Ministry of Power
Eight Projects with 8514 MW Capacity Under
Construction by NHPC
प्रव तथ: 11 DEC 2025 5:49PM by PIB Delhi
Total 23 hydropower projects have been commissioned by NHPC Limited and its JV/Subsidiary
companies till October, 2025 with a total installed capacity of 7,771 MW. Total generation from these
projects during the last 3 years and current year is as under:
Year Generation...
Ministry of Power Eight Projects with 8514 MW Capacity Under Construction by NHPC प्रव तथ: 11 DEC 2025 5:49PM by PIB Delhi Total 23 hydropower projects have been commissioned by NHPC Limited and its JV/Subsidiary companies till October, 2025 with a total installed capacity of 7,771 MW. Total generation from these projects during the last 3 years and current year is as under:
Year Generation (Million Units) 2022-23 29,894 2023-24 26,056 2024-25 25,194 2025-26 (Apr-Oct) 23,015 There are eight (8) hydropower projects that are currently under construction by NHPC Limited and its JV/Subsidiary companies with a total generation capacity of 8,514 MW (See Annexure).
NHPC Limited provides job opportunities to local people, including Project Affected Families (PAFs), through contractors, which generate local income and improve their living standards. Moreover, bidding opportunities are also provided to local residents and PAFs to promote local entrepreneurship and support local businesses.
Further, for redressal of any grievances, Govt. of India has launched a “Centralized Public Grievance Redress and Monitoring System – CPGRAMS” portal. The grievances received through this portal are examined and disposed of in a time-bound manner.
Annexure Details regarding name of projects, proposed generation capacities, projected power output, estimated total cost and expected date of commissioning of under-construction hydroelectric projects of NHPC Limited& its JV/Subsidiary companies Sl. Project State Capacity Design Anticipated Anticipated No. (MW) Energy cost Commissioning Date
(MU) (Rs. in cr)A NHPC
1. Subansiri Lower Arunachal 2000 7422 27948 Dec-26 Hydroelectric Project Pradesh
2. Dibang Multipurpose Arunachal 2880 11223 31876 Feb-32 Project Pradesh
3. Teesta-VI Hydroelectric Sikkim 500 2400 8449 Sept-29 Project Sub Total 5380 21045 68273 B JV/Subsidiaries
4. Rangit-IV Sikkim 120 508 1889 Apr-26 Hydroelectric Project (being implemented by JPCL*)
5. Ratle Hydroelectric UT of 850 3137 5282 Nov-28 Project Jammu & Kashmir (being implemented by RHPCL**)
6. PakalDul Hydroelectric UT of 1000 3230 12728 Dec-26 Project Jammu & Kashmir (being implemented by CVPPL***)
7. Kiru Hydroelectric UT of 624 2272 5409 Dec-26 Project Jammu & Kashmir (being implemented by CVPPL)
8. Kwar Hydroelectric UT of 540 1975 4526 Mar-28 Project Jammu & Kashmir (being implemented by CVPPL) Sub Total 3134 11122 29834 GRAND TOTAL 8514 32167 98107This Information was given by the Minister of Power, Shri Manohar Lal, in a written reply in the Lok Sabha today.