326,601
GIAL, Mopa, Goa’s submission Y-o-Y % growth
- 13.94% 22.62% 22.84% 12.97% -
in traffic
Authority’s Proposal Y-o-Y % growth in traffic - 13.94% 22.62% 22.84% 12.97% -
Domestic Cargo (in MT) FY 24 FY 25 FY 26 FY 27 FY 28 Total
Domestic Cargo submitted by GIAL, Mopa, Goa
5,397 7,058 7,806 9,560 10,474 40,295
(Table 19)
Domestic Cargo proposed by the Authority (Table
5,397 7,058 7,806 9,560 10,474 40,295
30) (I)
GIAL, Mopa, Goa’s submission Y-o-Y % growth
- 30.78% 10.60% 22.47% 9.56% -
in traffic
Authority’s Proposal Y-o-Y % growth in traffic - 30.78% 10.60% 22.47% 9.56% -
International Cargo (in MT) FY 24 FY 25 FY 26 FY 27 FY 28 Total
International Cargo submitted by GIAL, Mopa,
5,814 8,592 9,384 14,742 15,116 53,648
Goa (Table 19)
International Cargo proposed by the Authority
5,814 8,592 9,384 14,742 15,116 53,648
(Table 30) (J)
GIAL, Mopa, Goa’s submission Y-o-Y % growth
- 47.78% 9.22% 57.10% 2.54% -
in traffic
Authority’s Proposal Y-o-Y % growth in traffic - 47.78% 9.22% 57.10% 2.54% -
Total Cargo (in MT) FY 24 FY 25 FY 26 FY 27 FY 28 Total
Total Cargo submitted by GIAL, Mopa, Goa 11,211 15,650 17,190 24,302 25,590 93,943
Total Cargo proposed by the Authority (K=I+J) 11,211 15,650 17,190 24,302 25,590 93,943
GIAL, Mopa, Goa’s submission Y-o-Y % growth
- 39.60% 9.84% 41.37% 5.30% -
in traffic
Authority’s Proposal Y-o-Y % growth in traffic - 39.60% 9.84% 41.37% 5.30% -
Consultation Paper No. 11/2023-24 Page 43 of 156TRAFFIC FOR THE FIRST CONTROL PERIOD
4.3 Authority’s proposals regarding Traffic for the First Control Period
Based on the material before it and its analysis, the Authority proposes the following with regard to traffic
for the First Control Period:
4.3.1 To consider Passenger Traffic, ATM and Cargo Traffic for the First Control Period for Manohar International
Airport, Mopa, Goa as per Table 31.
4.3.2 To true up the traffic volumes (Passenger, ATM and Cargo) based on actual numbers for the First Control
Period at the time of determination of tariff for the next control period.
Consultation Paper No. 11/2023-24 Page 44 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
5. CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE
(RAB) FOR THE FIRST CONTROL PERIOD
5.1 Background
5.1.1 RAB is an essential element in the process of tariff determination. The return to be provided on the RAB
constitutes a considerable portion of the Aggregate Revenue Requirement for GIAL, Mopa, Goa. To
encourage the participation of the private sector in airport development and operations, investors must be
fairly compensated for the capital outlays involved. At the same time, to safeguard the interests of the airport
users, it must be ensured that the capital additions are efficient, their needs justified, and the return on
investment provided solely on the assets related to the core operations (i.e., Aeronautical services) of the
airport.
5.1.2 The Authority notes that, as part of the Concession Agreement (CA), GIAL, Mopa, Goa has proposed to plan
and develop Mopa, Goa in a phased manner during the Concession period, to cater to the annual passenger
throughput capacity (domestic and international) and annual cargo handling capacity, along with ancillary
facilities as per its demand projections. Development of the airport includes construction and procurement of
various assets as described in Schedule B to the CA such as:
• Runways, Taxiways, Apron, Aircraft parking bays and associated facilities.
• Construction and procurement of Terminal Building
5.1.3 The Authority notes that GIAL, Mopa, Goa is mandated to develop an integrated terminal building which is
efficiently planned, flexible for phase-wise development, sustainable and economical, as stipulated in
Schedule B of Annex I of the CA. Further, as per clause 26.8.1 of the CA, GIAL, Mopa, Goa should
participate in the user survey of (Airport Service Quality) ASQ undertaken by Airports Council International
(ACI) conducted every quarter and ensure that the Airport achieves and maintains a rating of at least 4.2 out
of 5.0 and / or shall appear within top 20 percentile of all airports, in its category in the world in such survey.
5.1.4 The Authority observed that the assessment of expansion/ modification plan of the Airport and its phasing is
a technical matter, which requires analysis by the domain expert. The Independent Consultant M/s KITCO
appointed by the Authority has performed an in-depth analysis of the submissions made by GIAL, Mopa,
Goa towards Capital Additions and RAB. In this respect, the Independent Consultant has performed the
following functions:
i. Examined the proposal of GIAL, Mopa, Goa in terms of the designated capacity of the airport/scope
with reference to Passenger Growth/Cargo volumes/Air Traffic Movement and assessed cost
effectiveness of the proposal.
ii. Examined the Building standards, Designs and Pavement works including Cost thereon proposed by
GIAL, Mopa, Goa to be in line with IMG norms/IATA/ICAO norms.
iii. Analyzed the reasonableness of the proposed cost with reference to the Tentative Ceiling decided by the
Authority vide order No. 7/2016-17 dated 13.06.2016 based on the details of the rates and quantity as
per Government / Industry approved norms.
iv. Sought documentary evidence and verified the process of approval of CAPEX projects including bidding
process for award of various work orders and justified reasonableness of Time Schedule of Completion
of work proposed by GIAL, Mopa, Goa.
Consultation Paper No. 11/2023-24 Page 45 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Based on the above, the Authority has rationalized the capital addition projects based on the essentiality,
necessity for Airport operations etc.
5.1.5 In addition to the above, M/s KITCO the independent consultant has analyzed the tendering procedures
adopted by GIAL, Mopa, Goa and relevant contract agreements related to capital expenditure submitted by
GIAL, Mopa, Goa.
5.1.6 The Authority has sought and examined GIAL, Mopa, Goa’s submission based on the following details/
criteria:
• Nature of the expenditure
• Necessity / requirement of the expenditure
• Business plan and Master plan for all projects
• Number of PAX projected for the First Control Period
• Terminal Capacity projected for the First Control Period
• Other short-term and long-term plans of the GIAL, Mopa, Goa
• Sustainability of airport operations
• Passenger consideration
• Safety and security of the airport
• Process of approval and sanction for various work orders / purchase orders
5.1.7 In the background of the facts stated above, the Authority has examined the entire CAPEX plan in detail,
considering the historical traffic trends in Goa and future traffic estimates such that only essential, reasonable
and efficient CAPEX is considered as part of RAB for the First Control Period with a view to encourage the
investors and maintain a balanced approach between the sustainable operations of the GIAL, Mopa, Goa and
the interest of the airport users. Further, the Authority takes cognizance of the fact that, if any excessive
CAPEX is allowed in this Control Period, it would be against the regulatory framework, as tariff would have
no link to the services/ facilities created at the Airport and the resultant high aeronautical charges would be
unfair to the ultimate users.
5.1.8 Towards this objective, the Authority has examined in detail the Aeronautical Capital Expenditure and RAB
submitted by the GIAL, Mopa, Goa and has presented its views in the following order:
i. Aeronautical Capital expenditure proposed for the First Control Period
ii. Asset Allocation Ratios and Aeronautical Allocation of CAPEX
iii. Aeronautical Depreciation for the First Control Period
iv. Regulatory Asset Base for the First Control Period
5.1.9 The Authority notes that the Independent Engineer appointed by GoG has recommended the capex costs
which has been approved by GoG.
Consultation Paper No. 11/2023-24 Page 46 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
5.1.10 Based on the above, the Authority through its Independent consultant (M/s PKF S&S LLP) has rationalized
the capital expenditure for all the projects and accordingly proposed capital additions for the First Control
Period.
5.2 GIAL’s submission regarding Capital Expenditure (CAPEX) for the First Control Period
5.2.1 GIAL, Mopa, Goa submitted a total Capital Expenditure of Rs. 4,494.65 crores** in the revised MYTP dated
29th March 2023, for the First Control period, the details of which are as given below:
Table 32: Project wise revised Capital Expenditure submitted by GIAL, Mopa, Goa for the First
Control Period
(Rs. in crores)
SL. Phase II Phase III CAPEX for First
Component Phase I
No Expansion Expansion Control Period
General Requirements & Site
1 964.34 - - 964.34
Establishment
Site Establishment & Site Management
a) 386.53 - - 386.53
charges
b) Site office/Admin building 43.47 - - 43.47
c) Site Preparation/Earthworks 534.34 - - 534.34
2 Airside infrastructure 716.95 65.51 67.50 849.96
a) Runway, Taxiways and Apron 415.95 65.51 63.00 544.46
Airside Buildings, Roads and Drainage
b) 301.00 0.00 4.50 305.50
Systems
3 Passenger Terminal Building (a to f) 730.00 108.18 369.50 1207.68
a) Civil & Structural Works 347.00 - - 347.00
Terminal Equipment
b) 232.00 - - 232.00
(HVAC, Plumbing, LV, ELV, etc.)
Contact Stand & Visual Docking
c) 16.00 - - 0.00
Guidance System (VDGS)
d) BHS & Other Aero Equipment 79.00 - - 79.00
e) Operating Equipment 19.00 - - 19.00
f) Utilities (Power & Water) 37.00 - - 37.00
4 Main Access Road and spine road 98.00 - - 98.00
5 Car Park Area 3.00 - - 3.00
6 Air Traffic Control (ATC) Complex 87.00 - - 87.00
7 Additional Works 68.00 - 2.00 70.00
8 Permanent Water and Electricity 20.00 - - 20.00
Aviation Skill Development Center
9 8.00 - - 8.00
(ASDC)
A Sub Total (1 to 9) 2695.29 173.69 439.00 3307.98
Consultation Paper No. 11/2023-24 Page 47 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
SL. Phase II Phase III CAPEX for First
Component Phase I
No Expansion Expansion Control Period
10 Design Consultancy & PMC Expenses 112.00 13.90 36.00 161.90
11 Pre-Operative Expense 259.00 3.47 3.30 265.77
12 Contingencies 0.00 9.55 22.50 32.05
B Sub Total (10 to 12) 371.00 26.92 61.80 459.72
13 Financing Allowance 448.00 15.44 52.25 515.69
14 Debt Service Reserve Account (DSRA) 89.00 - - 89.00
C Sub Total (13+14) 537.00 15.44 52.25 604.69
General Capex 125.00
Grand Total (A+B+C) 3603.29 216.05 553.05 4497.39*
*The total amount of Rs.4,497.39 crores include the Capital spend of Rs.6.85 crores on the City Side Development.
** The difference of Rs.2.74 crores between the MYTP submission of Rs. 4,494.65 crores as per para 5.2.1 and Rs. 4,497.39 crores
as per the table above, is due to certain rounding off differences in the Phase II and Phase III amounts submitted by GIAL, Mopa,
Goa.
Financing Allowance
5.2.2 GIAL, Mopa, Goa in its submission has stated that it has computed the Financing Allowance in accordance
with section 5.2.7 of AERA guidelines. As per GIAL, Mopa, Goa, following is the computation of financing
allowance:
Table 33: Financing Allowance as submitted by GIAL, Mopa, Goa for the First Control Period
(Rs. in crores)
Financial Year FY17 FY18 FY19 FY20 FY21 FY22 FY23 Total
Capital Work in Progress
- 12.38 25.18 156.95 316.70 631.39 1,456.59
(CWIP)-Opening Balance
Addition 12.38 12.80 131.77 159.75 314.69 825.20 1,691.49
Capitalization - - - - - - 3,148.07 3,148.07
Closing WIP 12.38 25.18 156.95 316.70 631.39 1,456.59 -
Average CWIP 6.19 18.78 91.07 236.83 474.05 1,043.99 728.30
Financing Allowance 0.63 1.93 9.69 25.53 50.96 112.23 247.20 448.17
Total 448.17
5.2.3 Further, GIAL, Mopa, Goa in its submission has considered financing allowance of Rs. 15.44 crores and Rs.
52.25 crores for Phase-II and Phase-III expansion for the purpose of calculating RAB for the First Control
Period.
Means of finance for the capital expenditure plan for the First Control Period
5.2.4 The debt and equity financing for the different capex categories as submitted by GIAL, Mopa, Goa has been
summarized below:
Table 34: Project Means & Finance as submitted by GIAL, Mopa, Goa for the First Control Period
(Rs. in crores)
Project Total Project Cost Equity Debt
Phase I 3,603.09 1,376.00 2,227.09
Phase II 200.00 60.00 140.00
Consultation Paper No. 11/2023-24 Page 48 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Project Total Project Cost Equity Debt
Phase III 500.00 150.00 350.00
General Capex 125.00 - -
5.2.5 The same has been discussed in detail in the Chapter 6.
5.3 Authority’s examination regarding Capital expenditure (CAPEX) for the First Control Period
Authority’s examination of Capital Expenditure
5.3.1 The Authority has carried out a detailed review of the Capital Expenditure for both the demonstration of need
and the reasonableness of costs incurred. This review has evaluated each project carried out by GIAL, Mopa,
Goa as part of Phase I and those proposed to be carried out as part of Phase II and Phase III of the current
control period.
5.3.2 The Authority observed that the assessment of the capital expenditure, expansion plans and its phasing is a
technical matter and therefore requires analysis to be undertaken by domain experts. In this backdrop, the
Authority appointed M/s KITCO to examine the overall project cost submitted by GIAL, Mopa, Goa. The
complete report of the independent study conducted by M/s KITCO is detailed in Appendix 1 of this
Consultation Paper.
5.3.3 M/s KITCO as a part of its examination has analyzed a total Capital Expenditure of Rs. 4,304.70 crores out
of total capital expenditure of Rs. 4,494.65 crores submitted by GIAL, Mopa, Goa. The list of items not
forming part of M/s KITCO’s analysis are as follows:
• Financing Allowance for Phase II and Phase III amounting to Rs. 15.44 crores and Rs. 51.45 crores
respectively.
• General Capex of Rs. 25 crores each year totaling Rs. 125 crores for the First Control Period
Table 35: Reconciliation between the Capex submitted by GIAL, Mopa, Goa and CAPEX analyzed by
M/s KITCO
(Rs. in crores)
Particulars Amount
Amount considered by M/s KITCO for its analysis 4,304.70
Add: Financing Allowance for Phase II 15.44
Add: Financing Allowance for Phase III 52.25
Add: General Capex 125.00
Amount submitted by GIAL, Mopa, Goa (para 5.2.1) 4,494.65
Add: Round off difference 2.74
Project wise amount submitted by GIAL, Mopa, Goa (Table
4,497.39
32)
5.3.4 The independent study conducted by M/s KITCO analyzed the submissions made by GIAL, Mopa, Goa
regarding CAPEX proposed for the First Control Period and examined the need for the proposed Project and
its capacity including assessment of cost-effective alternatives, whether the building standards and designs
are in line with IMG/IATA norms and the reasonableness of the proposed cost with reference to the tentative
Consultation Paper No. 11/2023-24 Page 49 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
ceiling as decided by the Authority. The independent study has the following observations and
recommendations with regards to the cost estimates proposed for the CAPEX of the First Control Period
which are summarized below:
Hard Cost
a) Airside Pavement (Runway, Taxiways and Apron)
The Apron area considered for evaluation by M/s KITCO is 7,93,241 sqm for Phase I & Phase II and 35,000
sqm for Phase III as submitted by GIAL, Mopa, Goa. M/s KITCO as per AERA normative approach order
No. 07/2016-17 issued on 13th June 2016, has rationalized the normative cost submitted by GIAL, Mopa, Goa
which is explained and summarized as follows:
• M/s KITCO has considered inflation adjusted normative cost for Pavement in FY 2021-22 (based on
actual Wholesale Price Index (WPI) inflation rates for period FY 2015-16 to FY 2020-21) and included
6% adjustment for the impact of GST as given in the table below:
Table 36: Inflation Adjusted Normative Cost for Apron
Normative Cost (INR per Sq.m) FY16 FY17 FY18 FY19 FY20 FY21
Apron (A) 4,700
WPI Index (B)* 109.70 111.60 114.90 119.80 121.80 123.40
Inflation adjusted Cost (C=A x B/109.70) 4,700 4,781 4,923 5,133 5,218 5,287
*Source: htttps://eaindustry.nic.in/default.as
Table 37: Inflation Adjusted Normative Cost for Pavement
Particulars (in Rs.) Amount (Rs.)
Normative Cost for Airside Pavement considered in FY 2020-21 (A) 5,287.00/Sq.m
Inflation considered for FY 2021-22 (B)* 7.14%
Inflation adjusted Normative Cost in FY 2021-22 (C)=[Ax(1+B)] 5,664.00/Sq.m
Adjustment for impact of GST (D)** 6%
Final cost in FY 2021-22 [ C x (1 +D)] 6,004.00/Sq.m
*Average of WPI inflation for FY 2020-21 and FY 2021-22
** Normative cost as per AERA Order No.7/2016-17 dated 13th June 2016 includes the prevalent tax of 12%, additional 6% provided
to account for the impact of GST as against 18%
Table 38: Inflation Indexed Rate considered for Phase III- Airside Pavement
Particulars FY 23 FY 24 FY 25 FY 26
WPI Inflation 9.70% 3.30% 3.30% 3.30%
Per Sq.m cost in INR 6,586 6,804 7,028 7,260
Consultation Paper No. 11/2023-24 Page 50 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Table 39: Cost Proposed by M/s KITCO for Airside Pavement for the First Control Period
Inflation Amount
adjusted claimed by Amount
unit rate Quantity GIAL, recommended by
Description Remarks by M/s KITCO
(Rs. per (Sq.m) Mopa, M/s KITCO (Rs.
Sq.m) as per Goa (Rs. in crores)
M/s KITCO in crores)
524.00 (Phase I & GIAL, Mopa, Goa has incurred
7,93,241 525.94 II) (Normative Rs. 50 crores for extra width of
(Phase I & (Phase I & Cost) 22 mtr for parallel taxi way to
II) II) Less: 50.00 be used as Emergency
(a) Cost of 474.00 Runway. It can be used as
Airside 7,260.00 Emergency runway only after
Pavement (Phase III) installation of all equipment
(Inflation 35,000 63.00 25.41 and DGCA approval.
adjusted (Phase III) (Phase III) (Phase III) Accordingly, this CAPEX can
normative be allowed (in absolute terms)
rate) when assets is put to use.
The delays in project extension
and resulting additional costs,
caused by constraints imposed
by the NGT and the Hon'ble
Supreme Court of India, cannot
be solely attributed to GIAL,
Mopa, Goa. The endorsement
(b) Prolongation process, supported by the
cost due to recommendation of the
restraints caused Independent Engineer, M/s
by National Engineers India Limited (EIL) is
28.77 28.77
Green Tribunal vital indicator that GIAL, Mopa,
(Phase I) (Phase I)
(NGT) & Goa adhered to regulatory
Hon'ble approvals. It is key to consider
Supreme Court that certain external factors, like
of India subsequent court interventions
significantly contributed to the
extended project timeline and
increased expenses. Further it is
noted that Independent engineer
appointed by GoG has
recommended this cost which
has been approved by GoG.
It is not to be considered, as
(c) Additional machinery to carry out
Overhead (OH) 13.99 - additional works including
charges due to (Phase I) (Phase I) mobilization, site office and
scope change other infrastructure was
already available. So,
Consultation Paper No. 11/2023-24 Page 51 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Inflation Amount
adjusted claimed by Amount
unit rate Quantity GIAL, recommended by
Description Remarks by M/s KITCO
(Rs. per (Sq.m) Mopa, M/s KITCO (Rs.
Sq.m) as per Goa (Rs. in crores)
M/s KITCO in crores)
remobilization of resources
related cost not applicable.
Total (a+b+c) 631.70 528.18
b) Passenger Terminal Building (PTB) including Fit Outs
GIAL, Mopa, Goa had submitted that the warm shell for PTB corresponding to 7.7 MPPA amounting Rs.
780.69 crores is commissioned in the FY 2022-23 and Fit Outs amounting to Rs. 108.81 crores for Phase II
is expected to be commissioned in the FY 2023-24.
M/s KITCO has worked out the justifiable cost based on following:
a) Cost allowed for various other PPP airports like Hyderabad International Airport Limited (HIAL),
Bangalore International Airport Limited (BIAL), Delhi International Airport Limited (DIAL) by AERA,
based on the studies conducted by Independent Consultants.
b) Terminal Building Cost considering the design and specifications provided by GIAL, Mopa, Goa
On the basis of above two factors, the cost of Phase I & Phase II is considered justified. During the review of
cost of PTB for Phase III, M/s KITCO has adopted the same procedure that had been adopted to calculate the
cost for the Airside Pavement. M/s KITCO has considered the inflation adjusted rate per sq.m for the Phase
III expansion as shown in the below table:
Table 40: Inflation Indexed rate considered for Phase III - PTB
Particulars FY 23 FY 24 FY 25 FY 26
WPI Inflation 9.70% 3.30% 3.30% 3.30%
Cost Per Sq.m (INR) 131,500* 135,840 140,322 144,953
Source: Survey of Professional Forecasters on Macroeconomic indicators – Results of 80th Round (RBI)
*Cost per sq.m by GIAL, Mopa, Goa in Phase I & Phase II
Table 41: Cost Proposed by M/s KITCO for PTB for the First Control Period
Amount
Inflation Amount
submitted by
adjusted unit recommended
Quantity GIAL, Mopa,
Description rate (Rs. per by M/s KITCO Remarks by M/s KITCO
(sq.m) Goa (Rs. in
sq.m) as per (Rs. in crores)
crores) including
M/s KITCO including GST
GST
(a) Cost for 888.87 888.87
1,31,500 67,726 Cost Justified as per analysis
PTB (Phase I & II) (Phase I & II)
Consultation Paper No. 11/2023-24 Page 52 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Amount
Inflation Amount
submitted by
adjusted unit recommended
Quantity GIAL, Mopa,
Description rate (Rs. per by M/s KITCO Remarks by M/s KITCO
(sq.m) Goa (Rs. in
sq.m) as per (Rs. in crores)
crores) including
M/s KITCO including GST
GST
1,44,953
369.50 362.38
(Inflation adjusted 25,000 Inflation adjusted cost
(Phase III) (Phase III)
normative cost)
The delays in project
extension and resulting
additional costs, caused by
constraints imposed by the
NGT and the Hon'ble
Supreme Court of India,
cannot be solely attributed to
GIAL, Mopa, Goa. The
endorsement process,
supported by the
recommendation of the
(b) Independent Engineer, M/s
Prolongation Engineers India Limited
cost due to 32.78 32.78 (EIL) is vital indicator that
restraints (Phase I) (Phase I) GIAL, Mopa, Goa adhered to
caused by regulatory approvals. It is
NGT & SCI key to consider that certain
external factors, like
subsequent court
interventions significantly
contributed to the extended
project timeline and
increased expenses. Further
it is noted that Independent
engineer appointed by GoG
has recommended this cost
which has been approved by
GoG.
It is not to be considered as
(c) machinery to carry out
Additional additional works including
Overhead 15.95 - mobilization, site office and
(OH) charges (Phase I) (Phase I) other infrastructure was
due to scope already available. So,
change remobilization of resources
related cost not applicable.
Total
1307.10 1284.03
(a+b+c)
Consultation Paper No. 11/2023-24 Page 53 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
c) Airside Buildings, Roads and Drainage Systems
M/s KITCO on analysis of the cost relating to the Airside Buildings, Roads and Drainage systems has
proposed the following:
Table 42: Cost Proposed by M/s KITCO for Airside Buildings, Roads and Drainage Systems for the
First Control period
(Rs. in crores)
Amount
Claimed Amount
SI. by recommended
Particulars Remarks by M/s KITCO
No. GIAL, by M/s
Mopa, KITCO
Goa
Length of RCC Drain for entire area considered is
19.126 km. As per the direction of Hon’ble Supreme
Court/ NGT, the complete drainage plan was
Storm water drainage
a. 107.34 revisited and additional provision of culverts,
system
manhole was also included, other than drainage
works. The cost was checked and found to be
reasonable.
As per GIAL, Mopa, Goa for flexible pavement of
Roads (Airside Road,
14.015 km, 2 lane road, rate adopted is Rs.
Cross Service Roads at
3632/sqm including marking, signage etc. all
both east and west of
b. 38.18 complete. As per MoRTH, for flexible pavement,
parking stands, Vehicle
rate per sqm comes to Rs. 4632/-, (considering
Turn Pads in Head of
BC:40mm, DBM: 60mm and SSB:250mm). Hence,
stand Road
rate considered is found reasonable.
Buildings & Other
Airside Infrastructure,
Fire station, Sub-station,
Pump house, NAVAID, For service building with Civil works, MEP and
c. Utility building, DG yard, 75.21 other service-related requirements, rates adopted are
STP, boundary wall, found to be reasonable considering DSR rates.
Workshop, Watch Tower
and Morcha) Washing &
Hot treatment area
MEP works (Runway,
taxiway lighting, AGL
Comparing with similar airside facilities airport the
system, CCTV system
d. 38.20 rates adopted for MEP works at Airside are found
and IT works, HT
reasonable.
Electrical works, Fire
Hydrant Line)
Gabion walls provided with heights varying from
Installation of Gabion 10.40 m to 18.40 m. Comparing the rate of
e. 20.36
wall Maccafferi Terramesh and other related components
with similar project values is found reasonable.
Consultation Paper No. 11/2023-24 Page 54 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Amount
Claimed Amount
SI. by recommended
Particulars Remarks by M/s KITCO
No. GIAL, by M/s
Mopa, KITCO
Goa
As the rates adopted by GIAL, Mopa, Goa are
comparable with the rates worked out by KITCO
comparing CPWD/ MoRTH/ Similar projects the
A Sub Total (a to e) 279.29 279.29
amount submitted by GIAL, Mopa, Goa under the
head Airside Buildings, Roads and Drainage system
is found justified.
The delays in project extension and resulting additional
costs, caused by constraints imposed by the NGT and
the Hon'ble Supreme Court of India, cannot be solely
attributed to GIAL, Mopa, Goa. The endorsement
process, supported by the recommendation of the
Prolongation Cost by EPC Independent Engineer, M/s Engineers India Limited
due to restraints imposed 14.48 14.48 (EIL) is vital indicator that GIAL, Mopa, Goa adhered
f.
by NGT & Hon’ble (Phase I) (Phase I) to regulatory approvals. It is key to consider that
Supreme Court of India certain external factors, like subsequent court
interventions significantly contributed to the extended
project timeline and increased expenses. Further it is
noted that Independent engineer appointed by GoG has
recommended this cost which has been approved by
GoG.
It is not to be considered as machinery to carry out
additional works including mobilization, site office
Additional OH charges by 7.04 -
g. and other infrastructure was already available. So,
EPC due to scope change (Phase I) (Phase I)
remobilization of resources related costs are not
applicable.
B Sub Total (A+f+g) 300.81 293.77 -
h. GST @18% 54.14 52.88 -
Sub Total (B+h)
C 354.95 346.65 -
including GST
Airside additional works Detailed estimate not provided for analysis. Hence,
i. 4.50 -
in Phase III not admitted
Total (C+i) 359.45 346.65 -
Consultation Paper No. 11/2023-24 Page 55 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
d) Site Preparation/Earth Work:
Cost of Site Preparation/Earth Work is as follows:
Table 43: Cost proposed by M/s KITCO for Site Preparation/Earth Work for the First Control Period
(Rs. in crores)
Amount
Amount
Rate submitted
Quantity recommended
Particulars (Rs. per by GIAL, Remarks by M/s KITCO
(m3) by M/s
m3) Mopa,
KITCO
Goa
* Total quantity considered in the tender
assuming ordinary soil and normal
excavation methodology.
** For the purpose of Amendment 1 to
EPC contract post Hon’ble Supreme
Court of India and Hon’ble High
Court/NGT stay order and related
delays, as on Jan 2019 (immediately
before Hon’ble Supreme Court of India
stay order, ~40 Lakh cubic meters of
excavation was completed at contracted
rate but out of that only ~0.6 lakh cubic
meter could be filled due to the
restriction on tree felling and
consequently unavailability of filling
sites. This balance excavated earth was
stored within the site at various locations
available for filling and remained there
for more than one year during the stay
order, exposed to natural elements
a) Earth work including monsoon rains.)
excavation in
1,17,00,000* 225.00** 263.25 263.25
ordinary While revised rates were worked out for
soil remaining cut & fill quantity of ~76.87
lakhs cubic meters, a reduced rate for re-
transport of balance quantity already
excavated and stored for refilling was
necessitated, and a rate of Rs. 117 per
cubic meter was agreed for re-
transportation and filling as the earth had
to be picked up through earth moving
equipment and transported to intended
fill locations before processing and
filling. This rate was lower than
amended composite Cut & Fill rate of
Rs. 225 as the earth was already
excavated and was only to be transported
and compacted. The amended rate so
arrived was inclusive of steep increase in
diesel price during this intervening
period and earthwork rates primarily
consists around 60% on account of
diesel since the machines are primarily
running on diesel. Diesel prices moved
Consultation Paper No. 11/2023-24 Page 56 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Amount
Amount
Rate submitted
Quantity recommended
Particulars (Rs. per by GIAL, Remarks by M/s KITCO
(m3) by M/s
m3) Mopa,
KITCO
Goa
up from Rs. 54 per liter to Rs. 72 per
liter, which was the primary factor.
In addition, an idling claim of Rs. 10.62
crores was also agreed to be paid as most
of the machineries used for Earthwork
(Rippers etc.) were kept at site due to the
uncertainty of lifting of stay order
Hon’ble Supreme Court of India till
June, 2019.
For the purpose of ease and enabling
measurements, all these above factors
were agreed to be captured in terms of
composite rate for entire quantity of
earthwork at a rate of Rs. 225 per cum
from Rs. 129 per cum (as per original
EPC contract) to arrive at the price in
Amended EPC contract, Amendment 1
(As per revised schedule 3A & 3B).
* Quantity allowed by GIAL, Mopa,
b) Earth work
Goa as rock requiring specialized
excavation in
excavation methodology
rock
i) Ripping 1,04,38,314* 51.00** 53.24 53.24
** Rate as per the conditional clause
submitted by EPC during tendering as
ii) Crushing 85,24,748* 161.00** 137.25 137.25
per item no. 2.1.2 (a) & (b).
c) Earth work
initiation 47.52 47.52
charge
The delays in project extension and
resulting additional costs, caused by
constraints imposed by the NGT and the
Hon'ble Supreme Court of India, cannot be
solely attributed to GIAL, Mopa, Goa. The
d)Prolongation endorsement process, supported by the
Cost due to recommendation of the Independent
restraints Engineer, M/s Engineers India Limited
imposed by 31.31 31.31 (EIL) is vital indicator that GIAL, Mopa,
NGT & (Phase I) (Phase I) Goa adhered to regulatory approvals. It is
Hon’ble key to consider that certain external
Supreme factors, like subsequent court interventions
Court of India significantly contributed to the extended
project timeline and increased expenses.
Further it is noted that Independent
engineer appointed by GoG has
recommended this cost which has been
approved by GoG.
Consultation Paper No. 11/2023-24 Page 57 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Amount
Amount
Rate submitted
Quantity recommended
Particulars (Rs. per by GIAL, Remarks by M/s KITCO
(m3) by M/s
m3) Mopa,
KITCO
Goa
Not admitted as machinery to carry out
e) Additional
additional works including mobilization,
Overhead
15.23 - site office and other infrastructure was
(OH) charges
(Phase I) (Phase I) already available. So, remobilization of
due to scope
resources included related cost not
change
applicable.
Total
547.80 532.57
(a+b+c+d+e)
Total incl.
646.41 628.43
GST@18%
e) Administrative Office Building & Site Office
Cost of Administrative Office Building & Site Office is as follows:
Table 44: Cost proposed by M/s KITCO for Administrative Office Building and Site Office for the
First Control Period
(Rs. in crores)
Amount
Claimed Amount
SI. by recommended
Particulars Remarks by M/s KITCO
No. GIAL, by M/s
Mopa, KITCO
Goa
Justified as per the similar works executed,
a. Building Works 35.95 35.95 considering the rate per sqm as Rs. 65,000/- (As per
CPWD Schedule of Rates)
Profit, Preliminaries, Already included in the rates adopted. Hence not
b. 0.69 -
Labor cess allowed
As per the similar works executed, the amount for
c. External works 4.29 4.29
Gabion wall is justified.
A Sub Total (a to c) 40.93 40.24
The delays in project extension and resulting additional
costs, caused by constraints imposed by the NGT and
the Hon'ble Supreme Court of India, cannot be solely
attributed to GIAL, Mopa, Goa. The endorsement
Prolongation Cost by
process, supported by the recommendation of the
contractor due to
2.45 2.45 Independent Engineer, M/s Engineers India Limited
d restraints by NGT &
(Phase I) (Phase I) (EIL) is vital indicator that GIAL, Mopa, Goa adhered
Hon’ble Supreme Court
to regulatory approvals. It is key to consider that
of India
certain external factors, like subsequent court
interventions significantly contributed to the extended
project timeline and increased expenses. Further it is
noted that Independent engineer appointed by GoG has
Consultation Paper No. 11/2023-24 Page 58 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Amount
Claimed Amount
SI. by recommended
Particulars Remarks by M/s KITCO
No. GIAL, by M/s
Mopa, KITCO
Goa
recommended this cost which has been approved by
GoG.
