Date: 29-Oct-2024 Category: Extra Ordinary State: Union Government Country: India

In exercise of powers conferred under clause h of subsection 1 of Section 79 read with clause g of sub section 2 of Section 178 of the Electricity Act

Issued by Central Electricity Regulatory Commission · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

What it means

  • This gazette notification introduces the Central Electricity Regulatory Commission (Indian Electricity Grid Code) (First Amendment) Regulations, 2024.
  • These amendments modify the existing Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2023, which were published on 11th July 2023.
  • The amendments cover various aspects of grid operations, including infirm power injection, demonstration of design capabilities, scheduling of generating stations, compensation for part load operation, and revision of declared capacity and schedules.

Key Changes

  • Infirm power injection period for generating stations other than REGS and ESS (excluding Hydro PSP ESS) is limited to one year from first synchronization.
  • Infirm power injection for REGS and ESS (excluding Hydro PSP ESS) is limited to 45 days from first-time energization and integration (FTC) approval.
  • Extension of infirm power injection period beyond the stipulated time for REGS and ESS (excluding Hydro PSP ESS) can be granted by the respective RLDC for up to three months, and beyond three months by the Commission.
  • The definition of continuous outage is changed to 'four hours on a cumulative basis in a single day' instead of 'continuous four hours'.
  • Generating stations can declare Commercial Operation Date (COD) based on available water drawing levels if design capabilities cannot be met due to insufficient reservoir levels, with a condition to demonstrate full capacity when sufficient water is available.
  • If design capabilities cannot be demonstrated even with sufficient water, generating companies can opt for a repeat trial run or de-rate the capacity, with de-rating effective from COD.
  • Scheduling of a generating station or unit will start from 0000 hours of D+2 (where D is the date of intimation of commercial operation) or the declared commercial operation date, whichever is later.
  • Compensation for part load operation of regional entity thermal generating stations with tariffs adopted under Section 63 of the Electricity Act, 2003, will be as per the contract with beneficiaries or buyers, or as per the existing mechanism under the 2010 regulations if no such contract exists.
  • Thermal generating stations with tariffs determined under Section 62 of the Electricity Act, 2003, will be compensated for part load operation as per the applicable tariff regulations.
  • Consent of beneficiaries is required for any changes to schedules, removing the previous provision where consent was assumed unless explicitly withheld.
  • A new clause (v-a) is added to Regulation 49(2)(a) to address scheduling of generating stations below minimum turndown levels during off-peak hours but above minimum turndown levels during peak hours.
  • The clause allowing the entire drawal schedule to be accommodated under SCED has been removed.
  • Partial outages are included as a reason for schedule revisions.
  • Downward revision of schedules by buyers after 1430 hrs on D-1 day for D day is only permissible for beneficiaries who have scheduled above their share of minimum turndown level and is limited such that overall schedule is at least the minimum turndown level.
  • Revision of Declared Capacity and schedule is allowed only for bilateral transactions, not for collective transactions.
  • Generating stations other than lignite, gas based thermal and hydro plants can have a maximum of 4 revisions of Declared Capacity and schedule in a day, up to 60 revisions per month.
  • Lignite, gas based thermal and hydro plants can have a maximum of 6 revisions of Declared Capacity and schedule in a day, up to 120 revisions per month.

Impact Analysis

Generating Companies

  • They must also be prepared to adjust their schedules based on the new SCED rules and the new provisions for downward revision of schedules by buyers.

Beneficiaries / Buyers

  • They will need to be aware of the new SCED rules and their impact on costs and scheduling.

Regional Load Dispatch Centers (RLDCs)

  • RLDCs may allow upward revision of DC beyond the set limits keeping in view grid requirements.

National Load Dispatch Center (NLDC)

  • NLDC will need to implement the new scheduling rules and SCED adjustments.

Commission

  • The commission will need to approve the procedure submitted by NLDC related to payment of charges.

Action Items

  • Beneficiaries need to assess the impact of the changes on their scheduling practices and costs and make necessary adjustments.