It is not to be considered as machinery to carry out
Additional Overhead additional works including mobilization, site office
1.19 -
e (OH) charges due to and other infrastructure was already available. So,
(Phase I) (Phase I)
scope change remobilization of resources related cost not
applicable.
B Sub Total (A + d + e) 44.57 42.69
f GST @18% 8.02 7.68
Amount admitted by KITCO excluding item (b) &
Total (B + f) 52.59 50.37
(e)
f) ATC Technical Block & ATC Tower
Cost of ATC Technical block & ATC tower is as follows:
Table 45: Cost proposed by M/s KITCO for ATC Technical block & ATC tower for the First Control
Period
(Rs. in crores)
Amount
Amount
claimed by
recommended
Particulars GIAL, Remarks by M/s KITCO
by M/s
Mopa,
KITCO
Goa
Rate adopted by GIAL for ATC TB including civil,
structural and MEP (considering the enhanced
(a) ATC Technical block of electromechanical and Extra Low Voltage (ELV)
built-up area 3826 sqm infrastructure) and with external envelope
including MEP and other 45.26 41.80 comprising of steel and aluminum sections and 46
services and with external mm thick DGU unitized glass facade is analyzed
envelope comparing similar projects executed and the
technical backup requirements. The final amount
justified and recommended is Rs. 41.80 Cr.
Rate adopted by GIAL for ATC Tower including
civil, structural (considering the height of 50 mtrs
approx. and related design considerations) and
(b) ATC Tower of built-up
MEP (considering the enhanced electromechanical
area 721sqm with MEP and
35.98 27.78 and Extra Low Voltage (ELV) infrastructure and
other services and with
with external envelope comprising of heavy steel
external envelope.
and aluminum sections and 46 mm thick DGU
unitized glass facade is analyzed comparing similar
projects executed and the technical backup
Consultation Paper No. 11/2023-24 Page 59 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Amount
Amount
claimed by
recommended
Particulars GIAL, Remarks by M/s KITCO
by M/s
Mopa,
KITCO
Goa
requirements. The final amount justified and
recommended is Rs. 27.78 Cr.
Sub Total A=(a+b) 81.24 69.58
The delays in project extension and resulting
additional costs, caused by constraints imposed by the
NGT and the Hon'ble Supreme Court of India, cannot
be solely attributed to GIAL, Mopa, Goa. The
endorsement process, supported by the
recommendation of the Independent Engineer, M/s
(c) Prolongation cost due to
Engineers India Limited (EIL) is vital indicator that
restraints imposed by NGT & 4.51 4.51
GIAL, Mopa, Goa adhered to regulatory approvals. It
Hon’ble Supreme Court of (Phase I) (Phase I)
is key to consider that certain external factors, like
India
subsequent court interventions significantly
contributed to the extended project timeline and
increased expenses. Further it is noted that
Independent engineer appointed by GoG has
recommended this cost which has been approved by
GoG.
It is not to be considered as machinery to carry out
(d) Additional Overhead additional works including mobilization, site office
2.19 -
(OH) charges due to scope and other infrastructure was already available. So,
(Phase I) (Phase I)
change remobilization of resources related cost not
applicable.
Sub Total (B=A+c+d) 87.94 74.09
(e) GST @ 18% 15.83 13.34
Total C=(B+e) 103.77 87.43
Table 46: Breakup of cost assessed by M/s KITCO for ATC Technical block and ATC Tower
(Rs. in crores)
A) ATC Technical Block of built-up area 3826 sq. mtr. Including MEP and other services and
Amount
with external envelope.
Cost for civil, structural, flooring and finishes= 3826 sq. mtr. X Rs. 35,000 * per sq.m 13.39
External envelope (consisting of 46 mm thick DGU glazing and associated structural supports) 9.43
Furniture and Cabling 2.90
MEP and ELV services (considering enhanced MEP and ELV infrastructure) 16.08
Total 41.80
B) ATC Tower of built up area 721 sq. mtr with MEP and other services and with external
Amount
envelope.
Cost for civil, structural, flooring and finishes= 721 sq. mtr. X Rs. 45,000* per sq. mtr 3.24
External envelope (consisting of 46 mm thick large panel DGU glazing and associated heavy
20.24
structural supports)
MEP and ELV services (considering enhanced MEP and ELV Infrastructure) 4.30
Total 27.78
*Rate (excluding GST) as per CPWD Schedule of rates
Consultation Paper No. 11/2023-24 Page 60 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
The Authority observes that the basic cost of ATC technical Block & ATC tower was higher than the cost of
the Terminal Building. Certain additional costs incurred by GIAL, Mopa, Goa as below has already been
considered by the Authority
• Extra height of control tower,
• Utilization of high-strength steel due to the tower's height, and
• Elevated expenses for Aluminum Glazing to counter the impact of wind pressure.
Cost after consideration of above factors is still higher than the cost per sq.m considered by the Authority for
Terminal Building. Accordingly, these costs have been rationalized by M/s KITCO as detailed in Table 46.
g) Main Access Road & Car Park
Cost analysis of Main Access Road and car park is as follows:
Table 47: Cost proposed by M/s KITCO for Main Access Road & Car Park for the First Control Period
(Rs. in crores)
Amount
Length
claimed Amount
of
Sl. by recommended
Particulars road Remarks by M/s KITCO
No. GIAL, by M/s
(in
Mopa, KITCO
KM)
Goa
Main access road to
terminal / car park
including, intersections,
a. 0.84 13.35
rotary, Marking, signage Total length of road = 4.723km (Item a to
and road furniture all d). Width of road 5 lane & 2 lane
complete
Terminal forecourt, As per MoRTH , for flexible pavement,
waiting lane, passenger rate per sqm comes to Rs. 4632/-,
drop-off, pick up points considering BC:40mm, DBM:60mm and
b. 0.663 8.94
including drainage, SSB:250mm
marking, signage and road 35.65
furniture all complete As per the details submitted by GIAL,
Service roads on land side Mopa, Goa, the rate per sqm including
including marking, marking, signages and etc. all complete
c. 2.00 8.94
signage and road furniture comes to Rs. 4,597.56/-
all complete
Other approach roads on As the amount claimed by GIAL, Mopa,
landside including Goa is within the amount as per the rate
d. Marking, Signage and 1.22 4.42 adopted based on MoRTH, the amount
Road furniture all claimed is justified. (a to d)
complete
Road connecting express As per PO submitted by GIAL, Mopa,
e 50.97 50.97
way to PTB Goa
I Sub Total (a+b+c+d+e) 86.62 86.62
Consultation Paper No. 11/2023-24 Page 61 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Amount
Length
claimed Amount
of
Sl. by recommended
Particulars road Remarks by M/s KITCO
No. GIAL, by M/s
(in
Mopa, KITCO
KM)
Goa
The delays in project extension and
resulting additional costs, caused by
constraints imposed by the NGT and the
Hon'ble Supreme Court of India, cannot be
solely attributed to GIAL, Mopa, Goa. The
endorsement process, supported by the
recommendation of the Independent
Prolongation cost due to Engineer, M/s Engineers India Limited
restraints by NGT & 2.14 2.14 (EIL) is vital indicator that GIAL, Mopa,
f
Hon’ble Supreme Court of (Phase I) (Phase I) Goa adhered to regulatory approvals. It is
India key to consider that certain external factors,
like subsequent court interventions
significantly contributed to the extended
project timeline and increased expenses.
Further it is noted that Independent
engineer appointed by GoG has
recommended this cost which has been
approved by GoG.
It is not to be considered as machinery to
carry out additional works including
Additional Overhead (OH)
1.04 - mobilization, site office and other
g charges due to scope
(Phase I) (Phase I) infrastructure was already available. So,
change
remobilization of resources related cost
not applicable.
II Sub Total (I+f+g) 89.80 88.73
h GST @ 18% 16.16 15.98
Amount admitted by KITCO excluding
Total (II + h) 105.96 104.71
item (g)
Not analyzed as not forming part of
i Car Park 3.00 -
aeronautical.
h) Additional works
Cost analysis of Additional work is as follows:
Table 48: Cost proposed by M/s KITCO for Additional Works for the First Control period
(Rs. in crores)
Amount claimed Amount
SI.
Particulars by GIAL, Mopa, recommended Remarks By KITCO
No.
Goa by KITCO
I Additional works for Phase I
Justified based on similar work
undertaken by KITCO. Hence admitting
a. Police Station 4.79 4.79
the amount submitted by GIAL, Mopa,
Goa
Out of Rs. 5.08 Crore submitted by
Taxi driver’s facility, AEP,
GIAL, Mopa, Goa details submitted is
Post office, Bank, Tensile
b. 5.41 1.79 only for Rs. 1.79 Crore as given below
Fiber covered footpath,
which is justified by KITCO:
Canteen etc.,
Canteen : Rs. 1.00 Cr
Consultation Paper No. 11/2023-24 Page 62 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Amount claimed Amount
SI.
Particulars by GIAL, Mopa, recommended Remarks By KITCO
No.
Goa by KITCO
AEP : Rs. 0.41 Cr
Taxi Driver Facility: Rs. 0.38 Cr
Total : Rs. 1.79 Cr
Material Storage yard Admitted as per details submitted by
c. 5.08 5.08
(2000 Sq.m GIAL, Mopa, Goa
Tax paid to Mopa, Airport
d. Infrastructure Tax 1.69 1.69
Development Authority.
Admitted as per the PO submitted by
GIAL, Mopa, Goa and as per the
e. Tree Translocation 0.85 0.66
requirement of Hon’ble Supreme Court
of India.
Admitted as per the PO submitted by
f. Landside Staff Canteen 0.85 0.85
GIAL, Mopa, Goa
Admitted as per the PO submitted by
g. Central Store 0.85 0.26
GIAL, Mopa, Goa
Post Office (20 sqm) & Admitted as per the PO submitted by
h. 0.85 0.85
Bank GIAL, Mopa, Goa
Admitted as per the PO submitted by
i. Miscellaneous 1.69 1.69
GIAL, Mopa, Goa
ASR/MSSR Building &
j. 5.63 5.63
Other Airside Infrastructure
MT and GSE WS Area
k. 5.09 5.09
(1000 SQM)
Compliance with new
conditions imposed by
l. 7.63 7.63
Hon’ble Supreme Court of
India
Admitted as per the PO submitted by
m. Art works -Subodh Kerkar 1.69 1.69
GIAL, Mopa, Goa for items (j) to (t).
n. Signages- NH66 1.69 1.69
o. Signages - Approach Road 0.85 0.85
p. Signages- Village Road 0.85 0.85
Signages & Installations-
q. 2.96 2.96
Airport
r. Horticulture 2.33 2.33
s. Pax Experience 3.28 3.28
t. City side Development 4.23 4.23
A Sub Total (a to t) 57.63 53.89
u. GST @18% 10.37 9.70
B Sub Total (A+u) 68.00 63.59
Additional works for Phase Cost not admitted as no details
v. 2.00
III available for analysis.
C Sub Total (v) 2.00
Total (B+C) 70.00 63.59
i) Permanent Water & Electricity
For Permanent Water & Electricity infrastructure, GIAL, Mopa, Goa has deposited Rs. 20 Cr. to GoG. Being
a statutory levy, the same is recommended to be considered.
Consultation Paper No. 11/2023-24 Page 63 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
j) Construction of Aviation Skill Development Center (ASDC)
As per the Concessionaire Agreement, development, operation and maintenance of ASDC and ancillary
facilities has been done by GIAL, Mopa, Goa. Thus, recommended to take this into consideration, as it aligns
with the specifications of the concession agreement.
Details of analysis and recommendations are given below:
Cost
Description of Variance (A) –
Sl. No
item (B)
As per GIAL (A) As per KITCO (B)
1 ASDC 8.00 7.66 0.34
Soft Cost
k) Design Consultancy & Project Management Consultancy (PMC) Expenses
Amount analysed by M/s KITCO for Design Consultancy & PMC expenses are as follows:
Table 49: Cost proposed by M/s KITCO for Design consultancy & PMC expenses
(Rs. in crores)
Amount
claimed by Amount
Description GIAL, Mopa, recommended Remarks by M/s KITCO
Goa (Phase I, by KITCO
II & III)
Design Consultancy
14.00 14.00 Admitted as per PO submitted by GIAL, Mopa, Goa.
Charges
a) As clause 3.2 (Technical Criteria) of RFQ for selection
of PMC Consultants for Mopa, Goa Project was found to
be restrictive, recommending a deduction of 0.5 % from
the PMC fee of Rs. 82 crores assessed.
a) 82.00 a) 81.59 b) As Phase II works includes only additional fit outs
PMC expenses Phase I Phase I required to attain 7.7 MPPA, and all items included are
towards Airside b) 13.90 b) 5.22 Supply, Installation, Testing and Commissioning (SITC),
works, PTB and Phase II Phase II only 3% of CAPEX submitted by GIAL, Mopa, Goa for
Landside works c) 36.00 c) 21.95 Phase II allowed towards PMC charges.
Phase III Phase III c) Phase III works considers increase in PTB area with fit
outs and expansion in Apron area. This being an
extension of already adopted procedures of contracting,
5% of CAPEX submitted by GIAL, Mopa, Goa for Phase
III considered for design and PMC charges.
Considered Rs. 15.07 crores as per PO submitted by
Fee for Independent
16.00 15.07 GIAL, Mopa, Goa (against claim amount of Rs. 16
Engineer Services
crores) and approved by GoG
Total 161.90 137.83
Consultation Paper No. 11/2023-24 Page 64 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
l) Pre-Operative Expenses
Pre-Operative expenses submitted by GIAL, Mopa, Goa is analyzed as follows:
Table 50: Cost proposed by M/s KITCO for Pre-Operative expenses
(Rs. in crores)
Cost submitted by
GIAL, Mopa, Goa
Amount
including cost to
S.No Description of item recommended Remarks by M/s KITCO
be incurred for
by M/s KITCO
International
Operations
I Phase I
1 Manpower related cost 96.65 96.65 Cost admitted as per details submitted
Other Consultancy by GIAL, Mopa, Goa/ CA certificate
2 38.07 38.07
Charges for amount incurred.
Others (Incl. Admin & *The cost provided by GIAL, Mopa,
3 87.37 87.37
Finance Charges) Goa includes security coverage for the
4 Security Cost 15.60 *10.40 entire area, encompassing both land
parcels and the airport premises. As a
result, only 2/3rd of the total cost is
allocated to security expenses
specifically related to the airport
premises.
5 Legal Charges 7.31 **4.87
** Since the legal charges primarily
pertain to complying with the orders of
the NGT and the Hon’ble Supreme
Court of India, 2/3rd of the cost is
allocated for these expenses.
Operational Readiness
6 and Airport Transfer 14.00 14.00 As submitted by GIAL, Mopa, Goa
(ORAT)
Total for Phase I 259.00 251.36 -
II Phase II 3.47 - No details submitted by GIAL, Mopa,
III Phase III 3.30 - Goa for analysis. Hence, not allowed.
Total (Phase I to III) 265.77 251.36 -
m) Contingency
The provision of contingencies is towards physical contingencies including any modification to the scope of
the work and unforeseen work. Considering the magnitude of the project, a provision of 3% towards
contingencies is considered adequate (Rs. 9.55 crores towards Phase-II and Rs. 22.50 crores towards Phase-
III totaling to Rs. 32.05 crores) as same is presently being followed by Govt. organizations such as CPWD
etc.
n) Financing Allowance
GIAL, Mopa, Goa has submitted financing allowance as part of capital expenditure of the First Control
Period. The computation of financing allowance by GIAL, Mopa, Goa has presented below:
Consultation Paper No. 11/2023-24 Page 65 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Table 51: Financing Allowance as submitted by GIAL, Mopa, Goa for the First Control Period
(Rs. in crores)
Financial Year FY17 FY18 FY19 FY20 FY21 FY22 FY23 Total
Capital Work in Progress
- 12.38 25.18 156.95 316.70 631.39 1,456.59
(CWIP)-Opening Balance
Addition 12.38 12.80 131.77 159.75 314.69 825.20 1,691.49
Capitalization - - - - - - 3,148.07 3,148.07
Closing WIP 12.38 25.18 156.95 316.70 631.39 1,456.59 -
Average CWIP 6.19 18.78 91.07 236.83 474.05 1,043.99 728.30
Financing Allowance 0.63 1.93 9.69 25.53 50.96 112.23 247.20 448.17
Total 448.17
M/s KITCO, based on the revised capital expenditure as proposed by it, has arrived at the financing allowance
by applying the formula as provided under section 5.2.7 of the AERA guidelines 2011. Further for the purpose
of Cost of Debt, M/s KITCO has adopted the rates provided by GIAL, Mopa, Goa. The estimated Financing
allowance worked out to be Rs. 306.76 crores as shown in the table below:
Table 52: Financing Allowance calculation proposed by M/s KITCO for the First Control Period
(Rs. in crores)
Particulars FY17 FY18 FY19 FY20 FY21 FY22 FY23 Total
Rate of interest 10.25% 10.25% 10.55% 10.78% 10.75% 10.75% 10.73%
Opening WIP - 13.01 27.80 169.45 356.08 725.96 1,673.56
Capital Expenditure 12.38 12.80 131.77 159.75 314.69 825.20 1,691.49 3,148.08
Capital Receipts - - - - - - -
Commissioned Assets 3,365.05
Closing WIP (before FA) 12.38 25.81 159.57 329.20 670.77 1,551.16 -
Financing Allowance (FA) 0.63 1.99 9.88 26.88 55.19 122.40 89.79 306.76
Closing WIP (after FA) 13.01 27.80 169.45 356.08 725.96 1,673.56
o) Debt Service Reserve Account (DSRA)
The Debt Service Reserve Account (DSRA) is a reserve account specifically set aside to make debt payments
in the event of a disruption of cash flows to the extent that debt cannot be serviced. GIAL has submitted
DSRA of Rs. 89 crores as part of capital expenditure for the First Control Period. M/s KITCO noted that
DSRA is not a part of CAPEX and hence recommended not to consider the same.
p) The analysis and remarks on the variations in components of the Capital expenditure by M/s KITCO is
summarized below in Table 53 together with detailing of reasons for other items not elaborated above.
Table 53: KITCO recommendations on Project wise capital expenditure
(Rs. in crores)
As per Revised Cost
MYTP assessed
Sl.
Particulars submitted by by Variations Remarks
No
GIAL, Mopa, M/s
Goa KITCO
Airside Pavement
1 (Runway, Taxiways and 631.70 528.18 103.52 Refer para 5.3.4 a)
Apron)
Consultation Paper No. 11/2023-24 Page 66 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
As per Revised Cost
MYTP assessed
Sl.
Particulars submitted by by Variations Remarks
No
GIAL, Mopa, M/s
Goa KITCO
Passenger Terminal
Building including Fit
2 1,307.10 1,284.03 23.07 Refer para 5.3.4 b)
Outs (for 7.7 MPPA)
(Phase I, II & III)
Airside buildings, Airside
3 roads & Drainage System 359.45 346.65 12.80 Refer para 5.3.4 c)
(Phase I & III)
Site Preparation/
4 646.41 628.43 17.98 Refer para 5.3.4 d)
Earthwork
Administrative building
5 52.59 50.37 2.22 Refer para 5.3.4 e)
& Site office
ATC Technical Block
6 103.77 87.43 16.34 Refer para 5.3.4 f)
and Tower
Main Access Road and
7 108.97 104.71 4.24 Refer para 5.3.4 g)
Car park
Additional Works (Phase
8 70.00 63.59 6.41 Refer para 5.3.4 h)
I & III)
Permanent Water &
9 20.00 20.00 - Refer para 5.3.4 i)
Electricity
10 ASDC 8.00 7.66 0.34 Refer para 5.3.4 j)
A Sub Total (1 to 10) 3307.99 3121.05 186.92
Design Consultancy &
11 145.90 122.76 23.14 Refer para 5.3.4 k)
PMC Expenses
Independent Engineer
12 16.00 15.07 0.93 Refer para 5.3.4 k)
Services
Pre-operative Expenses
13 265.77 251.36 14.41 Refer para 5.3.4 l)
(Phase I, II & III)
Contingencies (Phase I &
14 32.05 18.38 13.66 Refer para 5.3.4 m)
III)
B Sub Total (11 to14) 459.72 407.58 52.15
15 Financing Allowance 448.00 306.76 141.24 Refer para 5.3.4 n)
16 DSRA 89.00 - 89.00 Refer para 5.3.4 o)
C Sub Total (15 & 16) 537.00 306.76 230.24
Grand Total (A+B+C) 4,304.71 3,835.38 469.33
Note: The soft costs will be apportioned among the projects based on the proportion of each project's hard costs to the
total project cost.
5.3.5 The Authority proposes to consider the recommendation of the M/s KITCO report for the cost heads as above,
together with making certain changes in the following cost heads as detailed below:
• Airside Pavement (Runway, Taxiways & Apron)
• Passenger Terminal Building including Fit Outs
Consultation Paper No. 11/2023-24 Page 67 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
• Design Consultancy & PMC Expenses
• Contingencies
• Financing Allowance
Airside Pavement (Runway, Taxiways & Apron)
5.3.6 The Authority notes that M/s KITCO has computed the inflation adjusted normative cost for Pavement in FY
2021-22 (based on actual WPI inflation rates for period FY 2015-16 to FY 2020-21) including 6% adjustment
for GST impact as shown in the Table 37 above. Further M/s KITCO has adjusted the final cost (per sq. m)
of FY 2021-22 with the inflation rates as per the results of the 80th round of survey of professional forecasters
on macroeconomic indicators (RBI) to arrive at the per sq. m cost for FY 2022-23 and FY 2025-26
capitalizations (Refer Table 38). However, for the inflation rates of FY 2022-23 and FY 2025-26, the
Authority proposes to consider the recent Results of the Survey of Professional Forecasters on
Macroeconomic Indicators i.e., the 82nd Round released on 8th June 2023 published by the RBI.
5.3.7 Thus, in order to determine the cost per sqm, the Authority proposes to consider the inflation rates as per
Chapter 7 of this CP, as stated below:
Table 54: Inflation Indexed rate considered by the Authority for calculating cost for Airside Pavement
(Runway, Taxiways and Apron)
Particulars FY 23 FY 24 FY 25 FY 26
WPI Inflation 9.60% 1.90% 4.00% 4.00%
Per sqm cost Rs. 6,581 6,706 6,974 7,253
Table 55: Cost Proposed by Authority for Airside Pavement (Runway, Taxiways and Apron)
(Rs. in crores)
Particulars Phase I and II Phase III Total
Total Sqm 793,241 35,000
Rate per Sqm 6,581 7,253
Cost 522.01 25.39 547.40
Less: Cost for area not put to use (Refer 5.3.4 a)) 50.00 - 50.00
Net Cost 472.01 25.39 497.40
Prolongation cost due to restraints caused by NGT & SCI (Phase I) 28.77 - 28.77
Additional Overhead (OH) charges due to scope change (Phase I) - - -
Total 500.78* 25.39 526.17
*Cost proposed by the Authority for Airside Pavement (Runway, Taxiway and Apron) for Phase I is Rs. 435.53 crores and Phase II
is Rs. 65.25 crores.
5.3.8 This has resulted in a decrease of Rs. 2.01 crores from the estimate approved by M/s KITCO.
Consultation Paper No. 11/2023-24 Page 68 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Passenger Terminal Building including Fit Outs
5.3.9 The Authority on examination of cost for the PTB, proposes to adopt the same procedure that has been
adopted to calculate the cost of Runways, Apron & Taxiways i.e., to consider the inflation rates as explained
in Chapter 7 of this CP. Therefore, the revised calculation as per the Authority proposals are as follows:
Table 56: Inflation Indexed rate considered by the Authority for calculating cost for Passenger
Terminal Building
Particulars FY 23 FY 24 FY 25 FY 26
WPI Inflation 9.60% 1.90% 4.00% 4.00%
Per Sq.m cost Rs. 131,500 133,999 139,358 144,933
Table 57: Cost proposed by the Authority for PTB
(Rs. in crores)
Unit Rate (Rs Quantity
Particulars Amount
per Sq.m) (Sq.m)
Phase- I & II 131,500.00 67,726.00 888.87
a) Cost for PTB
Phase-III (FY26) 144,933.00 25,000.00 362.33
b) Prolongation cost due to restraints caused by NGT & SCI (Phase I) 32.78
c) Additional Overhead (OH) charges due to scope change (Phase I) -
Total 1,283.98
5.3.10 This has resulted in a decrease of Rs. 0.05 crores from the estimate approved by M/s KITCO.
Design Consultancy & PMC Expenses
5.3.11 The Authority notes that, as detailed in KITCO’s analysis on tendering process of Project Management
Consultancy Services that while many reputed national agencies, having experience in carrying out similar
services in other airports/ infrastructure projects are eligible, the criteria in the RFP was restrictive, resulting
in very few participants being considered for evaluation. This has been suitably considered and the value of
services proposed to be considered as part of RAB has been reduced appropriately (Refer para 5.3.4 k).
5.3.12 Further, the Authority on examination of the M/s KITCO report notes that the PMC expenses are calculated
on the following basis:
• Phase-II PMC expense - 3% of CAPEX submitted by GIAL, Mopa, Goa for Phase II
• Phase-III PMC expense - 5% of CAPEX submitted by GIAL, Mopa, Goa for Phase III
5.3.13 The Authority notes that the Phase II works includes only additional fit outs required to attain 7.7 MPPA, and
all items included are Supply, Installation, Testing and Commissioning (SITC) and Phase III includes increase
in PTB area with fit outs and expansion in Apron area which is being an extension of already adopted
procedures of contracting. Thus, the Authority proposes to consider 3% and 5% for Phase-II and Phase-III
respectively, on the CAPEX amount allowed by the Authority for Phase-II and Phase-III as shown in the
Table 55 and Table 57 above. Therefore, the revised Hard cost of Phase-II and Phase-III and the total PMC
expenses proposed by the Authority for the First Control Period is detailed as follows:
Consultation Paper No. 11/2023-24 Page 69 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Table 58: PMC expenses computed by the Authority
(Rs. in crores)
Phases Particulars Reference Amount PMC expenses
Airside Pavements Table 55 65.25
Phase-II PTB (Fit outs) Table 32 108.81
Total 174.06 5.22
Airside Pavements Table 55 25.39
PTB Table 57 362.33
Phase-III Airside Buildings Table 32 4.50
Additional works Table 32 2.00
Total 394.22 19.71
5.3.14 Based on the above, the Authority proposes to consider total cost for PMC expense as per Table 58 and for
the other components of total Design Consultancy and PMC expenses, the Authority proposes to consider as
per M/s KITCO’s analysis mentioned in Table 49 above.
Table 59: Cost proposed by the Authority for Design Consultancy and PMC expenses
(Rs. in crores)
Particulars Phase - I Phase - II Phase - III Total
Design Consultancy Charges 14.00 - - 14.00
PMC works 81.59 5.22 19.71 106.52
Independent Engineer Services 15.07 - - 15.07
Total 110.66 5.22 19.71 135.59
Financing Allowance
5.3.15 As per Direction 5 of the AERA Act and the Authority’s principles followed in the recent tariff orders, in
case of Greenfield Airports the Authority proposes to provide for Financing Allowance. The Authority
considers the capital projects that are being commissioned within the First Control Period to be initial phase
of capital expenditure and accordingly financing allowance will be calculated for the Projects that are
capitalized within the First Control Period of the airport.
5.3.16 The Authority has reviewed the calculations of the financing allowance for Phase-I as recommended by M/s
KITCO in its report and has recomputed the financing allowance for Phase-II and Phase-III being considered
within this control period.
5.3.17 The Authority vide email dated 13th June 2023 sought for certifications on Financing Allowance for Phase-I
and the details of the Cost of Debt from GIAL, Mopa, Goa. Based on the details and certificates provided by
GIAL, Mopa, Goa the financing allowance has been recomputed by the Independent Consultant (M/s PKF
S&S LLP) as below:
Table 60: Cost of Debt considered by the Authority for calculating the Financing Allowance
Particulars FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24
Rate of interest 10.25% 10.25% 10.64% 10.81% 10.75% 10.73% 10.69% 9.00%
Consultation Paper No. 11/2023-24 Page 70 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Table 61: Financing Allowance as proposed by the Authority for Phase I
(Rs. in crores)
Particulars FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24 Total
Opening WIP - 13.01 27.80 167.83 346.22 695.45 1,621.50 141.58
Capital Expenditure 12.61 16.10 132.47 152.21 296.84 808.67 1,044.02 456.32 2,919.24
Capital Receipts - - - - - - -
Commissioned Assets 0.23 3.30 2.28 0.18 0.74 0.59 2,613.42 605.00 3,225.79
Financing Allowance 0.63 1.99 9.89 26.36 53.13 117.98 89.47 7.10 306.55
Closing WIP 13.01 27.80 167.83 346.22 695.45 1,621.50 141.58 0.00 -
5.3.18 Furthermore, GIAL, Mopa, Goa has submitted estimate of Financing Allowance for Phase-II and Phase-III
as Rs. 15.44 crores and Rs. 52.25 crores respectively. Upon analysis and communication with GIAL, Mopa,
Goa via mail dated 13th June 2023, GIAL, Mopa, Goa stated that Phase-II work will commence in early FY
2023-24. The Authority based on the GIAL, Mopa, Goa’s submission notes that Phase-II work will start and
get commissioned by end of this year. Therefore, the Authority notes that there is no requirement of Financing
Allowance for Phase-II.
5.3.19 With respect to Phase-III, the Authority notes that the trigger for expansion for Phase-III is FY 2024-25
therefore, the Authority is of the view that the expenditure for Phase-III shall be incurred from FY 2024-25
and commissioned in FY 2025-26. The Authority assumes that 40% of the approved expenditure for Phase-
III will be spent in FY 2024-25 and the remaining will be in FY 2025-26, based on which financing allowance
for Phase-III is recalculated as Rs. 15.33 crores as against Rs. 52.25 crores submitted by GIAL, Mopa, Goa.
Other observations on Capital Expenditure
General Capex
5.3.20 The Authority notes that GIAL, Mopa, Goa had submitted Rs. 125 crores as General Capex to be incurred at
a rate of Rs. 25 crores each year starting from FY 2023-24. The Authority notes that Manohar International
Airport, Mopa, Goa is a newly constructed airport and additional expansion phases which have been included
in the capital expenditure plan, as submitted by GIAL, Mopa, Goa and reviewed by M/S KITCO is considered
by the Authority as part of Capital Expenditure for the First Control Period.
5.3.21 Upon seeking clarification from GIAL, Mopa, Goa vide email dated 5th July 2023, about the nature of General
Capex proposed for the First Control Period, GIAL, Mopa, Goa stated that the General Capex is required for
routine maintenance of the airport for various requirements which consists of the recurring expenditures
required for a company to continue operating at current state. These requirements may include but not be
limited to the following:
• Mandatory Security related expenditure resulting from directions of the regulatory authorities including
BCAS and DGCA.
• Re-laying of roads for the airports, especially post the monsoon season
• Unplanned expenditure emerging from the passenger and other requirement
• Replacement requirement due to wear and tear of plant and equipment
Consultation Paper No. 11/2023-24 Page 71 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
5.3.22 Considering the above factors and clarification received from GIAL, Mopa, Goa, the Authority notes that
there is no immediate need for significant Capex to be incurred by GIAL, Mopa, Goa. However, to account
for any security related upgrades or any regulatory requirements, the Authority deems it appropriate to
consider Rs. 10 crores each year as General Capex (Refer Table 62). These funds may only be utilized by
GIAL, Mopa, Goa in cases of specific requirements or regulatory mandates related to security or other
regulatory needs.
Debt Service Reserve Account (DSRA)
5.3.23 The Authority notes M/s KITCO comment on Debt Service Reserve Account (DSRA) as follows.
“An amount of Rs. 88.96 crores (out of total requirement of Rs.89.00 crores) has been transferred to DSRA
after completion of Phase I and COD and progressively till 06th May 2023 by the AO. Further, AO is earning
interest @ 7.19% p.a. (weighted average) on quarterly compounding on such deposit. Hence, the return to
be provided on the amount in DSRA is to be computed on differential interest i.e., Weighted Average Cost of
Capital (WACC) minus 7.19% p.a. (quarterly compounding), as per the applicable guidelines for the first
control period up to FY 2027-28. Since DSRA is not a part of CAPEX, therefore same is not being reflected
in the amount recommended by M/s KITCO for CAPEX.
5.3.24 While M/s KITCO has not considered this as part of the CAPEX cost, the Authority notes that M/s KITCO
has indicated that a return equivalent to the difference between WACC and the interest earned on the deposit
is to be given.
5.3.25 The Authority notes the following:
a. The requirement of DSRA is from the Loan arrangement entered into by GIAL, Mopa, Goa for the
purpose of financing the Airport Project. The Authority does not interfere in the manner of financing the
airport construction. The Authority notes that different financing arrangements could have different pre-
conditions which is primarily the responsibility of the GIAL, Mopa, Goa.
b. The Authority further notes that GIAL, Mopa, Goa is earning Interest at the rate of 7.25% per annum
approximately on Fixed Deposit kept as DSRA.
5.3.26 Hence, the Authority is not convinced of providing any additional return on the DSRA deposit.
Credits available with respect to Goods and Service Tax (GST)
5.3.27 The Authority notes that GIAL, Mopa, Goa would be eligible to claim GST Input Tax Credits on procurement
of certain movable property. The Authority expects that the GIAL, Mopa, Goa would properly account for
such credits in its submissions in accordance with Chapter V of The Central Goods and Services Tax Act,
2017 at the time of true up of the RAB for the First Control Period. The Authority may examine the accounting
of input tax credits and make necessary adjustments in this regard at the time of determination of tariffs for
the next Control Period.
5.3.28 Further, the Authority notes the following from the Audited Financial Statements submitted by GIAL, Mopa,
Goa for the year ended March 2023.
“The Hon'ble Orissa High Court vide Judgement in W.P.No.20463/2018, in the case of Safari Retreats
Private Limited, observed that the provisions of section 17(5)(d) of the CGST Act which put restrictions on
claiming of input tax credit are not in line with the objective of the Act, and accordingly, held that if an
Consultation Paper No. 11/2023-24 Page 72 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
assessee is required to pay GST on the rental income arising out of investment on which it has paid GST, it
is required to have input credit on the GST under section 17(5)(d) of the CGST Act.
GIAL (the company) will engage in rendering output supplies which are in the nature of letting out space/
facilities to various airline operators and other parties/ concessionaires, in return for consideration, known
by different nomenclatures, and are leviable to GST. Hence, in view of the above judgement of the Hon'ble
Orissa High Court, the Company is availing the GST ITC in respect of the costs for civil work incurred as
part of the project progress. Further, department has filed an appeal in Hon'ble Supreme Court of India
against the judgement of Hon'ble Orissa High Court. Pending outcome of judgement of Hon'ble Supreme
Court of India, considering the judgement of Hon'ble Orissa High Court and based on the opinion obtained
by the Company in this regard, the Management is of the view that GST ITC in respect of such civil work is
eligible to be availed by the Company. Having regard to the same, GST ITC has been claimed in GST return
and lying as balance to GST ITC unutilised kept in separate ledger in the books of accounts. Also, an
intervention application has been filed by GIAL vide IA 139524 /2022 dated 19th September 2022 before
Hon'ble Supreme Court of India in the matter of appeal filed by the department against Judgement of Orissa
High Court in the matter.
Further a Writ Petition has also been filed by the Company before Hon'ble High Court of Bombay at Panaji,
Goa on 18th December 2020, for ITC claim to be allowed of GST in respect of the civil works i.e. works
contract service and goods and services received by the Company for construction of immovable property
will be used for providing output taxable supplies. The writ was admitted, and numbered WP 99/2021. The
matter is awaiting listing for final hearing. During the pendency of the Writ Petition, GIAL, field a stay
application seeking stay of the demand notice as issued under 73 of the CGST Act and on 15th March 2023,
the Hon'ble High Court disposed off the stay application by recording that no final orders will be made
without seeking leave of the Court.
Considering that, the final decision in the SLP No. 26696/2019 filed by Union of India and other connected
matters, may take longer time, the management has taken a considered view for recognition of the project
expenditure in terms of the prudent accounting principles and prevailing circumstances and also in view of
the fact that various departmental activities under the project are partly completed and partly under
completion recognized as CWIP including the value of Input Tax Credit pertaining to the Civil Works as part
of cost under respective heads of asset instead of Input GST. However, the management reserves its right to
claim ITC in case of favorable decision from the Hon'ble Supreme Court on the above issue. Accordingly,
GST ITC on civil works amounting to Rs.36,824.07 lakhs accumulated till 31st March 2023 has been reversed
from GST recoverable account and now capitalized against the respective assets/ capital work in progress in
the books on accounts during financial year 2022-23.”
5.3.29 The Authority notes from the above that GIAL, Mopa, Goa has claimed Input Tax credit on the cost of civil
works also based on the order of Hon’ble Orissa High court and that this matter is pending before Hon’ble
Supreme Court for a final decision. The Authority notes that while GIAL, Mopa, Goa has contended that this
is recoverable as per the records maintained for GST purposes and also carried it as a GST recoverable asset
in the financial statements till March 2022, the same has been added to Capital Expenditure and accordingly
a significant portion of it would be also capitalized as RAB in FY 2022-23 and the remaining in FY 2023-24.
The Authority notes that if the GST credit is allowed, considering it as part of RAB would be inappropriate.
Consultation Paper No. 11/2023-24 Page 73 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
However, clarity on this will be available only when a decision on this is pronounced by Hon’ble Supreme
Court. Hence, the Authority proposes to consider this as part of Capital Expenditure and consequently RAB,
which will be trued up/ adjusted based on the decision on the same. If the same is allowable as a GST credit,
the same will be reduced from RAB from the year in which the addition was considered as part of RAB.
User Consultation
5.3.30 The Authority notes that GIAL, Mopa, Goa conducted Airport User Consultation Committee (AUCC)
Meeting (refer Appendix 2 for the Minutes of AUCC meeting) on 19th October 2021 with all the stakeholders
and discussed about Capital Expenditure proposed to be undertaken during the First Control Period of FY
2023-24 to FY 2027- 28. The meeting was attended by various airport stakeholders such as Airlines (IndiGo,
SpiceJet, Vistara and other airlines), International Air Traffic Association (IATA), Federation of Indian
Airlines (FIA), Fuel Farm (BPCL, HPCL), Central Industrial Security Force (CISF), Glenmark Pharma,
Celebi, Logistics (Broekman Logistics, Mega Freight) and others.
5.3.31 As per the minutes of the meeting, the Authority observed that GIAL, Mopa, Goa had broadly discussed the
following with the stakeholders:
• Importance of Goa, its catchment area, attractiveness and GMR group’s expertise in the airport sector
• Master/ Phase I development Plan and the construction progress update
• Present and future capex requirement and their respective means of Finance
• Cost comparison with AERA’s benchmark cost
5.3.32 The Authority also notes that several stakeholders had provided feedback, some of which are summarized
below:
• IATA raised concerns regarding the means of finance for security related investment, for which GIAL,
Mopa, Goa stated that the cost relating to security equipment would become a part of RAB and
accordingly recovered, however, CISF Capex and Opex would be recovered through Passenger Security
Fee (PSF). IATA also enquired about the trigger point for the second runway.
• IndiGo and SpiceJet suggested incorporating a greater number of check-in counters and baggage claim
carousels as the existing number of the same are less compared to the capacity of the airport.
• IndiGo raised concerns regarding project cost projected by GIAL, Mopa, Goa exceeding AERA’s
normative rates per sqm and its benchmarked cost. This was explained by GIAL, Mopa, Goa that AERA’s
normative rates are with reference to 2017 and if they are indexed to 2021 then GIAL, Mopa, Goa would
be marginally above the benchmarked cost and the same is said to be justified to AERA as per the
requirement.
CAPEX proposed by the Authority
5.3.33 Based on the above analysis, the adjustments between M/s KITCO’s report and Authority’s consideration of
Capital Expenditure for the First Control Period is summarized below:
Consultation Paper No. 11/2023-24 Page 74 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Table 62: Capex comparison between M/s KITCO and the Authority’s proposal for the First Control
Period (includes Phase I, II &II)
(Rs. in crores)
S.No Description Amount
A GIAL, Mopa, Goa’s submission (Table 35) 4,497.39
B Capex allowed as per M/s KITCO (Table 53) 3,835.38
C Difference (A-B) 662.01
D Adjustments by the Authority
D.1 Adjustment to Runways (2.01)
D.2 Adjustment to Terminal Building (0.05)
D.3 Adjustment to PMC Costs (2.24)
D.4 Adjustments to Financing allowance (including for Phase III) 15.12
D.5 General Capex estimate allowed (Refer para 5.3.22) 50.00
Total (D.1 to D.5) 60.82
E Total Capital Expenditure proposed by Authority (B+(D.1 to D.5)) 3,896.20
5.3.34 Consequently, the details of capital expenditure proposed by the Authority for the First Control Period is
given below:
Table 63: CAPEX proposed by the Authority for the First Control Period
(Rs. in crores)
S.No Description Amount
1 Runway, Taxiways and Apron - (Phase I, II & III) 526.17*
2 Passenger Terminal Building including Fit Outs (for 7.7 MPPA) (Phase I, II & III) 1,283.98
3 Airside buildings, Airside roads & Drainage System (Phase I & III) 346.65
4 Site Preparation/ Earthwork 628.43
5 Administrative building & Site office 50.37
6 ATC Technical Block and Tower 87.43
7 Main Access Road, Spine Road and Car park 104.71
8 Additional Works (Phase I & III) 63.59
9 Permanent Water & Electricity 20.00
10 ASDC 7.66
Consultation Paper No. 11/2023-24 Page 75 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
S.No Description Amount
11 General Capex 50.00
A Sub Total (1 to 10) 3,168.99
11 Design Consultancy & PMC Expenses 120.52
12 Independent Engineer Services 15.07
13 Pre-operative Expenses (Phase I, II & III) 251.36
14 Contingencies (Phase I & III) 18.38
B Sub Total (11 to14) 405.33
15 Financing Allowance 321.88
16 DSRA -
C Sub Total (15 & 16) 321.88
Grand Total (A+B+C) 3,896.20
17 Phase I 3,225.79
18 Phase II 179.28
19 Phase III 441.14
20 General Capex 50.00
* The above amount excludes the cost of Rs. 50 crores for extra width of 22 mtr for parallel taxiway (proposed by GIAL, Mopa, Goa)
which is to be used as Emergency runway only after installation of all equipment and DGCA approval. Accordingly, the Authority
proposes not to consider Rs. 50 crores at this stage and proposes the same to be allowed when asset is put to use (For detail refer
para 5.3.4 a)).
5.3.35 The Authority proposes to reduce (readjustment) 1% of the uncapitalized project cost from the ARR / target
revenue as re-adjustment in case any particular capital project is not completed/ capitalized as per the
approved capitalization schedule. It is further proposed that if the delay in completion of the project is beyond
the timeline given in the capitalization schedule, due to any reason beyond the control of GIAL, Mopa, Goa
or its contracting agency and is properly justified, the same would be considered by the Authority while truing
up the actual cost at the time of determination of tariff for the next Control Period. The re-adjustment in the
ARR/ Target Revenue is to protect the interest of the stakeholders who are paying for services provided by
GIAL, Mopa, Goa and is also encouragement for GIAL, Mopa, Goa to commission/ capitalize the proposed
assets as per the approved CAPEX plan/ schedule.
Year Wise Capital Additions
5.3.36 The Authority as per the proposal explained in para 3.2.7, proposes to consider the ratio of actual to total
capital expenditure of GIAL, Mopa, Goa as base for capitalizing the cost proposed by the Authority for Phase
I in FY 2022-23 and FY 2023-24. Accordingly, 81.24% (as calculated in Table 9) of the total Capital
Expenditure (Table 63) for Phase I is capitalized in FY 2022-23 and the balance in FY 2023-24.
5.3.37 Considering above factors, the Authority proposes the following year wise capital expenditure for the period
from COD to 31st March 2023 and First Control Period:
Consultation Paper No. 11/2023-24 Page 76 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Table 64: Year Wise Capital Expenditure proposed by the Authority
(Rs. in crores)
Total Total
Particulars FY23* FY24 FY25 FY26 FY27 FY28 (FY23 to (FY24 to
FY28) FY28)
Building 760.63 321.41 - 256.21 - - 1,338.25 577.62
Roads 172.84 57.21 - - - - 230.05 57.21
Runway 505.19 221.59 - 23.37 - - 750.15 244.96
Plant & Machinery 300.49 140.42 - 150.66 - - 591.57 291.08
Apron 78.79 38.91 - 5.51 - - 123.21 44.42
Furniture & Fixtures-
10.07 4.80 - 5.39 - - 20.25 10.18
other than trolley
General Capex - 10.00 10.00 10.00 10.00 10.00 50.00 50.00
Land Development 792.73 - - - - - 792.73 -
Total 2,620.74 794.33 10.00 451.14 10.00 10.00 3,896.20 1,275.47
* FY 23 capital additions presented in the table is considered in Chapter 3 – Tariff for period from COD to 31st March 2023.
5.4 Aeronautical Allocation of CAPEX for the First Control Period
GIAL, Mopa, Goa’s Submission
5.4.1 GIAL, Mopa, Goa has provided the allocation of assets as follows into different asset categories.
Table 65: Category wise asset values of total additions as submitted by GIAL, Mopa, Goa
(Rs. in crores)
Category Asset value
Aeronautical Assets 2,830.96
Non-Aeronautical Assets -
Common Assets 1,656.84
Non-Regulatory Assets 6.85
Total 4,494.65
5.4.2 GIAL, Mopa, Goa has submitted that it has adopted the following methodology to allocate the assets between
Aeronautical, Non-Aeronautical and Common assets:
a) Aeronautical assets are assumed to be those assets which are necessary or required for providing the
aeronautical services at the airport
b) Non-aeronautical assets are those which are necessary for the performance of the non-aeronautical
services at the airport.
c) Common assets are those assets which are not identifiable/categorized into either aeronautical asset or
non-aeronautical assets.
d) Passenger Terminal Building has been considered as common asset and the asset related to terminal
building are allocated in the ratio of the area of terminal building used for aeronautical and non-
aeronautical services.
5.4.3 Further, GIAL, Mopa, Goa has submitted the terminal area ratio of 91.03%: 8.97%, considering 6,075 sqm
as non-aero area out of total terminal area of 67,726 sqm.
Consultation Paper No. 11/2023-24 Page 77 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
5.4.4 Based on the above allocation methodology, GIAL, Mopa, Goa has submitted the detailed package wise cost
allocation for the First Control Period as table below:
Table 66: Detail of package wise cost and allocation as submitted by GIAL, Mopa, Goa
(Rs. in crores)
Total Financing Non- Non-
Package Classification Total Aero
Capex Allowance Aero Airport
Apron Aero 163.89 23.27 187.16 187.16 - -
Runway Aero 289.02 41.04 330.06 330.06 - -
Taxiway Aero 405.71 57.61 463.32 463.32 - -
Drainage Aero 236.55 33.59 270.14 270.14 - -
Other Airside Building Aero 395.72 56.19 451.91 451.91 - -
Roads Aero 280.44 39.82 320.26 320.26 - -
P&M Common 76.42 10.85 87.27 79.44 7.83 -
Fuel Hydrant System Non-Aero - - - - - -
PTB Common 765.06 108.64 873.70 795.33 78.37 -
ATC Aero 127.90 18.16 146.07 146.07 - -
Aeronautical Ground - -
Aero 40.30 5.72 46.02 46.02
Lighting (AGL)
Heating, Ventilation - -
and Air Conditioning Aero 76.16 10.81 86.97 86.97
(HVAC)
PH&E Aero 159.07 22.59 181.66 181.66 - -
Passenger Boarding - -
Bridges (PBB) & Aero 21.93 3.11 25.04 25.04
VGDS
BHS Aero 41.08 5.83 46.91 46.91 - -
X-ray Aero 52.53 7.46 59.99 59.99 - -
Furniture Common 16.31 2.32 18.62 16.95 1.67 -
Non- -
City Side Development 6.85 - 6.85 - 6.85
Regulatory
Phase II expansion Aero 200.00 15.44 215.44 215.44 - -
Phase III expansion Common 500.00 52.25 552.25 497.03 55.22 -
General Capex Common 125.00 - 125.00 122.00 3.00 -
Total 3,979.93 514.72 4,494.65 4,341.70 146.10 6.85
Authority’s examination on Asset Categorization / Asset Allocation
5.4.5 The Authority has reviewed the asset categorization provided by GIAL, Mopa, Goa. The Authority also notes
that GIAL, Mopa, Goa has submitted that the Fixed Asset Register is under preparation and is not completed.
Hence, review of asset categorization and asset allocation carried out now, will be on an estimate basis which
will be reviewed and updated at the time of true up in the next control period.
5.4.6 The Authority has obtained the area statement of the Terminal building and notes that GIAL, Mopa, Goa has
considered 58,440.95 sqm as aeronautical out of total area of 67,726.02 due to which Terminal Building Ratio
(TBLR) adopted by GIAL, Mopa, Goa is 91.03%:8.97%. The Authority examined the Terminal Area ratio
Consultation Paper No. 11/2023-24 Page 78 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
submitted by GIAL, Mopa, Goa and analyzed that the non-aeronautical area allocation considered by GIAL,
Mopa, Goa for computation of Terminal Area Ratio is low when compared to other PPP airports. Further, it
was observed that the area allocation towards non-aeronautical activities at the other PPP airports such as
DIAL, MIAL, BIAL and HIAL are much higher than 10%. Even the IMG norms on passenger terminals
recommend the non-aeronautical area allocation to be between 8-12% for any airport, while for bigger
airports, i.e., with passenger traffic exceeding 10 million, commercial area could be up to 20% of the overall
area. Considering that Manohar International Airport, Mopa, Goa is a newly established greenfield airport
situated in a prominent tourist destination, the Authority believes that it will attract a substantial amount of
traffic. The Authority encourages GIAL, Mopa, Goa to allocate a larger portion of the terminal building for
non-aeronautical activities which includes a wide range of amenities and services that cater to the needs and
preferences of tourists visiting the region, together with ensuring meeting of all Aeronautical requirements.
For the first control period, the Authority proposes a revised TBLR of 90%:10% for the First Control Period.
This will be reviewed in the next Control Period.
5.4.7 The Authority in para 3.2.10 & 3.2.11 has explained in detail and proposed to consider land development as
a separate line item. Further the Authority is of the view that land development is utilized commonly for
aeronautical, non-aeronautical and other activities, thus Gross Block Asset ratio as computed in Table 87 will
be applied to determine the aeronautical proportion of land development costs.
5.4.8 Based on the above, the aeronautical capital additions year wise for the First Control Period has been
presented below:
Table 67: Aeronautical Capital Additions proposed by the Authority for the First Control Period
(Rs. in crores)
Total Total
Asset Classificati
FY 23* FY24 FY25 FY26 FY27 FY28 (FY23 to (FY24 to
Classification on
FY28) FY28)
Apron Aero 78.79 38.91 - 5.51 - - 123.21 44.42
Runway Aero 183.88 83.49 - 9.72 - - 277.09 93.21
Taxiway Aero 195.04 96.31 - 13.65 - - 305.01 109.96
Drainage Aero 126.27 41.79 - - - - 168.06 41.79
Other Airside
Aero 192.11 63.59 - - - - 255.70 63.59
Building
Roads Aero 172.84 57.21 - - - - 230.05 57.21
P&M Common 59.50 25.87 - 22.71 - - 108.09 48.58
PTB Common 430.89 205.31 - 230.59 - - 866.78 435.89
ATC Aero 82.86 27.43 - - - - 110.29 27.43
HVAC Common 42.30 20.16 - 22.64 - - 85.09 42.79
PH&E Common 104.46 49.77 - 55.90 - - 210.14 105.67
PBB & VGDS Aero 13.53 6.45 - 7.24 - - 27.22 13.69
BHS Aero 25.35 12.08 - 13.57 - - 51.00 25.65
Consultation Paper No. 11/2023-24 Page 79 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Total Total
Asset Classificati
FY 23* FY24 FY25 FY26 FY27 FY28 (FY23 to (FY24 to
Classification on
FY28) FY28)
X-ray Aero 32.42 15.45 - 17.35 - - 65.21 32.79
Furniture Common 9.06 4.32 - 4.85 - - 18.22 9.16
Land
Common 758.61 - - - - - 758.61 -
Development
City Side
Non-Aero - - - - - - - -
Development
General Capex Common - 9.00 9.00 9.00 9.00 9.00 45.00 45.00
Total 2,507.92 757.11 9.00 412.73 9.00 9.00 3,704.76 1,196.84
* FY 23 aeronautical capital additions presented in the table is considered in Chapter 3 – Tariff for period from COD to 31st March
2023.
5.4.9 Asset category wise aeronautical capital additions for the First Control Period has been presented below:
Table 68: Asset category wise Aeronautical additions proposed by the Authority for the First Control
Period
(Rs. in crores)
Total Total
Particulars FY23* FY24 FY25 FY26 FY27 FY28 (FY23 to (FY24 to
FY28) FY28)
Building 705.86 296.32 - 230.59 - - 1,232.77 526.90
Roads 172.84 57.21 - - - - 230.05 57.21
Runway 505.19 221.59 - 23.37 - - 750.15 244.96
Plant & Machinery 277.57 129.77 - 139.41 - - 546.76 269.18
Apron 78.79 38.91 - 5.51 - - 123.21 44.42
Furniture & Fixtures- other
9.06 4.32 - 4.85 - - 18.22 9.16
than trolley
General Capex - 9.00 9.00 9.00 9.00 9.00 45.00 45.00
Land Development (Refer
758.61 - - - - - 758.61 -
para 5.4.7)
Total 2,507.92 757.11 9.00 412.73 9.00 9.00 3,704.76 1,196.84
* FY 23 aeronautical capital additions presented in the table is considered in Chapter 3 – Tariff for period from COD to 31st March
2023.
5.5 Depreciation for the First Control Period
GIAL, Mopa, Goa’s submission regarding depreciation for the First Control Period
5.5.1 GIAL, Mopa, Goa in its submission has stated that it has considered the useful life of an asset in line with the
AERA order No. 35/2017-18. Accordingly, the major asset heads for the purpose of capitalization and the
useful life of asset along with the effective rate of depreciation considered by GIAL, Mopa, Goa in submission
are as follows:
Consultation Paper No. 11/2023-24 Page 80 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Table 69: Useful life adopted by GIAL, Mopa, Goa
Asset Dep. Rate as per MYTP
Building 3.33%
Roads 10.00%
Runway 3.33%
Plant & Machinery 6.67%
Apron 3.33%
Furniture & Fixtures other than trolley 14.29%
General Capex 6.00%
Phase II and Phase III 4.56%
5.5.2 The following table summarizes GIAL, Mopa, Goa’s estimation of aeronautical depreciation for all assets in
First Control Period.
Table 70: Aeronautical Depreciation submitted by GIAL, Mopa, Goa for the First Control Period
(Rs. in crores)
Particulars FY23 FY24 FY25 FY26 FY27 FY28 Total
Building 14.51 46.46 46.46 46.46 46.46 46.46 246.80
Roads 10.01 32.04 32.04 32.04 32.04 32.04 170.19
Runway 11.08 35.46 35.46 35.46 35.46 35.46 188.39
Plant & Machinery 10.96 35.08 35.08 35.08 35.08 35.08 186.36
Apron 1.95 6.24 6.24 6.24 6.24 6.24 33.15
Furniture &Fixtures
0.76 2.42 2.42 2.42 2.42 2.42 12.87
(other than trolley)
General Capex - 0.73 2.20 3.66 5.12 6.59 18.29
Expansion - 4.91 9.82 21.16 32.49 32.49 100.87
Total 49.25 163.34 169.72 182.51 195.31 196.77 956.91
Authority’s Examination regarding depreciation for the First Control Period
5.5.3 The Authority notes that GIAL, Mopa, Goa has computed depreciation for the First Control Period based on
the rates prescribed by AERA vide Order No. 35/2017- 18 dated 12th January 2018, in the matter of
determination of useful life of Airports Assets. The Authority proposes to consider the same. For land
development costs, the Authority proposes to consider the useful life based on lease period available with
GIAL, Mopa, Goa i.e. 36.50 years (For details refer para 3.2.10 and Table 10).
5.5.4 The Useful Life adopted by the Authority and GIAL, Mopa, Goa is presented below:
Table 71: Useful life adopted by the Authority
Useful Life adopted by GIAL, Useful Life adopted by the
Asset
Mopa, Goa Authority
Building 30 30
Roads 10 10
Runway 30 30
Plant & Machinery 15 15
Apron 30 30
Consultation Paper No. 11/2023-24 Page 81 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Useful Life adopted by GIAL, Useful Life adopted by the
Asset
Mopa, Goa Authority
F&F other than trolley 7 7
General Capex (Average rate) 17 17
Land Development - 36.50
Phase II & Phase III * 22 -
* considered as per the relevant categories.
5.5.5 Considering the same and changes to the value of Capital Expenditure, allocation ratio and year of
capitalization, the Authority has computed the depreciation of assets. The following table summarizes the
revised depreciation proposed by the Authority:
Table 72: Total Aeronautical depreciation proposed by the Authority for the First Control Period
(Rs. in crores)
Total Total (FY24
Asset Class FY23 FY24 FY25 FY26 FY27 FY28 (FY23 to to FY28)
FY28)
Building 7.34 28.44 33.37 37.21 41.05 41.05 188.47 181.13
Roads 5.40 20.14 23.00 23.00 23.00 23.00 117.56 112.16
Runway 5.25 20.51 24.20 24.59 24.98 24.98 124.52 119.27
Plant & Machinery 5.78 22.84 27.17 31.82 36.47 36.47 160.55 154.77
Apron 0.82 3.27 3.92 4.01 4.10 4.10 20.23 19.41
F&F other than
0.40 1.60 1.91 2.26 2.60 2.60 11.38 10.98
trolley
General Capex - 0.27 0.81 1.35 1.89 2.43 6.75 6.75
Land Development 6.49 20.78 20.78 20.78 20.78 20.78 110.40 103.91
Total 31.49 117.86 135.17 145.03 154.88 155.42 739.86 708.37
5.6 Regulatory Asset Base (RAB) for the First Control Period
GIAL, Mopa, Goa’s submission regarding RAB for the First Control Period
5.6.1 As per GIAL, Mopa, Goa’s submission, the RAB for First Control Period is as detailed below:
Table 73: RAB submitted by GIAL, Mopa, Goa for the First Control Period
(Rs. in crores)
Particulars FY24 FY25 FY26 FY27 FY28 Total
Opening RAB (a) 3,459.09 3,535.58 3,390.25 3,730.15 3,559.23
Additions to RAB (b) 239.83 24.39 521.41 24.39 24.39 834.41
Deletions to RAB (c) - - - - -
Depreciation (d) 163.34 169.72 182.51 195.31 196.77 907.66
Closing RAB (e) = (a)+(b)-(c)-(d) 3,535.58 3,390.25 3,730.15 3,559.23 3,387.84
Authority’s examination regarding RAB for the First Control Period
5.6.2 The Authority has carefully examined the calculation of RAB and GIAL, Mopa, Goa’s submissions in this
regard. Considering the above, the RAB for the First Control Period as considered by the Authority is shown
below:
Consultation Paper No. 11/2023-24 Page 82 of 156CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET BASE (RAB) FOR THE
FIRST CONTROL PERIOD
Table 74: RAB proposed by the Authority for the First Control Period
(Rs. in crores)
Particulars FY24 FY25 FY26 FY27 FY28 Total
Opening RAB (a) 2,476.43 3,115.68 2,989.51 3,257.21 3,111.33
Additions to RAB (b) 757.11 9.00 412.73 9.00 9.00 1,196.84
Deletions to RAB (c) - - - - -
Depreciation (d) 117.86 135.17 145.03 154.88 155.42 708.37
Closing RAB (e) = (a)+(b)-(c)-(d) 3,115.68 2,989.51 3,257.21 3,111.33 2,964.90
Average RAB =[(a)+(e)]/2 2,796.05 3,052.60 3,123.36 3,184.27 3,038.11
*The significant difference in additions of FY24 between Table 73 and Table 74 is due to capitalization of Phase I remaining cost in
FY24 by Authority (this has been fully considered as capitalized in FY23 by GIAL, Mopa, Goa (refer para 5.3.36 for detailed
explanation)
5.7 Authority’s proposals regarding Capital Expenditure (CAPEX), Depreciation, and
Regulatory Asset Base (RAB) for the First Control Period
Based on the materials before it and its analysis, the Authority proposes the following with regard to CAPEX,
Depreciation, and RAB for the First Control Period
5.7.1 To consider the Terminal Building Ratio (TBLR) of 90:10 as mentioned in para 5.4.6 and in line with IMG
norms and as approved for other similar Airports.
5.7.2 To allow financing allowance during the First Control Period as detailed in Table 61, para 5.3.18 and para
5.3.19.
5.7.3 To adopt the Capital Expenditure for the First Control Period in accordance with Table 64.
5.7.4 To adopt the aeronautical additions for the First Control Period in accordance with Table 68.
5.7.5 To examine the accounting of input tax credits in accordance with Chapter V of The Central Goods and
Services Tax Act, 2017 and make necessary adjustments at the time of determination of tariffs for the next
Control Period (as detailed in para 5.3.27 and para 5.3.29).
5.7.6 To reduce (adjust) 1% of the uncapitalized project cost from the ARR in case any particular capital project is
not completed/ capitalized as per the approved capitalization schedule, as mentioned in para 5.3.35. The same
will be examined during the true up of the First Control Period, at the time of determination of tariff for the
next Control Period .
5.7.7 To true up the Aeronautical Capital expenditure based on actuals, cost efficiency and reasonableness, at the
time of determination of tariff for Next Control Period.
5.7.8 To adopt Aeronautical Depreciation as per Table 72 for the First Control Period.
5.7.9 To true up the Depreciation of the First Control period based on the actual asset additions and actual date of
capitalization during the tariff determination of the Next Control Period.
5.7.10 To consider average RAB for the First Control Period for Manohar International Airport, Mopa, Goa as per
Table 74.
5.7.11 To true up the RAB based on actuals at the time of tariff determination for the Next Control period.
Consultation Paper No. 11/2023-24 Page 83 of 156FAIR RATE OF RETURN FOR THE FIRST CONTROL PERIOD
6. FAIR RATE OF RETURN FOR THE FIRST CONTROL PERIOD
6.1 GIAL’s submission regarding Fair Rate of Return for the First Control Period
Cost of Equity
6.1.1 GIAL, Mopa, Goa had engaged the services of CRISIL to carry out a study on applicable Cost of equity.
Based on this study, the Airport Operator has considered the Cost of equity range as between 20.92% to
24.04%.
6.1.2 GIAL, Mopa, Goa submitted the following assumptions for estimating the Cost of equity:
• The risk-free rate which is the 10-year average yield for 10-year government securities comes out to be
7.42%.
• The market return is 16.82% which is calculated using the 40 years data of Bombay Stock Exchange (BSE)
Sensex, Geometric Mean method and adding Dividend Yield based on longest available data on BSE
Sensex.
• The debt/equity ratio is taken to be at 1.38, as per the pre-defined debt-equity makeup.
• A range of beta is taken, with 5-year beta average for developed and developing countries and 5-year beta
average for just the developing countries. This is then inflated to account for elevated risks associated with
the GIAL, Mopa, Goa.
• Additional CoE Alpha has been considered to factor the risks associated with Greenfield Airports in
Multiple Airport System.
6.1.3 GIAL, Mopa, Goa has submitted the following from CRISIL report relating to the risk profile of GIAL, Mopa,
Goa:
Greenfield projects are inherently riskier, due to factors like delays in construction/project execution,
subdued traffic as against projections, regulatory changes, inadequate liquidity, among others. These
risks might result in delays or in substantial variations in cashflow as against the projections.
Consequently, there is a view to account for these additional risks in the cost of equity calculations, by
using a factor to appropriately allocate these risks.
The operational environment of GIAL, Mopa, Goa, and the greenfield nature of the project, makes the
project riskier than the assets considered for beta calculation. Due to this, we project a higher level of
systemic risk associated with GIAL, Mopa, Goa. Among these, the presence of a fully operational Goa
International Airport in high proximity of the greenfield airport will ensure higher uncertainty in
cashflows and revenue. The same have been highlighted in the cashflow projections. However, due to the
elevated risks for GIAL, Mopa, Goa there is a strong case for adjustment of cost of equity for greenfield
projects, due to the riskier nature of the asset. We recommend introducing these changes through inflating
the beta used for cost of equity calculations, to reflect higher systemic risks.
While the concept of a peer group is a dominant way of determining the beta for unlisted companies, the
airports considered under the category of both developed and developing country are operational for
more than 10 -20 years and will not capture the risks associated to greenfield development. Hence,
Consultation Paper No. 11/2023-24 Page 84 of 156FAIR RATE OF RETURN FOR THE FIRST CONTROL PERIOD
considering a range of beta over various time horizons and capturing the maximum value and its
deviation will help in capturing the maximum risk profile.
Several airport assets were considered for the most appropriate risk representation for the GIAL, Mopa,
Goa. Consequently, Heathrow Airports Limited (HAL) showed an elevated risk level similar to those
shown by the GIAL, Mopa, Goa. Heathrow airport, situated in London, is among five others in the city.
This results in high risks to the revenues of the airport, similar to those faced by GIAL, Mopa, Goa due
to the presence of an operational international airport in Goa in close proximity to the GIAL, Mopa,
Goa. Consequently, we have approached beta inflation in a similar way as used by the HAL.
Since all the risks related to the development of this airport is subsumed in beta, to arrive at a reasonable
beta, we see the entire available asset beta range, i.e., average beta values calculated from daily beta for
a period of 1, 2, and 5 years, for both, developed and developing countries. The risks to GIAL, Mopa,
Goa are higher than the comparator assets considered for beta calculation.
This deviation is used to inflate the unlevered beta. Further, this modified asset beta is then re-levered to
arrive at the equity beta. Using the risk-free rate and market premium calculated earlier, we arrive at
the modified cost of equity. This new cost of equity contains the additional risks to the GIAL, Mopa, Goa,
which can be decomposed into an ‘alpha factor’. Difference between the modified cost of equity and
initial cost of equity will give us the alpha factor for cost of equity calculation. Additionally, we further
provide a range of this alpha factor, by using initial asset beta of (i) developed and developing countries;
and (ii) only developing countries.
6.1.4 Based on the above, the Cost of Equity computed by CRISIL is as detailed below.
Table 75: Cost of equity computation as per GIAL, Mopa, Goa’s submission
Parameter Value
Risk-Free Rate 7.42%
Total Market Return 16.82%
Debt-Equity ratio 1.38
Equity Beta 1.44
Initial Cost of Equity 19.49%
Modified Cost of Equity 20.92%
Additional CoE Alpha 1.42%
Cost of Debt
6.1.5 GIAL, Mopa, Goa has submitted that it has planned a Rupee Term Loan of Rs. 2227 crores for the first phase
of the project totaling to Rs. 3603 crores resulting in a Debt: Equity ratio of 62:38.