Key Entities Referenced

Central Electricity Regulatory Commission (CERC): The regulatory body that issued the gazette notification and is responsible for making regulations related to the electricity sector. Electricity Act, 2003: The primary legislation governing the electricity sector in India, which provides the legal basis for the regulations. Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2023: The original regulations that are being amended by this notification. Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2010: The previous regulations referred to for part load compensation mechanism. Regional Load Dispatch Centers (RLDCs): Entities responsible for the regional level grid operations and scheduling. National Load Dispatch Center (NLDC): Entity responsible for the national level grid operations and scheduling. REGS: Renewable Energy Generating Stations ESS: Energy Storage Systems Hydro PSP ESS: Hydro Pumped Storage Plant Energy Storage Systems SCED: Security Constrained Economic Dispatch
Official Source Record View Original Source →
See Full Document Text
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99 सी.जी.-डी.एल.-अ.-30102024-258347 xxxGIDHxxx CG-DL-E-30102024-258347 xxxGIDExxx असाधारण EXTRAORDINARY भाग III—खण् ड 4 PART III—Section 4 प्राजधकार स ेप्रकाजित PUBLISHED BY AUTHORITY स.ं 880] नई दिल्ली, मगं लवार, अक्त बू र 29, 2024/कार्तकि 7, 1946 No. 880] NEW DELHI, TUESDAY, OCTOBER 29, 2024/KARTIKA 7, 1946 अजधसचू ना नई दिल्ली, 23 अक् तूबर, 2024 .––dsUnzh; fo|qr fofu;ked vk;ksx fo|qr vf/kfu;e] 2003 ¼2003 dk 36½ dh /kkjk 178 ds mi&[k.M ¼2½ ds [k.M ¼N½ ds lkFk ifBr /kkjk 79 ds mi[k.M ¼1½ ds [k.M ¼t½ ds v/khu çnÙk 'kfDr;ks a rFkk bl fufeÙk lkeF;Zdkjh lHkh vU; 'kfDr;ks a dk ç;ksx djrs gq, Fkk iwoZ çdk'ku ds i'pkr~] dsUnzh; fo|qr fofu;ked vk;ksx ¼Hkkjrh; fo|qr fxzM dksM½ fofu;e] 2023 ¼blds i“pkr~ ^ewy fofu;e* ds :Ik eas lanfHkZr½ dk la'kks/ku djus ds fy, fuEufyf[kr fofu;e cukrk gS] vFkkZr~%& (1) bu fofu;eks a dk laf{kIr uke dsUnzh; fo|qr fofu;ked vk;ksx ¼Hkkjrh; fo|qr fxzM dksM½ ¼çFke la'kks/ku½ fofu;e] 2024 gSA (2) ; s fofu;e eyw fofu;e ds fofu;e 45 ds [k.M ¼12½ ds la” kks/ku dks NksM+dj Hkkjr ds jkti= eas çdk'ku dh rkjh[k ls ço`Ùk gksxa sA (3) fofu;e 45 ds [k.M ¼12½ dk la” kks/ku 1-04-2024 ls ço`Ùk gksxkA 7022 GI/2024 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] : (1) eyw fofu;e ds fofu;e 19 ds [k.M ¼2½ ds mi-[k.M ¼[k½ dks fuEukuqlkj mi[k.M ¼[k½ vkSj ¼x½ ls izfrLFkkfir fd;k tk,xk% “([k) buQe Z ikoj dk var%{ksi.k vkjbZth,l vkSj bZ,l,l ¼gkbMªks ih,lih bZ,l,l dks NkMs +dj½ ls fHkUu mRiknu LV”s kuksa ds fy, izFke flaØkWukbts” ku dh rkjh[k ls ,d o’kZ ls vf/kd ugha gksxkA (x) buQeZ ikoj dk var%{ksi.k vkjbZth,l vkSj bZ,l,l ¼gkbMªks ih,lih bZ,l,l dks NkMs +dj½ ds fy, izFke flaØksukbts” ku vkSj leds u ¼,QVhlh½ vuqeknsu dh rkjh[k ls 45 ¼iSarkfyl½ fnuks a ls vf/kd ugh a gksxkA** (2) ,d ijUrqd dks fuEukuqlkj ewy fofu;e ds fofu;e 19 ds [k.M ¼3½ eas “kkfey fd;k tk,xk% “ijUrq fd vkjbZth,l vkSj bZ,l,l ¼gkbMªks ih,lih bZ,l,l dks NksM+dj½ ds fy, fu/kkZfjr vof/k ds vkxs buQeZ ikoj ds var%{ksi.k ds fy, vof/k ds foLrkj dh vuqefr ¼d½ fd lacaf/kr vkj,yMhlh }kjk rhu eghus rd dh vof/k ds fy, nh tk,xh ijarq ;g fd bl izdkj ds vkjbZth,l vkSj bZ,l,l ¼gkbMªks ih,lih bZ,l,l dks NksM+dj½ u s fu/kkZfjr vof/k ds iwjk gksus ds de ls de 10 fnuks a eas vfxze :Ik ls foLr`r dkj.kks a lfgr lacaf/kr vkj,yMhlh dks vkosnu ¼vkosnuksa½ fd;k gS ¼[k½ fu/kkZfjr vof/k ds iwjk gksus ds vfxze :Ik ls de ls de 15 fnuks a esa foLr`r dkj.kks a lfgr bZ,ll ;k bl izdkj ds mRiknu LVs” ku ¼gkbMªks ih,lih bZ,l,l dks NkMs +dj½ }kjk fd, x, vkosnu ¼vkosnuksa½ ij vk;ksx }kjk 3 eghus ls vkxs dh vof/k ds fy, vuqefr nh tk ldrh gSA” : (1) **lrr pkj ¼4½ ?k.Vks*a* “kCnksa dks eyw fofu;e ds fofu;e 22 ds [k.M ¼3½ ds mi[k.M ¼?k½ eas **,d fnu eas lap;h vk/kkj ij pkj ¼4½ ?k.Vs** “kCnksa ls izfrLFkkfir fd;k tk,xkA (2) fuEufyf[kr ijarqd dks ewy fofu;e ds fofu;e 22 ds [k.M ¼3½ ds mi[k.M ¼p½ ds varxZr “kkfey fd;k tk,xk% “ijra q ;g fd ;fn vi;kZIr tyk” k; Lrjks a ds dkj.k jVs Ms okVj vkgj.k Lrjks a rd fMtkbu {kerk,a iznf” kZr djuk laHko ugh a gS rks lhvksMh bl “krZ ds v/;k/khu miyC/k okVj vkgj.k Lrjksa ij {kerkvks a dks iznf” kZr djus ds ckn ?kksf’kr fd;k tk, fd jVs Ms okVj vkgj.k Lrjksa rd fMtkbu {kerkvks a dks rRdky iznf” kZr fd;k tk,xk tc Ik;kZIr tyk” k; Lrj lhvksMh ds ckn miyC/k gSA Ikjarq ;g Hkh fd ;fn bl izdkj dk mRiknu LVs” ku fMtkbu {kerkvks a ds izn” kZu ds fy, leFkZ ugh a gS tc Ik;kZIr ty miyC/k gS] rks mRiknu daiuh ds ikl Vªk;y ju dh iqujko`fRr djus ;k {kerk dks fMjsV djus ds fy, fodYi gksxkA ;fn mRiknu daiuh bu fofu;eksa ds fofu;e 22 ds [k.M ¼2½ ds mi[k.M ¼[k½ ds vuqlkj ;wfuV {kerk dks fMjsV djus dk fu.kZ; yrs h gS rks bl izdkj dh fMjsfVax lhvksMh ls izHkkoh gksxhA” : (1) eyw fofu;e ds fofu;e 27 ds [k.M ¼2½ dks fuEukuqlkj izfrLFkkfir fd;k tk,xk: “okf.kfT;d izpkyu dh rkjh[k dh ?kks’k.kk ij] mRiknu LVs” ku ;k mlds ;wfuV dk vuqlwphdj.k Mh$2 ds 0000 ?k.Vs a ls vkjHa k gksxk] ¼tgka Mh og rkjh[k gS tc mRiknu LVs” ku] ml mRiknu LVs” ku ;k mlds ;wfuV ds okf.kfT;d izpkyu dks lwfpr djrk gS½** ;k mRiknu LVs” ku ;k mlds ;wfuV }kjk ?kksf’kr okf.kfT;d izzpkyu dh rkjh[k] tks Hkh ckn es a gks ls vkjaHk gksxkA** (1) eyw fofu;e ds fofu;e 45 ds [k.M 12 ds r`rh; vkSj prqFkZ ijUrqd dks fuEukuqlkj izfrLFkkfir fd;k tk,xk : “ijra q ;g fd izknfs” kd bdkbZ FkeZy mRiknu LVs” kuks a ftuds VSfjQ dks vf/kfu;e dh /kkjk 63 ds v/khu vaxhÑr fd;k x;k gS] muds vkaf” kd Hkkj izpkyu ds fy, {kfriwfrZ] vFkkZr ekudh; Lrj ls uhps mRiknu ds fy, ykHkkfFkZ;ks a ;k Øsrkvks a ds lkFk bl izdkj ds mRiknu LVs” kuks a }kjk izfo’V fd, x, dkaVªDs V ds mica/kks a ds v/khu gksxk ;k dsUnzh; fo|qr fofu;ked vk;ksx ¼Hkkjrh; fo|qr fxzM dksM½ fofu;e] 2010 ds v/khu igy s ls ykxw ra= ds vuqlkj gksxh ;fn bl izdkj dkaVªDs V es a bl izdkj ds mica/k dk vHkko gS([भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 3 ijra q ;g Hkh fd FkeZy mRiknu LVs” kuksa ftudk VSfjQ vk;ksx }kjk vf/kfu;e dh /kkjk 62 ds v/khu fu/kkZfjr fd;k tkrk gS] ykxw VSfjQ fofu;eks a ds mica/kks a ds vuqlkj vkfa” kd Hkkj izpkyu ds fy, {kfriwfrZ dh tk,xhA** (1) eyw fofu;e ds fofu;e 49 ds [k.M ¼1½ ds mi[k.M ¼I½ ds v/khu **tc rd fd fyf[kr esa ykHkkFkhZ ;k Øsrk }kjk lgefr jksdh ugha tkrh** “kCnks a dks **ykHkkFkhZ ¼ykHkkfFkZ;ks½a dh lgefr ds fcuk** “kCnks a ls izfrLFkkfir fd;k tk,xkA (2) ,d u;k mi[k.M ¼v-d½ eyw fofu;e ds fofu;e 49 ds [k.M ¼2½¼d½ ds mi[k.M ¼v½ ds ckn fuEukuqlkj tksM+k tk,xk% **¼v-d½ ;fn izknfs” kd bdkbZ mRiknu LVs” ku] ftldk VSfjQ vf/kfu;e dh /kkjk 62 ds v/khu vo/kkfjr fd;k tkrk gS] fnol ds vkWQ ihd ?k.Vks a ds fy, U;wure VeZMkmu Lrj ls uhps vuqlwph izkIr djrk gS] rFkkfi fnol ds ihd ?k.Vks a ds fy, U;wure VeZMkmu Lrj ls Åij vuqlwph izkIr djrk gS] tgka ihd ?k.Vs vkSj vkWQ ihd ?k.Vs VSfjQ fofu;eksa ds v/khu lacaf/kr vkj,yMhlh }kjk ;Fkk?kksf’kr fd, tk,axs] ,u,yMhlh dks bl izdkj ds mRiknu LVs” ku }kjk vuqjks/k ij U;wure VeZMkmu Lrj ls uhp s vuqlwph fuEukuqlkj lek;ksftr dh tk,xh% ¼d½ U;wure VeZMkmu Lrj ls uhps vuqlwph bl izdkj ,llhbZMh ds varxZr