6.1.6 GIAL, Mopa, Goa has submitted that in order to fund the project cost of Phase 1, GIAL, Mopa, Goa has tied
up loan with consortium of banks with Axis Bank as the lead bank. The facility has been taken for 18 years
which includes construction period of 3 years, 1 year moratorium and 14 years of repayment. As per the
facility agreement, GIAL, Mopa, Goa shall repay the 80% of Facility in 55 structured quarterly instalments
commencing from quarter ending 30th September 2023 with last instalment due on 31st March 2037. The
remaining 20% of the Facility shall be due as a bullet instalment on 30th June 2037. The rate of interest shall
be the sum of Axis Bank 1-Year Marginal Cost of Funds based Lending Rate (MCLR) and Spread per annum
Consultation Paper No. 11/2023-24 Page 85 of 156FAIR RATE OF RETURN FOR THE FIRST CONTROL PERIOD
plus applicable taxes and other statutory levy, if any. GIAL, Mopa, Goa has submitted that as on date, the A-
MCLR is 8.45% and the spread is 2%.
6.1.7 Based on the above, GIAL, Mopa, Goa has considered the cost of debt facility of 10.45% as the cost of debt
for the control period.
Weighted Average Cost of Capital
6.1.8 Based on the above Cost of Debt, Cost of Equity and normative gearing ratio of 48:52, the Weighted Average
Cost of Capital has been computed by GIAL, Mopa, Goa as below.
Table 76 : Weighted average cost of capital computation submitted by GIAL, Mopa, Goa for FRoR
Parameter Value
Cost of Equity 20.92%
Cost of Debt 10.45%
Weighted Average Gearing of Equity 52.00%
Weighted Average Gearing of Debt 48.00%
Weighted Average Cost of Capital 15.89%
6.2 Authority’s examinations regarding Fair Rate of Return for the First Control Period
Cost of Equity
6.2.1 The Authority had commissioned independent studies for the evaluation of cost of capital separately in case
of PPP Airports, namely DIAL, MIAL, HIAL, BIAL and Cochin International Airport Limited (CIAL)
through a premier institute, namely Indian Institute of Management (IIM) Bangalore and proposes to use
these study reports as a basis, to the extent applicable and relevant, to ascertain the Cost of equity of GIAL,
Mopa, Goa for the First Control Period.
6.2.2 The independent study reports have drawn from the international experience of airports and their conclusions
have been evaluated to the extent comparable with Manohar International Airport, Mopa, Goa in terms of
hybrid till, ownership structure, size, scale of operations and regulatory framework. The average Cost of
equity arrived at by the independent study reports is 15.18%.
6.2.3 The above independent study reports have used the Capital Asset Pricing Model (CAPM) and a notional
gearing (Debt: Equity) ratio of 48:52 to determine the levered Equity beta and accordingly, derive the Cost
of equity.
6.2.4 Based on the above reports, the Authority proposes the Cost of equity of 15.18% for GIAL, Mopa, Goa for
the First Control Period.
6.2.5 The Authority has noted GIAL, Mopa, Goa’s submission that “One of the important aspect covered by
CRISIL is the risk associated with Greenfield projects in multiple airport system. As per CRISIL the
Greenfield Airport have inherent risk related to construction period, liquidity, project execution and traffic.
Accordingly, there has to be some additional factor which needs to be factored in while arriving betas for
such greenfield airports. The risk in case of Mopa, Airport further multiplies due to competition with existing
airport. CRISIL has analyzed these scenarios and considered and alpha factor for such associated risk”
6.2.6 The Authority notes CRISIL report based on which GIAL, Mopa, Goa has stressed on certain key factors
specific to Greenfield Airports which include delays in construction/ project execution, subdued traffic,
regulatory changes, liquidity etc.
Consultation Paper No. 11/2023-24 Page 86 of 156FAIR RATE OF RETURN FOR THE FIRST CONTROL PERIOD
• The Authority notes that risks of construction/ project execution could arise in other situations also, not
necessarily due to multiple airports being located in the nearby vicinity. Also, the Authority provides for
Financing allowance on the work in progress assets for Greenfield airports, mitigating the risk of funds
being locked up.
• The Authority notes that traffic projections submitted by GIAL, Mopa, Goa in itself estimates additional
traffic for Goa as a whole, instead of a linear growth in traffic. Based on the same and considering the
positional advantage of Manohar International Airport, Mopa, Goa, the Authority perceives that inherent
risk of subdued traffic, if any is minimum and transitional.
• As for the risks of regulatory changes, liquidity etc., these are factors that could impact any infrastructure
development in general.
6.2.7 Hence, the Authority is not convinced that any specific risks that may arise due to two airports being present
in the nearby vicinity could impact the Cost of Equity, considering the current Regulatory and other
environment. Accordingly, the Authority proposes to consider Cost of Equity at 15.18% as detailed in para
6.2.4.
6.2.8 The Authority has noted the risk factors enumerated by GIAL, Mopa, Goa. However, the Authority notes that
Airport Operators in India have certain inherent advantages and protections built into the tariff determination
process that is being followed together with support being received from various Governments and
Government agencies:
• There is a well-documented and publicly notified regulatory regime for tariff determination. Proceedings
of tariff determination are conducted in a transparent and consultative manner, in compliance with AERA
Act and other relevant guidelines.
• The tariff determination methodology incorporates adequate returns on the Investment made by the
Airport Operator together with reimbursement of reasonable O&M expenses incurred for the
management of airport.
• The current tariff determination methodology also ensures truing up of certain building blocks based on
efficiency and reasonableness of the same.
• The Government of India, through the Ministry of Civil Aviation and various regulatory agencies,
provides adequate support and guidance on all operational, safety, airline, connectivity and stakeholder
related matters.
• The relevant State Governments help the Airport Operators by the way of allotment of land on
concessional rates in many of the cases, together with providing an improved connectivity from the city
to the airports with enhanced road/ rail infrastructure etc.
Cost of Debt
6.2.9 The Authority notes that the Airport Operator has considered Cost of debt at 10.45% for the First Control
Period based on its rate of borrowing at MCLR + 2% spread.
6.2.10 The Authority notes that the cost of debt of the Airport, in the past years, has ranged from 10.25% to 10.81%
in the years from FY 2017-18 to FY 2021-22, as per the certificates provided by the auditors of GIAL, Mopa,
Goa. The cost of debt for FY 2022-23 has reduced from the previous years (10.81% to 10.69%) and was at
Consultation Paper No. 11/2023-24 Page 87 of 156FAIR RATE OF RETURN FOR THE FIRST CONTROL PERIOD
10.42%. In FY 2022-23 the Company has taken Inter Corporate Loans, loans from NBFCs in addition to
raising convertible and non-convertible debentures from its group company.
6.2.11 The Authority recommends that the Airport shall bring in further efficiencies in its cost of borrowing in order
to reduce the interest rates. This suggestion is also in keeping with the spirit of PPP whereby it is expected
that the financial strength of PPP airports is maintained at an optimal level and their cost of capital is within
reasonably allowable limits. GIAL, Mopa, Goa should avail the synergies and benefits owed to it by its strong
shareholding and balance sheet of its Parent companies and therefore work towards bringing down the cost
of debt to the same levels as other PPP airports.
6.2.12 The Authority believes that PPP airports have scope of bringing in better efficiencies in financial and
operational management of an airport which would reflect in its overall cost of operations and lower FRoR.
6.2.13 Further the Authority has also noted that the Weighted Average Lending Rate (WALR) of public sector banks
and scheduled commercial banks as per the Reserve Bank of India’s publication of December 2022 has been
in the range of 8.92% to 9.52% p.a. The Authority has also noted that the average cost of debt of other five
PPP airports viz., DIAL, MIAL, HIAL, BIAL and CIAL is 8.96%. Also, the rates of loan provided by Axis
Bank range between 6.85% and 10.00% as per the information published by RBI for the period March 2023.
6.2.14 The Authority notes that the airport has already become operational with Commercial operations from 5th
January 2023 which would provide comfort to the lenders on its operational capabilities, ability of repayment
etc. which could also bring down the interest rates. With traffic flowing into the airport and revenues earned
from Aeronautical and Non-Aeronautical sources yielding benefits, the debt profile of Manohar International
Airport, Mopa, Goa is bound to improve and inherent financial risk as reflected in the Cost of Debt will reduce
to the levels of other PPP airports.
6.2.15 Accordingly, the Authority proposes to consider the Cost of Debt of 9% for the computation of Fair Rate of
Return.
Fair Rate of Return
6.2.16 Based on the above, the Authority proposes to consider the following FRoR for the First Control Period for
GIAL, Mopa, Goa.
Table 77: Fair Rate of Return proposed by the Authority for the First Control Period
Parameter Value
Cost of Equity (para 6.2.4) 15.18%
Cost of Debt (para 6.2.15) 9.00%
Weighted Average Gearing of Equity 52.00%
Weighted Average Gearing of Debt 48.00%
Weighted Average Cost of Capital 12.21%
6.3 Authority’s proposals regarding Fair Rate of Return for the First Control Period
Based on the materials before it and its analysis, the Authority proposes the following with regard to FRoR
for the First Control Period:
6.3.1 To consider the Cost of equity at 15.18% as per CAPM formula.
Consultation Paper No. 11/2023-24 Page 88 of 156FAIR RATE OF RETURN FOR THE FIRST CONTROL PERIOD
6.3.2 To consider the notional debt to equity (gearing) ratio of 48%:52% in line with target gearing ratio being
considered in case of other PPP airports.
6.3.3 To consider cost of debt of 9% for the First Control Period.
6.3.4 To consider FRoR of 12.21% for the First Control Period based on above mentioned Cost of equity, Cost of
debt and gearing ratio.
Consultation Paper No. 11/2023-24 Page 89 of 156INFLATION FOR THE FIRST CONTROL PERIOD
7. INFLATION FOR THE FIRST CONTROL PERIOD
7.1 GIAL’s submission regarding Inflation for the First Control Period
7.1.1 GIAL, Mopa, Goa has considered inflationary increase towards operating and maintenance expenses and non
aeronautical revenues for Manohar International Airport, Mopa, Goa for the First Control Period
7.1.2 For the purpose of inflation, GIAL, Mopa, Goa has considered WPI of 5% from the RBI survey of
professional forecasters on macroeconomic indicators – result of the 79th round released on 7th December
2022 for the First Control Period as summarized in the table below.
Table 78: Inflation rates submitted by GIAL, Mopa, Goa for the First control period
Particulars FY 24 FY 25 FY 26 FY 27 FY 28
WPI Inflation 5.00% 5.00% 5.00% 5.00% 5.00%
7.2 Authority’s examination regarding Inflation for the First Control Period
7.2.1 The Authority has examined the submission made by GIAL, Mopa, Goa on inflation to be considered during
the First Control Period and notes that GIAL, Mopa, Goa has considered WPI from the RBI’s 79th round of
survey. However, the Authority proposes to consider the recent “Results of the Survey of Professional
Forecasters on Macroeconomic Indicators: Round 82nd released on 8th June 2023 published by the Reserve
Bank of India (RBI).
7.2.2 Accordingly, the Authority proposes to consider the actual Wholesale Price Index (All commodities) for FY
2023-24 and the mean of WPI inflation forecast (All commodities) for FY 2024-25 and till FY 2027-28 as
given in the 82nd round of professional forecasters on macroeconomic indicators.
7.2.3 Further the Authority assumes that the inflation rate would be stable and remain constant from FY 2024-25
till FY 2027-28. Accordingly, the following table shows the inflation rates as proposed by the Authority for
the First control period.
Table 79: Inflation rates proposed by the Authority for the First control period
Particulars FY 24 FY 25 FY 26 FY 27 FY 28
WPI Inflation 1.90% 4.00% 4.00% 4.00% 4.00%
7.3 Authority’s proposal regarding Inflation for the First Control period
Based on the materials before it and its analysis, the Authority proposes the following for the First Control
Period:
7.3.1 To consider Inflation as per Table 79.
Consultation Paper No. 11/2023-24 Page 90 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
8. OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
8.1 GIAL’s submission regarding Operating and Maintenance Expenses for the First Control
Period
8.1.1 As a greenfield airport, GIAL, Mopa, Goa does not have historical data, making it challenging to accurately
determine Operating and Maintenance (O&M) expenses. GIAL, Mopa, Goa has analyzed each aspect of
O&M expenses considering infrastructure requirements, personnel costs, equipment maintenance, utilities,
security measures and other costs.
8.1.2 GIAL, Mopa, Goa has considered the following drivers as a basis to arrive at the projected O&M expenses
for the First Control Period:
• Inflationary increase – GIAL, Mopa, Goa has considered WPI Inflation of 5% based on the 79th round
of professional forecasters on macroeconomic indicators by RBI towards all expenses.
• Real Increase – Considering the current economic scenario and upcoming expansion, GIAL, Mopa, Goa
has considered 7% year-on-year real increase. This is mainly for manpower cost and office rentals.
• Upcoming expansion at Manohar International Airport, Mopa, Goa – As explained in Chapter 1 of
this Consultation Paper, Manohar International Airport, Mopa, Goa has to expand its capacity from
currently 4.4 MPPA to 11.1 MPPA during the First Control Period. In case of Phase II expansion, GIAL,
Mopa, Goa has assumed 10% incremental factor whereas in case of Phase III expansion i.e., from 7.7 Mn
to 11.1 Mn the incremental factor is assumed to be 50% of the capacity increase, in projecting O&M
expenses.
8.1.3 The broad heads under which GIAL, Mopa, Goa has classified its O&M expenses are as follows:
1. Manpower Expense
2. Admin and General Expense
3. Utility Expense
4. Operating Expense
5. Airport Operator Fee
8.1.4 Based on the above assumptions, GIAL, Mopa, Goa has submitted the following total operating and
maintenance expenses for the First Control Period:
Table 80: Total Operating and Maintenance Expenses submitted by GIAL, Mopa, Goa for the First
Control Period
(Rs. in crores)
Particulars FY24 FY25 FY26 FY27 FY28 Total
Manpower Expenses (A) 68.23 76.66 105.14 118.12 132.71 500.86
Admin and General Expenses
Rates & Taxes 1.77 1.86 2.61 2.74 2.88 11.86
Corporate cost allocation 7.50 7.88 8.27 8.68 9.12 41.45
Corporate Social Responsibility (CSR) - - 0.30 3.24 6.61 10.15
Bank Charges 1.00 1.05 1.10 1.16 1.22 5.53
Consultancy & Legal 18.98 19.93 20.93 21.98 23.08 104.90
Consultation Paper No. 11/2023-24 Page 91 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Particulars FY24 FY25 FY26 FY27 FY28 Total
Travel 3.87 1.56 2.00 2.10 2.21 11.74
Advertisement 13.64 14.33 15.04 15.79 16.58 75.38
Auditor & Director Fee 0.53 0.55 0.58 0.61 0.64 2.91
Office Maintenance etc. 14.64 17.53 22.52 29.03 34.44 118.16
Total Admin and General Expenses (B) 61.93 64.69 73.35 85.34 96.76 382.07
Utility Expenses
Electricity* 37.69 39.43 49.72 52.06 54.53 233.43
Water 1.24 1.49 1.91 2.46 2.92 10.02
Total Utility Expenses (C) 38.93 40.92 51.63 54.53 57.45 243.46
Operating Expenses
Repair and Maintenance 39.96 43.75 51.28 79.38 84.89 299.26
IT Operation related 0.36 - - - - 0.36
Enterprise IT 3.89 4.09 5.24 5.50 5.78 24.50
Housekeeping expense 13.60 13.86 18.91 19.34 19.81 85.52
Insurance 3.72 3.93 4.74 5.01 5.29 22.69
Security expense 13.96 17.13 22.01 27.58 31.68 112.36
Misc. expense 33.79 36.54 40.53 46.60 49.75 207.21
Total Operating Expenses (D) 109.29 119.29 142.70 183.41 197.20 751.89
Airport Operator Fee (E) 0.76 18.37 34.43 44.13 56.92 154.61
Total O&M Expenses
279.14 319.93 407.25 485.53 541.05 2,032.90
(A)+(B)+(C)+(D)+(E)
*Considered electricity expenses net of recoveries from the concessionaires providing non aeronautical services.
8.1.5 GIAL, Mopa, Goa has considered the following basis to calculate the estimated total O&M expenses for the
First Control period:
Manpower Expense
8.1.6 GIAL, Mopa, Goa has estimated its manpower cost by analyzing the manpower requirements (based on
internal estimations) for each department at the airport and determined the average cost per person. The
average cost of manpower, including salaries, wages, bonus, contribution to Provident Fund (PF), and gratuity
expenses was determined to Rs. 14.16 lakh per person considering year ending March 2023 i.e., FY 2022-23
as a base year. GIAL, Mopa, Goa submitted that the manpower cost related to Airport land development has
been considered separately. The department wise manpower details submitted by GIAL, Mopa, Goa is
presented below:
Table 81: Department wise manpower details submitted by GIAL, Mopa, Goa together with its
classification
Department Headcount Classification
CEO’s/ Dy. CEO’s Office 4 Common
CDO’s Office 2 Aeronautical
Planning & Business Intelligence 2 Common
Commercial & Business Development 17 Non-Aeronautical
Finance & Secretarial 12 Common
Procurement & Contracts 6 Common
Consultation Paper No. 11/2023-24 Page 92 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Department Headcount Classification
Human Resources & Flight Management System 10 Common
Project support function 15 Common
Corporate relation & Corp.Com.& Connectivity 12 Common
Legal 4 Common
Management Assurance Group (MAG) 3 Common
CSR 2 Common
IT 5 Common
Ethics & Intelligence 1 Common
COO’s Office 3 Aeronautical
Airside Ops 26 Aeronautical
Airports Operations Control Centre (AOCC) 20 Aeronautical
Aviation Rescue and Fire Fighting (ARFF) 84 Aeronautical
Environment, health & Safety (EHS) 6 Aeronautical
Landside Ops 4 Aeronautical
Technical Services 35 Aeronautical
Security & Vigilance 73 Aeronautical
Terminal operation and customer facility (TOPS & CFL) 27 Aeronautical
Quality & Service Delivery 3 Aeronautical
Total Employees 376
8.1.7 To calculate the initial manpower cost, GIAL, Mopa, Goa has multiplied the headcount with the average cost.
The initial cost is then adjusted for inflation, real growth, and expansion triggers as mentioned in para 8.1.2.
Admin and General Expenses
8.1.8 The basis adopted by GIAL, Mopa, Goa for forecasting Admin and General expenses for the First Control
Period in the MYTP submission are as follows:
Table 82: Breakup and basis of Admin and General expenses as submitted by GIAL, Mopa, Goa
Sl No Particulars Expense basis
The property tax rate for Manohar International Airport, Mopa, Goa has been
determined according to the provisions outlined in the Goa Panchayat Raj Act
1 Rates & Taxes
(Goa Act No. 14 of 1994). Additionally, an extra increase has been factored into
account for the expansion of the terminal building during Phase III.
GIAL, Mopa, Goa has received support from GAL (the Group Company) in areas
like strategic finance, funding, legal matters and more. GAL has appointed a
Corporate Cost consultant (Deloitte) to develop an allocation framework for expense distribution.
2
Allocation Based on revenue drivers or Gross Block ratios, GAL’s corporate costs allocated
to GIAL, Mopa, Goa has been estimated to be Rs. 7.5 crores for FY 2023-24,
with expected inflationary increases in the future.
CSR spending is calculated in accordance with the regulation i.e., 2% of last 3-
3 CSR
years PBT including cross subsidized non-aeronautical revenue.
As per Article 9 of the Concession Agreement, GIAL, Mopa, Goa is required to
4 Bank Charges maintain a performance bank guarantee (PBG) with the concessioning authority.
The PBG held by GIAL, Mopa, Goa amounts to Rs. 62 crores, with an annual fee
Consultation Paper No. 11/2023-24 Page 93 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Sl No Particulars Expense basis
of Rs. 0.60 crores. The remaining Rs. 0.40 crores has been estimated as other
bank fees relating to the loan.
Estimated based on department wise cost for the initial year and thereafter
5 Consultancy & Legal
escalated by inflation.
The estimated average cost per passenger is derived from benchmarking the costs
of two airports, HIAL and BIAL, and then adding an additional amount of Rs.1
6 Travel
crore for travel expenses related to initial business development. This estimated
cost is further escalated with inflation and an expansion factor.
7 Auditor & Director Fee Estimated Rs. 50 Lacs for 1st year; thereafter escalated by inflation.
GIAL, Mopa, Goa estimated advertisement cost taking into account the expected
8 Advertisement expenses and considered inflationary escalation from FY 2024-25 to FY 2027-
28.
Includes vehicle hire charges, miscellaneous expenses & general admin expenses.
9 Office Maintenance etc. Cost is estimated taking into account the expected expenses and thereafter
increased by inflation and pax growth.
Utility Expense
8.1.9 GIAL, Mopa, Goa estimated the utility costs for power and water consumption at a gross level, subtracting
recovery from airlines and concessionaires. Based on internal assessment, the power cost is estimated based
on a procurement cost of Rs. 7.33 per kWh for variable costs and Rs. 250 per Kva / month for fixed costs. A
5 MW solar project is planned to meet a significant portion of the energy requirements at a cost of Rs. 4 per
kWh.
8.1.10 For water consumption, GIAL, Mopa, Goa has an agreement with the water resource department guaranteeing
a minimum uptake of 1,700 cubic meters per day, with a rate of Rs. 20 per MLD. The initial cost is then
adjusted with inflation and pax growth from FY 2024-25 to FY 2027-28.
Operating Expense
a) Repairs and Maintenance
8.1.11 GIAL, Mopa, Goa has awarded the contract for repair and maintenance through a tendering process for the
maintenance of existing facilities except for the IT facilities. The cost based on the contract has been
considered for FY 2023-24. For further years of the First Control Period, GIAL, Mopa, Goa has used the
existing contract as a benchmark and escalated with an increase in capacity from 7.7 MPPA to 11.1 MPPA
i.e. Phase III expansion in order to forecast future costs.
b) IT related expenditure
8.1.12 In order to run the airport efficiently, GIAL, Mopa, Goa has outsourced all of its current and future IT
requirements to a specialized service provider to carry out all the capex and O&M expenses towards
Information and Communication Technology (ICT) services. In terms of the contract, GIAL, Mopa, Goa will
provide subsistence level support to IT concessionaire till the time Manohar International Airport, Mopa, Goa
achieves 6.6 Mn traffic for any financial year. After achieving the trigger traffic, the concessionaire will be
on revenue share at the rate of 3.25% of gross revenue it earns. The expected revenue share from the IT
concessionaire and subsistence level support are as follows:
Consultation Paper No. 11/2023-24 Page 94 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Table 83: Details of IT service contract
(Rs. in crores)
Particulars FY24 FY25 FY26 FY27 FY28
Contractual Payouts (A) 33.26 0.00 0.00 0.00 0.00
Estimated Revenue
CUTE (B) 28.05 32.00 39.12 48.04 54.27
Non-CUTE (C) 4.83 5.60 6.19 6.89 9.21
Cost to Manohar International Airport, Mopa, Goa
-0.36 0.00 0.00 0.00 0.00
(D=C+B-A)
Revenue Share to Manohar International Airport,
0.04 1.22 1.47 1.79 2.06
Mopa, Goa (E)
c) Enterprise IT
8.1.13 GIAL, Mopa, Goa estimated enterprise related IT expenses (includes network in corporate offices, MS office
licenses, Corporate IT solutions and support etc.) to be Rs. 2.27 crores for FY 2022-23 and Rs. 3.89 crores
for FY 2023-24 and considered inflationary increase and expansion factor thereon for the future years.
d) Other Operating Expenses
8.1.14 The basis for forecasting other Operating expenses by GIAL, Mopa, Goa in its MYTP submission are as
follows:
Table 84: Basis for Operating Expense as submitted by GIAL, Mopa, Goa
Sl No Particulars Expense basis
Housekeeping Considered the cost based on the awarded contract of housekeeping for FY 2023-24
1
expense and further increased with inflation and the area increase.
Estimated the cost of its insurance policies to be Rs. 2.65 crores based on the annual
premium. This cost is further adjusted with inflation for the remaining years of the
2 Insurance
First Control Period. Additionally, anticipated a one-time increase of 25% in insurance
premiums due to the potential rise in premiums related to airports.
Considered the cost based on the awarded contract to M/s RAXA for deploying the
3 Security expense security personnel for security related services apart from the CISF security personnels
and further escalated based on the pax growth.
Includes expenses in relation to EHS, trolley management, other Airside O&M, lease
4 Misc. expenses rental of equipment, UDF collection charges etc. which are estimated based on the
actual contract cost and best available estimates.
Airport Operator Fee
8.1.15 GIAL, Mopa, Goa estimated Airport operator fee of 3% based on the previous year revenue to be paid to the
Airport Operator who will provide support in airport operation as well as maintenance and bring in relevant
experience and advise to support airport operations.
Classification and Allocation of O&M expenses
8.1.16 GIAL, Mopa, Goa has categorized and assigned its O&M expenses into Aeronautical, Non-aeronautical, and
Common categories as presented below:
Consultation Paper No. 11/2023-24 Page 95 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Table 85: Classification and Allocation of O&M expenses submitted by GIAL, Mopa, Goa for the First
Control Period
Expense Non-
Particulars Allocation basis Aeronautical
Classification aeronautical
Employee Head Count
Manpower Common 94.41% 5.59%
Ratio
Admin and General
Expenses
Rate & Taxes Common Area allocation ratio 91.95% 8.05%
Employee Head Count
Corporate Allocation Cost Common 94.41% 5.59%
Ratio
CSR Aeronautical - 100.00% 0.00%
Bank charges Common Gross Block ratio 97.56% 2.44%
Consultancy & Legal Common Gross Block ratio 97.56% 2.44%
Employee Head Count
Travel Common 94.41% 5.59%
Ratio
Advertisement Common Terminal Building Ratio 91.03% 8.97%
Auditor & Director fee Common Gross Block ratio 97.56% 2.44%
Office Maintenance etc. Common Gross Block ratio 97.56% 2.44%
Utility Expenses Aeronautical - 100.00% 0.00%
Operating Expense
Repairs & Maintenance Common Gross Block ratio 97.56% 2.44%
IT cost-Airport operations Common Gross Block ratio 97.56% 2.44%
Enterprise IT Common Gross Block ratio 97.56% 2.44%
Housekeeping Common Terminal Building Ratio 91.03% 8.97%
Insurance Common Gross Block ratio 97.56% 2.44%
Security expense Common Terminal Building Ratio 91.03% 8.97%
Misc. expenses Common Gross Block ratio 97.56% 2.44%
AO fees Aeronautical - 100.00% 0.00%
8.1.17 Based on the above assumptions, GIAL, Mopa, Goa has submitted the following aeronautical Operating and
Maintenance expenses for the First Control Period:
Table 86: GIAL, Mopa, Goa’s submission of Aeronautical Operating and Maintenance expenditure
for the First Control Period
(Rs. in crores)
Particulars FY24 FY25 FY26 FY27 FY28 Total
Manpower Expense (A) 63.99 71.90 98.61 110.79 124.47 469.75
Admin and General Expenses
Rates & Taxes 1.63 1.71 2.40 2.52 2.65 10.91
Corporate cost allocation 7.08 7.44 7.81 8.20 8.61 39.13
CSR - - 0.30 3.24 6.61 10.15
Bank Charges 0.98 1.02 1.08 1.13 1.19 5.39
Consultancy & Legal 18.52 19.45 20.42 21.44 22.51 102.33
Travel 3.66 1.47 1.89 1.98 2.08 11.09
Advertisement 12.42 13.04 13.69 14.38 15.10 68.63
Consultation Paper No. 11/2023-24 Page 96 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Particulars FY24 FY25 FY26 FY27 FY28 Total
Auditor & Director Fee 0.51 0.54 0.56 0.59 0.62 2.83
Office Maintenance etc. 14.28 17.11 21.97 28.32 33.60 115.27
Total Admin and General Expenses (B) 59.07 61.78 70.12 81.81 92.96 365.73
Utility Expense
Electricity 37.69 39.43 49.72 52.06 54.53 233.42
Water 1.24 1.49 1.91 2.46 2.92 10.02
Total Utility Expense (C) 38.93 40.92 51.63 54.53 57.45 243.44
Operating Expenses
Repair and Maintenance 38.98 42.68 50.02 77.44 82.82 291.94
IT Operation related 0.35 - - - - 0.35
Enterprise IT 3.80 3.99 5.11 5.37 5.63 23.89
Housekeeping expense 12.38 12.62 17.21 17.60 18.03 77.84
Insurance 3.63 3.83 4.63 4.89 5.16 22.14
Security expense 12.71 15.59 20.04 25.11 28.84 102.29
Misc. expense 33.18 35.87 39.79 45.76 48.85 203.45
Total Operating Expenses (D) 105.03 114.58 136.80 176.16 189.34 721.91
Airport Operator Fee (E) 0.59 16.79 31.97 40.99 52.82 143.16
Total Aeronautical O&M expenses
267.62 305.96 389.12 464.26 517.03 1,944.00
(A)+(B)+(C)+(D)+(E)
8.2 Authority’s examination regarding Operating and Maintenance Expenses for the First Control
Period
8.2.1 The Authority has examined the basis and estimation of O&M expenses submitted by GIAL, Mopa, Goa for
the First Control Period. The Authority notes that GIAL, Mopa, Goa has analyzed O&M expenses considering
infrastructure requirements, personnel costs, equipment maintenance, utilities, security measures and other
costs. The Authority has conducted a detailed analysis of O&M expenses submitted by GIAL, Mopa, Goa in
the following order:
I. Allocation ratios
II. Examination of O&M expenses and its allocation into aeronautical and non-aeronautical expenses
I. Allocation Ratios
8.2.2 The following ratios have been analyzed and recomputed by the Authority for appropriate segregation of
Common expenses between Aeronautical and Non-aeronautical for First Control Period.
Terminal Building ratio
8.2.3 The Authority observed that GIAL, Mopa, Goa has considered the terminal building ratio of 91.03%:8.97%
based on the usage of area towards aeronautical and non-aeronautical activities considering 6,075 sqm as
non-aero area out of total terminal area of 67,726 sqm.
8.2.4 The Authority examined in detail the Terminal Building ratio submitted by GIAL, Mopa, Goa in Chapter 5
of this Consultation Paper. The Authority proposes to consider Terminal Building Ratio of 90%:10% for the
First Control Period (Refer para 5.4.6 for detailed explanation).
Consultation Paper No. 11/2023-24 Page 97 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Gross Block ratio
8.2.5 The Authority notes that GIAL, Mopa, Goa has calculated the Gross Block ratio based on the classification
of Gross Block of Assets capitalized for Phase I. Furthermore, the Authority observes that GIAL, Mopa, Goa
has maintained the same Gross Block ratio throughout the entirety of the First Control Period, without
revising it despite the capitalization of assets taking place each year during this period. The Authority, based
on the proposed capital expenditure in Table 64 & Table 68, proposes the Gross Block ratio for the First
Control Period as presented in the table below.
Table 87: Gross Block ratio proposed by the Authority for the First Control Period
(Rs. in crores)
Particulars FY24 FY25 FY26 FY27 FY28 Total
Aeronautical Gross Block
Opening Gross Block (A) 2,507.92 3,265.03 3,274.03 3,686.76 3,695.76
Addition (B) (Table 68) 757.11 9.00 412.73 9.00 9.00 1,196.84
Sales/Transfers/Disposals (C) - - - - -
Closing of Aeronautical Gross Block
3,265.03 3,274.03 3,686.76 3,695.76 3,704.76
(D=A+B-C)
Total Gross Block
Opening Gross Block (E) 2,620.74 3,415.07 3,425.07 3,876.20 3,886.20
Addition (F) (Table 64) 794.33 10.00 451.14 10.00 10.00 1,275.47
Sales/Transfers/Disposals (G) - - - - -
Closing of Total Gross Block
3,415.07 3,425.07 3,876.20 3,886.20 3,896.20
(H=E+F-G)
Aeronautical Gross Block Percentage
95.61% 95.59% 95.11% 95.10% 95.09%
(I=D ÷H)
Average of 5 year-Aeronautical
95.30%
Gross Block Ratio
Employee Head Count Ratio (EHCR)
EHCR submitted by GIAL, Mopa, Goa
8.2.6 The Authority has reviewed the submission made by GIAL, Mopa, Goa and observed that GIAL, Mopa, Goa
has submitted Employee Head Count ratio of 94.41%:5.59% (Aeronautical: Non-Aeronautical) based on the
nature of services provided by each department, segregated as aero, non-aero, or common.
Actual Employee Head Count & Expansion Factors
8.2.7 The Authority notes that GIAL, Mopa, Goa, in response to the query, has provided the actual head count of
employees working at Manohar International Airport, Mopa, Goa for the month of March 2023 department-
wise. Upon reviewing, the Authority notes that using the actual head count figures will offer an accurate
representation of the current number of employees and facilitate assessment of manpower expenses.
Therefore, the Authority proposes to adopt the actual head count data from March 2023 as the base for
assessing the Employee Head Count of the First Control Period for Manohar International Airport, Mopa,
Goa.
Consultation Paper No. 11/2023-24 Page 98 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Classification of Employees
8.2.8 After examining the functions of each department, the Authority has determined that the duties of employees
listed below extend beyond aeronautical activities and encompass the overall operations of the airport. As a
result, the Authority proposes reclassification of these departments as Common:
1. CDO’s Office
2. COO’s Office
3. Security Vigilance
8.2.9 Therefore, based on the above analysis, the Authority has recalculated the Employee Head Count Ratio
(EHCR) as presented below and proposes a revised ratio of 95.73% : 4.27% (Aeronautical: Non-
Aeronautical) for the allocation of expenses in the First Control Period.
Table 88: Employee Head Count Ratio proposed by the Authority for the First Control Period
Department Classification FY23
CEO's/ Dy. CEO's Office Common 3
CDO's Office Common 2
Planning & Business Intelligence Common 2
Commercial & Business Development Non-Aero 7
Finance & Secretarial Common 10
Procurement & Contracts Common 5
Human Resources & Flight Management System Common 9
Project support function Common 15
Corporate relation & Corp.Com.& Connectivity Common 13
Legal Common 2
Management Assurance Group (MAG) Common 2
CSR Common 1
IT Common 3
Ethics & Intelligence Common 1
COO's Office Common 2
Airside Ops Aero 23
AOCC Aero 20
ARFF Aero 81
EHS Aero 5
Security & Vigil. Common 88
Terminal operation and customer facility (TOPS & CFL) Aero 30
Quality & Service Delivery Aero 1
Passenger Exp Aero 3
Total 328
Employee Head Count
Aero 163
Non-Aero 7
Common 158
Common Employees to Aero & Non-Aero
Aero 151
Non-Aero 7
Total Employee Head Count
Consultation Paper No. 11/2023-24 Page 99 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Department Classification FY23
Aero 314
Non-Aero 14
Employee Head Count ratio (Aero : Non-Aero)
Aero 95.73%
Non-Aero 4.27%
Summary of Allocation Ratios proposed by the Authority for the First Control Period
8.2.10 The Allocation ratios proposed by the Authority for Manohar International Airport, Mopa, Goa for the First
Control Period are as follows:
Table 89: Allocation Ratios proposed by the Authority for the First Control Period
Particulars FY24 FY25 FY26 FY27 FY28
TBLR (para 5.4.6) 90.00% 90.00% 90.00% 90.00% 90.00%
Gross Block Ratio (Table 87) 95.30% 95.30% 95.30% 95.30% 95.30%
EHCR (Table 88) 95.73% 95.73% 95.73% 95.73% 95.73%
Classification and Allocation of O&M expenses
8.2.11 The Authority has classified and assigned the projected O&M expenses into three distinct categories:
Aeronautical, Non-aeronautical, and Common. Further, the common expenses have been allocated into
aeronautical and non-aeronautical categories, based on the established methodology followed by the
Authority across all airports. Presented below is the table illustrating the classification and allocation of O&M
expenses proposed by the Authority in the subsequent paragraphs, into the aeronautical and non-aeronautical
segments for the First Control Period:
Table 90: Classification and Allocation of O&M expenses proposed by the Authority for the First
Control Period
Expense Non-
Particulars Allocation basis Aeronautical
Classification aeronautical
Employee Head Count
Manpower Common 95.73% 4.27%
Ratio
Admin and General
Expenses
Area allocation ratio (Table
Rate & Taxes Common 90.92% 9.08%
95)
Employee Head Count
Corporate Allocation Cost Common 95.73% 4.27%
Ratio
CSR Aeronautical - 100.00% 0.00%
Bank charges Common Gross Block Asset ratio 95.30% 4.70%
Consultancy & Legal Common Gross Block Asset ratio 95.30% 4.70%
Employee Head Count
Travel Common 95.73% 4.27%
Ratio
Advertisement Common Terminal Building Ratio 90.00% 10.00%
Auditor & Director fee Common Gross Block Asset ratio 95.30% 4.70%
Consultation Paper No. 11/2023-24 Page 100 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Expense Non-
Particulars Allocation basis Aeronautical
Classification aeronautical
Office Maintenance etc. Common Gross Block Asset ratio 95.30% 4.70%
After Net recoveries from
Utility Expenses Aeronautical the Non-Aeronautical 100.00% 0.00%
Concessionaire
Operating Expense
Repairs & Maintenance Common Gross Block Asset ratio 95.30% 4.70%
IT cost-Airport operations Common Gross Block Asset ratio 95.30% 4.70%
Enterprise IT Common Gross Block Asset ratio 95.30% 4.70%
Housekeeping expense Common Terminal Building Ratio 90.00% 10.00%
Insurance Common Gross Block Asset ratio 95.30% 4.70%
Security expense Common Terminal Building Ratio 90.00% 10.00%
Misc. expenses
a. EHS Aeronautical - 100.00% 0.00%
b. Trolley Management Aeronautical - 100.00% 0.00%
c. Other Airside O&M Aeronautical - 100.00% 0.00%
d. Lease Rental Common Gross Block Asset ratio 95.30% 4.70%
e. UDF Collection Charges Aeronautical - 100.00% 0.00%
f. Other Tops Common Terminal Building Ratio 90.00% 10.00%
g. Other Misc. Expenses Common Terminal Building Ratio 90.00% 10.00%
AO fees - - - -
II. Examination of O&M expenses and its allocation into aeronautical and non-aeronautical expenses
8.2.12 The Authority has carefully examined GIAL, Mopa, Goa submission regarding various O&M expenses for
the First Control Period. The Authority in the following paragraphs presents its analysis of each expense
category and its corresponding allocation, organized in the following sequence:
a) Inflationary Increase
b) Expansion Increase
c) Manpower Expense and its allocation
d) Admin and General Expense and its allocation
e) Utility Expense and its allocation
f) Operating Expense and its allocation
g) Airport Operator Fee
Inflationary Increase
8.2.13 The Authority, on examination of the submission made by GIAL, Mopa, Goa, notes that WPI inflation of 5%
has been considered towards all expenses. However, the Authority in its analysis detailed in Chapter 7,
proposes to consider WPI inflation of 4% Y-o-Y published in the results of the 82nd round of the Survey of
Professional Forecasters on Macroeconomic Indicators released on 8th June 2023.
Consultation Paper No. 11/2023-24 Page 101 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Expansion Increase
8.2.14 The Authority notes that GIAL, Mopa, Goa in its submission has projected various expenses by considering
an incremental factor of 10% in FY 2023-24 and 22% in FY 2025-26. These increments were attributed to
the capacity expansion in Phase II and Phase III, respectively. Upon analysing, the Authority notes that a
more accurate representation of the impact of infrastructure development on expenses would be achieved by
considering the increase in terminal building area instead of just capacity. Thus, the Authority proposes to
use the area expansion in Phase II and III as the incremental factor.
The Authority also recognizes that the increase in expenses may not be directly proportional to the increase
in the Terminal Building area due to factors such as technological innovations, advancements, and economies
of scale. Hence, the Authority proposes to consider 2/3rd (66.67%) of the area increase i.e. 7% in FY 2023-
24 and 25% in FY 2025-26 as computed below as expansion increase while projecting expenses for the First
Control Period.
Table 91: Expansion Increase % proposed by the Authority for the First Control Period
Particulars Reference Amount
Phase-II Expansion Growth
Cost of Terminal Building (Rs in Cr)
Phase – I A 637.46
Phase – II B 69.65
Increase from Phase – I C=B/A 11%
Phase-II Expansion Growth D=C*2/3 7%
Phase-III Expansion Growth
Terminal Area (In Sqm)
Phase – II E 67,726
Phase – III F 92,726
Increase from Phase – II G=(F/E)-1 37%
Phase-III Expansion Growth H=G*2/3 25%
In respect of Manpower expenses, the Authority notes that GIAL, Mopa, Goa has claimed 22% expansion
increase in FY 2025-26 which the Authority finds to be reasonable and justified. Hence, the Authority
proposes to allow the same.
Manpower Expenses
8.2.15 The Authority notes that GIAL, Mopa, Goa has provided a weighted average employee cost of Rs. 14.16 lakh
per annum for FY 2022-23, with a projected annual increase of 7% Y-o-Y for the years of the First Control
Period. This average cost includes the salary expenses of all departments (refer to Table 81) and encompasses
various grades, starting from the highest managerial grade M1 to A5 level.
8.2.16 The Authority observes that GIAL, Mopa, Goa has taken into account the salaries of employees across
different roles and levels within the organization, resulting in a representative figure for the average cost. The
Authority is of the view that the average cost proposed by GIAL, Mopa, Goa covers all the grades of
employees. Therefore, the Authority proposes to accept the weighted average employee salary cost of Rs.
14.16 lakh per annum. However, aligning with the uniform approach taken for Manpower Expenses, the
Consultation Paper No. 11/2023-24 Page 102 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Authority proposes to rationalize the growth rate to 6% year-on-year for all years of the First Control Period,
starting from FY 2023-24.
8.2.17 Further, the Authority observes that GIAL, Mopa, Goa has factored in, the capacity expansion of 10% for
Phase II in FY 2023-24 and 22% for Phase III in FY 2025-26 and an inflation increase of 5% Y-o-Y starting
from FY 2023-24 onwards into the calculation of employee cost. The Authority after analysing the same,
proposes the following adjustments:
• To not consider the inflationary increase, as 6% growth rate has already been proposed.
• To consider area expansion of Phase II and Phase III, by 7% in FY 2023-24 and 22% in FY 2025-26
respectively (refer para 8.2.14 and Table 91) as the expansion of the facility comes with the challenge of
accommodating the corresponding increase in operations requiring additional manpower.
8.2.18 Additionally, the Authority notes that GIAL, Mopa, Goa in its calculation of manpower expenses considered
staff welfare expenses at the rate of 3% of employee cost. The Authority notes this to be reasonable. Thus,
the Authority proposes to consider staff welfare expenses at the rate of 3% on the employee cost proposed by
the Authority in para 8.2.16 and 8.2.17.
8.2.19 Taking the above factors into consideration, the Authority proposes the following manpower expenses for the
First Control Period:
Table 92: Manpower Expenses proposed by the Authority for the First Control Period
(Rs. in crores)
Particulars FY 24 FY 25 FY 26 FY 27 FY 28 Total
Manpower Expenses 54.26 57.52 74.38 78.85 83.58 348.58
Allocation of Manpower Expenses
8.2.20 The Authority, taking into the account the EHCR as presented in Table 88, proposes the following
aeronautical manpower expenses for determination of tariff of the First Control Period of Manohar
International Airport, Mopa, Goa.
Table 93: Aeronautical Manpower Expenses proposed by the Authority for the First Control Period
(Rs. in crores)
Particulars FY 24 FY 25 FY 26 FY 27 FY 28 Total
Manpower Expenses 51.95 55.06 71.21 75.48 80.01 333.71
Admin and General Expenses
8.2.21 The Authority notes that GIAL, Mopa, Goa has estimated Admin and General expenses for the First Control
Period of Rs. 382.07 crores and has provided the basis for each component of Admin and General expense
which is presented in Table 82. The Authority has analyzed each component of Admin and General expense
and proposes the Admin and General expense for the First Control Period as detailed below.
Consultation Paper No. 11/2023-24 Page 103 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Table 94:Admin and General expenses proposed by the Authority for the First Control Period
(Rs. in crores)
Particulars FY 24 FY 25 FY 26 FY 27 FY 28 Total Basis considered by the Authority
Proposes to consider the estimation base
provided by GIAL, Mopa, Goa for FY
2023-24. To account for inflation, an
annual increase of 4% (WPI) is applied
Rates & Taxes 1.78 1.85 2.40 2.50 2.60 11.12 for the remaining years of the First
Control Period. Furthermore, in FY
2025-26, 25% (Refer Table 91) increase
has been considered due to area
expansion.
The Authority has examined the
proposal for the allocation of Corporate
Cost amounting to Rs. 7.5 crores for FY
2023-24 submitted by GIAL, Mopa,
Goa. After careful consideration, the
Authority proposes to allow 50% of the
expense proposed by GIAL for FY
2023-24 as Corporate Cost allocation
and thereafter escalate with an
inflationary increase of 4% Y-o-Y for
the remaining years of the First Control
Period.
The proposal of Rs. 3.75 crores for FY
2023-24 is considered as a general
estimate due to the lack of detailed
computations or documentation
Corporate provided by GIAL, Mopa, Goa to
Cost 3.75 3.90 4.06 4.22 4.39 20.31 substantiate their submission. It is noted
Allocation that the study for allocation for
Corporate Cost was conducted by
Deloitte, for three group companies,
namely HIAL, DIAL and Manohar
International Airport, Mopa, Goa.
Despite continuous follow-ups till 6th
July 2023, GIAL, Mopa, Goa has failed
to provide a copy of the study conducted
by Deloitte and the basis for estimating
the expense. GIAL, Mopa, Goa
responded that the allocation has not
been finalized yet, as the current year
marks the first year of full operations
and the amount of Rs. 7.5 crores for FY
2023-24 is only an estimated figure that
may undergo finalization during the
year.
Consultation Paper No. 11/2023-24 Page 104 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Particulars FY 24 FY 25 FY 26 FY 27 FY 28 Total Basis considered by the Authority
The Authority expects that the
Corporate Cost allocation will be
towards efficiently spent expenditure,
backed by an appropriate methodology
of allocation.
CSR is estimated based on Aeronautical
P&L and the average of past 3 years’
profit.
CSR - - - - - - As this is dependent on the profitability
of the individual years of operation, the
same will be evaluated and trued up at
the time of next control period.
Proposes to consider the estimation base
provided by GIAL, Mopa, Goa for FY
2023-24 after excluding Rs.0.40 crores
which has been estimated by GIAL,
Mopa, Goa as other bank fees relating to
the term loan. This exclusion is
proposed because costs related to the
Bank Charges 0.60 0.62 0.65 0.67 0.70 3.25 term loan should be considered as part
of the Regulated Asset Base (RAB) and
not categorized as Operations &
Maintenance (O&M) expenses.
To account for inflation, an annual
increase of 4% (WPI) is applied for the
remaining years of the First Control
Period.
GIAL, Mopa, Goa vide email dated 7th
July 2023 provided detailed breakup of
Consultancy & legal charges estimated
for FY 2023-24. The Authority upon
detailed analysis of each head proposes
to consider Rs. 10.00 crores for FY
Consultancy
10.00 10.40 10.82 11.25 11.70 54.16 2023-24 (refer Annexure 2 for
and Legal
Authority’s observation and proposal
for each item). For the remaining period
of the First Control Period, it is
proposed to increase the estimates by
4% annually, in line with the inflation
rate (WPI) from FY 2024-25 onwards.
Consultation Paper No. 11/2023-24 Page 105 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Particulars FY 24 FY 25 FY 26 FY 27 FY 28 Total Basis considered by the Authority
Estimates made are based on
benchmarks from other airports. Initial
business development costs of Rs. 1
crore additional submitted by GIAL,
Mopa, Goa is not considered as the basis
Travel 1.97 2.05 2.13 2.22 2.30 10.67
and justification of the same was not
provided.
It is proposed to increase the estimates
by 4% annually, in line with the
inflation rate (WPI) from FY 2024-25.
Being a new airport, the Authority notes
the need for Advertisement costs in the
initial years. Accordingly, Rs. 8.50
Crores has been considered for FY
2023-24 together with an inflationary
increase for the next year.
However, Authority notes that, after the
initial period of two years, Manohar
Advertisement 8.50 8.84 4.60 4.78 4.97 31.69 International Airport, Mopa, Goa would
have had sufficient traction and hence
the cost of Advertising has been
rationalized by 50% from the next year
and estimated with the inflationary
increase.
The Authority urges GIAL, Mopa, Goa
to ensure efficient and optimal spend of
the same which will be reviewed in the
next control period.
Proposes to consider the estimation base
provided by GIAL, Mopa, Goa for FY
Auditor & 2023-24. To account for inflation, an
0.53 0.55 0.57 0.60 0.62 2.87
Director Fee annual increase of 4% (WPI) is applied
for the remaining years of the First
Control Period.
Consultation Paper No. 11/2023-24 Page 106 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Particulars FY 24 FY 25 FY 26 FY 27 FY 28 Total Basis considered by the Authority
For FY 2023-24, the Authority has
assessed the actual data submitted by
GIAL, Mopa, Goa for the three months
starting from COD till 31st March 2023
of FY 2022-23. This data is extrapolated
to estimate the expenses for FY 2023-24
Office along with 7% increase due to area
Maintenance, expansion (refer Table 91).
17.55 18.25 23.73 24.67 25.66 109.86
Vehicle Furthermore, for the remaining period
charges etc. of the First Control Period, it is
proposed to increase the estimates by
4% annually, in line with the inflation
rate (WPI) from FY 2024-25 and
considering 25% (Refer Table 91)
increase due to area expansion in FY
2025-26.
Total Admin
and General 44.67 46.46 48.95 50.91 52.94 243.93
Expenses
Allocation of Admin and General Expenses
8.2.22 The Authority has examined the allocation of Admin and General costs into Aero and Non-Aero. The
following breakdown provides a detailed account of the classification and allocation of each component
within the Admin and General expense:
Rates & Taxes
8.2.23 The Authority notes GIAL, Mopa, Goa's classification of each area within the Manohar International Airport,
Mopa, Goa for the purpose of calculating aeronautical rates and taxes and dividing them into aero, non-aero,
and common categories. The Authority based on its analysis, reclassifies each area into aero, non-aero, and
common and thereafter allocates common costs into aero and non-aero. The table presents the reclassification
and reallocation of rates and taxes proposed by the Authority for both the First Control Period.
Table 95: Aeronautical Rates and Taxes for FY 2023-24 proposed by the Authority
(Rs. in crores)
Aero taxes
Aero
Classification Classification as per
Area in Property taxes as
Particulars as per GIAL, as per GIAL,
Sqm tax pa per
Mopa, Goa Authority Mopa,
Authority
Goa
Passenger Terminal Building Common Common
67,726 1.35 1.23 1.22
(PTB) BLOCK 1 (TBLR) (TBLR)
Air Traffic Control -
Technical Building (ATC - 2,250 0.04 Aero Aero 0.04 0.04
TB)
Consultation Paper No. 11/2023-24 Page 107 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Aero taxes
Aero
Classification Classification as per
Area in Property taxes as
Particulars as per GIAL, as per GIAL,
Sqm tax pa per
Mopa, Goa Authority Mopa,
Authority
Goa
Air Traffic Control - Tower
1,341 0.03 Aero Aero 0.03 0.03
(ATC-T)
Crash Rescue Fire Station -
952 0.02 Aero Aero 0.02 0.02
Main (CRFS-M)
Crash Rescue Fire Station -
311 0.01 Aero Aero 0.01 0.01
Satellite (CRFS-S)
Common
Utility Building 2,040 0.04 Aero 0.04 0.04
(TBLR)
AGL Sub Station 578 0.01 Aero Aero 0.01 0.01
Airport surveillance radar
416 0.01 Aero Aero 0.01 0.01
(ASR) MSSR
ASDC Buildings (ASDC, Common Common
486 0.01 0.01 0.01
Cafeteria & Workshop) (TBLR) (TBLR)
Common Common
Administrative Block 4,844 0.10 0.09 0.09
(TBLR) (TBLR)
Common Common
Cafeteria 1,023 0.02 0.02 0.02
(TBLR) (EHCR)
Airport Utility Common Common
1,226 0.02 0.02 0.02
(Accommodation Centre) (TBLR) (TBLR)
Airline Engineering and
Maintenance Building 989 0.02 Aero Aero 0.02 0.02
(AEMB) - Block
Doppler Very High
Frequency Omni Range 73 0.00 Aero Aero 0.00 0.00
(DVOR)
Gate House -01 68 0.00 Aero Aero 0.00 0.00
Sewage Treatment Plant Common Common
534 0.01 0.01 0.01
(STP) (TBLR) (Asset ratio)
Gate House -02 68 0.00 Aero Aero 0.00 0.00
Gilde Path 25 0.00 Aero Aero 0.00 0.00
Localizer 25 0.00 Aero Aero 0.00 0.00
Common Common
Main Water Tank 2,012 0.04 0.04 0.04
(TBLR) (Asset ratio)
Common Common
MRSS Block 1,805 0.04 0.03 0.03
(TBLR) (TBLR)
Total 88,793 1.78 1.63 1.61
8.2.24 Based on its analysis, the Authority notes that the allocation basis selected by GIAL, Mopa, Goa for the other
components of Admin and General expenses is reasonable. As a result, the Authority proposes adopting the
same allocation basis, taking into consideration the revised ratios calculated in para 8.2.1 (I) as mentioned
earlier.
Consultation Paper No. 11/2023-24 Page 108 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
8.2.25 Based on the aforementioned proposals, the Authority proposes the following aeronautical Admin and
General expenses for the First Control Period.
Table 96: Aeronautical Admin and General Expenses proposed by the Authority for the First Control
Period
(Rs. in crores)
Particulars FY24 FY25 FY26 FY27 FY28 Total
Rates & Taxes 1.61 1.68 2.19 2.27 2.36 10.12
Corporate cost allocation 3.59 3.73 3.88 4.04 4.20 19.44
CSR - - - - - -
Bank Charges 0.57 0.59 0.62 0.64 0.67 3.10
Consultancy and Legal 9.53 9.91 10.31 10.72 11.15 51.62
Travel 1.89 1.96 2.04 2.12 2.21 10.21
Advertisement 7.65 7.96 4.14 4.30 4.47 28.52
Auditor & Director Fee 0.51 0.53 0.55 0.57 0.59 2.74
Office Maintenance etc. 16.72 17.39 22.61 23.51 24.46 104.70
Total Aeronautical Admin and General Expenses 42.07 43.76 46.33 48.18 50.11 230.44
Utility Expense
Power Cost
8.2.26 The Authority notes that GIA, Mopa, Goa has projected the power costs, factoring in the recoveries received
from the Concessionaires, which are estimated to be an average of 24% of the total power cost. This recovery
percentage is determined by considering a 20% recovery on the total units of power consumed and another
20% recovery on the Per unit rate of power from the concessionaires.
Upon careful assessment, the Authority finds this recovery percentage to be reasonable when compared to
other airports in the region. However, the Authority notes that as GIAL, Mopa, Goa gradually expands its
Non-aeronautical operations, it should also proportionately increase the power recovery.
8.2.27 The Authority notes that GIAL, Mopa, Goa has estimated a power consumption of 5.23 crores kilowatt-hours
(KWH) with a procurement cost of Rs. 7.69 per kWh (increased from Rs. 7.33 per kWh for FY 2022-23,
accounting for a 5% inflation) and fixed costs of Rs.250 per Kva/month for FY 2023-24. The Authority’s
analysis on the same is as follows:
• Units Consumption: The Authority, after reviewing the actual bills for the months of April 2023 and
May 2023, noticed that the consumption of power units for a single month amounted to approximately
14.68 lakhs units. Extrapolating this figure, it is estimated that the total consumption for the entire year
would be around 1.7 crores units.
Considering that Manohar International Airport, Mopa, Goa has recently initiated operations for domestic
traffic and is yet to commence international traffic in July 2023, it is expected that the power unit
consumption will increase in the future. Hence, the Authority proposes to consider double of the units
calculated as above, i.e., 1.7 crores units, for FY 2023-24. Consequently, the Authority proposes
considering the consumption at approximately 3.50 crores units for FY 2023-24, together with a 25%
increase (as shown in Table 91), due to the anticipated area expansion in FY 2025-26.
Consultation Paper No. 11/2023-24 Page 109 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
• Procurement Cost: GIAL, Mopa, Goa has provided the procurement cost of Rs. 7.33 per kWh and fixed
costs of Rs. 250 per Kva/month based on the actual bill issued by the Electricity Department of the
Government of Goa on 13th February 2023. However, the Authority considering the latest bill i.e. May
2023 proposes to consider average rate of Rs. 6.98 per kWh and fixed costs of Rs. 250 per Kva/month
for FY 2023-24. For the remaining years of the First Control Period of Manohar International Airport,
Mopa, Goa, an annual inflationary increase of 4% (WPI) will be applied to the power charges.
8.2.28 Additionally, GIAL, Mopa, Goa has installed a 5 MW Solar project on a Build-Own-Operate-Transfer
(BOOT) basis. The project aims to meet 7 million kWh of the airport's energy requirement, with an assumed
cost of Rs. 4 per kWh. The Authority has reviewed GIAL, Mopa, Goa's cost estimation for the solar project
and finds it reasonable. Therefore, the Authority proposes to consider this cost estimation and adjust the 7
million kWh of energy generated from solar power from the total unit consumption mentioned in para 8.2.27
above.
8.2.29 Taking into account all the factors discussed above, the Authority proposes the power cost for the First
Control Period as follows:
Table 97: Power Charges proposed by the Authority for the First Control Period
(Rs. in crores)
Particulars Reference FY 24 FY 25 FY 26 FY 27 FY 28 Total
Energy unit in Mus A 35.01 35.01 43.76 43.76 43.76 201.30
Solar Mus B 7.00 7.00 7.00 7.00 7.00 35.00
Grid in KWH C=A-B 28.01 28.01 36.76 36.76 36.76 166.30
Per unit cost D 6.98 7.26 7.55 7.85 8.16
Grid Variable cost E=CxD/10 19.54 20.33 27.74 28.85 30.01 126.48
Grid Fixed cost F 1.42 1.47 1.92 1.99 2.07 8.87
Solar Power cost G 2.80 2.80 2.80 2.80 2.80 14.00
Total Electricity Cost H=E+F+G 23.76 24.60 32.46 33.65 34.88 149.35
Expected recovery I 4.69 4.88 6.66 6.92 7.20 30.35
Net Electricity Cost
J=H-I 19.07 19.72 25.80 26.72 27.68 118.99
(Aeronautical)
Water Charges
8.2.30 The Authority notes that the water charges are based on the agreement with the water resource department of
Goa which is fixed in terms of rate and the minimum water intake for FY 2023-24. The Authority proposes
to adopt GIAL, Mopa, Goa's estimation for FY 2023-24 as the basis for water charges. For the subsequent
years of the First Control Period, the Authority proposes applying a 4% inflationary increase to the water
charges and adjusting the water intake based on the growth in airport traffic.
8.2.31 Further, the Authority notes that GIAL, Mopa, Goa has not considered recovery for water usage from the
concessionaires. Upon seeking clarification, GIAL, Mopa, Goa informed that the water consumption is
intended to be net of recoveries; however, it has inadvertently not been netted off from the expenses in the
Consultation Paper No. 11/2023-24 Page 110 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
model and requested to consider the same recovery % used for electricity. Thus, the Authority proposes to
consider 24% of the total water cost as recoveries from the concessionaires.
8.2.32 Taking the above factors into consideration, the Authority proposes the following Utility expenses for First
Control Period:
Table 98: Total Utility Expenses proposed by the Authority for the First Control Period
(Rs. in crores)
Particulars FY24 FY25 FY26 FY27 FY28 Total
Electricity Cost 23.76 24.60 32.46 33.65 34.88 149.35
Water Cost 1.24 1.47 1.87 2.39 2.81 9.78
Total Utility Expense 25.00 26.07 34.33 36.04 37.69 159.13
Allocation of Utility Expenses
8.2.33 In line with the discussion in para 8.2.26 and 8.2.31, the power and water charges has been considered as
Aeronautical after making adjustments in recoveries from the concessionaires. Taking into account the
recoveries from the concessionaires as adjustments from power and water charges, the Authority proposes to
consider the following aeronautical utility expenses for the First Control Period.
Table 99: Aeronautical Utility Expenses proposed by the Authority for the First Control Period
(Rs. in crores)
Particulars FY24 FY25 FY26 FY27 FY28 Total
Electricity Cost 19.07 19.72 25.80 26.72 27.68 118.99
Water Cost 0.94 1.12 1.42 1.82 2.14 7.44
Total Aeronautical Utility Expense 20.01 20.84 27.22 28.54 29.81 126.43
Operating Expense
a) Repairs and Maintenance (R&M)
8.2.34 The following paragraphs summarize the findings and proposals made by the Authority regarding R&M
expenses submitted by GIAL, Mopa, Goa for Manohar International Airport, Mopa, Goa:
• The Authority notes that GIAL, Mopa, Goa has entered into a engineering and maintenance contract with
a related party through a tendering process. The Authority has sought confirmation from GIAL, Mopa,
Goa that due process as mentioned in para 2.5.7 has been followed as per appropriate governance practices
and that Probity audit reports have been submitted to GoG and approved by GoG. GIAL, Mopa, Goa has
confirmed the same.
• The Authority analysed the percentage of R&M expenses in relation to the net block of assets for each
tariff year, as submitted by GIAL, Mopa, Goa. The Authority observed that GIAL, Mopa, Goa's estimated
R&M costs for the First Control Period fall in the range of 1.13% to 2.30% of the net block of assets. It is
important to note that Manohar International Airport, Mopa, Goa is a newly constructed greenfield airport,
hence, it will initially incur significant capital expenditure costs and will require minimal repairs and
maintenance.
• GIAL, Mopa, Goa's contract for R&M expenses indicates that the airport facilities are covered under the
defect liability period of two years from the EPC contractor and other project vendors. For monitoring that
defect liability period is properly complied, the contract provides responsibility to the contractor. Along
Consultation Paper No. 11/2023-24 Page 111 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
with this, the contractor will be responsible for carrying out the necessary engineering and maintenance
services to ensure the operational functionality of Manohar International Airport, Mopa, Goa from the
Commercial Operation Date (COD).
• The Authority is of the view that Manohar International Airport, Mopa, Goa is a newly constructed
infrastructure with several advantages, including guarantees, warranties, and a two-year defect liability
period. However, certain operational and maintenance related expenses would be incurred to ensure
smooth running of operation.
• Taking into account the benefits provided by guarantees, warranties, and the two-year defect liability
period, the Authority proposes a revised approach for considering the Repair and Maintenance (R&M)
expenses for the initial two years. Specifically, the proposed amounts for FY 2023-24 and FY 2024-25 are
considered at Rs. 15 crores and Rs. 20 crores respectively. Thereafter, the R&M expenses will be
considered at 70% of the expenses submitted by GIAL, Mopa, Goa for the subsequent years, noting that
the values of Repair and Maintenance costs proposed by GIAL, Mopa, Goa as high and that it may take
another couple of years in the control period for the operations at the airport to stabilize. By adopting this
approach, the Authority aims to strike a fair balance between recognizing the advantages of the initial
warranty and defect liability period while still accounting for the ongoing operational and maintenance
requirements of the airport in the years to come. These will be reviewed at the time of true up to evaluate
the reasonableness and optimum level of R&M costs, once the operations at the airport stabilize.
b) IT related expenditure
8.2.35 The Authority has taken note that GIAL, Mopa, Goa has awarded the license agreement for IT Services at
Manohar International Airport, Mopa, Goa through an e-tendering process. As per the agreement, upon COD
and until the Revenue Share Trigger Date, which is the date when the passenger traffic at the airport reaches
6.6 million, GIAL, Mopa, Goa has committed to providing subsistence level support to the IT concessionaire.
8.2.36 As part of this support, GIAL, Mopa, Goa will reimburse the IT concessionaire for the capital expenditure
and operational expenditure incurred in providing the necessary IT assets, IT works, and IT services to GIAL,
Mopa, Goa. The reimbursement will be calculated on a pro rata basis using the following formula:
“WACC return on Capex Incurred + Depreciation + Opex + 20% margin on Opex”
8.2.37 After the Revenue Share Trigger Date, GIAL, Mopa, Goa will receive a revenue share of 3.25% of the gross
revenue, which includes the revenue generated from both Common Use Terminal Equipment (CUTE) and
non-CUTE services.
8.2.38 GIAL, Mopa, Goa in its submission, has estimated the subsistence level support cost based on the values for
capital and operational expenditure obtained from the IT concessionaire's records. The Authority has also
observed that the estimated Revenue Share Trigger Date provided by GIAL, Mopa, Goa aligns with traffic
estimated by the Authority in Table 31 which is expected to be triggered in FY 2023-24.
8.2.39 Based on these considerations, the Authority notes that GIAL, Mopa, Goa's estimation of the IT-related cost
for subsistence level support and the revenue share calculation are reasonable. Therefore, the Authority
proposes to accept GIAL, Mopa, Goa's estimation for IT-related costs as part of O&M expenses (Refer Table
83) and the revenue generated from CUTE and non-CUTE services as part of the Aeronautical Income which
Consultation Paper No. 11/2023-24 Page 112 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
will be analyzed and discussed under Aeronautical Revenues after receiving the tariff rate card from GIAL,
Mopa, Goa during the Consultation Stage.
c) Enterprise IT
8.2.40 The Authority notes that GIAL, Mopa, Goa has estimated enterprise-related IT expenses for FY 2022-23 to
be Rs. 2.27 crores and Rs. 3.89 crores for FY 2023-24. These expenses encompass various aspects such as
network infrastructure in corporate offices, MS Office licenses, corporate IT solutions, and support.
The Authority is of the view that Enterprise IT is also important to meet the technological needs of the
organization, enhance productivity, and ensure efficient communication and collaboration. It includes
activities such as hardware and software maintenance, user support, system upgrades, and security measures.
However, as detailed basis of the expenditure was not submitted by GIAL, Mopa, Goa, the Authority proposes
to consider only 70% of the cost estimate submitted by GIAL, Mopa, Goa for FY 2023-24 and thereafter
increase the same with 4% inflation Y-o-Y.
d) Other Operating Expenses
8.2.41 The Authority analysed the basis for forecasting each component of Other Operating expenses submitted by
GIAL, Mopa, Goa. The analysis is as summarized below:
Housekeeping expense
8.2.42 GIAL, Mopa, Goa has awarded the contract of the housekeeping to various vendors and considered the
contract value as the base for estimating the housekeeping expense for FY 2023-24 and thereafter considered
expansion growth and inflationary increase. The Authority as part of its analysis had obtained the
housekeeping contract from GIAL, Mopa, Goa vide email dated 29th December 2022. The Authority, upon
reviewing the contract, proposes to consider the actual cost mentioned in the price schedule of the contract as
the housekeeping expenses for FY 2023-24.