lek;ksftr dh tk,xh fd fnol ds lHkh le;Cykdks a eas vuqlwph de ls de U;wure VeZMkmu Lrj ij gksxhA ekftZuy mRiknu LVs” ku ¼LVs” kuksa½ ¼*d*½ dh vuqlwph vFkkZr~ bl [k.M ds mi[k.M ¼iv½ ij pj.k ds iwjk gksus ds ckn vkSj rS;kj LVsd eas mPpre ÅtkZ izHkkj lfgr mRiknu LVs” ku jEs i vi ;k jEs i Mkmu nj] vuqfØ;k le;] ikjs’k.k ladqyrk vkSj foLr`r fØ;kfof/k es a ;Fkkfu/kkZfjr bl izdkj ds vU; iSjkehVjks a ds v/;/khu de fd;k tk,xkA ¼[k½ ;fn bl izdkj ds mRiknu LVs” ku ¼*d*½ ds] ;Fkkykxw ,llhbZMh ÅtkZ izHkkj ;k ,llhbZMh {kfriwfrZ izHkkj tks ,llhbZMh Mkmu tkjh djus ds fy, visf{kr Fkk] mRiknu LVs” ku ¼*[k*½ ds ÅtkZ izHkkj ls de gS ftldh vuqlwph U;wure VeZMkmu Lrj rd c<k+bZ xbZ Fkh] ,llhbZMh ÅtkZ izHkkj ;k ,llhbZMh {kfriwfrZ izHkkj ¼*d* ds fy,½ vkSj ÅtkZ izHkkj ¼*[k* ds fy,½ ds chp varj] ml bdkbZ }kjk lans; gksxk ftlls U;wure VeZ Mkmu Lrj ls uhp s mRiknu LVs” ku ;k mlds ;wfuV dh vulq wph gqbZ gSA ¼x½ ;fn bl izdkj ds mRiknu LVs” ku ¼*d*½ ds] ;Fkkykxw ,llhbZMh ÅtkZ izHkkj ;k ,llhbZMh {kfriwfrZ izHkkj tks ,llhbZMh Mkmu tkjh djus ds fy, visf{kr Fkk] mRiknu LVs” ku ¼*[k*½ ds ÅtkZ izHkkj ls vf/kd gS ftldh vuqlwph U;wure VeZMkmu Lrj rd c<k+bZ xbZ Fkh] ,llhbZMh ÅtkZ izHkkj ;k ,llhbZMh {kfriwfrZ izHkkj ¼*d* ds fy,½ vkSj ÅtkZ izHkkj ¼*[k* ds fy,½ ds chp varj dks bl [k.M ds mi[k.Mks a ¼viii½ ls ¼x½ ds vuqlkj lek;ksftr fd;k tk,xkA ¼?k½ mDr pj.kks a dks dsoy mlds ckn dk;kZfUor fd;k tk,xk tc fo|qr cktkj es a fo|qr dh fcØh ds ek/;e ls ¼f}i{kh; ;k lkewfgd laO;ogkj ds v/khu½ U;wure VeZMkmu Lrj dh vuqlwph dks izkIr djus ds fy, bl izdkj ds mRiknu LVs” ku }kjk fd, x, iz;kl vkj,yMhlh dks izLrqr fd, tkr s gSaA ¼³½ ,u,yMhlh] bu fofu;eks a dh vf/klwpuk ds ,d ekg ds vanj fofu;e 49(2)¼d½(v-d) ds mi[k.M ¼[k½ ds vuqlkj izHkkjks a ds Hkqxrku dh i)fr;ks a lfgr foLr`r fØ;kfof/k vk;ksx ds vuqeksnu ds fy, izLrqr djsxkA** (3) eyw fofu;e ds fofu;e 49 ds [k.M ¼2½ ds mi[k.M ¼d½¼vi½¼[k½ ds v/khu **vkSj ;g Hkh bl “krZ ds v/;/khu bl izdkj ds mRiknu LVs” ku dh lewph vkgj.k vuqlwph dks ,llhbZMh ds v/khu lek;ksftr fd;k tk ldrk gS** “kCnksa dks gVk fn;k tk,xkA (4) **;k vkaf” kd vkmVst bl fofu;e ds [k.M ¼7&d½ ds vuqlkj** “kCnksa dks eyw fofu;e ds fofu;e 49 ds [k.M ¼4½ ds mi[k.M ¼d½ ds izFke ijUrdq ds var eas tksM+k tk,xkA (5) fuEufyf[kr ijUrqd dks eyw fofu;e ds fofu;e 49 ds [k.M ¼4½ ds mi[k.M [k ¼ii½ ds v/khu “kkfey fd;k tk,xk% “ijra q fd mRiknu LVs” ku eas **Mh&1** fnol dks 1430 ?k.Vks a ds ckn **Mh** fnol ds fy, Øsrkvks a }kjk vuqlwfp;ks a ds v/kksxkeh iqujh{k.k dh vuqefr mUgha ykHkkfFkZ;ksa dks gksxh ftUgksua s mRiknu LVs” ku eas vius Hkkx ds U;wure VuZMkmu Lrj ds mij rd vuqlwfpr fd;k gS%4 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] Ikjarq bl izdkj ds ykHkkfFkZ;ks a ftUgksua s mRiknu LVs” ku eas viu s Hkkx ds U;wure VuZMkmu Lrj ds mij rd vuqlwfpr fd;k gS] muds }kjk v/kksxkeh iqujh{k.k bl izdkj dh ek=k rd lhfer gksxa s fd mRiknu LVs” ku dh lewph vulq wph de ls de U;wure VeZMkmu Lrj ij gksrh gSA *Mh&1* fnol ij 1430 ?k.Vks a ds ckn *Mh* fnol ds fy, bl izdkj ds ykHkkfFkZ;ks a }kjk vuqlwfp;ks a dk v/kksxkeh iqujh{k.k *Mh&1* fnol ds 1430 ?k.Vks a ij muds “ks;j ds U;wure VeZMkmu Lrj ls Åij dh fo|qr vuqlwph ds lekuqikfrd vk/kkj ij gksxkA ,d mRiknu LVs” ku ds ,d ueuw s le; CykWd ds fy, funsZ” kh % 55% 55% = X55% = - = = X ( / ( ) X100 ) 213 117 210 115 98 30.62% 37 682 706 1245 685 0 0 110 61 106 58 52 16.16% 19 354 195 335 184 170 53.12% 63 0 0 258 142 0 0 0 0 30 17 0 0 1359 1079 2184 320 119 1240 119 ” (6) fuEufyf[kr [k.M ¼7&d½ dks ewy fofu;e ds fofu;e 49 ds [k.M ¼7½ ds ckn “kkfey fd;k tk,xk: “¼7&d½ mRiknu LVs” ku ;k bZ,l,l ¼,d var%{ksi.kdkjh bdkbZ ds :Ik eas½ ds ?kksf’kr {kerk vkSj vuqlwph ds iqujh{k.k dh dsoy f}i{kh; laO;ogkjks a ds ekeys es a fuEufyf[kr C;ksjks a ds vuqlkj vuqefr gksxh vkSj lkefwgd laO;ogkjks a ds ekeys esa vuqefr ugha gksxh% (d) mRiknu LVs” ku ¼fyXukbV] xSl vk/kkfjr FkeZy mRiknu LVs” ku vkSj gkbMªks mRiknu LVs” ku ls fHkUu½ ;k bZ,l,l ¼,d var%{ksi.kdkjh bdkbZ ds :Ik es½a dh ;wfuV ds vkaf” kd vkmVst ;k bZa/ku xq.koRrk dh fHkUurk ;k fyf[kr es a fjdkWMZ fd, tku s okys fdlh vU; rduhdh dkj.k tSls dkj.kks a ds dkj.k ekg ds nkSjku vf/kdre 60 ¼lkB½ iqujh{k.kks a ds v/;k/khu fnol es a vuqlwph vkSj ?kksf’kr {kerk ds vf/kdre ¼pkj½ iqujh{k.kks a dh vuqefr gksxh% Ikjarq fd vkj,yMhlh fxzM vis{kkvks a dks /;ku eas j[krs gq, mDr lhek ds vkxs Mhlh ds m/oZxkeh iqujh{k.k dh vuqefr n s ldrk gSA ([k) fyXukbV] xSl ;k gkbMªks xSl ij vk/kkfjr mRiknu LVs” ku dks ;wfuV ds vkaf” kd vkmVts ] ;k gkbMªks mRiknu LVs” kuks a ds fy, ty miyC/krk ;k bZa/ku xq.koRrk ;k xSl mRiknu LVs” kuksa ds fy, xSl dh vkiwfrZ es a fHkUurk ;k fyf[kr eas fjdkWMZ fd, tku s oky s fdlh vU; rduhdh dkj.k tSls dkj.kks a ds dkj.k ekg ds nkSjku vf/kdre 120 ¼,d lkS chl½ iqujh{k.kks a ds v/;k/khu fnol es a vuqlwph vkSj ?kksf’kr {kerk ds 6 ¼N½ iqujh{k.kks a dh vuqefr gksxh%[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 5 Ikjarq fd vkj,yMhlh fxzM vis{kkvks a dks /;ku eas j[krs gq, mDr lhek ds vkxs Mhlh ds m/oZxkeh iqujh{k.k dh vuqefr n s ldrk gSA” gjçhr flag izqFkh] lfpo [जवज्ञापन-III/4/असा./650/2024-25] : (1) dsUæh; fo|qr fofu;ked vk;ksx ¼Hkkjrh; fo|qr fxzM dksM½ fofu;e] 2023 dks Hkkjr ds “kkldh; jkti= ¼vlk/kkj.k½ la[;k 488 ds Hkkx III] [k.M 4 esa rkjh[k 11-07-2023 dks izdkf'kr fd;k x;kA CENTRAL ELECTRICITY REGULATORY COMMISSION NOTIFICATION New Delhi, the 23rd October 2024 No. L-1/265/2022/CERC. ––In exercise of powers conferred under clause (h) of subsection (1) of Section 79 read with clause (g) of sub-section (2) of Section 178 of the Electricity Act, 2003 (36 of 2003), and all other powers enabling it in this behalf, and after previous publication, the Central Electricity Regulatory Commission hereby makes the following regulations to amend the Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2023 (hereinafter referred to as “the Principal Regulations”). 1. Short Title and Commencement (1) These regulations may be called the Central Electricity Regulatory Commission (Indian Electricity Grid Code) (First Amendment) Regulations, 2024. (2) These regulations shall come into force from the date of publication in the official Gazette except for Amendment to Clause (12) of Regulations 45 of Principal Regulations. (3) Amendment to Clause (12) of Regulation 45 shall come into force from 1.04.2024. 2. Amendment to Regulation 19 of the Principal Regulations: 1. Sub-Clause (b) of Clause (2) of Regulation 19 of the Principal Regulations shall be substituted with sub- clauses (b) and (c) as follows: “(b) Injection of infirm power shall not exceed one year from the date of first synchronization for generating stations other than REGS and ESS (except Hydro PSP ESS). (c) Injection of infirm power shall not exceed 45 (forty-five) days from the date of first-time energization and integration (FTC) approval for REGS and ESS (except Hydro PSP ESS).” 