8.2.43 Further, the Authority proposes to consider 25% (refer Table 91) increase due to area expansion in FY 2025-
26 and the inflation rate of 4% Y-o-Y for escalating the costs for the remaining period of the First Control
Period.
Insurance Cost
8.2.44 The Authority observes that the insurance policies submitted by GIAL, Mopa, Goa are mandatory as per the
requirements stated in the Concession Agreement between the Government of Goa (GOG) and GIAL, Mopa,
Goa for the Manohar International Airport, Mopa, Goa project. The annual premium of Rs. 2.65 crores for
all the policies submitted by GIAL, Mopa, Goa appear to be reasonable.
8.2.45 The Authority notes that GIAL, Mopa, Goa has claimed one time escalation of 25% in the Insurance cost due
to the following reasons:
• The high inflation in Europe and UK pushing the premiums northwards.
• The capacities have been shrinking and due to shortage of capital for the risk acceptance especially the
Aviation and the Terrorism (Stand Alone terrorism)
• The Nat Cat (Natural Catastrophic) losses have increase world over in US, UK, Japan & Europe as well
as Asia and the recent Earthquake.
Consultation Paper No. 11/2023-24 Page 113 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
8.2.46 The Authority notes that insurance covers are meant to mitigate risks that may arise and Premiums are
calculated based on these risk factors. Therefore, the Authority proposes not to consider GIAL, Mopa, Goa's
requested one-time escalation.
8.2.47 Further the Authority notes that GIAL, Mopa, Goa has also claimed Insurance expense at the rate of 0.09%
(GAL calculated it by considering 25% escalation on the annual premium) on the total gross block for each
tariff year along with the inflation of 5% from FY 2023-24. The Authority has reviewed the same and
proposes to consider the expense at the same rate of 0.09% on the revised gross block of assets (refer Table
87) along with the inflation of 4% from FY 2023-24.
Security Expense
8.2.48 The Authority notes that GIAL, Mopa, Goa has entered into a security contract with M/s RAXA a related
party, to deploy security personnel in all three shifts at the airport. The Authority has sought confirmation
from GIAL, Mopa, Goa that due process as mentioned in para 2.5.7 has been followed as per appropriate
governance practices and that Probity audit reports have been submitted to GoG and approved by GoG. GIAL,
Mopa, Goa has confirmed the same.
8.2.49 Further the Authority observes that GIAL, Mopa, Goa has estimated the cost for FY 2023-24 based on the
contract cost. The Authority as part of its analysis has obtained the security contract from GIAL, Mopa, Goa
vide email dated 29th December 2022. The Authority proposes to consider the actual cost mentioned in the
price schedule of the contract as the security expenses for all the years of the First Control Period.
8.2.50 The Authority is of the view that the contract with the security vendor already accounts for the growth factor.
Therefore, the Authority proposes not to consider the pax growth for escalating the security cost for the First
Control Period. However, in line with decisions made in the recent tariff orders, the Authority notes that there
shall be a proportionate increase in the security cost due to the expansion of the airport. Hence, the Authority
proposes to consider 25% (refer Table 91) increase due to area expansion in FY 2025-26.
Misc. Expenses
8.2.51 The Authority’s analysis and observations for the Misc. Expenses submitted by GIAL, Mopa, Goa are as
follows:
Table 100: Misc. Expenses analysis and observations by the Authority
(Rs. in crores)
Particulars FY 24 FY 25 FY 26 FY 27 FY28 Total Basis adopted by the Authority
GIAL, Mopa, Goa has awarded the
contract for Air monitoring and
compliance management at Manohar
International Airport, Mopa, Goa for
Rs. 0.87 crores and Rs. 0.35 crore each
EHS 1.22 1.22 1.22 1.22 1.22 6.11 year respectively and considered the
contract value as the expense for First
Control Period. The Authority
proposes to consider the actual cost
mentioned in the contract for each year
of the First Control Period.
Consultation Paper No. 11/2023-24 Page 114 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Particulars FY 24 FY 25 FY 26 FY 27 FY28 Total Basis adopted by the Authority
GIAL, Mopa, Goa has awarded the
contract for trolley management and
considered the contract value as the
base for estimating the expense for FY
2023-24. The Authority proposes to
consider the actual cost mentioned in
Trolley the price schedule of the contract for
1.54 1.60 2.08 2.16 2.25 9.62
Management FY 2023-24. Further, the Authority
proposes to consider 25% (refer Table
91) increase due to area expansion in
FY 2025-26 and the inflation rate of
4% Y-o-Y for escalating the costs for
the remaining period of the First
Control Period.
GIAL, Mopa, Goa has awarded the
contract for Other Airside O&M and
considered the contract value as the
base for estimating the expense for FY
2023-24. The Authority upon
reviewing the contract, proposes to
Other consider the actual cost mentioned in
Airside 1.48 1.54 2.00 2.08 2.16 9.26 the price schedule of the contract for
O&M FY 2023-24. Further, the Authority
proposes to consider 25% (refer Table
91) increase due to area expansion in
FY 2025-26 and the inflation rate of
4% Y-o-Y for escalating the costs for
the remaining period of the First
Control Period.
Consultation Paper No. 11/2023-24 Page 115 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Particulars FY 24 FY 25 FY 26 FY 27 FY28 Total Basis adopted by the Authority
GIAL, Mopa, Goa has awarded the
contract for Other Tops services
(includes services like solid waste
management, medical, passenger
guidance staff and porters etc). The
Authority upon reviewing the contract,
proposes to consider the actual cost
mentioned in the price schedule of the
contract for FY 2023-24. Further, the
Authority proposes to consider 25%
(refer Table 91) increase due to area
expansion in FY 2025-26 and the
Other TOPS 4.55 4.73 6.15 6.39 6.65 28.46 inflation rate of 4% Y-o-Y for
escalating the costs for the remaining
period of the First Control Period.
Further, the Authority vide email dated
21st August 2023 asked GIAL, Mopa,
Goa about recovery of porter charges
from the passengers, based on the cost
included in TOPS. In response, GIAL
vide email dated 23rd August 2023,
clarified that that no such revenue
accrues to GIAL from other TOPS
services.
Lease rentals projected by GIAL,
Mopa, Goa pertain to leased equipment
(Airfield fire crash tenders, Runway
Friction Machine, Self Baggage drop
etc) worth ~ Rs. 80 crores for which
there is a lease rent of Rs 14.76 crores
per annum. GIAL, Mopa, Goa has
communicated that the leasing
contracts were awarded through a
bidding process.
Lease Rental 14.49 14.76 14.76 14.76 14.76 73.53
The Authority proposes to consider the
GIAL, Mopa, Goa estimate for lease
rental amount submitted for the First
Control Period and expects that GIAL,
Mopa, Goa has carried out a detailed
cost benefit analysis for such leasing
decision.
The Authority expects GIAL, Mopa,
Goa to submit the cost benefit analysis
as part of stakeholders’ comments.
Consultation Paper No. 11/2023-24 Page 116 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Particulars FY 24 FY 25 FY 26 FY 27 FY28 Total Basis adopted by the Authority
Upon analyzing the UDF (User
Development Fee) collection charges
based on passenger traffic, the
Authority observes that GIAL, Mopa,
Goa has considered the total number of
passengers instead of embarking
passengers while calculating UDF
collections charges. Upon seeking
clarification, GIAL, Mopa, Goa
UDF submitted that the UDF collection
Collection 3.44 3.93 4.80 5.90 6.66 24.72 charges have been assumed to be Rs. 5
Charges per Departing and Rs. 5 per Arriving
passenger, as GIAL, Mopa, Goa
intends to charge UDF for both
Arriving and Departing passengers.
The Authority proposes to consider the
same for the purpose of computation in
Consultation Paper. However, this will
be decided based on the Stakeholder
comments at time of Consultation and
the final tariff order.
GIAL, Mopa, Goa did not provide any
basis or contract details for the estimate
of other expenses, as mentioned in their
submission. The Authority notes that
there may be misc. expenses which will
be incurred day to day to run the
operations efficiently as it is a new
Other Misc.
2.38 2.48 2.58 2.68 2.79 12.90 airport. The Authority proposes to
expenses
consider 50% of the GIAL, Mopa, Goa
estimate for FY 2023-24. Furthermore,
for the remaining period of the First
Control Period, it is proposed to
increase the estimates by 4% annually,
in line with the inflation rate (WPI)
from FY 2024-25.
Total Misc.
29.10 30.25 33.58 35.19 36.49 164.60
Expenses
8.2.52 Taking into the above factors into consideration, the Authority proposes the following Operating expenses
for the First Control Period:
Consultation Paper No. 11/2023-24 Page 117 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Table 101: Operating Expenses proposed by the Authority for the First Control Period
(Rs. in crores)
Particulars FY24 FY25 FY26 FY27 FY28 Total
Repair and Maintenance (para 8.2.34) 15.00 20.00 35.90 55.57 59.42 185.89
IT Operation related (para 8.2.39) 0.36 - - - - 0.36
Enterprise IT (para 8.2.40) 2.72 2.83 2.95 3.06 3.19 14.75
Housekeeping expense (para 8.2.43) 10.77 11.20 14.56 15.14 15.75 67.41
Insurance (para 8.2.47) 3.20 3.34 3.93 4.09 4.27 18.82
Security expense (para 8.2.50) 13.96 15.56 19.92 22.40 23.46 95.31
Misc. expense (Table 100) 29.10 30.25 33.58 35.19 36.49 164.60
Total Operating Expenses 75.11 83.18 110.83 135.45 142.57 547.14
Allocation of Operating Expenses
8.2.53 Based on its analysis, the Authority observes that the allocation basis used by GIAL, Mopa, Goa for the
components of Operating expenses is reasonable. As a result, the Authority proposes adopting the same
allocation basis, taking into consideration the revised ratios detailed in para 8.2.1 (I).
8.2.54 Based on the aforementioned proposals the aeronautical Operating expenses proposed by the Authority for
the First Control Period is as follows.
Table 102: Aeronautical Operating Expenses proposed by the Authority for the First Control Period
(Rs. in crores)
Particulars FY24 FY25 FY26 FY27 FY28 Total
Repair and Maintenance 14.29 19.06 34.21 52.95 56.63 177.15
IT Operation related 0.34 - - - - 0.34
Enterprise IT 2.59 2.70 2.81 2.92 3.04 14.06
Housekeeping expense 9.69 10.08 13.10 13.63 14.17 60.67
Insurance 3.05 3.18 3.74 3.90 4.07 17.93
Security expense 12.57 14.01 17.93 20.16 21.11 85.78
Misc. expense 27.72 28.83 32.02 33.59 34.85 157.01
Total Aeronautical Operating Expense 70.26 77.86 103.81 127.15 133.87 512.94
Airport Operator Fees
8.2.55 The Authority had sought details of the agreement entered into for the Airport Operator fee. In response to
the Authority's request via email dated 12th January 2023, GIAL, Mopa, Goa stated that they have not yet
entered into an agreement for Airport Operations with a service provider.
8.2.56 The Authority notes that the Request for Quote (RFQ) floated by the GoG for the Development of Greenfield
International Airport at Mopa, Goa had included a clause stating that the bidders must possess relevant
experience, which will be evaluated by the Authority to assess their Technical Capacity/ O&M capabilities
and only then the bidder shall be eligible to bid for the Request for Proposal (RFP). The clause is reproduced
below:
Consultation Paper No. 11/2023-24 Page 118 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
“2.2.2 To be eligible for pre-qualification and shortlisting, an Applicant shall fulfill the following conditions
of eligibility:
(A)Technical Capacity: For demonstrating technical capacity and experience (the “Technical Capacity”),
the Applicant shall, have:
(i) Developed at least 1 (one) Eligible Project during the Development Period in Category 1(A) and/or
Category 1(B) as specified in Clause 3.2.1 (“Development Experience”); and
(ii) Operated at least 1 (one) Eligible Project during the Operation Period in Category 2 as specified in
Clause 3.2.1 (“Operation Experience”).”
8.2.57 Furthermore, the Authority notes that the holding company GAL (GMR Airports Limited), based on their
successful management of airports such as DIAL and HIAL has the necessary experience and capability to
operate Manohar International Airport, Mopa, Goa and the past experience is the reason rendering them
technically competent.
8.2.58 Based on a combined reading of the above, the Authority proposes not to consider the Airport Operator Fee
for the purpose of tariff determination for the First Control Period of Manohar International Airport, Mopa,
Goa.
Total O&M Expenses proposed by the Authority
8.2.59 After incorporating the above observations by the Authority, the revised Total O&M expenses for Manohar
International Airport, Mopa, Goa for the First Control Period has been presented in the table below:
Table 103: Total O&M expenses proposed by the Authority for the First Control Period
(Rs. in crores)
GIAL,
Authority’s Proposal
Mopa, Diff =
Particulars Goa’s (C=B-
Total
Ref FY24 FY25 FY26 FY27 FY28 Submis A)
(A)
sion (B)
Manpower Table
54.26 57.52 74.38 78.85 83.58 348.58 500.86 152.28
Expenses (A) 92
Admin and
General - - -
Expense
Rates & Taxes 1.78 1.85 2.40 2.50 2.60 11.12 11.86 0.74
Corporate cost
3.75 3.90 4.06 4.22 4.39 20.31 41.45 21.14
allocation
CSR - - - - - - 10.15 10.15
Bank Charges 0.60 0.62 0.65 0.67 0.70 3.25 5.53 2.28
Consultanc8y. 2 .60 Table 10.00 10.40 10.82 11.25 11.70 54.16 104.90 50.74
Travel 94 1.97 2.05 2.13 2.22 2.30 10.67 11.74 1.07
Advertisement 8.50 8.84 4.60 4.78 4.97 31.69 75.38 43.69
Auditor &
0.53 0.55 0.57 0.60 0.62 2.87 2.91 0.04
Director Fee
Office
17.55 18.25 23.73 24.67 25.66 109.86 118.16 8.30
Maintenance etc.
Consultation Paper No. 11/2023-24 Page 119 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
GIAL,
Authority’s Proposal
Mopa, Diff =
Particulars Goa’s (C=B-
Total
Ref FY24 FY25 FY26 FY27 FY28 Submis A)
(A)
sion (B)
Total Admin
and General 44.67 46.46 48.95 50.91 52.94 243.93 382.07 138.14
Expense (B)
Utility Expense - - -
Table
Electricity 23.76 24.60 32.46 33.65 34.88 149.35 233.43 84.08
97
Water 8.2.30 1.24 1.47 1.87 2.39 2.81 9.78 10.02 0.24
Total Utility Table
25.00 26.07 34.33 36.04 37.69 159.13 243.46 84.33
Expense (C) 98
Operating
- - -
Expenses
Repair and
8.2.34 15.00 20.00 35.90 55.57 59.42 185.89 299.26 113.38
Maintenance
IT Operation
8.2.39 0.36 - - - - 0.36 0.36 -
related
Enterprise IT 8.2.40 2.72 2.83 2.95 3.06 3.19 14.75 24.50 9.75
Housekeeping
8.2.43 10.77 11.20 14.56 15.14 15.75 67.41 85.52 18.11
expense
Insurance 8.2.47 3.20 3.34 3.93 4.09 4.27 18.82 22.69 3.87
Security expense 8.2.50 13.96 15.56 19.92 22.40 23.46 95.31 112.36 17.05
Table
Misc. expense 29.10 30.25 33.58 35.19 36.49 164.60 207.21 42.61
100
Total
Table
Operating 75.11 83.18 110.83 135.45 142.57 547.14 751.89 204.75
101
Expense (D)
Airport
Operator Fee 8.2.58 - - - - - - 154.61 154.61
(E)
Total O&M
expense
199.05 213.23 268.49 301.24 316.77 1,298.78 2,032.90 734.12
(F)=(A)+(B)+(C
) + (D)+(E)
8.2.59 The Authority notes that for most of the components of O&M expenses, the allocation basis adopted by GIAL,
Mopa, Goa was in line. However, the ratios have been revised by the Authority due to which the distribution
of expenses among different components has been adjusted accordingly. Thus, considering the revision in
ratios and allocation basis, the Authority proposes the following aeronautical O&M expenses for the First
Control Period of the Manohar International Airport, Mopa, Goa.
Consultation Paper No. 11/2023-24 Page 120 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
Table 104: Aeronautical O&M expenses proposed by the Authority for the First Control Period
(Rs. in crores)
GIAL,
Authority’s Proposal
Mopa, Diff
Particulars Goa’s (C=B-
Reference FY24 FY25 FY26 FY27 FY28 Total (A) Submissi A)
on (B)
Manpower
Table 93 51.95 55.06 71.21 75.48 80.01 333.71 469.75 136.04
Expenses (A)
Admin and
- -
General Expense
Rates & Taxes 1.61 1.68 2.19 2.27 2.36 10.12 10.91 0.79
Corporate cost
3.59 3.73 3.88 4.04 4.20 19.44 39.13 19.68
allocation
CSR - - - - - - 10.15 10.15
Bank Charges 0.57 0.59 0.62 0.64 0.67 3.10 5.39 2.29
Consultancy 9.53 9.91 10.31 10.72 11.15 51.62 102.33 50.72
Travel 1.89 1.96 2.04 2.12 2.21 10.21 11.09 0.87
Advertisement Table 96 7.65 7.96 4.14 4.30 4.47 28.52 68.63 40.11
Auditor & Director
0.51 0.53 0.55 0.57 0.59 2.74 2.83 0.09
Fee
Office Maintenance
16.72 17.39 22.61 23.51 24.46 104.70 115.27 10.58
etc.
Total Admin and
General Expense 42.07 43.76 46.33 48.18 50.11 230.44 365.73 135.29
(B)
Utility Expense - -
Electricity Table 97 19.07 19.72 25.80 26.72 27.68 118.99 233.42 114.43
Water 8.2.30 0.94 1.12 1.42 1.82 2.14 7.44 10.02 2.58
Total Utility
Table 99 20.01 20.84 27.22 28.54 29.81 126.43 243.44 117.01
Expense (C)
Operating
- -
Expenses
Repair and
14.29 19.06 34.21 52.95 56.63 177.15 291.94 114.80
Maintenance
IT Operation
0.34 - - - - 0.34 0.35 0.01
related
Enterprise IT 2.59 2.70 2.81 2.92 3.04 14.06 23.89 9.84
Housekeeping
9.69 10.08 13.10 13.63 14.17 60.67 77.84 17.17
expense
Insurance 3.05 3.18 3.74 3.90 4.07 17.93 22.14 4.20
Security expense 12.57 14.01 17.93 20.16 21.11 85.78 102.29 16.51
Misc. expense 27.72 28.83 32.02 33.59 34.85 157.01 203.45 46.45
Total Operating Table
70.26 77.86 103.81 127.15 133.87 512.94 721.91 208.97
Expense (D) 102
Consultation Paper No. 11/2023-24 Page 121 of 156OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
GIAL,
Authority’s Proposal
Mopa, Diff
Particulars Goa’s (C=B-
Reference FY24 FY25 FY26 FY27 FY28 Total (A) Submissi A)
on (B)
Airport Operator
8.2.58 - - - - - - 143.16 143.16
Fee (E)
Total O&M
expense
184.29 197.51 248.56 279.35 293.80 1,203.51 1,944.00 740.49
(F)=(A)+(B)+
(C)+(D)+(E)
8.2.60 Key changes made by the Authority in Operation & Maintenance expenses relate to:
• Rationalisation of Employee Expenses – Rate of increase and headcount for expansion
• Rationalisation of Consultancy and Legal Costs.
• Rationalisation of Electricity Charges based on analysis of actual consumption trends.
• Reduction in estimate of Repairs & Maintenance Expenditures considering that the assets are newly
commissioned and covered by Defects Liability for a couple of years.
• Non-consideration of Airport Operators Fee.
8.2.61 The Authority expects Airport Operator to bring in efficiencies in the incurrence of O&M expenses for the
benefit of airport users and in line with AERA Act, AERA Guidelines and International Civil Aviation
Organization (ICAO) Principles.
8.3 Authority’s proposals regarding Operating and Maintenance Expenses for the First Control
Period
Based on the material before it and on its examination, the Authority proposes the following with regard to
O&M expenses for the First Control Period:
8.3.1 To consider aeronautical O&M Expenses for the First Control Period as per Table 104.
8.3.2 To consider the O&M expenses incurred by GIAL, Mopa, Goa during the First Control Period subject to
reasonableness and efficiency, at the time of tariff determination for the next Control Period.
Consultation Paper No. 11/2023-24 Page 122 of 156NON-AERONAUTICAL REVENUE FOR THE FIRST CONTROL PERIOD
9. NON-AERONAUTICAL REVENUE FOR THE FIRST CONTROL PERIOD
9.1 GIAL’s submission regarding Non-Aeronautical Revenue (NAR) for the First Control Period
9.1.1 GIAL, Mopa, Goa has submitted the projections of the Non-Aeronautical revenue under the following heads:
a) Direct Concession
b) Retails Concession
c) Land & Space
9.1.2 GIAL, Mopa, Goa has, in its revised MYTP dated 29th March 2023 submitted the following estimated revenue
from Non-Aeronautical services for the First Control Period for Manohar International Airport, Mopa, Goa.
Table 105: Non-Aeronautical Revenue submitted by GIAL, Mopa, Goa for the First Control Period
(Rs. in crores)
Particulars FY 24 FY 25 FY 26 FY 27 FY 28 Total
Direct Concession
In Flight Kitchen- Concession Fee (A) 1.59 1.93 2.33 2.92 3.54 12.31
Retail Concession
Food and Beverages (F&B) 42.86 51.43 65.66 92.93 110.09
Lounge Income 5.74 6.88 8.80 12.47 14.77
Retail Duty Paid 73.11 87.63 112.32 159.21 188.78
Duty Free 45.90 57.34 62.77 82.86 94.00
Car parking 3.18 3.81 4.89 6.93 8.22
Advertisement 24.08 28.85 37.04 52.55 62.33
Others 3.80 4.07 4.35 4.66 4.98
Total 198.66 240.01 295.84 411.60 483.18
Revenue Share to GIAL, Mopa, Goa
40.23 48.60 59.91 83.35 97.84 329.93
(B)
Land & Space (C) 10.66 11.20 11.75 12.34 12.96 58.91
Total (D) = (A+B+C) 52.48 61.73 73.99 98.62 114.34 401.16
9.1.3 GIAL, Mopa, Goa has submitted that it has estimated the revenues by conducting benchmarking analyses
with comparable airports and additionally considered Goa specific factors for discounting the estimates,
taking into account actual contract awards etc. GIAL, Mopa, Goa has provided the following basis for
estimating various revenues from non-aeronautical services:
a) Direct Concession
In-Flight Kitchen
9.1.4 GIAL, Mopa, Goa has awarded In-Flight Kitchen contract to M/s Taj SATS Air Catering Ltd. with the
contract to pay 13% license fees till 5th year from COD and 15% from thereafter. GIAL, Mopa, Goa has
Consultation Paper No. 11/2023-24 Page 123 of 156NON-AERONAUTICAL REVENUE FOR THE FIRST CONTROL PERIOD
estimated earnings based on Average Ticket Value (ATV) of a passenger. The ATV is increased with inflation
of 5% in following years.
b) Retail Concession
9.1.5 GIAL, Mopa, Goa submitted that it has outsourced all non-aeronautical businesses (listed below) to the
Master Concessionaire, GMR Airports Limited (GAL), vide Master Services Agreement dated 15th December
2021:
• Food & Beverages
• Lounge Income
• Retail
• Duty Free shop
• Car Parking
• Advertisement
• Others (Space rent)
9.1.6 In accordance with the agreement, the scope of GAL at Manohar International Airport, Mopa, Goa is to
undertake the design, development, operation, and management of the specified non-aeronautical facilities
and services listed above. GAL is expected to adhere to best-in-class guidelines and ethical business
standards, ensuring that the facilities provided are at par with those available at comparable airports. GAL
shall make payments to GIAL, Mopa, Goa based on the higher of the following amounts:
a) Revenue share percentage (20.25%) of the Gross Revenue of the Licensee for such License month or
b) Minimum Guarantee amount for that License Month
“Gross Revenue” shall mean the aggregate of all revenue billed and/or accrued and/or received by the Licensee
and by its direct sub-licenses and direct sub-contractors in relation to the Project from any source whatsoever,
which shall include, without limitation the following:
(a) the total revenue earned (excluding taxes) in respect of provision of Non-Aero Facilities and Services by
the Licensee and by its direct sub-licenses and direct sub-contractors in connection with the provision on
Non-Aero Facilities and Services;
(b) all revenue generated from any promotional activities carried (with the prior written consent of GIAL,
Mopa, Goa) at the Locations or from other activities permitted by GIAL, Mopa, Goa in accordance with
the terms of the License Agreement; and
(c) any other consideration received by the Licensee in relation to the provision of Non-Aero Facilities and
Services.
9.1.7 Revenues from retail concession have been projected by GIAL, Mopa, Goa based on benchmarking analysis,
the details of which are as follows:
Food and Beverages (F&B)
9.1.8 GIAL, Mopa, Goa has assumed Sales per passenger (SPP) of Rs. 60 per pax in case of domestic and Rs. 80
in case of international in line with Delhi and Hyderabad Airport. GIAL, Mopa, Goa has also evaluated the
airport operator revenue of FY 2019-20 of Dabolim Airport and calculated that Income per pax (IPP) in the
Consultation Paper No. 11/2023-24 Page 124 of 156NON-AERONAUTICAL REVENUE FOR THE FIRST CONTROL PERIOD
hands of airport operator was Rs. 10. In case of GIAL, Mopa, Goa with higher F&B area and plenty of new
brands and fine dining options, GIAL, Mopa, Goa expects to achieve around 20% higher IPP.
Lounge income
9.1.9 GIAL, Mopa, Goa has estimated ATV and penetration to arrive at SPP for lounge. The resultant SPP has been
increased with inflation and pax growth to arrive at lounge income. In case of domestic, GIAL, Mopa, Goa
estimated Rs. 750 ATV with 0.5% penetration for airport lounges and Rs.1250 ATV and 1% penetration in
case of commercial lounge based on which the effective SPP is Rs. 16.25. In case of international, GIAL,
Mopa, Goa estimated Rs.1000 ATV with 0.5% penetration for airport lounges and Rs.1500 ATV and 1%
penetration in case of commercial lounge based on which the effective SPP is Rs. 20.
Retail
9.1.10 Considering the passenger profile and longer dwell time of passengers at Manohar International Airport,
GIAL, Mopa, Goa has benchmarked the SPP mainly with Delhi Terminal 1. The SPP at Delhi Airport T1 is
in the range of Rs. 105 - Rs. 110. Accordingly, GIAL, Mopa, Goa has assumed Rs. 105 SPP in case of
domestic pax of Manohar International Airport, Mopa, Goa. In case of international, considering the lower
volume, GIAL, Mopa, Goa has assumed 10% higher SPP i.e. Rs. 116. In line with other non-aero revenue
forecasts, the retails SPP has been escalated with inflation.
Duty Free
9.1.11 GIAL, Mopa, Goa has considered benchmarks of Delhi and Hyderabad Airport. In case of Delhi the duty free
SPP is USD 10 – USD 11 whereas in case of Hyderabad the SPP is in the range of USD 5- USD 7. Considering
the passenger profile and lower penetration, GIAL, Mopa, Goa expects that the Mopa, Goa SPP should be
mainly aligned to Hyderabad Airport, considering the tourist destination and passenger profile which majorly
consists of Russian and UK residents, the SPP for Manohar International Airport, Mopa, Goa is considered
towards higher band of Hyderabad Airport i.e. USD 7. Revenue from Duty free has been forecasted by
considering the inflation increase in line with international passenger traffic growth.
Car Parking
9.1.12 According to GIAL, Mopa, Goa, the local unions have a significant impact on the Goa taxi business, and
Dabolim airport encounters opposition from the regional taxi associations. The parking revenues at Manohar
International Airport, Mopa, Goa are impacted by the powerful union of taxi operators. It is anticipated that
there will be virtually little traffic in the Manohar International Airport, Mopa, Goa's parking lot. With a
projected ATV of Rs. 171 and a car park penetration rate of 5.4%, the effective SPP comes to Rs. 9.23. The
growth in SPP over the balance period is correlated with both passenger growth and inflation.
Advertisement
9.1.13 The SPP for Manohar International Airport, Mopa, Goa is benchmarked with Hyderabad which is around Rs.
35 per passenger. GIAL, Mopa, Goa has lower sites compared to Hyderabad as the approach road linking to
highway is being built by the state government. However, GIAL, Mopa, Goa has still continued with the SPP
of Hyderabad in terms of advertisement.
Consultation Paper No. 11/2023-24 Page 125 of 156NON-AERONAUTICAL REVENUE FOR THE FIRST CONTROL PERIOD
Others (Space Rent)
9.1.14 As per the master service agreement, space of 150 sqm has been provided to GAL at an average rent of Rs.
21,112 per sqm per month.
c) Land & Space
Others – Space rent
9.1.15 GIAL, Mopa, Goa forecasted rent of Rs. 0.66 crores for FY 2023-24 on land space of 49,437 sqm. All
spaces/land are expected to have 100% occupancy from FY 2023-24 and the space rental is assumed to grow
by inflation rate of 7%.
9.2 Authority’s examination regarding Non-Aeronautical Revenue for the First Control Period
9.2.1 The Authority has examined the basis and the projections of non-aeronautical revenue submitted by GIAL,
Mopa, Goa for the First Control Period. The Authority notes that GIAL, Mopa, Goa has utilized
benchmarking analyses, specific factors for discounting, actual contract awards and tentative business
estimates to estimate their non-aeronautical revenues.
9.2.2 The Authority has conducted a detailed analysis of revenue streams submitted by GIAL, Mopa, Goa in the
following order:
a) Direct Concession
b) Retails Concession
c) Land & Space
Following are the observations and assessments by the Authority regarding GIAL, Mopa, Goa's projections
for Non-aeronautical revenue.
a) Direct Concession
In Flight Kitchen (IFK)
9.2.3 The Authority has taken note of the fact that GIAL, Mopa, Goa has awarded the In-Flight Kitchen contract
to M/s Taj SATS Air Catering Ltd. (Licensee). The Authority notes the following from the agreement
provided:
1. The Licensee has been granted an area of 4,046 sqm to carry out the services. For this area, the Licensee
is required to pay a Land Licensee fee (Space rent) of Rs. 256 per sqm per month, which will be increased
annually based on the notified CPI (IW) from the 2nd year of the contract. The revenue from this
arrangement has been categorized by GIAL, Mopa, Goa under the Space rent head and is further discussed
by the Authority in para 9.2.22.
2. As per the agreement, the Licensee is obligated to pay GIAL, Mopa, Goa a license fee of 13% of Gross
Revenue until the 5th year from COD, and 15% thereafter. GIAL, Mopa, Goa has projected the gross
revenue based on the assumption of an Average Ticket Value (ATV) and passengers opting for in-flight
eatables for both domestic and international passengers.
9.2.4 The Authority has reviewed the assumptions made by GIAL, Mopa, Goa for calculating the gross revenue
and has noted that the estimated ATV and percentage of passengers opting for the same, as indicated by
Consultation Paper No. 11/2023-24 Page 126 of 156NON-AERONAUTICAL REVENUE FOR THE FIRST CONTROL PERIOD
GIAL, Mopa, Goa are not available as a benchmark from other airports. Therefore, the Authority proposes to
forecast the in-flight revenues based on the benchmark of the airports compared in terms of the regional area
(i.e. Airports located specifically at Southern Areas) and for which data is available. Accordingly, the main
regional airports where the inflight revenues are generated are HIAL and Chennai.
9.2.5 The revenues per passenger proposed by AERA for other airports comparable to Manohar International
Airport, Mopa, Goa, has been presented below:
Table 106: Revenues per passenger of In-Flight Kitchen of Comparable Airports to Manohar
International Airport, Mopa, Goa
Revenue (Rs. in Traffic (in MPPA)
Airport Order No Revenue Per Pax
crores) (FY 24) (FY 24)
HIAL Order No_12_2021-22 15.42 23.36 6.60
Chennai Order No_38_2021-22 9.21 23.92 3.85
Average Revenue Per Pax (RPP) 5.23
9.2.6 The Authority estimates the revenues for Manohar International Airport, Mopa, Goa, considering the average
revenue per passenger of the two comparable airports as mentioned above of Rs. 5.23 per passenger applied
on the passenger traffic proposed by the Authority in Table 31 for the first year of the control period, i.e., FY
2023-24. Further, considering that Manohar International Airport, Mopa, Goa is a new greenfield airport
which commenced its commercial operations on 5th January 2023 and has to compete with another airport in
close vicinity, the Authority proposes to moderate the estimated per passenger revenue by 30% from the
average revenue per pax from the table above in order to provide a more realistic and reliable projection for
the first year of the control period at Manohar International Airport, Mopa, Goa.
Table 107: In Flight Kitchen Revenue for FY 2023-24 for Manohar International Airport, Mopa, Goa
proposed by the Authority
Particulars Reference FY 24
Traffic (A) (in MPPA) Table 31 6.88
Average Revenue Per Pax adjusted by 30% (B) (Rs. Per Pax) Table 106 3.66
In Flight Kitchen Revenue proposed by the Authority (C) = (A)x(B)/10 (Rs. in crores) 2.52
9.2.7 For the subsequent years, the Authority proposes to consider an inflation growth of 4% year-on-year (based
on WPI as per Table 79) and passenger traffic growth as stated in Table 31 from FY 2024-25 for the remaining
years. The total revenue from inflight kitchen as proposed by the Authority for the First Control Period for
Manohar International Airport, Mopa, Goa is as follows:
Table 108: In Flight Kitchen Revenue proposed by the Authority for the First Control Period for
Manohar International Airport, Mopa, Goa
(Rs. in crores)
Particulars FY 24 FY 25 FY 26 FY 27 FY 28 Total
Submitted by GIAL, Mopa, Goa (A) (Table 105) 1.59 1.93 2.33 2.92 3.54 12.31
In Flight Kitchen Revenue Proposed by the
2.52 2.99 3.80 4.85 5.70 19.85
Authority (B)
Difference (C=B-A) 0.93 1.05 1.47 1.93 2.16 7.54
Consultation Paper No. 11/2023-24 Page 127 of 156NON-AERONAUTICAL REVENUE FOR THE FIRST CONTROL PERIOD
b) Retail Concession
9.2.8 The Authority notes that GIAL, Mopa, Goa has awarded the concession rights for six services i.e. F&B (Food
and Beverage), Retail, Lounge, Duty Free, Car parking, and advertisements to GMR Airports Limited (GAL)
through an e-tendering process. As per the terms of the agreement, GAL is required to make following
payments to GIAL, Mopa, Goa:
1. Fees based on the higher amount of the below:
a) Revenue share percentage (20.25%) of the Gross Revenue of the Licensee for such License month or
b) Minimum Guarantee amount for that License Month
2. Rent for space: Space of 150 sqm has been provided to GAL at an average rent of Rs.21,112 per sqm per
month. The same has been discussed by the Authority in para 9.2.22.
Cancellation of Master Service Agreement
9.2.9 Based on the information provided in the Audited Financial statements by GIAL, Mopa, Goa for the financial
year ending in March 2023, following were noted:
• GIAL, Mopa, Goa issued an RFP for the design, development, operation, and management of Non-Aero
Facilities and Services at the Airport. GMR Airports Limited (GAL) emerged as the successful bidder
and a Master Services License Agreement was signed between GIAL, Mopa, Goa and GAL.
• However, the Government of Goa did not provide clearance for the master concession agreement, and
they directed GIAL, Mopa, Goa to cancel the existing agreement and re-bid the contract which should be
transparent and with due participation of Government representative in the selection process.
• In the event of early termination, GIAL, Mopa, Goa is liable to purchase the capital expenditure incurred
by GAL at a fair value, as determined by the terms of the agreement.
9.2.10 Based on the disclosed information, the Authority is of the view that the contract of GIAL, Mopa, Goa with
GAL will be null and void due to the government's directive.
9.2.11 In response to Authority’s query, GIAL, Mopa, Goa has submitted that the re-tendering process is underway
and is expected to be completed by September 2023.
9.2.12 The Authority proposes to evaluate the projected revenues from Retail concessions independently and will
examine the specific details of the contract to be awarded and assess the revenues generated from Non-
Aeronautical services during the true-up exercise in the next control period.
9.2.13 GIAL, Mopa, Goa has based its projections on a comparison of Sales per passenger (SPP) and Income per
passenger (IPP) with other airport terminals, namely Delhi and Hyderabad. The Authority notes that these
airports are not fully comparable to Manohar International Airport, Mopa, Goa in terms of various factors
such as traffic volume, region etc. Further, the Authority notes that the data used by GIAL, Mopa, Goa is not
a benchmark available in public domain.
9.2.14 The Authority proposes using the average Non-Aeronautical Revenue per passenger from similar services at
the other comparable airports in the region i.e. HIAL, Dabolim and Chennai. These comparable airports have
been identified as suitable benchmarks for projecting revenues from F&B, Retail, Lounge, Duty Free, Car
parking, and advertisements at Manohar International Airport, Mopa, Goa for the FY 2023-24.
Consultation Paper No. 11/2023-24 Page 128 of 156NON-AERONAUTICAL REVENUE FOR THE FIRST CONTROL PERIOD
9.2.15 The revenues per passenger for the aforementioned six services proposed for other airports is as presented
below:
Table 109: Revenues per passenger (FY 2022-24) for the six services of comparable Airports to
Manohar International Airport, Mopa, Goa
Airports (FY 2023- Lounge Retail Duty
F&B Car parking Advertisement
24) Income Outlets Free*
Revenue (Rs. in crores)
HIAL 42.71 33.70 71.37 66.11 71.54 40.05
Chennai 25.78 NA 76.37 82.84 20.71 67.26
Dabolim 12.84 NA 13.32 10.02 1.97 8.67
Traffic (In MPPA)
HIAL 23.36 23.36 23.36 3.85 23.36 23.36
Chennai 23.92 23.92 23.92 5.80 23.92 23.92
Dabolim 8.02 8.02 8.02 NA** 8.02 8.02
Revenue Per Pax (RPP)
HIAL 18.28 14.43 30.55 171.71 30.63 17.14
Chennai 10.78 NA 31.93 142.83 8.66 28.12
Dabolim 16.00 NA 16.60 NA** 2.46 10.81
Average RPP 15.02 14.43 26.36 157.27 13.91 18.69
*Average RPP of duty free is calculated by dividing the revenues by international passengers
**Duty Free Revenue Per Pax of Dabolim Airport amounts to Rs. 371.11 per pax. However, for the calculation of Average Revenue
Per Pax for Manohar International Airport, Mopa, Goa, this value has been excluded as it appears inconsistent when compared to
other major airports..
9.2.16 The Authority proposes to estimate the revenues for the services of Manohar International Airport, Mopa,
Goa, considering the average revenue per passenger of the comparable airports as mentioned in Table 109 as
a base and applying the passenger traffic proposed by the Authority in Table 31 for the first year of the control
period, i.e., FY 2023-24. Further, for services such as lounge income, car parking and advertisement, the
Authority proposes the following adjustments to ensure a fair and accurate estimation of revenues.
i. Lounge Income: The Authority notes that the airport lounge will be mostly used by specific groups of
passengers, such as business class flyers, frequent flyers, premium card holders or those who purchase
access on a pay-per-use basis and that business class passengers make up about 10% to 12% of all airline
passengers. Considering the possible differing profile of passengers in Manohar International Airport,
Mopa, Goa, the Authority proposes to rationalize the Lounge revenue per passenger by 30% from the
average estimated above.
ii. Car Parking: The Authority has reviewed the Multi-Year Tariff Proposal (MYTP) submitted by GIAL,
Mopa, Goa and has observed a significant influence from local taxi unions on the taxi market at Manohar
International Airport, Mopa, Goa. This influence has led to opposition from regional taxi associations,
as seen in the current situation at Goa's Dabolim Airport.
Additionally, the Authority has taken note that the average revenue per passenger of other airports, as
indicated in the Table 109, is considerably higher compared to Dabolim Goa Airport. It is essential to
consider these disparities in revenue when analyzing the MYTP.
Furthermore, Dabolim Goa Airport faces operational challenges in generating Parking revenue. In light
of these factors, the Authority proposes using two times the revenue per passenger at Dabolim Airport
Consultation Paper No. 11/2023-24 Page 129 of 156NON-AERONAUTICAL REVENUE FOR THE FIRST CONTROL PERIOD
as the baseline for estimating the parking revenue at Manohar International Airport, Mopa, Goa. This
proposal aims to create a fair and reasonable projection, given the prevailing market conditions and
challenges faced by both airports.
iii. Advertisements: The Authority notes from the concession agreement between GIAL, Mopa, Goa and
the state government that the government is responsible for constructing the approach road connecting
the airport to the highway. As a result, GIAL, Mopa, Goa has fewer sites available for advertisements.
In light of this, the Authority proposes to rationalize the revenue per passenger from advertisements by
30%.
9.2.17 Based on the above analysis, the Authority has estimated the revenues for these six services at Manohar
International Airport, Mopa, Goa as follows:
Table 110: Revenue for Six services for FY 2023-24 of Manohar International Airport, Mopa, Goa
Lounge Retail Duty Car Advertis
Particulars F&B Total
Income Outlet Free park ement
Traffic (A) 6.88 6.88 6.88 0.79 6.88 6.88
Average RPP (B) 15.02 10.10* 26.36 157.27 4.91 13.08*
Total revenue for Six services
proposed by the Authority (C) 10.33 6.95 1 8 . 1 4 12.42 3.38 9.00 6 0 . 2 2
= (A)x(B)/10
* Average RPP for Lounge Income and Advertisement adjusted by 30% as explained in para 9.2.16 (i) & (iii) respectively.
9.2.18 For the subsequent years, the Authority proposes to consider an inflation growth of 4% year-on-year (based
on WPI as per Table 79) and passenger traffic growth as stated in Table 31 starting from FY 2024-25 for the
remaining years. The total revenue from six services as proposed by the Authority for the control period is as
follows:
Table 111: Revenue for six services proposed by the Authority for the First Control Period
(Rs. in crores)
Particulars FY 24* FY 25 FY 26 FY 27 FY 28 Total
Submitted by GIAL, Mopa, Goa including Space
40.23 48.60 59.91 83.35 97.84 329.93
rent (A)
Other-Land Space Rent (B) (Refer para 9.2.8 (2)) 0.77 0.82 0.88 0.94 1.01 4.43
Revenue for Six services submitted by GIAL,
39.46 47.78 59.03 82.41 96.84 325.51
Mopa, Goa (C=A-B)
F&B 10.33 12.26 15.60 19.92 23.41 81.52
Lounge Income 6.95 8.24 10.49 13.39 15.74 54.81
Retail Duty Paid 18.14 21.52 27.37 34.96 41.08 143.06
Duty Free 12.42 15.37 16.67 19.81 22.26 86.55
Car parking 3.38 4.01 5.10 6.51 7.65 26.65
Advertisement 9.00 10.68 13.58 17.35 20.39 71.00
Total revenue for Six services proposed by the
60.22 72.09 88.81 111.95 130.52 463.59
Authority (D)
Difference (E=D-C) 20.76 24.31 29.78 29.54 33.68 138.08
*FY24 figures has been derived from Table 110
Consultation Paper No. 11/2023-24 Page 130 of 156NON-AERONAUTICAL REVENUE FOR THE FIRST CONTROL PERIOD
9.2.19 From the above, the Authority notes that GIAL, Mopa, Goa's estimation of revenue share is lower than the
revenue projections made by the Authority. This indicates that GIAL, Mopa, Goa may not have fully explored
the potential of generating revenue from these non-aeronautical services.
9.2.20 The Authority's projections, on the other hand, take into account the potential for growth in these non-
aeronautical services. By considering comparable airports and their average revenues per passenger, the
Authority's calculations provide a more realistic estimation of revenue from these services at Manohar
International Airport, Mopa, Goa
9.2.21 Overall, there is a need for GIAL, Mopa, Goa to focus on growing revenues from non-aeronautical services
at Manohar International Airport, Mopa, Goa by exploring innovative approaches and implementing best
practices from comparable airports.
c) Land & Space
9.2.22 The Authority has taken note of GIAL, Mopa, Goa's revenue forecast for space rental in all areas designated
for Non-Aeronautical services. The following table presents the details of the areas rented out by GIAL,
Mopa, Goa, along with their purpose and monthly rent per square meter.
Table 112: Area Let out with purpose and rent per sqm per month
(Rs. in crores)
Particulars Purpose Area in sqm Rate/Sqm/Month
Comm, Lounge, DF bonded Office,
Back of House (BOH) Area 515 1,200
F&B Kitchen,
Ticket counter Ticketing office, Forecourt 49 3,056
Office Space – Airlines Office for Airlines 384 2,300
Office Space – Ramp Offices Office for Airlines for Ramp Activities 139 2,300
AEMB & Others AEMB for Self-Handling Airlines 565 2,042
IFK-Airside unpaved IFK 4,046 256
GH unpaved land GH 2,160 256
Cargo Land Cargo 15,087 25
Fuel Fuel 24,367 25
Ground Support Equipment (GSE)
Ground Handling - Paved land 1,300 1,300
Parking for CELEBI
Self-Handling Airlines – Paved
GSE Parking for Self-Handling Airlines 825 1,300
Land
Total 49,437
9.2.23 The Authority has observed that the areas leased for Cargo, Ground handling, Fuel farm (CGF), and airlines
have been categorized as Non-Aeronautical. However, the Authority notes that the revenue collected from
aeronautical service providers, such as CGF and Airlines, should be classified as Aeronautical Revenues as
the revenue generated from leasing land to CGF and airlines is closely tied to aeronautical services. CGF and
Airlines are directly involved in providing essential services for aircraft operations, including fueling, cargo
handling, and ground handling services. These activities are inherently a part of airport operations and are
essential for the functioning of airlines and other aeronautical service providers. Accordingly, the Authority
proposes to consider the rent received from CGF and Airlines for the allocated space as aeronautical revenues.
Consultation Paper No. 11/2023-24 Page 131 of 156NON-AERONAUTICAL REVENUE FOR THE FIRST CONTROL PERIOD
9.2.24 The Authority also proposes that the space rented out under the Master Service Agreement (refer para (9.2.8
(2)) should be included in the revenue from land and space, rather than being considered as revenue from the
master services provided by GAL.
Table 113: Area let out for Master Services and rent per sqm per month
Nature Area in Sq.m Rate/Sq.m/Month
ATMs 15 28,259
Banks 25 11,412
Hotel Counters 50 28,529
Other Area 60 17,117
Total 150
9.2.25 The Authority has noted that the revenue from space rent (excluding space let out for master services) has
been increased by an annual inflation growth rate of 5% according to GIAL, Mopa, Goa's projections.
Additionally, a real growth rate of 7% has been applied to the revenue from space let for master services.
However, the Authority has observed that GIAL, Mopa, Goa has employed varying growth rates for
estimating income from space rent, which lacks consistency when considering the airport as a whole.
Therefore, the Authority proposes adopting a consistent real growth rate of 7% for all revenues from space
rental, starting from FY 2024-25 until the end of the tariff period, i.e., FY 2027-28.
9.2.26 Furthermore, the Authority notes that GIAL, Mopa, Goa has projected expansion of Terminal Building in FY
2025-26 and the same has been considered by the Authority in Chapter 5 i.e., RAB. In line with the expansion
in area, the Authority proposes a 25% (Refer Table 91) increase in revenue from space rental from FY 2025-
26.
9.2.27 The proposed revenue from land and space, as proposed by the Authority for the First Control Period, is
outlined in the following table:
Table 114: Revenue from Land and Space proposed by the Authority for the First Control Period
(Rs. in crores)
Particulars Reference FY 24 FY 25 FY 26 FY 27 FY 28 Total
GIAL, Mopa, Goa's Submission A 10.66 11.20 11.75 12.34 12.96 58.91
Authority’s Proposal
Back of House (BOH) Area a 0.74 0.79 1.06 1.14 1.22 4.95
Ticket counter b 0.18 0.19 0.26 0.28 0.29 1.20
Office Space – Airlines c 1.06 1.13 1.52 1.62 1.74 7.07
Office Space – Ramp Offices d 0.38 0.41 0.55 0.59 0.63 2.56
AEMB & Others e 1.38 1.48 1.98 2.12 2.27 9.24
IFK-Airside unpaved f 1.24 1.33 1.78 1.90 2.04 8.29
GH unpaved land g 0.66 0.71 0.95 1.02 1.09 4.43
Cargo Land h 0.45 0.48 0.65 0.69 0.74 3.02
Fuel i 0.73 0.78 1.05 1.12 1.20 4.88
Ground Handling - Paved land j 2.03 2.17 2.90 3.11 3.32 13.53
Self-Handling Airlines – Paved Land k 1.29 1.38 1.84 1.97 2.11 8.59
ATMs l 0.51 0.54 0.73 0.78 0.83 3.39
Banks m 0.34 0.37 0.49 0.52 0.56 2.28
Consultation Paper No. 11/2023-24 Page 132 of 156NON-AERONAUTICAL REVENUE FOR THE FIRST CONTROL PERIOD
Particulars Reference FY 24 FY 25 FY 26 FY 27 FY 28 Total
Hotel Counters n 1.71 1.83 2.45 2.62 2.80 11.42
Other Area o 1.23 1.32 1.76 1.89 2.02 8.22
Total Revenue from Land and B=Sum of
13.95 14.93 19.96 21.36 22.86 93.06
Space proposed by the Authority a to o
Revenue from Land and Space
C=c+d+g
considered Aeronautical (Refer para 6.61 7.07 9.45 10.12 10.82 44.07
+h+i+j+k
9.2.23)
Revenue from Land and Space
D=B-C 7.34 7.86 10.51 11.25 12.03 48.99
considered Non-Aeronautical
Difference E=D-A (3.32) (3.34) (1.24) (1.10) (0.93) (9.92)
Other Income
9.2.28 The Authority has observed that GIAL, Mopa, Goa has not provided the necessary estimates for Interest
Income in order to calculate Non-Aeronautical Revenues. It is pertinent to note that Interest Income falls
under the category of Non-Aeronautical Revenues. The calculation of Interest Income estimates depends on
cash flows and surpluses, which are determined based on the projected revenue collection.
9.2.29 The Authority proposes including the actual Interest Income, along with any other Non-Aeronautical
Revenues, in the subsequent Control period's true-up process. This will allow for a comprehensive adjustment
and alignment of the financial figures to reflect the accurate revenue generated during the specified period.
9.2.30 Based on the aforementioned factors, the Authority has estimated the total Non-Aeronautical revenues for the
First Control Period of Manohar International Airport, Mopa, Goa as follows:
• Revenue from the In-Flight Kitchen has been projected by considering the average revenue per passenger,
based on the comparison with benchmark airports in the regional areas (HIAL and Chennai), for FY
2023-24. This estimate is further increased by an annual inflation rate of 4% and traffic growth for the
remaining years of the Control Period.
• Revenue from six services, namely F&B (Food and Beverage), Retail, Lounge, Duty-Free, Car parking,
and advertisements, has been estimated by considering the average revenue per passenger based on
benchmark airports in the regional areas (HIAL, Dabolim, and Chennai) for FY 2023-24. This estimate
is further increased by an annual inflation rate of 4% and traffic growth for the remaining years of the
Control Period.
• For FY 2023-24, revenue from the leasing of space has been calculated based on the monthly rent per
square meter, as stipulated in the executed contracts. However, land rent from CGF (Cargo and Ground
Facilities) and airlines has been classified as aeronautical revenue. For subsequent years, a real growth
rate of 7% has been considered year-on-year, and 25% increase in land area due to expansion in the
Passenger Terminal Building (PTB) area is anticipated in FY 2025-26 and accordingly, revenue has been
computed for the same.
9.2.31 Based on the analysis as detailed above, the Authority proposes the following estimates for Non-Aeronautical
Revenue for the First Control Period:
Consultation Paper No. 11/2023-24 Page 133 of 156NON-AERONAUTICAL REVENUE FOR THE FIRST CONTROL PERIOD
Table 115: Non-Aeronautical Revenue proposed by the Authority for First Control Period
(Rs. in crores)
Particulars Reference FY 24 FY 25 FY 26 FY 27 FY 28 Total
Direct Concession
Flight Kitchen- Concession Fee Table 108 2.52 2.99 3.80 4.85 5.70 19.85
Retail Concession
F&B 10.33 12.26 15.60 19.92 23.41 81.52
Lounge Income 6.95 8.24 10.49 13.39 15.74 54.81
Retail Duty Paid 18.14 21.52 27.37 34.96 41.08 143.06
Table 111
Duty Free 12.42 15.37 16.67 19.81 22.26 86.55
Car park 3.38 4.01 5.10 6.51 7.65 26.65
Advertisement 9.00 10.68 13.58 17.35 20.39 71.00
Total Retail Concession 60.22 72.09 88.81 111.95 130.52 463.59
Contract linked Revenues
Land & Space Table 114 7.34 7.86 10.51 11.25 12.03 48.99
Total NAR as proposed by the
70.08 82.94 103.11 128.05 148.25 532.43
Authority (A)
Lease rentals proposed by GIAL,
Mopa, Goa as Non-Aero but 6.61 7.07 9.45 10.12 10.82 44.07
considered as Aero by Authority (B)
GIAL, Mopa, Goa's Submission (C) Table 105 52.48 61.73 73.99 98.62 114.34 401.16
Difference (D=A+B-C) 24.21 28.28 28.57 39.55 44.73 175.34
9.2.32 The Authority emphasizes the importance for GIAL, Mopa, Goa to generate and receive adequate amount of
Non-Aeronautical Revenue comparable to other PPP airports in this aspect. This is necessary to effectively
cross-subsidize the charges imposed on users and ensure efficient operations.
9.3 Authority’s proposals regarding Non-Aeronautical Revenues for the First Control Period
Based on the material before it and based on its analysis, the Authority proposed the following with regard to
non-aeronautical revenue for the First Control Period.
9.3.1 To consider non-aeronautical revenues for the First Control Period for Manohar International Airport, Mopa,
Goa in accordance with Table 115.
9.3.2 GIAL, Mopa, Goa should make efforts to substantially increase the NAR of Manohar International Airport,
Mopa, Goa for the First Control Period, in line with similar airports.
Consultation Paper No. 11/2023-24 Page 134 of 156TAXATION FOR THE FIRST CONTROL PERIOD
10. TAXATION FOR THE FIRST CONTROL PERIOD
10.1 GIAL’s submission regarding Aeronautical Taxation for the First Control Period
10.1.1 GIAL, Mopa, Goa has submitted that it has opted for benefit provided under Section 115BAA of the Income
Tax Act resulting in an effective tax rate of 25.17%. Consequently, the company need not pay tax under MAT
(Minimum Alternate Tax) if they opt for Section 115BAA. Accordingly, GIAL, Mopa, Goa has not
considered MAT in tax calculations.
10.1.2 While calculating tax, GIAL, Mopa, Goa has considered the following:
• Concession fee payable by GIAL, Mopa, Goa is not considered as an expense.
• 30% Non-Aeronautical Revenue has been considered for cross subsidization.
10.1.3 GIAL, Mopa, Goa has calculated tax based on standalone Aeronautical P&L arrived on the basis of
aeronautical building blocks.
10.1.4 Estimated Tax proposed by GIAL, Mopa, Goa, based on building blocks as per MYTP submission is as
detailed below:
Table 116: Aeronautical taxes submitted by GIAL, Mopa, Goa for First Control Period
(Rs. in crores)
Particulars FY24 FY25 FY26 FY27 FY28 Total
Aero Revenue 559.62 1,065.72 1,366.20 1,760.62 2,087.57 6,839.73
Non-Aero cross subsidy 8.05 6.39 7.50 1.94 0.78 24.66
Total Aero Revenue 567.67 1,072.11 1,373.70 1,762.55 2,088.35 6,864.38
Aero Opex (267.62) (305.96) (389.12) (464.26) (517.03) (1,944.00)
Depreciation (163.34) (169.72) (182.51) (195.31) (196.77) (907.66)
Interest (226.87) (224.33) (214.90) (194.76) (158.80) (1,019.66)
Aero PBT (90.16) 372.10 587.17 908.21 1,215.74 2,993.06
Add: Book Depreciation 163.34 169.72 182.51 195.31 196.77 907.65
Less: Tax depreciation (347.61) (338.55) (300.20) (332.22) (292.46) (1,611.04)
Taxable Profit (274.42) 203.27 469.48 771.31 1,120.96 2,290.60
C/f loss adjusted (203.27) (400.83) (604.10)
Net Taxable profit - - 68.65 771.31 1,120.96 1,960.92
Tax rate 25.17% 25.17% 25.17%
Income Tax 17.28 194.12 281.90 493.30
10.2 Authority’s examination regarding Aeronautical taxation for the First Control Period
10.2.1 The Authority notes that GIAL, Mopa, Goa has considered 30% Non-aeronautical Revenue in the estimation
of Aeronautical Profit Before Tax (PBT), which was then used in the computation of aeronautical taxes. The
fact that a part of Non-aeronautical Revenue is used for cross subsidization as per the Hybrid Till mechanism
does not change the nature of such revenue to Aeronautical. Further, the cross subsidization as per the Hybrid
till mechanism is done in order to reduce tariff pressure on passengers and to incentivize GIAL, Mopa, Goa
to make effective investments in Non-aeronautical income generating sources.
10.2.2 Therefore, the Authority is of the view that:
Consultation Paper No. 11/2023-24 Page 135 of 156TAXATION FOR THE FIRST CONTROL PERIOD
• 30% Non-Aeronautical Revenue should not be treated as a subsidy for GIAL, Mopa, Goa as GIAL, Mopa,
Goa has already earned it from non-aeronautical services and is meant as a cross subsidy to the airport
user.
• The consideration of 30% Non-Aeronautical Revenue as part of revenue from aeronautical services would
result in an unfair enrichment to GIAL, Mopa, Goa, effectively reducing the cross-subsidy benefit to the
airport user from the present 30% non-aeronautical income.
10.2.3 Therefore, the Authority proposes to consider only aeronautical revenue and expenses in the calculation of
aeronautical PBT.
10.2.4 The Authority notes that the Interest cost considered by GIAL, Mopa, Goa as a reduction to compute
Aeronautical Profit is not reflective of the actual estimated Interest cost. GIAL, Mopa, Goa has computed the
Interest cost for reduction from Profit as follows:
• Average Aeronautical RAB for the year is considered as the base value
• On this, the Debt: Equity ratio for the respective year is applied and a quantum of debt is arrived notionally.
• Cost of debt is applied on this notional value to compute the interest cost
10.2.5 This has resulted in considering lower interest cost, significantly for FY 2025-26 to FY 2027-28, which results
in estimating higher Aeronautical Profit and consequently, higher Aeronautical taxes. This difference is
explained in the below table.
Table 117: Interest cost as per MYTP submission and Interest cost considered in Aeronautical P&L by
GIAL, Mopa, Goa
(Rs. in crores)
Particulars Reference FY24 FY25 FY26 FY27 FY28 Total
Interest cost to be
Average Debt as per GIAL,
A 2,358.74 2,491.90 2,588.79 2,475.83 2,302.27
Mopa, Goa
Interest cost estimate at 9% B=A*9% 212.29 224.27 232.99 222.82 207.20 1,099.58
Asset ratio as per GIAL, Mopa,
C 97.60% 97.60% 97.60% 97.60% 97.60%
Goa
Aero Interest cost as per above D=B*C 207.19 218.89 227.40 217.48 202.23 1,073.19
Interest cost considered
Average Aeronautical RAB E 3,497.34 3,462.92 3,559.70 3,643.69 3,472.04
Debt: equity ratio F 62.07% 61.99% 57.77% 51.15% 43.77%
Base value for Interest G=E*F 2,170.96 2,146.70 2,056.41 1,863.77 1,519.58
Aero Interest cost considered H=G*10.4
226.87 224.33 214.90 194.76 158.80 1,019.65
at 10.45% 5%
10.2.6 The Authority proposes to correct the methodology of estimating Interest cost for computing Profit, by
aligning the same with the estimated interest cost for the relevant year.
10.2.7 Also, the Authority has recomputed Aeronautical Tax of GIAL, Mopa, Goa based on the changes proposed
to the other building blocks and based on the proposal discussed above on exclusion of Non-aeronautical
Revenue.
10.2.8 Based on the above, the following table summarizes the aeronautical taxes proposed by the Authority for the
First Control Period.
Consultation Paper No. 11/2023-24 Page 136 of 156TAXATION FOR THE FIRST CONTROL PERIOD
Table 118: Aeronautical taxes proposed to be considered by the Authority for First Control Period
(Rs. in crores)
Particulars Reference FY24 FY25 FY26 FY27 FY28 Total
Aero Revenue * A 452.88 614.24 779.63 992.94 1,164.91 4,004.59
Aero Opex B 184.29 197.51 248.56 279.35 293.79 1,203.51
Depreciation as per
C 291.72 302.10 294.28 287.05 256.70 1,431.85
Income Tax **
Total D=A-B-C (23.13) 114.62 236.79 426.54 614.42 1,369.23
Interest cost estimate E 207.19 218.89 227.40 217.48 202.23 1,073.19
Aero PBT F=D-E (230.33) (104.27) 9.39 209.07 412.19 296.05
C/f loss of previous
(215.68) (446.00) (550.27) (540.88) (331.82)
years
Losses Added/Utilized (230.33) (104.27) 9.39 209.07 412.19
PBT after set off of
(446.00) (550.27) (540.88) (331.82) 80.37
C/f losses
Tax rate 25.17% 25.17% 25.17% 25.17% 25.17%
Income Tax - - - - 20.23
* Aero revenue is computed based on Net ARR per pax; this is subject to revision based on tariff rate card which is to be submitted
by GIAL, Mopa, Goa.
**Computed using WDV method considering useful lives as per IT Act
10.3 Authority’s proposals regarding Aeronautical taxation for the First Control Period
Based on the materials before it and its analysis, the Authority proposes the following with regard to taxation
for the First Control Period:
10.3.1 To consider aeronautical tax as per Table 118 for the First Control Period.
10.3.2 To true up the aeronautical tax amount appropriately taking into consideration all relevant facts at the time of
tariff determination for the next Control Period.
Consultation Paper No. 11/2023-24 Page 137 of 156QUALITY OF SERVICE FOR THE FIRST CONTROL PERIOD
11. QUALITY OF SERVICE FOR THE FIRST CONTROL PERIOD
11.1 GIAL’s submission regarding Quality of Service for the First Control Period
11.1.1 GIAL, Mopa, Goa has not made any submissions related to Quality of Service as part of its MYTP submission
for the First Control Period.
11.2 Authority’s examination regarding Quality of Service for the First Control Period
11.2.1 The Authority notes that:
• As per section 13 (1) (d) of the AERA Act, 2008, the Authority shall “monitor the set performance standards
relating to quality, continuity and reliability of service as may be specified by the Central Government or any
Authority authorized by it in this behalf.”
• As per section 13(1)(a)(ii), the Authority is required to determine the tariff for Aeronautical services taking
into consideration “the service provided, its quality and other relevant factors.”
11.2.2 The Authority notes that Annexure 1 of Schedule L of the Concession Agreement for Manohar International
Airport, Mopa, Goa, Goa lays down the following:
“The subjective quality of service shall be measured on the parameter of "Overall satisfaction with the
airport" on the ACI ASQ survey to be conducted every quarter. The benchmark score for the parameter
"Overall satisfaction with the airport" shall be at least equivalent to such score that the Airport is identified
within top 20 (twenty) per centile of all airports in its category in the world. The Concessionaire shall also
provide performance on all measured parameters of the ACI ASQ survey as part of the Statements being
submitted as per the provisions of the Agreement.”
11.2.3 Also, clause 26.8.1 of the CA states that GIAL, Mopa, Goa should participate in the user survey of ASQ
undertaken by ACI, conducted every quarter and ensure that the Airport achieves and maintains a rating of at
least 4.2 out of 5.0 and / or shall appear within top 20 percentile of all airports, in its category in the world in
such survey.
11.2.4 Further, the Authority noted from AAI's website that the ACI ASQ survey results for Goa International
Airport of AAI at Dabolim for the 2021 to 2023-Q1 have been in the range of 4.74 to 4.89 (overall score), as
against the average score of AAI Airports which ranges from 4.60 to 4.73.
Table 119: ASQ rating for Goa International Airport, Dabolim for the years 2021-2023 Q1
Year ASQ rating
2021 4.89
2022 4.90
2023 - Q1 4.74
11.2.5 The Authority noted that the ASQ rating awarded to Goa International Airport of AAI, Dabolim is close to
the average rating of the AAI airports.
11.2.6 As per the provisions outlined in the Concession Agreement and taking into consideration the ASQ rating
maintained by the Airports Authority of India (AAI) at Dabolim Airport, it is expected that Manohar
International Airport, Mopa, Goa will strive to achieve a similar or higher ASQ rating. The Authority sets
this expectation based on the understanding that the Manohar International Airport, Mopa, Goa, being a new
Consultation Paper No. 11/2023-24 Page 138 of 156QUALITY OF SERVICE FOR THE FIRST CONTROL PERIOD
airport, should aim to provide a level of service that is at least on par with the existing Dabolim Airport, if
not surpass it.
11.3 Authority’s proposals regarding Quality of Service for the First Control Period
Based on the material before it and its analysis, the Authority proposes the following with regard to Quality
of service for the First Control Period:
11.3.1 GIAL, Mopa, Goa should ensure that service quality at Manohar International Airport, Mopa, Goa adheres
to the performance standards outlined in the Concession Agreement throughout the control period.
11.3.2 In addition to meeting these standards, GIAL, Mopa, Goa is expected to meet and maintain the service quality
provided at Dabolim Airport, which is operated by the Airports Authority of India (AAI).