2. A Proviso shall be inserted in Clause (3) of Regulation 19 of the Principal Regulations as follows: “Provided that for REGS and ESS (except Hydro PSP ESS), extension of period for injection of infirm power beyond the stipulated period may be allowed (a) for a period up to three months by respective RLDC on an application(s) made by such generating station or ESS(except Hydro PSP ESS) to respective RLDC along with detailed reasons, at least 10 days in advance of the completion of the stipulated period, (b) for a period beyond three months, by the Commission on an application(s) made by such generating station or ESS(except Hydro PSP ESS) along with detailed reasons, at least 15 days in advance of the completion of the stipulated period”. 3. Amendment to Regulation 22 of the Principal Regulations: (1) Words “continuous four (4) hours” shall be replaced with words “four (4) hours on a cumulative basis in a single day” in sub-clause (d) of Clause (3) of Regulation 22 of the Principal Regulations. (2) The following proviso shall be inserted under sub-clause (f) of Clause (3) of Regulation 22 of the Principal Regulations: “Provided that if it is not possible to demonstrate the design capabilities up to the rated water drawing levels due to insufficient reservoir levels, the COD may be declared after demonstrating the capabilities at available water drawing levels, subject to the condition that design capabilities up to the rated water drawing levels shall be demonstrated immediately when sufficient reservoir level is available after COD.6 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] Provided further that if such a generating station is not able to demonstrate the design capabilities when sufficient water is available, the generating company shall have the option to either go for a repeat trial run or de-rate the capacity. If the generating company decides to de-rate the unit capacity in terms of sub-clause (b) of Clause (2) of Regulation 22 of these Regulations, such de-rating shall be effective from the COD.” 4. Amendment to Regulation 27 of the Principal Regulations: (1) The Clause (2) of the of Regulation 27 of the Principal Regulations shall be substituted as under: “On declaration of commercial operation date, scheduling of the generating station or unit thereof, shall start from 0000 hours of D+2 (where D is the date when a generating station intimates the commercial operation of the generating station or unit thereof) or the commercial operation date declared by the generating station or unit thereof, whichever is later.” 5. Amendment of Regulation 45 of the Principal Regulations (1) The Third and Fourth Proviso to Clause 12 of Regulation 45 of the Principal Regulations shall be substituted as follows: “Provided further that the regional entity thermal generating stations whose tariffs are adopted under Section 63 of the Act shall be compensated for part load operation, that is, for generation below the normative level of operation, in terms of the provisions of the contract entered into by such generating stations with the beneficiaries or buyers, or in the absence of such provision in the contract, as per the mechanism already in force under the Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2010: Provided further that the thermal generating stations whose tariffs are determined under Section 62 of the Act by the Commission, shall be compensated for part load operation as per the provisions of applicable Tariff Regulations.” 6. Amendment to Regulation 49 of the Principal Regulations (1) The words “unless the consent is withheld by the beneficiary or buyer in writing” under sub-clause (l) of Clause (1) of Regulation 49 of the Principal Regulations shall be substituted with the words “without the consent of beneficiary(ies).” (2) A new sub-clause (v-a) shall be added after sub-clause (v) of Clause (2)(a) of Regulation 49 of the Principal Regulations as follows: “(v-a) In case a regional entity generating station, whose tariff is determined under Section 62 of the Act, gets a schedule below minimum turndown level for Off-Peak hours of the day, however, gets a schedule above minimum turndown level for Peak hours of the day, where Peak hours and Off-Peak hours shall be as declared by the concerned RLDC under the Tariff Regulations, the schedule below the minimum turndown level may, on the request by such generating station to NLDC shall be adjusted as follows: (a) the schedule below the minimum turndown level shall be adjusted under SCED such that the schedule in all time blocks of the day is at least at the minimum turndown level. The schedule of the marginal generating station (s) (‘A’), that is, the generating station with the highest energy charge in the stack prepared under and after completion of step at sub-clause (iv) of this clause, shall be reduced, subject to ramp up or ramp down rate, response time, transmission congestion and such other parameters as stipulated in the Detailed Procedure. (b) In case the SCED energy charge or SCED Compensation Charge, as applicable, of such generating station (‘A’), which was required to be issued SCED down, is lower than the energy charge of the generating station (‘B’) whose schedule was increased up to the minimum turndown level, the difference between the SCED energy charge or the SCED Compensation Charge (for ‘A’) and the energy charge (for ‘B’) shall be payable by the entity which has caused the schedule of the generating station or unit thereof below minimum turndown level. (c) In case the SCED energy charge or SCED Compensation Charge, as applicable, of such generating station (‘A’) which was required to be issued SCED down, is higher than the energy charge of the generating station (‘B) whose schedule was increased up to the minimum turndown level, the difference between the SCED energy charge or SCED Compensation Charge (for ‘A’) and the energy charge (for ‘B’) shall be adjusted in accordance with sub-clauses (viii) to (x) of this clause. (d) The above steps shall be carried out only after the generating station furnishes to the RLDC the efforts made by such generating station to achieve a schedule of Minimum turndown level through the sale of power in the Power market (under bilateral or collective transactions).[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 7 (e) NLDC shall submit a detailed Procedure including the modalities of payment of charges as per sub- clause (b) of Regulation 49(2)(a)(v-a), within a month of notification of these regulations, for approval of the Commission.” (3) The words “, and also subject to the condition the entire drawal schedule against such generating station can be accommodated under SCED” under sub-clause (a)(vi)(b) of Clause (2) of Regulation 49 of the Principal Regulations shall be deleted. (4) The words “or partial outage as per clause (7-a) of this Regulation” shall be added at the end of the first proviso to sub-clause (a) to Clause (4) of Regulation 49 of the Principal Regulations. (5) The following proviso shall be inserted under sub-clause b(ii) of Clause (4) of Regulation 