Consultation Paper No. 11/2023-24 Page 139 of 156AGGREGATE REVENUE REQUIREMENT FOR THE FIRST CONTROL PERIOD
12. AGGREGATE REVENUE REQUIREMENT FOR THE FIRST CONTROL PERIOD
12.1 GIAL’s submission regarding ARR for the First Control Period
12.1.1 GIAL, Mopa, Goa has submitted ARR and Yield per Passenger (YPP) for the period from 7th December 2022
to 31st March 2023 and First Control Period as per the table below:
Table 120: Aggregate revenue requirement (ARR) submitted by GIAL, Mopa, Goa for the First
Control Period
(Rs. in crores)
Particulars Reference FY23* FY24 FY25 FY26 FY27 FY28 Total
RAB A 3,483.72 3,497.34 3,462.92 3,559.70 3,643.69 3,472.04
FRoR B 15.89% 15.89% 15.89% 15.89% 15.89% 15.89%
Return on RAB C=A*B 175.34 555.88 550.41 565.79 579.14 551.86 2,978.43
Depreciation D 49.25 163.34 169.72 182.51 195.31 196.77 956.91
Operating Expense E 93.74 267.62 305.96 389.12 464.26 517.03 2,037.74
Taxation F - - - 17.28 194.12 281.90 493.30
30% of NAR G 1.62 15.74 18.52 22.20 29.58 34.30 121.96
Aggregate Revenue H=(C+D+
316.72 971.10 1,007.57 1,132.51 1,403.25 1,513.26 6,344.41
Requirement E+F-G)
Total Pax I 0.70 6.88 7.85 9.60 11.79 13.32
PV Factor J 1.05 0.86 0.74 0.64 0.55 0.48
PV of ARR K=H*J 331.87 837.92 750.16 727.53 777.83 723.77 4,149.08
Sum of PV of ARR L 4,149.08
Projected Revenue M 19.78 559.62 1,065.72 1,366.20 1,760.62 2,087.57 6,859.50
PV of Projected Revenue N=M*J 20.73 482.87 793.45 877.66 975.92 998.45 4,149.08
Sum of PV of Projected
O 4,149.08
Revenue
Effective YPP P 1,271.32
*ARR submitted by GIAL, Mopa, Goa includes the period from 7th December 2022 to 31st March 2023
12.2 Authority’s examination regarding ARR for the First Control Period
12.2.1 The observations and proposals of the Authority across the regulatory building blocks impact the computation
of ARR and Yield. With respect to each element of the regulatory building blocks considered by GIAL, Mopa,
Goa in computation of ARR and Yield in the table above, the Authority proposes to consider the regulatory
building blocks as discussed in the previous chapters.
12.2.2 The following table shows the proposed ARR and YPP as per the Authority.
Table 121: Aggregate Revenue Requirement proposed by Authority for the First Control Period
(Rs. in crores)
Particulars Table Ref Reference FY24 FY25 FY26 FY27 FY28 Total
Average RAB Table 74 A 2,796.05 3,052.60 3,123.36 3,184.27 3,038.11
Fair Rate of
Table 77 B 12.21% 12.21% 12.21% 12.21% 12.21%
Return
Return on
C=A*B 341.40 372.72 381.36 388.80 370.95 1,855.24
average RAB
Consultation Paper No. 11/2023-24 Page 140 of 156AGGREGATE REVENUE REQUIREMENT FOR THE FIRST CONTROL PERIOD
Particulars Table Ref Reference FY24 FY25 FY26 FY27 FY28 Total
Operating
Table 104 D 184.29 197.51 248.56 279.35 293.80 1,203.51
Expense
Depreciation Table 72 E 117.86 135.17 145.03 154.88 155.42 708.37
Taxation Table 118 F - - - - 20.23 20.23
Aggregate
G=C+D+
Revenue 643.55 705.41 774.95 823.03 840.40 3,787.34
E+F
Requirement
PV of Under-
recovery of the
period from Table 18 H 179.75 179.75
COD to 31st
March 2024
Aggregate
Revenue I=G+H 823.30 705.41 774.95 823.03 840.40 3,967.10
Requirement
NAR Table 115 J 70.08 82.94 103.11 128.05 148.25 532.43
30% of NAR K=J*30% 21.02 24.88 30.93 38.41 44.48 159.73
Net ARR L=I-K 802.28 680.53 744.02 784.62 795.93 3,807.37
Discount
factor M 1.00 0.89 0.79 0.71 0.63
(@12.21%)
PV of ARR N=L*M 802.28 606.48 590.91 555.34 502.05 3,057.06
Sum of ARR O 3,057.06
Total Traffic Table 31 P 49.44
YPP on total traffic Q=O/P 618.34
12.2.3 The Authority notes that, it is necessary to have the individual year wise tariff card laying down the different
aeronautical charges and the workings for the aeronautical revenues, in order to have a constructive
stakeholder discussion and hence GIAL, Mopa, Goa is directed to submit the detailed Annual Tariff proposals
in line with the ARR and Yield arrived at by the Authority within 7 days of issue of the Consultation Paper.
12.2.4 The Authority for the purpose of calculating CSR and Tax has considered aeronautical revenue based on YPP
computed in the ARR table above assuming all the revenues arrived from various services like UDF, parking
and landing, CUTE, Lease rentals etc. The Authority proposes to evaluate the same based on the tariff rate
card at the time of issue of Multi Year Tariff Order.
12.2.5 The Authority is of the view that when a new airport is constructed, it involves significant capital investment
in infrastructure, facilities, and operational costs. These costs are typically recovered through tariffs imposed
on airlines, passengers, and other users of the airport's services. However, setting tariffs at excessively high
levels can potentially discourage airlines from operating at the airport and deter passengers from choosing it
as their preferred gateway. Conversely, setting tariffs too low may result in inadequate revenue generation,
making it challenging for the airport to cover its operating costs and debt obligations.
This requires a delicate balance between cost recovery and its potential impact on air traffic demand. This
balance is crucial for the financial viability of the airport and its ability to sustain operations while also
ensuring that the tariffs remain competitive enough to attract and retain airlines and passengers. Therefore,
Consultation Paper No. 11/2023-24 Page 141 of 156AGGREGATE REVENUE REQUIREMENT FOR THE FIRST CONTROL PERIOD
the Authority, based on the tariff rate card to be submitted by GIAL, Mopa, Goa will decide the balance
between cost recovery and its potential impact on air traffic demand.
12.3 Authority’s proposal regarding ARR for the First Control Period
Based on the material before it and based on its analysis, the Authority proposes the following with regard to
ARR for the First Control Period:
12.3.1 To consider the ARR and YPP for the First Control Period for Manohar International Airport, Mopa, Goa in
accordance with Table 121.
12.3.2 To direct GIAL, Mopa, Goa to submit the Annual Tariff Proposal (Tariff Rate Card) within 7 days from issue
of this Consultation Paper which will be reviewed and put up for stakeholder consultations.
Consultation Paper No. 11/2023-24 Page 142 of 156SUMMARY OF AUTHORITY’S PROPOSALS PUT FORTH FOR STAKEHOLDER CONSULTATIONS
13. SUMMARY OF AUTHORITY’S PROPOSALS PUT FORTH FOR STAKEHOLDER
CONSULTATIONS
CHAPTER 3: DETERMINATION OF TARIFF FOR THE PERIOD FROM COD (5TH JANUARY) TO
31ST MARCH 2023
3.3.1 To consider Traffic as per Table 8
3.3.2 To consider RAB and depreciation as per Table 12.
3.3.3 To consider FRoR as per para 3.2.17.
3.3.4 To consider Aeronautical O&M expenses as per Table 13.
3.3.5 To consider Non-aeronautical revenue as per Table 14.
3.3.6 To consider the Aeronautical tax as per Table 15
3.3.7 To consider Aeronautical revenue as per Table 17.
3.3.8 To consider under recovery of Rs. 179.75 crores as per Table 18 and adjust the same in the ARR for the First
Control Period.
3.3.9 To true up the additions to RAB and depreciation for the year based on the total completed cost for Phase I
and the Fixed Asset Register to be submitted by GIAL in the next control period.
CHAPTER 4: TRAFFIC FOR THE FIRST CONTROL PERIOD
4.3.1 To consider Passenger Traffic, ATM and Cargo Traffic for the First Control Period for Manohar International
Airport, Mopa, Goa as per Table 31.
4.3.2 To true up the traffic volumes (Passenger, ATM and Cargo) based on actual numbers for the First Control
Period at the time of determination of tariff for the next control period.
CHAPTER 5: CAPITAL EXPENDITURE (CAPEX), DEPRECIATION AND REGULATORY ASSET
BASE (RAB) FOR THE FIRST CONTROL PERIOD
5.7.1 To consider the Terminal Building Ratio (TBLR) of 90:10 as mentioned in para 5.4.6 and in line with IMG
norms and as approved for other similar Airports.
5.7.2 To allow financing allowance during the First Control Period as detailed in Table 61, para 5.3.18 and para
5.3.19.
5.7.3 To adopt the Capital Expenditure for the First Control Period in accordance with Table 64.
5.7.4 To adopt the aeronautical additions for the First Control Period in accordance with Table 68.
5.7.5 To examine the accounting of input tax credits in accordance with Chapter V of The Central Goods and
Services Tax Act, 2017 and make necessary adjustments at the time of determination of tariffs for the next
Control Period (as detailed in para 5.3.27 and para 5.3.29).
5.7.6 To reduce (adjust) 1% of the uncapitalized project cost from the ARR in case any particular capital project is
not completed/ capitalized as per the approved capitalization schedule, as mentioned in para 5.3.35. The same
will be examined during the true up of the First Control Period, at the time of determination of tariff for the
next Control Period .
Consultation Paper No. 11/2023-24 Page 143 of 156SUMMARY OF AUTHORITY’S PROPOSALS PUT FORTH FOR STAKEHOLDER CONSULTATIONS
5.7.7 To true up the Aeronautical Capital expenditure based on actuals, cost efficiency and reasonableness, at the
time of determination of tariff for Next Control Period.
5.7.8 To adopt Aeronautical Depreciation as per Table 72 for the First Control Period.
5.7.9 To true up the Depreciation of the First Control period based on the actual asset additions and actual date of
capitalization during the tariff determination of the Next Control Period.
5.7.10 To consider average RAB for the First Control Period for Manohar International Airport, Mopa, Goa as per
Table 74.
5.7.11 To true up the RAB based on actuals at the time of tariff determination for the Next Control period.
CHAPTER 6: FAIR RATE OF RETURN FOR THE FIRST CONTROL PERIOD
6.3.1 To consider the Cost of equity at 15.18% as per CAPM formula.
6.3.2 To consider the notional debt to equity (gearing) ratio of 48%:52% in line with target gearing ratio being
considered in case of other PPP airports.
6.3.3 To consider cost of debt of 9% for the First Control Period.
6.3.4 To consider FRoR of 12.21% for the First Control Period based on above mentioned Cost of equity, Cost of
debt and gearing ratio.
CHAPTER 7: INFLATION FOR THE FIRST CONTROL PERIOD
7.3.1 To consider Inflation as per Table 79.
CHAPTER 8: OPERATING & MAINTENANCE EXPENSES FOR THE FIRST CONTROL PERIOD
8.3.1 To consider aeronautical O&M Expenses for the First Control Period as per Table 104.
8.3.2 To consider the O&M expenses incurred by GIAL, Mopa, Goa during the First Control Period subject to
reasonableness and efficiency, at the time of tariff determination for the next Control Period.
CHAPTER 9: NON-AERONAUTICAL REVENUE FOR THE FIRST CONTROL PERIOD
9.3.1 To consider non-aeronautical revenues for the First Control Period for Manohar International Airport, Mopa,
Goa in accordance with .
9.3.2 GIAL, Mopa, Goa should make efforts to substantially increase the NAR of Manohar International Airport,
Mopa, Goa for the First Control Period, in line with similar airports.
CHAPTER 10: TAXATION FOR THE FIRST CONTROL PERIOD
10.3.1 To consider aeronautical tax as per Table 118 for the First Control Period.
10.3.2 To true up the aeronautical tax amount appropriately taking into consideration all relevant facts at the time
of tariff determination for the next Control Period.
CHAPTER 11: QUALITY OF SERVICE FOR THE FIRST CONTROL PERIOD
11.3.1 GIAL, Mopa, Goa should ensure that service quality at Manohar International Airport, Mopa, Goa adheres
to the performance standards outlined in the Concession Agreement throughout the control period.
Consultation Paper No. 11/2023-24 Page 144 of 156SUMMARY OF AUTHORITY’S PROPOSALS PUT FORTH FOR STAKEHOLDER CONSULTATIONS
11.3.2 In addition to meeting these standards, GIAL, Mopa, Goa is expected to meet and maintain the service
quality provided at Dabolim Airport, which is operated by the Airports Authority of India (AAI).
CHAPTER 12: AGGREGATE REVENUE REQUIREMENT FOR THE FIRST CONTROL PERIOD
12.3.1 To consider the ARR and YPP for the First Control Period for Manohar International Airport, Mopa, Goa in
accordance with Table 121
12.3.2 To direct GIAL, Mopa, Goa to submit the Annual Tariff Proposal (Tariff Rate Card) within 7 days from
issue of this Consultation Paper which will be reviewed and put up for stakeholder consultations.
Consultation Paper No. 11/2023-24 Page 145 of 156STAKEHOLDER CONSULTATION TIMELINE
14. STAKEHOLDER CONSULTATION TIMELINE
14.1.1 In accordance with the provision of Section 13(4) of the AERA Act, 2008, the proposals contained in the
Chapter 13 – Summary of the Authority’s proposals read with the relevant discussion in the other chapters
of the Paper is hereby put forth for Stakeholders’ Consultation.
14.1.2 For removal of doubts, it is clarified and explained that the contents of this Consultation Paper may not be
construed as any Order or Direction by the Authority. The Authority shall pass an order in the matter, only
after considering the submissions of the stakeholders in response hereto and by making such decisions fully
documented and explained in terms of the provisions of the Act.
14.1.3 The Authority welcomes written evidence-based feedback, comments and suggestions from stakeholders
on the proposals made in this Consultation Paper, latest by 29th September 2023.
Secretary
Airports Economic Regulatory Authority of India
AERA Building, Administrative Complex,
Safdarjung Airport, New Delhi- 110003
Tel: 011-24695044-47; Fax: 011-24695048
(Chairperson)
Consultation Paper No. 11/2023-24 Page 146 of 156ANNEXURES
15. ANNEXURES
15.1 Annexure 1: Key clauses of Concession Agreement
GIAL, Mopa, Goa entered into a Concession Agreement with Government of Goa (GoG) on 8th November,
2016 to develop Greenfield International Airport at Mopa, in Goa under the DBFOT (Design, Build, Finance,
Operate and Transfer) model for an initial period of 40 years from the appointed date i.e. 4th September 2017,
which is extendable by another 20 years (based on a bidding process) with the First Right of Refusal available
to the Concessionaire, GIAL, Mopa, Goa.
Certain relevant Clauses of the Concession Agreement read as below:
5.6 Obligations relating to procurement of goods and services
5.6.1 “The Concessionaire agrees and undertakes that it shall procure contracts, goods and services for the
construction and operation of the Airport in a fair, transparent and efficient manner, and without any undue
favour or discrimination in this behalf. In pursuance hereof, it shall frame a procurement policy specifying the
principles and procedures that it shall follow in awarding contracts for supply of goods and services, and shall
place the policy on its website for the information of general public and all interested parties. The policy shall
also include the principles and procedures to be followed for leasing, licensing, sub-licensing, or grant or
allocation of any space, building, rights or privileges to private entities.”
5.6.2 “For procurement of goods, works or services and for award of leases, licenses, sub-licenses or any other rights
or privilege where the consideration exceeds Rs. 25,00,00,000 (Rupees twenty-five crores) in any Accounting
Year (collectively the “Contracts”), the Concessionaire shall invite offers through open competitive bidding by
means of e-tendering and shall select the awardees in accordance with the policy specified under Clause 5.6.1.
For the avoidance of doubt, the Parties agree that the Concessionaire may, in its discretion, pre-qualify and
short-list the applicants in a fair and transparent manner for ensuring that only experienced and qualified
applicants are finally selected on arm's length in a manner that is commercially prudent and protects the
interests of the Users. The Parties further agree that the Concessionaire shall not enter into any Related Party
Transaction or Contract with any Related Party except with (a) with the prior written consent of the Authority,
which consent shall not be unreasonably withheld as a reserved item/affirmative action in accordance with the
terms of the Shareholders' Agreement; and (b) such transaction is on arm's length basis and is in compliance
with the provisions of the Companies Act, 2013. The Parties also agree that before granting any consent
hereunder, the Authority shall be entitled to seek such information as it may reasonably require in relation to
the Contract and the Related Party with whom the Contract is proposed to be executed and in the event the
Authority does not approve or reject the proposal within 30 (thirty) days of the date on which the required
information has been provided, it shall be deemed that the Authority has no- objection to such Contract.”
5.6.3 “Notwithstanding anything contained contrary elsewhere, the Concessionaire shall adhere to the following
contracting principles in respect of any of the Related Party Transactions:
(a) No shareholder of the Concessionaire, and/or Key Managerial Person that has an interest in the contract,
can be involved in the design of the contract, or the contracting process or decision-making;
(b) Where a shareholder of the Concessionaire, Key Managerial Person or any Related Party intends to tender
for the contract, an independent probity auditor must be appointed to review and monitor the tender to ensure
a complete arms' length arrangement. It is clarified that the independent probity auditor shall not be a Related
Consultation Paper No. 11/2023-24 Page 147 of 156ANNEXURES
Party of the Concessionaire or any of its shareholders. Concessionaire shall agree to the appropriate terms of
reference and the selection procedure of the independent probity auditor as laid down by the Authority; and
(c) The Concessionaire shall constitute an audit committee headed by a nominee of the Authority which would
be responsible for auditing all the Related Party Transactions. The Board of the Concessionaire shall provide
the terms of reference of the audit committee at the time of its constitution. The Concessionaire shall enter into
any Related Party Transaction only after obtaining approval of audit committee in writing. Any amendment /
modification in the terms and conditions of the Related Party Transaction shall also require prior approval of
the audit committee.”
12.2 Master Plan for the Site
12.2.1“The Concessionaire shall at all times procure and ensure that the Airport is constructed and developed in
accordance with the Master Plan set forth in Schedule-A.”
12.2.2“The Concessionaire may, with prior written consent of the Authority, use any area earmarked for future
expansion of the Airport, for other purposes incidental to or associated with the Airport, until the same is
required for the expansion specified in the Master Plan, subject to the condition that only temporary structures
may be constructed in such area and the use thereof shall at all times be in conformity with Applicable Laws
and Good Industry Practice.”
12.2.3“The Concessionaire may, at any time during the Concession Period, seek approval of the Authority for
modifications in the Master Plan to improve or augment the Aeronautical Services and upon receipt of any
request hereunder, the Authority may grant such approval to the extent reasonably required.”
12.9 Development of MRO Facilities
12.9.1“Subject to the provisions of this Clause 12.9 and Clause 21.3, the Concessionaire shall undertake the
development of the MRO Facilities and as specified in Schedule B together with provision of Project Facilities
as specified in Schedule C, in conformity with the Specifications and Standards set forth in Schedule D and in
accordance with the provisions of this Agreement, Applicable Laws, relevant ICAO Documents and Annexes,
CAR Guidelines and Good Industry Practice.”
12.9.2“The area earmarked for the MRO Facilities in the Master Plan, may not be used for any other purpose.”
12.9.3“Any development, addition or modification to the MRO Facilities and its surrounding areas shall be in
accordance with the Master Plan and in harmony with the overall design and environment of the Airport.”
18.2 Ground handling Services
18.2.1“The Concessionaire shall provide or cause to be provided, the infrastructure required for operation of the
ground handling services required at the Airport for and in respect of aircrafts, passengers and cargo, which
shall include ramp handling, traffic handling, aircraft handling, aircraft cleaning, loading and unloading (the
"Ground Handling Services"). Such infrastructure shall include luggage conveyor belts, computer terminals,
IT backbone and associated facilities in accordance with the provisions of this Agreement, Applicable Laws
and Good Industry Practice.”
18.3 Aircraft Fueling Services
18.3.1 “The Concessionaire shall provide, or cause to be provided, the infrastructure required for operation of fueling
services for aircrafts at the Airport (the "Aircraft Fueling Services"). Such infrastructure shall include tank
Consultation Paper No. 11/2023-24 Page 148 of 156ANNEXURES
farms, common hydrant fueling systems and associated facilities in accordance with the provisions of this
Agreement, Applicable Laws and Good Industry Practice.”
21.3 Operation and Maintenance of MRO Facilities
“As and when developed, the Concessionaire shall operate and maintain or cause to be operated and maintained
the MRO Facilities, subject to an independent study duly verified by the Independent Engineer. Such
independent study including the Independent Engineer's recommendations, if any is to be commissioned by the
Concessionaire at the Concessionaire's cost, within 2 (two) years of COD of the Airport. Such study shall be
conducted every 2 (two) years till such time as MRO facilities are set up. The Concessionaire shall provide or
cause to be provided, the associated services to airlines and consignors as per the requirements specified in
Schedule B and in accordance with the provisions of this Agreement, Applicable Laws and Good Industry
Practice”.
26.8 Target Rating and User Survey
26.8.1“The Concessionaire shall participate in the passenger survey of Airport Service Quality (the "ASQ")
undertaken by Airports Council International (the "ACI") or any substitute thereof, conducted every quarter
and shall ensure that the Airport achieves and maintains a rating of at least 4.2 (four point two) in such survey
(the "Target Rating").
30.2 Annual Premium
30.2.1“Concessionaire agrees to pay to the Authority for each year commencing from the 6th (sixth) year of the
occurrence of the Appointed Date, a premium (the "Annual Premium") equal to 36.99 % of the Gross Revenue.”
32.3 Principles of Determination and Revision of Aeronautical Charges
32.3.2 “The GOI has, vide its letter no. F. No. AV.24011/12/2013-AD dated April 13, 2015, approved the 30% (thirty
per cent) shared-till framework for the determination and regulation of the Aeronautical Charges at the Airport,
and the same shall be accordingly considered by AERA. For avoidance of doubt, revenues of the Concessionaire
from City Side Development shall be excluded from the Shared-Till framework for the determination and
regulation of the Aeronautical Charges.”
32.3.3“The Annual Premium shall not be considered as a part of the capital outlay for the Airport or the regulatory
asset base or operating expense for the purpose of the determination of the Aeronautical Charges, and shall
always be excluded from being considered as a part of the cost for the determination of the Aeronautical
Charges.”
Relevant extract of Annexure – II of Schedule – A of the Concession Agreement
2. “It is proposed to develop the Airport in a phase-wise manner over the Concession Period. The concessionaire
shall prepare and submit the Master Plan for all phases. The phases would be based on the achievement of
traffic trigger mentioned in the table below.”
Table 1: Design Capacity and Traffic for Phasing
Traffic Design Capacity (Million Passengers Per
Phasing Trigger for Phasing
Annum)
Phase I 4.4
Phase II 5.8 80% of Phase I Capacity
Consultation Paper No. 11/2023-24 Page 149 of 156ANNEXURES
Traffic Design Capacity (Million Passengers Per
Phasing Trigger for Phasing
Annum)
Phase III 9.4 80% of Phase II Capacity
Phase IV 13.1 80% of Phase III Capacity
3. “The Concessionaire will prepare the Master Plan using the land use plan provided herewith (refer Map 1)
as a guideline with the following provisions:
• The Concessionaire shall plan and construct the facilities as identified under the different land use
provided in Map 1B of this Agreement. The concessionaire has flexibility to plan and design the facilities
within the defined land use subject to provisions of this Agreement.
• The Master Plan should be in accordance with Civil Aviation Requirements (CAR) as prescribed by the
DGCA, ICAO guidelines and conforming to Good Industry Practice.
• Level of service for Terminal Building - IATA Level of Service "C" (optimum standards) compliant. The
total area of the Terminal Building should be based on 25-40 square meter per peak hour passenger for
the design year.
• Terminal design must be capable of incremental expansion with minimum impact on current operations.
• The City Side development shall be as per provisions of this agreement, applicable development control
regulations and Applicable Law.”
Relevant extract from Schedule B of the Concession Agreement
3.1 Development of Airport shall include:
(i) “Construction and procurement of the Aeronautical Assets, including Runways, taxiways, apron, aircraft
parking bays and other associated" facilities with following requirements;
a. ICAO Aerodrome Reference Code: Airport to be designed for Code 4E at the minimum for Phase 1 and
2. Airport to be designed for Code 4F at the minimum for Phase 3. The Concessionaire can build a Code
4F airport at its discretion for Phase 1 and/or 2.
b. Location of Runway:
Runway Orientation 09 L 27 R
Direction 950 2750
Easting 376154.703 379890.325
Northing 1741181.09 1740854.265
(ii) construction and procurement of the Terminal Building as follows:
a. Level of service for Terminal Building - IATA Level of Service "C” (optimum standards) compliant. The
total area of the Terminal Building should be based on 25-40 square meter per peak hour passenger for
the design year;
b. 80% (eighty per cent) of each of the international and domestic aircrafts B737/ A320 or larger aircrafts
shall be served by the boarding bridges;
c. Provide international standard range of retail and other passenger services; and
d. Terminal design must be capable of incremental expansion with minimum impact on current
operations.”
Consultation Paper No. 11/2023-24 Page 150 of 156ANNEXURES
6. Defense Area
6.1 “The Concessionaire shall, in the Master Plan, earmark and carve out an area of 5 acres for the use of the
Defense Forces ("Defense Area"), which area shall be allocated by the Authority to the concerned Defense
Forces.”
6.2 “The Defense Area preferably should be located as identified in the land use plan provided in Map 1b in this
Agreement with a separate independent entry/exit to the defense facilities.”
6.3 “The Concessionaire shall provide adequate access and good surface connectivity of the Airport to the
boundary of the Defense Area on the land side.”
6.4 “While preparing the Master Plan, the Concessionaire shall also take into consideration providing access
to defense aircrafts apron from Runway with adequate taxiway system.”
7. Cargo Facilities
7.1 “The Concessionaire shall earmark land within the Site for the development of a Cargo Facility in the
Airport”.
7.2 “The Cargo Facilities including apron, cargo terminal for international and domestic cargo and other allied
facilities shall be developed in a Phase wise manner as per the applicable Standards and Specifications.”
8. MRO Facilities
8.1 “The Concessionaire shall earmark minimum 26 acres of land within the Site for the development of MRO
Facility in the Airport as per the applicable Standards and Specifications.”
8.2 “The area earmarked for the MRO Facilities in the Master Plan, may not be used for any other facility until
any inquiry comes and the Concessionaire enters into any arrangement with any third party or the
Concessionaire itself decides for developing and operating the MRO Facilities and for associated
activities.”
8.3 “The MRO Facility shall be developed, subject to the requirements specified in Clause 12.9 of the Concession
Agreement, for serving aircrafts of type and size as per the demand established, which shall include the
buildings, structures and equipment required by the aircraft as per the provisions in CAR 145 of DGCA.
This will be built in accordance with the provisions of this Agreement, Applicable Laws, relevant ICAO
Documents and Annexes, CAR Guidelines and Good Industry Practice.”
Relevant extract of Annexure – I of Schedule – L of the Concession Agreement
“The subjective quality of service shall be measured on the parameter of "Overall satisfaction with the airport"
on the ACI ASQ survey to be conducted every quarter. The benchmark score for the parameter "Overall
satisfaction with the airport" shall be at least equivalent to such score that the Airport is identified within top
20 (twenty) per centile of all airports in its category in the world. The Concessionaire shall also provide
performance on all measured parameters of the ACI ASQ survey as part of the Statements being submitted as
per the provisions of the Agreement.”
Consultation Paper No. 11/2023-24 Page 151 of 156ANNEXURES
15.2 Annexure 2: Consultancy and Legal Charges for FY 2023-24 submitted by GIAL, Mopa,
Goa and proposed by the Authority
(Rs. in crores)
GIAL, Details given by
Authority’s’
Heads Mopa, Goa GIAL, Mopa, Authority’s’ Observation
Proposal
Submission Goa
The Authority understands the importance of
establishing a brand presence and enhancing the
Road Signages,
image of Manohar International Airport, Mopa,
Brand Creative
Goa. The Authority notes that however, the costs
Passenger Exp 9.30 4.65 Agency, Digital
needs to be spent efficiently. The Authority
Creative Agency,
proposes to rationalize the cost estimates
Hoi App, etc.
submitted by GIAL, Mopa, Goa by 50% for these
initiatives.
Regarding IT-related expenses, the Authority
notes that GIAL, Mopa, Goa has already
ITO consultancy,
considered the costs associated with implementing
Manpower for RF
efficient and secure IT infrastructure, as well as
and Solar panel
the SAP Licensee fee, under IT related
Closed Circuit
IT 2.60 1.30 expenditure and Enterprise IT category
Television
respectively. While there are bound to be costs
(CCTV) Support,
relating to Solar Panel, CCTV etc. the Authority
SAP Licensee Fee,
proposes to rationalize these by 50% from the
etc.
estimates provided as other costs are considered
by the Authority.
During the initial stages of a new airport, it is
common to outsource certain manpower
requirements to achieve flexibility and benefit
from specialized expertise across various
Outsourced
functions. However, the Authority notes that
manpower;
Human Resource 2.70 1.35 GIAL, Mopa, Goa has already appointed
Consultants and
employees to provide similar services for which
specialists
outsourcing manpower costs are proposed. In light
of this, the Authority proposes to rationalize the
estimated outsourcing manpower cost submitted
by GIAL, Mopa, Goa to 50%.
The Authority notes the importance of ensuring
transparency and fairness in commercial
Probity Auditor,
transactions related to aeronautical operations.
Commercial - technical support,
0.80 0.80 The proposed cost by GIAL, Mopa, Goa for the
Aero cargo &
probity audit aligns with this objective. Therefore,
warehousing study
the Authority proposes to include the cost
estimate.
Consultancy These costs are related to City Side Development,
related to which falls outside the scope of aeronautical
ALD 0.70 -
architectural operations, the Authority does not propose to
design, market include these costs as part of the estimate.
Consultation Paper No. 11/2023-24 Page 152 of 156ANNEXURES
GIAL, Details given by
Authority’s’
Heads Mopa, Goa GIAL, Mopa, Authority’s’ Observation
Proposal
Submission Goa
research fees such
as lagoon
feasibility, golf
course feasibility
In terms of legal and regulatory compliance, the
Authority understands the necessity of allocating
Secretarial Audit
funds for relevant fees to meet these requirements.
Finance 0.70 0.70 fee; Certification
Thus, the Authority proposes to consider the cost
fees
estimate related to legal and regulatory
compliance.
Engaging an audit consultancy to assess
operational efficiency, identify areas for
Operation Audit improvement, and implement best practices is
MAG 0.50 0.50
consultancy fees crucial for enhancing overall airport operations
and service quality. Hence, the Authority proposes
including the estimated cost.
ACI membership,
Audit fees, 5S The Authority proposed to consider the estimate
Quality and BE 0.40 0.40 training, audit, by GIAL, Mopa, Goa for these initiatives only
ACI ASQ survey, related to passenger facilities.
Skytrax audit
Passenger survey,
Commercial -
0.40 - Benchmarking
Non Aero
study etc.
Mobile Medical
Unit ops through
third party, Annual
The Authority proposes including the cost
CSR 0.30 0.30 Maintenance
estimates for these initiatives.
Charges (AMC)
for software for e-
learning
Fees for Aconex
software for
The Authority proposes not to consider the cost
document and
Planning 0.20 - estimate submitted by GIAL, Mopa, Goa for
communication
Professional and Planning consultancy charges as
management
the costs of planning are already part of the Capital
system
costs.
Professional
Others 0.40 -
charges
Total 18.90 10.00
Consultation Paper No. 11/2023-24 Page 153 of 156ANNEXURES
15.3 Annexure 3: Operating & Maintenance Expense for the period from COD to 31st March
2023
Operating expenditure as per IND AS Amount proposed by
Particulars
the Financial Statement (A) Adjustment (B) the Authority (C=A+B)
Employee Benefits Expense
Salaries, wages and bonus
9.06 0.00 9.06
(a)
Contribution to provident
0.35 0.00 0.35
and other funds (b)
Total (c=a+b) 9.41 0.00 9.41
Bank Charges (d) 0.17 0.00 0.17
Other expenses
Rent (e) 0.58 2.99 3.57
Operating and maintenance
25.26 0.00 25.26
expenses (f)
Office maintenance (g) 1.15 0.00 1.15
Inauguration expenses (h) 10.53 0.00 10.53
Rates and taxes (i) 3.41 0.00 3.41
Legal and professional fees
1.36 0.00 1.36
(j)
Vehicle hire charges (k) 1.24 0.00 1.24
Administrative and General
1.56 0.00 1.56
Expenses (l)
Miscellaneous expenses
1.14 0.00 1.14
(m)
Total (n=e to m) 46.21 2.99 49.20
Total Opex (o=c+d+n) 55.79 2.99 58.78
Consultation Paper No. 11/2023-24 Page 154 of 156ANNEXURES
15.4 Annexure 4: Revenue from Operations for the period from COD to 31st March 2023
Particulars Revenue as per the IND AS Adjustment Total (C=
Financial Statement (A) (B) A+B)
Revenue from operations
Aeronautical Revenue
Landing and parking charges (a) 3.33 0.00 3.33
User Development Fee (UDF) (b) 15.06 0.00 15.06
Fuel farm (c) 1.39 (1.02) 0.38
Ground handling (d) 1.37 (0.52) 0.85
Cargo (e) 0.29 (0.22) 0.07
Land and space — Rentals (f) 1.05 - 1.05
Aeronautical Revenue (g=a to f) 22.49 (1.75) 20.74
Non-Aeronautical Revenue
Retail revenue (h) 3.78 (0.74) 3.04
Land and space — Rentals (i) 0.20 (0.03) 0.17
Others (j) 0.31 - 0.31
Other income (k) (0.96) 1.64 0.67
Non-Aeronautical Revenue (l=h to 3.33 0.86 4.19
k)
Consultation Paper No. 11/2023-24 Page 155 of 156APPENDICES
16. APPENDICES
16.1 Appendix 1 - Independent Study on Capital Expenditure for Development of Greenfield Airport
Facilities at Mopa, Goa
16.2 Appendix 2 - Minutes of AUCC meeting
Consultation Paper No. 11/2023-24 Page 156 of 156