49 of the Principal Regulations: “Provided that downward revision of schedules by the buyers for ‘D’ day, after 1430 hrs on ‘D-1’ day in the generating station is permissible only for beneficiaries which have scheduled above their respective share of minimum turndown level in the generating station: Provided also that downward revision by such beneficiaries, which have scheduled above their respective share of minimum turndown level in the generating station, shall be permissible limited to a quantum such that overall schedule of the generating station is at least at Minimum turndown level. The downward revision of schedules by such beneficiaries for ‘D’ day, after 1430 hrs on ‘D-1’ day shall be permissible on a pro-rata basis of the power scheduled above the minimum turndown level of their share at 1430 hrs of ‘D-1’ day. Illustration for a sample generating station for a sample time block: State Schedules Schedule for 'D' Allocation 55% Share Ratio (in Maximum down given prior day after after allocation taken %) permitted after to 2.30 pm downward deducting (considering above 2.30 PM on on 'D-1' (in revision for a auxiliary MTL as MTL (in ‘D-1’/’D’ day MW) sample day (in consumption 55%) (in MW) (in MW) MW) (in MW) MW) A B C D = C x 55% E = A-D F = G=F X (total (E/sigma schedule at 2.30 E) X 100 PM on ‘D-1’ - MTL) State A 213 117 210 115 98 30.62% 37 State B 682 706 1245 685 0 0 State C 110 61 106 58 52 16.16% 19 State D 354 195 335 184 170 53.12% 63 State E 0 0 258 142 0 0 State F 0 0 30 17 0 0 1359 1079 2184 320 119 MTL 1240 MW Schedule at 2.30 PM on ‘D-1’ - MTL 119 MW ” (6) The following Clause (7-a) shall be inserted after Clause (7) of Regulation 49 of the Principal Regulations: “(7-a) Revision of Declared Capacity and schedule of a generating station or ESS (as an injecting entity) shall be allowed only in case of bilateral transactions and not in case of collective transaction as per following details: (a)The generating station (other than lignite, gas based thermal generating station, and hydro generating station) or ESS (as an injecting entity) shall be allowed a maximum of 4 (four) revisions of Declared Capacity and schedule in a day subject to a maximum of 60 (sixty) revisions during a month, due to reasons such as a partial outage of the unit or variation of fuel quality or any other technical reason to be recorded in writing:8 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] Provided that RLDC may allow upward revision of DC beyond the above limit keeping in view grid requirements. (b) The generating station based on lignite, gas, or hydro generating station shall be allowed 6(six) revisions of Declared Capacity and schedule in a day subject to a maximum of 120 (One hundred twenty) revisions during a month, due to reasons such as a partial outage of the unit or water availability for hydro generating stations or fuel quality or variations in the supply of gas for gas generating stations or any other technical reason to be recorded in writing: Provided that RLDC may allow upward revision of DC beyond the above limit keeping in view grid requirements.” HARPREET SINGH PRUTHI, Secy. [ADVT.-III/4/Exty./650/2024-25] Note: The Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2023, were published on 11.07.2023 in Part III, Section 4 of the Gazette of India (Extraordinary) No 488. Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064 and Published by the Controller of Publications, Delhi-110054.